Upload
balint-laszlo
View
2
Download
1
Tags:
Embed Size (px)
Citation preview
210 x 297mm
September 2014
TRANSMISSION
CAPITALDELIVERYLondonPower Tunnels
In February 2011, National Grid
embarked upon a seven-year, £1 billion
project to rewire the capital. The
project uses deep underground tunnels
in order to minimise disruption while
facilitating on-going maintenance and
providing long-term flexibility.
Procurement efficiencies and strong
project management have encouraged
innovation and should bring the project
in ahead of schedule and 5–10%
under budget.
RE REORGANISING NEGOTIATING
REENGINEERING
�
�
�
�
Complex engineering challenge in a densely
populated area
Innovative solutions providing environmental
benefits
Strong performance management of multiple
contractual arrangements
Proactive stakeholder and community
outreach
210 x 297mm
London Power Tunnels
Project map
Awards
Complex tunnelling operations
Innovative solutions
Transformers
Ventilation
New, smaller transformers with water cooling reduce
substation footprint
Land developed into social and privately owned housing
Waste energy used to heat local school
Dynamic system modelling takes into account cooling effect
of the tunnel linings
Power supply size reduced and control system reduces
occasions when fans are run
Waste and spoil removal
Mining technology used to remove spoil from tunnels
Spoil used to fill legacy gas holder sites, reducing both
disposal and site remediation costs
�
�
�
�
�
�
�
�
�
�
International Tunnelling Awards 2012:
International Tunnelling Awards 2013:
Brownfield Briefing Award 2012:
Safety Initiatives Award
Sustainability Award
Best Re-use of Materials
Existing Substation
Phase 1 cable route
Existing cable route
Other existing routes
New Substation