MAGULON BHS

Embed Size (px)

Citation preview

  • 7/27/2019 MAGULON BHS

    1/67

    Project : MAGULON BHS

    Location : Magulon, Lamut, Ifugao

    Procuring Entity : Provincial Local Government Unit of Ifugao

    Date of Bid : __________________________________

    Item Unit QuantityUnit

    Cost (P)Total

    I Preliminaries/General requirements:

    1. Project Billboard lot 1.00

    II Civil Works

    a. Earthworks

    a.1. Excavation m 47.89

    a.2. Backfilling & Compaction m 34.20

    a.3. Gravel Bedding m 7.99

    a.4 Soil Poisoning m 174.60

    b. Concreting Works m 29.44

    c. Rebar Works & Tie Wire kgs 4,416.98

    d. Formworks & Scaffolding

    e. Carpentry Works

    e.1 Door Jamb bd.ft 150.22e.2 Ceiling joists & hanger m 90.42

    e.3 Ceiling board m 90.42

    e.4 Fascia board l.m. 36.00

    e.5 Moulding l.m. 84.03

    e.6 Wood Louver Ventilation sets 2.00

    f. Roof Framing

    f.1 Truss bd.ft 326.00

    f.2 Rafter bd.ft 206.00

    f.3 Purlins m 110.00

    g. Roofing Works

    g.1 Corrugated GI Roof m 110.00

    g.2 Plain GI Ridge Roll & Flashing l.m 53.00

    h. Masonry Works m 176.27

    i. Plastering & Finishing

    i.1 Walls m 346.50

    i.2 Columns & Beams m 68.25

    j. Doors & Windows

    j.1 Doors m 16.80

    j.2 Windows m 16.20

    k. Tileworks m 29.97

    l. Painting and Varnishing

    l.1 Ceiling

    l.1.1 Ground Floor Ceiling m 90.42l.1.2 Basement Floor Ceiling m 22.91

    l.2 Walls, Columns & Beams m 414.75

    III SANITARY WORKS

    a.1 Sewerage System lot 1.00

    a.2 Water Lines & Fittings lot 1.00

    a.3 Sanitary Fixtures & Accessories lot 1.00

    IV ELECTRICAL WORKS lot 1.00

    Total, Direct Cost

    V Indirect Cost

    VI Total (Direct Cost and Indirect Cost)

    VII Value Added Tax (8.50%)

    Description

  • 7/27/2019 MAGULON BHS

    2/67

    Project : MAGULON BHS

    Location : Magulon, Lamut, Ifugao

    Procuring Entity : Provincial Local Government Unit of Ifugao

    Date of Bid : __________________________________

    Item Unit QuantityUnit

    Cost (P)Total (P)Description

    Prepared by : Approved by :

    GERLIE B. ASENIERO JOEL BAUTISTA

    Cost Engineer Head - PDT

    TOTAL ESTIMATED COST

  • 7/27/2019 MAGULON BHS

    3/67

    D

    NAME OF CONTRACT : Type of Project

    Construction of Magulon BHS Type of Structure/s

    Project Length 9.00

    Location of Contract : Magulon, Lamut, Ifugao Project Width 7.00

    Source of Fund : EC Grant Floor Area/Area 63.00

    Appropriation : No. of Culverts

    Limits : No. of Span/Storey 2.00

    Mode of Implementati Straight Contract Straight Contract Duration 90

    Contract Brief: Construction of Barangay Health Station

    EQUIPMENT REQUIREMENT

    DESCRIPTION available required DESCRIPTIO available

    Item

    No. %TAGE UNIT QUANTITY UNIT COST AM

    I Preliminaries/General requirements:

    1. Project Billboard 0.08 lot 1.00 1,012.00

    II CIVIL WORKS

    a.1. Excavation 0.98 m 47.89 263.37

    a.2. Backfilling & Compaction 0.91 m 34.20 340.44

    a.3. Gravel Bedding 1.11 m 7.99 1,789.62

    a.4 Soil Poisoning 0.81 m 174.60 59.61

    b. Concreting Works 13.89 m 29.44 6,068.15

    c. Rebar Works & Tie Wire 16.14 kgs 4,416.98 46.99

    d. Formworks & Scaffolding 9.54 m 201.82 607.81

    e. Carpentry Works

    e.1 Door Jamb 0.84 bd.ft 150.22 71.77

    e.2 Ceiling joists & hanger 1.88 m 90.42 267.11

    e.3 Ceiling board 1.28 m 90.42 182.70

    e.4 Fascia board 0.48 l.m. 36.00 171.79

    e.5 Moulding 0.26 l.m. 84.03 40.05

    e.6 Wood Louver Ventilation 0.10 sets 2.00 625.55

    e.7 Lavatory cabinet door(flush door type) & 0.63 lot 1.00 8,115.82e.8 Counter Top(Midwife Station) 0.29 lot 1.00 3,686.63

    f. Roof Framing

    1.70 bd.ft 326.00 66.89

    1.10 bd.ft 206.00 68.96

    1.18 m 110.00 138.20

    g. Roofing Works

    g.1 Corrugated GI Roof 2.65 m 110.00 310.05

    g.2 Plain GI Ridge Roll & Flashing 0.63 l.m 53.00 151.91

    h. Masonry Works 9.33 m 176.27 680.81

    i. Plastering & Finishing

    6.35 m 346.50 235.46i.2 Columns & Beams 1.54 m 68.25 289.64

    j Doors & Windows 0 00

    a. Earthworks

    f.1 Truss

    f.2 Rafter

    f.3 Purlins

    i.1 Walls

    Php 1,000,000.00

    ESTIMATED PROJECT COS

    WORK TO BE DONE

    Republic of the Philippines

    Province of Ifugao

    OFFICE OF THE PROVINCIAL ENGINEER

    Lagawe, Ifugao

    PROGRAM OF WORK

    Buil

    Split

  • 7/27/2019 MAGULON BHS

    4/67

    a.3 Sanitary Fixtures & Accessories 2.25 lot 1.00 28,935.61

    IV ELECTRICAL WORKS 6.80 lot 1.00 87,429.21

    COST % TAGE EXPENDITURES

    1. Material Cost A. Estimated Contract Cost

    2. Equipment Expense (Direct Cost + Indirect Cost)

    3. Labor Cost B. Estimated Prov'l. Gov't. Expenses:

    4. Hauling Cost B.1 Administrative Overhead

    5. Mob./Demob. Cost B.2 Engineering Overhead

    6. Total Contract Cost B.3 Quaity Control

    7. Prov'l. Gov't. Expenses B.4 ROW/Site Acquisition

    8. Reserve/Contingency B.5 Contingencies/Reserved

    9. Appropriation D. Total Estimated Project Cost

    Prepared by: Reviewed by:

    JONATHAN D. PAHIGON JULIAN B. DULAWAN

    Engineer III

    Approved:

    Prov'l Health Officer II Prov'l Engineer Prov'l Governor

    1,2

    ssistant Prov'l Enginee

    Recommending Approval:

    MARY JO P. DULAWAN MD.MHA. ORLANDO D. SAROL TEODORO B. BAGUILAT

    1,2

    BREAKDOWN OF ESTIMATES

    EXPENDITURES

  • 7/27/2019 MAGULON BHS

    5/67

    T E

    m

    m

    sq.m

    CD

    required

    OUNT

    1,012.00

    12,613.32

    11,643.05

    14,300.85

    10,407.91

    178,621.30

    207,553.89

    122,666.69

    10,781.58

    24,152.09

    16,519.73

    6,184.44

    3,365.40

    1,251.10

    8,115.823,686.63

    21,806.14

    14,205.76

    15,202.00

    34,105.50

    8,051.23

    120,006.38

    81,585.7119,767.93

    15,202.00

    81,585.7119,767.93

    8,051.23

    120,006.38

    3,365.40

    1,251.10

    14,205.76

    34,105.50

    21,806.14

    122,666.69

    10,781.58

    24,152.09

    16,519.73

    6,184.44

    12,613.32

    14,300.85

    178,621.30

    207,553.89

    11,643.05

    10,407.91

    1,012.00

    3,686.638,115.82

    ing

    ype

  • 7/27/2019 MAGULON BHS

    6/67

    28,935.61

    87,429.21

    1,285,596.74

    JR.

    87,429.21

    28,935.61

    85,596.74

    JR.

    85,596.74

  • 7/27/2019 MAGULON BHS

    7/67

    Name of Project : MAGULON BHS

    Location : Magulon, Lamut, Ifugao

    Appropriation : Php 1,000,000.00

    Source of Fund : EC Grant

    Item no.

    I Preliminaries/General requirements: QTY = 1 lot

    1. Project Billboard Unit Qty Unit Price Amountlot 1 800 800

    Direct Cost = 800.00

    II CIVIL WORKS

    a. Earthworks

    a.1. Excavation QTY = 47.89 m

    Column Footing = 18.96 m

    Wall Footing = 7.80 m

    Basement Floor = 8.40 m

    Stair Footing = 0.42 m

    Septic Tank = 12.31 m

    Labor Cost:

    Prod. Rate = 1.5 m/man-day

    Employ = 1 Foreman

    = 5 Laborers

    Duration = 6.39 say 6.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 6.5 2,073.50

    Laborers 5 243 6.5 7,897.50

    9,971.00

    Direct Cost = 9,971.00

    a.2. Backfilling & Compaction QTY = 34.20 m

    Labor Cost:(Placing)Prod. Rate = 2.75 m/man-day

    Employ = 1 Foreman

    = 5 Laborers

    Duration = 2.49 say 2.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2.5 797.5

    Laborers 5 243 2.5 3,037.50

    3,835.00

    Labor Cost:(Compaction)

    Prod. Rate = 2 m/man-day

    Employ = 1 Foreman

    = 5 LaborersDuration = 3.42 say 3.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 3.5 1,116.50

    Laborers 5 243 3.5 4,252.50

    5,369.00

    Direct Cost = 9,204.00

    a.3. Gravel Bedding QTY = 7.99 m

    Material Cost:

    D E T A I L E D E S T I M A T E S

  • 7/27/2019 MAGULON BHS

    8/67

    Description Unit Qty Unit Cost Amount

    Gravel m 8 1312.50 10,500.00

    Labor Cost:(Placing)

    Prod. Rate = 4 m/man-day

    Employ = 1 Foreman

    = 2 Laborers

    Duration = 1 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00

    Laborers 2 243 1 486.00

    805.00

    Direct Cost = 11,305.00

    a.4 Soil Poisoning QTY = 174.60 m

    Column footing = 81.84 m

    Wall footing = 31.50 m

    Stair footing & pedestal = 2.04 m

    Basement floor slab = 22.01 m

    Ground Floor slab = 37.21 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Soil Poison (Termite-X) liters 5 921.00 4,605.00

    Labor Cost:

    Prod. Rate = 20 m/man-day

    Employ = 1 Foreman

    2 Laborers

    Duration = 4.37 say 4.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 4.5 1,435.50

    Laborers 2 243 4.5 2,187.003,622.50

    Direct Cost = 8,227.50

    b. Concreting Works QTY = 29.44 m

    Column footing = 4.39 m

    Wall footing = 2.40 m

    Stair footing & pedestal = 0.26 m

    Column = 5.69 m

    Basement floor slab = 2.20 m

    Ground floor slab = 5.63 m

    Ground floor beams = 2.60 m

    Roof beams = 2.51 m

    Lintel beams = 0.96 mCantilever beam = 0.21 m

    Stair 1 and landing(above) = 1.15 m

    Stair 2 = 0.63 m

    Lavatory Counter = 0.37 m

    Septic tank's slab and cover = 0.43 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Portland Cement bags 268 252.00 67,536.00

    Sand(S-1) m 15 1212.50 18,187.50

  • 7/27/2019 MAGULON BHS

    9/67

    Gravel(G-1) m 26 1312.50 34,125.00

    119,848.50

    Labor Cost:

    Prod. Rate = 0.66 m/man-day

    Employ = 1 Foreman

    3 Mason

    5 Laborers

    Duration = 5.57 say 6 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 6 1,914.00

    Mason 3 259 6 4,662.00

    Laborers 5 243 6 7,290.00

    13,866.00

    Equipment Cost:

    Description No. Rate No. of Days Amount

    1 Bagger Mixer 1 1,248 6 7,488.00

    Direct Cost = 141,202.50

    3,103.00

    c. Rebar Works & Tie Wire QTY = 4,416.98 kgs

    Column footing = 20 -16x6m= 189.40 kgs

    Wall footing = 23 -10x6m= 85.10 kgs

    Stair footing & pedestal = 4 -12x6m= 21.32 kgs

    2 -10x6m= 7.40 kgs

    Column = 96 -16x6m= 909.12 kgs

    125 -10x6m= 462.50 kgs

    Basement floor slab = 18 -10x6m= 66.60 kgs

    Ground floor slab = 50 -12x6m= 266.50 kgs

    35 -10x6m= 129.50 kgs

    Basement Floor Beams(Tie Beams)= 8 -16x6m= 75.76 kgs

    8 -16x7.5m= 94.72 kgs

    26 -10x6m= 96.20 kgs

    Ground floor beams = 18 -16x6m= 170.46 kgs

    19 -16x7.5m= 224.96 kgs

    61 -10x6m= 225.70 kgsRoof beams = 19 -16x6m= 179.93 kgs

    28 -16x7.5m= 331.52 kgs

    89 -10x6m= 329.30 kgs

    Lintel beams = 10 -16x6m= 94.70 kgs

    13 -10x6m= 48.10 kgs

    Cantilever beam = 7 -16x6m= 66.29 kgs

    8 -10x6m= 29.60 kgs

    Stair 1 and landing(above) = 9 -16x6m= 85.23 kgs

    8 -12x6m= 42.64 kgs

    24 -10x6m= 88.80 kgs

    Lavatory Counter = 10 -10x6m= 37.00 kgs

    Septic tank's slab and cover = 11 -12x6m= 58.63 kgs

    Material Cost:

    Description Unit Qty Unit Cost Amount

    16mm RSB kg 2,422.09 35.50 85,984.20

    12mm RSB kg 389.09 35.50 13,812.70

    10mm RSB kg 1,568.80 35.50 55,692.40

    Ga #16 Tie Wire kg 66 74.00 4,884.00

    155,489.29

    Labor Cost:

    Prod. Rate = 180 kg/man-day

    Employ = 1 Foreman

  • 7/27/2019 MAGULON BHS

    10/67

    2 Steelmen

    2 Laborers

    Duration = 6.13 say 6.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 6.5 2,073.50

    Steelmen 2 259 6.5 3,367.00

    Laborers 2 243 6.5 3,159.00

    8,599.50

    Direct Cost = 164,088.79

    d. Formworks & Scaffolding QTY = 201.82 m

    Column = 72.72 m

    Ground floor slab = 56.28 m

    Ground floor beams = 25.00 m

    Roof beams = 13.60 m

    Lintel beams = 10.64 m

    Cantilever beam = 2.51 m

    Stair 1 and landing = 9.21 m

    Stair 2 = 4.23 m

    Lavatory Counter = 3.42 m

    Septic tank's slab and cover = 4.22 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    1/4" Ordinary plywood pcs 71 318.00 22,578.00

    2"x2"x10' b.f. 1167 22.00 25,674.00

    2"x3"x10' b.f. 750 22.00 16,500.00

    Assorted CWN kg 30 79.00 2,370.00

    67,122.00

    Labor Cost: (Formworks fabrication & installation)

    Prod. Rate = 35 m/crew-day

    Employ = 1 Foreman

    2 Carpenter

    4 LaborersDuration = 5.77 say 6 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 6 1,914.00

    Carpenter 2 259 6 3,108.00

    Laborers 4 243 6 5,832.00

    10,854.00

    Labor Cost: (Formworks removal)

    Prod. Rate = 60 m/crew-day

    Employ = 1 Foreman

    1 Carpenter

    2 LaborersDuration = 3.36 say 3.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 3.5 1,116.50

    Carpenter 1 259 3.5 906.50

    Laborers 2 243 3.5 1,701.00

    3,724.00

    Labor Cost: (False works Installation)

    Prod. Rate = 50 bd.ft./man-day

    Employ = 1 Foreman

  • 7/27/2019 MAGULON BHS

    11/67

    2 Carpenter

    4 Laborers

    Duration = 5.48 say 5.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 5.5 1,754.50

    Carpenter 2 259 5.5 2,849.00

    Laborers 4 243 5.5 5,346.00

    9,949.50Labor Cost: (False works removal)

    Prod. Rate = 100 bd.ft/man-day

    Employ = 1 Foreman

    1 Carpenter

    2 Laborers

    Duration = 4.79 say 5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 5 1,595.00

    Carpenter 1 259 5 1,295.00

    Laborers 2 243 5 2,430.00

    5,320.00

    Direct Cost = 96,969.50

    e. Carpentry Works

    e.1 Door Jamb QTY = 150.22 bd.ft

    Material Cost:

    Description Unit Qty Unit Cost Amount

    D-1 (1.4mX2.1m) sets 1 1200 1,200.00

    D-2 (1mX2.1m) sets 2 1000 2,000.00

    D-3 (0.8mX2.1m) sets 2 1000 2,000.00

    D-4 (0.8mX2.1m) sets 2 1000 2,000.00D-5 (0.7X2.1m)-incorporated in Item J.1 7,200.00

    Labor Cost:

    Prod. Rate = 40 bd.ft/man-day

    Employ = 1 Foreman= 2 Carpenter

    = 2 Laborers

    Duration = 0.94 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00

    Carpenter 2 259 1 518.00

    Laborers 2 243 1 486.00

    1,323.00

    Direct Cost = 8,523.00

    e.2 Ceiling joists & hanger QTY = 90.42 m

    inside area = 56.36 moutside area = 34.06 m

    e.2.1 Inside

    Description Unit Qty Unit Cost Amount

    7- 2"x2"x8' b.f. 19 22.00 410.67

    66- 2"x2"x10' b.f. 220 22.00 4,840.00

    7- 2"x2"x12' b.f. 28 22.00 616.00

    14- 2"x2"x14' b.f. 65 22.00 1,437.33

    Assorted CWN kg 7 79.00 553.00

    7,857.00

    e.2.2 Outside

  • 7/27/2019 MAGULON BHS

    12/67

    Material Cost:

    Description Unit Qty Unit Cost Amount

    32- 2"x2"x8' b.f. 85 22.00 1,877.33

    36- 2"x2"x12' b.f. 144 22.00 3,168.00

    Assorted CWN kg 3 79.00 237.00

    5,282.33

    Labor Cost:

    Prod. Rate = 5.3 m/man-dayEmploy = 1 Foreman

    = 2 Carpenter

    = 2 Laborers

    Duration = 4.27 say 4.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 4.5 1,435.50

    Carpenter 2 259 4.5 2,331.00

    Laborers 2 243 4.5 2,187.00

    5,953.50

    Direct Cost = 19,092.83

    e.3 Ceiling board QTY = 90.42 m

    inside area = 56.36 m

    outside area = 34.06 m

    e.3.1 Inside

    Description Unit Qty Unit Cost Amount

    1/4" thk Marine Plywood pcs 20 318.00 6,360.00

    1" CWN kg 2 79.00 158.00

    6,518.00

    e.3.2 Outside

    Material Cost:

    Description Unit Qty Unit Cost Amount

    1/4" thk Marine Plywood pcs 12 318.00 3,816.00

    1" CWN kg 1 79.00 79.00

    3,895.00

    Labor Cost:

    Prod. Rate = 12.5 m/man-day

    Employ = 1 Foreman

    = 2 Carpenter

    = 2 Laborers

    Duration = 1.81 say 2 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2 638.00

    Carpenter 2 259 2 1,036.00

    Laborers 2 243 2 972.00

    2,646.00

    Direct Cost = 13,059.00

    e.4 Fascia board QTY = 36.00 l.m.

    Material Cost:

    Description Unit Qty Unit Cost Amount

    8pcs-1"x12"x8' b.f. 64 22.00 1,408.00

    8pcs-1"x12"x10' b.f. 80 22.00 1,760.00

    Assorted CWN kg 1 79.00 79.00

    3,247.00

    Labor Cost: (Installation)

    Prod. Rate = 10 l.m/man-day

  • 7/27/2019 MAGULON BHS

    13/67

    Employ = 1 Foreman

    = 1 Carpenter

    = 1 Laborers

    Duration = 1.8 say 2 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2 638.00

    Carpenter 1 259 2 518.00

    Laborers 1 243 2 486.001,642.00

    Direct Cost = 4,889.00

    e.5 Moulding QTY = 84.03 l.m.

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Quarter round moulding pcs 36.00 50.00 1,800.00

    Assorted CWN kg 0.50 79.00 39.50

    1,839.50

    Labor Cost:

    Prod. Rate = 50 l.m/man-day

    Employ = 1 Foreman

    = 1 Carpenter

    = 1 Laborers

    Duration = 0.84 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00

    Carpenter 1 259 1 259.00

    Laborers 1 243 1 243.00

    821.00

    Direct Cost = 2,660.50

    e.6 Wood Louver Ventilation QTY = 2.00 sets

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Ventilation set 2 350 700.00

    Labor Cost:

    Prod. Rate = 4 sets/man-day

    Employ = 1 Foreman

    = 1 Carpenter

    Duration = 0.5 say 0.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 0.5 159.50

    Carpenter 1 259 0.5 129.50

    289.00

    Direct Cost = 989.00

    e.7 Lavatory cabinet door(flush door type) & jambs QTY = 1.00 lot

    Material Cost:

    Description Unit Qty Unit Cost Amount

    2"x4"x10' b.f. 47 22.00 1,026.67

    2"x3"x8' b.f. 56 22.00 1,232.00

    1/4" thk Marine Plywood pcs 2 318.00 636.00

    Assorted CWN kg 3 79.00 237.00

    3,131.67

    Labor Cost: (Fabrication & Installation)

    Description No. Rate No. of Days Amount

  • 7/27/2019 MAGULON BHS

    14/67

    Foreman 1 319 4 1,276.00

    Carpenter 1 259 4 1,036.00

    Laborer 1 243 4 972.00

    3,284.00

    Direct Cost = 6,415.67

    e.8 Counter Top(Midwife Station) QTY = 1.00 lot

    Material Cost:

    Description Unit Qty Unit Cost Amount2"x5"x8' Jambs b.f. 13 22.00 293.33

    Quarter Round Moulding pcs 2 50.00 100.00

    1/4" thk Clear Glass sq.ft. 16 50.00 800.00

    Assorted CWN kg 1 79.00 79.00

    1,272.33

    Labor Cost: (Fabrication & Installation)

    Description No. Rate No. of Days Amount

    Foreman 1 319 2 638.00

    Carpenter 1 259 2 518.00

    Laborer 1 243 2 486.00

    1,642.00

    Direct Cost = 2,914.33

    f. Roof Framing

    f.1 Truss QTY = 326.00 bd.ft

    Material Cost:

    Description Unit Qty Unit Cost Amount

    4pcs- 2"x"6"x16' Top Chord b.f. 64 22.00 1,408.00

    8pcs- 2"x6"x14' Bottom Chord b.f. 112 22.00 2,464.00

    1pc-2"x6"x10' King Post b.f. 10 22.00 220.00

    Web Members

    2pcs- 2"x6"x12' b.f. 24 22.00 528.00

    2pcs- 2"x6"x10' b.f. 16 22.00 352.00

    2pcs- 2"x6"8' b.f. 20 22.00 440.00

    2pcs- 2"x6"x10' Collar Plate b.f. 20 22.00 440.00

    2pcs-2"x6"x8' Wood Block b.f. 16 22.00 352.00

    3pcs-2"x6"x10' Truss support b.f. 30 22.00 660.00

    1pc- 2"x8"x10' Base plate b.f. 14 22.00 308.00Assorted CWN kg 5 79.00 395.005/8"x10" Machine Bolts w/ nuts & washer pcs 16 70 1,120.005/8"x8" Machine Bolts w/ nuts & washer pcs 52 56 2,912.00

    6mm thk metal strap pcs 8 126 1,008.00

    12,607.00

    Labor Cost: (fabrication & installation)

    Prod. Rate = 27 bd.ft/man-day

    Employ = 1 Foreman

    2 Carpenter

    2 Laborers

    Duration = 3.02 say 3.5 days

    Description No. Rate No. of Days AmountForeman 1 319 3.5 1,116.50

    Carpenter 2 259 3.5 1,813.00

    Laborers 2 243 3.5 1,701.00

    4,630.50

    Direct Cost = 17,237.50

    f.2 Rafter QTY = 206.00 bd.ft

    Material Cost:

    Description Unit Qty Unit Cost Amount

    10pcs- 2"x"6"x16' Top Chord b.f. 160 22.00 3,520.00

  • 7/27/2019 MAGULON BHS

    15/67

    3pcs- 2"x6"x10' Collar Plate b.f. 30 22.00 660.00

    1pc- 2"x8"x12' Base plate b.f. 16 22.00 352.00

    Assorted CWN kg 4 79.00 316.00

    5/8"X10" anchor bolts w/ N&W pcs 24 70.00 1,680.00

    1/2"X8" anchor bolts w/ N&W pcs 20 54.00 1,080.00

    5/8"X3" machine bolts w/ N&W pcs 6 21.00 126.00

    6mm thk metal strap pcs 12 126 1,512.00

    9,246.00

    Labor Cost: (fabrication & installation)Prod. Rate = 40 bd.ft/man-day

    Employ = 1 Foreman

    = 2 Carpenter

    = 2 Laborers

    Duration = 1.29 say 1.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1.5 478.50

    Carpenter 2 259 1.5 777.00

    Laborers 2 243 1.5 729.00

    1,984.50

    Direct Cost = 11,230.50

    f.3 Purlins QTY = 110.00 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    64pcs- 2"x"3"x10' Purlins b.f. 320 22.00 7,040.00

    12pcs- 2"x2"x10' Cleats b.f. 40 22.00 880.00

    Assorted CWN kg 10 79.00 790.00

    8,710.00

    Labor Cost:

    Prod. Rate = 11.5 m/man-day

    Employ = 1 Foreman

    = 2 Carpenter

    = 2 Laborers

    Duration = 2.39 say 2.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2.5 797.50

    Carpenter 2 259 2.5 1,295.00

    Laborers 2 243 2.5 1,215.00

    3,307.50

    Direct Cost = 12,017.50

    g. Roofing Works

    g.1 Corrugated GI Roof QTY = 110.00 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Ga #26 Corrugated GI Roofing(10ft length) lin.ft 320 32.50 10,400.00

    Ga #26 Corrugated GI Roofing(8ft length) lin.ft 256 32.50 8,320.00

    Umbrella Nail kgs 12 105.00 1,260.00 19,980.00

    Labor Cost:

    Prod. Rate = 5.3 m/man-day

    Employ = 1 Foreman

    4 Carpenter

    4 Laborers

    Duration = 2.59 say 3 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 3 957.00

  • 7/27/2019 MAGULON BHS

    16/67

    Carpenter 4 259 3 3,108.00

    Laborers 4 243 3 2,916.00

    6,981.00

    Direct Cost = 26,961.00

    g.2 Plain GI Ridge Roll & Flashing QTY = 53.00 l.m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Ga #26 Pre-fab Flashing(8' length) pcs 20 162.00 3,240.00Ga #26 Pre-fab Ridge Roll(15"x8' length) pcs 6 162.00 972.00

    Flat head nail kg 2 84.00 168.00

    4,380.00

    Labor Cost:

    Prod. Rate = 11.5 l.m./man-day

    Employ = 1 Foreman

    2 Carpenter

    2 Laborers

    Duration = 1.15 say 1.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1.5 478.50

    Carpenter 2 259 1.5 777.00

    Laborers 2 243 1.5 729.00

    1,984.50

    Direct Cost = 6,364.50

    h. Masonry Works QTY = 176.27 m

    Basement Floor Wall(6" CHB) = 29.12 m

    Basement Floor Wall(4" CHB) = 24.14 m

    Ground Floor Walls(4"CHB) = 109.29 m

    Lavatory (6" CHB) = 3.36 m

    Septic Vault (4" CHB) = 13.72 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    4" CHB pcs 1932 10.00 19,320.00

    6" CHB pcs 427 13.75 5,871.25Portland Cement bags 111 252.00 27,972.00

    Sand(S-1) m 10 1212.50 12,125.00

    12mm(Horizontal & Vertical bars) kg 37.31 35.50 1,324.51

    10mm(Horizontal & Vertical bars) kg 295 35.50 10,472.50

    Ga #16 Tie Wire kg 6 74.00 444.00

    77,529.26

    Labor Cost: (4"CHB)

    Prod. Rate = 3 m/man-day

    Employ = 1 Foreman

    3 Mason

    3 Laborers

    Duration = 7.41 say 7.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 7.5 2,392.50

    Mason 3 259 7.5 5,827.50

    Laborers 3 243 7.5 5,467.50

    13,687.50

    Labor Cost: (6"CHB)

    Prod. Rate = 2.5 m/man-day

    Employ = 1 Foreman

    3 Mason

  • 7/27/2019 MAGULON BHS

    17/67

    3 Laborers

    Duration = 1.94 say 2 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2 638.00

    Mason 3 259 2 1,554.00

    Laborers 3 243 2 1,458.00

    3,650.00

    Direct Cost = 94,866.76i. Plastering & Finishing

    i.1 Walls QTY = 346.50 m

    Basement Floor Walls(inside & outside) = 61.91 m

    Ground Floor Walls(inside & outside) = 263.31 m

    Lavatory counter top stand = 6.72 m

    Septic Vault = 14.56 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Portland Cement pcs 104 252.00 26,208.00

    Sand pcs 9 1212.50 10,912.50

    37,120.50

    Labor Cost:

    Prod. Rate = 4 m/man-day

    Employ = 1 Foreman

    3 Mason

    3 Laborers

    Duration = 15 say 15 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 15 4,785.00

    Mason 3 259 15 11,655.00

    Laborers 3 243 15 10,935.00

    27,375.00

    Direct Cost = 64,495.50

    i.2 Columns & Beams QTY = 68.25 m

    Basement Floor Columns = 23.00 mGround Floor Beams & Columns = 30.75 m

    Roof Beams = 14.50 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Portland Cement pcs 21 252.00 5,292.00

    Fine Sand pcs 2 1212.50 2,425.00

    7,717.00

    Labor Cost:

    Prod. Rate = 2.8 m/man-day

    Employ = 1 Foreman

    3 Mason

    2 Laborers

    Duration = 5 say 5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 5 1,595.00

    Mason 3 259 5 3,885.00

    Laborers 2 243 5 2,430.00

    7,910.00

    Direct Cost = 15,627.00

    j. Doors & Windows

    j.1 Doors QTY = 16.80 m

  • 7/27/2019 MAGULON BHS

    18/67

    Computations:

    D-1(2.1mx1.4m) = 2.94 m

    D-2(2.1mx1.0m) = 4.20 m

    D-3(2.1mx0.8m) = 3.36 m

    D-4(2.1mx0.8m) = 3.36 m

    D-5(2.1mx0.7m) = 2.94 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    D-1(2.1mx1.4m Panel Type Door) sets 1 6000 6,000.00D-2(2.1mx1.0m Panel Type Door) sets 2 4000 8,000.00

    D-3(2.1mx0.8m Flush Type Door) sets 2 2200 4,400.00

    D-4(2.1mx0.8m Flush Type Door) sets 2 2200 4,400.00

    D-5(2.1mx0.7m PVC Type Door) sets 2 1365 2,730.00

    4"x4" Loose Pin Hinges pcs 21 53.00 1,113.00

    Door Knob(Lever Type) sets 9 473.00 4,257.00

    30,900.00

    Labor Cost: (Installation of doors,hinges & door knob)

    Prod. Rate = 2 m/man-day

    Employ = 1 Foreman

    = 2 Carpenter

    = 2 Laborers

    Duration = 2.1 say 2.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2.5 797.50

    Carpenter 2 259 2.5 1,295.00

    Laborers 2 243 2.5 1,215.00

    3,307.50

    Direct Cost = 34,207.50

    j.2 Windows QTY = 16.20 m

    Computations:

    W-1(1.5mx1.8m) = 5.4 m

    W-2(1.5mx1.2m) = 7.20 m

    W-3(1.2mx1.2m) = 2.88 m

    W-4(0.6mx0.6m) = 0.72 mMaterial Cost:

    Description Unit Qty Unit Cost Amount

    W-1(1.5mx1.8m) sq.ft 58 210.00 12,201.00

    W-2(1.5mx1.2m) sq.ft 77 210.00 16,266.60

    W-3(1.2mx1.2m) sq.ft 31 210.00 6,505.80

    W-4(0.6mx0.6m) sq.ft 8 210.00 1,627.50

    3/16" Clear Glass sq.ft 174 25.00 4,357.25

    Silicon pcs 20 158.00 3,160.00

    Silicon Gun pcs 1 158.00 158.00

    44,276.15

    Labor Cost: (Installation)

    Prod. Rate = 1.6 m/man-day

    Employ = 1 Foreman= 2 Welders

    = 2 Laborers

    Duration = 2.53 say 3 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 3 957.00

    Welders 2 259 3 1,554.00

    Laborers 2 243 3 1,458.00

    3,969.00

    Direct Cost = 48,245.15

  • 7/27/2019 MAGULON BHS

    19/67

    k. Tileworks QTY = 29.97 m

    Toilet Floor Tiles = 4.20 m

    Toilet Walls Tiles = 14.85 m

    Lavatory = 10.92 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    8"X8" Ceramic Tiles pcs 367.00 14.00 5,138.00Tile Trim pcs 13.00 53.00 689.00

    Tile Grout(2-kg pack) bags 15 53.00 795.00

    Portland Cement bags 3 252.00 756.00

    Sand m 1 1212.50 1,212.50

    8,590.50

    Labor Cost: (Installation)

    Prod. Rate = 5 m/man-day

    Employ = 1 Foreman

    = 1 Skilled Laborer

    = 1 Laborers

    Duration = 3 say 3 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 3 957.00

    Skilled Laborer 1 259 3 777.00

    Laborers 1 243 3 729.00

    2,463.00

    Direct Cost = 11,053.50

    l. Painting and Varnishing

    l.1 Ceiling

    l.1.1 Ground Floor Ceiling QTY = 90.42 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Flatwall enamel gal 5 499.00 2,495.00

    Semi-gloss Quick Drying Enamel(2nd

    Coat) gal 4 538.00 2,152.00

    Semi-gloss Quick Drying Enamel(3rd

    Coat) gal 4 538.00 2,152.00

    9" Paint Roller(With Handle) set 4 168.00 672.00Paint Tray pcs 2 38.00 76.00

    1" Paint Brush pcs 4 15.00 60.00

    2" Paint Brush pcs 4 26.00 104.00Choco Brown (for the Moulding) gal 1 530.00 530.00

    Glazing Putty gal 1 578.00 578.00

    Paint thinner gal 1 273.00 273.00

    Laquer Thinner gal 1 263.00 263.00

    # 100 Sand Paper pcs 10 53.00 530.00

    # 120 Sand Paper pcs 8 53.00 424.00

    # 140 Sand Paper pcs 8 53.00 424.00

    10,733.00

    Labor Cost 1:(Surface Preparation)

    Prod. Rate = 80 m/man-dayEmploy = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.57 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00

    Painter 1 259 1 259.00

    Laborer 1 243 1 243.00

    821.00

  • 7/27/2019 MAGULON BHS

    20/67

    Labor Cost 2:(1st

    Coat Wood Primer)

    Prod. Rate = 57 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.79 say 1 days

    Description No. Rate No. of Days AmountForeman 1 319 1 319.00

    Painter 1 259 1 259.00

    Laborer 1 243 1 243.00

    821.00

    Labor Cost 3:(2nd

    Coat enamel paint)

    Prod. Rate = 53 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.85 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00Painter 1 259 1 259.00

    Laborer 1 243 1 243.00

    821.00

    Labor Cost 4:(3rd

    Coat ename paint)

    Prod. Rate = 50 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.9 say 1 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 1 319.00

    Painter 1 259 1 259.00

    Laborer 1 243 1 243.00

    821.00

    Direct Cost = 14,017.00

    l.1.2 Basement Floor Ceiling QTY = 22.91 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Flatwall Latex(1st

    Coat) gal 1 448.00 448.00

    Semi-gloss Latex(2nd

    Coat) gal 1 518.00 518.00

    Concrete Neutralizer gal 1 430.00 430.00

    Masonry Putty gal 1 480.00 480.00

    9" Paint Roller(With Handle) set 2 168.00 336.00

    Paint Tray pcs 2 38.00 76.001" Paint Brush pcs 2 15.00 30.00

    2" Paint Brush pcs 2 26.00 52.00

    # 100 Sand Paper pcs 5 53.00 265.00

    # 120 Sand Paper pcs 5 53.00 265.00

    # 140 Sand Paper pcs 5 53.00 265.00

    3,165.00

    Labor Cost 1:(Surface Preparation)

    Prod. Rate = 100 m/man-day

    Employ = 1 Foreman

  • 7/27/2019 MAGULON BHS

    21/67

    = 1 Painter

    = 1 Laborer

    Duration = 0.11 say 0.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 0.5 159.50

    Painter 1 259 0.5 129.50

    Laborer 1 243 0.5 121.50

    410.50

    Labor Cost 2:(Masonry Sealer)

    Prod. Rate = 57 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.46 say 0.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 0.5 159.50

    Painter 1 259 0.5 129.50

    Laborer 1 243 0.5 121.50

    410.50

    Labor Cost 3:(1st

    Coat)Prod. Rate = 50 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.23 say 0.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 0.5 159.50

    Painter 1 259 0.5 129.50

    Laborer 1 243 0.5 121.50

    410.50

    Labor Cost 4:(2nd &

    3rd

    Coat)

    Prod. Rate = 44 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 0.3 say 0.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 0.5 159.50

    Painter 1 259 0.5 129.50

    Laborer 1 243 0.5 121.50

    410.50

    Direct Cost = 4,807.00

    l.2 Walls, Columns & Beams QTY = 414.75 m

    Material Cost:

    Description Unit Qty Unit Cost Amount

    Flatwall Latex(1st

    Coat) gal 17 448.00 7,616.00

    Semi-gloss Latex(2nd

    Coat) gal 17 518.00 8,806.00

    Concrete Neutralizer gal 14 430.00 6,020.00

    Masonry Putty gal 2 480.00 960.00

    9" Paint Roller(with Handle) set 4 168.00 672.00

    Paint Tray pcs 4 38.00 152.00

  • 7/27/2019 MAGULON BHS

    22/67

    1" Paint Brush pcs 2 15.00 30.00

    2" Paint Brush pcs 2 26.00 52.00

    # 100 Sand Paper pcs 10 53.00 530.00

    # 120 Sand Paper pcs 6 53.00 318.00

    # 140 Sand Paper pcs 6 53.00 318.00

    25,474.00

    Labor Cost 1:(Surface Preparation)

    Prod. Rate = 100 m/man-day

    Employ = 1 Foreman= 1 Painter

    = 1 Laborer

    Duration = 2.07 say 2.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 2.5 797.50

    Painter 1 259 2.5 647.50

    Laborer 1 243 2.5 607.50

    2,052.50

    Labor Cost 2:(Masonry Sealer)

    Prod. Rate = 57 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 3.64 say 4 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 4 1,276.00

    Painter 1 259 4 1,036.00

    Laborer 1 243 4 972.00

    3,284.00

    Labor Cost 3:(1st

    Coat)Prod. Rate = 50 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer Duration = 4.15 say 4.5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 4.5 1,435.50

    Painter 1 259 4.5 1,165.50

    Laborer 1 243 4.5 1,093.50

    3,694.50

    Labor Cost 4:(2nd &

    3rd

    Coat)Prod. Rate = 44 m/man-day

    Employ = 1 Foreman

    = 1 Painter

    = 1 Laborer

    Duration = 4.71 say 5 days

    Description No. Rate No. of Days Amount

    Foreman 1 319 5 1,595.00

    Painter 1 259 5 1,295.00

    Laborer 1 243 5 1,215.00

    4,105.00

    Direct Cost = 38,610.00

    III SANITARY WORKS

    a.1 Sewerage System QTY = 1.00 lot

  • 7/27/2019 MAGULON BHS

    23/67

    Material Cost:

    Description Unit Qty Unit Cost Amount

    100mmx3.0m PVC pipe(Orange) pcs 6 578.00 3468

    100mmx100mm wye pcs 1 189.00 189

    100mmx50mm wye reducer pcs 8 189.00 1512

    100mmx45 deg elbow pcs 5 189.00 945

    100mm dia. clean out pcs 2 100.00 200

    50mmx 3.0m pvc pipe pcs 3 368.00 1104

    50mmx50mm Tee pcs 7 79.00 55350mmx90 deg elbow pcs 8 47.00 376

    50mmx45 deg elbow pcs 19 47.00 893

    50mm p-trap pcs 4 79.00 316

    100mm x 100mm stainless, floor drain pcs 2 95.00 190

    Teflon tape pcs 5 25.00 125

    Solvent liter 2 180.00 360

    10,231.00

    Labor Cost:

    Description No. Rate No. of Days Amount

    Foreman 1 319 3 957.00

    Plumber 2 259 3 1,554.00

    Laborer 2 243 3 1,458.00

    3,969.00

    Direct Cost = 14,200.00

    a.2 Water Lines & Fittings QTY = 1.00 lot

    Material Cost:

    Description Unit Qty Unit Cost Amount

    13mmx6m G.I. Pipe(sch. 40) pcs 5 299.00 1495

    13mm coupling pcs 2 42.00 84

    13mm union pcs 2 37.00 74

    13mm dia. tee pcs 14 16.00 224

    13mm dia. X 90 deg elbow pcs 11 11.00 121

    13mm dia. gate valve pcs 1 210.00 210

    13mmx300mm nipple pcs 9 45.00 405

    Wall faucet(short) pcs 2 210.00 420

    Gooseneck Spout Faucet pcs 5 851.00 4255Teflon tape pcs 5 25.00 125

    7,413.00

    Labor Cost:

    Description No. Rate No. of Days Amount

    Foreman 1 319 2 638.00

    Plumber 2 259 2 1,036.00

    Laborer 2 243 2 972.00

    2,646.00

    Direct Cost = 10,059.00

    a.3 Sanitary Fixtures & Accessories QTY = 1.00 lot

    Material Cost:

    Description Unit Qty Unit Cost AmountLavatory(Stainless) & Accessories sets 3 2100.00 6300

    Lavatory(ceramic) wall hang sets 2 924.00 1848

    Water closet sets 2 5040.00 10080

    3/8mm (1 1/2") x 0.60m stainless steel grab bar sets 2 350.00 700

    Tissue holder pcs 2 280.00 560

    Soap holder pcs 2 280.00 560

    Hose bib pcs 2 90.00 180

    20,228.00

    Labor Cost:

    Description No. Rate No. of Days Amount

  • 7/27/2019 MAGULON BHS

    24/67

    Foreman 1 319 2 638.00

    Plumber 2 259 2 1,036.00

    Laborer 2 243 2 972.00

    2,646.00

    Direct Cost = 22,874.00

    IV ELECTRICAL WORKS QTY = 1.00 lot

    Material Cost:

    Description Unit Qty Unit Cost AmountEntrance cap set 1 150 150

    Meter box set 1 800 800

    Kilowatt-hour meter with base set 1 2420 2420

    Panel board center main TQC all bolt set 1 12700 12700

    2 poles, 1-100A, 4-15A, 6-20A

    13mm dia. pvc pipe(Mark Certified) pcs 150 55 8250

    32mm dia pvc pipe(Mark Certified) pcs 2 150 300

    12mm dia. X 3m ground rod pcs 1 500 500

    38.0mm2

    TW l. m. 3 240 720

    2.0mm2

    THHN(Phelph-dodge) box 2 2600 5200

    3.5.0mm2

    THHN(Phelph-dodge) box 2 3300 6600

    50mm x 100mm utility box (deep type) pcs 32 25 800

    Junction box pcs 27 30 810Convenience outlet element pcs 38 50 1900

    Weatherproof duplex convenience outlet sets 4 450 1800

    Electrical switch element

    Single Pole switch element sets 18 50 900

    Threeway switch sets 6 180 1080

    Switch & Convenient Outlet plate

    Single gang plate sets 5 25 125

    Two gang plate sets 11 25 275

    Three gang plate sets 3 25 75

    4" dia. receptacle pcs 25 35 875

    20 watts CFL (Philips) pcs 25 220 5500

    Electrical Tape(Big) pcs 5 27 135

    51,915.00

    Labor Cost:(Note: Including installation/setting of panel board & breakers )

    Description No. Rate No. of Days Amount

    Foreman 1 319 13 4,147.00

    Electrician 2 259 13 6,734.00

    Laborer 2 243 13 6,318.00

    17,199.00

    Direct Cost = 69,114.00

    A. TRANSHIPMENT OF CEMENT

    Source: Lamut

    Ave.Hauling Loaded Unloaded

    Dist. (Kms) Speed(Kph) Speed(Kph)

    Paved road at 7%-12% Grade 1 15 20

    Unpaved road at 7%-12% Grade 13 5 10

    Manuevering time/ Slack Time = 6 mins

    Loading Time = 30 mins

    Loaded Travel Time = 160 mins

    Unloaded Travel Time = 81 mins

    Unloading Time = 30 mins

    307 mins

    Using 1 Unit Dumptruck with capacity of 120bags

    Working hours/day = 8 hrs

    DERIVATION OF UNIT COST OF MATERIALS

    Road condition

  • 7/27/2019 MAGULON BHS

    25/67

    Rate per day = 4800 php

    Total cycle time = 307 mins

    Transhipment Cost/bag = 307 mins x 4,800/day x 1 day/8hrs x 1hr/60mins.

    120 bags

    Php. = 25.58 say 26.00 /bag

    B. TRANSHIPMENT OF SAND AND GRAVEL

    Source: Ongto

    Ave.Hauling Loaded Unloaded

    Dist. (Kms) Speed(Kph) Speed(Kph)

    Paved road at 7%-12% Grade 10 15 20

    Unpaved road at 7%-12% Grade (single lane) 13 5 10

    Manuevering time/ Slack Time = 6 mins

    Loading Time = 10 mins

    Loaded Travel Time = 196 mins

    Unloaded Travel Time = 108 mins

    Unloading Time = 5 mins

    325 mins

    Using 1 Unit Dumptruck with capacity of 4.00 Cu.m Dump truck

    Working hours/day = 8 hrs

    Rate per day = 4800 php

    Total cycle time = 325 mins

    Transhipment Cost/m = 325 mins x 4,800/1day x 1 day/8hrs x 1hr/60mins.

    4 m

    Php. = 812.50 say 812.50 /m

    Description Unit Pick-up Transhipment Unit Cost

    Price

    Cement Bag(s) 226 26.00 252.00

    Sand Cu.m 400 812.50 1212.50

    Gravel Cu.m 500 812.50 1312.50RSB Kgs 35 0.50 35.50

    Plywood (1/4") Pcs 315 3.00 318.00

    Marine plywood Pcs 315 3.00 318.00

    #16 tie wire kg 74 0.00 74.00

    Common Wire Nail kg 79 0.00 79.00

    Flat Head Nail kg 84 0.00 84.00

    Flatwall latex gal 448 0.00 448.00

    Semi-gloss latex gal 518 0.00 518.00

    Concrete neutralizer gal 430 0.00 430.00

    Masonry putty gal 480 0.00 480.00

    Flatwall enamel gal 499 0.00 499.00

    Semi-gloss Quick Drying Enamel gal 538 0.00 538.00

    Glazing Putty gal 578 0.00 578.00

    Choco Brown gal 530 0.00 530.00Laquer thinner gal 263 0.00 263.00

    Paint thinner gal 273 0.00 273.00

    Paint Roller pc 168 0.00 168.00

    Paint Tray pc 38 0.00 38.00

    2" Paint Brush pc 26 0.00 26.00

    1" Paint Brush pc 15 0.00 15.00

    # 100 Sand Paper pc 53 0.00 53.00

    # 120 Sand Paper pc 53 0.00 53.00

    # 140 Sand Paper pc 53 0.00 53.00

    Quarter round cornice pc 50 0.00 50.00

    SUMMARY OF UNIT COST

    Road condition

  • 7/27/2019 MAGULON BHS

    26/67

    12' Ga #26 Corrugated GI Roofing(Galvalume) lin.ft. 32.00 0.50 32.50

    8' Ga #26 Corrugated GI Roofing(Galvalume) lin.ft. 32 0.50 32.50

    Ga #26 Plain GI(2.4m length) lin.ft. 475 0.25 475.25

    Ga #26 Ridge Roll(2.4m length) lin.ft. 110 0.25 110.25

    5/8"x8" Machine Bolts w/ nuts & washer lin.In. 56 0.00 56.00

    5/8"x10" Machine Bolts w/ nuts & washer lin.In. 70 0.00 70.00

    5/8"x3" Machine Bolts w/ nuts & washer lin.In. 21 0.00 21.00

    1/2"x8" Anchor Bolts w/ nuts & washer set 54 0.00 54.00

    1/4"x2" Post Strap pc 126 0.00 126.00

    Umbrella Nail kg 105 0.00 105.00

    Ga #26 Prefab flashing pc 162 0.00 162.00

    Ga #26 Prefab Ridge Roll pc 162 0.00 162.00

    4" CHB pc 9.5 0.50 10.00

    6" CHB pc 13 0.75 13.75

    4"x4" Loose Pin Hinges pc 53 0.00 53.00

    Door Knob set 473 0.00 473.00

    Steel casement window sq.ft 210 0.00 210.00

    3/16" Clear glass sq.ft 25 0.00 25.00

    silicon pc 158 0.00 158.00

    Silicon Gun pc 158 0.00 158.00

    8"x8" Tiles(Mariwasa) pc 14 0.00 14.00

    Tile Trim pc 53 0.00 53.00

    Tile Grout(2-kg pack) bag 53 0.00 53.00

    Lumber bd.ft 22 0.00 22.00100mmx3.0m PVC pipe pc 578 0.00 578.00

    100mmx100mm wye pc 189 0.00 189.00

    100mm dia.x50mm dia. wye reducer pc 189 0.00 189.00

    100mm dia.x45 deg elbow pc 189 0.00 189.00

    100mm dia. clean out pc 100 0.00 100.00

    50mm dia. x 3.0m pvc pipe pc 368 0.00 368.00

    50mm dia.x50mm dia. Tee pc 79 0.00 79.00

    50mm dia.x90 deg elbow pc 47 0.00 47.00

    50mm dia.x45 deg elbow pc 47 0.00 47.00

    50mm dia. p-trap pc 79 0.00 79.00

    100mm x 100mm stainless, floor drain pc 95 0.00 95.00

    Teflon tape pc 25 0.00 25.00

    Solvent liter 180 0.00 180.00

    13mmx6m G.I. Pipe(sch. 40) pc 299 0.00 299.0013mm coupling pc 42 0.00 42.00

    13mm union pc 37 0.00 37.00

    13mm dia. tee pc 16 0.00 16.00

    13mm dia. X 90 deg elbow pc 11 0.00 11.00

    13mm dia. gate valve pc 210 0.00 210.00

    13mmx300mm nipple pc 45 0.00 45.00

    Gooseneck Spout Faucet pc 851 0.00 851.00

    Lavatory(Stainless) & Accessories pc 2100 0.00 2100.00

    Water closet(Tank Type) pc 5040 0.00 5040.00

    3/8mm (1 1/2") x0.60m stainless steel grab bar pc 350 0.00 350.00

    Tissue holder pc 280 0.00 280.00

    Soap holder pc 280 0.00 280.00

    Hose bib pc 90 0.00 90.00

  • 7/27/2019 MAGULON BHS

    27/67

    Item Description % Wt Quantity Unit DC IC UC Amount

    I Preliminaries/General requirements:

    1. Project Billboard 0.08 1.00 lot 800.00 212 1012 1,012.00

    II CIVIL WORKS

    a. Earthworks

    a.1. Excavation 0.98 47.89 m 9,971.00 2642.32 263.37 12,613.32

    a.2. Backfilling & Compaction 0.91 34.20 m 9,204.00 2439.06 340.44 11,643.05a.3. Gravel Bedding 1.11 7.99 m 11,305.00 2995.83 1789.6 14,300.85

    a.4 Soil Poisoning 0.81 174.60 m 8,227.50 2180.29 59.61 10,407.91

    b. Concreting Works 13.89 29.44 m 141,202.50 37418.7 6068.2 178,621.30

    c. Rebar Works & Tie Wire 16.14 4416.98 kgs 164,088.79 43483.5 46.99 207,553.89

    d. Formworks & Scaffolding 9.54 201.82 m 96,969.50 25696.9 607.81 122,666.69

    e. Carpentry Works

    e.1 Door Jamb 0.84 150.22 bd.ft 8,523.00 2258.6 71.77 10,781.58

    e.2 Ceiling joists & hanger 1.88 90.42 m 19,092.83 5059.6 267.11 24,152.09

    e.3 Ceiling board 1.28 90.42 m 13,059.00 3460.64 182.7 16,519.73

    e.4 Fascia board 0.48 36.00 l.m. 4,889.00 1295.59 171.79 6,184.44

    e.5 Moulding 0.26 84.03 l.m. 2,660.50 705.03 40.05 3,365.40

    e.6 Wood Louver Ventilation 0.10 2.00 sets 989.00 262.09 625.55 1,251.10

    e.7 Lavatory cabinet door(flush door 0.63 1.00 lot 6,415.67 1700.15 8115.8 8,115.82

    e.8 Counter Top(Midwife Station) 0.29 1.00 lot 2,914.33 772.3 3686.6 3,686.63

    f. Roof Framing

    f.1 Truss 1.70 326.00 bd.ft 17,237.50 4567.94 66.89 21,806.14

    f.2 Rafter 1.10 206.00 bd.ft 11,230.50 2976.08 68.96 14,205.76

    f.3 Purlins 1.18 110.00 m 12,017.50 3184.64 138.2 15,202.00

    g. Roofing Works

    g.1 Corrugated GI Roof 2.65 110.00 m 26,961.00 7144.67 310.05 34,105.50

    g.2 Plain GI Ridge Roll & Flashing 0.63 53.00 l.m 6,364.50 1686.59 151.91 8,051.23

    h. Masonry Works 9.33 176.27 m 94,866.76 25139.7 680.81 120,006.38

    i. Plastering & Finishing

    i.1 Walls 6.35 346.50 m 64,495.50 17091.3 235.46 81,585.71

    i.2 Columns & Beams 1.54 68.25 m 15,627.00 4141.16 289.64 19,767.93

    j. Doors & Windows 0.00

    j.1 Doors 3.37 16.80 m 34,207.50 9064.99 2575.7 43,272.43j.2 Windows 4.75 16.20 m 48,245.15 12785 3767.3 61,030.10

    k. Tileworks 1.09 29.97 m 11,053.50 2929.18 466.56 13,982.80

    l. Painting and Varnishing

    l.1 Ceiling

    l.1.1 Ground Floor Ceiling 1.38 90.42 m 14,017.00 3714.51 196.1 17,731.36

    l.1.2 Basement Floor Ceiling 0.47 22.91 m 4,807.00 1273.86 265.42 6,080.77

    l.2 Walls, Columns & Beams 3.80 414.75 m 38,610.00 10231.7 117.76 48,840.37

    III SANITARY WORKS

    a.1 Sewerage System 1.40 1.00 lot 14,200.00 3763 17963 17,963.00

    a.2 Water Lines & Fittings 0.99 1.00 lot 10,059.00 2665.64 12725 12,724.64a.3 Sanitary Fixtures & Accessories 2.25 1.00 lot 22,874.00 6061.61 28936 28,935.61

    IV ELECTRICAL WORKS 6.80 1.00 lot 69,114.00 18315.2 87429 87,429.21

    Total Direct Cost = 1,016,299.03

    Indirect Cost(26.5% of TDC) = 269,319.24

    Sub-total = 1,285,618.27

    PLGU Overhead Expenses =

    Construction Contingencies =

    Total Estimated Project Cost = 1,285,618.27

    SUMMARY

  • 7/27/2019 MAGULON BHS

    28/67

  • 7/27/2019 MAGULON BHS

    29/67

  • 7/27/2019 MAGULON BHS

    30/67

  • 7/27/2019 MAGULON BHS

    31/67

  • 7/27/2019 MAGULON BHS

    32/67

  • 7/27/2019 MAGULON BHS

    33/67

  • 7/27/2019 MAGULON BHS

    34/67

  • 7/27/2019 MAGULON BHS

    35/67

  • 7/27/2019 MAGULON BHS

    36/67

    Computations for CHB & bars: No. of wall/ RSB

    Width Height door/window Hor.

    Basement:(6"CHB) 2.7 3.2 2 17.28 5 pcs X 2.7

    3.7 3.2 1 11.84 5 pcs X 3.7

    29.12

    Basement:(4"CHB) 2.7 3.2 2 17.28 5 pcs X 2.7

    3.7 3.2 1 11.84 5 pcs X 3.7

    less doors/windows 1 2.1 1 2.11.2 1.2 2 2.88

    24.14

    Ground Floor: 3.7 2.7 2 19.98 5 pcs X 3.7

    2.7 2.7 9 65.61 5 pcs X 2.7

    2.7 2.7 3 21.87 5 pcs X 2.7

    3.4 3 1 10.2 5 pcs X 3.4

    2.8 3 1 8.4 5 pcs X 2.8

    1.9 3 1 5.7 5 pcs X 1.9

    1.85 3 1 5.55 5 pcs X 1.85

    less doors/windows 2.1 1.4 1 2.94

    2.1 1 1 2.1 plus 12% factor

    2.1 0.8 2 3.36 2.1 0.8 2 3.36

    2.1 0.7 2 2.94

    1.8 1.5 2 5.4

    1.2 1.5 4 7.2

    0.6 0.6 2 0.72

    109.29

    Septic Vault: 1.3 1.4 2 3.64

    1 1.4 1 1.4

    3.1 1.4 2 8.68

  • 7/27/2019 MAGULON BHS

    37/67

    13.72 m

    lavatory: 0.6 0.8 7 3.36 m

    Computat ions fo r wal l plaster ing: No. of faces/

    Width Height door/window

    Basement:(6"CHB) 2.7 2.45 2 13.233.7 2.45 1 9.065

    22.295 m

    Basement:(4"CHB) 2.7 2.45 4 26.46

    3.7 2.45 2 18.13

    less doors/windows 1 2.1 1 2.1

    1.2 1.2 2 2.88

    39.61 m

    Ground Floor: 3.7 2.7 4 39.96

    2.7 2.7 26 189.54

    3.4 2.7 2 18.36

    2.8 2.7 2 15.12

    1.9 2.7 2 10.26

    1.85 2.7 2 9.99

    1.5 2.7 2 8.1

    less doors/windows 2.1 1.4 1 2.94

    2.1 1 1 2.1

    2.1 0.8 2 3.36

    2.1 0.8 2 3.36

    2.1 0.7 2 2.94

    1.8 1.5 2 5.4

    1.2 1.5 4 7.2

    0.6 0.6 2 0.72

    263.31 m

    Septic Vault: 1.1 1.4 4 6.16

    1 1.4 2 2.82 1.4 2 5.6

    14.56 m

    Lavatory: 0.6 0.8 14 6.72 m

    Computat ions for columns & beams:

    Width Height No. of faces

    Basement floor:

    Columns: 0.5 2.8 5 7

    0.8 2.8 1 2.24

    0.2 2.45 4 1.96

    Beams: 2.7 0.5 4 5.43.7 0.5 1 1.85

    2.7 0.25 4 2.7

    3.7 0.25 2 1.85

    Ground Floor:

    Columns: 0.75 3 3 6.75

    0.8 3 1 2.4

    0.5 3 6 9

    0.2 3 11 6.6

    0.5 3 4 6

    Roof Beams:

  • 7/27/2019 MAGULON BHS

    38/67

    2.7 0.4 8 8.64

    3.7 0.4 2 2.96

    2.7 0.1 8 2.16

    3.7 0.1 2 0.74

    68.25

  • 7/27/2019 MAGULON BHS

    39/67

  • 7/27/2019 MAGULON BHS

    40/67

  • 7/27/2019 MAGULON BHS

    41/67

  • 7/27/2019 MAGULON BHS

    42/67

  • 7/27/2019 MAGULON BHS

    43/67

  • 7/27/2019 MAGULON BHS

    44/67

  • 7/27/2019 MAGULON BHS

    45/67

  • 7/27/2019 MAGULON BHS

    46/67

  • 7/27/2019 MAGULON BHS

    47/67

    1.00

    47.89

    34.20174.60

    29.44

    4,416.98

    201.82

    150.22

    36.00

    2.00

    326.00

    206.00

    110.00

    110.00

    53.00

    176.27

    47.44

    16.80

    16.20

    29.97

    1.00

    1.001.00

    1.00

    1,285,597.00

  • 7/27/2019 MAGULON BHS

    48/67

  • 7/27/2019 MAGULON BHS

    49/67

  • 7/27/2019 MAGULON BHS

    50/67

  • 7/27/2019 MAGULON BHS

    51/67

  • 7/27/2019 MAGULON BHS

    52/67

  • 7/27/2019 MAGULON BHS

    53/67

  • 7/27/2019 MAGULON BHS

    54/67

  • 7/27/2019 MAGULON BHS

    55/67

  • 7/27/2019 MAGULON BHS

    56/67

    Ver

    m 5 pcs X 3.20 m = 29.5 m

    m 7 pcs X 3.20 m = 40.9 m

    m 5 pcs X 3.20 m = 29.5 m

    m 7 pcs X 3.20 m = 40.9 m

    m 7 pcs X 2.70 m = 37.4 m

    m 5 pcs X 2.70 m = 27 m

    m 5 pcs X 2.70 m = 27 m

    m 6 pcs X 3.00 m = 35 m

    m 5 pcs X 3.00 m = 29 m

    m 4 pcs X 3.00 m = 21.5 m

    m 4 pcs X 3.00 m = 21.25 m

    338.95 m

    (splice & hooks) 372.845 m x 0.617kg/m= 258 kgs

  • 7/27/2019 MAGULON BHS

    57/67

  • 7/27/2019 MAGULON BHS

    58/67

  • 7/27/2019 MAGULON BHS

    59/67

  • 7/27/2019 MAGULON BHS

    60/67

  • 7/27/2019 MAGULON BHS

    61/67

  • 7/27/2019 MAGULON BHS

    62/67

  • 7/27/2019 MAGULON BHS

    63/67

  • 7/27/2019 MAGULON BHS

    64/67

  • 7/27/2019 MAGULON BHS

    65/67

  • 7/27/2019 MAGULON BHS

    66/67

  • 7/27/2019 MAGULON BHS

    67/67