EMCal Meeting CERN – July 2nd 2007 LPSC Status 1 J-F Muraz
LPSC StatusLPSC Status.
Assembly Hall.
- Removal starts and is in progress.
- Main infrastructure work will be done in November.
(floor and wall painting, services installation).
EMCal Meeting CERN – July 2nd 2007 LPSC Status 2 J-F Muraz
Strip Modules handling tool.
- Hydraulic strike ordered and delivered in next few days.
- Structure scheduled for July in our mechanical workshop.
- We do a dummy strip module (real size and weight) in order to test
this tool and the SM assembly procedure.
LPSC StatusLPSC Status.
EMCal Meeting CERN – July 2nd 2007 LPSC Status 3 J-F Muraz
LPSC StatusLPSC Status.
SM Platform.
- Detailed drawings are in progress.
- Scheduled in our mechanical workshop for December
EMCal Meeting CERN – July 2nd 2007 LPSC Status 4 J-F Muraz
LPSC StatusLPSC Status.
SM tilt over mechanism. (needed in vertical Cosmic tests design)
- Basic design is in progress.
Winch
Tilt platform
Cable
EMCal Meeting CERN – July 2nd 2007 LPSC Status 5 J-F Muraz
LPSC StatusLPSC Status.
SM tilt over mechanism. (needed in vertical Cosmic tests design)
- Conceptual design is in progress.
EMCal Meeting CERN – July 2nd 2007 LPSC Status 6 J-F Muraz
LPSC StatusLPSC Status.
Test beam Scintillators paddles:
- Done and tested.