Upload
ashley-woods
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
M12 GA - Brussels Status of WP6 and next phases
09/09/2015 – Mario Sisinni (SMS)
1. Introduction to WP6• Objectives of WP6• Official Deadlines• Progresses2. Refinement phase• Main achievements- Conference calls and events- Use Cases Objectives and boundaries- Profiles production- Grid models production- Simulations- Smart grid simulations
3. Implementation phase• Initial activities4. PMs allocation5. Communications
1. Introduction to WP6
WP6 is dedicated to the implementation of the technical use cases of the project. These will be used to test and validate the monitoring & management platform created in WPs 3-4-5 according to the business cases developed in WP1 and the platform technical requirements defined in WP2.
Objectives
Use case
General objectives Quantified objectives Security objectives
1
Connection between DSO and HAN
Dwelling - level energy savings up to 10%
Enhanced data privacy by resilience to malicious exploitation of household data
2
Effective energy management at district level (against classical grid flexibility)
Peak load reduction and energy savings up to 15%
Data integrity assurance techniques
Sabotage prevention
3
Enhanced grid reliability, performance and resilience
Grid losses reduction by 5-7%
Renewable grid hosting capacity increased by 12-15%
Reduced switch-off time per year
Cyber-attacks at LV grid level
1. Introduction to WP6
Official Deadlines
MS3 → M10Detailed use cases scenarios definition starts based on the outcomes of the second thematic workshopComment: Minutes of WP6 KO meeting available to the PTC. Note that this milestone is also related to WP1
D6.1 → M21Detailed use cases scenarios
MS4 → M27First use cases assessment based on the first version of the integrated platform (delivered at M24)Comment: Internal delivery – related WP6 technical meeting minutes submitted to the PTC. Note that this milestone is also related to WP2 to 5.
D6.2 → M33Validation report
D6.3 → M33Use cases assessment and wider uptake
1. Introduction to WP6
1. Introduction to WP6Progresses
Phase Completion date Progress
6.1 Refinement M21 90%
6.1 Implementation M33 Initial activities
6.2 Assessment M33 0%
• We are ahead of schedule with the refinement phase, that was supposed to start only after the second thematic workshop (that will be held in Brussels on the 11th of September);
• We are a bit late with the Milestone, but we started the refinement process very early. Refinement will be integrated with the outcomes of the September workshop with the DSOs and the results of the MAS prototype.
2. Refinement phaseMain achievements – Conference calls and events
Event Date Achievements
Kick-off meeting in Paris 4-5 Sept 14 • Presentation of WP6
Project workshop in Paris 13-14 Jan 15 • Initial discussion regarding Use Cases
6th Month GA in Waterford 25-27 Feb 15
• Wide brainstorming session on WP6 including district & management definition, reference standard and smart grid, simulations, physical tests, Link-Boxes, etc.
WP6 Conference call with consortium: “Actors of the smart grid”
19 Mar 15 • Definition of the actors of the smart grid, district manager and local dispatching services
WP6 Conference call with consortium: “Simulations and data”
1 Apr 15 • Definition of electrical and MAS simulations processes• Discussion on provision of load profiles and other data required
by simulations
WP6 Conference calls with specific partners
Mar-May 15 • Consistency in prototype definition & creation• Definition of user stories for the use cases
Meeting with CU in Cardiff 27 Apr 15 • Technical challenges related to district management & Link Boxes
• Impact assessment on penetration of smart grid technologies
Project workshop in Milan 6 May 15 • District management and Link Boxes from a business perspective
• Local dispatching and flexibility services• Local dispatching and flexibility market
Project workshop in Paris 29-30 Jun 15 • Clarification on use cases objectives and boundaries
WP6 Conference calls with specific partners & second meeting with CU
Jul-Sep 15 • Agreement on data production & simulation activities• Agreement on physical tests
2. Refinement phaseMain achievements – Use cases objectives and boundaries
Use case 1
Demonstration of secure and effective connection of commercial home energy boxes with public DSO meters. In particular in terms of:- Enabling HAN side energy consumption data collection- Enabling connection between DSO smart meter and the TI smart gateway- Ensuring data privacy- Ability to schedule domestic loads
Main progresses
- Objectives and boundaries of UC1 agreed with TI and the consortium- Advanced list of physical tests to be carried out for UC1 to be issued by TI by the 18 th of
September and showed during the review meeting
Next phases
- Start with the implementation phase
2. Refinement phaseMain achievements – Use cases objectives and boundaries
Use case 2Demonstration of the effectiveness of balancing and optimization at district/neighbourhood level as an alternative to traditional centralized optimization. This use case will focus on the optimization at more local level (i.e. between two or few more energy boxes) to demonstrate the potential benefits of such a local energy management to DSOs. Due to this decentralized and small-scale approach, the use case will only rely on physical tests to be carried out in LAB and ENGIE facilities and on implementation of MAS optimization at such low level (If needed it will also rely on simulations of very small portion of the LV grid). The aim is to verify, based on real data, how these local areas can adapt to varying external conditions by simple interaction between energy boxes and enhanced demand side management. In this scenario the DSO provides the inputs/objectives of the local optimization (e.g. reduction of the peak at a certain time) according to some specific user stories. However in UC2 these user stories do not take into consideration aspects related to the actual energy market and regulations and to the conflicting objectives of final customers and DSOs. These and other aspects related to the complex relationships between grid actors and the consequent benefits & effects on the global optimization process will be properly taken into account in Use case 3.
Main progresses
- Objectives and boundaries of UC2 agreed with ENGIE and the consortium- Advanced list of physical tests to be carried out for UC2 to be discussed during GA issued by ENGIE
by the 18th of September to be showed during the review meeting
Next phases- Finalise list of physical tests for UC2- Start with the implementation phase
2. Refinement phaseMain achievements – Use cases objectives and boundaries
Use case 3Use case 3 can be considered as an extension of UC2, aiming at demonstrating the benefits of local district management at LV grid level (including more district/neighbourhoods) and with the collaboration of the DSO and other actors of the grid to the optimization process. Also, the scenario will take into consideration the complex relationships between grid actors, the existing energy markets in the various countries and the related constraints, trying to define a framework in which actors can successfully coexist and the objectives of the project can be achieved (this framework includes the introduction of new actors and services). In particular use case 3 will attempt to overcome the issue related to the antagonistic objectives of final customers (that want to pay less) and DSO (that want to reduce losses and consumption). Due to the greater complexity of such a scenario, this will only rely on simulations to assess the effectiveness of such an approach. However, while the simulations will demonstrate the technical feasibility of such a mechanism, the economic viability will be analysed in parallel based on the results of the simulations (reduction in grid losses, increased renewable hosting capacity, increased reliability, etc.) and the market constraints of the proposed scenario.
Main progresses
- Objectives and boundaries of UC3 agreed with all partners (SMS, LAB & CEA in particular)- Data production & simulation activities refined- Advanced list of simulations to be carried out for UC3 to be discussed during GA and issued by LAB by
the 18th of September to be showed during the review meeting
Next phases- Finalise list of physical tests for UC2- Start with the implementation phase
2. Refinement phaseMain achievements – UC3: Profiles production
Standard profiles provided by UK DNO
Diversification of standard grid profiles
Production of projected profiles
Data includes, for 6 substations:
- Average daily load profiles of different categories of users (HH granularity) referred to typical weekday, Saturday & Sunday of 5 periods of the year (Autumn, Winter, Spring, Summer, High Summer);
- Annual consumption (kWh/y) of each individual user of the grid.
Each user of the grid will be characterised by an individual load profile.
The aggregation of the diversified load profiles will correspond to the profiles provided by DSO to keep consistency.
Standard grid profile will be affected by the penetration of smart grid technologies.
The production of the consequent projected profiles will rely on scenarios based on UK National grid’s studies.
Scenarios will be driven by project’s objective (at least one) and then iterated if required.
2. Refinement phaseMain achievements – UC3: Grid models production
Standard grid data provided by UK DNO Projected grid
Data includes, for the 6 substations:
- Details of cables (type and size)- Details of transformers- All other relevant features of the LV
grid
The grid layout of the projected grid will stay the same of the reference standard grid, but will include new district users and Link Boxes
Also, domestic users will be characterised with RES smart appliances.
Definition of projected grid will be based again on the scenarios based on UK National Grid’s studies.
Data will be translated into LV grid schematics and/or inserted into more
usable data collection templates.
Data will be used to create a model of the standard grid using
Grid-LAB D
Data will be used to create a model of the projected grid
using Grid-LAB D
2. Refinement phaseMain achievements – UC3: Simulations
Simulations Objective Software
1) Standard grid Show the current performance of the standard gridResults to be compared with projected and smart grid’s ones to assess the achievement of the objectives of the project.
Grid-Lab D
2) Projected grid (without local MAS optimization)
Show the performances of the projected grid (not yet smart)Results to be compared with optimised smart grid’s ones to assess the achievement of the objectives of the project.
Grid-Lab D + MAS (Default management)
3) Smart grid (with local MAS optimization)
Demonstrate the benefits of local optimization.Results to be compared with standards and projected grids’ ones to assess the achievement of the objectives of the projects
Grid-Lab D + MAS (Full optimization)
Additional Simulations
Objective Software
4) Specific simulations for Link Boxes
Analyse specific issues related to Link Boxes (e.g. transients). It is not based on the reference LV grid
Transient – analysis software
2. Refinement phaseMain achievements – Smart Grid Simulations
The MAS is used to optimise use of smart grid’s elements according to external varying conditions and objectives of the optimization.
• Projected profiles for each node
• Forecasted information (price of electricity, renewable generation, etc.)
• Available flexibility• Objective of the
optimization
MAS optimises use of the smart grid’s elements and provides updated profiles
Profiles are used into electrical simulation to check that grid statutory limits and physical constraints are always met at all nodes.
Every time additional information is provided the process starts again
Final profiles for each time step are recorded for assessment (T6.2)
Grid physical constraints are part of the optimization
2. Refinement phaseMain achievements – Smart Grid Simulations
Varying conditions
Price of electricity
Weather conditions
Period of the year
Day of the week
Initial status of batteries
Flexibility provided by domestic smart appliances
Others?
Optimization/Simulation’s objective
Default management
Maximise grid losses reduction
Maximise peak reduction
Maximise efficient use of storage systems (charging and discharging cycles)
Maximise final user’s energy savings or reduction in energy expenditure
Maximise time in which local portion of the grid can work “stand alone”
Maximise grid power quality
Combination of the previous
Others?
Varying conditions and specific objectives of the optimization/simulation
2. Refinement phaseMain achievements – Smart Grid Simulations
Outcomes of the simulations/KPIs Where Standard grid Projected grid Smart grid
Transformer losses All transformers
• • •
Cables losses All cables • • •
Amount of time in which voltage is not within statutory limits
All nodes • • •
Voltage level / statutory limit All nodes • • •
Overall demand & consumption All nodes • • •
Maximum demand during the day All nodes • • •
Peak/Base load All nodes • • •
Positive or negative flow All nodes • •
Amount of time in which portion of the grid could work stand-alone
Selected portions of the
grid
• •
Energy transferred between districts through Link Boxes
All districts • •
Amount of time in which Link Boxes are used
All districts • •
Etc…
Results of the simulations and quantitative indicators for project’s result assessment
3. Implementation phase
Initial activities
The implementation phase is about to start:
- Tasks related to implementation of physical tests will start after the end of the refinement phase (end of September 2015).
- Tasks related to the data production activities have already started with the obtainment of DSOs data for the UK grid. Data is in the process to be anonymised and made available to the consortium (18th September 2015). After that, the activities related to the diversification of standard profiles and the creation of projected profiles will start. Also the creation of a model of the standard grid in Grid Lab D will start.
4. PMs allocation
Partner SMS CEA ENGIE LAB TI CU R2M CCS TSSG
PMs 12 6 8 8.5 10 5.5 8 4.75 3T6.1 ENGIE All partners 44 7 4 5.5 7 7.5 5 3.5 3.5 1
T6.1.1 ENGIE All partners 13 5.5 1.5 1.5 1.25 1 0.5 1 0.5 0.25T6.1.1.1 SMS - 0.5 0.5T6.1.1.2 LAB - 0.25 0.25T6.1.1.3 ENGIE - 0.25 0.25
T6.1.1.4 SMS - 0.5 0.5
T6.1.1.5 SMS CEA, CU, LAB, GDF, TI 0.5 0.5
T6.1.1.6 SMSAll the other partners
6.25 2.5 1.5 0.5 0.25 0.5 0.75 0.25
T6.1.1.7
Relevant partners from
countries other than UK
- 0.5 0.25 0.25
T6.1.1.8 CU, SMSAll other partners, in particular GDF, LAB, CEA & R2M
1.25 0.5 0.5 0.25
T6.1.1.9 TI All the other partners
0.5 0.5
T6.1.1.10 ENGIE All the other partners
0.5 0.5
T6.1.1.11 SMS All the other partners
0
T6.1.1.12 CCS TSSG and all involved partners
0.5 0.5
T6.1.1.13 LAB All involved partners 0.5 0.5
T6.1.1.14 SMS All involved partners 0.5 0.5
T6.1.1.15 SMS All involved partners 0.5 0.5
Additional contributors
None - Previous ly SMS had 0.25 PMs
Task/Subtask code
Task/Subtask name
Refinement of use cases:- Definition of district management (technical and
business aspects)- Definition of Link Boxes
- Definition of simulations and required data- Other elements
Definition of further standard and smart grids configurations for other countries
Formalization of tests/tasks for the production of required data
Definition of physical tests to be carried out for Use case 1
Use cases refinement & implementationRefinement of use cases
Overview on Use cases 1,2,3Description of LABORELEC experimental facilities
Description of GDF experimental facilities
Task/sub-task
leaders
Definition of physical tests to be carried out for Use case 2
Definition of physical tests to be carried out for Use case 3 (if any)
Definition of tests to be carried for each of the three use cases to assess cyber security
Formalization of simulation campaign (MAS + electric grid)
Completion of refinement phase after second thematic Workshop with DSO and elicitation of scenarios
Further refinement of use cases scenarios
Definition of reference standard grid and provision of substation average load profiles
Initial Proposal of reference smart grid and scenarios for Use cases 1,2,3
4. PMs allocation
Partner SMS CEA ENGIE LAB TI CU R2M CCS TSSG
PMs 12 6 8 8.5 10 5.5 8 4.75 3T6.1.2 ENGIE All partners 31 1.5 2.5 4 5.75 6.5 4.5 2.5 3 0.75
a) Production of load profiles for reference standard grid
SMS, R2M
b) Development of smart grid scenarios SMS, R2Mc) Production of projected profiles SMS, R2Md) Production of additional data (weather data, price of electricity and other varying external conditions)
SMS, R2M
a) Production of standard and smart LV grid electrical models
LAB, CU 1.25
b) Adaptation of MAS system developed in WP3 to reference smart grid
CEA, TSSG 1.25 0.25
c) Coupling of electrical grid simulation models with MAS
CU,CEA 1.25 0.25
d) Simulation campaign All other partners 3.25
a) Test related to Use case 1 TI All involved partners 0.5 5
b) Test related to Use case 2 ENGIE All involved partners 3.5 0.5 1.5
c) Test related to Use case 3 SMS All involved partners
T6.1.2.4 CCS All involved partners 0.25 3 0.25
T6.2 SMS All partners 21.75 5 2 2.5 1.5 2.5 0.5 4.5 1.25 2T6.2.1 21.75 5 2 2.5 1.5 2.5 0.5 4.5 1.25 2
0.50.5
2
0.5
Additional contributors
40.5
0.25
0.5
None (previously LAB had 1PM thas has been moved to Simulation campaign)
6.5
9.25
15
Cyber security tests
Use cases assessmentSub-tasks to be defined
Task/Subtask code
Task/Subtask name
T6.1.2.3Physical
tests
Task/sub-task
leaders
CU
LAB
Implementation of use cases
T6.1.2.1Data
production
T6.1.2.2 Simulations
5. Communications
From now on (and probably until the end of the project) we will have bi-weekly WP6 conference calls (1 call for all WP6 activities).
• TI will report regarding physical tests for UC1• ENGIE will report regarding physical tests for UC2• SMS will report regarding data production activities (with support from CU) and
simulation activities (with support from LAB)• CCS will report regarding cyber security tests
Thank You