Oracle Projects - ProjectCosting Release 11iVolume 1 Student Guide
14786GC10
Production 1.0
October
MO-12818
Copyright © Oracle Corporation, 2000. All rights reserved.
This documentation contains proprietary information of Oracle Corporation. It is provided under a licenseagreement containing restrictions on use and disclosure and is also protected by copyright law. Reverseengineering of the software is prohibited. If this documentation is delivered to a U.S. Government Agency of theDepartment of Defense, then it is delivered with Restricted Rights and the following legend is applicable:
Restricted Rights Legend
Use, duplication or disclosure by the Government is subject to restrictions for commercial computer softwareand shall be deemed to be Restricted Rights software under Federal law, as set forth in subparagraph (c)(1)(ii)of DFARS 252.227-7013, Rights in Technical Data and Computer Software (October 1988).
This material or any portion of it may not be copied in any form or by any means without the express priorwritten permission of the Education Products group of Oracle Corporation. Any other copying is a violation ofcopyright law and may result in civil and/or criminal penalties.
If this documentation is delivered to a U.S. Government Agency not within the Department of Defense, then it isdelivered with “Restricted Rights,” as defined in FAR 52.227-14, Rights in Data-General, including Alternate III(June 1987).
The information in this document is subject to change without notice. If you find any problems in thedocumentation, please report them in writing to Worldwide Education Services, Oracle Corporation, 500 OracleParkway, Box SB-6, Redwood Shores, CA 94065. Oracle Corporation does not warrant that this document iserror-free.
Oracle and all references to Oracle Products are trademarks or registered trademarks of Oracle Corporation.
All other products or company names are used for identification purposes only, and may be trademarks of theirrespective owners.
Author
Barbara Fox
Technical Contributors and Reviewers
Peter Budelov
Michael Lee
Connie Kim
This book was published using:
Oracle Tutor
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsi
Table of Contents
Overview of Oracle Projects .................................................................................................1-1Overview of Oracle Projects................................................................................................1-2Objectives ............................................................................................................................1-3Purpose of Oracle Projects...................................................................................................1-4How to Use Oracle Projects.................................................................................................1-5Overview of Oracle Projects................................................................................................1-6Project Definition.................................................................................................................1-8Project Classes .....................................................................................................................1-9Using the Information Stored in Oracle Projects ................................................................1-10Central Repository...............................................................................................................1-13Project Costing.....................................................................................................................1-14Project Billing......................................................................................................................1-15Oracle Projects Features ......................................................................................................1-16Project-Tracking Tools ........................................................................................................1-18Work Breakdown Structure .................................................................................................1-20Project Budgets....................................................................................................................1-21Cost Collection and Calculation Capabilities .....................................................................1-23Types of Cost.......................................................................................................................1-24Methods of Cost Entry.........................................................................................................1-25Cost Controls .......................................................................................................................1-27Cost Calculations .................................................................................................................1-28Multiple-Organization Support............................................................................................1-29Multinational Support..........................................................................................................1-30Function Security.................................................................................................................1-31Function Security Example..................................................................................................1-32Project and Labor Cost Security ..........................................................................................1-33Project and Function Security..............................................................................................1-34Project Asset Creation .........................................................................................................1-35Capitalization of Project Costs ............................................................................................1-36Flexible Revenue Accrual and Invoicing Functions ...........................................................1-38Revenue Accrual and Billing...............................................................................................1-39Billing Controls ...................................................................................................................1-40Online Reporting and Hard Copy Reporting .......................................................................1-42Online Inquiry and Reporting ..............................................................................................1-43Sub Ledger Accounting .......................................................................................................1-44Full Adjustment Capabilities ...............................................................................................1-45Transferring Transactions ....................................................................................................1-47Other Cost Adjustments.......................................................................................................1-48Billing Transaction Adjustments .........................................................................................1-49Integration with Other Oracle and Non-Oracle Financial Applications..............................1-50Oracle Projects Interfaces ....................................................................................................1-51Overview of Activity Management Gateway ......................................................................1-56Integration with External Systems .......................................................................................1-57Overview of Oracle Project Connect ...................................................................................1-59Attachments .........................................................................................................................1-60Summary..............................................................................................................................1-61
Overview of Oracle Project Costing.....................................................................................2-1Overview of Oracle Project Costing ....................................................................................2-2Objectives ............................................................................................................................2-3Project Costing Flow ...........................................................................................................2-4Project Types .......................................................................................................................2-5
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsii
Project Cost Budgets............................................................................................................2-6Entering Project Expenditures .............................................................................................2-7Cost Processing....................................................................................................................2-8Capitalizing Project Costs....................................................................................................2-9Project Status Inquiry...........................................................................................................2-10Summary..............................................................................................................................2-11
Creating Projects ...................................................................................................................3-1Creating Projects..................................................................................................................3-2Objectives ............................................................................................................................3-3Agenda.................................................................................................................................3-4Section 1 Overview of Project Concepts .............................................................................3-5Project Definitions ...............................................................................................................3-6Project Classes .....................................................................................................................3-7Project Types .......................................................................................................................3-8Project Classes and Project Types .......................................................................................3-9Section 2 Creating and Configuring Projects.......................................................................3-10Creating and Configuring Projects ......................................................................................3-11Project Templates and Quick Entry .....................................................................................3-12Required Project Data..........................................................................................................3-13Optional Project Data ..........................................................................................................3-14Additional Project Data .......................................................................................................3-15Project Status Controls ........................................................................................................3-16How to Create a Project Status ............................................................................................3-18How to Create a New Project ..............................................................................................3-19Key Members.......................................................................................................................3-22Classification Information ...................................................................................................3-23Work Breakdown Structure .................................................................................................3-24Processing by Task Levels...................................................................................................3-25Basic Task Information........................................................................................................3-26Task Numbering and Naming..............................................................................................3-27Basic Task Information........................................................................................................3-28Changing Default Task Information ....................................................................................3-29How to Create a Task ..........................................................................................................3-30How to Enter Task Details...................................................................................................3-31Finding Tasks ......................................................................................................................3-32Transaction Controls............................................................................................................3-33Logic of Transaction Controls .............................................................................................3-37Organization Overrides........................................................................................................3-38Burden Multipliers...............................................................................................................3-39Review of Project Definition ...............................................................................................3-40Reports for Project and Task Setup .....................................................................................3-41Section 3 Maintaining Projects and Tasks ...........................................................................3-42Maintaining Projects and Tasks...........................................................................................3-43Changing the Project Information........................................................................................3-44Changing the Project Organization......................................................................................3-47Benefits of Reorganizations.................................................................................................3-50Flexible Organization Change Methods ..............................................................................3-51Mass Update ........................................................................................................................3-52Changing the Task Information ...........................................................................................3-53Changing the WBS ..............................................................................................................3-55Changing Project Statuses; Integration with Oracle Workflow..........................................3-56Business Benefits of Using Workflow.................................................................................3-57Summary..............................................................................................................................3-58Practice 3-1 Overview .........................................................................................................3-59
Cost Budgets...........................................................................................................................4-1
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsiii
Cost Budgets........................................................................................................................4-2Objectives ............................................................................................................................4-3Agenda.................................................................................................................................4-4Section 1 Overview of Budget Features ..............................................................................4-5Overview of Budget Features ..............................................................................................4-6Budget Structure ..................................................................................................................4-7Budget Types and Versions .................................................................................................4-9Budget Versions...................................................................................................................4-10Budget Entry Method (BEM) ..............................................................................................4-11Levels of Budgets ................................................................................................................4-14Selecting Costs.....................................................................................................................4-15Time-Phased Budgets ..........................................................................................................4-16Resource List .......................................................................................................................4-17Resource Groups..................................................................................................................4-19Resource List .......................................................................................................................4-21Budget Security ...................................................................................................................4-23Section 2 Entering and Baselining Budgets........................................................................4-24Entering Budgets .................................................................................................................4-25Creating Budgets .................................................................................................................4-26Budget Amounts ..................................................................................................................4-27Task-Level Budget...............................................................................................................4-28Budget Lines........................................................................................................................4-29Budgeting by Quantity and Units ........................................................................................4-30Lines Overflow Region........................................................................................................4-31Baselining Budgets ..............................................................................................................4-32Submitting Budgets .............................................................................................................4-33Baselining Budgets ..............................................................................................................4-34Baselining with Workflow...................................................................................................4-35Standard Baseline Requirements .........................................................................................4-36Section 3 Maintaining Budgets............................................................................................4-37Maintaining Budgets............................................................................................................4-38Budget Processing Flow ......................................................................................................4-39Budget Versions...................................................................................................................4-40Revising Baselined Budgets ................................................................................................4-41Revising Original Budgets...................................................................................................4-42Revising Draft Budgets........................................................................................................4-43Summary..............................................................................................................................4-44Practice 4-1 Overview .........................................................................................................4-45
Transactions ...........................................................................................................................5-1Transactions.........................................................................................................................5-2Objectives ............................................................................................................................5-3Agenda.................................................................................................................................5-4Section 1 Overview of Transactions ...................................................................................5-5Overview of Transactions....................................................................................................5-6Actuals and Commitments...................................................................................................5-7Transaction Details ..............................................................................................................5-9Summary of Expenditure Definition....................................................................................5-11Methods of Transaction Entry .............................................................................................5-13Terminology of Transactions...............................................................................................5-14Charge Control Validation...................................................................................................5-15Section 2 Preapproved Expenditure Batch Entry................................................................5-16Preapproved Expenditure Batch Entry.................................................................................5-17Typical Preapproved Expenditure Batch Flow ....................................................................5-18Preapproved Batches ...........................................................................................................5-19Entering Preapproved Batches.............................................................................................5-20Entering Expenditures .........................................................................................................5-22
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsiv
Entering Preapproved Usages..............................................................................................5-23Entering Perapproved Usages..............................................................................................5-24Copying Preapproved Timecards.........................................................................................5-25Resolving Problems in Expenditure Entry...........................................................................5-26Preapproved Expenditure Entry Audit Report .....................................................................5-27Submitting Preapproved Expenditures ................................................................................5-28Purpose of Releasing Preapproved Batches.........................................................................5-29Purpose of Reversing Preapproved Batches ........................................................................5-31Purpose of Correcting Preapproved Batches .......................................................................5-32Preapproved Expenditure Approvals ...................................................................................5-33Submitting and Releasing Batches.......................................................................................5-34Expenditure Batch Status Report .........................................................................................5-35Review of Preapproved Expenditure Entry .........................................................................5-36Section 3 Project Allocations and AutoAllocations.............................................................5-37Project Allocations Overview..............................................................................................5-38Project Allocations Business Need ......................................................................................5-39Project Allocation Amounts.................................................................................................5-40Project Allocation Definitions .............................................................................................5-41Project Allocation Example .................................................................................................5-43Basis Method .......................................................................................................................5-44Basis Method - Spread Evenly.............................................................................................5-45Target % and Spread Evenly ...............................................................................................5-46Prorate..................................................................................................................................5-47Target % and Prorate ...........................................................................................................5-48Allocation Rule Definition...................................................................................................5-49Allocation Rule Sources ......................................................................................................5-50Allocation Rule Targets .......................................................................................................5-51Allocation Rule Definition...................................................................................................5-52Allocation Rule Offset .........................................................................................................5-53Allocation Rule Sources ......................................................................................................5-54Source Resources.................................................................................................................5-55Allocation Rule Targets .......................................................................................................5-56Process an Allocation Rule ..................................................................................................5-57Allocation Run Review........................................................................................................5-60Allocation Exceptions..........................................................................................................5-61Missing Amounts.................................................................................................................5-62Basis Details ........................................................................................................................5-63Source Details......................................................................................................................5-64Transactions.........................................................................................................................5-65Copying Rules .....................................................................................................................5-66AutoAllocations...................................................................................................................5-67AutoAllocations Overview ..................................................................................................5-68AutoAllocations Business Need ..........................................................................................5-69AutoAllocations Example....................................................................................................5-70AutoAllocations Setup.........................................................................................................5-71AutoAllocation Types..........................................................................................................5-72AutoAllocations Processes ..................................................................................................5-73AutoAllocation Set Definition .............................................................................................5-74AutoAllocation Set Submission...........................................................................................5-75View AutoAllocation Statuses.............................................................................................5-76View Step Statuses ..............................................................................................................5-77AutoAllocation Rollback Feature ........................................................................................5-78Practice 5-1 Overview .........................................................................................................5-79Section 4 Self-Service Time ................................................................................................5-80Self-Service Time ................................................................................................................5-81Business Flow......................................................................................................................5-82
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsv
On-Line Entry......................................................................................................................5-83Alias Setup...........................................................................................................................5-84Disconnected Entry..............................................................................................................5-85Project and Task View.........................................................................................................5-86Section 5 Expense Reports ..................................................................................................5-87Creating Project-Related Expense Reports .........................................................................5-88Entering Project-Related Expense Reports in Oracle Projects ............................................5-89Entering Project-Related Expense Reports in Self-Service Expenses .................................5-90Self-Service Expenses Business Flow .................................................................................5-91Entering Project-Related Expense Reports in Self-Service Expense...................................5-92Self-Service Expense Disconnected Expense Report .........................................................5-93Entering Project-Related Expense Reports in Oracle Payables ...........................................5-94Integrating with Oracle Manufacturing ...............................................................................5-95Integrating with Oracle Inventory........................................................................................5-96Section 6 Project-Related Transactions in PO and AP .......................................................5-97Project-Related Transactions in PO and AP .......................................................................5-98Tracking Requisitions and Purchase Orders .......................................................................5-99Commitments.......................................................................................................................5-100Entering Project-Related Transactions in PO and AP..........................................................5-101Default Project Information .................................................................................................5-103Entering Project-Related Requisitions.................................................................................5-104Entering Project-Related Purchase Orders..........................................................................5-105Entering Project-Related Supplier Invoices........................................................................5-106Interfacing Supplier Invoices to Oracle Projects ................................................................5-107Section 7 Multi-Currency Transactions ...............................................................................5-108Multicurrency Transaction Overview..................................................................................5-109Multicurrency Transaction Business Need ..........................................................................5-110Multicurrency Transaction Features ....................................................................................5-111Multicurrency Transaction Definitions................................................................................5-112Multicurrency Transaction Currency Conversion................................................................5-115Multicurrency Transaction Example....................................................................................5-116Implementation Options ......................................................................................................5-117Project Definition.................................................................................................................5-118Task Details .........................................................................................................................5-119Expenditure Entry................................................................................................................5-120Multicurrency Expense Reports...........................................................................................5-121Multicurrency Expenditures ................................................................................................5-122Transaction Import...............................................................................................................5-123Expenditure Inquiry .............................................................................................................5-126Cost Distribution Lines........................................................................................................5-127Practice 5-2 Overview .........................................................................................................5-128Section 8 Transaction Import...............................................................................................5-129Transaction Import...............................................................................................................5-130Basic Business Requirements ..............................................................................................5-131Transaction Import Functions..............................................................................................5-132Transaction Import Flow .....................................................................................................5-133Transaction Source ..............................................................................................................5-134Costed Transactions.............................................................................................................5-135Accounted Transactions.......................................................................................................5-136Burdening Transactions .......................................................................................................5-137Foreign Currency Transactions............................................................................................5-138Descriptive Flexfield Option ...............................................................................................5-139Running Transaction Import ................................................................................................5-140Viewing Rejected Transactions ...........................................................................................5-141Correcting Rejected Rows ...................................................................................................5-142Review Transactions Window.............................................................................................5-143
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsvi
Auditing Imported Transactions ..........................................................................................5-144Viewing Imported Transactions...........................................................................................5-145Section 9 Review of Project Expenditures...........................................................................5-146Summary Flow.....................................................................................................................5-147Reviewing Project Expenditures..........................................................................................5-148Inquiry - Project Mode.........................................................................................................5-149Inquiry - All Mode...............................................................................................................5-150Reporting Project Expenditures ...........................................................................................5-151Summary..............................................................................................................................5-152Practice 5-3 Overview .........................................................................................................5-153Practice 5-4 Overview .........................................................................................................5-154
Costing ....................................................................................................................................6-1Costing.................................................................................................................................6-2Objectives ............................................................................................................................6-3Agenda.................................................................................................................................6-4Section 1 Overview of Costing............................................................................................6-5Overview of Costing............................................................................................................6-6Cost Distribution..................................................................................................................6-7Cost Concepts ......................................................................................................................6-8Raw Cost Calculations.........................................................................................................6-9Cost Calculations .................................................................................................................6-10Burdened Cost Calculations.................................................................................................6-11Burden Cost Terminology ...................................................................................................6-12Burden Cost Accounting......................................................................................................6-14Burden Schedules ................................................................................................................6-15Burden Cost Processing.......................................................................................................6-16Assigning Multipliers to Organizations ...............................................................................6-17Account Distribution ...........................................................................................................6-18AutoAccounting...................................................................................................................6-19Accounting Dates in Oracle Projects ...................................................................................6-20Summary of Accounting Transactions.................................................................................6-21Overtime Calculation Methods ............................................................................................6-22Labor Extensions .................................................................................................................6-23Section 2 Cost Plus Processing............................................................................................6-24Cost Plus Processing............................................................................................................6-25Burden Schedule Override...................................................................................................6-26Cost Plus Features................................................................................................................6-29Burden Cost Buildup ...........................................................................................................6-30Firm Rates and Provisional Rates ........................................................................................6-31Applying Actuals to Provisionals ........................................................................................6-32Cost Plus Reporting .............................................................................................................6-33Viewing Burden Costs .........................................................................................................6-34Interfacing Costs..................................................................................................................6-35Cost Processing....................................................................................................................6-36Interfacing Costs..................................................................................................................6-37Interfacing Costs to GL........................................................................................................6-38Cost Flow for Labor and Usages .........................................................................................6-40Interfacing Expense Reports to AP......................................................................................6-41Applying Advances or Holds to Expense Reports..............................................................6-42Cost Flow for Expense Reports ...........................................................................................6-43Expense Reports Flow in AP and GL..................................................................................6-44Interface Streamline Processing...........................................................................................6-45Submitting Costing Processes..............................................................................................6-46Viewing Expenditure Costs .................................................................................................6-47Expenditure Inquiry Drilldown............................................................................................6-48Folder Tool ..........................................................................................................................6-49
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsvii
Viewing Cost Distribution Details.......................................................................................6-50Interface Status and Interfacing ...........................................................................................6-51Error Identification and Diagnosis.......................................................................................6-52Summary..............................................................................................................................6-54Practice 6-1 Overview .........................................................................................................6-56Practice 6-2 Overview .........................................................................................................6-57
Adjustments ...........................................................................................................................7-1Adjustments .........................................................................................................................7-2Objectives ............................................................................................................................7-3Agenda.................................................................................................................................7-4Section 1 Types of Adjustments ..........................................................................................7-5Types of Adjustments ..........................................................................................................7-6Types of Adjustments in Oracle Projects............................................................................7-7Supplier Invoice Adjustments in Oracle Projects ...............................................................7-9Correcting Approved Expenditure Items ............................................................................7-11Correcting Approved Labor/Usage or Expense Report Items ............................................7-12Correcting Supplier Invoices in Oracle Payables................................................................7-13Transferring Expenditure Items ...........................................................................................7-14Audit of Transferred Items ..................................................................................................7-16Splitting Expenditure Items .................................................................................................7-17Recalculating Raw Cost.......................................................................................................7-18Recalculating Burden Cost ..................................................................................................7-19Multicurrency Transaction Adjustments..............................................................................7-20Adjusting Project Expenditures ...........................................................................................7-22Mass Adjustment of Expenditures .......................................................................................7-24Splitting Expenditure Items .................................................................................................7-25Splitting Expenditure Items Results.....................................................................................7-26Section 2 Adjustment Processing........................................................................................7-27Accounting Transaction Adjustment ...................................................................................7-28Distributing Costs for Adjustments .....................................................................................7-29Interfacing Adjustments.......................................................................................................7-30Summary of Adjustment Flow.............................................................................................7-31Audit Trail of Adjustments ..................................................................................................7-32Summary..............................................................................................................................7-33Practice 7-1 Overview .........................................................................................................7-34
Analysis and Reporting .........................................................................................................8-1Analysis and Reporting........................................................................................................8-2Objectives ............................................................................................................................8-3Agenda.................................................................................................................................8-4Section 1 Overview of Analysis and Reporting...................................................................8-5Overview of Analysis and Reporting...................................................................................8-6Oracle Projects Strategy for Analysis and Reporting .........................................................8-8Section 2 Definition of Project Status Inquiry ....................................................................8-10Definition of Project Status Inquiry.....................................................................................8-11Project Summary Amounts..................................................................................................8-12Percent Complete Entry .......................................................................................................8-14Section 3 Functionality of Project Status Inquiry (PSI)......................................................8-16PSI Drilldown Capabilities ..................................................................................................8-17Project Status Columns........................................................................................................8-18Online PSI............................................................................................................................8-20Project Status .......................................................................................................................8-21Task Status...........................................................................................................................8-22Resource Status....................................................................................................................8-23Resource List .......................................................................................................................8-24Commitments.......................................................................................................................8-25
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsviii
Actuals .................................................................................................................................8-26Budget Types .......................................................................................................................8-27Project Status Reports..........................................................................................................8-28Creating Custom Reports Using Views ...............................................................................8-29Section 4 Maintaining Project Summary Amounts..............................................................8-31Updating Project Summary Amounts ..................................................................................8-32Resource Mapping ...............................................................................................................8-34Precedence-Based Mapping.................................................................................................8-35Unclassified Resources ........................................................................................................8-36Summary..............................................................................................................................8-37Practice 8-1 Overview .........................................................................................................8-38
Capital Projects......................................................................................................................9-1Capital Projects....................................................................................................................9-2Objectives ............................................................................................................................9-3Agenda.................................................................................................................................9-4Section 1 Overview of Capital Projects ...............................................................................9-5Overview of Capital Projects...............................................................................................9-6Purpose of Capital Projects..................................................................................................9-7Construction In Process (CIP) .............................................................................................9-8Accounting Flow .................................................................................................................9-9Oracle Systems Integration..................................................................................................9-10Capitalizing Project Costs....................................................................................................9-11Functional Overview of Capital Projects............................................................................9-12Section 2 Creating a Capital Project ....................................................................................9-13Creating a Capital Project ....................................................................................................9-14Capitalization Controls ........................................................................................................9-16Transaction Controls............................................................................................................9-17Capital Project Types...........................................................................................................9-18CIP Cost Summarization .....................................................................................................9-19CIP Grouping Methods........................................................................................................9-20Capital Project Options........................................................................................................9-21Grouping Levels ..................................................................................................................9-22Grouping at Project Level....................................................................................................9-23Grouping at Top Task Level ................................................................................................9-24Grouping at Lowest Task Level...........................................................................................9-25Grouping at Mixed Task Level ............................................................................................9-26Grouping Level Types .........................................................................................................9-27Capital Project Example ......................................................................................................9-29Asset Assignment Combinations .........................................................................................9-34Section 3 Defining Assets....................................................................................................9-35Defining Assets....................................................................................................................9-36Asset Definition...................................................................................................................9-38Defining Multiple Assets .....................................................................................................9-39Capital Projects Window .....................................................................................................9-40Section 4 Placing a CIP Asset in Service.............................................................................9-41Placing a CIP Asset in Service ............................................................................................9-42Assets Window....................................................................................................................9-44Creating Asset Lines............................................................................................................9-45Additional Fields for Asset Lines ........................................................................................9-46Matching Strategy for Asset Lines ......................................................................................9-47Group Supplier Invoices ......................................................................................................9-48Non-Grouped Supplier Invoices ..........................................................................................9-49Override Asset Assignment .................................................................................................9-50Reviewing and Assigning Asset Lines ................................................................................9-51Interfacing Asset Lines ........................................................................................................9-52Running the Interface Assets Process ..................................................................................9-53
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsix
Section 5 Adjusting Asset Lines ..........................................................................................9-54Adjustments .........................................................................................................................9-55Post-capitalization Adjustments...........................................................................................9-56Amortize Adjustments .........................................................................................................9-57Reversing Capitalization......................................................................................................9-58Abandoning a CIP Asset......................................................................................................9-59Section 6 Accounting for CIP and Capitalized Asset Costs.................................................9-60Accounting for CIP Costs ....................................................................................................9-61Accounting Example ...........................................................................................................9-62Summary..............................................................................................................................9-67Practice 9-1 Overview .........................................................................................................9-68
Basic Project Costing Setup ..................................................................................................10-1Basic Project Costing Setup.................................................................................................10-2Objectives ............................................................................................................................10-3Project Templates ................................................................................................................10-4Budget Types .......................................................................................................................10-5Resources.............................................................................................................................10-6Cost Plus Processing............................................................................................................10-7Burden Schedules ................................................................................................................10-8Project Status Columns........................................................................................................10-9Project Status Inquiry...........................................................................................................10-10Project Types .......................................................................................................................10-12AutoAccounting and Account Generator.............................................................................10-13Client Extensions .................................................................................................................10-14Summary..............................................................................................................................10-15
Summary of Project Costing.................................................................................................11-1Summary of Project Costing................................................................................................11-2Project Costing Flow ...........................................................................................................11-3Summary..............................................................................................................................11-4
Appendix A: Practices and Solutions...................................................................................12-1Appendix A Practices and Solutions....................................................................................12-2Practice 3-1: Indirect Projects..............................................................................................12-3Practice 4-1: Cost Budgets...................................................................................................12-13Practice 5-1: Allocations......................................................................................................12-17Practice 5-2: Expenditures ...................................................................................................12-21Practice 5-3: Supplier Invoices ............................................................................................12-27Practice 6-1: Burden Schedule Overrides ............................................................................12-31Practice 6-2: Cost Processes ................................................................................................12-33Practice 7-1: Modifying Expenditures .................................................................................12-40Practice 8-1: Project Status Inquiry .....................................................................................12-45Practice 9-1: Capital Projects...............................................................................................12-51
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxi
Preface
Profile
Before You Begin This Course
Before you begin this course, you should have the following qualifications:
• Thorough knowledge of project accounting.
• Working experience with tracking project costs.
Prerequisites
• There are no prerequisites for this course.
How This Course Is Organized
Oracle Projects – Project Costing is an instructor-led course featuring lectureand hands-on exercises. Online demonstrations and written practice sessionsreinforce the concepts and skills introduced.
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxii
Related Publications
Oracle Publications
Title Part Number
Oracle Projects User’s Guide A58474-01
Additional Publications
• System release bulletins
• Installation and user’s guides
• read.me files
• Oracle Magazine
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxiii
Typographic Conventions
Typographic Conventions in Text
Convention Element ExampleBold italic Glossary term (if
there is a glossary)The algorithm inserts the new key.
Caps andlowercase
Buttons,check boxes,triggers,windows
Click the Executable button.Select the Can’t Delete Card check box.Assign a When-Validate-Item trigger to theORD block.Open the Master Schedule window.
Courier new,case sensitive(default islowercase)
Code output,directory names,filenames,passwords,pathnames,URLs,user input,usernames
Code output: debug.set (‘I”, 300);Directory: bin (DOS), $FMHOME (UNIX)Filename: Locate the init.ora file.Password: User tiger as your password.Pathname: Open c:\my_docs\projectsURL: Go to http://www.oracle.comUser input: Enter 300Username: Log on as scott
Initial cap Graphics labels(unless the term is aproper noun)
Customer address (but Oracle Payables)
Italic Emphasized wordsand phrases,titles of books andcourses,variables
Do not save changes to the database.For further information, see Oracle7 ServerSQL Language Reference Manual.Enter [email protected],where user_id is the name of the user.
Quotationmarks
Interface elementswith long namesthat have onlyinitial caps;lesson and chaptertitles in cross-references
Select “Include a reusable module component”and click Finish.
This subject is covered in Unit II, Lesson 3,“Working with Objects.”
Uppercase SQL columnnames, commands,functions, schemas,table names
Use the SELECT command to viewinformation stored in the LAST_NAMEcolumn of the EMP table.
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxiv
Convention Element ExampleArrow Menu paths Select File—> Save.Brackets Key names Press [Enter].
Commas Key sequences Press and release keys one at a time:[Alternate], [F], [D]
Plus signs Key combinations Press and hold these keys simultaneously:[Ctrl]+[Alt]+[Del]
Typographic Conventions in Code
Convention Element ExampleCaps andlowercase
Oracle Formstriggers
When-Validate-Item
Lowercase Column names,table names
SELECT last_nameFROM s_emp;
Passwords DROP USER scottIDENTIFIED BY tiger;
PL/SQL objects OG_ACTIVATE_LAYER(OG_GET_LAYER
(‘prod_pie_layer’))
Lowercaseitalic
Syntax variables CREATE ROLE role
Uppercase SQL commands andfunctions
SELECT useridFROM emp;
Typographic Conventions in Navigation Paths
This course uses simplified navigation paths, such as the following example, todirect you through Oracle Applications.
(N) Invoice > Entry > Invoice Batches Summary (M) Query > Find (B) Approve
This simplified path translates to the following:
1. (N) From the Navigator window, select Invoice > Entry > Invoice BatchesSummary.
2. (M) From the menu, select Query > Find.
3. (B) Click the Approve button.
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxv
Notations :
(N) = Navigator
(M) = Menu
(T) = Tab
(I) = Icon
(H) = Hyperlink
(B) = Button
Typographical Conventions in Help System Paths
This course uses a “navigation path” convention to represent actions you performto find pertinent information in the Oracle Applications Help System.
The following help navigation path, for example—
(Help) General Ledger > Journals > Enter Journals
—represents the following sequence of actions:
1. In the navigation frame of the help system window, expand the GeneralLedger entry.
2. Under the General Ledger entry, expand Journals.
3. Under Journals, select Enter Journals.
4. Review the Enter Journals topic that appears in the document frame of thehelp system window.
Getting Help
Oracle Applications provides you with a complete online help facility.
Whenever you need assistance, simply choose an item from the Help menu topinpoint the type of information you want.
Copyright © Oracle Corporation, 2000. All rights reserved.
Oracle Projects - Project Costing Release 11i Table of Contentsxvi
To display help for a current window:
1. Choose Window Help from the Help menu, click the Help button on thetoolbar, or hold down the Control key and type 'h'.
A web browser window appears, containing search and navigation frames onthe left, and a frame that displays help documents on the right.
The document frame provides information on the window containing thecursor. The navigation frame displays the top-level topics for yourresponsibility, arranged in a tree control.
2. If the document frame contains a list of topics associated with the window,click on a topic of interest to display more detailed information.
3. You can navigate to other topics of interest in the help system, or chooseClose from your web browser's File menu to close help.
Searching for Help
You can perform a search to find the Oracle Applications help information youwant. Simply enter your query in the text field located in the top-left frame of thebrowser window when viewing help, then click the adjacent Find button.
A list of titles, ranked by relevance and linked to the documents in question, isreturned from your search in the right-hand document frame. Click on whichevertitle seems to best answer your needs to display the complete document in thisframe. If the document doesn't fully answer your questions, use your browser'sBack button to return to the list of titles and try another.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 1
Overview of Oracle ProjectsChapter 1
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 2
Overview of Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Oracle ProjectsOverview of Oracle Projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 3
Objectives
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ObjectivesObjectives
After completing this lesson, you should be able todo the following:• Describe the fundamental concepts of Oracle
Projects• Discuss common business requirements• Describe Oracle Projects features
After completing this lesson, you should be able todo the following:• Describe the fundamental concepts of Oracle
Projects• Discuss common business requirements• Describe Oracle Projects features
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 4
Purpose of Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Purpose of Oracle ProjectsPurpose of Oracle Projects
The purpose of Oracle Projects is to track and controlwork (or activity) on a project.• You track activity on a project by comparing actual
activity with expected activity.• Record actual activity as actuals (transactions).• Record expected activity in a budget.
The purpose of Oracle Projects is to track and controlwork (or activity) on a project.• You track activity on a project by comparing actual
activity with expected activity.• Record actual activity as actuals (transactions).• Record expected activity in a budget.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 5
How to Use Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Use Oracle ProjectsHow to Use Oracle Projects
The following is a typical process flow using Oracleprojects:• Create a project• Enter a budget• Collect actuals (transactions)• Process cost, revenue, and invoice transactions• Capitalize asset costs• Perform analysis/reporting
The following is a typical process flow using Oracleprojects:• Create a project• Enter a budget• Collect actuals (transactions)• Process cost, revenue, and invoice transactions• Capitalize asset costs• Perform analysis/reporting
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 6
Overview of Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Oracle ProjectsOverview of Oracle Projects
Performserver andclient sideinstallation
Implement Oracle ProjectsSet up project types, expense types,project PA periods, AutoAccountingrules, and so on.
Closeproject
Use Project• Record actuals against project• Release and approve transactions• Cost transactions (that is,
determine dollar amount andproper account)
• Summarize• Identify and review variances• Process revenue/invoice
transactions• Perform analysis/reporting
Createproject
Maintainproject
Reviseproject
One Time
Many Times
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 7
Overview of Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Oracle ProjectsOverview of Oracle Projects
You define a project and work breakdown structure(WBS) to record work and process transactions asyou and your company require. Project definitionscan be simple or complex, depending on yourrequirements.Project definitions can include:
You define a project and work breakdown structure(WBS) to record work and process transactions asyou and your company require. Project definitionscan be simple or complex, depending on yourrequirements.Project definitions can include:
• Classification information• Work breakdown
structures• Charge controls• Costing overrides
• Revenue and billinginformation
• Single- or multiple-organization usage
• Function or project securitycontrols
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 8
Project Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project DefinitionProject Definition
A project is a unit of work made up of one or moretasks. For example, you can use projects to track:A project is a unit of work made up of one or moretasks. For example, you can use projects to track:
Indirect Work• Indirect projects• Research andDevelopment
Product/AssetDevelopment
• Cost of product/assetdevelopment
• Cost capitalization• Capital projects
Services• Customer billing• Professionalservices consulting
• Construction/engineering
• Governmentcontractors
• Contract projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 9
Project Classes
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project ClassesProject Classes
You can use three predefined project classes to trackthe following types of information:• Indirect projects: Track overhead activities and
costs.• Capital projects: Track product/asset development
activities and costs. Costs are capitalized as oneor more assets.
• Contract projects: Track activities, cost, revenue,and billing for work performed for and reimbursedby an internal or external customer.
You can use three predefined project classes to trackthe following types of information:• Indirect projects: Track overhead activities and
costs.• Capital projects: Track product/asset development
activities and costs. Costs are capitalized as oneor more assets.
• Contract projects: Track activities, cost, revenue,and billing for work performed for and reimbursedby an internal or external customer.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 10
Using the Information Stored in Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Using the Information Storedin Oracle Projects
Using the Information Storedin Oracle Projects
You can answer questions related to all project areas:• Costs
– What are the actual costs incurred?(labor, expenses, materials, and usages)
– What are the outstanding committed costs?– What are the forecasted costs over future time
periods?• Labor utilization
– What types of skills are used on projects?– What percent of employees are billable?– Can labor costs be recovered?
You can answer questions related to all project areas:• Costs
– What are the actual costs incurred?(labor, expenses, materials, and usages)
– What are the outstanding committed costs?– What are the forecasted costs over future time
periods?• Labor utilization
– What types of skills are used on projects?– What percent of employees are billable?– Can labor costs be recovered?
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 11
Using the Information Stored in Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Using the Information Storedin Oracle Projects
Using the Information Storedin Oracle Projects
Continued examples:• Funding
– How have we allocated customer funding toprojects?
– How much revenue have we accrued to date?• Customer invoice
– Did we invoice for the latest completed deliverable?
– What is the total project billing?
Continued examples:• Funding
– How have we allocated customer funding toprojects?
– How much revenue have we accrued to date?• Customer invoice
– Did we invoice for the latest completed deliverable?
– What is the total project billing?
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 12
Using the Information Stored in Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Using the Information Storedin Oracle Projects
Using the Information Storedin Oracle Projects
Continued examples:• Asset utilization
– Are the costs of nonlabor company assetsrecovered with current bill rates or markups?
– Are all costs allocated from service centers toserved organizations?
Continued examples:• Asset utilization
– Are the costs of nonlabor company assetsrecovered with current bill rates or markups?
– Are all costs allocated from service centers toserved organizations?
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 13
Central Repository
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Central RepositoryCentral Repository
Oracle Projects is a central repository that provides acompletely integrated cost management solution forall the projects and activities across your enterprise.It has two main components:• Project Costing• Project Billing
Oracle Projects is a central repository that provides aOracle Projects is a central repository that provides acompletely integrated cost management solution forcompletely integrated cost management solution forall the projects and activities across your enterprise.all the projects and activities across your enterprise.It has two main components:It has two main components:•• Project CostingProject Costing•• Project BillingProject Billing
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 14
Project Costing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project CostingProject Costing
Project Costing provides:• A central cost collections system• A bridge between project management and
financial accounting• A mechanism for providing timely, detailed cost
information to project managers and financialaccountants
Project Costing provides:•• A central cost collections systemA central cost collections system•• A bridge between project management andA bridge between project management and
financial accountingfinancial accounting•• A mechanism for providing timely, detailed costA mechanism for providing timely, detailed cost
information to project managers and financialinformation to project managers and financialaccountantsaccountants
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 15
Project Billing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project BillingProject Billing
Project Billing provides:• Simplified customer invoicing• Flexible revenue accrual• Profitability and performance measurements• Integration with Oracle Receivables
Project Billing provides:• Simplified customer invoicing• Flexible revenue accrual• Profitability and performance measurements• Integration with Oracle Receivables
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 16
Oracle Projects Features
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects FeaturesOracle Projects Features
Defineprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 17
Oracle Projects Features
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects FeaturesOracle Projects Features
Oracle Projects has many features that addresscommon business needs:• Project-tracking tools• Cost collection and calculation capabilities• Allocations and allocation sets features• Project asset creation functions• Flexible revenue accrual and invoicing functions• Online reporting and hard-copy reporting• Full adjustment capabilities• Multi-national, multi-organization features• Oracle and non-Oracle applications integration
Oracle Projects has many features that addresscommon business needs:• Project-tracking tools• Cost collection and calculation capabilities• Allocations and allocation sets features• Project asset creation functions• Flexible revenue accrual and invoicing functions• Online reporting and hard-copy reporting• Full adjustment capabilities• Multi-national, multi-organization features• Oracle and non-Oracle applications integration
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 18
Project-Tracking Tools
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project-Tracking ToolsProject-Tracking Tools
DefineprojectsDefineDefine
projectsprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 19
Project-Tracking Tools
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project-Tracking ToolsProject-Tracking Tools
Project managers use Oracle Projects to trackdetailed costs, manage within budget, and stay onschedule while achieving project objectives.
Project managers use Oracle Projects to trackdetailed costs, manage within budget, and stay onschedule while achieving project objectives.
Transaction10 hours of labor onMonday, May 13, 1996 onproject XYZ, task 1
Company-Cost Center—Account Amount
01-100-5153 $220
Financial analysts require the details to manage theoverall business. Oracle Projects translates projectdetails into financial transactions so the financialanalysts have the details they require.
Financial analysts require the details to manage theoverall business. Oracle Projects translates projectdetails into financial transactions so the financialanalysts have the details they require.
Project Status InquiryOracle Projects uses Project Status Inquiry (PSI), a powerful online tool that allowsdifferent users to view and analyze data in the way that is most meaningful to their jobrole.For example, project managers may want to see the lowest level cost detail, andfinancial managers may want to display just the cost roll-up.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 20
Work Breakdown Structure
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Work Breakdown StructureWork Breakdown Structure
Your project, which consists of one or more tasks,can be as simple or detailed as you want it to be.You can define an unlimited hierarchy of tasks,called a work breakdown structure (WBS), toorganize and monitor project activities.
Your project, which consists of one or more tasks,can be as simple or detailed as you want it to be.You can define an unlimited hierarchy of tasks,called a work breakdown structure (WBS), toorganize and monitor project activities.
Task 2.1 Task 2.2
Task 2Task 2
Task 1.1 Task 1.2
Task 1Task 1
Project
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 21
Project Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project BudgetsProject Budgets
Oracle Projects provides you with many budgetingfeatures. You can:• Define multiple cost and revenue budgets for your
project• Copy budget versions to simplify the budget
setup process• Copy actuals• Define time-phased budgeting
Oracle Projects provides you with many budgetingfeatures. You can:• Define multiple cost and revenue budgets for your
project• Copy budget versions to simplify the budget
setup process• Copy actuals• Define time-phased budgeting
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 22
Project Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project BudgetsProject Budgets
Project budgeting features continued:• Enter budget amounts directly• Define standardized budget entry methods to
enforce consistency of budgeting at specific levelswithin the WBS
• Define budget calculations (using client extension)Example: You can enter a quantity of hours that isused to calculate your budgeted raw and burdenedcost amounts, based on your rates and businessrules.
• Upload budget numbers from external sources
Project budgeting features continued:• Enter budget amounts directly• Define standardized budget entry methods to
enforce consistency of budgeting at specific levelsenforce consistency of budgeting at specific levelswithin the WBSwithin the WBS
• Define budget calculations (using client extension)Example: You can enter a quantity of hours that isused to calculate your budgeted raw and burdenedcost amounts, based on your rates and businessrules.
• Upload budget numbers from external sources
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 23
Cost Collection and Calculation Capabilities
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Cost Collectionand Calculation Capabilities
Cost Collectionand Calculation Capabilities
Defineprojects
Defineterms and
rulesCollect costs
Collect Collect costscosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 24
Types of Cost
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Types of CostTypes of Cost
You record transactions against a project to recordactual work performed or cost incurred. For example:• Timecards• Expense reports• Usage logs• Posted supplier invoice (posted to GL)You also record committed costs. For example:• Requisitions• Purchase orders• Pending supplier invoices (not posted to GL)
You record transactions against a project to recordactual work performed or cost incurred. For example:• Timecards• Expense reports• Usage logs• Posted supplier invoice (posted to GL)You also record committed costs. For example:• Requisitions• Purchase orders• Pending supplier invoices (not posted to GL)
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 25
Methods of Cost Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Methods of Cost EntryMethods of Cost Entry
Oracle Projects lets you track and account for allproject costs in your company using the followingmethods:• Preapproved Expenditure Batch: Input charges
directly into Oracle Projects.• Oracle Self-Service Time and Expenses: Input
labor and expense charges using Oracle Self-Service applications.
• Oracle Purchasing and Oracle Payables: Importcharges from requisitions, purchase orders, andsupplier invoices.
• Transaction Import: Import charges collected inexternal systems.
Oracle Projects lets you track and account for allproject costs in your company using the followingmethods:• Preapproved Expenditure Batch: Input charges
directly into Oracle Projects.• Oracle Self-Service Time and Expenses: Input
labor and expense charges using Oracle Self-Service applications.
• Oracle Purchasing and Oracle Payables: Importcharges from requisitions, purchase orders, andsupplier invoices.
• Transaction Import: Import charges collected inexternal systems.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 26
Methods of Cost Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Methods of Cost EntryMethods of Cost Entry
Oracle Projects also provides a Project Allocationfeature that allows you to allocate costs from one ormore source projects, from GL accounts, or from afixed amount to one or more target projects on aperiodic basis.Your allocations can:• Distribute costs to projects evenly• Distribute costs using target percentages• Prorate costs based on actual or budgeted
amounts• Calculate cost distribution using a custom formula
Oracle Projects also provides a Project Allocationfeature that allows you to allocate costs from one ormore source projects, from GL accounts, or from afixed amount to one or more target projects on aperiodic basis.Your allocations can:• Distribute costs to projects evenly• Distribute costs using target percentages• Prorate costs based on actual or budgeted
amounts• Calculate cost distribution using a custom formula
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 27
Cost Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Cost ControlsCost Controls
You can control which charges can be made againsta project and task.You can control which charges can be made againsta project and task.
Oracle Projects:10 hours labor25-AUG-1999
Oracle TimeManagement:8 hours labor18-AUG-1999
Oracle Purchasing:$100 Outside
Construction work29-DEC-1999
Oracle Payables:$100 Outside
Construction work05-JAN-2000rejected
accepted
rejectedaccepted
accepted
Project XYZ• Only labor and outside construction work can be charged.• No charges are allowed after 31-DEC-1999.
External CostCollection System:
$1,200 airfare04-AUG-1999
Cross ChargesUsing the Cross Charge Setup window, you can allow or disallow charges from otheroperating units.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 28
Cost Calculations
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Cost CalculationsCost Calculations
Processed transactions can have the following costs:• Raw cost: The costs that are directly attributable
to work performed (also referred to as direct cost).• Burden cost: The cost of running the business
that supports the raw cost (also referred to asindirect cost).
• Total Burdened Cost: Raw Cost + Burden Cost
Processed transactions can have the following costs:• Raw cost: The costs that are directly attributable
to work performed (also referred to as direct cost).• Burden cost: The cost of running the business
that supports the raw cost (also referred to asindirect cost).
• Total Burdened Cost: Raw Cost + Burden Cost
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 29
Multiple-Organization Support
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multiple-Organization SupportMultiple-Organization Support
Oracle Projects supports multiple organizations in asingle installation. You can:• Secure data access across organizations• Integrate Oracle Projects with other Oracle
Applications that have multiple-organizationsupport.
• Cross-charge across business groups, acrosslegal entities, across operating units within thesame legal entity, and across organizations withinthe same operating unit.
Oracle Projects supports multiple organizations in asingle installation. You can:• Secure data access across organizations• Integrate Oracle Projects with other Oracle
Applications that have multiple-organizationsupport.
• Cross-charge across business groups, acrosslegal entities, across operating units within thesame legal entity, and across organizations withinthe same operating unit.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 30
Multinational Support
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multinational SupportMultinational Support
Many enterprises manage projects that spancountries and currencies as well as organizations. Tosupport such multinational activities, Oracle Projectsprovides the capabilities to:• Incur costs in any currency• Invoice customers in any currency• Share resources across organizational and
currency boundaries and generate the appropriateaccounting transactions and legal documents
Many enterprises manage projects that spancountries and currencies as well as organizations. Tosupport such multinational activities, Oracle Projectsprovides the capabilities to:• Incur costs in any currency• Invoice customers in any currency• Share resources across organizational and
currency boundaries and generate the appropriateaccounting transactions and legal documents
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 31
Function Security
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Function SecurityFunction Security
Access to Oracle Projects functionality is notrestricted by default. However, using functionsecurity rules along with customized responsibilities,you can control what the user can see and do withinthe entire application.
Access to Oracle Projects functionality is notrestricted by default. However, using functionsecurity rules along with customized responsibilities,you can control what the user can see and do withinthe entire application.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 32
Function Security Example
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Function Security ExampleFunction Security Example
You may want some users to be able to create andsubmit an approved cost budget but not to baselineit. You would:• Create a responsibility that allows them access to
the Enter Budget window• Create a function security rule that would disallow
the baseline budget function
You may want some users to be able to create andsubmit an approved cost budget but not to baselineit. You would:• Create a responsibility that allows them access to
the Enter Budget window• Create a function security rule that would disallow
the baseline budget function
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 33
Project and Labor Cost Security
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project and Labor Cost SecurityProject and Labor Cost Security
You can provide three levels of project-basedsecurity to protect data ownership and sensitivity inrelation to a given project or project template:• The ability of a user to query project information• The ability of a user to update project information
and perform functions on a project• The ability of a user to view labor costs of detail
expenditure itemsFor each level of security, you can override thedefault rules or add additional security criteria usinga project security client extension.
You can provide three levels of project-basedsecurity to protect data ownership and sensitivity inrelation to a given project or project template:• The ability of a user to query project information• The ability of a user to update project information
and perform functions on a project• The ability of a user to view labor costs of detail
expenditure itemsFor each level of security, you can override thedefault rules or add additional security criteria usinga project security client extension.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 34
Project and Function Security
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project and Function SecurityProject and Function Security
How project security and function securitywork together:• Project security controls what projects you can
view and update.• Function security controls what functions you can
perform.• The two together allow you to control which
functions you can perform on which projects.
How project security and function securitywork together:• Project security controls what projects you can
view and update.• Function security controls what functions you can
perform.• The two together allow you to control which
functions you can perform on which projects.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 35
Project Asset Creation
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Asset CreationProject Asset Creation
Defineprojects
Defineterms and
rules
Collectcosts
Place asset in
service
Place asset Place asset in in
serviceserviceOther
Oracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 36
Capitalization of Project Costs
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Capitalization of Project CostsCapitalization of Project Costs
You can easily manage all project relatedconstruction-in-process (CIP) costs and expenses forcapital projects. Oracle Projects becomes the CIPsubledger for project related CIP costs.Work breakdown structures (WBS) provide anefficient mechanism for managing the project andtracking asset costs as they accumulate over time.
You can easily manage all project relatedconstruction-in-process (CIP) costs and expenses forcapital projects. Oracle Projects becomes the CIPsubledger for project related CIP costs.Work breakdown structures (WBS) provide anefficient mechanism for managing the project andtracking asset costs as they accumulate over time.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 37
Capitalization of Project Costs
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Capitalization of Project CostsCapitalization of Project Costs
With Oracle Projects, you can:• Associate project assets with a work breakdown
structure• Collect actual project costs• Capitalize the assets• Use the Oracle Assets Mass Additions
functionality to allow project information to flowdirectly from Oracle Projects to Oracle Assets
• Easily adjust asset costs, even after capitalization.
With Oracle Projects, you can:• Associate project assets with a work breakdown
structure• Collect actual project costs• Capitalize the assets• Use the Oracle Assets Mass Additions
functionality to allow project information to flowdirectly from Oracle Projects to Oracle Assets
• Easily adjust asset costs, even after capitalization.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 38
Flexible Revenue Accrual and Invoicing Functions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Flexible Revenue Accrualand Invoicing Functions
Flexible Revenue Accrualand Invoicing Functions
Defineprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognize revenue
Recognize Recognize revenuerevenue
Generate invoice
Generate Generate invoiceinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 39
Revenue Accrual and Billing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Revenue Accrual and BillingRevenue Accrual and Billing
Oracle Project Billing functionality provides theflexibility to keep up with your changing businessneeds. You can automatically accrue revenueaccording to your company policies. For example:• Time and material bill rates• Cost plus buildup• Percent spent ratio• Or any algorithm you defineYou can accrue revenue differently based on the typeof project. You can also bill each project differently,even if the same client has multiple projects. You caneasily manage cash collection in Oracle Receivables.
Oracle Project Billing functionality provides theflexibility to keep up with your changing businessneeds. You can automatically accrue revenueaccording to your company policies. For example:• Time and material bill rates• Cost plus buildup• Percent spent ratio• Or any algorithm you defineYou can accrue revenue differently based on the typeof project. You can also bill each project differently,even if the same client has multiple projects. You caneasily manage cash collection in Oracle Receivables.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 40
Billing Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Billing ControlsBilling Controls
You can control which transactions are billable forprojects and tasks.
Billable means that you can accrue revenue and billyour customers.
Nonbillable means that you cannot accrue revenueor bill your customers.
You can control which transactions are billable forprojects and tasks.
Billable means that you can accrue revenue and billyour customers.
Nonbillable means that you cannot accrue revenueor bill your customers.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 41
Billing Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Billing ControlsBilling Controls
Construction Work05-SEP-1999
Labor
• Labor is billable.• All expenses except entertainment expenses are billable.• Supplier invoices dated before 01-SEP-1999 are billable.
EntertainmentExpense
Construction Work28-AUG-1999Billable
Nonbillable
BillableBillable
Nonbillable
Meals
Project ABC
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 42
Online Reporting and Hard Copy Reporting
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Online Reporting and Hard CopyReporting
Online Reporting and Hard CopyReporting
Defineprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 43
Online Inquiry and Reporting
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Online Inquiry and ReportingOnline Inquiry and Reporting
To ensure project control and profitability, you needimmediate information for informed decision making.You can analyze project data at any point and makeadjustments easily, while maintaining a full audit trail.Oracle Projects provides several reporting andanalysis tools including:• Project Status Inquiry (PSI)• Standard reports• Database views for custom reports• Business Intelligence System (BIS) integration• Oracle Cash Management System integration
To ensure project control and profitability, you needimmediate information for informed decision making.You can analyze project data at any point and makeadjustments easily, while maintaining a full audit trail.Oracle Projects provides several reporting andanalysis tools including:• Project Status Inquiry (PSI)• Standard reports• Database views for custom reports• Business Intelligence System (BIS) integration• Oracle Cash Management System integration
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 44
Sub Ledger Accounting
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Sub Ledger AccountingSub Ledger Accounting
Oracle Projects provides the ability to viewaccounting lines for transactions interfaced to GL.You can:• Drill up from Oracle Projects to view accounting
details in GL.• Drill down from GL to the transactions interfaced
from Oracle Projects
Oracle Projects provides the ability to viewaccounting lines for transactions interfaced to GL.You can:• Drill up from Oracle Projects to view accounting
details in GL.• Drill down from GL to the transactions interfaced
from Oracle Projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 45
Full Adjustment Capabilities
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Full Adjustment CapabilitiesFull Adjustment Capabilities
Defineprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 46
Full Adjustment Capabilities
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Full Adjustment CapabilitiesFull Adjustment Capabilities
Oracle Projects records an audit trail of alladjustments.Oracle Projects records an audit trail of allOracle Projects records an audit trail of alladjustments.adjustments.
WhoWho WhatWhat WhenWhen
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 47
Transferring Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transferring TransactionsTransferring Transactions
You can transfer a transaction from one project ortask to another and maintain full tracing abilities.When the transaction is posted, the following occurs:• A reversing item is created for the old project.• A new item is created for the new project.• The new “transferred” transaction is posted to the
current open period• The new transaction is recosted with the new
burdened amount for the destination project ortask.
You can transfer a transaction from one project ortask to another and maintain full tracing abilities.When the transaction is posted, the following occurs:• A reversing item is created for the old project.• A new item is created for the new project.• The new “transferred” transaction is posted to the
current open period• The new transaction is recosted with the new
burdened amount for the destination project ortask.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 48
Other Cost Adjustments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Other Cost AdjustmentsOther Cost Adjustments
You can split a transaction into two transactions andthen:• Adjust the items• Transfer items to other projects or tasks
You can recalculate cost amounts due to:• Change in cost or burden rates• Change in GL account or AutoAccounting
You can split a transaction into two transactions andthen:• Adjust the items• Transfer items to other projects or tasks
You can recalculate cost amounts due to:• Change in cost or burden rates• Change in GL account or AutoAccounting
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 49
Billing Transaction Adjustments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Billing Transaction AdjustmentsBilling Transaction Adjustments
You can make billing adjustments againsttransactions. For example:• Billable or nonbillable reclassifications• Billing holds• Billing releases• Recalculated cost, revenue, bill amounts
(resulting from a change in cost rate, bill rate, orestimated completion time)
You can manage revenue and invoice write-off inOracle Projects. Once adjustments are complete,regenerate the revenue and/or invoice.
You can make billing adjustments againsttransactions. For example:• Billable or nonbillable reclassifications• Billing holds• Billing releases• Recalculated cost, revenue, bill amounts
(resulting from a change in cost rate, bill rate, orestimated completion time)
You can manage revenue and invoice write-off inOracle Projects. Once adjustments are complete,regenerate the revenue and/or invoice.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 50
Integration with Other Oracle and Non-Oracle FinancialApplications
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Integration with Other Oracle andNon-Oracle Financial ApplicationsIntegration with Other Oracle andNon-Oracle Financial Applications
Defineprojects
Defineterms and
rules
Collectcosts
Placeasset inservice
OtherOracle andnon-Oracle
applications
Recognizerevenue
Generateinvoice
Comprehensive online inquiry and reportingComprehensive online inquiry and reporting
Full adjustment capabilitiesFull adjustment capabilities
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 51
Oracle Projects Interfaces
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects InterfacesOracle Projects Interfaces
Oracle ProjectsProjectManagement
HumanResources
StatusReporting
CustomerInvoice
AccountingTransactions
CostCollectionSystems
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 52
Oracle Projects Interfaces
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects InterfacesOracle Projects Interfaces
Oracle ProjectsProjectManagement
HumanResources
StatusReporting
CustomerInvoice
AccountingTransactions
CostCollectionSystems
ProjectsProjects
BudgetsBudgets ExpendituresExpenditures
Oracle Projects EngineOracle Projects Engine
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 53
Oracle Projects Interfaces
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects InterfacesOracle Projects Interfaces
Projects
Budgets Expenditures
CostingCosting
Revenue AccrualRevenue Accrual CapitalizationCapitalization
SummarizationSummarization
Status Reporting(Actual vs. Budget)
CustomerInvoice
AccountingTransactions
InvoicingInvoicing
Oracle Projects
Oracle ProjectsEngine
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 54
Oracle Projects Interfaces
Copyright Oracle Corporat ion, 2000. All rights reserved.®
OraclePayables
Oracle Projects InterfacesOracle Projects InterfacesOracle Projects
ProjectsProjects
Revenue AccrualRevenue Accrual CapitalizationCapitalization
InvoicingInvoicing
ProjectManagement
OracleHuman
ResourcesEmployees
andOrganizations
DataWarehouse
ProjectStatusInquiry
OracleReceivables
OracleAssets
Oracle General Ledger
Self ServiceTime and Expense
External
OraclePurchasingSummarizationSummarization
ExpendituresExpendituresBudgetsBudgets
CostingCosting
WIP
Inventory
BIS
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 55
Oracle Projects Interfaces
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Oracle Projects InterfacesOracle Projects Interfaces
MFG R esource Costs
ReferenceEmploy ees andOrganizations
Plan
ActualsTimecards
Import
AccountsPayablePurchasing
Oracle Projects
General Ledger Pos t Usage DistributionPos t La bor Distribution
Post CashPost Cash
Usa ges
Supplie r Invoic es,Invoice Adjustments
Pos t Reve nue
Invoices Expense Reports
Pos t Actual Expens e
Adjustments
Report Committed Costs
AccountsReceivable
Timecards
Ass ets
Fixed AssetsOracleHuman
ResourcesPayrollService
External Transaction
Project Management
ReferenceCustomers
Oracle Inventory
Issues and Rece ipts
Work In
Process
Oracle WorkFlow
Data Warehouse
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 56
Overview of Activity Management Gateway
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Activity ManagementGateway
Overview of Activity ManagementGateway
Activity Management Gateway (AMG) enablesexternal applications to interface with Oracle Projectsto perform the following functions:• Create and maintain projects and budgets• Analyze commitments, actual costs and revenue• Manage progress (percent complete and earned
value)
Activity Management Gateway (AMG) enablesexternal applications to interface with Oracle Projectsto perform the following functions:• Create and maintain projects and budgets• Analyze commitments, actual costs and revenue• Manage progress (percent complete and earned
value)
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 57
Integration with External Systems
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Integration with External SystemsIntegration with External Systems
Using the AMG APIs you can:• Define projects in your project management
system and then import the project structure andbudgets into Oracle Projects.
• Export summarized project transactions fromOracle Projects to your project managementsystem.
Using the AMG APIs you can:• Define projects in your project management
system and then import the project structure andbudgets into Oracle Projects.
• Export summarized project transactions fromOracle Projects to your project managementsystem.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 58
Integration with External Systems
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Integration with External SystemsIntegration with External Systems
You can use the AMG APIs to integrate OracleApplications with a wide variety of external systems,including the following:• Project management systems• Sales management systems• Work management systems• Customer asset management and plant
maintenance systems• Project manufacturing systems• Legacy systems
You can use the AMG APIs to integrate OracleApplications with a wide variety of external systems,including the following:• Project management systems• Sales management systems• Work management systems• Customer asset management and plant
maintenance systems• Project manufacturing systems• Legacy systems
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 59
Overview of Oracle Project Connect
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Oracle Project ConnectOverview of Oracle Project Connect
Define project/tasks
Assign Resources
Schedule Project
Status Progress
Define project/tasks
Distribute and summarize Costs/Rev.
Define Resources
Collect Transactions
Capitalize Costs Generate Rev.
Project/Task DataProject/Task Data
Resource ListsResource Lists
Budget (Baseline/Cost)Budget (Baseline/Cost)Forecast PlanForecast Plan
Actual Costs/Rev.Actual Costs/Rev.
% Complete% Complete
Microsoft ProjectMicrosoft Project Oracle ProjectsOracle Projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 60
Attachments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AttachmentsAttachments
You can attach word processing documents,spreadsheets, or images to certain windows. OracleProjects supports attachments for the followingentities:• Projects: Attach project scope/definition
document• Tasks: Attach task scope/definition document• Budget versions: Attach preparation document• Expenditures: Attach timecards/expense reports• Project assets: Attach description of the asset• Agreements: Attach image of customer agreement• Project funding: Attach approval document• Draft invoice: Attach actual customer invoice
You can attach word processing documents,spreadsheets, or images to certain windows. OracleProjects supports attachments for the followingentities:• Projects: Attach project scope/definition
document• Tasks: Attach task scope/definition document• Budget versions: Attach preparation document• Expenditures: Attach timecards/expense reports• Project assets: Attach description of the asset• Agreements: Attach image of customer agreement• Project funding: Attach approval document• Draft invoice: Attach actual customer invoice
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 61
Summary
Copyright Oracle Corporat ion, 2000. All rights reserved.®
SummarySummary
In this lesson you should have learned to:• Use the wealth of information about projects,
tasks, resources, and transactions to analyze dataand answer the questions that are key to yourbusiness
• Describe Oracle Projects features• Describe Oracle Projects integration with other
applications
In this lesson you should have learned to:• Use the wealth of information about projects,
tasks, resources, and transactions to analyze dataand answer the questions that are key to yourbusiness
• Describe Oracle Projects features• Describe Oracle Projects integration with other
applications
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle ProjectsChapter 1 - Page 62
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 1
Overview of Oracle ProjectCostingChapter 2
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 2
Overview of Oracle Project Costing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Oracle Project CostingOverview of Oracle Project Costing
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 3
Objectives
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ObjectivesObjectives
After completing this course, you should be able todescribe the following:• Project costing flow• Cost budgeting• Expenditure entry and cost processing• Capitalization• Project Status Inquiry
After completing this course, you should be able todescribe the following:• Project costing flow• Cost budgeting• Expenditure entry and cost processing• Capitalization• Project Status Inquiry
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 4
Project Costing Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Costing FlowProject Costing Flow
Collect costs Place assetin service
Enter preapproved expenditures
Enter Reqs/ POs in
PO
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
Interface to Oracle Assets
InterfaceDistribute
costs
InterfaceImport to
G/LEnter
supplier invoices
External transactions
Enter time
Baseline budget
Enter budget
Transaction import
Upload
Review and adjust
asset lines
Generate asset lines
Enter project
Define assets
Overview of Oracle Project CostingUsing Oracle Project Costing, you can define projects, work breakdownstructures, and budgets; record and report costs against projects; and integratewith other Oracle and non-Oracle applications.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 5
Project Types
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project TypesProject Types
The project type determines how Oracle Projectsprocesses costs (expenditure items) for a project andprovides defaults and controls for project entry andprocessing. You must associate each project typewith a project type class:• Indirect: Collect and track expenditure item costs
and labor hours for overhead activities• Capital: Collect and track costs and labor hours
for asset development activities that you plan tocapitalize as one or more assets
• Contract: Collect and track costs, labor hours,revenue, and billing for services performed for andreimbursed by a client
The project type determines how Oracle Projectsprocesses costs (expenditure items) for a project andprovides defaults and controls for project entry andprocessing. You must associate each project typewith a project type class:• Indirect: Collect and track expenditure item costs
and labor hours for overhead activities• Capital: Collect and track costs and labor hours
for asset development activities that you plan tocapitalize as one or more assets
• Contract: Collect and track costs, labor hours,revenue, and billing for services performed for andreimbursed by a client
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 6
Project Cost Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Cost BudgetsProject Cost Budgets
User-definedbudget
Forecast cost budget
DRAFTDRAFT
DRAFT
BudgetBudgetversionsversions
Budget Budget typestypes
Original 1st
Revised original 2nd
Historical 3rd
Revised original 4th
Current 5th version
Submit and baseline
Approved cost budget
Overview of BudgetingYou use budgets to enter estimated quantities and costs required to performwork to complete a project or task. You can track project status andperformance by comparing budgeted amounts to actual transactions.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 7
Entering Project Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project ExpendituresEntering Project Expenditures
SupplierSupplierinvoicesinvoices
PurchasePurchaseordersorders
Self Service timeSelf Service timeand expenseand expense
Labor, expense, andLabor, expense, andusagesusages
Transaction import fromTransaction import fromother applicationsother applications
ProjectProjectcostcost
expendituresexpenditures
Overview of Project TransactionsYou must charge all actual expenditure items and future commitments to aproject and task in order to record actual work performed, cost incurred, andcommitted cost you expect to incur.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 8
Cost Processing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Raw CostAmount
Quantity• Hours• Each• Miles ...
×RawCostRate
Cost ProcessingCost Processing
×
Burdened CostBurdened Cost
Burden Multiplier• Expenditure type• Burden structure• Organization burden Rates
Definition of Cost ProcessingCosting is the processing of expenditures to calculate their total cost and todetermine the GL accounts to which the costs will be posted.
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 9
Capitalizing Project Costs
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Capitalizing Project CostsCapitalizing Project Costs
OracleOraclePurchasingPurchasing
OracleOraclePayablesPayables
OracleOracleAssetsAssets
OracleOracleProjectsProjects
OracleOracleGeneral LedgerGeneral Ledger
Send purchasingSend purchasingdetailsdetails
Send non-CIPSend non-CIPassetsassets
SendSendprojectprojectcostscosts Send CIPSend CIP
asset costsasset costs
Post invoicePost invoiceCIP andCIP andexpensedexpensedcostscosts
PostPost noninvoice noninvoice CIP and CIP andexpensed costsexpensed costs
Post assetPost assetcosts andcosts andclear CIPclear CIPaccountsaccounts
Send expenseSend expensereport costsreport costs
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 10
Project Status Inquiry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Status InquiryProject Status Inquiry
You can review summary amounts and calculationsby project, task, and resource using Project StatusInquiry (PSI). This function allows you to:• Review the current status of your projects• Drill down for more detailed review of a project
and its tasks• Use folder technology to customize the
appearance of information displayed in PSIwindows
You can review summary amounts and calculationsby project, task, and resource using Project StatusInquiry (PSI). This function allows you to:• Review the current status of your projects• Drill down for more detailed review of a project
and its tasks• Use folder technology to customize the
appearance of information displayed in PSIwindows
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 11
Summary
Copyright Oracle Corporat ion, 2000. All rights reserved.®
SummarySummary
This lesson provided an overview of:• Indirect projects• Project budgets• Cost Processing• Capitalized project costs
This lesson provided an overview of:• Indirect projects• Project budgets• Cost Processing• Capitalized project costs
Copyright © Oracle Corporation, 2000. All rights reserved.
Overview of Oracle Project CostingChapter 2 - Page 12
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 1
Creating ProjectsChapter 3
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 2
Creating Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Creating ProjectsCreating Projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 3
Objectives
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ObjectivesObjectives
After completing this lesson, you should be able todo the following:• Describe project classes and types• Describe the purpose and uses of project and task
configuration options• Create an indirect project• Create and modify a work breakdown structure
(WBS)• Enter overrides for the project and its tasks
After completing this lesson, you should be able todo the following:• Describe project classes and types• Describe the purpose and uses of project and task
configuration options• Create an indirect project• Create and modify a work breakdown structure
(WBS)• Enter overrides for the project and its tasks
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 4
Agenda
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AgendaAgenda
• Section 1: Overview of Project Concepts• Section 2: Creating and Configuring Projects• Section 3: Maintaining Projects and Tasks
• Section 1: Overview of Project Concepts• Section 2: Creating and Configuring Projects• Section 3: Maintaining Projects and Tasks
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 5
Section 1 Overview of Project Concepts
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 1Overview of Project Concepts
Section 1Overview of Project Concepts
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 6
Project Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project DefinitionsProject Definitions
Task 2.1 Task 2.2
Task 2
Task 1.1 Task 1.2
Task 1
Project
Task 2.2.2Task 2.2.1Task 1.1.1
A project is a primary unit of work that can be brokendown into one or more tasks.A project is a primary unit of work that can be brokendown into one or more tasks.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 7
Project Classes
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project ClassesProject Classes
You can use three predefined project classes thattrack the following types of information:• Indirect projects: Track overhead activities and
costs.• Capital projects: Track product/asset development
activities and costs, and costs are capitalized asone or more assets.
• Contract projects: Track activities, cost, revenue,and billing for work performed for and reimbursedby an internal or external customer.
You can use three predefined project classes thattrack the following types of information:• Indirect projects: Track overhead activities and
costs.• Capital projects: Track product/asset development
activities and costs, and costs are capitalized asone or more assets.
• Contract projects: Track activities, cost, revenue,and billing for work performed for and reimbursedby an internal or external customer.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 8
Project Types
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project TypesProject Types
Each project is assigned a project type. Project typesare user defined and are used to:• Control processing• Control project defaults• Generate reports• Specify AutoAccounting rules (if desired)
Each project is assigned a project type. Project typesare user defined and are used to:• Control processing• Control project defaults• Generate reports• Specify AutoAccounting rules (if desired)
How the Project Type Controls Processing and DefaultsProcessing:
• Whether to burden costs• Indirect, Capital, or Contract classification• Whether to budget
Defaults:• Task classification, which is called a service type• Burden options, if you burden costs• Budget control options, if you budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 9
Project Classes and Project Types
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Classes and Project TypesProject Classes and Project Types
Project Classes Project Types Project Classes Project Types
Indirect
Capital
Contract (Project Billing Only)
Bid and Proposal
Overhead
Product Development
Time and Materials
Cost Plus
Project classes are predefined, but project types areimplementation-defined.Project classes are predefined, but project types areimplementation-defined.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 10
Section 2 Creating and Configuring Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 2Creating and Configuring Projects
Section 2Creating and Configuring Projects
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 11
Creating and Configuring Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Comprehensive online inquiry and reporting
Adjustments
Creating and Configuring ProjectsCreating and Configuring Projects
Define projectsIdentifybusiness
termsand rules
Enter projectEnter project
Collect costs
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 12
Project Templates and Quick Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Templates and Quick EntryProject Templates and Quick Entry
All projects defined in Oracle Projects must originatefrom a template (or an existing project). Templatesare used to:• Simplify the project setup process• Copy projects and WBS• Copy commonly used project and task optionsQuick Entry provides:• A way to enter variable project information that
may change between projects• A way to override certain values defined for the
project template
All projects defined in Oracle Projects must originatefrom a template (or an existing project). Templatesare used to:• Simplify the project setup process• Copy projects and WBS• Copy commonly used project and task optionsQuick Entry provides:• A way to enter variable project information that
may change between projects• A way to override certain values defined for the
project template
Project CreationYou can create a new project by copying a project template or an existingproject.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 13
Required Project Data
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Required Project DataRequired Project Data
You can define a project with just the basic projectinformation:• Number
– Unique identifier– System-generated or manually entered; based
on implementation• Name: Unique description of the project• Type
– What type of project?– What type of work?
• Organization: The organization responsible forthe project
You can define a project with just the basic projectinformation:• Number
– Unique identifier– System-generated or manually entered; based
on implementation• Name: Unique description of the project• Type
– What type of project?– What type of work?
• Organization: The organization responsible forthe project
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 14
Optional Project Data
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Optional Project DataOptional Project Data
The following information is defaulted and can bechanged:• Duration: When does the project start and end?• Status: Is the project active (chargeable) or closed
(non-chargeable)?• Public Sector: Is the client public or private?
Selecting the Public Sector box affects projectreporting and AutoAccounting.
The following information is defaulted and can bechanged:• Duration: When does the project start and end?• Status: Is the project active (chargeable) or closed
(non-chargeable)?• Public Sector: Is the client public or private?
Selecting the Public Sector box affects projectreporting and AutoAccounting.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 15
Additional Project Data
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Additional Project DataAdditional Project Data
You can define additional information based on therequirements of your project or company. Optionsmay include:
You can define additional information based on therequirements of your project or company. Optionsmay include:
• Burden Multipliers• Multinational• Billing Information• Bill Rates and
Overrides• Organization
Overrides• Transaction Controls
• Tasks• Classifications• Key Members• Resource List
Assignment• Customers and
Contacts• Asset Information
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 16
Project Status Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Status ControlsProject Status Controls
You can use project status to control whatprocessing is allowed at the various stages of aproject. Oracle predefines the following statuses:• Active• Unapproved• Submitted• Approved• Rejected• Pending close• Closed
You can use project status to control whatprocessing is allowed at the various stages of aproject. Oracle predefines the following statuses:• Active• Unapproved• Submitted• Approved• Rejected• Pending close• Closed
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 17
Project Status Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Status ControlsProject Status Controls
When you define a project status, you specify whichfunctions are allowed for that status. You can controlthe following functions:• Create new transactions• Adjust transactions• Generate revenue• Generate invoice• Capitalize assets• Include in status reports
When you define a project status, you specify whichfunctions are allowed for that status. You can controlthe following functions:• Create new transactions• Adjust transactions• Generate revenue• Generate invoice• Capitalize assets• Include in status reports
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 18
How to Create a Project Status
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Create a Project StatusHow to Create a Project Status
Project Statuses(N) Setup—>Projects—>Statuses (B) Open
How to Create a Project Status1 In the Project Statuses window enter the status information.2 Check the Starting Status check box if you want the project status to be eligible for
use as the starting status for a new project.3 Save your status record.4 Review the Status Controls region.5 Allow Status Control actions as desired.6 Save your work.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 19
How to Create a New Project
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Create a New ProjectHow to Create a New Project
Find Projects(N) Projects
How to Create a New Project1 In the Find Projects window, enter your search criteria to find the template or
project that you want to copy.2 Click the Find button.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 20
How to Create a New Project
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Create a New ProjectHow to Create a New Project
Projects, Templates Summary(N) Projects (B) Find
How to Create a New Project (continued)3 Select the template or project that you want to copy in the Projects, Templates
Summary window.4 Click Open if you want to review the template or project before you copy it.5 Click the Copy To… button to copy the selected template or project definition into
your new project.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 21
How to Create a New Project
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Create a New ProjectHow to Create a New Project
Find Projects(N) Projects (B) Find (B) Copy To
How to Create a New Project (continued)6 Fill in the Project Quick Entry data required for your project definition and any
appropriate optional fields.7 Click OK.8 Choose Open to modify the new project definition (if necessary).
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 22
Key Members
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Key MembersKey Members
Key members are employees who can:• Enter and maintain project data• View labor cost details charged to
the project (based on project roletype definition)
Key members are employees who can:• Enter and maintain project data• View labor cost details charged to
the project (based on project roletype definition)
Key member information includes:• Employee name and number• Project role type (defined during implementation)
Each project can have only one project manager at a time.
Key member information includes:• Employee name and number• Project role type (defined during implementation)
Each project can have only one project manager at a time.
Examples of Key Members• Project manager• Project accountant• Project coordinator
Cross-Project Security in Oracle ProjectsYou can also define responsibilities for cross-project users who are able to enter andmaintain project data even if they are not assigned as key members.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 23
Classification Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Classification InformationClassification Information
You classify projects based on implementationdefined classification categories and codes.The category definition specifies whether:• More than one code per category is allowed.• A class code for the category is mandatory.
You classify projects based on implementationdefined classification categories and codes.The category definition specifies whether:• More than one code per category is allowed.• A class code for the category is mandatory.
Use codes forUse codes forAutoAccountingAutoAccounting
Use codes forUse codes forreportingreporting
Examples of Categories and Codes
Funding Source Market SectorPrivate EnvironmentalFederal StructuralState or Local
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 24
Work Breakdown Structure
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Work Breakdown StructureWork Breakdown Structure
A work breakdown structure (WBS) is a task treeshowing the organization of project work. It can beas simple or detailed as you want it to be. There areno limits in width or levels.
A work breakdown structure (WBS) is a task treeshowing the organization of project work. It can beas simple or detailed as you want it to be. There areno limits in width or levels.
Task 2.1 Task 2.2
Task 2
Task 1.1 Task 1.2
Task 1
Project
Task 2.2.1Task 1.1.1
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 25
Processing by Task Levels
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Processing by Task LevelsProcessing by Task Levels
Tasks can be used and processed based on theirlocation in the WBS.• Top tasks
– Budgeting– Rollup Reporting
• Middle tasksRollup Reporting
• Lowest tasks– Budgeting– Transaction Entry– Override Entry
Tasks can be used and processed based on theirlocation in the WBS.• Top tasks
– Budgeting– Rollup Reporting
• Middle tasksRollup Reporting
• Lowest tasks– Budgeting– Transaction Entry– Override Entry
Examples of Task Levels
Task 1 Task 2 Task 3Top Task and Top Task Top Task andLowest Task Lowest Task
______ |______ | |
Task 2.1 Task 2.2Middle Task Lowest and Middle Task
_____|______ | |
Task 2.1.1 Task 2.1.2Lowest Task Lowest Task
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 26
Basic Task Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basic Task InformationBasic Task Information
Information defined for all tasks:• Number• Name• Description (optional)• Task manager (optional)Information defaulted from project or parent task• Owning organization• Start and completion dates• Service type
Information defined for all tasks:• Number• Name• Description (optional)• Task manager (optional)Information defaulted from project or parent task• Owning organization• Start and completion dates• Service type
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 27
Task Numbering and Naming
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Task Numbering and NamingTask Numbering and Naming
Tasks are indented to indicate their location in theWBS. When planning your WBS numbering method,choose your task numbers carefully.The Task Number field is used as a sort key within atask level for reporting purposes. Since it isalphanumeric, numbers precede letters.
Tasks are indented to indicate their location in theWBS. When planning your WBS numbering method,choose your task numbers carefully.The Task Number field is used as a sort key within atask level for reporting purposes. Since it isalphanumeric, numbers precede letters.
2.1 2.2
21
Project
2.2.11.1.1
1.1
11
Project
01
2.1 2.2
02
2.2.1
11
1.1.1
1.1
NumberingIf the WBS has ore than 10 tasks, you must always use a leading zero for single-digitnumbers.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 28
Basic Task Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basic Task InformationBasic Task Information
Task chargeable check box:• Specifies whether lowest task can be charged• Defaults to allow charges for lowest tasks;
defaults to parent task value for middle tasks• Automatically unchecks for parent tasks when
subtasks are created
Task chargeable check box:• Specifies whether lowest task can be charged• Defaults to allow charges for lowest tasks;
defaults to parent task value for middle tasks• Automatically unchecks for parent tasks when
subtasks are created
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 29
Changing Default Task Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing Default Task InformationChanging Default Task Information
You can override the default task information.• Default information is used for new subtasks.• Changes do not cascade to existing tasks.
You can override the default task information.• Default information is used for new subtasks.• Changes do not cascade to existing tasks.
PROJECTOrg = Environ.
PROJECTOrg = Environ.
.
Task 1Org = Environ.
Task 1Org = Environ.
Task 2Org = Elect.
Task 2Org = Elect.
Task 3Org = Elect.
Task 3Org = Elect.
1.1Org = Environ.
1.1Org = Environ.
2.1Org = Elec.
2.1Org = Elec.
3.1Org = Environ.
3.1Org = Environ.
2.2Org = Elec.
2.2Org = Elec.
Example• Task 1: No detai l change• Task 2: Changed before subtasks created• Task 3: Changed after subtasks created
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 30
How to Create a Task
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Create a TaskHow to Create a Task
Tasks(N) Projects (B) Find (B) Open (B) Detail
How to Create a New Top Task1 Select a top task.2 Click the Create Peer Task button.
How to Create a New Subtask1 Select the task for which you want to create a subtask.2 Click the Create Subtask button.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 31
How to Enter Task Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
How to Enter Task DetailsHow to Enter Task Details
Tasks(N) Projects (B) Find (B) Open (B) Detail (B) Options
How to View Task Details1 Select a task in the Tasks window.2 Click the Options button.3 Select Task Detail in the Task Options window.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 32
Finding Tasks
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Finding TasksFinding Tasks
Tasks(N) Projects (B) Find (B) Open (B) Detail
Using the Find Tasks WindowIf you enable the profile option PA: Display Find Tasks, you can automatically displaythis window when you select the Tasks option in the Projects, Templates window. Thiswindow is very helpful if your projects have many tasks.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 33
Transaction Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ControlsTransaction Controls
In the Transaction Controls window, you list controlsbased on the Limit to Transaction Controls checkbox:• Checked = Inclusive limit to transaction controls
Allows only charges that are included on the list.Anything not listed is not chargeable.
• Unchecked = Exclusive limit to transactioncontrolsSpecifies charges that are not allowed. Anythingnot listed is chargeable.
You can control exceptions to any rule using theChargeable check box.
In the Transaction Controls window, you list controlsbased on the Limit to Transaction Controls checkbox:• Checked = Inclusive limit to transaction controls
Allows only charges that are included on the list.Anything not listed is not chargeable.
• Unchecked = Exclusive limit to transactioncontrolsSpecifies charges that are not allowed. Anythingnot listed is chargeable.
You can control exceptions to any rule using theChargeable check box.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 34
Transaction Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ControlsTransaction Controls
Transaction Controls(N) Projects (B) Find (B) Open (B) Detail
Result of This Transaction ControlElaine and Sharon can charge labor and contractor expenditures only. No otheremployees can charge to the project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 35
Transaction Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ControlsTransaction Controls
Transaction Controls(N) Projects (B) Find (B) Open (B) Detail
Result of This Transaction ControlElaine and Sharon can charge all types of transactions (including Expenses). No otheremployees can charge to the project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 36
Transaction Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ControlsTransaction Controls
Transaction Controls(N) Projects (B) Find (B) Open (B) Detail
Result of This Transaction ControlElaine can charge all types of transactions (including Material). All employees exceptSharon can charge everything except materials. Sharon cannot charge to the project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 37
Logic of Transaction Controls
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Logic of Transaction ControlsLogic of Transaction Controls
You can enter transaction controls at the projectand lowest task levels. Task transaction controlsoverride project transaction controls.The priority of processing when there is more thanone applicable row is as follows:• Person-Expenditure category-Expenditure Type
(NLR)• Person-Expenditure category• Person• Expenditure category-Expenditure type-(NLR)• Expenditure category
You can enter transaction controls at the projectand lowest task levels. Task transaction controlsoverride project transaction controls.The priority of processing when there is more thanone applicable row is as follows:• Person-Expenditure category-Expenditure Type
(NLR)• Person-Expenditure category• Person• Expenditure category-Expenditure type-(NLR)• Expenditure category
ReferenceFor more information, see Oracle Projects User’s Guide.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 38
Organization Overrides
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Organization OverridesOrganization Overrides
Organization Overrides(N) Projects (B) Find (B) Open (B) Detail
Organization Overrides Usability• Redirect an employee’s or organization’s costs to another organization.• Override expenditure organization used in Cost Plus processing and
AutoAccounting.
Note: Organization overrides can only be entered at the project level.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 39
Burden Multipliers
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Burden MultipliersBurden Multipliers
• A burden multiplier applies to a raw cost amountto reflect the actual cost of doing business. Theseextra costs include employee benefits, officespace, and so on.
• A cost burden schedule is an implementation-defined set of burden multipliers used for costingto derive total cost amounts. You can applycosting burden schedules across projects.
• Burden schedule overrides are revisions to theburden schedule attached to the project. Whenyou define project types at implementation, youdecide whether overrides will be allowed for eachproject type.
• A burden multiplier applies to a raw cost amountto reflect the actual cost of doing business. Theseextra costs include employee benefits, officespace, and so on.
• A cost burden schedule is an implementation-defined set of burden multipliers used for costingto derive total cost amounts. You can applycosting burden schedules across projects.
• Burden schedule overrides are revisions to theburden schedule attached to the project. Whenyou define project types at implementation, youdecide whether overrides will be allowed for eachproject type.
ReferenceFor more information, see Oracle Projects User’s Guide.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 40
Review of Project Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Review of Project DefinitionReview of Project Definition
Below is a summary of data elements and optionsavailable for indirect projects and tasks:Below is a summary of data elements and optionsavailable for indirect projects and tasks:
Project/Task OptionsClassificationCustomers and ContactsKey MembersOrganization OverridesResource List AssignmentsTransaction ControlsMultinational OptionsBurden MultipliersCosting Burden schedule
Burden Schedule
ProjectTopTask
MiddleTask
LowestTask
Default Default Default Default
Level at Which Entry Is Allowed
Review of the Steps to Create a New Project1 Create a new project by copying from a project template or an existing project.2 Enter basic project information.3 Specify project tracking information:
• Key members• Classifications
4 Define the WBS.5 Define additional project/task information to manage and process the project:
• Transaction controls• Costing overrides• Other
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 41
Reports for Project and Task Setup
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Reports for Project and Task SetupReports for Project and Task Setup
You can verify project and task setup with thesereports:• Project Configuration Report: Displays project
detail information and project overrides.• Task Details Report: Displays task detail
information and task overrides.• Work Breakdown Structure (WBS) Report:
Displays hierarchical format of work breakdownstructure.
You can verify project and task setup with thesereports:• Project Configuration Report: Displays project
detail information and project overrides.• Task Details Report: Displays task detail
information and task overrides.• Work Breakdown Structure (WBS) Report:
Displays hierarchical format of work breakdownstructure.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 42
Section 3 Maintaining Projects and Tasks
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 3Maintaining Projects and Tasks
Section 3Maintaining Projects and Tasks
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 43
Maintaining Projects and Tasks
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Maintaining Projects and TasksMaintaining Projects and Tasks
Collect costsDefine projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
AdjustmentsMaintain Projects and TasksMaintain Projects and Tasks
Enter projectEnter project
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 44
Changing the Project Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project InformationChanging the Project Information
You can make two types of changes to projectinformation, unrestricted and conditional, dependingon the type of information:Unrestricted changes:• Name/Description• Status• Public sector• Start date: Must be on or before any task start
date; will not change existing task attributes• Completion date: Must be on or after any task
completion date; will not change existing taskattributes
You can make two types of changes to projectinformation, unrestricted and conditional, dependingon the type of information:Unrestricted changes:• Name/Description• Status• Public sector• Start date: Must be on or before any task start
date; will not change existing task attributes• Completion date: Must be on or after any task
completion date; will not change existing taskattributes
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 45
Changing the Project Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project InformationChanging the Project Information
Conditional changes:• Project organization
– Change is allowed only before transactions arecharged to a project.
– An audit is retained to track transactionaccounts that were determined from the oldorganization using AutoAccounting rules.
Conditional changes:• Project organization
– Change is allowed only before transactions arecharged to a project.
– An audit is retained to track transactionaccounts that were determined from the oldorganization using AutoAccounting rules.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 46
Changing the Project Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project InformationChanging the Project Information
Conditional changes (Continued):• Project number
– Change is allowed only before transactions arecharged to a project. Transactions includetimecards, expense reports, usage logs,supplier invoices, purchase orders,requisitions, and events.
– Change is allowed only if manual projectnumbering is used.
• Project type: Change is allowed only beforetransactions are charged to a project.
Conditional changes (Continued):• Project number
– Change is allowed only before transactions arecharged to a project. Transactions includetimecards, expense reports, usage logs,supplier invoices, purchase orders,requisitions, and events.
– Change is allowed only if manual projectnumbering is used.
• Project type: Change is allowed only beforetransactions are charged to a project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 47
Changing the Project Organization
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project OrganizationChanging the Project Organization
Oracle Projects provides the functionality to changethe organization hierarchy. You can change youroriginal organization hierarchy and optionally placeeffective dates on multiple versions of the hierarchy.
You can make changes to project and taskorganization hierarchies after you enter transactionsfor the project or task.
Oracle Projects provides the functionality to changethe organization hierarchy. You can change youroriginal organization hierarchy and optionally placeeffective dates on multiple versions of the hierarchy.
You can make changes to project and taskorganization hierarchies after you enter transactionsfor the project or task.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 48
Changing the Project Organization
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project OrganizationChanging the Project Organization
You can define the following types of organizationhierarchies for different uses:• Project/task owning organization hierarchy• Expenditure/event organization hierarchy• Default reporting organization hierarchy• Project burdening organization hierarchy
You can define the following types of organizationhierarchies for different uses:• Project/task owning organization hierarchy• Expenditure/event organization hierarchy• Default reporting organization hierarchy• Project burdening organization hierarchy
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 49
Changing the Project Organization
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Project OrganizationChanging the Project Organization
Along with organization hierarchies, you can useorganization classifications to specify whichorganizations are allowed to:• Manage projects and tasks (project organization
hierarchy)• Incur expenditures (expenditure organization
hierarchy)
Along with organization hierarchies, you can useorganization classifications to specify whichorganizations are allowed to:• Manage projects and tasks (project organization
hierarchy)• Incur expenditures (expenditure organization
hierarchy)
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 50
Benefits of Reorganizations
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Benefits of ReorganizationsBenefits of Reorganizations
The following are business benefits of organizationhierarchies:• Accommodate company reorganizations for a
single or for multiple projects.• Determine which organizations can own projects
or incur costs through organizationclassifications.
• Indicate which organizations are valid project-owning organizations or expenditureorganizations for an operating unit throughorganization hierarchy assignment.
The following are business benefits of organizationhierarchies:• Accommodate company reorganizations for a
single or for multiple projects.• Determine which organizations can own projects
or incur costs through organizationclassifications.
• Indicate which organizations are valid project-owning organizations or expenditureorganizations for an operating unit throughorganization hierarchy assignment.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 51
Flexible Organization Change Methods
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Flexible Organization Change MethodsFlexible Organization Change Methods
Oracle Projects provides flexible change methods tomeet your business needs:• Change single project/task organization using the
Project form• Change multiple project/task organizations using
the Mass Update Batch form• Use function security, Projects: Org Update:
Update Override Standard Checks, or implementthe Verify Organization Change client extension toenforce organization change rules
Oracle Projects provides flexible change methods tomeet your business needs:• Change single project/task organization using the
Project form• Change multiple project/task organizations using
the Mass Update Batch form• Use function security, Projects: Org Update:
Update Override Standard Checks, or implementthe Verify Organization Change client extension toenforce organization change rules
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 52
Mass Update
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Mass UpdateMass Update
Mass Update Batches(N) Project Maintenance—>Mass Update Batches
Creating a Batch for Mass UpdateYou use the Mass Update Batches window to change the organization of multipleprojects and tasks. This window performs the following functions:
• Generates a batch of projects and/or tasks for which you want to update the owningorganization.
• Initiates a process that updates the organization on all projects and tasks specifiedin the batch.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 53
Changing the Task Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Task InformationChanging the Task Information
You can apply the following types of changes to atask definition:Unrestricted changes:• Task name• Description• Task manager• Task service type• Start date: Must be on or after project start date;
will not change existing task attributes• Completion date: Must be on or before project
completion date; will not change existing taskattributes
You can apply the following types of changes to atask definition:Unrestricted changes:• Task name• Description• Task manager• Task service type• Start date: Must be on or after project start date;
will not change existing task attributes• Completion date: Must be on or before project
completion date; will not change existing taskattributes
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 54
Changing the Task Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the Task InformationChanging the Task Information
Conditional changes:• Task number: Change is allowed only before
transactions are charged to a task.• Task organization: Change is allowed only before
transactions are charged to a task.• Chargeable check box: Change is allowed only at
the lowest task.
Conditional changes:• Task number: Change is allowed only before
transactions are charged to a task.• Task organization: Change is allowed only before
transactions are charged to a task.• Chargeable check box: Change is allowed only at
the lowest task.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 55
Changing the WBS
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing the WBSChanging the WBS
You can make the following types of changes to theWBS:• Adding a task: Can add any task without overrides
or transactions.• Deleting a task: Can delete any task without
transactions, subtasks, or budget amounts. Youwill delete overrides when the task is deleted.
• Changing the task level: Cannot be done directly,but it can be done by creating a new desiredstructure. This may require the transfer of anyitems that are charged to old tasks.
You can make the following types of changes to theWBS:• Adding a task: Can add any task without overrides
or transactions.• Deleting a task: Can delete any task without
transactions, subtasks, or budget amounts. Youwill delete overrides when the task is deleted.
• Changing the task level: Cannot be done directly,but it can be done by creating a new desiredstructure. This may require the transfer of anyitems that are charged to old tasks.
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 56
Changing Project Statuses; Integration with OracleWorkflow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Changing Project Statuses;Integration with Oracle Workflow
Changing Project Statuses;Integration with Oracle Workflow
You can use Oracle Workflow to define an approvalprocess to change the statuses of projects orbudgets. Using Oracle Workflow, you can:• Model workflows to meet your business processes• Automatically route projects and budgets to
approvers• Receive status notifications• Automatically update the project or budget based
on the approver’s actions
You can use Oracle Workflow to define an approvalprocess to change the statuses of projects orbudgets. Using Oracle Workflow, you can:• Model workflows to meet your business processes• Automatically route projects and budgets to
approvers• Receive status notifications• Automatically update the project or budget based
on the approver’s actions
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 57
Business Benefits of Using Workflow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Business Benefits of Using WorkflowBusiness Benefits of Using Workflow
Workflow gives you the ability to:• Create more accurate project and budgets by
dividing responsibility of entering and cross-checking information.
• Define your approval process in project andbudget status changes.
• Combine project and budget verification rules.• Choose which projects and tasks are routed via
Workflow• Choose the approval route and business rules that
apply
Workflow gives you the ability to:• Create more accurate project and budgets by
dividing responsibility of entering and cross-checking information.
• Define your approval process in project andbudget status changes.
• Combine project and budget verification rules.• Choose which projects and tasks are routed via
Workflow• Choose the approval route and business rules that
apply
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 58
Summary
Copyright Oracle Corporat ion, 2000. All rights reserved.®
SummarySummary
This lesson described how to perform these tasks:• Define project classes and types• Create a new indirect project• Create a WBS• Enter the appropriate project information• Apply transaction controls• Maintain projects
This lesson described how to perform these tasks:• Define project classes and types• Create a new indirect project• Create a WBS• Enter the appropriate project information• Apply transaction controls• Maintain projects
SummaryProject setup drives processing of transactions charged to the project.You define a project and a WBS to record work and process transactions as youand your company require.Project definition can be simple or complex, depending on your requirements.
• Key members• Classification information• Work breakdown structure• Charge controls• Costing overrides• Other
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 59
Practice 3-1 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 3-1 OverviewPractice 3-1 Overview
The practice covers:• Creating project types• Creating a project template• Creating an indirect project• Defining key members and classifications• Defining WBS, task details, transaction controls,
project status, and audit reports
The practice covers:• Creating project types• Creating a project template• Creating an indirect project• Defining key members and classifications• Defining WBS, task details, transaction controls,
project status, and audit reports
Copyright © Oracle Corporation, 2000. All rights reserved.
Creating ProjectsChapter 3 - Page 60
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 1
Cost BudgetsChapter 4
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 2
Cost Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Cost BudgetsCost Budgets
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 3
Objectives
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ObjectivesObjectives
After completing this lesson, you should be able todo the following:• Describe the options for budgeting project costs
– Budget entry method (BEM)– Detail of budget amounts
• Enter a project budget• Baseline the budget• Review the budget history• Revise the budget
After completing this lesson, you should be able todo the following:• Describe the options for budgeting project costs
– Budget entry method (BEM)– Detail of budget amounts
• Enter a project budget• Baseline the budget• Review the budget history• Revise the budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 4
Agenda
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AgendaAgenda
• Section 1: Overview of Budget Features• Section 2: Entering and Baselining Budgets• Section 3: Maintaining Budgets
• Section 1: Overview of Budget Features• Section 2: Entering and Baselining Budgets• Section 3: Maintaining Budgets
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 5
Section 1 Overview of Budget Features
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 1Overview of Budget Features
Section 1Overview of Budget Features
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 6
Overview of Budget Features
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of Budget FeaturesOverview of Budget Features
Collect costsDefine projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
Baseline budget
Enter budget
Enter project
Maintain Budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 7
Budget Structure
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget StructureBudget Structure
Every project budget that you enter is classified by abudget type. Each budget type is defined as either acost budget type or a revenue budget type. OracleProjects predefines four budget types:• Approved Cost budget• Approved Revenue budget• Forecast Cost budget• Forecast Revenue budget
Every project budget that you enter is classified by abudget type. Each budget type is defined as either acost budget type or a revenue budget type. OracleProjects predefines four budget types:• Approved Cost budget• Approved Revenue budget• Forecast Cost budget• Forecast Revenue budget
Budget TypesYou can define additional budget types. For example, your company may want tocreate a separate budget from the Approved Cost budget to track “what if” scenariosfor future project alternatives.You can use any budget type for project status tracking.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 8
Budget Structure
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget StructureBudget Structure
For cost budgets, you can enter:• Quantities• Raw cost• Burdened costsFor revenue budgets, you can enter:• Quantities• Revenue amounts
For cost budgets, you can enter:• Quantities• Raw cost• Burdened costsFor revenue budgets, you can enter:• Quantities• Revenue amounts
Budget AmountsThe Budget Entry Method may indicate user entry for some or all of the budget amountchoices.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 9
Budget Types and Versions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget Types and VersionsBudget Types and Versions
User-Definedbudget
Forecast Cost budget
DRAFTDRAFT
DRAFT
BudgetBudgetVersionsVersionsBudget Budget
TypesTypes
Original 1st
Revised original 2nd
Historical 3rd
Revised original 4th
Current 5th version
Submit and baseline
Approved Cost budget
Budget VersionsOracle Projects maintains a history of all baselined budgets for each budget type.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 10
Budget Versions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget VersionsBudget Versions
Budget versions are grouped as follows:• Original: First baselined budget• Current: Most recently baselined budget• Revised original: Current and historical revisions
of the original budget• Historical: Historical copies of previously
baselined budgets that are not original or current
Budget versions are grouped as follows:• Original: First baselined budget• Current: Most recently baselined budget• Revised original: Current and historical revisions
of the original budget• Historical: Historical copies of previously
baselined budgets that are not original or current
Budget ReportingThe current and original (or revised original) are used in reporting.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 11
Budget Entry Method (BEM)
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget Entry Method (BEM)Budget Entry Method (BEM)
For each version of each budget type, these four keybudgeting options must be determined:• Level of budget (project versus task levels)• Cost amount types (quantity, raw, and/or burdened
cost)• Time-phase (total duration versus time periods)• Detail of budget (summary versus categorized
detail)Every combination of these key elements is assignedto a unique budget entry method.
For each version of each budget type, these four keybudgeting options must be determined:• Level of budget (project versus task levels)• Cost amount types (quantity, raw, and/or burdened
cost)• Time-phase (total duration versus time periods)• Detail of budget (summary versus categorized
detail)Every combination of these key elements is assignedto a unique budget entry method.
Budget Entry MethodThe Budget Entry Method that you select when you enter a budget determines the levelof detail for the budget in these four areas. A more detailed budget allows you moredetail in status tracking and exception analysis but requires more time to maintain.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 12
Budget Entry Method (BEM)
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget Entry Method (BEM)Budget Entry Method (BEM)
Oracle Projects predefines three budget entrymethods:• By lowest tasks and date range, categorized by
resource• By lowest tasks and GL Period, categorized by
resource• By lowest tasks and PA Period, categorized by
resourceYou can define additional budget entry methods.
Oracle Projects predefines three budget entrymethods:• By lowest tasks and date range, categorized by
resource• By lowest tasks and GL Period, categorized by
resource• By lowest tasks and PA Period, categorized by
resourceYou can define additional budget entry methods.
BEM DefaultsYou can accept or override the default BEM:
• If you are entering the first draft for the budget type, the default BEM isdetermined by the project type of the project.
• If a prior version of the budget type exists, the default BEM is the budget entrymethod of the project’s current budget for the budget type.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 13
Budget Entry Method (BEM)
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget Entry Method (BEM)Budget Entry Method (BEM)
BEM SelectionIf you select a categorized BEM for the first draft budget of any type, all subsequentdraft budgets of that type must also use categorized BEMs. The same is true foruncategorized BEMs. The list of values for Entry Method will show only valid BEMsfor the budget.Categorized budgets are tracked by resource. Uncategorized budget amounts areentered at the work breakdown structure level for your budget. Amounts maysummarize a combination of labor, expenses, and other costs.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 14
Levels of Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Levels of BudgetsLevels of Budgets
PROJECT
Top Task Top Task
LowestTask
LowestTask
LowestTask SubtaskSubtask
LowestTask
You canYou canbudget herebudget here
You canYou canbudget herebudget here
You canYou canbudget herebudget here
You can neverYou can neverbudget at thisbudget at this
levellevel
Budget Entry LevelYou can budget your project at one of these levels:
• Project• Top task• Lowest task• Top or lowest task, different levels in different WBS branches
You should choose the budget level and detail that you need for tracking variances.This is not always at the lowest level.
• If you budget at the project level, you cannot budget at the task level.• If you budget at the top and lowest task levels, you can use a combination of the
top tasks and the lowest tasks in the same budget but not within the same WBSbranch.
• You can never budget at the middle task level.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 15
Selecting Costs
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Selecting CostsSelecting Costs
Budgets(N) Budgets
Cost Amount TypesSelect any combination of the following data elements to enter:
• Quantity• Raw cost• Burdened Cost
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 16
Time-Phased Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Time-Phased BudgetsTime-Phased Budgets
Choose either type of time-phased budgeting:• Amounts by time periods
– GL periods– PA periods– Date ranges
• Amounts at completionNo duration, defaults to project start/end dates
Choose either type of time-phased budgeting:• Amounts by time periods
– GL periods– PA periods– Date ranges
• Amounts at completionNo duration, defaults to project start/end dates
Examples
GL Periods PA Periods Date Ranges No Duration99-07 99-07-02 July 10 Defaults to task
99-07-03 through or project99-07-04 July 25 start/end dates
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 17
Resource List
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource ListResource List
To effectively manage your projects, you must trackthe activities and resources used on the project.Activities are defined in a WBS. Resources areamounts needed to track, complete, and account forproject work. For example:• Labor• Services• Material• Equipment
To effectively manage your projects, you must trackthe activities and resources used on the project.Activities are defined in a WBS. Resources areamounts needed to track, complete, and account forproject work. For example:• Labor• Services• Material• Equipment
Resource ListYou select the resources you want to use in your project budget from the resource listyou choose when you enter the draft.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 18
Resource List
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource ListResource List
You use Resource Lists as groupings by which youwant to budget and summarize actuals. You candefine resources lists made of:• Employees• Organizations• Jobs• Suppliers• Expenditure categories• Revenue categories• Expenditure types• Event types
You use Resource Lists as groupings by which youwant to budget and summarize actuals. You candefine resources lists made of:• Employees• Organizations• Jobs• Suppliers• Expenditure categories• Revenue categories• Expenditure types• Event types
Resource BudgetingYou can choose to budget by different resources for different kinds of projects. Forexample, you can budget labor by employees for small research and developmentprojects, and by organization for large design projects.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 19
Resource Groups
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource GroupsResource Groups
You can define a simple list of resources or a twolevel hierarchy of resource groups and resources.You can group resources by:• Organization• Revenue category• Expenditure category• No category
You can define a simple list of resources or a twolevel hierarchy of resource groups and resources.You can group resources by:• Organization• Revenue category• Expenditure category• No category
Using Resource GroupsIf you choose to use resource groups, you should include all expenditure categories,revenue categories, or organizations in your resource list.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 20
Resource Groups
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource GroupsResource Groups
Resources can be tracked byResources can be tracked by
A A laborlabor resource group resource groupand individual and individual employeesemployees
An An expensesexpenses resource resourcegroup and group and airfare, auto,airfare, auto,hotel and mealshotel and mealsexpenditure typesexpenditure types
A A materialmaterialresource groupresource group
Resource GroupsResource Groups allow you to:
• Budget using either the resource group or the resource• Review actuals at a higher level• Use multiple roll up structures for cross project reporting• Drill down to the resources for more details
Actuals are summarized at the lowest level in the resource list and rolled up to theresource group.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 21
Resource List
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource ListResource List
Resource Lists(N) Setup—>Budgets —>Resource Lists
Resource TypesDifferent resource types can be defined for each resource group.
• Projects can use different resources for different types of projects.• Projects can use different resources for different types of budgets on the same
project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 22
Resource List
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resource ListResource List
Resource List AssignmentDuring project template and project setup, you assign resource lists to a project toindicate which resource lists you want to use for summarizing project actuals. OracleProjects requires that every project have at least one resource list assignment.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 23
Budget Security
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget SecurityBudget Security
You can secure your project budget using one of thefollowing levels of budget security:• Project security: Controls which projects you can
select for budgeting and whether you can update abudget
• Function security: Controls a user’s access tofunctions based on the user’s responsibility
• Project management security: Controls updatingof budgets imported from external systems
• Budget line source security: Controls whether youcan update amounts in budget lines, based on thesource of the amount
You can secure your project budget using one of thefollowing levels of budget security:• Project security: Controls which projects you can
select for budgeting and whether you can update abudget
• Function security: Controls a user’s access tofunctions based on the user’s responsibility
• Project management security: Controls updatingof budgets imported from external systems
• Budget line source security: Controls whether youcan update amounts in budget lines, based on thesource of the amount
Budget SecurityThe budget line source security is implemented using function security. You canspecify limits on updating amounts that were calculated by a budget calculationextension, amounts that were copied from actuals, or amounts copied from budgetversions.For more information, seeOracle Projects User’s Guide, “Function Security” and “Project-Based Security.”
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 24
Section 2 Entering and Baselining Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 2 Entering and Baselining Budgets
Section 2 Entering and Baselining Budgets
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 25
Entering Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering BudgetsEntering Budgets
Collect costsDefine projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
Enter budgetEnter budget
Enter project
Maintain Budget
Enter budgetEnter budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 26
Creating Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Creating BudgetsCreating Budgets
Budgets(N) Budgets
Draft BudgetsYou enter or revise the budget amounts for a project in a draft budget. The status for adraft budget is Working.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 27
Budget Amounts
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget AmountsBudget Amounts
You enter budget amounts using one of the followingmethods:• Copy a project or template from the Projects,
Templates Summary window• Enter a budget directly in the Budgets window• Copy an earlier budget version and optionally
adjust amounts by a specified percentage• Copy project actuals• Enter budget quantities• Upload amounts from project management
systems
You enter budget amounts using one of the followingmethods:• Copy a project or template from the Projects,
Templates Summary window• Enter a budget directly in the Budgets window• Copy an earlier budget version and optionally
adjust amounts by a specified percentage• Copy project actuals• Enter budget quantities• Upload amounts from project management
systems
Entering Budget AmountsNote the following regarding budget amount entry methods:
• When copying a project or template from the Projects, Templates Summarywindow, the current budget (or draft if no baselined budget exists) is copied intothe new project for each budget type used by the source project or template.
• You can only copy actuals if you are using a PA or GL period time-phased BEM.• You can use the budget calculation extension to calculate the raw and burdened
costs and the revenue amounts for each budget line based on the quantity or rawcost that you enter.
• You can use the Activity Management Gateway or Oracle Project Connect toupload budget amounts from an external project management system.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 28
Task-Level Budget
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Task-Level BudgetTask-Level Budget
Task Budgets(N) Budgets (B) Details
How to View the Task-Level Budget1 Navigate to the Budgets window.2 Choose the Find Draft button to find the draft for the appropriate budget type.3 Choose the Details Button. If you are entering a task-level budget, the Tasks
Budgets window will open. You can see the summary of quantity, raw cost, andburdened cost for each task and the total for the project.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 29
Budget Lines
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget LinesBudget Lines
Task Budgets(N) Budgets (B) Details (B) Budget Lines
How to Enter Detailed Budget Information1 Navigate to the Task Budgets window.2 Select a task and click the Budget Lines button.3 Enter the resource information, unit of measure, and amounts for quantity, raw
cost, and burdened cost.4 View the totals, based on the selected amount type.
Note: You can enter the resource information, amount type, and amounts for up to fourperiods at a time using the matrix entry Budget Lines window.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 30
Budgeting by Quantity and Units
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budgeting by Quantity and UnitsBudgeting by Quantity and Units
Projects can budget by units at the detail-line levelappropriate for the given resource type. Whenviewing summary accounts:• The detail screen summarize all units• At summary levels above the detail lines, only
labor hours are summarized at the top task orproject level
Projects can budget by units at the detail-line levelappropriate for the given resource type. Whenviewing summary accounts:• The detail screen summarize all units• At summary levels above the detail lines, only
labor hours are summarized at the top task orproject level
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 31
Lines Overflow Region
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Lines Overflow RegionLines Overflow Region
Overflow regionThis window includes an overflow region for entry and display of the change reason,comments, and descriptive flexfield for each budget line. If hours, raw cost, andburdened cost for the same resource are entered, these fields are identical for all linesfor a given period. The descriptive flexfield is available for time-phased budgets.The profile option PA: Tab to Budget Matrix Fields controls how you can navigate tothe overflow region of the matrix entry Budget Lines window.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 32
Baselining Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Baselining BudgetsBaselining Budgets
Baselining is the process of approving a budget foruse in reporting and accounting.Baselining is the process of approving a budget foruse in reporting and accounting.
CurrentCurrentBudgetBudget
HistoricalHistoricalBaselinedBaselined Versions Versions
BaseliningThe first time you baseline a budget, that budget becomes the Original Budget. Themost recent baselined version is named the Current budget, which is used for reporting.All previously baselined budgets are named as historical baselined versions. TheProject Status Inquiry (PSI) compares actuals to the Current and Original (or revisedoriginal) budgets.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 33
Submitting Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Submitting BudgetsSubmitting Budgets
Submitting BudgetsWhen you complete budget entry, you can submit your draft to indicate that it is readyfor review and baselining.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 34
Baselining Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Baselining BudgetsBaselining Budgets
Baselining BudgetsWhen you baseline a budget for which Workflow is not enabled:
1 Oracle Projects calls the budget verification extension– If the budget baseline rules are not met, an error is issued and the status is not
changed.– If the budget baseline rules are met, the process continues.
2 Oracle Projects applies the standard baseline requirements to the budget.– If the standard rules are not met, an error is issued and the status is not
changed.– If the standard rules are met, the status is changed to Baselined.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 35
Baselining with Workflow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Baselining with WorkflowBaselining with Workflow
Baselining Budgets with Workflow1 Oracle calls the budget verification extension when the budget is submitted.
If the budget submission rules are met, budget baseline rules are verified. If eitherfails, an error is issued and the status does not change. If submission and baselinerules are met, the process continues.
2 Oracle calls the Workflow process indicated in the budget workflow extension.If the budget passes through the Workflow process, the process continues.Otherwise, an error is issued and the status does not change.
3 Oracle applies the standard baseline requirements to the budget.If the standard rules are met, the process continues. Otherwise, an error is issuedand the status does not change.
4 Oracle calls the budget verification extensionsIf the budget baseline rules are met, the status is changed to Baselined. Otherwise,an error is issued and the status does not change.
Note: Workflow calls the verification extension twice: once before it initiates thebudget approval process, and again before it changes the budget status. This ensuresthat the verification rules for the status change are met, even it changes have been madeto the budget during the approval process.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 36
Standard Baseline Requirements
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Standard Baseline RequirementsStandard Baseline Requirements
Standard baseline requirements only apply tocontract projects.Standard baseline requirements only apply tocontract projects.
Approved RevenueApproved RevenueBudgetBudget
FundingFunding
Standard Baseline RequirementsFor contract projects in Oracle Project Billing, the baseline function verifies that thebudget amounts for the budget type Approved Revenue Budget equals the total fundingfor the project or for the top tasks within the project, if using task level funding. If thischeck is successful, a new budget version is created. If the amounts are not equal,Oracle Projects displays an error and does not create a new budget version.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 37
Section 3 Maintaining Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 3Maintaining Budgets
Section 3Maintaining Budgets
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 38
Maintaining Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Maintaining BudgetsMaintaining Budgets
Collect costsDefine projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
Baseline budget
Enter budget
Enter project
Maintain Budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 39
Budget Processing Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget Processing FlowBudget Processing Flow
Enter/revise draft
Baseline draft
Submit draft
Copybudget
Reworksubmitted
budget
Create projects
BaselinedBaselinedbudget versionsbudget versionsTrack budget vs. actuals
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 40
Budget Versions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Budget VersionsBudget Versions
Budget Version History(N) Budgets (B) History
Budget VersionsAll versions of each budget type are maintained as a historical record for reportingpurposes. You can access any version of a budget from the Budgets window by:1 Selecting the appropriate budget type in the Find Budget region2 Clicking the History button
All baselined budgets are displayed in the Budget Version History window.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 41
Revising Baselined Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Revising Baselined BudgetsRevising Baselined Budgets
You cannot directly change the amounts or structureof a budget that has been baselined. If you need tomake changes to a baselined budget, you must:• Update the draft• Baseline that version as the new Current budget.
You cannot directly change the amounts or structureof a budget that has been baselined. If you need tomake changes to a baselined budget, you must:• Update the draft• Baseline that version as the new Current budget.
Revising Baselined BudgetsAfter you baseline a budget, the draft is the same as the last current budget version.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 42
Revising Original Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Revising Original BudgetsRevising Original Budgets
You may want to modify the Original Budget tocorrect data entry errors or scope changes which youwant to include in the original budget amounts.
You may want to modify the Original Budget tocorrect data entry errors or scope changes which youwant to include in the original budget amounts.
Revising the Original BudgetTo create a revised original budget:1 Choose the New Original box in the Budgets window.2 In the Budget Lines window, enter the revised budget amounts for the draft.3 Submit the budget for baselining.4 Choose Baseline. Oracle Projects creates a new version which is identified as the
new Current Budget and the new Original Budget. This new version is the“official” original budget for online status reporting.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 43
Revising Draft Budgets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Revising Draft BudgetsRevising Draft Budgets
There are different methods for revising draft budgetsin the Budgets window:• Changing amounts
– Navigate to the budget line and easily changeany field value, delete the budget item ifneeded, and add a new line.
– Copy previous budgets or actuals into a draft.• Changing BEM
– Navigate to the Entry Method field.– Select a different method. All budget lines are
deleted from the draft.
There are different methods for revising draft budgetsin the Budgets window:• Changing amounts
– Navigate to the budget line and easily changeany field value, delete the budget item ifneeded, and add a new line.
– Copy previous budgets or actuals into a draft.• Changing BEM
– Navigate to the Entry Method field.– Select a different method. All budget lines are
deleted from the draft.
Revising Draft BudgetsTo assign a budget line to a different resource:
• Delete the line• Re-enter using the correct resource.
To delete a budget line:• Select the budget line you want to delete.• Choose the Delete Record button from the toolbar.
To fully delete a budget line for a resource using the Budget Matrix Entry window, youmust enter zeros for all amounts and for all periods for that resource.
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 44
Summary
Copyright Oracle Corporat ion, 2000. All rights reserved.®
SummarySummary
This lesson described how to perform these tasks:• Create a project budget• Enter or revise a draft budget• Submit a draft budget• Baseline a draft budget• Revising baselined budgets• Track budgeted versus actual costs
This lesson described how to perform these tasks:• Create a project budget• Enter or revise a draft budget• Submit a draft budget• Baseline a draft budget• Revising baselined budgets• Track budgeted versus actual costs
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 45
Practice 4-1 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 4-1 OverviewPractice 4-1 Overview
• Creating a new budget• Baselining a budget• Modifying a budget
• Creating a new budget• Baselining a budget• Modifying a budget
Copyright © Oracle Corporation, 2000. All rights reserved.
Cost BudgetsChapter 4 - Page 46
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 1
TransactionsChapter 5
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 2
Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
TransactionsTransactions
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 3
Objectives
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ObjectivesObjectives
After completing this lesson, you should be able todo the following:• Set up the types of transactions in Oracle Projects• Describe the effects of charge controls• Explain the flow and entry of the following:
– Preapproved expenditure batches– Allocations and AutoAllocation Sets– Oracle Self Service Time and Expense– Transaction import– Project-related requisitions, purchase orders,
and supplier invoices– Multicurrency transactions
After completing this lesson, you should be able todo the following:• Set up the types of transactions in Oracle Projects• Describe the effects of charge controls• Explain the flow and entry of the following:
– Preapproved expenditure batches– Allocations and AutoAllocation Sets– Oracle Self Service Time and Expense– Transaction import– Project-related requisitions, purchase orders,
and supplier invoices– Multicurrency transactions
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 4
Agenda
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AgendaAgenda
• Section 1: Overview of Transactions• Section 2: Preapproved Expenditure Batch Entry• Section 3: Project Allocations and
AutoAllocations• Section 4: Oracle Self Service Time• Section 5: Expense Reports• Section 6: Project-Related Transactions in
Oracle Purchasing and Oracle Payables• Section 7: Multicurrency Transactions• Section 8: Transaction Import• Section 9: Review of Project Expenditures
• Section 1: Overview of Transactions• Section 2: Preapproved Expenditure Batch Entry• Section 3: Project Allocations and
AutoAllocations• Section 4: Oracle Self Service Time• Section 5: Expense Reports• Section 6: Project-Related Transactions in
Oracle Purchasing and Oracle Payables• Section 7: Multicurrency Transactions• Section 8: Transaction Import• Section 9: Review of Project Expenditures
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 5
Section 1 Overview of Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 1 Overview of Transactions
Section 1 Overview of Transactions
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 6
Overview of Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Overview of TransactionsOverview of Transactions
Collect costs
Enter preapproved expenditures
Enter Reqs/ POs in
PO
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
InterfaceImport to
G/L
Enter supplier invoices
External transactionsEnter Time & Expenses
Baseline budget
Enter budget
Transaction import
Upload
Enter project
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 7
Actuals and Commitments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Actuals and CommitmentsActuals and Commitments
You record the following transactions against aproject to record actual work performed or costincurred:• Timecards• Expense reports• Asset utilization usage logs• Supplier invoices• Miscellaneous• Burden• Work in process• Inventory
You record the following transactions against aproject to record actual work performed or costincurred:• Timecards• Expense reports• Asset utilization usage logs• Supplier invoices• Miscellaneous• Burden• Work in process• Inventory
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 8
Actuals and Commitments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Actuals and CommitmentsActuals and Commitments
You record the following transactions against aproject to record committed costs:• Requisitions• Purchase orders• unposted supplier invoices
You record the following transactions against aproject to record committed costs:• Requisitions• Purchase orders• unposted supplier invoices
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 9
Transaction Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction DetailsTransaction Details
Each transaction must be charged to a project’slowest-level task.Each detailed transaction is recorded with theseattributes:• Employee/supplier/organization that incurred
transaction• Expenditure item date = when work was performed
or cost was incurred• Project number• Task number = lowest-level task
Each transaction must be charged to a project’slowest-level task.Each detailed transaction is recorded with theseattributes:• Employee/supplier/organization that incurred
transaction• Expenditure item date = when work was performed
or cost was incurred• Project number• Task number = lowest-level task
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 10
Transaction Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction DetailsTransaction Details
• Expenditure type = type of transaction• Units of measure (UOM) = units defined by
expenditure type• Quantity = the quantity of units incurred• Nonlabor resource = asset utilized (for usage logs
only)• Nonlabor organization = organization that owns
the nonlabor asset (for usage logs only)
• Expenditure type = type of transaction• Units of measure (UOM) = units defined by
expenditure type• Quantity = the quantity of units incurred• Nonlabor resource = asset utilized (for usage logs
only)• Nonlabor organization = organization that owns
the nonlabor asset (for usage logs only)
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 11
Summary of Expenditure Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Summary of Expenditure DefinitionSummary of Expenditure DefinitionExpenditureType Class
ExpenditureCategory
ExpenditureType
Nonlabor Resource
NonlaborOrganization
StraightTime Labor Administrative
Professional
ExpenseReport
Travel AirfareMeals
OtherExpenses
EntertainmentOther Expenses
SupplierInvoices
OutsideServices
ConstructionConsulting
OtherExpenses
EquipmentRentalSupplies
Usages In-HouseRecoverables
ComputerServices
Vehicles
PC Data SystemsFinanceISMidwestEast
TruckVan
Sparc
Expenditure Type Classes for Miscellaneous CostsYou can simplify the collection of miscellaneous costs using the following newexpenditure type classes:
• Miscellaneous transaction– Tracks miscellaneous project costs– Similar to the usages expenditure type class– Does not require a nonlabor resource or organization
• Burden transaction– Tracks burden costs that are calculated in an external system or generated
within the projects setup– Is created as separate expenditure item that has burdened cost amounts, but has
not quantities and no raw costs– Can be interface to Oracle General Ledger
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 12
Summary of Expenditure Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Summary of Expenditure DefinitionSummary of Expenditure Definition
ExpenditureType Class
ExpenditureCategory
ExpenditureType
Nonlabor Resource
NonlaborOrganization
Miscellaneous
BurdenTransaction
Inventory
WorkInProcess
Fixed AssetsDepreciation
Computer SrvcsVehicles
Overhead
Materials
Materials
Labor Overhead
Building Materials
Building Materials
Expenditure Type Classes for Miscellaneous Costs (continued)• Work In Process transaction
– Tracks manufacturing resource costs that are interfaced from OracleManufacturing for project manufacturing integration.
– Can be used when you import other manufacturing costs using transactionimport.
• Inventory– Tracks manufacturing materials costs that are interfaced from Oracle
Manufacturing and inventory issues and receipts from Oracle Inventory.– Can be used when you import other manufacturing costs using transaction
import.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 13
Methods of Transaction Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Methods of Transaction EntryMethods of Transaction Entry
You record transactions using these methods• Preapproved batches• Project allocations• Transaction import• Oracle Self-Service Time and Expenses• Other Oracle applications
You record transactions using these methods• Preapproved batches• Project allocations• Transaction import• Oracle Self-Service Time and Expenses• Other Oracle applications
Preapproved BatchesApproved on paper; batch entry online in Oracle Projects.
• Timecards• Expense reports• Usage logs• Miscellaneous transactions
Transaction Import Imported from external cost collection systems.
Other Oracle ApplicationsStandard use of product.
• Requisitions (Oracle Purchasing)• Purchase orders (Oracle Purchasing)• Supplier invoices (Oracle Payables)• Timecards (Oracle Self Service Time)• Expense reports (Oracle Self Service Expense)
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 14
Terminology of Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Terminology of TransactionsTerminology of Transactions
Oracle Projects uses these terms for transactions:• Expenditure item: The smallest unit of expenditure
charged to a project and task.• Expenditure: A group of expenditure items
incurred by an employee or organization for anexpenditure period.
• Expenditure batch: A user-defined name used totrack a batch of preapproved expenditures, suchas timecards and expense reports.
Oracle Projects uses these terms for transactions:• Expenditure item: The smallest unit of expenditure
charged to a project and task.• Expenditure: A group of expenditure items
incurred by an employee or organization for anexpenditure period.
• Expenditure batch: A user-defined name used totrack a batch of preapproved expenditures, suchas timecards and expense reports.
ExamplesExpenditure Item
• Amy Marlin, 19-APR-2000, Profession Labor, 8 hours• Amy Marlin, 20-APR-2000, Profession Labor, 8 hours
Expenditure• Amy Marlin, Control Total = 16, Week Ending = 21-APR-2000
Expenditure Batch• Batch 123, 21-APR-2000
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 15
Charge Control Validation
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Charge Control ValidationCharge Control Validation
The following transactions charged to a project andtask must pass the charge controls defined for theproject and task:• Preapproved timecards, expense reports, and
usage logs in Oracle Projects (validation occursonline)
• SST and SSE (validation occurs during submit)• External transaction import (validation occurs
during import)• Supplier invoices in Oracle Payables (validation
occurs online)• Requisitions and purchase orders in Oracle
Purchasing (validation occurs online)
The following transactions charged to a project andtask must pass the charge controls defined for theproject and task:• Preapproved timecards, expense reports, and
usage logs in Oracle Projects (validation occursonline)
• SST and SSE (validation occurs during submit)• External transaction import (validation occurs
during import)• Supplier invoices in Oracle Payables (validation
occurs online)• Requisitions and purchase orders in Oracle
Purchasing (validation occurs online)
Online Validation• Start/completion dates: Must be within dates of project or task.• Project Status: Can charge only to a nonclosed project.• Task chargeability: Task must be chargeable and at lowest level.• Transaction controls: See ‘Creating Projects.’
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 16
Section 2 Preapproved Expenditure Batch Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 2 Preapproved Expenditure Batch Entry
Section 2 Preapproved Expenditure Batch Entry
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 17
Preapproved Expenditure Batch Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Preapproved Expenditure Batch EntryPreapproved Expenditure Batch Entry
Collect costs
Enter preapproved expenditures
Enter preapproved expenditures
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
Baseline budget
Enter budget
Enter project
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 18
Typical Preapproved Expenditure Batch Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Typical Preapproved Expenditure BatchFlow
Typical Preapproved Expenditure BatchFlow
Local OrganizationsLocal Organizations
1. Preparepreapprovedbatches.
2. Enter data;status is Working..
3. Print andreview entryaudit report.
6.Release/approvebatches.
5. Data isverified;submitsubmit batches.
4. Correct ifnecessary.
Central (Corporate) OrganizationCentral (Corporate) Organization
8. Print and reviewexp. batch statusreports.
9. Ensure that allbatches arereleased.
10. Distributecosts.
7. Reversebatches?
Yes
No
Local OrganizationsSteps 1 through 5 usually are done by data entry personnel, but step 6 can beaccomplished by the employee’s supervisor.
Central OrganizationsContact local organizations if all batches are not released.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 19
Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Preapproved BatchesPreapproved Batches
You can perform some of these typical pre-entryactivities:• Standardize the batch-naming process.• Organize batches of input documents.
Batch by item similarity within batch, which makescopying easier and simplifies repetitive data entry.
• Count the number of input documents in thebatch, which reduces potential error.
• Calculate the sum of all the transaction amounts(quantities).
You can perform some of these typical pre-entryactivities:• Standardize the batch-naming process.• Organize batches of input documents.
Batch by item similarity within batch, which makescopying easier and simplifies repetitive data entry.
• Count the number of input documents in thebatch, which reduces potential error.
• Calculate the sum of all the transaction amounts(quantities).
Examples• Standarize the batch-naming process.
T4/21CHI (T = Timecards, 4/21 = Date, CHI = Organization)• Organize batches of input documents.
All indirect employees; all employees working on one project• Count the number of input documents in the batch.
20 employees = 20 timecards = 20 input documents in one batch• Calculate the sum of all the transaction amounts (quantities).
Hours, dollars, days, and so on
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 20
Entering Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Preapproved BatchesEntering Preapproved Batches
Expenditure Batches(N) Expenditures—>Preapproved Batches —>Enter
Expenditure Type ClassesEach of the following expenditures can be entered in the Expenditure Batches window:
• Timecards• Expense reports• Usage• Miscellaneous Transaction• Burden Transaction• Inventory• Work in process
These classifications represent expenditure type classes. The class you choose in theExpenditure Batches window determines the expenditure type choices available to youin the Expenditures window.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 21
Entering Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Preapproved BatchesEntering Preapproved Batches
Expenditure Batches(N) Expenditures—>Preapproved Batches —>Enter
Expenditure Type Classes (continued)For example, if the class is Expense Reports (Expenditure Batches window), airfareshould be a choice in the Expenditure Type field (Expenditures window).
To Create a New Batch:1 Navigate to the Expenditure Batches window.2 Enter a unique batch name to identify this set of expenditures.3 Enter the expenditure ending date for the batch. A day of the week is specified as
the expenditure week ending date during implementations.4 Select the expenditure type class for this batch.5 Enter a description of the batch (optional).6 Use the fields in the Amounts region to verify actual versus control totals
(optional).7 Click Expenditures to enter the batch.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 22
Entering Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering ExpendituresEntering Expenditures
Expenditure Batches(N) Expenditures—>Preapproved Batches —>Enter (B) Expenditures
To Enter Expenditures1 In the Expenditures window, enter the employee or organization that incurred the
cost.2 Optionally enter the total units of measure in the Control Total field.3 In the Expenditure Item region, enter the date of the expenditure item.4 Enter the project number and the lowest-level task number.5 Enter the expenditure type for this expenditure item.6 Enter the quantity of units or amount (depending on the expenditure type class for
this expenditure item).7 Save your work.8 Submit the batch for review.
Note: Before entering expenditures, you enable the profile option PA: Tasks to Displayfor Expenditure Entry to indicate which tasks to include in the task list of values. Validchoices are All tasks, Chargeable tasks, and Lowest tasks.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 23
Entering Preapproved Usages
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Preapproved UsagesEntering Preapproved Usages
Similar to preapproved timecards, with a fewdifferences:Expenditure Batches windowClass = usuagesExpenditures window• In the Expenditures region, enter employee or
organization.• In the Expenditures Items region, select the usage
expenditure type, such as vehicle, field equipment,computer services.
• Nonlabor Resource and Organization: These fieldsare required for nonlabor usage entry.
Similar to preapproved timecards, with a fewdifferences:Expenditure Batches windowClass = usuagesExpenditures window• In the Expenditures region, enter employee or
organization.• In the Expenditures Items region, select the usage
expenditure type, such as vehicle, field equipment,computer services.
• Nonlabor Resource and Organization: These fieldsare required for nonlabor usage entry.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 24
Entering Perapproved Usages
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Perapproved UsagesEntering Perapproved Usages
Expenditures window• Resource: Enter the resource utilized. The list is
limited to those defined for the type and theorganization.
• Organization: Enter the organization that ownsthe asset utilized.
• Quantity: Enter the number of units.• Units vary by type, for example:
– Vehicles —> days– Field equipment —> hours– Computer service —> hours
Expenditures window• Resource: Enter the resource utilized. The list is
limited to those defined for the type and theorganization.
• Organization: Enter the organization that ownsthe asset utilized.
• Quantity: Enter the number of units.• Units vary by type, for example:
– Vehicles —> days– Field equipment —> hours– Computer service —> hours
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 25
Copying Preapproved Timecards
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Copying Preapproved TimecardsCopying Preapproved Timecards
You can copy preapproved timecards to speed entry.• You can copy timecards from one batch to
another.• The ‘Copy to’ target batch must first be created.• The date ending for the target batch defaults on all
line items.• You can copy with or without expenditure detail.
You can copy preapproved timecards to speed entry.• You can copy timecards from one batch to
another.• The ‘Copy to’ target batch must first be created.• The date ending for the target batch defaults on all
line items.• You can copy with or without expenditure detail.
Copy OptionUse the copy option to create similar batches on a repetitive bases.You can copy with or without expenditure detail.With detail:
• Copies employee, project/task, type, and amount• Used when employees typically work on the same project each week
Without detail:• Copies employee(s) only• Used when employees typically work on different projects each week
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 26
Resolving Problems in Expenditure Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Resolving Problemsin Expenditure EntryResolving Problemsin Expenditure Entry
You may encounter these problems when enteringexpenditures:• The project or the task does not allow charges.• The expenditure batch-control totals do not match
running totals.
You may encounter these problems when enteringexpenditures:• The project or the task does not allow charges.• The expenditure batch-control totals do not match
running totals.
What If the Project or Task Does Not Allow Charges?• Read the description and try to determine the proper number (transposed?).• Contact the employee, supervisor, or project manager and ask for a correction.• Last resort: Assign to a suspense project. This is a company policy decision. You
can report charges to a suspense project by organization to help to correct or clearcharges from the project.
What if the Expenditure Batch-Control Totals Do Not Match the RunningTotals?
• Determine whether the problem is with the entry or the control total:– Missing or duplicated entries– Wrong amounts
• Change the control total when:– It is incorrectly calculated.– An expenditure is removed from the batch.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 27
Preapproved Expenditure Entry Audit Report
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Preapproved Expenditure EntryAudit Report
Preapproved Expenditure EntryAudit Report
• You can review and verify data entry ofpreapproved batches using the PreapprovedExpenditure Entry Audit Report.
• This report displays the details of preapprovedexpenditure batches, including expenditures andexpenditure items.
• You can review and verify data entry ofpreapproved batches using the PreapprovedExpenditure Entry Audit Report.
• This report displays the details of preapprovedexpenditure batches, including expenditures andexpenditure items.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 28
Submitting Preapproved Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Submitting Preapproved ExpendituresSubmitting Preapproved Expenditures
• You submit the preapproved batch when you havefinished entry.
• The batch running totals must equal the controltotals (if using control totals) before you cansubmit the batch.
• You submit the preapproved batch when you havefinished entry.
• The batch running totals must equal the controltotals (if using control totals) before you cansubmit the batch.
What if the Running and Control Totals Are Not Equal?• Status will not change.• Error message is displayed.
To fix the error:1. Return to the Expenditure Batches window.2. Correct the Control and Running fields totals.
– Data entry error– Control total error
3. Click the Submit button.4. Save your work.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 29
Purpose of Releasing Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Purpose of ReleasingPreapproved BatchesPurpose of ReleasingPreapproved Batches
• Releasing a batch is a second level of review afterentry. This is usually done by someone other thanthe entry person, typically the entry person’ssupervisor. You can use function security toremove the release capability from the entryperson’s responsibilities.– Use the Preapproved Expenditure Entry Audit
Report to review batch input before release.– Expenditure batches can be edited before
release; the status must be ‘Working’ to makecorrections.
• Releasing a batch is a second level of review afterentry. This is usually done by someone other thanthe entry person, typically the entry person’ssupervisor. You can use function security toremove the release capability from the entryperson’s responsibilities.– Use the Preapproved Expenditure Entry Audit
Report to review batch input before release.– Expenditure batches can be edited before
release; the status must be ‘Working’ to makecorrections.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 30
Purpose of Releasing Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Purpose of ReleasingPreapproved BatchesPurpose of ReleasingPreapproved Batches
• Release makes expenditures ready for costdistribution; only approved expenditures can becost distributed.
• Release is synonymous with ‘Approval.’
• Release makes expenditures ready for costdistribution; only approved expenditures can becost distributed.
• Release is synonymous with ‘Approval.’
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 31
Purpose of Reversing Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Purpose of ReversingPreapproved BatchesPurpose of ReversingPreapproved Batches
• You can reverse an expenditure batch if thecurrent batch is released and the transactionsource of the batch allows adjustments.
• When you reverse an expenditure batch, allexpenditure items are reversed except:– Related items– Expenditure items that have been already
reversed– Reversing items (net zero adjusted items)– Expenditure items that were created as a result
of a transfer adjustment
• You can reverse an expenditure batch if thecurrent batch is released and the transactionsource of the batch allows adjustments.
• When you reverse an expenditure batch, allexpenditure items are reversed except:– Related items– Expenditure items that have been already
reversed– Reversing items (net zero adjusted items)– Expenditure items that were created as a result
of a transfer adjustment
Note• When the reversal is complete, you can display the number of items that are
adjusted and rejected.• You must use the Reverse button in the Expenditure Batches window to reverse the
entire preapproved expenditure batch.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 32
Purpose of Correcting Preapproved Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Purpose of CorrectingPreapproved BatchesPurpose of CorrectingPreapproved Batches
• After submitting a batch, you can makecorrections such as adding, deleting, and revisingexpenditures and expenditure items that wereincorrectly reported or entered.
• If the status of the batch is submitted, you mustreturn it to working, and then make the correctionsat the expenditure/expenditure item level beforeresubmitting the batch.
• If the status of batch is released, you must reversethe full amount of the original item before enteringthe correct information.
• After submitting a batch, you can makecorrections such as adding, deleting, and revisingexpenditures and expenditure items that wereincorrectly reported or entered.
• If the status of the batch is submitted, you mustreturn it to working, and then make the correctionsat the expenditure/expenditure item level beforeresubmitting the batch.
• If the status of batch is released, you must reversethe full amount of the original item before enteringthe correct information.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 33
Preapproved Expenditure Approvals
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Preapproved Expenditure ApprovalsPreapproved Expenditure Approvals
Expenditure Batch Statusand the Approval ProcessExpenditure Batch Statusand the Approval Process
Working Submitted
Released
Approved
Needs Adjustments?
Reversed
NoNo
YesYes
Working• In the process of creation.• Can exit and return to the batch.• Control totals do not have to match.
Editing allowed: All changes are acceptable.
Submitted• Ready for review.• Control totals must match.• Eligible for release.
Editing allowed: Can change status back to Working and then make edits.
Released• Approved.• Ready for cost distribution.• Cannot be changed back to Submitted.
Editing allowed: No changes allowed; must reverse entries in a new batch.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 34
Submitting and Releasing Batches
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Submitting and Releasing BatchesSubmitting and Releasing Batches
Expenditure Batches Summary(N) Expenditures—>Preapproved Batches —>Review (B) Find
Expenditure Batches Summary WindowUsing the Expenditure Batches Summary window, you can:
• Release one or more batches (Release button).• Submit one or more batches (Submit button).• Navigate to the Expenditure Batches window to review batch details (Open).• Navigate to the Expenditures window to review expenditure items (Expenditures
button).
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 35
Expenditure Batch Status Report
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Expenditure Batch Status ReportExpenditure Batch Status Report
• Use this report to determine which expenditurebatches by organizations are not yet released.
• The report usually runs by a centralized process.• This report lists preapproved expenditure batches
by organization. It includes the person whoentered the batch and the status of the batches.
• Use this report to determine which expenditurebatches by organizations are not yet released.
• The report usually runs by a centralized process.• This report lists preapproved expenditure batches
by organization. It includes the person whoentered the batch and the status of the batches.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 36
Review of Preapproved Expenditure Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Review of PreapprovedExpenditure Entry
Review of PreapprovedExpenditure Entry
You enter preapproved expenditure batches using thefollowing steps:1. Enter preapproved batches; status is Working.2. Submit batches; status is Submitted.3. Release batches; status is Released.
You enter preapproved expenditure batches using thefollowing steps:1. Enter preapproved batches; status is Working.2. Submit batches; status is Submitted.3. Release batches; status is Released.
NoteSteps 1 and 2 are performed by an entry person. Step 3 can be performed by anotherperson, usually the entry person’s supervisor.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 37
Section 3 Project Allocations and AutoAllocations
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 3Project Allocations and AutoAllocations
Section 3Project Allocations and AutoAllocations
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 38
Project Allocations Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocations OverviewProject Allocations Overview
What are Allocations?
Allocations are amounts from one or more sourceprojects/tasks, GL accounts, and/or fixed amountsdistributed (or allocated) to one or more targetprojects and/or tasks.
What are Allocations?
Allocations are amounts from one or more sourceprojects/tasks, GL accounts, and/or fixed amountsdistributed (or allocated) to one or more targetprojects and/or tasks.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 39
Project Allocations Business Need
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocations Business NeedProject Allocations Business Need
Project managers often need to allocate certain costsfrom one project to another. The allocations featurein Oracle Projects can distribute amounts:• Between projects and tasks• Within projects and tasks• To projects in other organizational unitsFor example, a manager could distribute acrossseveral projects amounts such as salaries,administrative overhead, and equipment charges.
Project managers often need to allocate certain costsfrom one project to another. The allocations featurein Oracle Projects can distribute amounts:• Between projects and tasks• Within projects and tasks• To projects in other organizational unitsFor example, a manager could distribute acrossseveral projects amounts such as salaries,administrative overhead, and equipment charges.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 40
Project Allocation Amounts
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocation AmountsProject Allocation Amounts
When you allocate amounts, you create expenditureitems whose amounts are derived from one or moreof the following:• Existing summarized expenditure items in Oracle
Projects• A fixed amount• Amounts in a General Ledger account balance
When you allocate amounts, you create expenditureitems whose amounts are derived from one or moreof the following:• Existing summarized expenditure items in Oracle
Projects• A fixed amount• Amounts in a General Ledger account balance
Allocating AmountsYou can specify exactly how and where you want to allocate selected amounts. Forexample, you may want to:
• Allocate the actual cost of office supplies equitably among various projects• Charge certain projects a larger percentage of costs• Allocate overhead costs, charging them to projects that benefited from the
overhead activities
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 41
Project Allocation Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocation DefinitionsProject Allocation Definitions
Source:The costs comprising the pool amount you wantto allocate. These costs can be comprised ofsummarized projects costs, posted GL balancesor fixed amounts (or a combination of all threesources).
Target:The projects and/or tasks receiving a percentageof the source pool amount.
Basis:The percentage of the source pool amountreceived by each chargeable task.
Source:The costs comprising the pool amount you wantto allocate. These costs can be comprised ofsummarized projects costs, posted GL balancesor fixed amounts (or a combination of all threesources).
Target:The projects and/or tasks receiving a percentageof the source pool amount.
Basis:The percentage of the source pool amountreceived by each chargeable task.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 42
Project Allocation Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocation DefinitionsProject Allocation Definitions
Offset:The reversing transactions to projects.
GL Allocation Batch:Allocation batches created in GL. For example:Mass Allocation, Recurring Journals, MassBudget.
AutoAllocation:A way to process one or more Projects allocationrules and GL allocation batches, both at the sametime or one after the other.
Offset:The reversing transactions to projects.
GL Allocation Batch:Allocation batches created in GL. For example:Mass Allocation, Recurring Journals, MassBudget.
AutoAllocation:A way to process one or more Projects allocationrules and GL allocation batches, both at the sametime or one after the other.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 43
Project Allocation Example
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project Allocation ExampleProject Allocation Example
Source Project collects costs and allocates amounts(determined by the basis) to Targets A, B, and C andcreates negative transactions to an Offset Project.
Source Project collects costs and allocates amounts(determined by the basis) to Targets A, B, and C andcreates negative transactions to an Offset Project.
Target B
Target C
Target A
Basis
Source
Offset
Allocation ExampleYou identify the sources (costs you want to allocate) and then define the targets(projects and tasks to which you want to allocate amounts). If you want, you can offsetthe allocations with reversing transactions.The system gathers source amounts into a source pool, and then allocates to the targetsat the rate (basis) that you specify.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 44
Basis Method
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basis MethodBasis Method
The basis method defines how and in what proportionthe amounts in the source pool are to be dividedamong the target projects. Each basis method has itsown characteristics.You can choose from the following four basismethods:• Spread Evenly• Target % - Spread Evenly• Prorate• Target % - Prorate
The basis method defines how and in what proportionthe amounts in the source pool are to be dividedamong the target projects. Each basis method has itsown characteristics.You can choose from the following four basismethods:• Spread Evenly• Target % - Spread Evenly• Prorate• Target % - Prorate
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 45
Basis Method - Spread Evenly
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basis Method - Spread EvenlyBasis Method - Spread Evenly
This method is the most simple and direct. The ruledivides the source pool amount equally among all thechargeable target tasks specified in the rule.
This method is the most simple and direct. The ruledivides the source pool amount equally among all thechargeable target tasks specified in the rule.
Source Amount
$100
P1 - $25
P2 - $25
P3 - $25
P4 - $25
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 46
Target % and Spread Evenly
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Target % and Spread EvenlyTarget % and Spread Evenly
This is another simple method. You specify thepercentage of the source pool that you want toallocate to each target line. The rule calculates theamount to allocate to the line, and then spreads theresults evenly among the tasks.
This is another simple method. You specify thepercentage of the source pool that you want toallocate to each target line. The rule calculates theamount to allocate to the line, and then spreads theresults evenly among the tasks.
Source Amount
$100
Target %P1 - 10%
P2 - 90%
T1 - $5
T2 - $5
T1 - $45
T2 - $45
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 47
Prorate
Copyright Oracle Corporat ion, 2000. All rights reserved.®
ProrateProrate
This basis method uses the basis attributes toapportion the source amount among all the tasksdefined by the rule.
This basis method uses the basis attributes toapportion the source amount among all the tasksdefined by the rule.
Source Amount
$100
P1
P2
Basis = raw cost
T1(Cost = $40)Allocation = $20 T2(Cost = $60)Allocation = $30
T1(Cost = $70)Allocation =$35T2(Cost = $30)Allocation =$15
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 48
Target % and Prorate
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Target % and ProrateTarget % and Prorate
This method uses the attributes set in the Basiswindow to derive the rate at which the source poolamount is apportioned among the target projects andtasks. The rule first uses the target percentage tocalculate the amount to allocate to the line, and thengoes on to apportion the results among all the tasks.
This method uses the attributes set in the Basiswindow to derive the rate at which the source poolamount is apportioned among the target projects andtasks. The rule first uses the target percentage tocalculate the amount to allocate to the line, and thengoes on to apportion the results among all the tasks.
Source Amount
$100
T1 (Cost = $40)Allocation = $8
T1
T2
Basis = raw costsTarget %P1 - 20%
P2 - 80%
T2 (Cost = $60)Allocation = $12
T1(Cost = $40)Allocation = $32
T2(Cost = $60)Allocation = $48
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 49
Allocation Rule Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule DefinitionAllocation Rule Definition
Allocation Rule(N) Allocations—>Allocation Rules
Allocation Rule Definition Steps - 10 Steps1 Enter a unique rule name and optional description, and specify the effective
dates.2 Choose a basis method. The basis and allocation method defines how and in what
proportion the amounts in the source pool are to be divided among the targetprojects.
3 Choose an Allocation Method.• Full - allocates the full source pool amount only once during a PA or GL
period.• Incremental - allocates the difference between each run per period PA or GL
period.4 Define your Allocation Period Type. This field specifies whether you want to
identify amounts based on the Oracle General Ledger (GL) fiscal calendar or theOracle Projects (PA) calendar.
5 Define your Targets Selection. This field specifies whether you want to selecttarget projects from the current operating unit only (default), or the current legalentity or current business group. The last two options require cross–charge setup.
6 Define your Rule Attributes. Select the Expenditure Org, Expenditure TypeClass, and Expenditure Type for your allocation transactions.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 50
Allocation Rule Sources
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule SourcesAllocation Rule Sources
Sources(N) Allocations—>Allocation Rules (B) Sources
Allocation Rule Definition Steps - 10 Steps (Cont.)7 Define your source(s). The allocation pool can be created from a fixed amount,
open projects (including resources within a project), Oracle General Ledger accountbalances, and projects defined by a client extension. The rule accumulates theamounts for the source pool during a specific period of time.The end date of that time period is based on the amount class. (The amount class isthe period or periods during which the amounts are accumulated.)The start date is determined by both the allocation period type (either GL or PA, asset in the Allocation Rule window) and the amount class.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 51
Allocation Rule Targets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule TargetsAllocation Rule Targets
Targets(N) Allocations—>Allocation Rules (B) Targets
Allocation Rule Definition Steps - 10 Steps (Cont.)8 Define your Target(s).
Targets are the projects and tasks to which the allocation distributes amounts. Youcan define targets either by specifying projects and tasks in the Target window, orby designating projects and tasks in the Allocation Target client extension.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 52
Allocation Rule Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule DefinitionAllocation Rule Definition
Basis(N) Allocations—>Allocation Rules (Basis)
Allocation Rule Definition Steps - 10 Steps (Cont.)9 Define a Basis Method.
If you select a proration basis method (Prorate or Target % and Prorate) in theAllocation Rule window, you must define exactly how you want to prorate thesource pool amount to the target projects. Proration basis methods derive theproportion of the source amount to be allocated to target projects and tasks. Todefine a basis method:
1 Choose Basis from the Allocation Rule window (the Basis button is availableonly if you selected the basis methods of Prorate or Target % and Prorate).
2 Enter the Basis Category of Budget or Actual.3 Enter the Amount Type and Amount Class.4 Enter the relative period to denote the current (0) or earlier (less than 0)
period. For example, if you want to use the period preceding the current one,enter -1.
5 Enter the Budget Type.6 Choose Resource List and Include or Exclude any resources in the list.
Continued...
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 53
Allocation Rule Offset
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule OffsetAllocation Rule Offset
Offset(N) Allocations—>Allocation Rules (B) Offset
Allocation Rule Definition Steps - 10 Steps (Cont.)10 Define an offset (Optional).
Offsets are reversing transactions used to balance the allocation transaction byoffsetting the source project or another project. Do not specify an offset to thesource project if you do not want to change the total amount in the source project.All offset projects and tasks must be open and chargeable, and in the sameoperating unit as the source projects. The rule creates the offset transactions for theoffset project and task when you run the PRC: Generate Allocations Transactionsprocess.
1 Choose Offset from the Allocations Window.2 Select an Offset Method (None (Default), Source Project and Task, Source
Project - Client Extension for Task, Client Extension for Project and Task,Specific Project and Task)
3 Define your Offset Transaction Attributes (Expenditure Org, ExpenditureType Class, Expenditure Type)
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 54
Allocation Rule Sources
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule SourcesAllocation Rule Sources
The following rules apply to allocation rule sources:• All allocation rules must have at least one defined
source.• All source projects and tasks must be from the
same operating unit.• All source projects and tasks must be open.• All tasks must be top or lowest level tasks.
The following rules apply to allocation rule sources:• All allocation rules must have at least one defined
source.• All source projects and tasks must be from the
same operating unit.• All source projects and tasks must be open.• All tasks must be top or lowest level tasks.
Sources(N) Allocations—>Allocation Rules (B) Sources
Source(s) Definition To define the sources for your allocation rule:
1 From the Allocation Rule window, choose the Sources button.2 In the Allocation Pool % field, enter a percentage to specify how much of the
total source pool to allocate. The default is 100%. Next, specify the amounts thatyou want to include in the source pool.
3 (Optional) In the Fixed Source Amount field, enter an amount that you want toinclude in the source pool. (This amount is over and above the other sourceamounts)
4 For Amount Class, select from the list of values. The field name is preceded byGL or PA, depending on the allocation period type you selected in the AllocationRule window: PA Periods (Period to Date, Inception to Date) and GL Periods(Period to Date, Quarter to Date, Year to Date)
5 Choose your Projects and/or GL sources6 (Optional) Select Resource button. Enter a resource list and/or resources you
want to include or exclude from your project source pool.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 55
Source Resources
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Source ResourcesSource Resources
Resources(N) Allocations—>Allocation Rules (B) Sources (B) Resources
Resources for SourcesOptionally, you can limit the resources that are part of the designated projects. If youdo not limit the resources, the rule uses all the resource types in the specified project inthe source pool amount.Enter the resource or resource group and the percent you want to include. The totalpercentage for included resources must equal 100. To exclude a specific resource,select Exclude on the appropriate line.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 56
Allocation Rule Targets
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Rule TargetsAllocation Rule Targets
The following rules apply to allocation rule targets:• All allocation rules must have at least one defined
target.• All target projects and tasks must be open and
chargeable.• If cross-charging is enabled, you can allocate
amounts to target projects that are in differentoperating units than the source projects.
The following rules apply to allocation rule targets:• All allocation rules must have at least one defined
target.• All target projects and tasks must be open and
chargeable.• If cross-charging is enabled, you can allocate
amounts to target projects that are in differentoperating units than the source projects.
Target DefinitionSpecify one or more open projects to which you want to distribute the source. Enter anumber in the Line Num field, and then select from the list of values to enter projectinformation in the Project Org, Project Type, Class Category, Class Code, Project, andTask fields.Excluding Projects
• To exclude a project from the target definition, select Exclude on the appropriateline.
• To exclude a specific task within a project, enter the project on two lines: on oneline, leave the Task field blank; on the other line, enter the task that you want toexclude and select the Exclude check box.
Duplicate TargetsIf you include the same project on multiple lines, the Allow Duplicate Targetsoption in the Allocation Rule window affects the way the rule behaves:
– If you allow duplicate targets, the rule allocates amounts to the project as manytimes as it appears in the transactions generated by the PRC: GenerateAllocations Transactions process.
– If you do not allow duplicate targets, the rule allocates amounts only to theproject with the lowest line number.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 57
Process an Allocation Rule
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Process an Allocation RuleProcess an Allocation Rule
Generate Allocation: Once you have created a rulefor allocating costs, use the PRC: Generate AllocationTransactions process to generate allocationtransactions and (if specified) offset transactions in adraft that you can review and evaluate.
Generate Allocation: Once you have created a rulefor allocating costs, use the PRC: Generate AllocationTransactions process to generate allocationtransactions and (if specified) offset transactions in adraft that you can review and evaluate.
Note: Expenditure Item Date = date assigned to new transaction
Submit Request(N) Other—>Requests—>Run
PRC: Generate Allocation Transactions ProcessAs the system executes the process, the run status changes. You can use the ReviewAllocation Runs window to carry out certain activities depending on the run status.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 58
Process an Allocation Rule
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Process an Allocation RuleProcess an Allocation Rule
Review Allocation: Use Review Allocation Runs formto review allocation details.Review Allocation: Use Review Allocation Runs formto review allocation details.
Find Allocation Runs(N) Allocations—>Review Allocation Runs
Review AllocationIf the draft allocation fails or does not produce the results you expect, you can deletethe draft in the Review Allocation Runs window. Then change the rule parameters inthe Allocation Rule Window and generate another draft.You can create, review, and delete draft runs until you are satisfied with the results.However, you cannot create a draft if another draft exists for the same rule. Althoughyou can run the Generate Allocations Transactions process at any time, it is a goodpractice to prepare for the allocation run by distributing costs and running all interfacesand summarization processes beforehand. Doing so ensures that the allocation runincludes all relevant amounts.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 59
Process an Allocation Rule
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Process an Allocation RuleProcess an Allocation Rule
Release Allocation: When you are satisfied with thedraft run and its status is Draft Success, use thePRC: Release Allocation Transactions process torelease the allocation run.The run status shows the state of the allocation run.
Release Allocation: When you are satisfied with thedraft run and its status is Draft Success, use thePRC: Release Allocation Transactions process torelease the allocation run.The run status shows the state of the allocation run.
In Process The process is not yet complete.DraftSuccess
DraftFailure
ReleaseSuccess
ReleaseFailure
The process has created draft transactions which areready for release.The process encountered problems and could not createdraft transactions.
The system has written the transactions to the target and (ifspecified) offset projects and tasks.
The system has not written the transactions, perhaps becauseprojects or tasks included in the draft run were deleted or closed.
Submit Request(N) Other—>Requests—>Run
Release AllocationYou can release the allocation run using the Review Allocation Runs window or byrunning the PRC: Release Allocation Transactions process.Warning: If you use an allocation rule that is set up for full allocation more than oncein a run period, you will generate duplicate transactions in your target projects. If thishappens, you can reverse the run.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 60
Allocation Run Review
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation Run ReviewAllocation Run Review
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 61
Allocation Exceptions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Allocation ExceptionsAllocation Exceptions
Draft Exceptions(N) Allocations—>Review Allocation Runs (B) Exceptions
Draft Exceptions WindowView the exceptions for a failed allocation run in the Draft Exceptions window. TheAllocation Run Report also list all exceptions.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 62
Missing Amounts
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Missing AmountsMissing Amounts
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 63
Basis Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basis DetailsBasis Details
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 64
Source Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Source DetailsSource Details
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 65
Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
TransactionsTransactions
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 66
Copying Rules
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Copying RulesCopying Rules
Copy a rule when you want to use an existing rule asa template. You can copy rules only within the sameoperating unit.
Copy a rule when you want to use an existing rule asa template. You can copy rules only within the sameoperating unit.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 67
AutoAllocations
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocationsAutoAllocations
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 68
AutoAllocations Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocations OverviewAutoAllocations Overview
What are AutoAllocations?
AutoAllocations provide the ability to generateallocations more efficiently by grouping processesand running them in a specified sequence(step down allocations) or at the same time (parallelallocations).
What are AutoAllocations?
AutoAllocations provide the ability to generateallocations more efficiently by grouping processesand running them in a specified sequence(step down allocations) or at the same time (parallelallocations).
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 69
AutoAllocations Business Need
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocations Business NeedAutoAllocations Business Need
Businesses need to automate the General Ledger andProjects Allocation processes through the utilizationof AutoAllocations and the workflow process.
Businesses need to automate the General Ledger andProjects Allocation processes through the utilizationof AutoAllocations and the workflow process.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 70
AutoAllocations Example
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocations ExampleAutoAllocations Example
You can automate the allocation of administrativeoverhead costs posted to a GL account to severalprojects within your organization.
You can automate the allocation of administrativeoverhead costs posted to a GL account to severalprojects within your organization.
ADMINISTRATIVE AUTOALLOCATION SET
Enter and PostRecurring GLJournal
Allocate posted GL balance to all projectsin your project org
AutoAllocationsYou can group allocation processes defined in Oracle General Ledger with allocationprocesses defined in Oracle Projects. In General Ledger, the allocation definition iscalled a batch. In Projects, the allocation definition is called a rule.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 71
AutoAllocations Setup
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocations SetupAutoAllocations Setup
You can create AutoAllocation sets in Oracle Projectsor Oracle General Ledger.When created in Oracle Projects:• Sets may contain Projects allocation rules and GL
allocation batches• Can only be viewed and ran by Oracle Projects
responsibilitiesWhen created in Oracle General Ledger:• Sets can only contain General Ledger batches• Can only be viewed and ran by General Ledger
responsibilities
You can create AutoAllocation sets in Oracle Projectsor Oracle General Ledger.When created in Oracle Projects:• Sets may contain Projects allocation rules and GL
allocation batches• Can only be viewed and ran by Oracle Projects
responsibilitiesWhen created in Oracle General Ledger:• Sets can only contain General Ledger batches• Can only be viewed and ran by General Ledger
responsibilities
AutoAllocation Set DefinitionYour responsibility defines which types of AutoAllocation sets are available. TheAutoAllocation form is the same in both Projects and General Ledger.Note: You can only run the AutoAllocation Set from the application in which it wascreated.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 72
AutoAllocation Types
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocation TypesAutoAllocation Types
There are two types of AutoAllocation Sets:• Step down allocations carry out the specified
steps of the AutoAllocation set in sequence, oneafter the other. Each step depends on the fullcompletion and success of the previous step.
• Parallel allocations carry out the specified stepsall at once and do not depend on previousallocation runs.
There are two types of AutoAllocation Sets:• Step down allocations carry out the specified
steps of the AutoAllocation set in sequence, oneafter the other. Each step depends on the fullcompletion and success of the previous step.
• Parallel allocations carry out the specified stepsall at once and do not depend on previousallocation runs.
Step Down Allocation SetsStep down allocation sets perform additional processing steps not included in parallelallocations (See Table next page). Oracle Workflow controls the flow of theAutoAllocations set.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 73
AutoAllocations Processes
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocations ProcessesAutoAllocations Processes
Projects
Project Allocations
ProjectAllocations
Step Down
Parallel
Generate Allocations TransactionsRelease Allocation TransactionsDistribute Miscellaneous Costs and UsagesUpdate Project Summary Amounts
Generate Allocations TransactionsRelease Allocation Transactions
General LedgerMass Allocation
Mass Budget
Mass Encumbrances
Recurring Journal
Step Down
Parallel
Run MassAllocationsRecurring Journal EntryBudget FormulasPosting
Run MassAllocationsRecurring Journal EntryBudget Formulas
AutoAllocation Set ProcessesAutoAllocations sets are made of one or more of the above processes. Note theadditional processing that occurs in Step Down sets.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 74
AutoAllocation Set Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocation Set DefinitionAutoAllocation Set Definition
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 75
AutoAllocation Set Submission
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocation Set SubmissionAutoAllocation Set Submission
You can submit your request to run immediately orschedule it to run at a later date. Depending on thesteps included in your AutoAllocation Set,parameters may include:• Batch name (optional)• Period (GL Batches)• Budget (optional)• Journal Effective Date• Calculation Effective Date• Usage (Standard Balances or Average balances)
You can submit your request to run immediately orschedule it to run at a later date. Depending on thesteps included in your AutoAllocation Set,parameters may include:• Batch name (optional)• Period (GL Batches)• Budget (optional)• Journal Effective Date• Calculation Effective Date• Usage (Standard Balances or Average balances)
Submission ParametersThe following parameters should be entered for sets that contain GL batches:
• Name: Enter a batch name. Used for display only.• Period: Select an accounting period.• Budget: If your allocation uses budget amounts, select a defined budget.
If your set contains General Ledger batches and your General Ledger uses an averagebalance set of books, the following addition parameters should be entered:
• Journal Effective Date: Select or enter a date.• Calculation Effective Date: Select a date in any open, future, closed, or
permanently closed period.• Usage: Select Standard Balances or Average Balances.
If your set contains Project rules, enter the following parameter values:• GL Period and/or PA Period: If the project rules belong only to the GL period
type, enter only the GL Period. If the project rules belong only to the PA periodtype, enter only the PA Period. Otherwise, enter both fields.
• Expenditure Item Date: Enter an expenditure item date for the allocationtransactions.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 76
View AutoAllocation Statuses
Copyright Oracle Corporat ion, 2000. All rights reserved.®
View AutoAllocation StatusesView AutoAllocation Statuses
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 77
View Step Statuses
Copyright Oracle Corporat ion, 2000. All rights reserved.®
View Step StatusesView Step Statuses
Allocation Step Details(N) Allocations—>AutoAllocations—>View Statuses (B) Step Details
Allocation Step Details WindowThis window will show you the status of each step included in your AutoAllocationSet.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 78
AutoAllocation Rollback Feature
Copyright Oracle Corporat ion, 2000. All rights reserved.®
AutoAllocation Rollback FeatureAutoAllocation Rollback Feature
Step Down AutoAllocation Sets can rollbackprocessed steps as follows:Step Down AutoAllocation Sets can rollbackprocessed steps as follows:
AutoAllocationAutoAllocation Set Contents Set Contents Rollback CapabilityRollback Capability
GL batches onlyGL batches only YesYes
PA rules onlyPA rules only NoNo
GL batches and PA rulesGL batches and PA rules NoNo
Rollback FunctionIf an AutoAllocation set contains only General Ledger batches and fails to complete,you can choose to rollback the steps that were processed before the failure.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 79
Practice 5-1 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 5-1 OverviewPractice 5-1 Overview
This practice covers the following topics:1. Setting up allocation rules2. Generating allocations transactions3. Reviewing and releasing allocation runs4. Querying allocation expenditure batches
This practice covers the following topics:1. Setting up allocation rules2. Generating allocations transactions3. Reviewing and releasing allocation runs4. Querying allocation expenditure batches
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 80
Section 4 Self-Service Time
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 4Self-Service Time
Section 4Self-Service Time
Self-Service TimeSelf-Service Time is a browser-based time entry product that is seamlessly integratedwith Oracle Projects for project tracking, costing, and billing. When used with Self-Service Expenses, these two products provide an end-to-end solution for time andexpense management.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 81
Self-Service Time
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Self-Service TimeSelf-Service Time
Users can:• Create Timecards by using a web browser
– Easy to deploy– Intuitive interface
• Track the progress of timecards in process• Respond to workflow notifications to approve,
reject, or reassign timecards
Users can:• Create Timecards by using a web browser
– Easy to deploy– Intuitive interface
• Track the progress of timecards in process• Respond to workflow notifications to approve,
reject, or reassign timecards
Self-Service TimeWith Self-Service Time:
• Employees or administrative assistants can enter timecards• Managers can evaluate employee utilization and productivity• Timecard policies can be automatically enforced using configurable rules for
approval.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 82
Business Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Business FlowBusiness Flow
Approval
Oracle Projects•Project Costing•Project BillingWorkflow-based
Approval Process
Create Online
Timecard
Create Disconnected(via Excel)
Self-Service TimeWith Self-Service Time:
• Timecards are entered online or disconnected.• Timecards entered by an administrative assistant will follow routing as if they were
created by the employees themselves.• Project related timecards can be imported to Oracle Projects for costing and billing.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 83
On-Line Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
On-Line EntryOn-Line Entry
On-Line EntryWhen using the On-Line Entry feature:
• Users enter timecards over the web using a standard browser.• All information entered is validated online before submission, including project,
task, expenditure type, date, hours and overriding approver.• A control number is given to the user upon saving or submitting the timecard for
future tracking.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 84
Alias Setup
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Alias SetupAlias Setup
User AliasesTo expedite entry, each user can define aliases for a grouping of project, task, andexpenditure type.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 85
Disconnected Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Disconnected EntryDisconnected Entry
Disconnected EntryAn Excel template is available for users to download and use for disconnected entry.The template allows users to enter and track all information available in the onlineapplication, the only exception being context-sensitive descriptive flexfields.To submit the spreadsheet timecard for full validation and approval, users simplyupload it into Oracle Self-Service Time once they are online again.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 86
Project and Task View
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project and Task ViewProject and Task View
View Project TasksSelf-Service Time can generate a listing of projects and tasks that can be exported intoa format that can then be used with the disconnected spreadsheet.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 87
Section 5 Expense Reports
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 5Expense Reports
Section 5Expense Reports
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 88
Creating Project-Related Expense Reports
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Creating Project-RelatedExpense Reports
Creating Project-RelatedExpense Reports
Project-related expense reports can be entered in:• Oracle Projects• Self-Service Expenses• Oracle Payables
Project-related expense reports can be entered in:• Oracle Projects• Self-Service Expenses• Oracle Payables
Expense ReportsExpense reports can be entered in Oracle Projects, Self-Service Expenses, or OraclePayables. Oracle Payables maintains and tracks payment, and then sends theaccounting transactions to Oracle General Ledger.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 89
Entering Project-Related Expense Reports in OracleProjects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related ExpenseReports in Oracle Projects
Entering Project-Related ExpenseReports in Oracle Projects
Expense Reports Entered in Oracle ProjectsExpense reports can be entered as Pre-Approved Expenditure Batches in OracleProjects. The Expenditure Class value should be Expense Reports. The project, task,and expenditure type can be specified for each expenditure item.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 90
Entering Project-Related Expense Reports in Self-Service Expenses
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related ExpenseReports in Self-Service ExpensesEntering Project-Related ExpenseReports in Self-Service Expenses
Users can:• Create expense reports by using a Web browser
– Easy to deploy– Intuitive interface
• Choose project-related expense items• Enter project and task information for each
project-related expense item• Track the progress of expense reports in process• Respond to Workflow notifications to approve,
reject, or reassign Web expense reports
Users can:• Create expense reports by using a Web browser
– Easy to deploy– Intuitive interface
• Choose project-related expense items• Enter project and task information for each
project-related expense item• Track the progress of expense reports in process• Respond to Workflow notifications to approve,
reject, or reassign Web expense reports
Self-Service ExpensesOracle Self-Service Expenses combines the power of Oracle Workflow, Oracle Self-Service Applications, and Oracle Payables to provide a Web based Expense Reportentry extension for core Oracle Financials. Armed with a simple web browser, andoptionally an Excel spreadsheet, you are able to enter expense reports and review theirstatus at any time.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 91
Self-Service Expenses Business Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Self-Service Expenses Business FlowSelf-Service Expenses Business Flow
ManagementApproval
Create InvoiceWorkflow-based Approval Process
Create Online(Use Wizards!)
Pay Invoice
Employees
ElectronicPayment
ExpenseReport
Create D isconnected(Use Spreadsheet!)
AP Approval
Business FlowWhen using Self-Service Expenses:
• Employees enter expense reports using a web browser or in disconnected modeusing an Excel spreadsheet.
• Reports are submitted for approval which starts the expense report workflowprocess and populates the Oracle Payables invoice interface tables.
• Reports are reviewed and approved or rejected by employee managers.• The accounts payable department reviews, audits, adjusts, and approves expense
reports using the Expense Report windows in Oracle Payables. Note that theproject fields are not available in this window.
• After manager and AP approval, the invoice import process is used to generateinvoices for the expense reports.
• Invoices are then processed and paid in Oracle Payables.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 92
Entering Project-Related Expense Reports in Self-Service Expense
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related ExpenseReports in Self-Service Expense
Entering Project-Related ExpenseReports in Self-Service Expense
Expense Reports Entered in Self-Service ExpenseNote the following when using Self-Service Expense to enter project related expenses:
• Expense reports can be entered via a standard web browser or a disconnectedexpense spreadsheet.
• Projects information (project and task number) must be entered for each project-related expense item entered.
• Both project-related and nonproject-related receipts can be entered in the sameexpense report.
• Projects information is validated on-line when the report is submitted.• Oracle Projects builds GL accounts for receipts based on accounting rules defined
in Projects using Oracle Projects Account Generator.• Project-related expense reports can be paid, posted, and then interfaced to Oracle
Projects for project burdening and tracking.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 93
Self-Service Expense Disconnected Expense Report
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Self-Service ExpenseDisconnected Expense Report
Self-Service ExpenseDisconnected Expense Report
Expense ReportCost Center
PurposeExpense Template TravelOverride Approver
Total 0.00
Line Date From Date To DaysDaily
AmountReceipt Amount Currency Code Rate
Converted Amount Expense Type Project Number Task Number
Receipt Missing
Expense Group
1 0 0.00 USD 1. 0.00 2 0 0.00 USD 1. 0.00 3 0 0.00 USD 1. 0.00 4 0 0.00 USD 1. 0.00 5 0 0.00 USD 1. 0.00 6 0 0.00 USD 1. 0.00 7 0 0.00 USD 1. 0.00 8 0 0.00 USD 1. 0.00 9 0 0.00 USD 1. 0.00
10 0 0.00 USD 1. 0.00 11 0 0.00 USD 1. 0.00 12 0 0.00 USD 1. 0.00 13 0 0.00 USD 1. 0.00 14 0 0.00 USD 1. 0.00 15 0 0.00 USD 1. 0.00 16 0 0.00 USD 1. 0.00 17 0 0.00 USD 1. 0.00 18 0 0.00 USD 1. 0.00
Total 0.00
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar
USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar AirfareAirfareAirfareAirfareUSD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar USD - US dollar
Disconnected EntryAn Excel template is available for users to download and use for disconnected entry.To submit the spreadsheet expense report for full validation and approval, users simplyupload it into Oracle Self-Service Expense once they are online again.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 94
Entering Project-Related Expense Reports in OraclePayables
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related ExpenseReports in Oracle Payables
Entering Project-Related ExpenseReports in Oracle Payables
Expense Reports Entered in Oracle PayablesNote the following when using Oracle Payables to enter project related expenses:
• Enter project-related expense reports in the Invoices Workbench.• Project-related Expense Reports cannot be entered in Expense Reports window.• The employee must be set up as a Supplier.• Select Expense Report as the invoice type.• Enter the project-related information in the same way as a project-related Supplier
Invoice.• The Project Expense Report Account Generation is called to build the expense
account.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 95
Integrating with Oracle Manufacturing
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Integrating with Oracle ManufacturingIntegrating with Oracle Manufacturing
OracleOracleManufacturingManufacturing
Oracle ProjectsOracle Projects
Project manufacturing costsProject manufacturing costs
Oracle Project ManufacturingOracle Projects integrates with Oracle Manufacturing to provide Oracle ProjectManufacturing, a solution for companies that manufacture products using projects orcontracts.When you use Oracle Projects as a part of Project Manufacturing, it acts as a costrepository for manufacturing-related activities from other products in the ProjectManufacturing suite. This also allows you to:
• Set up the WBS for a manufacturing project in Oracle Projects.• Track all manufacturing costs by project and task in Oracle Projects.• Import all manufacturing costs to Oracle Projects using the Activity Management
Gateway (AMG).• Charge project costs from inventory and work in process to a project and task.• Include project costs from manufacturing and distribution in your budget to actual
cost analysis in Oracle Projects.When costs are incurred in Oracle Manufacturing that are related to a project, the CostCollector process in Oracle Cost Management passes those costs to Oracle Projects.Oracle Projects imports the costs using the Transaction Import Process.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 96
Integrating with Oracle Inventory
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Integrating with Oracle InventoryIntegrating with Oracle Inventory
Issues andreceipts
Transaction import interface table
Costprocessor
Oracle ProjectsOracle Projects
Costedtransactions
Oracle InventoryOracle Inventory
Costcollector
Interface to OracleProjects
Transactionimport
Correcttransaction
Expenditure
Oracle Inventory IntegrationOracle Projects integration with Oracle Inventory allows you to:
• Enter inventory transactions in Oracle Inventory and import them to OracleProjects.
• Order and receive items into inventory before assigning them to a project, thenassign the items to a project as they are taken out of or received into OracleInventory.
When you enter project-related transactions in Oracle Inventory, you enter the projectinformation on the source transaction. Oracle Inventory and Oracle Projects carry theproject information through from the Issue To or Receipt From transaction in OracleInventory to the project expenditure in Oracle Projects.The above flowchart shows the flow of project-related inventory transactions in a non-manufacturing environment. You import the transactions to Oracle Projects asaccounted and costed. The cost distribution cannot be modified in Oracle Projects.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 97
Section 6 Project-Related Transactions in PO and AP
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 6Project-Related Transactions
in PO and AP
Section 6Project-Related Transactions
in PO and AP
This section includes the following items:• Tracking requisitions and purchase orders• Commitment• Entering project-related transactions in PO and AP• Entering project-related requisitions• Entering project-related purchase orders• Entering project-related supplier invoices• Auditing supplier invoices from AP
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 98
Project-Related Transactions in PO and AP
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project-Related Transactionsin PO and AP
Project-Related Transactionsin PO and AP
Collect costs
Enter preapproved expenditures
Enter Reqs/ POs in
PO
Enter Reqs/ POs in
PO
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
InterfaceImport to
G/LEnter
supplier invoices
External transactionsEnter Time & Expenses
Baseline budget
Enter budget
Transaction import
Upload
Enter project
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 99
Tracking Requisitions and Purchase Orders
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Tracking Requisitionsand Purchase OrdersTracking Requisitionsand Purchase Orders
You can record project-related requisitions andpurchase orders in order to track committed costs.• Committed costs are outstanding expenses you
have not yet incurred but expect (commit) to incurin the future.
• Commitments refer to outstanding requisitions.• Obligations refer to outstanding purchase orders.• Some companies include requisitions in the
committed costs amount.
You can record project-related requisitions andpurchase orders in order to track committed costs.• Committed costs are outstanding expenses you
have not yet incurred but expect (commit) to incurin the future.
• Commitments refer to outstanding requisitions.• Obligations refer to outstanding purchase orders.• Some companies include requisitions in the
committed costs amount.
What Is the Total Cost?The total cost is the cost that project managers want to track to have an overall view ofproject status. To calculate the total cost, use the following formula:Total Cost = Committed Costs + Actual Costs
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 100
Commitments
Copyright Oracle Corporat ion, 2000. All rights reserved.®
CommitmentsCommitments
Enterrequisition
Create purchaseorder
Createsupplierinvoice
Collect costin OracleProjects
Committed costs Actual costs
OracleOraclePayablesPayables
OracleOracleProjectsProjects
OracleOraclePurchasingPurchasing
Viewing CommitmentsYou can view commitment amounts online using Project Status Inquiry (PSI).
• You can drill down to Oracle Purchasing to see supporting commitment details forthe commitment summary amounts.
• You can drill down from the Task Status window in PSI to the Oracle PayablesInvoice Overview window.
• Oracle Projects provides views for tables in Oracle Purchasing and Oracle Payablesto help you easily report committed costs for a project.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 101
Entering Project-Related Transactions in PO and AP
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related Transactions inPO and AP
Entering Project-Related Transactions inPO and AP
You enter the same information for project-relatedtransactions in PO and AP as you do for transactionsentered in Oracle Projects:• Project number• Task number• Expenditure type• Expenditure organization• Expenditure item date• Quantity
You enter the same information for project-relatedtransactions in PO and AP as you do for transactionsentered in Oracle Projects:• Project number• Task number• Expenditure type• Expenditure organization• Expenditure item date• Quantity
Expenditure TypeTypes with expenditure class of Supplier Invoices are used in PO and AP.
Expenditure Organization• Organization that is ordering or incurring the expense• Can be used to specify organizations other than project organization; particularly
used for indirect projects
Expenditure Item DateFor requisitions and purchase orders, the date that you expect to incur the expense forthe goods or services that you are requesting. For invoices, the date that you incur thecharge.
QuantityQuantity of goods or services that you are charged for (applicable only to supplierinvoices).
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 102
Entering Project-Related Transactions in PO and AP
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related Transactions inPO and AP
Entering Project-Related Transactions inPO and AP
When you enter project related transactions:• All project information that you enter in PO and AP
is validated online using the charge controlsdefined in Oracle Projects.
• You can enter project-related and nonproject-related lines on the same document.
• The GL accounts for the project-relatedtransactions are automatically determined fromthe project information that you enter usingAccount Generator.
When you enter project related transactions:• All project information that you enter in PO and AP
is validated online using the charge controlsdefined in Oracle Projects.
• You can enter project-related and nonproject-related lines on the same document.
• The GL accounts for the project-relatedtransactions are automatically determined fromthe project information that you enter usingAccount Generator.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 103
Default Project Information
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Default Project InformationDefault Project Information
All project information is held at the distribution-linelevel. You can enter default information at a higherlevel to speed entry.
All project information is held at the distribution-linelevel. You can enter default information at a higherlevel to speed entry.
Req. HeaderReq. LineDistribution
Line
PO HeaderPO Line
PO ShipmentDistribution
Line
DistributionLine
InvoiceBatch
RequisitionsRequisitions Purchase OrdersPurchase Orders Supplier InvoicesSupplier Invoices
Default entryDefault entryNo entry allowedNo entry allowedDirect entry; information is held at this levelDirect entry; information is held at this level
Default InformationRequisition and PO defaults are session defaults.Supplier invoice defaults are stored on the invoice and are retained when you requerythe invoice.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 104
Entering Project-Related Requisitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-Related RequisitionsEntering Project-Related Requisitions
EnterEnterrequisitionrequisition
Create purchaseorder
Createsupplierinvoice
Collect costin OracleProjects
OracleOraclePayablesPayables
OracleOracleProjectsProjects
OracleOraclePurchasingPurchasing
Project-Related Requisitions in Oracle PurchasingYou enter project-related requisitions in Oracle Purchasing using the Requisitionswindow.You approve and process project-related requisitions as you do nonproject-relatedrequisitions.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 105
Entering Project-Related Purchase Orders
Copyright Oracle Corporat ion, 2000. All rights reserved.®
CreateCreatepurchase orderpurchase order
Entering Project-RelatedPurchase Orders
Entering Project-RelatedPurchase Orders
Enterrequisition
Createsupplierinvoice
Collect costin OracleProjects
OracleOraclePayablesPayables
OracleOracleProjectsProjects
OracleOraclePurchasingPurchasing
Project-Related Purchase Orders in Oracle PurchasingYou can create project-related purchase orders using one of these methods:
• AutoCreate the purchase order from the requisition.– Project and GL account information is copied from the requisition.
• Enter standard purchase orders.• Enter blanket releases against agreement purchase orders.
You approve and process project-related purchase orders as you do nonproject-relatedpurchase orders.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 106
Entering Project-Related Supplier Invoices
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Entering Project-RelatedSupplier Invoices
Entering Project-RelatedSupplier Invoices
Enterrequisition
Create purchaseorder
CreateCreatesuppliersupplierinvoiceinvoice
Collect costin OracleProjects
OracleOraclePayablesPayables
OracleOracleProjectsProjects
OracleOraclePurchasingPurchasing
Project-Related Supplier Invoices in Oracle PayablesYou can create project-related supplier invoices using one of these methods:
• Match the invoice to the purchase order.– Project and GL account information is copied from the purchase order.
• Enter invoices directly using the Enter Invoices form.• Create invoices using project-related distribution sets.
– You can use project-related distribution sets for project costs that recur overtime.
You approve and process project-related invoices as you do nonproject-relatedinvoices.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 107
Interfacing Supplier Invoices to Oracle Projects
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Interfacing Supplier Invoicesto Oracle Projects
Interfacing Supplier Invoicesto Oracle Projects
Create supplierinvoice
Collect cost inOracle Projects
Approveinvoices
Post invoices Interface SIfrom Payables
OracleOraclePayablesPayables
OracleOracleProjectsProjects
Project-Related Supplier InvoicesYou must approve and post project-related supplier invoices before you can interfacethem to Oracle Projects.You can then interface supplier invoices to Oracle Projects. You run the InterfaceSupplier Invoices from Payables process in Oracle Projects. Each invoice becomes anexpenditure; each invoice distribution becomes an expenditure item and a costdistribution line. The amounts and GL account information are copied from AP toOracle Projects.You can use the Supplier Invoice Interface Audit Report to audit supplier invoicestransferred from AP to Oracle Projects. The report lists distribution-line detailtransferred from Oracle Payables to Oracle Projects.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 108
Section 7 Multi-Currency Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 7Multi-Currency Transactions
Section 7Multi-Currency Transactions
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 109
Multicurrency Transaction Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionOverview
Multicurrency TransactionOverview
What is a Multicurrency Transaction (MCT)?
A Multicurrency Transaction is a transaction which isautomatically converted into different currencyamounts for reimbursement, accounting, invoicing, orproject reporting purposes.
What is a Multicurrency Transaction (MCT)?
A Multicurrency Transaction is a transaction which isautomatically converted into different currencyamounts for reimbursement, accounting, invoicing, orproject reporting purposes.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 110
Multicurrency Transaction Business Need
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionBusiness Need
Multicurrency TransactionBusiness Need
Many enterprises manage projects that spancountries and currencies. To enable projectmanagement to manage their projects, and financialmanagement to account for the project activitieseffectively, Oracle Projects must be able to incur andimport cost transactions in any currency.
Many enterprises manage projects that spancountries and currencies. To enable projectmanagement to manage their projects, and financialmanagement to account for the project activitieseffectively, Oracle Projects must be able to incur andimport cost transactions in any currency.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 111
Multicurrency Transaction Features
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionFeatures
Multicurrency TransactionFeatures
The Multicurrency Transaction functionality allowsthe user to:• Incur transactions in any currency• Import transactions in any currency• Provide different project rate types, rate dates, and
exchange rates for transactions• Display functional, transaction, project, and
receipt currency amounts for actual costs andcommitments for both raw and burdened costs
• Report displaying transaction currency and/orfunctional currency when appropriate
The Multicurrency Transaction functionality allowsthe user to:• Incur transactions in any currency• Import transactions in any currency• Provide different project rate types, rate dates, and
exchange rates for transactions• Display functional, transaction, project, and
receipt currency amounts for actual costs andcommitments for both raw and burdened costs
• Report displaying transaction currency and/orfunctional currency when appropriate
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 112
Multicurrency Transaction Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionDefinitions
Multicurrency TransactionDefinitions
Receipt CurrencyExpense Reports: The currency in which anemployee incurs a foreign currency expensereport item (physical receipt).
Reimbursement CurrencyExpense reports: The currency in which anemployee wishes to be reimbursed for a particularexpense report (equivalent to TransactionCurrency).
Transaction CurrencyFor all non-expense report expenditures, thecurrency in which a transaction cost is incurred.
Receipt CurrencyExpense Reports: The currency in which anemployee incurs a foreign currency expensereport item (physical receipt).
Reimbursement CurrencyExpense reports: The currency in which anemployee wishes to be reimbursed for a particularexpense report (equivalent to TransactionCurrency).
Transaction CurrencyFor all non-expense report expenditures, thecurrency in which a transaction cost is incurred.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 113
Multicurrency Transaction Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionDefinitions
Multicurrency TransactionDefinitions
Functional CurrencyThe functional currency of the Set of Books (SOB)associated with a transaction for accountingpurposes. For costing, the expenditure functionalcurrency is derived from the SOB associated withthe expenditure Operating Unit (OU).
Project CurrencyThe common currency into which all transactionsfor a particular project are converted for costing,revenue recognition, WIP management, andproject summarization. In R11i, project currency =Project OU Functional Currency.
Functional CurrencyThe functional currency of the Set of Books (SOB)associated with a transaction for accountingpurposes. For costing, the expenditure functionalcurrency is derived from the SOB associated withthe expenditure Operating Unit (OU).
Project CurrencyThe common currency into which all transactionsfor a particular project are converted for costing,revenue recognition, WIP management, andproject summarization. In R11i, project currency =Project OU Functional Currency.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 114
Multicurrency Transaction Definitions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionDefinitions
Multicurrency TransactionDefinitions
Exchange Rate TypeThe specification of the source of an exchangerate. For example, a corporate exchange rate or auser exchange rate.
Exchange Rate DateA new implementation option for OUs thatdetermines the exchange rate date for atransaction. Users may choose either PA PeriodEnding Date or Expenditure Item Date.
Exchange Rate TypeThe specification of the source of an exchangerate. For example, a corporate exchange rate or auser exchange rate.
Exchange Rate DateA new implementation option for OUs thatdetermines the exchange rate date for atransaction. Users may choose either PA PeriodEnding Date or Expenditure Item Date.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 115
Multicurrency Transaction Currency Conversion
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionCurrency ConversionMulticurrency TransactionCurrency Conversion
PA Expenditure Item
AP Distribution Line
GL JE Line
ReceiptCurrency
CostFunctionalCurrency
CostProjectCurrency
MRC Item
CostCostReportingReportingCurrencyCurrency
CostTransactionCurrency
ReimbursementCurrency
Conversion
ReimbursementCurrency
Conversion
FunctionalCurrency
Conversion
FunctionalCurrency
Conversion
ProjectCurrency
Conversion
ProjectCurrency
Conversion
MultipleReportingCurrency
Conversion
MultipleReportingCurrency
Conversion
Currency ConversionWhen you enter transactions that originated in a currency different from the functionalcurrency or project currency, Oracle Projects must convert the transaction amount tothe functional and project currencies. Oracle Projects converts currency during thecosting program for pre-approved batches and during Transaction Import for externaltransactions.To convert foreign currency transactions to the functional and project currencies,Oracle Projects must first determine the exchange rate type and exchange rate date.These attributes are used to obtain a conversion rate. Values for these currencyattributes can be entered or can default from the task, project, or systemimplementation options. The defaulting logic varies depending on whether or not thefunctional currency and project currency are the same. For defaulting logic details seethe Oracle Projects User’s Guide.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 116
Multicurrency Transaction Example
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency TransactionExample
Multicurrency TransactionExample
A Japanese employee works in UK on a US ownedproject.A Japanese employee works in UK on a US ownedproject.
CostTransactionCurrency
CostFunctionalCurrency
USD
ReceiptCurrency
JPYGBPJPY
ReimbursementCurrency Conversion
ReimbursementCurrency Conversion
Functional CurrencyConversion
Functional CurrencyConversion
TransactionsThe Japanese employee enters expenditures as follows:
• Timecard entries are recorded in JPY at the employee’s cost rate.• Expense report entries are recorded in both GBP and JPY and are to be reimbursed
in JPY.• All expenditures are charged directly to the US project.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 117
Implementation Options
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Implementation OptionsImplementation Options
Implementation Options(N) Setup—>System —>Implementation Options
Currency FieldsYou can specify currency conversion attribute defaults at the operating unit level. Thecurrency region of the Implementation Options window specifies the following:
• Functional Currency - Display-only field that shows the functional currency ofyour company's set of books. The operating unit assigned to your loginresponsibility determines the functional currency.
• Exchange Rate Date Type - The date that will be used to determine the conversionrate (either the expenditure item date or the PA period end date).
• Exchange Rate Type - The exchange rate type to be used for conversion.Conversion Rate Types are defined in Oracle General Ledger.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 118
Project Definition
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Project DefinitionProject Definition
Project Cross Charge Setup(N) Projects (B) Find (B) Open (B) Detail (with Cross Charge option selected)
Project Currency AttributesThe Project Currency Attributes are optional default values. The attributes you selectare displayed as the defaults during expenditure entry, and are used as defaults forimported transactions. During project and task setup, the values you enter are copied toall the underlying tasks in the project work breakdown structure.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 119
Task Details
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Task DetailsTask Details
Task Cross Charge Setup(N) Projects (B) Find (B) Open (B) Detail (with Tasks option selected)Find the appropriate task and choose the Cross Charge option.
Task Currency AttributesYou can optionally override the values for the project at the task level. During projectand task setup, the values you enter are copied to all the underlying tasks in the projectwork breakdown structure.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 120
Expenditure Entry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Expenditure EntryExpenditure Entry
Expenditures(N) Expenditure—>Pre-Approved Batches —>Enter
Currency Fields for ExpendituresIf you are entering an expense report, you can specify any Reimbursement Currency.You specify one reimbursement currency for the entire expenditure (rather than foreach expenditure item).
Currency Fields for Expenditure Items• Project Rate Type, Project Rate Date, Project Exchange Rate:
– If the project currency is the same as the functional currency, these fields aredisplay-only. They display the same values as the functional currency attributefields.
– If the project currency is not the same as the functional currency, you can enterthese currency attributes.
• Receipt Currency, Receipt Amount - For expense report expenditures, the currencyin which the expenditure item originally occurred, amount of receipt, and exchangerate to convert the receipt currency to the reimbursement currency.
• Reimbursement Currency - For expense reports only.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 121
Multicurrency Expense Reports
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency Expense ReportsMulticurrency Expense Reports
Multicurrency expense report entry:1. Enter required project, task, and expenditure
information.2. Enable currency folder regions.3. Enter reimbursement currency.4. Enter quantity.5. Enter receipt currency, receipt amount, and receipt
exchange rate.
Multicurrency expense report entry:1. Enter required project, task, and expenditure
information.2. Enable currency folder regions.3. Enter reimbursement currency.4. Enter quantity.5. Enter receipt currency, receipt amount, and receipt
exchange rate.
Multicurrency Expense ReportsNote the following regarding multicurrency expense report entry:
• Only one reimbursement currency is permitted per expense report.• The functional currency attributes are defaulted at the expenditure and expenditure
item level. No overrides are permitted.• The reimbursement (transaction) currency defaults to the expenditure item from the
expenditure header. No overrides are permitted.• If receipt currency does not equal the reimbursement currency, then the receipt
amount and rate are required. In this case, quantity is equal to receipt amounttimes receipt rate and is calculated by the system.
• If the reimbursement currency equals the functional currency, then all expendituretypes are permitted.
• If the reimbursement currency does not equal the functional currency, then onlyexpenditure types that do not use cost rates are permitted.
• If the expenditure type has a cost rate, then the receipt attributes are disabled.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 122
Multicurrency Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Multicurrency ExpendituresMulticurrency Expenditures
Multicurrency expenditures (not expense reports):1. Enter required project, task, and expenditure
information.2. Enter quantity.3. Enable currency folder regions.4. Enter transaction currency when applicable.
Multicurrency expenditures (not expense reports):1. Enter required project, task, and expenditure
information.2. Enter quantity.3. Enable currency folder regions.4. Enter transaction currency when applicable.
Multicurrency ExpendituresNote the following regarding multicurrency expenditure entries which are not tied to anexpense report:
• The transaction currency should be the currency in which the transaction occurred.• If the project currency is not the same as the functional currency, you can enter the
project rate type, project rate, and project rate date.• If the transaction currency is not the same as the functional currency, you can enter
the functional rate type, functional rate, and functional rate date.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 123
Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ImportTransaction Import
Expenditures(N) Expenditures—>Transaction Import —>Review Transactions
Currency Conversion Attributes for Imported TransactionsWhen transactions are imported that originated in a currency different from thefunctional currency or project currency, Oracle Projects must convert the transactionamount to those currencies.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 124
Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ImportTransaction Import
Functional Currency Rate Typeand Rate Date
Project Currency RateType and Rate Date
The following hierarchy is used:1 User-entered value2 Default value from the lowest
task3 Default value from the project4 Default value from the
expenditure operating unit'simplementation options
The functional currencyattributes are used.
Project and functional currencies are the same.Project and functional currencies are the same.
Functional Currency Equals Project CurrencyIf the functional currency of the operating unit that incurred the cost (the expenditureoperating unit) is equal to the functional currency of the operating unit that owns theproject to which the cost is charged (the project operating unit), the above logic is usedto determine the currency conversion attributes used in converting the transactionamounts from the transaction currency.The attributes are used to obtain a conversion rate, which is used to convert thetransaction currency amount to the functional currency. Since the functional currency isequal to the project currency, the project currency amount is equal to the functionalcurrency amount.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 125
Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ImportTransaction Import
Differing project and functional currenciesDiffering project and functional currencies
Functional CurrencyRate Type and RateDate
Project Currency Rate Type andRate Date
The followinghierarchy is used:1 User-entered value2 Default value from
the expenditureoperating unit'simplementationoptions
The following hierarchy is used:1 User-entered value2 Default value from the lowest task3 Default value from the project4 For the rate type, the default value
from the project operating unit'simplementation options.For the rate date, the default valuefrom the expenditure operatingunit's implementation options.
Functional Currency Does Not Equal Project CurrencyIf the functional currency for the transaction is not equal to the project currency, theabove logic is used to determine the currency conversion attributes.The functional currency attributes are used to obtain a conversion rate, which is used toconvert the transaction currency amount to the functional currency. The projectcurrency attributes are used to obtain a conversion rate, which is used to convert thetransaction currency amount to the project currency.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 126
Expenditure Inquiry
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Expenditure InquiryExpenditure Inquiry
Expenditures(N) Expenditures—>Expenditure Inquiry —>Project (B) Find
Currency FieldsThe functional, project, transaction, and receipt currency fields can be displayed asneeded using the folder tools.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 127
Cost Distribution Lines
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Cost Distribution LinesCost Distribution Lines
Expenditures(N) Expenditures—>Expenditure Inquiry—>Project (B) Find (B) Item Detail
Cost Distribution LinesThe Cost Distribution Lines window has regions to display the functional currencyamounts, the project currency amounts, and the transaction currency amounts.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 128
Practice 5-2 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 5-2 OverviewPractice 5-2 Overview
• Entering pre-approved usage logs• Entering pre-approved timecards• Submitting and releasing expenditures
• Entering pre-approved usage logs• Entering pre-approved timecards• Submitting and releasing expenditures
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 129
Section 8 Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 8Transaction Import
Section 8Transaction Import
This section includes the following items:• Basic business requirements• Transaction import functions• Transaction source• Transaction import flow• Running transaction import• Viewing imported transactions• Auditing imported transactions• Review of transaction import
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 130
Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction ImportTransaction Import
Collect costs
Enter preapproved expenditures
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
External transactions
Enter Time
Baseline budget
Enter budget
Transaction import
Transaction import
Upload
Enter project
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 131
Basic Business Requirements
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Basic Business RequirementsBasic Business Requirements
Client costClient costcollection systemcollection system
ElectronicElectronicdata exchangedata exchange
OracleOracleProjectsProjects
What Is Transaction Import?Transaction Import is an open interface that enables you to load transactions fromexternal cost collection systems into Oracle Projects. Transaction Import createspreapproved expenditure items from transaction data entered in external cost collectionsystems.Examples of external cost collection systems include:
• Timecard entry systems• Expense report entry systems• Electronic data collection systems for asset usage• Payroll systems that calculate complex transactions• Fixed-assets systems that calculate depreciation• Manufacturing systems such as Inventory and WIP
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 132
Transaction Import Functions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction Import FunctionsTransaction Import Functions
When you import transaction information, OracleProjects:• Records the transaction details and the source of
the imported transactions• Validates the transaction information• Reports any exceptions• Creates transactions for all valid records
When you import transaction information, OracleProjects:• Records the transaction details and the source of
the imported transactions• Validates the transaction information• Reports any exceptions• Creates transactions for all valid records
Transaction ImportYou can import costed or uncosted, accounted or unaccounted, and adjustedtransactions into Oracle Projects. Adjustments are transactions with negativequantities. Unmatched import adjustments do not reverse any transaction in OracleProjects. All other adjusting transactions in Oracle Projects must reverse anothertransaction.You can use Transaction Import to import transactions that originate in any currency.The original currency and amount of each transaction is stored if the transactioncurrency is different from the project and/or functional currency.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 133
Transaction Import Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Rejectedtransactions
Transaction Import FlowTransaction Import Flow
Validtransaction?
Cost collectionsystems 1,2,3,...
Filters 1,2,3,... toload transactions
Transactioninterface table
Read pendingtransactions
NoNo
YesYesCreate expenditure
records
Expenditurerecords
Transaction ImportTransaction Import
Delete transactionrecords
Reporttransactions
Expenditurebatches created
Oracle ProjectsOracle Projects
Transaction Import Process• Read pending transactions.
– Rejected and accepted items are not processed.– Transactions are grouped into expenditures using the transaction source and
other criteria based on the type of transaction.• Timecards and Expense Reports: Employee, week ending date, batch• Usage: Employee/organization, week ending date, batch
• Validate transactions.If one item in the expenditure fails validation, then no items for that expenditureare imported. All items are marked as rejected.
• Create expenditure records.Create released, preapproved expenditure batches, expenditures, and expenditureitems.
• Purge accepted transactions.If the transaction source is purgeable, then accepted rows are deleted.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 134
Transaction Source
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Transaction SourceTransaction Source
A transaction source is defined duringimplementation to identify each source of importedtransactions.
A transaction source is defined duringimplementation to identify each source of importedtransactions.
Transaction Source
Expenditure TypeClass Costed Purgeable Description
Faxed timecard
Straight Time No Faxed timecard
Yes
PBX Usage Yes Yes Telephoneusage log
Defining Transaction SourceWhen you set up each transaction source, you select options that determine howtransactions are processed by Transaction Import.The following are some of the fields and actions you can control when you choosetransaction source options:
• the default expenditure type class• whether Projects calculates raw cost amounts• whether Projects calculates burden amounts• whether Projects interfaces amounts to GL and AP• whether Projects imports the expenditure organization for employee transactions• whether to allow manual adjustments before transaction import• whether duplicate reference IDs are allowed within a transaction source• whether the transaction can be reversed or adjusted after it is imported• whether Projects calculates MRC reporting currency amounts• whether Projects performs cross charge processing
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 135
Costed Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Costed TransactionsCosted Transactions
If the Import Raw Cost Amounts option is selected fora transaction source, it indicates that the transactionshave already been costed.For these transactions:• Oracle Projects does not recalculate the raw cost.• You can perform accounting for these
transactions.• You can perform burdening for these transactions.
If the Import Raw Cost Amounts option is selected fora transaction source, it indicates that the transactionshave already been costed.For these transactions:• Oracle Projects does not recalculate the raw cost.• You can perform accounting for these
transactions.• You can perform burdening for these transactions.
Costed and Uncosted ItemsWhen importing costed items you must provide the quantity and the raw cost. OracleProjects does not recalculate the raw cost.When importing uncosted items you provide only the quantity. Oracle Projects coststhe transactions like other transactions based on the cost multiplier and the quantity.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 136
Accounted Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Accounted TransactionsAccounted Transactions
If the Raw Cost GL Accounted option is selected for atransaction source, it indicates that the transactionsare accounted.For these transactions, Transaction Import:• Creates cost distribution lines with a status of
Received• Creates expenditures and expenditure items that
are identified as accounted• Does not call any extensions• Does not create any related items• Does not allow you to import related items
If the Raw Cost GL Accounted option is selected for atransaction source, it indicates that the transactionsare accounted.For these transactions, Transaction Import:• Creates cost distribution lines with a status of
Received• Creates expenditures and expenditure items that
are identified as accounted• Does not call any extensions• Does not create any related items• Does not allow you to import related items
Accounted and Unaccounted ItemsFor accounted items the raw cost and GL accounts have already been determined andposted to general ledger by the external system. You must provide the debit and creditcode combination ID for each imported transaction.When loading unaccounted items (GL account has not been determined), theTransaction Import Process:
• Calls any transaction control extensions that you have defined• Calculates costs for uncosted items• Determines the GL account to which the cost should be posted
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 137
Burdening Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Burdening TransactionsBurdening Transactions
When importing transactions you can:• Import the burdened cost as a value on the
expenditure item• Import the burdened cost as a separate burden
transaction expenditure item• Allow Oracle Projects to calculate the burdened
costs
When importing transactions you can:• Import the burdened cost as a value on the
expenditure item• Import the burdened cost as a separate burden
transaction expenditure item• Allow Oracle Projects to calculate the burdened
costs
Importing Burden Transaction Expenditure ItemsBurden transactions have raw costs and quantities of zero and only burden amountsassociated with the transaction. You identify burden transactions by assigning them anexpenditure type class of Burden Transactions.There is no predefined transaction source for burden transactions. You can create anew transaction source with a default expenditure type class of Burden Transaction andthen use this transaction source to import burden transactions.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 138
Foreign Currency Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Foreign Currency TransactionsForeign Currency Transactions
When transactions are imported that originated in acurrency different from the functional currency or theproject currency, Oracle Projects must convert thetransaction amounts into those currencies.
When transactions are imported that originated in acurrency different from the functional currency or theproject currency, Oracle Projects must convert thetransaction amounts into those currencies.
TransactionTransaction
CurrencyCurrency
Functional CurrencyFunctional Currency
Project CurrencyProject Currency
Currency ConversionTo convert foreign currency transactions, Oracle Projects must determine an exchangerate type and exchange rate date for each transaction. If these values are not providedin the import record, Oracle Projects uses defaulting logic to derive their values. Thedefaulting values may be derived from the task, the project, the implementation optionsfor the expenditure operating unit, or the implementation options for the projectoperating unit.The defaulting hierarchy varies depending on whether or not the functional currencyand project currency are the same. For details, see the Oracle Projects User’s Guide.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 139
Descriptive Flexfield Option
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Descriptive Flexfield OptionDescriptive Flexfield Option
You have the option to transfer descriptive flexfieldson supplier invoices and expense reports betweenOracle Payables and Oracle Projects.When this option is enabled, Transaction Import:• Verifies that valid values are transferred• Verifies that all required flexfields are populated• Generates any appropriate error messages
You have the option to transfer descriptive flexfieldson supplier invoices and expense reports betweenOracle Payables and Oracle Projects.When this option is enabled, Transaction Import:• Verifies that valid values are transferred• Verifies that all required flexfields are populated• Generates any appropriate error messages
Descriptive Flexfield OptionTo enable the Descriptive Flexfield Option, set the profile option PA: Transfer DFFwith AP to Yes. The default mapping for descriptive flexfields is from ATTRIBUTE1to ATTRIBUTE1, ATTRIBUTE2 to ATTRIBUTE2, etc. Using client extensions youcan determine your own attribute mapping rules between two descriptive flexfields, ifdesired.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 140
Running Transaction Import
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Running Transaction ImportRunning Transaction Import
Submit Transaction Import by:• Transaction source (required)• Batch name (optional)Review the results of the output report• Rejected transactions and rejection reason• Created expenditure batches and number of
expenditures
Submit Transaction Import by:• Transaction source (required)• Batch name (optional)Review the results of the output report• Rejected transactions and rejection reason• Created expenditure batches and number of
expenditures
Running Transaction ImportWhen you submit Transaction Import, you must identify the source of the transactionthat you want to import. The source can be any transaction source you defined or anysource predefined by Oracle Projects.The list of values for the transaction source parameter displays all the transactionsources in the PA_TRANSACTION_SOURCES table. Any transaction sources thathave pending records in the transaction interface table are marked with an asterisk inthe list of values.Note: You can run multiple, concurrent transaction imports by source and batch name.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 141
Viewing Rejected Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Viewing Rejected TransactionsViewing Rejected Transactions
Use one of these methods to view rejectedtransactions:• Review Transaction window: You can search for
rejected transactions by transaction source orbatch name.
• Transaction Import Exception Report: For eachrejected transaction, the report displays the keyfields and the rejection reason code.
Use one of these methods to view rejectedtransactions:• Review Transaction window: You can search for
rejected transactions by transaction source orbatch name.
• Transaction Import Exception Report: For eachrejected transaction, the report displays the keyfields and the rejection reason code.
Rejected RecordsTransaction records that fail validation remain in the interface table. If any oneexpenditure item in the expenditure fails validation, Oracle Projects rejects the entireexpenditure and updates each expenditure item in the expenditure with a status of R(Rejected). However, only the expenditure item that failed validation appears on theexception report. Expenditures within the same batch that pass validation areinterfaced to Oracle Projects.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 142
Correcting Rejected Rows
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Correcting Rejected RowsCorrecting Rejected Rows
You can correct rejected rows in two ways:• Use the Review Transactions window to correct
the data online.• Delete the rejected rows, correcting the data in the
source system, and then reload the data into theinterface table.
You can correct rejected rows in two ways:• Use the Review Transactions window to correct
the data online.• Delete the rejected rows, correcting the data in the
source system, and then reload the data into theinterface table.
Rejection Reason CodesTransaction Import may reject imported transactions for a variety of reasons. You canobtain a list of all rejection reasons from the Oracle Projects Technical ReferenceManual.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 143
Review Transactions Window
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Review Transactions WindowReview Transactions Window
Review Transactions Window(N) Expenditures—>Preapproved Batches —>Review
Window UsageYou can view and correct transactions with the Review Transactions window. OracleProjects automatically updates the status of corrected items and all other transactions inthe same expenditure to P (Pending).You can also use the Review Transaction window to create one or more newtransactions without loading them from the feeder system. This feature was designedto expedite minor additions to expenditure batches, primarily for testing purposes.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 144
Auditing Imported Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Auditing Imported TransactionsAuditing Imported Transactions
Each imported transaction is uniquely identified by:• Transaction source• Original transaction reference• Transaction interface ID (if the transaction source
allows duplicate system references)You can use this unique identifier to reference theoriginal transaction in the external system.
Each imported transaction is uniquely identified by:• Transaction source• Original transaction reference• Transaction interface ID (if the transaction source
allows duplicate system references)You can use this unique identifier to reference theoriginal transaction in the external system.
Audit TableWhen you update rejected or pending transactions in the interface table, the originaland revised transactions are stored in the PA_TRX_INTERFACE_AUDIT_ALL table.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 145
Viewing Imported Transactions
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Viewing Imported TransactionsViewing Imported Transactions
You can view and report on imported transactions asyou do all other transactions in Oracle Projects.Use the following report and windows:• Preapproved Expenditure Entry Audit report• Appropriate Preapproved Expenditures windows
– Enter preapproved batches– Review preapproved batches
• Expenditure Inquiry (search criteria includestransaction source)
You can view and report on imported transactions asyou do all other transactions in Oracle Projects.Use the following report and windows:• Preapproved Expenditure Entry Audit report• Appropriate Preapproved Expenditures windows
– Enter preapproved batches– Review preapproved batches
• Expenditure Inquiry (search criteria includestransaction source)
Viewing Imported TransactionsTransaction Import loads transactions as pre-approved expenditure items. The batchname for an imported batch is set to <Batch Name><Interface Run ID>.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 146
Section 9 Review of Project Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Section 9Review of Project Expenditures
Section 9Review of Project Expenditures
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 147
Summary Flow
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Summary FlowSummary Flow
Collect costs
Enter preapproved expenditures
Enter preapproved expenditures
Enter Reqs/ POs in
PO
Enter Reqs/ POs in
PO
Define projects
Comprehensive online inquiry and reporting
Identifybusiness
termsand rules
Adjustments
InterfaceImport to
G/LEnter
supplier invoices
Enter supplier invoices
External transactions
Enter TimeEnter Time
Baseline budget
Enter budget
Transaction import
Transaction import
Upload
Enter project
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 148
Reviewing Project Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Reviewing Project ExpendituresReviewing Project Expenditures
You can review detailed expenditures charged to aproject using the Expenditure Items window. Twoexpenditure inquiry modes are available in OracleProjects:• Project: The Project mode expenditure inquiry
allows you to view expenditure items for a singleproject only.
• All: The All mode expenditure inquiry allows youto view expenditure items across projects (see thenext two slides).
You can review detailed expenditures charged to aproject using the Expenditure Items window. Twoexpenditure inquiry modes are available in OracleProjects:• Project: The Project mode expenditure inquiry
allows you to view expenditure items for a singleproject only.
• All: The All mode expenditure inquiry allows youto view expenditure items across projects (see thenext two slides).
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 149
Inquiry - Project Mode
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Inquiry - Project ModeInquiry - Project Mode
Project Expenditure Items(N) Expenditures—>Expenditure Inquiry —>Project (B) Find
How to Review Project Expenditures Using Project Mode OptionWhen using Project mode:
• You are required to enter a project number or project name in the Find ProjectExpenditure Items window before you can execute the query.
• If project security is implemented, you can select only projects that you are allowedto see.
Splitting Expenditure ItemsYou can split expenditure items to change its billing, capitalizable, and hold status for aportion of the original item’s quantity. You create a reversing entry for the originalexpenditure item and generate two new expenditure items, totaling the same quantity asthe original item.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 150
Inquiry - All Mode
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Inquiry - All ModeInquiry - All Mode
Expenditure Items(N) Expenditures—>Expenditure Inquiry —>All (B) Find
How to Review Project Expenditures Using All Mode OptionIn All mode expenditure inquiry:
• You are not required to enter a project number or name in the Find ExpenditureItems window. You can select other criteria such as employee name or expenditurecategory to display the expenditure items across all projects.
• No project security implementation is required to query expenditure items acrossprojects.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 151
Reporting Project Expenditures
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Reporting Project ExpendituresReporting Project Expenditures
You can use the following reports to review detailedproject expenditures:• Expenditure Details Report: Lists expenditure
details charged to a project.• Expenditure Summary Report: Lists project
expenditures summarized by employee, task, date,or expenditure type.
You can use the following reports to review detailedproject expenditures:• Expenditure Details Report: Lists expenditure
details charged to a project.• Expenditure Summary Report: Lists project
expenditures summarized by employee, task, date,or expenditure type.
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 152
Summary
Copyright Oracle Corporat ion, 2000. All rights reserved.®
SummarySummary
This lesson described how to perform these tasks:• Recording these transactions against a project to
indicate actual work performed or cost incurred:
This lesson described how to perform these tasks:• Recording these transactions against a project to
indicate actual work performed or cost incurred:
– Timecards– Expense reports– Asset usage logs– Supplier invoices
– Timecards– Expense reports– Asset usage logs– Supplier invoices
– Miscellaneous– Multicurrency– Inventory– Work in process
– Miscellaneous– Multicurrency– Inventory– Work in process
• Recording these transactions against a project toshow committed costs:– Requisitions– Purchase orders
• Recording these transactions against a project toshow committed costs:– Requisitions– Purchase orders
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 153
Practice 5-3 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 5-3 OverviewPractice 5-3 Overview
• Entering pre-approved usage logs• Entering pre-approved timecards• Submitting and releasing pre-approved
expenditures
• Entering pre-approved usage logs• Entering pre-approved timecards• Submitting and releasing pre-approved
expenditures
Copyright © Oracle Corporation, 2000. All rights reserved.
TransactionsChapter 5 - Page 154
Practice 5-4 Overview
Copyright Oracle Corporat ion, 2000. All rights reserved.®
Practice 5-4 OverviewPractice 5-4 Overview
• Creating a supplier invoice in Oracle Payables• Viewing committed cost and actual cost on your
project in Oracle Projects
• Creating a supplier invoice in Oracle Payables• Viewing committed cost and actual cost on your
project in Oracle Projects