Kawartha Pine Ridge District School Board
2015-2020 Long Term Accommodation Plan
Table of Contents Introduction Page 1
Demographics Page 3
Long Term Accommodation Planning Summaries Page 7
Associated School Groupings (ASG)
Adam Scott Collegiate Vocational Institute Page 11 Bowmanville High School Page 13 Campbellford District High School Page 15 Clarington Central Secondary School Page 17 Clarke High School Page 19 Cobourg Collegiate Institute Page 21 Courtice Secondary School Page 23 Crestwood Secondary School Page 25 East Northumberland Secondary School Page 27 Kenner Collegiate Vocational Institute Page 29 Lakefield District Secondary School Page 31 Norwood District High School Page 33 Port Hope High School Page 35 Thomas A. Stewart Secondary School Page 37 Alternative Education Centres-Secondary Page 39
Inventory of Land Assets Page 41
School Profiles Page 43
Facility Condition Indices Page 45
Summary of 5 Year Event Costs by School Page 47 Elementary School Profiles and Enrolment Data Page 49 Secondary School Profiles and Enrolment Data Page 201
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
Introduction
The Kawartha Pine Ridge District School Board has an obligation to provide the best possible learning opportunities and environments regardless of where our students reside/attend school. The Board is responsible for managing its school capital assets in an effective manner, being stewards of Board resources, and making the best possible use of taxpayer dollars.
As a district we must respond to changing demographics and program needs while ensuring continued student achievement and well-being, and the financial viability/sustainability of the school Board through the establishment of a Long Term Accommodation Plan.
This plan requires the consolidation of multiple factors which impact on the quality of programming the Kawartha Pine Ridge District School Board strives to provide to each child, each family and each community within its jurisdiction.
Purposes of the Long Term Accommodation Plan
The Long Term Accommodation Plan is intended to provide the Board with information and/or direction on:
School buildings 20% over utilization capacity
School buildings where utilization is less than 80% of capacity
Issues regarding program viability
Ten year enrolment projections
Status of physical plant including accessibility, physical condition and buildings where operations/maintenance costs exceed the norm
Indicators for future directions regarding new schools and/or additions, school consolidations/closures, boundary reviews/changes
It is understood that while this is intended to be a multi-year plan, it is revised annually as new information is available and projections are updated. At any point, new schools for review may be added to the plan.
1
Kawartha Pine Ridge District School Board
2015-2020 Long Term Accommodation Plan
Demographics
Enrolment Summary Enrolment in the Kawartha Pine Ridge District School Board has continued to decline over the past decade. Specifically, there has been a 15.1% decline in enrolment since the 2006-2007 school year. This trend is consistent with most school districts across the province. The Board historical enrolment data is: 2006-2007 2013-2014 Change % Change Elementary Headcount
25,013 21,695 (3,318) (13.3%)
Secondary Average Daily Enrolment (ADE)
13,614 11,109 (2,505) (18.4%)
Total 38,627 32,804 (5,823) (15.1%) Elementary enrolment decline has levelled off, however, secondary is continuing to decline as the small grade sizes from elementary move through to the high schools. Birth data on a Board-wide basis for the period of 1990 through 2013 showed a significant decline from their peak in 1991 to a low point in 2000 with a gradual rebound in subsequent years:
Year 1991 2000 2013 Births 3,349 2,407 3,081
The data sources are the Provincial Birth Registry, Canada Revenue Agency Child Tax Credit information and the Census.
Births Board-wide
3
The Boards planning software projects that over the next ten years births will continue to increase gradually and they are expected to be approximately 3,300 in the year 2024.
Based on this information, as well as other demographic trends, the Boards enrolment is projected to increase to just under 35,000 by the year 2024. Within this total, secondary (under 21) enrolment is projected to continue to decline over the next five years, bottoming out at an estimated headcount of 9,500 in the year 2020, after which a gradual rebound is projected to bring enrolment to approximately 10,300 in 2024.
RT = Regular Track
2700
2800
2900
3000
3100
3200
3300
3400
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
ProjectedBirthsBoardwide
4
Elementary headcount is projected to gradually increase to over 24,300 by the year 2024.
Overall enrolment is projected to decline through 2016, stabilize, and then begin to increase through 2024.
By 2024, enrolment is projected to be above the 2014 levels by about 2,150 students, but changes will vary significantly by level:
Enrolments for JK-6 are projected to increase by almost 2,300 Enrolments for 7-8 are projected to increase by about 250 Enrolments for 9-12 are projected to decrease by almost 400 by 2024, with a low point
in 2020, when enrolment will be about 925 students below the current level
5
KawarthaPineRidgeDistrictSchoolBoard2015-2020 Long Term Accommodation Plan
Planning Summaries by
Associated School Groupings (ASG)
7
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
The 2015-2020 Long Term Accommodation Plan is a comprehensive review of all schools and communities within our school board. Over the last months, we have talked with our students, teachers, support staff and principals, visited other school boards, and held a number of focus group meetings with our communities to explore the accommodation realities for our low-enrolment secondary schools. The Long Term Accommodation Planning Process is being shared with all regional councils.
The Long Term Accommodation Plan is administrations proposed plan for the future. It is understood that while this is intended to be a multi-year plan, it is revised annually as new information is available and projections are updated. At any point, new schools for review may be added to the plan.
The following Planning Summaries section only includes schools with recommended actions.
9
2015-2020 Long Term Accommodation Planning by ASG
ADAM SCOTT COLLEGIATE VOCATIONAL INSTITUTE ASG
School Names
Recommendations
Timelines
Edmison Heights P.S.
Build an addition and upgrade facility to address
current enrolment pressures and continue to monitor enrolment in the future.
Allow French Immersion students to attend in
Junior Kindergarten where the parental intention is to enrol the student in French Immersion in Senior Kindergarten.
September
2016
Highland Heights P.S. and Queen Elizabeth P.S.
Conduct an Accommodation Review to
consolidate Queen Elizabeth P.S. and Highland Heights P.S. into a new building at the Queen Elizabeth P.S. site. Review to commence in the 2016-2017 school year with potential implementation in 2017-2018.
September
2016
R.F. Downey P.S.
Build an addition to address enrolment pressures.
September
2016
Summary: Enrolment at Edmison Heights P.S. is currently 475 students. The school has a capacity of 409 and is currently 16% over capacity. Enrolment is projected to increase significantly over the next 10 years. An addition is required to meet current enrolment pressures. Enrolment will continue to be monitored in the future. Student enrolment at Queen Elizabeth P.S. and Highland Heights P.S. is projected to increase marginally over the next 10 years. Highland Heights P.S., built in 1959, with an addition in 1965, has a population of 174, a capacity of 300 with 58% of the school currently being utilized. Queen Elizabeth P.S., built in 1939 with additions in 1954, 1957, and 1967, has a population of 222, a capacity of 295 with 75% of the school currently being utilized. The walking distance between the two schools is 1.2 km. An Accommodation Review is recommended to consider the consolidation of Highland Heights P.S. and Queen Elizabeth P.S. in a new building at the Queen Elizabeth P.S. site. Review is to commence in the 2016-2017 school year with potential implementation in 2017-2018.
11
If consolidation of the schools is not feasible then it is understood that investments will be required to continue to maintain both operations. Enrolment at R.F. Downey P.S. is currently 268 students. The school has a capacity of 222 and is 21% over capacity. Enrolment is projected to increase over the next 10 years. An addition is required to meet current enrolment pressures.
12
BOWMANVILLE HIGH SCHOOL ASG
School Names
Recommendations
Timelines
Bowmanville H.S.
Build an addition to address enrolment pressures.
September
2016
Summary: Bowmanville H.S. has been over capacity for many years with 9 portables currently on site. The school has a capacity of 903, its current enrolment is 1,030 which is 14% above capacity. Enrolment is projected to continue to be above capacity in the next 10 years. A permanent addition is recommended to address enrolment pressures. There is projected development in north Bowmanville which will lead to enrolment pressures on our existing elementary schools. The Board will need to consider purchasing sites to address future growth.
13
CAMPBELLFORD DISTRICT HIGH SCHOOL ASG
Recommendation/Summary: Enrolment in the Campbellford District H.S. Associated School Grouping is remaining relatively stable over the next 10 years. Maintaining the status quo is recommended for the area.
15
CLARINGTON CENTRAL SECONDARY SCHOOL ASG
School Names
Recommendations
Timelines
Hampton Junior P.S. and M.J. Hobbs Senior P.S.
Conduct an Accommodation Review to
consolidate M.J. Hobbs Senior P.S. and Hampton Junior P.S. at the M.J. Hobbs Senior P.S. site. Review to commence in the 2017-2018 school year with potential implementation for the 2018-2019.
September
2017
Summary: Hampton Junior P.S. was built in 1955 with additions in 1961 and 1971. The schools current enrolment is 154. It has a capacity of 144 and is 7% over capacity. Enrolment is expected to grow significantly over the next 10 years. The Hampton Junior P.S. site is 2.99 acres and has other service restrictions that would make an addition on site difficult. M.J. Hobbs Senior P.S. was built in 1966. The schools current enrolment is 207. It has a capacity of 308 with 67% of the school currently being utilized. Enrolment is projected to increase in the future. An Accommodation Review is recommended to consider the consolidation of Hampton Junior P.S. and M.J. Hobbs Senior P.S. at the M.J. Hobbs Senior P.S. site. The options of an addition versus a new building will need to be considered. Review is to commence in the 2017-2018 school year with potential implementation in 2018-2019. There is projected development in north Bowmanville which will lead to enrolment pressures on our existing elementary schools. The Board will need to consider purchasing sites to address future growth.
17
CLARKE HIGH SCHOOL ASG
School Names
Recommendations
Timelines
Clarke H.S. and The Pines Senior P.S.
Determine if a new consolidated Grade 7-12 school
in Newcastle is feasible.
September
2017
Kirby Centennial P.S. and Orono P.S.
Conduct an Accommodation Review to consolidate
Kirby Centennial P.S. and Orono P.S. at the Orono P.S. site. Review to commence in the 2017-2018 school year with potential implementation in 2018-2019.
September
2017
Summary: Clarke H.S. was built in 1962 with an addition in 1976. The schools current enrolment is 370. It has a capacity of 576, with 64% of the school currently being utilized. The Pines Senior P.S. was built in 1974. It has an enrolment of 215, a capacity of 251 with 86% of the school being utilized. Education Development Charge consultants are projecting an increase in the school age population in the Newcastle area over the next 15 year period. A replacement school for Clarke H.S. and The Pines Senior P.S. should be considered in the Newcastle urban area. Kirby Centennial P.S. was built in 1968. The schools current enrolment is 92. It has a capacity of 164, with 56% of the school currently being utilized. Enrolment will remain stable over the next 10 years. Orono P.S. was built in 1968 with an addition in 1971. The schools current enrolment is 124. It has a capacity of 176 with 70% of the school currently being utilized. Enrolment is projected to decline slightly in the future. An Accommodation Review is recommended to consider the consolidation of Kirby Centennial P.S. and Orono P.S. at the Orono P.S. site. Review to commence in the 2017-2018 school year with potential implementation in 2018-2019. Long-term population growth should be monitored in the Newcastle urban area to determine whether the Board will to need to consider acquiring new sites to address future demand.
19
COBOURG COLLEGIATE INSTITUTE ASG
Recommendation/Summary: Beginning in 2015-2016, all schools in the Cobourg District Collegiate Institute West ASG will be included in the Cobourg Collegiate Institute (CCI) ASG.
Overall enrolment in the CCI ASG is projected to remain relatively stable over the next 10 years. Maintaining the status quo is recommended for the area. However, in the future we may need to consider closing Dale Road Senior P.S. and having Grade 7 and 8 students remain at their home schools. C.R. Gummow P.S. begins French Immersion in Senior Kindergarten. Like other dual track schools across the district, it is recommended that students in Junior Kindergarten, where the parental intention is to enrol the student in French Immersion in Senior Kindergarten, be allowed to attend at the French Immersion school site.
21
COURTICE SECONDARY SCHOOL ASG
Recommendation/Summary:
The student population for the area schools is projected to remain stable over the next 10 years. Maintaining the status quo is recommended for these schools. There is expected development in Courtice, north of Highway 2. The Board will need to consider acquiring land for a future elementary school site. Dr. G.J. MacGillivray P.S. begins French Immersion in Senior Kindergarten. Like other dual track schools across the district, it is recommended that students in Junior Kindergarten, where the parental intention is to enrol the student in French Immersion in Senior Kindergarten, be allowed to attend at the French Immersion school site.
23
CRESTWOOD SECONDARY SCHOOL ASG
School Names
Recommendations
Timelines
Millbrook/South Cavan P.S.
Build an addition to address current student
population.
September
2016
Westmount P.S.
Build an addition to address student growth.
Allow French Immersion students to attend in
Junior Kindergarten where the parental intention is to enrol the student in French Immersion in Senior Kindergarten.
September
2017
September 2017
Summary: Enrolment at Millbrook/South Cavan P.S. is currently 413 students. The school has a capacity of 349 and is currently 18% over capacity. Enrolment is projected to remain consistent over the next 10 years. Enrolment at Westmount P.S. is currently 448 students. The school has a capacity of 375 and is currently 20% over capacity. Enrolment is projected to continue to increase over the next 10 years. Funding options will be explored to support permanent additions at both schools.
25
EAST NORTHUMBERLAND SECONDARY SCHOOL ASG
School Names
Recommendations
Timelines
Smithfield P.S. and Spring Valley P.S.
Conduct an Accommodation Review to
consolidate Smithfield P.S. and Spring Valley P.S. at the Spring Valley P.S. site. Review to commence in the 2016-2017 school year with potential implementation in 2017-2018.
September
2016
Summary:
Smithfield P.S. was built in 1951 with additions in 1966 and 1968. Smithfield P.S. has a population of 132, a capacity of 187 with 71% of the school currently being utilized. Enrolment will remain stable over the next 10 years. Spring Valley P.S., built in 1964 with an addition in 1968, has a population of 193, a capacity of 291 with 66% of the school currently being utilized. Enrolment is projected to decline slightly in the future. An Accommodation Review is recommended to consider the consolidation of Smithfield P.S. and Spring Valley P.S. at the Spring Valley P.S. site. Review to commence in the 2016-2017 school year with potential implementation in 2017-2018.
27
KENNER COLLEGIATE VOCATIONAL INSTITUTE ASG
School Names
Recommendations
Timelines
Prince of Wales P.S.
Consider renovations to upgrade and right-size
facility while maintaining historical integrity of the building.
Allow French Immersion students to attend in Junior Kindergarten where the parental intention is to enrol the student in French Immersion in Senior Kindergarten.
September
2017
September 2016
Summary: Enrolment at Prince of Wales P.S. is currently 492 students. The school has a capacity of 622 with 79% of the building currently being utilized. Enrolment is projected to increase slightly over the next 10 years. Recent ministry reports indicate that the facility requires $5.1 million to address medium and high priority issues (lighting, windows, flooring, etc.). Upgrading and right-sizing the building while maintaining the historical integrity of the building is recommended.
29
LAKEFIELD DISTRICT SECONDARY SCHOOL ASG
School Names
Recommendations
Timelines
Lakefield District Secondary and Intermediate Schools
Conduct an Accommodation Review to consolidate
Lakefield District S.S. and Thomas A. Stewart S.S. at the T.A.S.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017.
Grade 7 and 8 students would remain at their current feeder schools, if the consolidation option is adopted.
September
2015
Ridpath Junior P.S.
Allow French Immersion students to attend in
Junior Kindergarten where the parental intention is to enrol the student in French Immersion in Senior Kindergarten.
September
2016
Summary: Student enrolment continues to decline at Lakefield District Secondary and Intermediate School. Enrolment has declined in the Secondary School from 653 students to its current enrolment of 312 (over the last 15 years) and is projected to decline to 270 students. The Intermediate School has dropped from 227 to 106 students over that same time frame. The overall site has a capacity of 918 students with 46% of the building currently being utilized. During the Low Enrolment School Focus Group meeting, the community identified the strengths and challenges associated with operating a low enrolment secondary school. The community also indicated a strong desire for a decision to resolve the question about the future of the school. An Accommodation Review is recommended to consider the consolidation of Lakefield District S.S. and Thomas A. Stewart S.S. at the T.A.S.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017. If the consolidation option is adopted, then Grade 7 and 8 students who attend Lakefield Intermediate School would remain at their current feeder schools.
31
NORWOOD DISTRICT HIGH SCHOOL ASG
School Names
Recommendations
Timelines
Norwood District H.S.
Accommodation Review beginning in
September 2016.
September
2016
Summary: Norwood District H.S. has a student population of 290, a capacity of 681, with 43% of the building currently being utilized. Enrolment is projected to remain in this utilization range for the next 10 years. During the Low Enrolment School Focus Group meeting the community identified the strengths and challenges associated with operating a low enrolment secondary school. The community identified several options for the school. An Accommodation Review is recommended for September 2016. Options to be considered include:
establish a K-12 school on the Norwood District H.S. site. create a Grade 7-12 school on the Norwood District H.S. site. close Norwood District H.S. site with students to attend either Peterborough or
Campbellford depending upon where they reside.
As part of any option, consider providing alternative programming (CIS) within the Norwood community.
33
PORT HOPE HIGH SCHOOL ASG
School Names
Recommendations
Timelines
George Hamilton P.S.
Conduct an Accommodation Review to
consolidate George Hamilton P.S. and Ganaraska Trail P.S. at the Ganaraska Trail P.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017.
Allow French Immersion students to attend in Junior Kindergarten where the parental intention is to enrol the student in French Immersion in Senior Kindergarten.
September
2015
September 2016
Summary: Student enrolment at George Hamilton P.S. is 59, the school has a capacity of 150, with 39% of the school currently being utilized. Population is projected to continue to decline.
Conduct an Accommodation Review to consolidate George Hamilton P.S. and Ganaraska Trail P.S. at the Ganaraska Trail P.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017.
35
THOMAS A. STEWART SECONDARY SCHOOL ASG
School Names
Recommendations
Timelines
Armour Heights P.S. and King George P.S.
Conduct an Accommodation Review to
consolidate King George P.S. and Armour Heights P.S. at the King George P.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017.
September
2015
Summary: Student enrolment is stabilizing at these two schools. Armour Heights P.S., built in 1952 with additions in 1958 and 1968, has a population of 222, a capacity of 311 with 71% of the building currently being utilized. King George P.S., built in 1912, with an addition in 1967, has a population of 229, a capacity of 291 with 79% of the building currently being utilized. Students from King George P.S. attend Grade 7 and 8 at Armour Heights P.S. The walking distance between the two schools is 0.75 km. Consolidating students from both schools at the King George P.S. site would allow for one less transition for King George P.S. students. Refurbishing and building an environmentally friendly addition at the King George P.S. site, while maintaining the historical integrity of the building, would provide an improved facility for students within the area. Alternatively, building a new school at the King George P.S. site and disposing of both Armour Heights P.S. and King George P.S. could be considered for this consolidation. An Accommodation Review is recommended to consider the consolidation of King George P.S. and Armour Heights P.S. at the King George P.S. site. Review to commence in the 2015-2016 school year with potential implementation in 2016-2017. If consolidation of both schools is not feasible then it is understood that investments in both sites will be required to continue to maintain both operations.
37
ALTERNATIVE EDUCATION CENTRES - SECONDARY
Summary: KPR has three Alternative Education Centres throughout the school district: Clarington Centre for Individual Studies Northumberland Centre for Individual Studies at Grant Sine Peterborough Alternative and Continuing Education (PACE) at PCVS. Clarington and Northumberland sites offer alternative programming which include Teen Education and Mothering, and PACE offers the School for Young Moms Program for students both under and over 21. Enrolment has increased as the programs have moved to improved facilities. Maintaining the status quo is recommended for the future of these sites.
39
Kawartha Pine Ridge District School Board
Inventory of Land Assets
Property Name Size B = Building V = Vacant
ASG Recommendations for Action
Timeline
Maple Grove East P.S./Bowmanville CIS 2226 Maple Grove Rd. N. Bowmanville
5.614
+/- acres
V
N/A
Not currently required
for pupil accommodation
ONTARIO STREET 116 Ontario St., Bowmanville
3.04 +/- acres
B
BHS
Not currently required
for pupil accommodation
COBOURG D.C.I.W. 135 King St. W. Cobourg
2.36 +/- acres
B
CCI
Not currently required
for pupil accommodation
COBOURG D.C.I.W. Sports Field West side of Durham St., Cobourg
4.623
+/- acres
V
CCI
Retain for possible
future use.
WESTWOOD Kerr St. at Westwood Dr. and Ewing St., Cobourg Pt4,39R-123 and Lot 9 Plan 414
14.19
+/- acres
V
CCI
Not currently required
for pupil accommodation
GLENFOREST 1555 Glenforest Blvd., Peterborough Block 27m Plan 45M-146
7.0 +/-acres
V
CRS
Not currently required
for pupil accommodation
Monitor population growth for the area north of Parkhill Rd./Brealey, and consider acquiring a school site.
SOUTH MONAGHAN 211 County Rd. 28, Bailieboro
5.50 +/- acres
B
CRS
Not currently required for pupil accommodation
BHS = Bowmanville High School CCI = Cobourg Collegiate Institute CRS = Crestwood Secondary School N/A = Not applicable
41
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School Profiles
1. The school profiles include: Enrolment history for the period of 2010-2011 through 2014-2015 Enrolment projections for the period of 2015-2016 through 2024-2025 School Utilization percentage both actual and projected from 2010-2011 through
2028-2029
Our Baragar Planning software is the source of this data. All enrolment is on a headcount basis. Alternative Education Centre numbers include both students under and over the age of 21.
2. Utilization percentages are based on the current building capacity.
Note: The legend for the School Utilization Table is:
The capacity of a school is determined by the Ministry of Education by loading all instructional spaces within the facility to current Ministry standards for class size requirements and room areas.
3. The Ministry of Education has now completed the first four years of the Condition Assessment Program. Over this period, more than 3,700 school facilities have been assessed across all 72 school boards. 2015 represents the fifth and final year of the assessment cycle that began in 2011 and KPR has 23 facilities remaining that will be inspected this summer.
These assessments provide the Facility Condition Index (FCI) which is a building condition determined by calculating the ratio between the five-year (5) renewal needs and the replacement value for each facility. FCI is included with the school profiles, where available.
In addition to the FCI, the Ministry assessment details Building Renewal needs,which we have consolidated into four (4) categories for our review:
Architectural/Structural includes Substructure, Shell/Superstructure and Interiors.
HVAC includes plumbing, heating, ventillation and air conditioning. Electrical includes electrical supply, distribution, lighting and fire alarms. Site Work includes parking lots, sidewalks, fencing and playfields.
IC = In Catchment
OC = Out of Catchment
BP = Board Program
CSE = LLS Class
43
The estimated costs of these renewal needs are included with the school profiles, where available. A summary of the findings to date are also included in the following table.
44
45
46
47
48
Kawartha Pine Ridge District School Board
2015-2020 Long Term Accommodation Plan
Elementary School Profiles
and Enrolment Data
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
Elementary School Profiles and Enrolment Data
Adam Scott Intermediate School Page 52 Apsley Central Public School Page 54 Armour Heights Public School Page 56 Baltimore Public School Page 58 Beatrice Strong Public School Page 60 Brighton Public School Page 62 Buckhorn Public School Page 64 Burnham Public School Page 66 C.R. Gummow Public School Page 68 Camborne Public School Page 70 Central Public School Page 72 Charles Bowman Public School Page 74 Chemong Public School Page 76 Colborne Public School Page 78 Courtice Intermediate School Page 80 Coutice North Public School Page 82 Dale Road Senior Public School Page 84 Dr. Emily Stowe Public School Page 86 Dr. G.J. MacGillivray Public School Page 88 Dr. M.S. Hawkins Senior Public School Page 90 Dr. Ross Tilley Public School Page 92 Duke of Cambridge Public School Page 94 Edmison Heights Public School Page 96 Enniskillen Public School Page 98 Ganaraska Trail Public School Page 100 George Hamilton Public School Page 102 Grafton Public School Page 104 Hampton Junior Public School Page 106 Harold Longworth Public School Page 108 Hastings Public School Page 110 Havelock-Belmont Public School Page 112 Highland Heights Public School Page 114 Hillcrest Public School Page 116 James Strath Public School Page 118 John M. James Public School Page 120 Kawartha Heights Public School Page 122
49
Keith Wightman Public School Page 124 Kenner Intermediate School Page 126 Kent Public School Page 128 King George Public School Page 130 Kirby Centennial Public School Page 132 Lakefield Intermediate School Page 134 Lydia Trull Public School Page 136 M.J. Hobbs Senior Public School Page 138 Merwin Greer Public School Page 140 Millbrook/South Cavan Public School Page 142 Murray Centennial Public School Page 144 Newcastle Public School Page 146 North Cavan Public School Page 148 North Hope Central Public School Page 150 North Shore Public School Page 152 Northumberland Hills Public School Page 154 Norwood District Public School Page 156 Orono Public School Page 158 Otonabee Valley Public School Page 160 Percy Centennial Public School Page 162 Plainville Public School Page 164 Prince of Wales Public School Page 166 Queen Elizabeth Public School Page 168 Queen Mary Public School Page 170 R.F. Downey Public School Page 172 Ridpath Junior Public School Page 174 Roger Neilson Public School Page 176 Roseneath Centennial Public School Page 178 S.T. Worden Public School Page 180 Smithfield Public School Page 182 Spring Valley Public School Page 184 Stockdale Public School Page 186 Terry Fox Public School Page 188 The Pines Senior Public School Page 190 Vincent Massey Public School Page 192 Warsaw Public School Page 194 Waverley Public School Page 196 Westmount Public School Page 198
51
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Adam Scott Collegiate Vocational Institute ASG and Intermediate School 175 Langton Street, Peterborough, ON K9H 6K3
On The Ground capacity (OTG): Secondary
On The Ground capacity (OTG): Intermediate
Intermediate Gross Floor Area (GFA):
Site Acreage for Adam Scott C.V.I.:
Original Building built: Grades and Programs:
1,017 pupil places
225 pupil places
180,726 square feet or 16,790 square metres
15.00 +/- acres or 6.07 ha
1960, Addition(s) 1971 and 2013
Grade 7 and Grade 8
52
Enrolment History
Enrolment Projections
Adam Scott Intermediate School
Facility Condition Index (FCI): 14.46% Total Event Costs: $ 4,855,214
School Utilization Percentages
53
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Apsley Central Public School and Child Care Centre Lakefield District Secondary School ASG
238 Burleigh Street, Apsley, ON K0L 1A0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Apsley Central P.S.: Original Building built: Grades and Programs:
141 pupil places
19,721 square feet or 1,832 square metres
6.19 +/- acres or 2.50 ha
2010, Addition(s) this is a replacement school
Junior Kindergarten to Grade 8 and Child Care Centre
54
Enrolment History
Enrolment Projections
School Utilization Percentages
Apsley Central Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
55
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Armour Heights Public School Thomas A. Stewart Secondary School ASG
245 McFarlane Street, Peterborough, ON K9H 1K1
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Armour Heights P.S.: Original Building built: Grades and Programs:
311 pupil places
28,605 square feet or 2,658 square metres
3.83 +/- acres or 1.55 ha
1952, Addition(s) 1958 and 1968
Junior Kindergarten to Grade 8
56
Enrolment Projections
School Utilization Percentages
Armour Heights Public School
Facility Condition Index (FCI): 20.33% Total Event Costs: $ 1,457,837
Enrolment History
57
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Baltimore Public School Cobourg Collegiate Institute ASG
9320 Burwash Road, Baltimore, ON K0K 1C0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Baltimore P.S.: Original Building built: Grades and Programs:
291 pupil places
34,673 square feet or 3,221 square metres
4.68 +/- acres or 1.89 ha
1958, Addition(s) 1967 and 1992
Junior Kindergarten to Grade 6
58
Enrolment History
Enrolment Projections
School Utilization Percentages
Baltimore Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
59
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Beatrice Strong Public School and Child Care Centre Port Hope High School ASG
90 Rose Glen Road North, Port Hope, ON L1A 3V6 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Beatrice Strong P.S.: Original Building built: Grades and Programs:
372 pupil places
41,125 square feet or 3,820 square metres
5.837+/- acres or 2.36 ha
1992, Addition(s) n/a
Junior Kindergarten to Grade 6 and Child Care Centre
60
Enrolment History
Enrolment Projections
SchoolUtilizationPercentages
Beatrice Strong Public School
Facility Condition Index (FCI): 37.06% Total Event Costs: $ 2,935,806
61
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Brighton Public School and Child Care Centre East Northumberland Secondary School ASG
24 Elizabeth Street, Brighton, ON K0K 1C0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Brighton P.S.: Original Building built: Grades and Programs:
504 pupil places
50,216 square feet or 4,665 square metres
9.86 +/- acres or 4.00 ha
1967, Addition(s) 2012 replacement of 1915 and 1961 wings
Junior Kindergarten to Grade 8and Extended French Immersion
and Living and Life Skills (LLS) and Child Care Centre
62
Enrolment History
Enrolment Projections
School Utilization Percentages
Brighton Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
63
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Buckhorn Public School Lakefield District Secondary School ASG
1,800 Lakehurst Road, Lakehurst, ON K0L 1A0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Buckhorn P.S.: Original Building built: Grades and Programs:
118 pupil places
11,888 square feet or 1,104 square metres
7.94 +/- acres or 3.62 ha
1972, Addition(s) N/A
Junior Kindergarten to Grade 6
64
Enrolment History
Enrolment Projections
School Utilization Percentages
Buckhorn Public School
Facility Condition Index (FCI): 7.77% Total Event Costs: $ 281,060
65
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Burnham Public School Cobourg Collegiate Institute ASG
614 Burnham Street, Cobourg, ON K9A 2X1 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Burnham P.S.: Original Building built Grades and Programs:
315 pupil places
24,168 square feet or 2,245 square metres
5.00 +/- acres or 2.02 ha
1956, Addition(s) 1962
Junior Kindergarten to Grade 6
66
Enrolment Projections
School Utilization Percentages
Enrolment History
Burnham Public School
Facility Condition Index (FCI): 41.09% Total Event Costs: $ 2,953,710
67
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
C.R. Gummow Public School (replacement) Cobourg Collegiate Institute ASG
311 Cottesmore Avenue, Cobourg, ON K9A 4E3 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for C.R. Gummow P.S.: Original Building built: Grades and Programs:
678 pupil places
67,427 square feet or 6,264 square metres
11.12 +/- acres or 4.50 ha
2015, Addition(s) replacement school (3 buildings)
Junior Kindergarten to Grade 8 and French Immersion and Gifted
68
Enrolment History
Enrolment Projections
School Utilization Percentages
C. R. Gummow Public School
School Condition Inspections are not completed
on facilities built in the past 5 Years
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
69
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Camborne Public School Cobourg Collegiate Institute ASG
3546 Kennedy Road, Camborne, ON K9A 4J7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Camborne P.S.: Original Building built: Grades and Programs:
176 pupil places
15,571 square feet or 1,447 square metres
7.39 +/- acres or 2.99 ha
1961, Addition(s) 1966 and 2014
Junior Kindergarten to Grade 6
70
Enrolment History
Enrolment Projections
School Utilization Percentages
Camborne Public School
Facility Condition Index (FCI): 34.46% Total Event Costs: $ 1,664,813
71
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Central Public School Bowmanville High School ASG
120 Wellington Street, Bowmanville, ON L1C 1V9 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Central P. S.: Original Building built: Grades and Programs:
234 pupil places
28,293 square feet or 2,628 square metres
1.92 +/- acres or 0.78 ha
1889, Addition(s) 1926 and 1968
Junior Kindergarten to Grade 6
72
Enrolment History
Enrolment Projections
School Utilization Percentages
Central Public School (Bowmanville)
Facility Condition Index (FCI): 29.60% Total Event Costs: $ 1,701,066
73
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Charles Bowman Public School Bowmanville High School ASG
195 Bons Avenue, Bowmanville, ON L1C 0L3 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Charles Bowman P.S.: Original Building built: Grades and Programs:
686 pupil places
63,110 square feet or 5,863 square metres
5.05 +/- acres or 2.04 ha
2011, Addition(s) 2015
Junior Kindergarten to Grade 8
74
Enrolment History
Enrolment Projections
School Utilization Percentages
Charles Bowman Public School
School Condition Inspections are not completed
on facilities built in the past 5 Years
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Note: When school addition is completed, school capacity is projected to increase to 686.
75
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Chemong Public School Adam Scott Collegiate Vocational Institute ASG
1029 Gore Street, Bridgenorth, ON K0L 1H0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Chemong P.S.: Original Building built: Grades and Programs:
501 pupil places
43,700 square feet or 4,060 square metres
12.16 +/- acres or 4.92 ha
1968, Addition(s) 1972, 2002 and 2014
Junior Kindergarten to Grade 8
76
Enrolment History
Enrolment Projections
School Utilization Percentages
Chemong Public School
Facility Condition Index (FCI): 36.95% Total Event Costs: $ 4,225,233
77
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Colborne Public School East Northumberland Secondary School ASG
8 Alfred Street, Colborne, ON K0K 1S0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Colborne P.S.: Original Building built: Grades and Programs:
254 pupil places
20,402 square feet or 1,895 square metres
7.04 +/- acres or 2.85 ha
1957, Addition(s) 1961 and 1968
Junior Kindergarten to Grade 8
78
Enrolment History
Enrolment Projections
School Utilization Percentages
Colborne Public School
Facility Condition Index (FCI): 47.10% Total Event Costs: $ 2,820,007
79
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Courtice Intermediate and Secondary School ASG
1717 Nash Road, Courtice, ON L1E 2L8 On The Ground capacity (OTG): Secondary On The Ground capacity (OTG): Intermediate Gross Floor Area (GFA): Site Acreage for Courtice Secondary School: Original Building built: Grades and Programs:
750 pupil places
115 pupil places
117,240 square feet or 10,892 square metres
16.38 +/- acres or 6.63 ha
1960, Addition(s) 1966 and 1971
Grade 7 and Grade 8
80
Enrolment History
Enrolment Projections
School Utilization Percentages
Courtice Secondary School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
81
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Courtice North Public School Courtice Secondary School ASG
1675 Nash Road, Courtice, ON L1E 2L8 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Courtice North P.S.: Original Building built: Grades and Programs:
353 pupil places
43,882 square feet or 4,077 square metres
5.46 +/- acres or 2.21 ha
1994, Addition(s) 2014
Junior Kindergarten to Grade 8and Living and Life Skills (LLS)
82
Enrolment History
Enrolment Projections
School Utilization Percentages
Courtice North Public School
Facility Condition Index (FCI): 31.88% Total Event Costs: $ 2,499,204
83
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Dale Road Senior Public School Cobourg Collegiate Institute ASG
8228 Dale Road, Cobourg, ON K9A 4J7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Dale Road Senior P.S.: Original Building built: Grades and Programs:
124 pupil places
14,068 square feet or 1,307 square metres
8.79 +/- acres or 3.56 ha
1965, Addition(s) 1966
Grade 7 and Grade 8
84
Enrolment History
Enrolment Projections
School Utilization Percentages
Dale Road Senior Public School
Facility Condition Index (FCI): 22.18% Total Event Costs: $ 754,908
85
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Dr. Emily Stowe Public School Courtice Secondary School ASG
71 Sandringham Drive, Courtice, ON L1E 1W8 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Dr. Emily Stowe P.S.: Original Building built: Grades and Programs:
422 pupil places
43,450 square feet or 4,036 square metres
5.89 +/- acres or 2.38 ha
1990, Addition(s) N/A
Junior Kindergarten to Grade 8and Gifted
86
Enrolment History
Enrolment Projections
School Utilization Percentages
Dr. Emily Stowe Public School
Facility Condition Index (FCI): 27.50% Total Event Costs: $ 2,379,218
87
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Dr. G.J. MacGillivray Public School Courtice Secondary School ASG
75 Meadowglade Road, Courtice, ON L1E 3G7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Dr. G.J. MacGillivray P.S.: Original Building built: Grades and Programs:
795 pupil places
70,595 square feet or 6,558 square metres
6.02 +/- acres or 2.44 ha
2002, Addition(s) 2015
Junior Kindergarten to Grade 6and French Immersion
88
Enrolment History
Enrolment Projections
School Utilization Percentages
Dr. G.J. MacGillivray Public School
Facility Condition Index (FCI): 19.69% Total Event Costs: $ 3,049,147
89
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Dr. M.S. Hawkins Senior Public School within P.H.H.S. Port Hope High School ASG
130 Highland Drive, Port Hope, ON L1A 2A3 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Dr. M.S. Hawkins Senior P.S.: Original Building built: Grades and Programs:
262 pupil places
part of Port Hope H.S.
part of Port Hope H.S.
1955, Addition(s) 2001(PHHS) Hawkins Gym Addition
Grade 7 and Grade 8
90
Dr. M.S. Hawkins Senior Public School within Port Hope High School
Facility Condition Index (FCI): 16.86% Total Event Costs: $ 4,402,102
Enrolment History
Enrolment Projections
School Utilization Percentages
91
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Dr. Ross Tilley Public School and Child Care Centre Clarington Central Secondary School ASG
200 Clarington Boulevard, Bowmanville, ON L1C 5N8 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Dr. Ross Tilley P.S.: Original Building built: Grades and Programs:
456 pupil places
54,012 square feet or 5,018 square metres
5.06 +/- acres or 2.03 ha
1996, Addition(s) 2013
Junior Kindergarten to Grade 8 and Child Care Centre
92
Dr. Ross Tilley Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment History
Enrolment Projections
School Utilization Percentages
93
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Duke of Cambridge Public School Bowmanville High School ASG
47 Liberty Street North, Bowmanville, ON L1C 2L8 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Duke of Cambridge P.S.: Original Building built: Grades and Programs:
703 pupil places
66,664 square feet or 6,193 square metres
6.75 +/- acres or 2.73 ha
2013, Addition(s) n/a
Junior Kindergarten to Grade 8single track French Immersion
94
Duke of Cambridge Public School
School Condition Inspections are not completed
on facilities built in the past 5 Years
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment History
Enrolment Projections
School Utilization Percentages
95
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Edmison Heights Public School Adam Scott Collegiate Vocational Institute ASG
1111 Royal Drive, Peterborough, ON K9H 6P9 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Edmison Heights P.S.: Original Building built: Grades and Programs:
409 pupil places
32,550 square feet or 3,024 square metres
8.55 +/- acres or 3.46 ha
1963, Addition(s) 1965 and 2012
Junior Kindergarten to Grade 6and French Immersion
96
Enrolment Projections
School Utilization Percentages
Enrolment History
Edmison Heights Public School
Facility Condition Index (FCI): 51.94% Total Event Costs: $ 4,435,787
97
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Enniskillen Public School Clarington Central Secondary School ASG
8145 Old Scugog Road, Enniskillen, ON L0B 1J0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Enniskillen P.S.: Original Building built: Grades and Programs:
219 pupil places
26,615 square feet or 2,473 square metres
5.20 +/- acres or 2.10 ha
1926, Addition(s) 1968 and 1972
Junior Kindergarten to Grade 6
98
Enrolment History
Enrolment Projections
School Utilization Percentages
Enniskillen Public School
Facility Condition Index (FCI): 14.86% Total Event Costs: $ 849,462
99
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Ganaraska Trail Public School and Child Care Centre Port Hope High School ASG
34 Percival Street, Port Hope, ON L1A 2B7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Ganaraska Trail P.S.: Original Building built: Grades and Programs:
389 pupil places
39,930 square feet or 3,709 square metres
5.194 +/- acres or 2.10 ha
2009, Addition(s) replacement Howard Jordan/Central
Junior Kindergarten to Grade 6 and Child Care Centre
100
Enrolment History
Enrolment Projections
Ganaraska Trail Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
School Utilization Percentages
101
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
George Hamilton Public School Port Hope High School ASG
3200 County Road 10, Port Hope, ON L1A 3V5
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for George Hamilton P.S.: Original Building built: Grades and Programs:
150 pupil places
13,176 square feet or 1,224 square metres
5.747 +/- acres or 2.33 ha
1958, Addition(s) 1966
Junior Kindergarten to Grade 6
102
Enrolment Projections
School Utilization Percentages
George Hamilton Public School
Facility Condition Index (FCI): 52.79% Total Event Costs: $ 2,173,588
Enrolment History
103
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Grafton Public School Cobourg Collegiate Institute ASG
654 Station Road, Grafton, ON K0K 2G0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Grafton P.S.: Original Building built: Grades and Programs:
291 pupil places
27,050 square feet or 2,513 square metres
5.01 +/- acres or 2.03 ha
1957, Addition(s) 1967 and 1973
Junior Kindergarten to Grade 8
104
Enrolment History
Enrolment Projections
School Utilization Percentages
Grafton Public School
Facility Condition Index (FCI): 18.64% Total Event Costs: $ 1,210,909
105
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Hampton Junior Public School Clarington Central Secondary School ASG
43 Ormiston Street, Hampton, ON L0B 1J0
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Hampton Junior P.S.: Original Building built: Grades and Programs:
144 pupil places
19,202 square feet or 1,784 square metres
2.99 +/- acres or 1.21 ha
1955, Addition(s) 1961 and 1971
Junior Kindergarten to Grade 3
106
Hampton Junior Public School
Facility Condition Index (FCI): 18.52% Total Event Costs: $ 732,061
Enrolment History
Enrolment Projections
School Utilization Percentages
107
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Harold Longworth Public School Bowmanville High School ASG
350 Longworth Avenue, Bowmanville, ON L1C 5J5 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Harold Longworth P.S.: Original Building built: Grades and Programs:
585 pupil places
56,975 square feet or 5,293 square metres
6.16 +/- acres or 2.49 ha
2003, Addition(s) N/A
Junior Kindergarten to Grade 8
108
Enrolment History
Harold Longworth Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment Projections
School Utilization Percentages
109
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Hastings Public School Campbellford District High School ASG
25 Albert Street, Hastings, ON K0L 1Y0
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Hastings P.S.: Original Building built: Grades and Programs:
164 pupil places
15,445 square feet or 1,435 square metres
1.899 +/- acres or 0.77 ha
1952, Addition(s) 1963 and 1988
Junior Kindergarten to Grade 8
110
Enrolment History
Enrolment Projections
School Utilization Percentages
Hastings Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
111
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Havelock-Belmont Public School Norwood District High School ASG
55 Matheson Street East, Havelock, ON K0L 1Z0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Havelock-Belmont P.S.: Original Building built: Grades and Programs:
326 pupil places
24,133 square feet or 2,242 square metres
8.216 +/- acres or 3.33 ha
1963, Addition(s) 1967
Junior Kindergarten to Grade 8
112
Enrolment History
Enrolment Projections
School Utilization Percentages
Havelock-Belmont Public School
Facility Condition Index (FCI): 36.09% Total Event Costs: $ 2,752,883
113
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Highland Heights Public School Adam Scott Collegiate Vocational Institute ASG
430 Highland Road, Peterborough, ON K9H 5J7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Highland Heights P.S.: Original Building built: Grades and Programs:
300 pupil places
26,158 square feet or 2,430 square metres
5.07 +/- acres or 2.05 ha
1959, Addition(s) 1965
Junior Kindergarten to Grade 8and Living and Life Skills (LLS)
114
Enrolment Projections
Highland Heights Public School
Facility Condition Index (FCI): 16.94% Total Event Costs: $ 1,175,535
Enrolment History
School Utilization Percentages
115
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Hillcrest Public School Campbellford District High School ASG
55 Elmore Street, Campbellford, ON K0L 1L0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Hillcrest P.S.: Original Building built: Grades and Programs:
384 pupil places
33,432 square feet or 3,106 square metres
10.00 +/- acres or 4.05 ha
1967, Addition(s) N/A
Junior Kindergarten to Grade 8with extended French Immersion
116
Enrolment Projections
School Utilization Percentages
Enrolment History
Hillcrest Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
117
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
James Strath Public School and Child Care Centre Crestwood Secondary School ASG
1175 Brealey Drive, Peterborough, ON K9K 0C1 On The Ground capacity (OTG): Gross Floor Area (GFA): (including Child Care Centre) Site Acreage for James Strath P.S.: Original Building built: Grades and Programs:
714 pupil places
76,475 square feet or 7,105 square metres
8.36 +/- acres or 3.38 ha
1992, Addition(s) 2014
Junior Kindergarten to Grade 8and Living and Life Skills (LLS)
and Child Care Centre
118
School Utilization Percentages
Enrolment History
Enrolment Projections
James Strath Public School
Facility Condition Index (FCI): 26.49% Total Event Costs: $ 3,720,883
119
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
John M. James Public School Bowmanville High School ASG
175 Mearns Avenue, Bowmanville, ON L1C 5C6 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for John M. James P.S.: Original Building built: Grades and Programs:
504 pupil places
52,650 square feet or 4,891 square metres
6.11 +/- acres or 2.47 ha
2001, Addition(s) 2013
Junior Kindergarten to Grade 8
120
School Utilization Percentages
John M. James Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment History
Enrolment Projections
121
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Kawartha Heights Public School Crestwood Secondary School ASG
11 Kawartha Heights Blvd., Peterborough, ON K9J 1N4 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Kawartha Heights P.S.: Original Building built: Grades and Programs:
268 pupil places
25,210 square feet or 2,342 square metres
6.19 +/- acres or 2.51 ha
1958, Addition(s) 1961, 1967 and 1976
Junior Kindergarten to Grade 6
122
School Utilization Percentages
Enrolment History
Enrolment Projections
Kawartha Heights Public School
Facility Condition Index (FCI): 17.68% Total Event Costs: $ 1,099,850
123
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Keith Wightman Public School Kenner Collegiate Vocational Institute ASG
860 St. Marys Street, Peterborough, ON K9J 4H6 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Keith Wightman P.S.: Original Building built: Grades and Programs:
353 pupil places
31,875 square feet or 2,961 square metres
4.85 +/- acres or 1.96 ha
1955, Addition(s) 1966
Junior Kindergarten to Grade 6
124
Enrolment Projections
School Utilization Percentages
Enrolment History
Keith Wightman Public School
Facility Condition Index (FCI): 15.34% Total Event Costs: $ 1,202,599
125
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Kenner Collegiate Vocational Institute and Intermediate School Kenner Collegiate Vocational Institute ASG
633 Monaghan Road South, Peterborough, ON K9J 5J2 On The Ground capacity (OTG) Secondary: On The Ground capacity (OTG) Intermediate: Gross Floor Area (GFA): Site Acreage for Kenner C.V.I. and Intermediate School: Original Building built:
918 pupil places306 pupil places
174,325 square feet or 16,195 square metres
17.62 +/- acres or 7.13 ha
1952, Addition(s) 1957, 1964, 1966, 1971
126
School Utilization Percentages
Enrolment Projections
Enrolment History
Kenner Intermediate School within Kenner Collegiate Vocational Institute
Facility Condition Index (FCI): 13.87% Total Event Costs: $ 4,487,246
127
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Kent Public School Campbellford District High School ASG
150 Kent Street, Campbellford, ON K0L 1L0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Kent P.S.: Original Building built: Grades and Programs:
281 pupil places
24,267 square feet or 2,254 square metres
6.00 +/- acres or 2.43 ha
1958, Addition(s) 1966 and 2013
Junior Kindergarten to Grade 8and Living and Life Skills (LLS)
128
School Utilization Percentages
Enrolment History
Enrolment Projections
Kent Public School
Facility Condition Index (FCI): 11.31% Total Event Costs: $ 709,635
129
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
King George Public School Thomas A. Stewart Secondary School ASG
220 Hunter Street, Peterborough, ON K9H 1H1 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for King George P.S.: Original Building built: Grades and Programs:
291 pupil places
29,712 square feet or 2,760 square metres
5.99 +/- acres or 2.43 ha
1912, Addition(s) 1967
Junior Kindergarten to Grade 6
130
Enrolment History
Enrolment Projections
School Utilization Percentages
King George Public School
Facility Condition Index (FCI): 14.96% Total Event Costs: $ 971,578
131
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Kirby Public School Clarke High School ASG
3675 Concession Road 7, Orono, ON L0B 1M0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Kirby Centennial P.S.: Original Building built:
Grades and Programs:
164 pupil places
14,120 square feet or 1,312 square metres
10.02+/- acres or 4.05 ha
1968, Addition(s) n/a
Junior Kindergarten to Grade 6
132
Enrolment History
Enrolment Projections
School Utilization Percentages
Kirby Centennial Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
133
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Lakefield Intermediate School Lakefield District Secondary School ASG
71 Bridge Street, Lakefield, ON K0L 2H0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Lakefield District S.S.: and Intermediate School: Original Building built: Grades and Programs:
216 pupil places
33,312 square feet or 3,095 square metres
18.88 +/- acres or 7.64 ha
1975, Addition(s) n/a
Grade 7 and Grade 8
134
Enrolment History
Enrolment Projections
School Utilization Percentages
Lakefield Intermediate School
Facility Condition Index (FCI): 46.66% Total Event Costs: $ 2,975,485
135
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Lydia Trull Public School Courtice Secondary School ASG
80 Avondale Drive, Courtice, ON L1E 3C2 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Lydia Trull P.S.: Original Building built: Grades and Programs:
469 pupil places
50,735 square feet or 4,713 square metres
5.37 +/- acres or 2.17 ha
1998, Addition(s) N/A
Junior Kindergarten to Grade 8
136
Enrolment History
Enrolment Projections
School Utilization Percentages
Lydia Trull Public School
Facility Condition Index (FCI): 16.48% Total Event Costs: $ 1,575,956
137
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
M.J. Hobbs Senior Public School and Clarington Community Education Centre Clarington Central Secondary School ASG
2296 Taunton Road, Hampton, ON L0B 1J0 On The Ground capacity (OTG): Gross Floor Area (GFA):
Site Acreage for M.J. Hobbs Senior P.S.: Original Building built: Grades and Programs:
308 pupil places
28,470 square feet or 2,645 square metres
11.01 +/- acres or 4.46 ha
1966, Addition(s) n/a
Grade 4 to Grade 8and Clarington Community
Education Centre
138
Enrolment History
Enrolment Projections
School Utilization Percentages
M.J. Hobbs Senior Public School
Facility Condition Index (FCI): 71.18% Total Event Costs: $ 5,098,300
139
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Merwin Greer Public School Cobourg Collegiate Institute ASG
457 King Street East, Cobourg, ON K9A 1M7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Merwin Greer P.S.: Original Building built: Grades and Programs:
107 pupil places
11,236 square feet or 1,044 square metres
6.40 +/- acres or 2.59 ha
1952, Addition(s) 1957 and 1966
Junior Kindergarten to Grade 6
140
Enrolment History
Enrolment Projections
School Utilization Percentages
Merwin Greer Public School
Facility Condition Index (FCI): 22.14% Total Event Costs: $ 650,433
141
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Millbrook/South Cavan Public School Crestwood Secondary School ASG
47 Tupper Street, Millbrook, ON L0A 1G0
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Millbrook/South Cavan P.S.: Original Building built: Grades and Programs:
349 pupil places
36,571 square feet or 3,397 square metres
10.03 +/- acres or 4.06 ha
1960, Addition(s) 1965, 1987 and 2005
Junior Kindergarten to Grade 8
142
School Utilization Percentages
Enrolment History
Enrolment Projections
Millbrook/South Cavan Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
143
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Murray Centennial Public School East Northumberland Secondary School ASG
654 County Road 40, Trenton, ON K8V 5P4 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Murray Centennial P.S: Original Building built: Grades and Programs:
467 pupil places
42,745 square feet or 3,971 square metres
12.37 +/- acres or 5.00 ha
1968, Addition(s) 1972 and 2013
Junior Kindergarten to Grade 8 and Extended French Immersion
144
Enrolment History
Enrolment Projections
School Utilization Percentages
Murray Centennial Public School
Facility Condition Index (FCI): 39.91% Total Event Costs: $ 3,806,486
145
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Newcastle Public School and Child Care Centre Clarke High School ASG
50 Glass Court, Newcastle, ON L1B 1M5 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Newcastle P.S.: Original Building built: Grades and Programs:
554 pupil places
58,384 square feet or 5,424 square metres
9.733 +/- acres or 3.94 ha
1996, Addition(s) 2012 replacement Newcastle school
Junior Kindergarten to Grade 6 and Child Care Centre
146
Enrolment History
Enrolment Projections
School Utilization Percentages
Newcastle Public School
Facility Condition Index (FCI): 32.58% Total Event Costs: $ 3,626,019
147
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
North Cavan Public School Crestwood Secondary School ASG
2001 County Road #10, Cavan, ON L0A 1C0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for North Cavan P.S.: Original Building built: Grades and Programs:
130 pupil places
13,635 square feet or 1,267 square metres
8.06 +/- acres or 3.26 ha
1963, Addition(s) 1967 and 2013
Junior Kindergarten to Grade 6
148
Enrolment History
Enrolment Projections
School Utilization Percentages
North Cavan Public School
Facility Condition Index (FCI): 16.66% Total Event Costs: $ 594,516
149
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
North Hope Central Public School Port Hope High School ASG
3278 Ganaraska Road, Campbellcroft, ON L0A 1B0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for North Hope Central P.S.: Original Building built: Grades and Programs:
95 pupil places
9,663 square feet or 898 square metres
13.36 +/- acres or 5.4 ha
1960, Addition(s) 1967
Junior Kindergarten to Grade 6
150
Enrolment History
Enrolment Projections
School Utilization Percentages
North Hope Central Public School
Facility Condition Index (FCI): 93.44% Total Event Costs: $ 2,436,742
151
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
North Shore Public School and Child Care Centre Thomas A. Stewart Secondary School ASG
42 Pinecrest Avenue, Keene, ON K0L 2G0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for North Shore P.S.: Original Building built: Grades and Programs:
441 pupil places
46,965 square feet or 4,363 square metres
7.74 +/- acres or 3.13 ha
1990, Addition(s) n/a
Junior Kindergarten to Grade 8 and Child Care Centre
152
Enrolment History
Enrolment Projections
School Utilization Percentages
North Shore Public School
Facility Condition Index (FCI): 19.86% Total Event Costs: $ 1,789,193
153
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Northumberland Hills Public School East Northumberland Secondary School ASG
2246 Spring Street, Castleton, ON K0K 1M0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Northumberland Hills P.S.: Original Building built: Grades and Programs:
343 pupil places
34,106 square feet or 3,168 square metres
9.77 +/- acres or 3.95 ha
2010, Addition(s) Castleton and South Cramahe replacement
Junior Kindergarten to Grade 8
154
Enrolment History
Enrolment Projections
School Utilization Percentages
Northumberland Hills Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
155
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Norwood District Public School Norwood District High School ASG
28 Flora Street, Norwood, ON K0L 2V0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Norwood District P.S.: Original Building built: Grades and Programs:
323 pupil places
25,186 square feet or 2,340 square metres
4.987 +/- acres or 2.02 ha
1961, Addition(s) 1967 and 2012
Junior Kindergarten to Grade 8
156
Enrolment History
Enrolment Projections
School Utilization Percentages
Norwood District Public School
Facility Condition Index (FCI): 28.83% Total Event Costs: $ 2,080,520
157
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Orono Public School Clarke High School ASG
171 Church Street, Orono, ON L0B 1M0 On The Ground capacity (OTG):
Gross Floor Area (GFA): Site Acreage for Orono P.S.:
Original Building built: Grades and Programs:
176 pupil places
21,153 square feet or 1,965 square metres
10.097+/- acres or 4.09 ha
1968, Addition(s) 1971
Junior Kindergarten to Grade 6
158
Enrolment History
Enrolment Projections
School Utilization Percentages
Orono Public School
Facility Condition Index (FCI): 18.27% Total Event Costs: $ 882,669
159
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Otonabee Valley Public School Kenner Collegiate Vocational Institute ASG
580 River Road South, Peterborough, ON K9J 1E7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Otonabee Valley P.S.: Original Building built: Grades and Programs:
459 pupil places
46,370 square feet or 4,308 square metres
5.76 +/- acres or 2.33 ha
1964, Addition(s) 1995
Junior Kindergarten to Grade 6
160
Enrolment History
Enrolment Projections
School Utilization Percentages
Otonabee Valley Public School
Facility Condition Index (FCI): 22.21% Total Event Costs: $ 2,102,252
161
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Percy Centennial Public School Campbellford District High School ASG
129 Church Street, Warkworth, ON K0K 3K0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Percy Centennial P.S.: Original Building built: Grades and Programs:
245 pupil places
21,261 square feet or 1,975 square metres
8.357 +/- acres or 3.38 ha
1967, Addition(s) 2014
Junior Kindergarten to Grade 8
162
Enrolment History
Enrolment Projections
School Utilization Percentages
Percy Centennial Public School
Facility Condition Index (FCI): 33.99% Total Event Costs: $ 2,027,054
163
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Plainville Public School Cobourg Collegiate Institute ASG
4877 Burnham Street, Gores Landing, ON K0K 2E0
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Plainville P.S.: Original Building built: Grades and Programs:
199 pupil places
21,877 square feet or 2,032 square metres
7.00 +/- acres or 2.83 ha
1958, Addition(s) 1989
Junior Kindergarten to Grade 8
164
Plainville Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment History
Enrolment Projections
School Utilization Percentages
165
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Prince of Wales Public School Kenner Collegiate Vocational Institute ASG
1211 Monaghan Road South, Peterborough, ON K9J 5L4
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Prince of Wales P.S.: Original Building built: Grades and Programs:
622 pupil places
64,510 square feet or 5,993 square metres
7.99 +/- acres or 3.23 ha
1919, Addition(s) 1950 and 1965
Junior Kindergarten to Grade 8 and French Immersion
166
Enrolment History
Enrolment Projections
School Utilization Percentages
Prince of Wales Public School
Facility Condition Index (FCI): 79.35% Total Event Costs: $ 9,866,057
167
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Queen Elizabeth Public School Adam Scott Collegiate Vocational Institute ASG
830 Barnardo Avenue, Peterborough, ON K9H 5V9 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Queen Elizabeth P.S.: Original Building built: Grades and Programs:
295 pupil places
30,806 square feet or 2,862 square metres
6.97 +/- acres or 2.82 ha
1939, Addition(s) 1954, 1957 and 1967
Junior Kindergarten to Grade 8and Living and Life Skills (LLS)
168
School Utilization Percentages
Queen Elizabeth Public School
Facility Condition Index (FCI): 58.48% Total Event Costs: $ 3,810,141
Enrolment History
Enrolment Projections
169
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Queen Mary Public School Adam Scott Collegiate Vocational Institute ASG
1445 Monaghan Road North, Peterborough, ON K9J 5M8 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Queen Mary P.S.: Original Building built: Grades and Programs:
421 pupil places
52,320 square feet or 4,860 square metres
3.92 +/- acres or 1.59 ha
1912, Addition(s) 1947 and 1965
Junior Kindergarten to Grade 8
170
Queen Mary Public School
Facility Condition Index (FCI): 58.12% Total Event Costs: $ 5,021,856
Enrolment History
Enrolment Projections
School Utilization Percentages
171
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
R.F. Downey Public School Adam Scott Collegiate Vocational Institute ASG
1221 Neptune Street, Peterborough, ON K9H 7L9 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for R.F. Downey P.S.: Original Building built: Grades and Programs:
222 pupil places
22,850 square feet or 2,123 square metres
8.55 +/- acres or 3.46 ha
1967, Addition(s) 2012
Junior Kindergarten to Grade 6
172
Enrolment History
R.F. Downey Public School
Facility Condition Index (FCI): 65.09% Total Event Costs: $ 3,726,107
Enrolment Projections
School Utilization Percentages
173
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Ridpath Junior Public School Lakefield District Secondary School ASG
39 Ermatinger Street, Lakefield, ON K0L 2H0
On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Ridpath Junior P.S.: Original Building built: Grades and Programs:
435 pupil places
35,593 square feet or 3,307 square metres
5.937 +/- acres or 2.40 ha
1959, Addition(s) 1968, 1975, 2009 and 2012
Junior Kindergarten to Grade 6and French Immersion
174
Ridpath Junior Public School
Facility Condition Index (FCI): 15.22% Total Event Costs: $ 1,521,340
Enrolment History
Enrolment Projections
School Utilization Percentages
175
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Roger Neilson Public School Kenner Collegiate Vocational Institute ASG
550 Erskin Avenue, Peterborough, ON K9J 5T4 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Roger Neilson P.S.: Original Building built: Grades and Programs:
338 pupil places
39,157 square feet or 3,638 square metres
5.03 +/- acres or 2.03 ha
2004, Addition(s) n/a
Junior Kindergarten to Grade 6and Living and Life Skills (LLS)
176
Roger Neilson Public School
School Condition Inspections are to be completed during 2015
Facility Condition Index (FCI): - % Total Event Costs: $ n/a
Enrolment History
Enrolment Projections
School Utilization Percentages
177
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
Roseneath Centennial Public School Cobourg Collegiate Institute ASG
9047 Highway 45, Roseneath, ON K0K 2X0 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for Roseneath Centennial P.S.: Original Building built: Grades and Programs
196 pupil places
17,646 square feet or 1,646 square metres
7.02 +/- acres or 2.84 ha
1967, Addition(s) 1970 and 1995
Junior Kindergarten to Grade 8
178
Roseneath Centennial Public School
Facility Condition Index (FCI): 9.04% Total Event Costs: $ 486,325
Enrolment Projections
School Utilization Percentages
Enrolment History
179
Kawartha Pine Ridge District School Board 2015-2020 Long Term Accommodation Plan
School and Site Fact Sheet
S.T. Worden Public School Courtice Secondary School ASG
1462 Nash Road, Courtice, ON L1E 1S7 On The Ground capacity (OTG): Gross Floor Area (GFA): Site Acreage for S.T. Worden P.S.: Original Building built: Grades and Programs:
277 pupil places
30,365 square feet or 2,821 square metres
3.93 +/- acres or 1.59 ha
1956, Addition(s) 1963 and 1988
Junior Kindergarten to Grade 8
180
Enr