14
Low-Level RF of BEPCII Sun YI IMAC’07 May. 11, 2007 IHEP

Low-Level RF of BEPCII

  • Upload
    zev

  • View
    52

  • Download
    0

Embed Size (px)

DESCRIPTION

Low-Level RF of BEPCII. Sun YI IMAC’07 May. 11, 2007 IHEP. Review the past one year. The Hardest and key time was from Apr.06 to Dec.06 West LLRF was used for the horizontal test and the Q0 measurement at the test room; - PowerPoint PPT Presentation

Citation preview

Page 1: Low-Level RF of BEPCII

Low-Level RF of BEPCII

Sun YI

IMAC’07May. 11, 2007

IHEP

Page 2: Low-Level RF of BEPCII

Review the past one year

• The Hardest and key time was from Apr.06 to Dec.06• West LLRF was used for the horizontal test and the Q0 meas

urement at the test room; All the Q0, both East and West SCC, are higher than the desi

gn target. ( June~Sep. 2006) The first time on the high power test of SCC in China made a

big challenge on the LLRF• LLRF installation 、 cabling 、 and calibration (Mar.~Oct. 200

6)• Commissioning 2 stations of SRF ( Oct.~Nov. 2006 )• The East station join in the beam commissioning ( Nov. 2006)• SR run with only East station ( Dec. 2006 ~ Feb. 2007)• West station was used for the e+ ring commissioning ( Feb. 2007)• Two stations have been used for physic collision run ( Apr. 2007)

Page 3: Low-Level RF of BEPCII

e+

e+ e-

e-One machine / two purposes:

1 SCC / ring physic run2 SCC / outside ring dedicate the SR users

Harmonic number 398 ( Phy.) / 402 ( SR)

by pass chamber (SR run)

West SC East SC

RF hall (E)RF hall (W)

Refrigerator/ valve box500W / 2SC Test room for SC

Down side

SR run

IP-2#hall

Frf 499.8 MHzIb 900mA/ring 300mAPb 123kw ~80kwSCC 1/ring 2Kly. 250KW/ring 2*250KWHOMs ~5kw/scQL 1.7E5 1.7E5Q0 ( 2.0MV ) 5E8 5E8 (1.5MV) 1E9 1E9

During the past one year, 2 LLRF stations have been finished, installation 、 cabling 、 calibration 、 high power test and Q0 measurement 、 commissioning SRF, now e+/e- beam run perfectly.

Page 4: Low-Level RF of BEPCII

God and the Double Interlock prevent SRF from damageHigh power INTL: cooling water & wind 、 temperature 、 Klystron & circulator, etc.LLRF INTL: quench 、 arc 、 RF power limitation 、 vacuum 、 cryogenic 、 tuner ,etc.

超导高频系统状态显示面板

紧急停机

本地 远控

控制选择

对撞 同步

运行模式

速调管

主振信号源fRF = 499.8MHz

VSWR

M

Vc set

LLRF ON

DRFB

入射功率

反射功率

门钮

P+ P-

真空e+束流

RESET

系统恢复

负载

环行器

功率

高压电源

High Power Interlock

e-束流

氦气压力

低温槽

液氦液面

LHe Flow

陶瓷窗

PLL-kly AGC

下限位

调谐器

上限位压电陶瓷

F l oop ONTuned

ALC-kly

ALC-Vc

PLL-Vc

GV

失超保护

Heater

GV

Page 5: Low-Level RF of BEPCII

Calibration Vc by 3 methods• Determine Vc by RF forwarding power P+

R/Q=95.3 QL≈2E+5 P+=13kw →Vc=1MV

• Confirm Vc by RF field inside the SCC

Q15D≈1.09E+11 P15D=90mw → Vc=1MV

• Calibration Vc by synchrotron oscillation frequency

measured result: fs=22.3KHz at Vc=0.6MV

0

cos2

p c ss

heVE

4 LRVc Q PQ

15 150.266 36.72 D DEacc Vc P Q 6

80

2 499.8 10/ 2 / 2 2.99792458 10 0.266

C C C Cacc C

eff g

V V V VE VL C f m

0

3L

dB

fQBW

Page 6: Low-Level RF of BEPCII

Beam and RF power matched in a typical SR run

Page 7: Low-Level RF of BEPCII

Vc oscillation result in the beam trip by LLRF

• 60mA e- lost at Dec.4, 2006 • RF voltage recovered and t

he oscillation disappeared after the beam lost

• Vc=0.6MV, the oscillation period=3ms

• After adjusting the ALC feedback loop parameter, this problem was cured, the beam current can be increased to 200mA in Dec.2006

• This is not the Robinson instability, I still set the cavity frequency detune angle=0 degree till 200mA

Page 8: Low-Level RF of BEPCII

First high power test of #2 SCC at June 06

• Apr 29~May 11 finished the room temperature RF aging to coupler 150KW• May 23 purify GHe• May 30 cold down SCC 、 June 7 LHe level=46% 、 June 13 level=95%• June 1~18 LLRF commissioning with Klytron 、 calibration RF power • June 19 LLRF test the frequency tuner and piezo for cavity• June 20 RF aging on the coupler 100kw 、 cavity detune at 4K temperature• June 21 quench protection test 、 tuning the cavity• June 22 detune±1KHz 、 ±450 、 cavity frequency locked 、 measured QL=2.1E

5 • June 23 first reached 1MV 、 calibration Vc 、 RF power 、 setting LLRF loops• June 24 1.2MV 、 measurement Q0=1×109

• June 25 LLRF test the RF pulse aging 、 5 radiation sensors test OK• June 26 Sino-Japan confirmed the safty and the Vc calibration • June 27 1.55MV first quench happened• June 28 1.7MV 、 36.5KW 、 radiation 32mSv/hr• June 29 reached 2MV in the first time• June 30 RF pulse aging , at 2MV measurement Q0=5.4×108

• July 1 measureQ0 at 1.8MV 、 1.5MV 、 1.4MV 、 1.3MV• July 3 warm up the #2 SCC• July 11 #2 SCC reached room temperature

Page 9: Low-Level RF of BEPCII

Using LHe consumption to measure Q0

• Function

Vc—RF voltage PC—RF power consumed by the cavity wall Ptotalloss—the whole module heat loss under a Vc Pstaticloss—cryostat heat loss without RF field Pheater—the heater power inside the cryostat • Liquid Helium parameters: at 1.2bar 、 4.2K liquid Helium→Gas potential heat=19.4 KJ/Kg LHe proportion gravity = 122Kg/m3

after closing the input valve, LHe level will be reduced from 96% to 85% within a time

LHe volume vs level = 2.73Liter/1% (roughly)

with a given Vc, to determine the PC by the reducing of the LHe

2 21 10

95.3C C

C totalloss staticloss heater

V VQ

R P P P PQ

Page 10: Low-Level RF of BEPCII

First measurement of Q0 for #2SCCVc—over 2MV 、 heater=0w 、 LHe level=red

Page 11: Low-Level RF of BEPCII

High power test and Q0 measurement

Page 12: Low-Level RF of BEPCII
Page 13: Low-Level RF of BEPCII

RF pulse aging to increase the quench Vc and reduce the radiationbefore the aging: quench happened at 1.7MV, radiation 35mSv/hrafter RF aging: quench at 2MV, radiation=10mSv/hr at 1.7MV At 2MV , the radiation intensity maybe 300~500mSv/hr ( over the meter range )

辐射剂量与超导腔高频老练前后的腔压关系

1. 55 , 11. 60 , 5

1. 70 , 10

1. 80 , 25

1. 90 , 50

1. 95 , 741. 97 , 80

0

10

20

30

40

50

60

70

80

90

100

0. 80 1. 00 1. 20 1. 40 1. 60 1. 80 2. 00 2. 20 2. 40

MV高频超导腔电压( )

mSv/

辐射剂量(

小时)

老练前辐射剂量一轮脉冲老练后二轮脉冲老练后三轮脉冲老练后

Page 14: Low-Level RF of BEPCII

Summary1) West LLRF finished the high power test for #2 & #1 SCC ( June~Sep.) at 2MV: Q0=5.8E8 (East SC) Q0=1E9 (West SC) Vacuum gate valves were not damaged by the dark current2) East LLRF joined in the beam run at Nov.2006 ( on time)3) East station was dedicated the SR run ( Dec.06~Feb.07) reached e- beam [email protected] ~64kw4) West station was put in the e+ ring commissioning ( Feb. 2007 ) reached e+ beam [email protected] ~18kw5) frf=499.8MHz±14KHz were shifted by 0.2KHz step without beam loss6) fs、 φs 、 Vc 、 and RF power are matched7) RF power limitation at LLRF were released over 80KW ( Apr.2007 ) LLRF will be test under the heavy Beam loading in the future

• Thanks to Prof. K. Akai , T. Furuya, S. Mitsunobu for help.• Thanks to Dr. Wang Chaoen of TLS , and Dr.Zhao zhentang of SSRF for the use

ful discussions.• Thanks to Prof. S. Kurokawa for pushing on the co-operation.

Thanks every expert and colleague