LS1 Status @ Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May2013 24/05/2013 LSC – EN-MEF-OSS 1

LS1 Status @ Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May2013 24/05/2013LSC – EN-MEF-OSS1

Embed Size (px)

Citation preview

LSC – EN-MEF-OSS 1

LS1 Status @ Injectors

K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane

LSC 24th May2013

24/05/2013

LSC – D. Hay 2

ENPSB (1/4)

24/05/2013

The clean up campaign to remove surface & underground cables is now completed.

Installation of the underground cables is estimated to be at ~8% completion.

Cable continuity and Burndy connector tests for the Multipole power converters are ongoing.

On site preparations for the beam dump replacement project are ongoing.

Installation of electrical power sockets. Clean up campaign in the Booster basement (BTM/BTY beam

element storage).

The new PAD access control system is now fully operational. PAD functional tests successfully completed. Biometric access will commence on Monday 27th May. Installation of the D31 MAD is in progress.

Burndy conncetors

New access system

LSC – D. Hay 3

ENPSB (2/4)

24/05/2013

Replacement of the PSB lift AS-45 has started (the lift is no longer operational). The special lifting support device for the removal of the lift

motor and ancillary electrical equipment is under construction (EN-HE T.Foreste).

Works access SAS’s are currently being installed at each floor level.

Material access to the Booster’s radiation controlled areas will be via the tremie in 361 supervised by the transport and RP services. During the works, access to the booster complex will be

redirected via the BHP hall as indicated.

Lifting support installation

Access to PSB

LSC – D. Hay 4

ENPSB (3/4)

24/05/2013

2013

2014

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

2013

2014

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

PSB Hall PSB Tunnel

MAGNET TESTS

TESTS MULTIP. CONV.

General maintenance

General maintenance

Survey

MagnetsCables

Cables

LIFT

RE

PLAC

EMEN

T

MU

LTIP

. CO

NV.

TE-A

BT

Survey

Hardware commissioning and cold check out

CV

SETUP WITH BEAM

VACU

UM

RF

EN-S

TI

BE-B

I & C

O

BE-B

I & C

O

ACCE

SS

COMMISSIONING NEW ACCESS SYSTEM

Beam back from L2 to PSB 30/05/2014Beam back from PSB to PS 20/06/2014

Beam Off : 11/02/2013

CV

Survey Magnets Cable Lift &

crane CV Vacuum RF BI & CO Access EPCPowerin

gTests

Collimation (STI)

KickersSepta

LSC – D. Hay 5

ENPSB (4/4)

24/05/2013

50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Forecast

2.8

5.2

6.4

6.6

6.6

7.2

9.4

13.4

17.2

20 23.6

24.2

27.4

28.8

31.6

33.8

36.6

37.6

42 44.8

46.8

51 54.4

58.4

61.6

64.2

65.8

69.2

72 72.6

74.6

74.8

76.6

78.6

79.8

80.4

81.2

81.6

85.2

86.2

88 88 88 88 NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

Actual

2.8

5.2

6.4

6.6

6.6

7.2

9.4

13.4

17.2

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

5

15

25

35

45

55

65

75

85

95

Progress curve - PSB machine - week 21 (21/05/2013)

Prog

ress

(For

ecas

t vs A

ctua

l)

LSC – S. Mataguez 6

ENCPS (1/5)

24/05/2013

PS Tune Strip-line BPM in SS72 has been installed and aligned.

Route Goward shielding improvement program is advance, the Septum 16 External Shielding program is on study how to start 1 month earlier.

Main magnets HV tests are completed How many Main Magnets need to be refurbished?

PS Tune Strip-line

Goward road

S. Mataguez 7

ENCPS (2/5)

24/05/2013

• CV Consolidation program is on-going.– Removal of asbestos:

• HVAC TR 6 & 8 and galleries 1&3 completed (galleries 1&3 are accessible)• HVAC TR 1 & 3 and galleries 5 & 7 in progress (40%)

– Mechanical dismantling of HVAC TR 5 just started (10%)– Civil engineering activity

• HVAC TR 6 & 8 is completed• chimney 6 & 8 just started

• The 10 MHz Coarse Tuning Groups of Two 10 MHz Cavities is completedTest will be done before the water station stopped (31/05)

• PS PSS Safety and Access System Installation: – The access via Door 101 is not possible from 01/04 to 20/06– The access via Door 111 is not possible from 21/05 to 24/06

• General Maintenance of the Kickers system is on-going.

HVAC5 mechanical dismantling

Door 111 is out of service !

LSC – S. Mataguez 8

ENCPS (3/5)

24/05/2013

• Forecast– Sector PR90 will be venting in order to remove PR.BWS85 for re-

calibration and to remove the tuner of the 80MHz cavity

– Removal of SMH16 & SMH42

– Dismantling of cranes PR06 & PR20

– Start of the refurbishment of the piping of the chilled water circuit (no chilled water in PS, L2, L3)

LSC – S. Mataguez 9

EN

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

2013

2014

PS Surface

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

S1

2013

2014

Oct1(SS01-SS13)

102121

Oct2(SS14-SS26)S2 122

SYOct3

(SS27-SS39)S3 SY104

Oct4(SS40-SS51)S4 117

SYOct5

(SS52-SS64)S5 Oct6(SS65-SS76)S6 111 S7 Oct7

(SS77-SS90)112 Oct8

(SS91-SS100)S8 TT2 Line101 CRG7G5G3G1

CPS (4/5)

24/05/2013

Magnet

Civil engineering

Access CVVentil

CV water

Septa (SE)

Kickers

Collimation (STI)

Vacuum Cable EL

(pow.)Lift & crane

Powering

TestsRF Contro

lEPCFire

detection

Survey

Beam instrumenta

tion

RF

CE

CE

CE

R.Goward

Lift B269

Maintenance Sealing

Powering tests

EPC

Magnet tests

Magnet tests

MU14 MU55\57 MU75

SS15 Liberate

CE

PS PSS complex new access system commissioning

Sept.16

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

HVAC

CV water

SMH16

SEH23Dummy

SMH42

SMH57

STP

STP

Vacuum bake-outs

STP

STP

STP

EL

RF

RF

RF

RF

RF

RF RF

RF

10/07

01/05

Physics

PS Setup with BeamPS Operations Cold Check-out

Control

DSO tests

Ready for extraction 10/07/14

LSC – D. Hay 10

EN

50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Forecast

2.8

5.2

6.4

6.6

6.6

7.2

9.4

13.4

17.2

20 23.6

24.2

27.4

28.8

31.6

33.8

36.6

37.6

42 44.8

46.8

51 54.4

58.4

61.6

64.2

65.8

69.2

72 72.6

74.6

74.8

76.6

78.6

79.8

80.4

81.2

81.6

85.2

86.2

88 88 88 88 NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

Actual

2.8

5.2

6.4

6.6

6.6

7.2

9.4

13.4

17.2

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

5

15

25

35

45

55

65

75

85

95

Progress curve - PSB machine - week 21 (21/05/2013)

Prog

ress

(For

ecas

t vs A

ctua

l)CPS (5/5)

24/05/2013

LSC – D. McFarlane 11

ENSPS (1/3)

24/05/2013

• Preparation works for the Civil engineering works in TT10 have begun.– Vacuum chambers have been removed from the work area– Magnets are in the process of being removed

• EL cable campaigns are slightly ahead of schedule.– EL are currently working in BA1 (surface, shaft and 1-), BA3 and BA5– EL will be starting at BA4 next week (1 month ahead of schedule)

• The remaining 17 magnets that need to be changed (identified during the magnet tests in March) are now scheduled to be change during the 1st 2 weeks of June.

• The vertical realignment of sextant 6 is progressing well. (on schedule)

• CV will be replacing the main isolating– (starting in June) as a result the main SPS ring main will be drained from the

17th June until the 30th August. While the ring main is drained there will be no water in the fire hydrants. In order for the fire brigade to still have access to fire water at each point in the event of an emergency they are in the process of installing large water reservoirs at each point.

Water reservoir in BA1

TT10 line –dismantled

Cabling campaign in SPS

12

ENSPS (2/3)

24/05/2013 LSC - D. McFarlane

LSC – D. Hay 13

ENSPS (3/3)

24/05/2013

50 52 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Forecast

0 0 0 0 0 1.875

3.125

6.5

10.8125

13.8125

18.0625

23.875

25.625

27.6875

32.875

35.5625

37.3125

40.9375

43.625

48.5

49.625

52.625

53.1875

54.6875

58.375

62.0625

63.875

65.6875

66.875

69.9375

70.5

72.3125

76.3125

76.875

79 80.1875

81.375

86.375

90.75

93.875

94.0625

94.25

94.4375

96.5

97.3125

97.5

99.375

100

100

100

100

100

Actual

0 0 0 0 0 1.875

3.125

6.4375

10.125

12.1875

15.8125

20.6875

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

NaN

5

15

25

35

45

55

65

75

85

95

Progress curve - machine SPS - 24/05/2013

Prog

ress

(For

ecas

t vs A

ctua

l)

LSC – N. Gilbert 14

ENAD (1/2)

24/05/2013

• Buffer zone equipped with access system. TREC system installation is progress

• Vacuum:– maintenance is progressing well– Girder line 7000: : 3D layout finalized. Vacuum team now takes over for the

manufacturing of the connection elements

• Electrical activities are progressing well

• BNH06 removal - delays in coil manufacturing – 1st coil manufactured by the end of this month

• Renewal stoch. cooling power supply : commissioning could not be

completed (foreseen by the end of this month)

• Concern : cooling water is needed for the bake-outs, but a solution looks possible (discussion with EN/CV on 23/05) ! Discussions to be continued with EN/CV.

AD buffer zone

Power supply of stoch. cooling

LSC – D. Hay 15

ENAD (2/2)

24/05/2013

LSC – N. Gilbert 16

ENLEIR (1/2)

24/05/2013

• Buffer zone at the Linac is progressing well. (will be shared with LEIR)

• Reshuffling shielding blocks for new access point was

completed 2 weeks ago. • Scheduling and organizing of future bake-out (sectors 1, 2

and 5) in progress– Concerns with the chilled water availability

LSC – N. Gilbert 17

ENLEIR (2/2)

24/05/2013