624
LOCUST AVENUE & VINEYARD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS (REVISED) November 2, 2017

LOCUST AVENUE & VINEYARD AVENUE PROJECT TRAFFIC … · LOCUST AVENUE & VINEYARD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS (REVISED) November 2, 2017 Prepared by: Chris Pylant Carl Ballard,

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • ���������

    ��������������������������

    ��������������������������������������������������

    ��������������������� ������!��"���!#���������$���#�%���������"�

    LOCUST AVENUE & VINEYARD AVENUE PROJECT

    TRAFFIC IMPACT ANALYSIS (REVISED)

    November 2, 2017

  • LOCUST AVENUE & VINEYARD AVENUE PROJECT

    TRAFFIC IMPACT ANALYSIS (REVISED)

    November 2, 2017

    Prepared by:

    Chris Pylant ■ Carl Ballard, LEED GA ■ William Kunzman, P.E.

    Kunzman Associates, Inc.

    1111 Town & Country Road, Suite 34 ■ Orange, California 92868 5005 La Mart Drive, Suite 201 ■ Riverside, California 92507

    (714) 973-8383 ■ www.traffic-engineer.com JN 7010

    03/31/2018

  • TABLE OF CONTENTS EXECUTIVE SUMMARY

    I. INTRODUCTION ................................................................................................................. 1 A. Purpose and Objectives ................................................................................................... 1 B. Project Description .......................................................................................................... 1 C. Study Area ........................................................................................................................ 1 D. Analysis Scenarios ............................................................................................................ 2

    II. METHODOLOGY ................................................................................................................. 5 A. Intersection Analysis Methodology ................................................................................. 5 B. Roadway Segment Analysis Methodology ....................................................................... 5 C. Level of Service Standards ............................................................................................... 6 D. Thresholds of Significance ............................................................................................... 6

    III. EXISTING CONDITIONS ....................................................................................................... 8 A. Existing Traffic Controls & Intersection Geometry .......................................................... 8 B. Existing Traffic Volumes ................................................................................................... 8 C. Existing Levels of Service .................................................................................................. 8 D. General Plan General Plan/Renaissance Specific Plan Circulation Element .................... 9 E. Transit Service .................................................................................................................. 9

    IV. PROJECT TRIPS ................................................................................................................. 22 A. Trip Generation .............................................................................................................. 22 B. Trip Distribution ............................................................................................................. 22 C. Trip Assignment ............................................................................................................. 22 D. Project Trip Contribution Test ....................................................................................... 22

    V. FUTURE TRAFFIC VOLUMES .............................................................................................. 30 A. Method of Projection ..................................................................................................... 30 B. Future Traffic Volumes ................................................................................................... 30

    1. Existing Plus Project Traffic Volumes ................................................................... 30 2. Project Completion (Existing Plus Ambient Growth Plus Project) Traffic

    Volumes ................................................................................................................ 30 3. Cumulative Conditions (Existing Plus Ambient Growth Plus Project Plus

    Cumulative) Traffic Volumes ................................................................................ 31 4. General Plan Buildout (With Project) Traffic Volumes ......................................... 31

    VI. FUTURE LEVELS OF SERVICE ............................................................................................. 47 A. Existing Plus Project Roadway Segment & Intersection Level of Service ...................... 47 B. Project Completion (Existing Plus Ambient Growth Plus Project) Roadway

    Segment & Intersection Levels of Service ..................................................................... 47 C. Cumulative Conditions (Existing Plus Ambient Growth Plus Project Plus

    Cumulative) Roadway Segment & Intersection Levels of Service ................................. 47 D. General Plan Buildout (With Project) Roadway Segment & Intersection Levels

    of Service ....................................................................................................................... 48

    VII. MITIGATION MEASURES AND COST ESTIMATES ............................................................... 58

  • A. Intersection Improvements ........................................................................................... 58 B. Roadway Segment Improvements ................................................................................. 58

    VIII. CONCLUSIONS .................................................................................................................. 63 A. Off-Site Mitigation Measures ......................................................................................... 63 B. On-Site/Access Recommendations ................................................................................ 63

    APPENDICES Appendix A – Glossary of Transportation Terms Appendix B – Scoping Agreement Appendix C – Intersection Turning Movement Count Worksheets Appendix D – Intersection Delay and Level of Service Worksheets Appendix E – Preliminary Construction Cost Estimates for Congestion Management Program

  • LIST OF TABLES Table 1. Existing Roadway Segment Capacity Analysis ............................................................ 10 Table 2. Existing Intersection Delay and Level of Service ........................................................ 11 Table 3. Project Trip Generation .............................................................................................. 23 Table 4. Other Development Trip Generation ......................................................................... 32 Table 5. Existing Plus Project Roadway Segment Capacity Analysis ........................................ 50 Table 6. Existing Plus Project Intersection Delay and Level of Service .................................... 51 Table 7. Project Completion Roadway Segment Capacity Analysis ......................................... 52 Table 8. Project Completion Intersection Delay and Level of Service ..................................... 53 Table 9. Cumulative Conditions Roadway Segment Capacity Analysis .................................... 54 Table 10. Cumulative Conditions Intersection Delay and Level of Service ................................ 55 Table 11. General Plan Buildout (With Project) Roadway Segment Capacity Analysis .............. 56 Table 12. General Plan Buildout (With Project) Intersection Delay and Level of Service .......... 57 Table 13. Summary of Intersection Improvements and Costs ................................................... 60 Table 14. Project Fair Share Intersection Traffic Contribution .................................................. 61 Table 15. Roadway Segment Improvements, Cost, and Fair Share Contribution ...................... 62

  • LIST OF FIGURES Figure 1. Project Location Map.................................................................................................... 3 Figure 2. Site Plan ........................................................................................................................ 4 Figure 3. Existing Through Travel Lanes and Intersection Controls .......................................... 12 Figure 4. Existing Average Daily Traffic Volumes ...................................................................... 13 Figure 5. Existing Morning Peak Hour Intersection Turning Movement Volumes .................... 14 Figure 6. Existing Evening Peak Hour Intersection Turning Movement Volumes ..................... 15 Figure 7. City of Rialto General Plan Circulation Element ......................................................... 16 Figure 8. City of Rialto General Plan Roadway Cross-Sections .................................................. 17 Figure 9. City of Rialto Truck Routes ......................................................................................... 18 Figure 10. Renaissance Specific Plan Bicycle and Pedestrian Circulation Plan ............................ 19 Figure 11. Existing Pedestrian Facilities ....................................................................................... 20 Figure 12. Existing Transit/Rail Routes and Service Areas........................................................... 21 Figure 13. Project Trip Distribution - Cars ................................................................................... 24 Figure 14. Project Trip Distribution - Trucks ................................................................................ 25 Figure 15. Project Average Daily Traffic Volumes ....................................................................... 26 Figure 16. Project Morning Peak Hour Intersection Turning Movement Volumes ..................... 27 Figure 17. Project Evening Peak Hour Intersection Turning Movement Volumes ...................... 28 Figure 18. Project Trip Contribution Test Volumes ..................................................................... 29 Figure 19. Other Development Location Map ............................................................................. 34 Figure 20. Existing Plus Project Average Daily Traffic Volumes ................................................... 35 Figure 21. Existing Plus Project Morning Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 36 Figure 22. Existing Plus Project Evening Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 37 Figure 23. Project Completion Average Daily Traffic Volumes .................................................... 38 Figure 24. Project Completion Morning Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 39 Figure 25. Project Completion Evening Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 40 Figure 26. Cumulative Conditions Average Daily Traffic Volumes .............................................. 41 Figure 27. Cumulative Conditions Morning Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 42 Figure 28. Cumulative Conditions Evening Peak Hour Intersection Turning Movement

    Volumes ...................................................................................................................... 43 Figure 29. General Plan Buildout (With Project) Average Daily Traffic Volumes ........................ 44 Figure 30. General Plan Buildout With Project Morning Peak Hour Intersection Turning

    Movement Volumes ................................................................................................... 45

  • Figure 31. General Plan Buildout With Project Evening Peak Hour Intersection Turning Movement Volumes ................................................................................................... 46

    Figure 32. Circulation Recommendations ................................................................................... 64

  • EXECUTIVE SUMMARY  The purpose of this report is to provide an assessment of potential traffic impacts resulting from development of the proposed Locust Avenue & Vineyard Avenue project and to identify the traffic mitigation  measures  necessary  to  maintain  the  established  level  of  service  standard  for  the elements of  the  impacted  roadway system.   The  traffic  issues  related  to  the proposed  land use and development have been evaluated in the context of the California Environmental Quality Act (CEQA).  The City of Rialto  is the  lead agency responsible for preparation of the traffic  impact analysis,  in accordance with California Environmental Quality Act authorizing legislation.  This report analyzes traffic  impacts  for the anticipated opening date with occupancy of the development  in Opening Year 2019, at which time  it will be generating trips at  its full potential.   This report also analyzes potential project traffic impacts for General Plan Buildout (Post‐2035) traffic conditions.  Although  this  is a  technical  report, every effort has been made  to write  the  report  clearly and concisely.  To assist the reader with those terms unique to transportation engineering, a glossary of terms is provided in Appendix A.  A.  Project Description 

     The project site  is  located at the northeast corner of the Locust Avenue/Vineyard Avenue intersection  in  the  City  of  Rialto.    The  6.32  acre  project  site  is  proposed  to  consist  of  a 120,600 square foot warehouse facility.  Access is proposed to be provided to Locust Avenue and Vineyard Avenue.  For purposes of this analysis, the project is planned to be fully operational by year 2019.  

    B.  Traffic Conditions  The  study  area  roadway  segments  currently operate  at  acceptable  Levels of  Service  (see Table 1).  The  study area  intersections  currently operate within acceptable  Levels of Service during the peak hours for Existing traffic conditions (see Table 2).  The  proposed  project  is  forecast  to  generate  approximately  719  daily  passenger  car equivalent trips, 59 passenger car equivalents trips of which will occur during the morning peak hour and 64 passenger car equivalent trips of which will occur during the evening peak hour (see Table 3).  The study roadway segments are forecast to operate within acceptable Levels of Service for Existing Plus Project traffic conditions (see Table 5).    

  • ii 

    The  proposed  project  is  forecast  to  result  in  no  significant  traffic  impacts  at  the  study intersections for Existing Plus Project traffic conditions (see Table 6).  The study roadway segments are forecast to operate within acceptable Levels of Service for Project Completion traffic conditions (see Table 7).  The  proposed  project  is  forecast  to  result  in  no  significant  traffic  impacts  at  the  study intersections for Project Completion traffic conditions (see Table 8).  As shown in Table 5, the following roadway segments are forecast to operate at a deficient Level of Service (E or F) for Cumulative traffic conditions without improvements (see Table 9):  ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue ■ Locust Avenue from Vineyard Avenue to Casmalia Street  The study roadway segments are forecast to operate within acceptable Levels of Service for Cumulative traffic conditions with improvements (see Table 9).  The  proposed  project  is  forecast  to  result  in  a  significant  traffic  impact  at  the  following study  intersections  based  on  the  net  change  in  delay  for  Cumulative  traffic  conditions without improvements (see Table 10):  

    Alder Avenue (NS) at: Sierra Lakes Parkway/Casmalia Street (EW) ‐ #1  (morning/evening peak hours) SR‐210 Freeway Westbound Ramps (EW) ‐ #2  (evening peak hour) 

     The  proposed  project  is  forecast  to  result  in  no  significant  traffic  impacts  at  the  study intersections for Cumulative traffic conditions with improvements (see Table 10).  The following roadway segments are forecast to operate at a deficient Level of Service (E or F) for General Plan Buildout traffic conditions with improvements (see Table 11).  ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue ■ Locust Avenue from Vineyard Avenue to Casmalia Street  The  proposed  project  is  forecast  to  result  in  a  significant  traffic  impact  at  the  following study  intersections  based  on  the  net  change  in  delay  for  General  Plan  Buildout  traffic conditions without improvements (see Table 12):  

    Alder Avenue (NS) at: Sierra Lakes Parkway/Casmalia Street (EW) ‐ #1  (morning/evening peak hours) SR‐210 Freeway Westbound Ramps (EW) ‐ #2  (evening peak hour)  

    Locust Avenue (NS) at: Bohnert Avenue (EW) ‐ #4      (morning/evening peak hours) Casmalia Street (EW) ‐ #8      (morning/evening peak hours) 

     

  • iii 

    The  proposed  project  is  forecast  to  result  in  no  significant  traffic  impacts  at  the  study intersections for General Plan Buildout traffic conditions with improvements (see Table 12).  

    C.  Off‐Site Mitigation Measures  The  proposed  project  shall  contribute  on  a  fair  share  basis  through  an  adopted development impact fee program, or in dollar equivalent in lieu mitigation contributions, in the implementation of the improvements identified in Section VI and summarized  in Table 13 and Table 15.  

    D.  On‐Site/Access Recommendations  Site‐specific circulation and access recommendations are depicted on Figure 32.  The  proposed  project  driveways  shall  be  constructed  in  conformance with  City  of  Rialto standards, including provisions for sight distance and truck turning path requirements.  Locust Avenue along the project boundary shall be constructed at  its ultimate half‐section width, including landscaping and parkway improvements in conjunction with development, as necessary.  Vineyard  Avenue  along  the  project  boundary  shall  be  constructed  at  its  ultimate  half‐section  width,  including  landscaping  and  parkway  improvements  in  conjunction  with development, as necessary.  On‐site  traffic  signing  and  striping  shall  be  submitted  for  City  of  Rialto  approval  in conjunction with detailed construction plans for the project.  Off‐street parking shall be provided to meet City of Rialto parking code requirements.  

    1

    ChrisText Box

  •  

    I.  INTRODUCTION  This section discusses the project  location and proposed development and study area.   Figure 1 shows the project location map and Figure 2 illustrates the project site plan.  A.  Purpose and Objectives 

     The purpose of this report is to provide an assessment of potential traffic impacts resulting from  development  of  the  proposed  Locust  Avenue  &  Vineyard  Avenue  project  and  to identify  the  traffic  mitigation  measures  necessary  to  maintain  the  established  level  of service  standard  for  the  elements  of  the  impacted  roadway  system.    The  traffic  issues related to the proposed  land use and development have been evaluated  in the context of the California Environmental Quality Act (CEQA).  The  City  of  Rialto  is  the  lead  agency  responsible  for  preparation  of  the  traffic  impact analysis,  in  accordance with  California  Environmental Quality  Act  authorizing  legislation.  This report analyzes traffic impacts for the anticipated opening date with occupancy of the development  in  Opening  Year  2019,  at which  time  it will  be  generating  trips  at  its  full potential.   This report also analyzes potential project traffic  impacts for Long‐Range (Post‐2035) traffic conditions.  Although this  is a technical report, every effort has been made to write the report clearly and concisely.  To assist the reader with those terms unique to transportation engineering, a glossary of terms is provided in Appendix A.  

    B.  Project Description  The project site  is  located at the northeast corner of the Locust Avenue/Vineyard Avenue intersection  in  the  City  of  Rialto.    The  6.32  acre  project  site  is  proposed  to  consist  of  a 120,600 square foot warehouse facility.  Access is proposed to be provided to Locust Avenue and Vineyard Avenue.  For purposes of this analysis, the project is planned to be fully operational by year 2019.  

    C.  Study Area  Based on  the City‐approved  scoping  agreement  contained  in Appendix B,  the  study  area consists of the following intersections and roadway segments located in the City of Rialto:  Study Intersections ■ Alder Avenue (NS) at Sierra Lakes Parkway/Casmalia Street (EW)1 ‐ #1 ■ Alder Avenue (NS) at SR‐210 Freeway Westbound Ramps (EW) ‐ #2 ■ Alder Avenue (NS) at SR‐210 Freeway Eastbound Ramps (EW) ‐ #3 ■ Locust Avenue (NS) at Bohnert Avenue Parkway (EW) ‐ #4 ■ Locust Avenue (NS) at North Project Driveway (EW) ‐ #5 

                                                                1 NS = North‐South Roadway; EW = East‐West Roadway; SR = State Route 

    2

  • 2

    ■ Locust Avenue (NS) at South Project Driveway (EW) - #6 ■ Locust Avenue (NS) at Vineyard Avenue (EW) - #7 ■ Locust Avenue (NS) at Casmalia Street (EW) - #8 ■ Locust Avenue (NS) at Renaissance Parkway (EW) - #9 ■ Cedar Avenue (NS) at Casmalia Street (EW) - #10 Study Roadway Segments ■ Locust Avenue between Bohnert Avenue and Vineyard Avenue ■ Locust Avenue between Vineyard Avenue and Casmalia Street ■ Casmalia Street between Locust Avenue and Linden Avenue

    D. Analysis Scenarios The following scenarios are analyzed in accordance with City of Rialto Traffic Impact Analysis Report Guidelines and Requirements (December 2013): (1) Existing Conditions; (2) Existing Plus Project Conditions2; (3) Project Completion (Existing Plus Ambient Growth Plus Project); (4) Cumulative Conditions (Existing Plus Ambient Growth Plus Project Plus Cumulative); (5) General Plan Buildout (With Project) Conditions.

    2 The existing plus project conditions has been analyzed to comply with the Sunnyvale West Neighborhood Association

    v. City of Sunnyvale CEQA court case. This scenario assumes the full development of the proposed project and full absorption of the proposed project trips on the circulation system at the present time.

    3

  • 4

  • 5

  •  

    II.  METHODOLOGY  The scope of  this  traffic  impact analysis  is based on  the guidance provided  in  the City of Rialto Traffic Impact Analysis Report Guidelines and Requirements (December 2013).  A.  Intersection Analysis Methodology 

     The  technique  used  to  assess  the  performance  of  an  intersection  is  known  as  the intersection  delay  method  based  on  the  procedures  contained  in  the  2010  Highway Capacity Manual  (Transportation Research Board, 2010).   The methodology compares  the volume of traffic using the  intersection to the capacity of the  intersection to calculate the delay  associated  with  associated  with  the  traffic  control  at  the  intersection.    The intersection delay  is then correlated to a performance measure known as Level of Service based on the following thresholds:  

    Level of 

    Service 

    Intersection Control Delay (Seconds / Vehicle) Signalized Intersection 

    Unsignalized Intersection 

    A  ≤ 10.0  ≤ 10.0 

    B  > 10.0 to ≤ 20.0  > 10.0 to ≤ 15.0 

    C  > 20.0 to ≤ 35.0  > 15.0 to ≤ 25.0 

    D  > 35.0 to ≤ 55.0  > 25.0 to ≤ 35.0 

    E  > 55.0 to ≤ 80.0  > 35.0 to ≤ 50.0 

    F  > 80.0  > 50.0 Source: Highway Capacity Manual 2010 (Transportation Research Board, 2010). 

     Level  of  Service  is  used  to  qualitatively  describe  the  performance  of  a  roadway  facility, ranging  from  Level  of  Service  A  (free‐flow  conditions)  to  Level  of  Service  F  (extreme congestion and system failure).  Signalized intersection analysis input parameters for Highway Capacity Manual calculations were used  in accordance with Exhibit C of the City of Rialto Traffic  Impact Analysis Report Guidelines and Requirements (December 2013).  

    B.  Roadway Segment Analysis Methodology  Roadway  segments are analyzed based on a volume  to  capacity analysis of average daily traffic volumes compared to the roadway capacities defined by the City of Rialto as follows:      

    6

  •  

      

    Roadway Classification 

    Numberof 

    Lanes 

    Two‐Way Traffic Volume (ADT)1,2 

    LOS C  LOS D  LOS E 

    Local  2  2,500 ‐ 2,799  2,800 ‐ 3,099  3,100 + 

    Collector (60' or 64')  2  9,900 ‐ 11,199  11,200 ‐ 12,499  12,500+ 

    Industrial (45')  2  9,900 ‐ 11,199  11,200 ‐ 12,499  12,500+ 

    Arterial3  2  14,400 ‐ 16,199  16,200 ‐ 17,999  18,000+ 

    Secondary Highway  4  16,900 ‐ 19,399  19,400 ‐ 21,999  22,000+ 

    Modified Arterial (100')  4  26,200 ‐ 29,599  29,600 ‐ 32,999  33,000+ 

    Arterial (120')  6  38,700 ‐ 44,099  44,100 ‐ 49,499  49,500+ 1  All capacity figures are based on optimum conditions and are intended as guidelines for planning purposes only. 

    2  Maximum two‐way ADT values are based on the 1999 Modified Highway Capacity Manual Level of Service Tables. 

    3  Two‐lane roads designated as future arterials that conform to arterial design standards for vertical and horizontal alignments are analyzed as arterials. 

    Source:    City  of  Rialto  Public  Works  Department,  Traffic  Impact  Analysis  Report Guidelines and Requirement, December 2013.  

    C.  Level of Service Standards  The City of Rialto 2010 General Plan Update  contains  the  following policies applicable  to Level of Service standards within the City:  ■ Policy 4‐1.20: Design City streets so that signalized  intersections operate at Level of 

    Service  (LOS) D or better during  the morning and evening peak hours, and  require new development to mitigate traffic impacts that degrade LOS below that level.  The one exception will be Riverside Avenue south of the Metrolink  tracks all the way to the City’s southern border, which can operate at LOS E. 

    ■ Policy 4‐1.21: Design City streets so  that unsignalized  intersections operate with no vehicular movement having  an  average delay  greater  than 120  seconds during  the morning and evening peak hours, and  require new development  to mitigate  traffic impacts that increase delay above that level. 

     Based  on  the  above  thresholds,  signalized  study  intersections  and  roadway  segments operating  at  Level  of  Service  E  or  F  are  considered  deficient.    Unsignalized  study intersections operating  at  Level of  Service  F with  greater  than  120  seconds  of delay  are considered deficient.  

    D.  Thresholds of Significance  In accordance with Exhibit F of the City of Rialto Traffic  Impact Analysis Report Guidelines and Requirements (December 2013), a significant impact is deemed to occur if:  

    7

  •  

    ■ The  project  causes  the  worst  vehicular  movement  at  an  unsignalized  study intersection to exceed 120 seconds; or 

    ■ The project causes a signalized study  intersection or roadway segment to  fall below Level of Service D  (except Riverside Avenue  from  the Metrolink  tracks  to  the City’s southern border, which can operate at LOS E); or 

    ■ The project causes the peak hour delay to increase as follows:  

    Level of Service  Increase in Delay (seconds) 

    A/B  10.0 seconds 

    C  8.0 seconds 

    D  5.0 seconds 

    E  2.0 seconds 

    F  1.0 seconds 

    8

  •  

    III.  EXISTING CONDITIONS  A.  Existing Traffic Controls & Intersection Geometry 

     Figure 3  identifies  the Existing number of  through  lanes,  intersection  traffic controls, and intersection geometry based on a field survey of the study area.  Regional access  to/from  the project site  is provided by  the SR‐210 Freeway.   North‐south local  circulation  in  the  project  vicinity  is  primarily  provided  by  Locust Avenue  and Alder Avenue.    East‐west  roadways  that provide  local  circulation  in  the project  vicinity  include Casmalia Street, Bohnert Avenue, and Renaissance Parkway.  

    B.  Existing Traffic Volumes  Existing peak hour traffic volumes are based upon morning peak period and evening peak period intersection turning movement counts conducted in June 2017 and December 2016 and during  typical weekday  conditions.   The morning peak period was  counted between 7:00 AM and 9:00 AM and the evening peak period was counted between 4:00 PM and 6:00 PM.  The actual peak hour within the peak period is the four consecutive 15‐minute periods with the highest total volume when all movements are added together.  Thus, the weekday evening peak hour at one intersection may be 4:45 PM to 5:45 PM if those four consecutive 15‐minute  periods  have  the  highest  combined  volume.    Intersection  Turning Movement count worksheets are provided in Appendix C.  The peak hour  intersection  turning movement  counts were  converted  into passenger  car equivalents  in accordance with the City of Rialto Traffic  Impact Analysis Report Guidelines and  Requirements  (1.5  passenger  car  equivalents  for  2‐axle  trucks,  2.0  passenger  car equivalents  for 3‐axle  trucks, and 3.0 passenger car equivalents  for trucks with 4 or more axles).  The existing  average daily  traffic  volumes have been directly measured or  factored  from peak hour volumes using the following formula for each intersection leg based on measured daily traffic counts at 3 representative locations in the study area:  

    PM Peak Hour (Approach Volume + Exit Volume) x 13.8 = Leg Volume.  Figure 4 depicts the existing average daily traffic volumes.   Figure 5 and Figure 6 show the existing morning peak hour and evening peak hour intersection turning movement volumes (in passenger car equivalents), respectively.  

    C.  Existing Levels of Service  Existing roadway segment capacity analysis  is shown  in Table 1.   As shown  in Table 1, the study area roadway segments currently operate at acceptable Levels of Service.  The morning  and evening peak hour  intersection delay  and  Levels of  Service  for Existing traffic conditions have been calculated and are shown in Table 2.  As shown in Table 2, the 

    9

  • 9

    study area intersections currently operate within acceptable Levels of Service during the peak hours for Existing traffic conditions. Existing intersection delay and Level of Service worksheets are provided in Appendix D.

    D. General Plan General Plan/Renaissance Specific Plan Circulation Element The City of Rialto General Plan Circulation Element is shown on Figure 7. Existing and future roadways are included in the Circulation Element of the General Plan and are graphically depicted on Figure 7. This figure shows the nature and extent of arterial highways that are needed to adequately serve the ultimate development depicted by the Land Use Element of the General Plan. The City of Rialto General Plan roadway cross‐sections are shown on Figure 8. The City of Rialto designated truck route map is illustrated on Figure 9. The Renaissance Specific Plan bicycle and pedestrian circulation plan is illustrated on Figure 10. Existing pedestrian facilities adjacent to the project site are shown on Figure 11.

    E. Transit Service Figure 12 shows the City of Rialto transit/rail routes and service areas. As shown on Figure 12, Omnitrans Route 22 runs along Locust Avenue and Bohnert Avenue, providing transit connection between Rialto and the Arrowhead Regional Medical Center in Colton.

    10

  • CapacityNumber for Deficient

    of Roadway Level of Level ofFrom To Lanes Classification Service D Service?

    Bohnert Avenue Vineyard Avenue 11,300 2 Secondary Arterial 17,999 NoVineyard Avenue Casmalia Street 11,400 2 Secondary Arterial 17,999 No

    Casmalia Street

    Sierra Lakes Parkway/ Casmalia Street (EW) ‐ #1 Linden Avenue 6,500 2 Secondary Arterial 17,999 No

    1  Average Daily Traffic Volume in Passenger Car Equivalents (PCEs).

    Table 1

    Existing Roadway Segment Capacity Analysis

    Segment 

    Average Daily Traffic Volume1Roadway

    Locust Avenue

    11

  • TrafficJurisdiction Control3 L T R L T R L T R L T R Morning Evening

    Sierra Lakes Parkway/Casmalia Street (EW) ‐ #1 Rialto TS 1 2 d 1 2 1 1 1 d 1 1 1 20.7‐C 25.9‐C

    SR‐210 WB Ramps (EW) ‐ #2 Caltrans TS 1 2 0 0 2 d 0 0 0 1 0.5 0.5 17.1‐B 18.0‐B

    SR‐210 EB Ramps (EW) ‐ #3 Caltrans TS 0 2 d 1 2 0 0.5 0.5 1 0 0 0 14.9‐B 17.1‐B

    Bohnert Avenue (EW) ‐ #4 Rialto CSS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 14.6‐B 18.2‐C

    Vineyard Avenue (EW) ‐ #7 Rialto CSS 0.5 0.5 d 0.5 0.5 d 0 1 0 0 1 0 13.4‐B 16.8‐C

    Casmalia Street (EW) ‐ #8 Rialto TS 1 1.5 0.5 1 1.5 0.5 1 1 d 1 1 d 20.1‐C 22.0‐C

    Renaissance Parkway (EW) ‐ #9 Rialto TS 1 1 d 1 1 1 1 1.5 0.5 1 1.5 0.5 22.4‐C 22.5‐C

    Casmalia Street (EW) ‐ #10 Rialto AWS 0 0 0 0.5 0 0.5 0.5 0.5 0 0 0.5 0.5 7.9‐A 8.5‐A

    1

    2

    3TS = Traffic Signal; CSS = Cross Street Stop; AWS = All Way Stop

    Alder Avenue (NS) at:

    Delay and Level of Service has been calculated using the following analysis software: Vistro, Version 4.00‐00.  Per the 2010 Highway Capacity Manual, overall average intersection delay and Level of Service are shown for intersections with traffic signal or all way stop control.  For intersections with cross street stop control, the delay and Level of Service for the worst individual movement (or movements sharing a single lane) are shown.

    When a right turn lane is designated, the lane can either be striped or unstriped.  To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes.L = Left; T = Through; R = Right; d = De Facto Right Turn

    Cedar Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Table 2

    Existing Intersection Delay and Level of Service

    Intersection Approach Lanes1 Peak HourDelay‐LOS2Northbound Southbound Eastbound Westbound

    Intersection

    12

  • 13

  • 14

  • 15

  • 16

  • 17

  • 18

  • 19

  • 20

  • 21

  • 22

  •  

    22 

    IV.  PROJECT TRIPS  A.  Trip Generation 

     Trip  generation  rates were  determined  for  daily  trips, morning  peak  hour  inbound  and outbound trips, and evening peak hour  inbound and outbound trips for the proposed  land use.  The number of trips forecast to be generated by the proposed project are determined by multiplying the trip generation rates by the land use quantity.  Table 3 shows the project trip generation based upon rates obtained from the  Institute of Transportation Engineers, Trip Generation Manual, 9th Edition, 2012.  The project trip generation has been converted into  passenger  car  equivalent  trips  in  accordance  with  the  truck  percentages  and  PCE factors  outlined  in  the  City  of  Rialto  Traffic  Impact  Analysis  Report  Guidelines  and Requirements (2014).  As shown  in Table 3, the proposed project  is forecast to generate approximately 719 daily passenger car equivalent trips, 59 passenger car equivalent trips of which will occur during the morning peak hour and 64 passenger car equivalent trips of which will occur during the evening peak hour.  

    B.  Trip Distribution  Figure  13  and  Figure  14  show  the  project  trip  distribution  patterns  for  cars  and  trucks, respectively.   The  forecast project trip distributions are based on review of existing traffic data,  surrounding  land  uses,  and  the  local  and  regional  roadway  facilities  in  the  project vicinity.  

    C.  Trip Assignment  Based  on  the  identified  trip  generation  and  distributions,  project  average  daily  traffic volumes have been calculated and shown on Figure 15.   Morning and evening peak hour intersection turning movement volumes expected from the project are shown on Figure 16 and Figure 17, respectively.  

    D.  Project Trip Contribution Test  Figure 18  shows  the  forecast project  trip  contribution  test used  for  identifying  the  study area.   The City of Rialto  requires  the  study area  to  include any  intersection of  streets on which  at  least  one  street  is  classified  as  Collector  or  above  and  the  proposed  project  is forecast  to  contribute more  than  50  peak  hour  trips.    Figure  18  shows  the  project  trip contribution  test volumes on  the  roadways adjacent  to  the potential  intersection analysis locations until the project volume has dropped below the 50 peak hour trip threshold. 

    23

  • Passenger 2 Axle 3 Axle 4+ Axle TotalQuantity Units2 Car Truck Truck Truck Trucks Total

    Land Use: Warehousing 120.600    TSF 60.0% 0.8% 11.2% 28.0% 40.0% 100%

    Trip Generation Ratesin trips per TSF

    Daily 2.136 0.029 0.399 0.997 1.424 3.56

    Morning Peak Hour 0.180 0.002 0.034 0.084 0.120 0.30Evening Peak Hour 0.192 0.003 0.036 0.090 0.128 0.32

    Trip Generation in Vehicles

    Daily 258             3                 48               120             171             429            Morning Peak Hour

    Inbound 17               ‐             3                 8                 11               28              Outbound 4                 ‐             1                 2                 3                 7                

    Total 21               ‐             4                 10               14               35              Evening Peak Hour

    Inbound 6                 ‐             1                 3                 4                 10              Outbound 17               ‐             3                 8                 11               28              Total 23               ‐             4                 11               15               38              

    Passenger Car Equivalent(PCE) Factor3 1.00 1.50 2.00 3.00

    Trip Generation in PCEsDaily 258             5                 96               360             461             719            Morning Peak Hour

    Inbound 17               ‐             6                 24               30               47              Outbound 4                 ‐             2                 6                 8                 12              Total 21               ‐             8                 30               38               59              

    Evening Peak HourInbound 6                 ‐             2                 9                 11               17              Outbound 17               ‐             6                 24               30               47              Total 23               ‐             8                 33               41               64              

    1  Source:  Institute of Transportation Engineers, Trip Generation Manual, 9th Edition, 2012, Land Use Code 150 and City of Rialto Traffic Impact Analysis

       Report Guidelines and Requirements, 2014.

    2  TSF = Thousand Square Feet

    3  Passenger Car Equivalent factors are from City of Rialto Traffic Impact Analysis Report Guidelines and Requirements, 2014.  

    Table 3

    Type of Vehicle

    Descriptor

    Project Trip Generation1

    24

  • 25

  • 26

  • 27

  • 28

  • 29

  • 30

  •  

    30 

    V.  FUTURE TRAFFIC VOLUMES  A.  Method of Projection 

     To assess  future  traffic conditions, existing  traffic  is combined with project  trips, ambient growth, and other development.  The project completion year for analysis purposes in this report is 2019.  1.  Ambient Growth 

     To account for ambient growth on roadways, existing traffic volumes were increased by two percent per year over a two year period.  

    2.  Other Development  A  list of other pending or approved development projects were provided by City of Rialto  staff.    Table  4  shows  the  forecast  trip  generation  for  other  developments forecast to add future traffic to the study area.  Figure 19 shows the location of other developments.  

    3.  General Plan Buildout Conditions  General Plan Buildout  traffic volumes are based on  the “Year 2035 With RSPA Peak Hour Traffic Volumes” contained in the Renaissance Specific Plan Amendment [RSPA] Traffic  Impact Analysis (LSA, 2015).   The forecast turning movements were reviewed for  reasonableness  and  adjusted  as  necessary  to  ensure  traffic  growth  over cumulative (Year 2019) traffic conditions.  

    B.  Future Traffic Volumes  

    1.  Existing Plus Project Traffic Volumes  The traffic volumes for Existing Plus Project conditions have been derived by adding the project generated trips to existing traffic volumes.   Existing Plus Project average daily  traffic  volumes  are  shown  on  Figure  20.    Existing  Plus  Project morning  and evening peak hour  intersection  turning movement volumes are shown on Figure 21 and Figure 22, respectively.  

    2.  Project Completion (Existing Plus Ambient Growth Plus Project) Traffic Volumes  To  assess  traffic  conditions  at  project  completion,  ambient  growth  and  project‐generated  trips  are  added  to  existing  traffic  volumes.    Project Completion  average daily  traffic  volumes  are  shown  on  Figure  23.    Project  Completion  morning  and evening peak hour  intersection  turning movement volumes are shown on Figure 24 and Figure 25, respectively.  

    31

  • 31

    3. Cumulative Conditions (Existing Plus Ambient Growth Plus Project Plus Cumulative) Traffic Volumes To assess cumulative traffic conditions, existing traffic is combined with ambient growth, project generated trips, and trips generated by other development. Cumulative Conditions average daily traffic volumes are shown on Figure 26. Cumulative Conditions morning and evening peak hour intersection turning movement volumes are shown on Figure 27 and Figure 28, respectively.

    4. General Plan Buildout (With Project) Traffic Volumes General Plan Buildout (With Project) traffic conditions represent full buildout of the City of Rialto according to the General Plan Land Use Element/Renaissance Specific Plan. As previously described, General Plan buildout traffic volumes are based on the traffic forecasts contained in the Renaissance Specific Plan Amendment [RSPA] Traffic Impact Analysis (LSA, 2015). General Plan Buildout (With Project) average daily traffic volumes are shown on Figure 29. General Plan Buildout (With Project) morning and evening peak hour intersection turning movement volumes are shown on Figure 30 and Figure 31, respectively.

    32

  • 1 of 2

    Include? In Out Total In Out Total1 General Light Industrial Yes 618.400 TSF 636 85 721 94 667 761 5,4702 Alder Avenue Distribution Center Yes 630.000 TSF 249 67 316 84 253 337 3,7613 Warehouse Yes 300.800 TSF 94 24 118 32 94 126 1,4034 I-210 Gateway Center Yes 614.800 TSF 192 49 241 65 192 257 2,8685 B & B Plastics Yes 150.000 TSF 64 17 81 22 64 86 9636 Baseline Logistics Center Yes 725.000 TSF 227 57 284 75 227 302 3,3837 PA 108 Yes

    - Monster Beverage 1,094.900 TSF 434 115 549 148 441 589 6,533- Building 5 614.848 TSF 571 73 644 458 584 1,042 6,353- Building 6 649.800 TSF 152 939 1,091 941 43 981 9,353- Remaining Warehouse 416.000 TSF 496 132 628 140 417 557 2,393

    Subtotal 1,653 1,259 2,912 1,687 1,485 3,172 24,6328 Renaissance Marketplace Yes 302 166 468 661 821 1,482 17,7809 Pannatoni 5 Yes 200.000 TSF 77 22 99 26 78 104 1,193

    10 Morin Warehouse Yes 200.000 TSF 77 22 99 26 78 104 1,19311 State Pipe Yes 43.357 TSF 42 12 54 18 34 52 277

    Arco Center Yes

    - Fast Food w/ Drive Through4 5.800 TSF 68 66 134 49 45 94 2,653- Car Wash5 1 Site 18 18 36 55 55 110 900- Quick Lubrication Vehicle Shop 2 Bay 4 2 6 6 5 11 80- Motel 77 RM 12 22 34 20 17 37 434

    Subtotal 102 108 210 130 122 252 4,067NWC Alder/Renaissance Yes- Service Station w/ Convenience Market- Fast Food w/ Drive Through 4.500 TSF 53 51 104 38 35 73 2,059- Fast Food w/o Drive Through 1.000 TSF 26 18 44 13 13 26 716- High Turnover (Sit-Down) Restaurant- Motel 100 RM 16 29 45 25 22 47 563

    Subtotal 188 189 377 196 186 382 6,19614 Locust/Stonehurst Warehouse Yes 150.000 TSF 59 17 76 18 60 78 89615 Locust/Lowell Warehouse Yes 150.000 TSF 59 17 76 18 60 78 89616 Prologis Building 7 Yes 473.000 TSF 155 20 175 47 182 229 2,33917 Mobile Mini Yes

    - Existing -30 -29 -59 -20 -19 -39 -389- Proposed Expansion 33 32 65 22 21 43 428

    Subtotal 3 3 6 2 2 4 3918 Prologis Building 5 Yes 384.893 TSF 155 42 197 51 155 206 2,29719 I-210 Logistics Center III 730.000 TSF 294 72 366 97 294 391 4,35720 Shaw Development Warehouse 175.900 TSF 70 18 88 23 70 93 1,050

    12

    162

    Table 4

    Other Development Trip Generation1,2

    Traffic Analysis

    Zone Name/Land Use

    Peak Hour

    DailyMorning Evening

    Quantity Units3

    108 108 216 2,604

    2.000 TSF 12 10

    13

    16 FP 81 81

    22 12 8 20 254

    33

  • 2 of 2

    Include? In Out Total In Out Total

    Table 4

    Other Development Trip Generation1,2

    Traffic Analysis

    Zone Name/Land Use

    Peak Hour

    DailyMorning Evening

    Quantity Units3

    21 Alder Avenue High-Cube Warehouse 123.000 TSF 18 4 22 6 18 24 26322 Truck Yard (Locust/Lowell) TSF 65 64 129 63 63 126 450

    23 NEC Ayala/Renaissance Shopping Center 245 219 464 210 185 395 5,74224 I-210 Logistics Center IV 431.265 TSF 171 45 216 58 173 231 2,573

    Total 5,129 2,532 7,661 3,660 5,518 9,178 91,435

    1 Source: Renaissance Specific Plan Amendment Traffic Impact Analysis, prepared by LSA, December 3, 2015 and Institute of Transportation Engineers, Trip Generation Manual,

    9th Edition, 2012, Land Use Codes 140, 150, 210, 320, 820, 854, 933, 934, 941, & 945.

    5 Source: Evening Peak Hour rates from Appendix A of the Coastal Transportation Corridor Specific Plan, Ordinance No. 168,999 Effective September 22, 1993. Morning Peak Hour and Daily rates from the San Diego Association of Governments, Brief Guide of Vehicular Traffic Generation Rates for the San Diego Region, April 2002. Automatic Car Wash rates are used.

    3 DU = Dwelling Units; TSF = Thousand Square Feet; RM = Rooms; FP = Fueling Positions

    2 Trips are presented in Passenger Car Equivalents, where applicable.

    4 Based on a field visit performed by Kunzman Associates, Inc. staff, development is currently occupied and fully operational according to the current tenant.

    34

  • 35

  • 36

  • 37

  • 38

  • 39

  • 40

  • 41

  • 42

  • 43

  • 44

  • 45

  • 46

  • 47

  • 47

    VI. FUTURE LEVELS OF SERVICE Detailed intersection delay and Level of Service calculation worksheets for each of the following analysis scenarios are provided in Appendix D. A. Existing Plus Project Roadway Segment & Intersection Level of Service

    Table 5 shows the roadway segment capacity analysis for Existing Plus Project traffic conditions based on the existing number of lanes. As shown in Table 5, the study area roadway segments are forecast to operate at acceptable Levels of Service for Existing Plus Project traffic conditions. Table 6 shows intersection delay and Level of Service for Existing Plus Project traffic conditions based on existing lane geometry and project driveway improvements. As shown in Table 6, the study area intersections are projected to operate within acceptable Levels of Service during the peak hours for Existing Plus Project traffic conditions. As also shown Table 6, the proposed project is forecast to result in no significant traffic impacts at the study intersections for Existing Plus Project traffic conditions.

    B. Project Completion (Existing Plus Ambient Growth Plus Project) Roadway Segment & Intersection Levels of Service Table 7 shows the roadway segment capacity analysis for Project Completion traffic conditions based on the existing number of lanes. As shown in Table 7, the study area roadway segments are forecast to operate at acceptable Levels of Service for Project Completion traffic conditions. Table 8 shows intersection delay and Level of Service for Project Completion traffic conditions without and with improvements. As shown in Table 8, the study area intersections are projected to operate within acceptable Levels of Service during the peak hours for Project Completion traffic conditions without improvements. As shown in Table 8, the proposed project is forecast to result in no significant traffic impacts at the study intersections for Project Completion traffic conditions with improvements.

    C. Cumulative Conditions (Existing Plus Ambient Growth Plus Project Plus Cumulative)

    Roadway Segment & Intersection Levels of Service Table 9 shows the roadway segment capacity analysis for Cumulative traffic conditions based on the existing number of lanes. As shown in Table 9, the following study area roadway segments are forecast to operate at deficient Levels of Service (E or F) for Cumulative traffic conditions without improvements: ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue ■ Locust Avenue from Vineyard Avenue to Casmalia Street

    48

  • 48

    The following roadway segment improvements are recommended for Cumulative traffic conditions: ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue

    o Widen from a two lane secondary arterial to four lane modified arterial ■ Locust Avenue from Vineyard Avenue to Casmalia Street

    o Widen from a two lane secondary arterial to four lane modified arterial As shown in Table 9, the study roadway segments are forecast to operate within acceptable Levels of Service for Cumulative traffic conditions with improvements. Table 10 shows intersection delay and Level of Service for Cumulative traffic conditions without and with improvements. As shown in Table 10, the following study area intersections are projected to operate at a deficient Level of Service (E or F) during the peak hours for Cumulative traffic conditions without improvements:

    Alder Avenue (NS) at: Sierra Lakes Pkwy/Casmalia St (EW) - #1 (morning and evening peak hour) SR-210 Westbound Ramps (EW) - #2 (morning and evening peak hour) SR-210 Eastbound Ramps (EW) - #3 (morning and evening peak hour)

    As also shown in Table 10, the proposed project is forecast to result in a significant traffic impact at the following study intersections based on the net change in delay for Cumulative traffic conditions without improvements:

    Alder Avenue (NS) at: Sierra Lakes Pkwy/Casmalia St (EW) - #1 (morning and evening peak hour) SR-210 Westbound Ramps (EW) - #2 (evening peak hour only)

    As shown in Table 10, the proposed project is forecast to result in no significant traffic impacts at the study intersections for Cumulative traffic conditions with improvements.

    D. General Plan Buildout (With Project) Roadway Segment & Intersection Levels of Service Table 11 shows the roadway segment capacity analysis for General Plan Buildout (With Project) traffic conditions. As shown in Table 11, the study area roadway segments are projected to provide sufficient capacity for General Plan Buildout (With Project) traffic conditions, with the exception of Alder Avenue from SR-210 to Renaissance Parkway. As also shown in Table 11, the following study area roadway segments are forecast to operate at deficient Levels of Service (E or F) for General Plan Buildout (With Project) traffic conditions without improvements: ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue ■ Locust Avenue from Vineyard Avenue to Casmalia Street The following roadway segment improvements are recommended for Cumulative traffic conditions:

    49

  • 49

    ■ Locust Avenue from Bohnert Avenue to Vineyard Avenue

    o Widen from a two lane secondary arterial to four lane modified arterial ■ Locust Avenue from Vineyard Avenue to Casmalia Street

    o Widen from a two lane secondary arterial to four lane modified arterial As shown in Table 11, the study roadway segments are forecast to operate within acceptable Levels of Service for General Plan Buildout (With Project) traffic conditions with improvements. Table 12 shows intersection delay and Level of Service for General Plan Buildout (With Project) traffic conditions. As shown in Table 12, the following study area intersections are projected to operate at a deficient Level of Service (E or F) during the peak hours for General Plan Buildout (With Project) traffic conditions:

    Alder Avenue (NS) at: Sierra Lakes Parkway/Casmalia Street (EW) - #1 (morning/evening peak hours) SR-210 Freeway Westbound Ramps (EW) - #2 (morning/evening peak hours) SR-210 Freeway Eastbound Ramps (EW) - #3 (morning/evening peak hours)

    Locust Avenue (NS) at: Bohnert Avenue (EW) - #4 (morning/evening peak hours) Vineyard Avenue (EW) - #7 (evening peak hour) Casmalia Street (EW) - #8 (morning/evening peak hours) Renaissance Parkway (EW) - #9 (evening peak hour)

    As also shown in Table 12, the proposed project is forecast to result in a significant traffic impact at the following study intersections based on the net change in delay for General Plan Buildout (With Project) traffic conditions without improvements:

    Alder Avenue (NS) at: Sierra Lakes Parkway/Casmalia Street (EW) - #1 (morning/evening peak hours) SR-210 Freeway Westbound Ramps (EW) - #2 (evening peak hour)

    Locust Avenue (NS) at: Bohnert Avenue (EW) - #4 (morning/evening peak hours) Casmalia Street (EW) - #8 (morning/evening peak hours)

    As shown in Table 12, the proposed project is forecast to result in no significant traffic impacts at the study intersections for General Plan Buildout (With Project) traffic conditions with improvements.

    50

  • CapacityNumber for Deficient

    of Roadway Level of Level ofFrom To Lanes Classification Service D Service?

    Bohnert Avenue Vineyard Avenue 11,400 2 Secondary Arterial 17,999 NoVineyard Avenue Casmalia Street 12,000 2 Secondary Arterial 17,999 No

    Casmalia Street Locust Avenue Linden Avenue 6,800 2 Secondary Arterial 17,999 No

    Existing Plus Project Roadway Segment Capacity Analysis

    Table 5

    1 Average Daily Traffic Volume in Passenger Car Equivalents (PCEs).

    RoadwaySegment

    Average Daily

    Traffic Volume1

    Without Improvements

    Locust Avenue

    51

  • TrafficJurisdiction Control3 L T R L T R L T R L T R Morning Evening Morning Evening Morning Evening

    Sierra Lakes Parkway/Casmalia Street (EW) - #1 Rialto TS 1 2 d 1 2 1 1 1 d 1 1 1 20.7-C 25.9-C 21.0-C 26.9-C +0.3 +1.0 No

    AldSierra Lakes Parkway/Casmalia Street (EW) - #1SR-210 WB Ramps (EW) - #2 Caltrans TS 1 2 0 0 2 d 0 0 0 1 0.5 0.5 17.1-B 18.0-B 18.3-B 18.2-B +1.2 +0.2 No

    SR-210 EB Ramps (EW) - #3 Caltrans TS 0 2 d 1 2 0 0.5 0.5 1 0 0 0 14.9-B 17.1-B 16.0-B 17.2-B +1.1 +0.1 No

    Bohnert Avenue (EW) - #4 Rialto CSS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 14.6-B 18.2-C 14.7-B 18.4-C +0.1 +0.2 No

    North Project Driveway (EW) - #5 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 12.8-B 15.6-C - - n/a

    South Project Driveway (EW) - #6 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 12.7-B 15.5-C - - n/a

    Vineyard Avenue (EW) - #7 Rialto CSS 0.5 0.5 d 0.5 0.5 d 0 1 0 0 1 0 13.4-B 16.8-C 14.0-B 18.2-C +0.6 +1.4 No

    Casmalia Street (EW) - #8 Rialto TS 1 1.5 0.5 1 1.5 0.5 1 1 d 1 1 d 20.1-C 22.0-C 20.9-C 22.6-C +0.8 +0.6 No

    Renaissance Parkway (EW) - #9 Rialto TS 1 1 d 1 1 1 1 1.5 0.5 1 1.5 0.5 22.4-C 22.5-C 22.4-C 22.5-C 0.0 0.0 No

    Casmalia Street (EW) - #10 Rialto AWS 0 0 0 0.5 0 0.5 0.5 0.5 0 0 0.5 0.5 7.9-A 8.5-A 8.0-A 8.6-A +0.1 +0.1 No

    1

    2

    3TS = Traffic Signal; CSS = Cross Street Stop; AWS = All Way Stop

    When a right turn lane is designated, the lane can either be striped or unstriped. To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes.L = Left; T = Through; R = Right; d = De Facto Right Turn; BOLD = Improvement

    Delay and Level of Service has been calculated using the following analysis software: Vistro, Version 5.00-00. Per the 2010 Highway Capacity Manual, overall average intersection delay and Level of Service are shown for intersections with traffic signal or all way stop control. For intersections with cross street stop control, the delay and Level of Service for the worst individual movement (or movements sharing a single lane) are shown.

    Delay

    Change in

    Sign

    ifica

    ntIm

    pact

    ?

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Cedar Avenue (NS) at:

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Existing Plus Project Intersection Delay and Level of Service

    Table 6

    Intersection Approach Lanes1

    Northbound Southbound Eastbound Westbound Existing

    Intersection

    Peak Hour Delay-LOS2

    Existing Plus Project

    52

  • CapacityNumber for Deficient

    of Roadway Level of Level ofFrom To Lanes Classification Service D Service?

    Bohnert Avenue Vineyard Avenue 11,900 2 Secondary Arterial 17,999 NoVineyard Avenue Casmalia Street 12,500 2 Secondary Arterial 17,999 No

    Casmalia Street Locust Avenue Linden Avenue 7,000 2 Secondary Arterial 17,999 No

    Project Completion Roadway Segment Capacity Analysis

    Table 7

    1 Average Daily Traffic Volume in Passenger Car Equivalents (PCEs).

    RoadwaySegment

    Average Daily

    Traffic Volumes1

    Without Improvements

    Locust Avenue

    53

  • TrafficJurisdiction Control3 L T R L T R L T R L T R Morning Evening Morning Evening Morning Evening

    Sierra Lakes Parkway/Casmalia Street (EW) - #1 Rialto TS 1 2 d 1 2 1 1 1 d 1 1 1 21.1-C 26.3-C 21.3-C 27.0-C +0.2 +0.7 No

    SR-210 WB Ramps (EW) - #2 Caltrans TS 1 2 0 0 2 d 0 0 0 1 0.5 0.5 17.6-B 18.5-B 17.6-B 18.7-B 0.0 +0.2 No

    SR-210 EB Ramps (EW) - #3 Caltrans TS 0 2 d 1 2 0 0.5 0.5 1 0 0 0 15.3-B 17.4-B 15.3-B 17.4-B 0.0 0.0 No

    Bohnert Avenue (EW) - #4 Rialto CSS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 14.8-B 18.5-C 14.9-B 18.8-C +0.1 +0.3 No

    North Project Driveway (EW) - #5 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 12.9-B 15.8-C - - n/a

    South Project Driveway (EW) - #6 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 12.8-B 15.7-C - - n/a

    Vineyard Avenue (EW) - #7 Rialto CSS 0.5 0.5 d 0.5 0.5 d 0 1 0 0 1 0 13.6-B 17.1-C 14.1-B 18.5-C +0.5 +1.4 No

    Casmalia Street (EW) - #8 Rialto TS 1 1.5 0.5 1 1.5 0.5 1 1 d 1 1 d 20.2-C 22.3-C 20.9-C 22.9-C +0.7 +0.6 No

    Renaissance Parkway (EW) - #9 Rialto TS 1 1 d 1 1 1 1 1.5 0.5 1 1.5 0.5 22.4-C 22.6-C 22.4-C 22.6-C 0.0 0.0 No

    Casmalia Street (EW) - #10 Rialto AWS 0 0 0 0.5 0 0.5 0.5 0.5 0 0 0.5 0.5 7.9-A 8.6-A 8.0-A 8.7-A +0.1 +0.1 No

    1

    2

    3TS = Traffic Signal; CSS = Cross Street Stop; AWS = All Way Stop

    Delay and Level of Service has been calculated using the following analysis software: Vistro, Version 5.00-00. Per the 2010 Highway Capacity Manual, overall average intersection delay and Level of Service are shown for intersections with traffic signal or all way stop control. For intersections with cross street stop control, the delay and Level of Service for the worst individual movement (or movements sharing a single lane) are shown.

    When a right turn lane is designated, the lane can either be striped or unstriped. To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes.L = Left; T = Through; R = Right; d = De Facto Right Turn; BOLD = Improvement

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Cedar Avenue (NS) at:

    Table 8

    Project Completion Intersection Delay and Level of Service

    Change in

    Intersection

    Intersection Approach Lanes1Project Completion

    Peak Hour Delay-LOS2

    Sign

    ifica

    ntIm

    pact

    ?

    Northbound Southbound Eastbound Westbound Without Project With Project Delay

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    54

  • Capacity CapacityNumber for Deficient Number for Deficient

    of Roadway Level of Level of of Roadway Level of Level ofFrom To Lanes Classification Service D Service? Lanes Classification Service D Service?

    Bohnert Avenue Vineyard Avenue 20,200 2 Secondary Arterial 17,999 Yes 4 Modified Arterial 32,999 NoVineyard Avenue Casmalia Street 20,800 2 Secondary Arterial 17,999 Yes 4 Modified Arterial 32,999 No

    Casmalia Street Locust Avenue Linden Avenue 13,400 2 Secondary Arterial 17,999 No

    Table 9

    Cumulative Conditions Roadway Segment Capacity Analysis

    With Improvements

    1 Average Daily Traffic Volume in Passenger Car Equivalents (PCEs).

    RoadwaySegment

    Average Daily

    Traffic Volume1

    Without Improvements

    Locust Avenue

    55

  • Traffic

    Jurisdiction Control3 L T R L T R L T R L T R Morning Evening Morning Evening Morning Evening

    Sierra Lakes Parkway/Casmalia Street (EW) - #1

    - Without Improvements Rialto TS 1 2 d 1 2 1 1 1 d 1 1 1 59.8-E 125.1-F 63.0-E 126.8-F +3.2 +1.7 Yes- With Improvements Rialto TS 1 2 1> 1 2 0.5 1 1 1> 2 0.5 0.5 - - 20.0-C 36.4-D -39.8 -88.7 No

    SR-210 WB Ramps (EW) - #2- Without Improvements Caltrans TS 1 2 0 0 2 d 0 0 0 1 0.5 0.5 143.4-F 290.6-F 144.3-F 292.0-F +0.9 +1.4 Yes- With Improvements Caltrans TS 2 2 0 0 2 1>> 0 0 0 2 0.5 0.5 - - 26.0-C 26.2-C -117.4 -264.4 No

    SR-210 EB Ramps (EW) - #3- Without Improvements Caltrans TS 0 2 d 1 2 0 0.5 0.5 1 0 0 0 164.7-F 264.8-F 165.4-F 264.8-F +0.7 0.0 No- With Improvements Caltrans TS 0 2 d 2 2 0 1.5 0.5 2> 0 0 0 - - 18.6-C 24.3-C -146.1 -240.5 No

    Bohnert Avenue (EW) - #4- Without Improvements Rialto CSS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 49.5-E 77.5-F 51.3-F 80.5-F +1.8 +3.0 No- With Improvements Rialto TS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 - - 4.7-A 4.2-A -44.8 -73.3 No

    North Project Driveway (EW) - #5 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 27.8-D 41.1-E - - No

    South Project Driveway (EW) - #6 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 27.2-D 39.7-E - - No

    Vineyard Avenue (EW) - #7 Rialto CSS 0.5 0.5 d 0.5 0.5 d 0 1 0 0 1 0 33.1-D 49.4-E 35.5-E 65.4-F +2.4 +16.0 No

    Casmalia Street (EW) - #8 Rialto TS 1 1.5 0.5 1 1.5 0.5 1 1 d 1 1 d 34.3-C 34.3-C 36.8-D 35.9-D +2.5 +1.6 No

    Renaissance Parkway (EW) - #9 Rialto TS 1 1 d 1 1 1 1 1.5 0.5 1 1.5 0.5 33.9-C 34.9-C 33.9-C 34.9-C 0.0 0.0 No

    Casmalia Street (EW) - #10 Rialto AWS 0 0 0 0.5 0 0.5 0.5 0.5 0 0 0.5 0.5 25.5-D 42.9-E 27.7-D 46.8-E +2.2 +3.9 No

    1

    2

    3TS = Traffic Signal; CSS = Cross Street Stop; AWS = All Way Stop

    When a right turn lane is designated, the lane can either be striped or unstriped. To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes.L = Left; T = Through; R = Right; d = De Facto Right Turn; > =Right Turn Overlap; >> = Free Right Turn; BOLD = Improvement

    Delay and Level of Service has been calculated using the following analysis software: Vistro, Version 5.00-00. Per the 2010 Highway Capacity Manual, overall average intersection delay and Level of Service are shown for intersections with traffic signal or all way stop control. For intersections with cross street stop control, the delay and Level of Service for the worst individual movement (or movements sharing a single lane) are shown.

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Cedar Avenue (NS) at:

    Table 10

    Cumulative Conditions Intersection Delay and Level of Service

    Cumulative Conditions Peak Hour Delay-LOS2Intersection Approach Lanes1

    Intersection Sign

    ifica

    ntIm

    pact

    ?

    Northbound Southbound Eastbound Westbound Without Project With Project Delay

    Change in

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    56

  • Capacity CapacityNumber for Deficient Number for Deficient

    of Roadway Level of Level of of Roadway Level of Level ofFrom To Lanes Classification Service D Service? Lanes Classification Service D Service?

    Bohnert Avenue Vineyard Avenue 22,200 2 Secondary Arterial 17,999 Yes 4 Modified Arterial 32,999 NoVineyard Avenue Casmalia Street 22,900 2 Secondary Arterial 17,999 Yes 4 Modified Arterial 32,999 No

    Casmalia Street Locust Avenue Linden Avenue 13,400 2 Secondary Arterial 17,999 No

    1 Average Daily Traffic Volumes on Locust Avenue have been calculated by applying 10% growth over Cumulative traffic conditions. Average Daily Traffic Volumes on Casmalia Street were determined by selecting the

    higher of the following two volumes: that included in the Renaissance Specific Plan Amendment Traffic Impact Analysis and those calculated for Cumulative traffic conditions.

    With Improvements

    Table 11

    General Plan Buildout Roadway Segment Capacity Analysis1

    2 Average Daily Traffic Volume in Passenger Car Equivalents (PCEs).

    RoadwaySegment

    Average Daily

    Traffic Volume2

    Without Improvements

    Locust Avenue

    57

  • TrafficJurisdiction Control3 L T R L T R L T R L T R Morning Evening Morning Evening Morning Evening

    Sierra Lakes Parkway/Casmalia Street (EW) - #1- Without Improvements Rialto TS 1 2 d 1 2 1 1 1 d 1 1 1 115.0-F 176.9-F 119.2-F 181.9-F +4.2 +5.0 Yes- With Improvements Rialto TS 1 2 1> 1 2 0.5 1 1 1> 2 0.5 0.5 - - 28.8-C 41.3-D -86.2 -135.6 No

    SR-210 WB Ramps (EW) - #2- Without Improvements Caltrans TS 1 2 0 0 2 d 0 0 0 1 0.5 0.5 149.0-E 306.9-F 149.5-F 310.0-F +0.5 +3.1 Yes- With Improvements Caltrans TS 2 2 0 0 2 1>> 0 0 0 2 0.5 0.5 - - 21.8-C 31.0-C -127.2 -275.9 No

    SR-210 EB Ramps (EW) - #3- Without Improvements Caltrans TS 0 2 d 1 2 0 0.5 0.5 1 0 0 0 162.1-E 246.5-F 162.8-F 246.6-F +0.7 +0.1 No- With Improvements Caltrans TS 0 2 d 2 2 0 1.5 0.5 2> 0 0 0 - - 14.6-C 19.3-B -147.5 -227.2 No

    Bohnert Avenue (EW) - #4- Without Improvements Rialto CSS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 1,958.2-F 996.2-F 1,999.3-F 1,025.7-F +41.1 +29.5 Yes- With Improvements Rialto TS 0 1 0 0.5 0.5 d 0 1 0 0 1 0 - - 19.3-B 9.2-A -1938.9 -987.0 No

    North Project Driveway (EW) - #5 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 61.6-F 78.2-F - - No

    South Project Driveway (EW) - #6 Rialto CSS 0 0.5 0.5 0.5 0.5 0 0 0 0 0 1 0 - - 57.5-F 71.4-F - - No

    Vineyard Avenue (EW) - #7 Rialto CSS 0.5 0.5 d 0.5 0.5 d 0 1 0 0 1 0 14.2-B 93.8-F 93.5-F 163.4-F +79.3 +69.6 No4

    Casmalia Street (EW) - #8- Without Improvements Rialto TS 1 1.5 0.5 1 1.5 0.5 1 1 d 1 1 d 71.6-E 81.3-F 74.4-E 85.1-F +2.8 +3.8 Yes- With Improvements Rialto TS 1 1.5 0.5 1 0.5 1.5 2 1 d 2 1 d 0.0- 0.0- 49.3-D 53.1-D -22.3 -28.2 No

    Renaissance Parkway (EW) - #9- Without Improvements Rialto TS 1 1 d 1 1 1 1 1.5 0.5 1 1.5 0.5 54.2-D 77.3-E 54.2-D 77.4-E 0.0 +0.1 No- With Improvements Rialto TS5 1 1.5 0.5 1 1.5 0.5 1 1.5 0.5 1 1.5 0.5 0.0- 0.0- 33.5-C 45.6-D -20.7 -31.7 No

    Casmalia Street (EW) - #10 Rialto AWS 0 0 0 0.5 0 0.5 0.5 0.5 0 0 0.5 0.5 55.3-F 71.9-F 60.3-F 77.1-F +5.0 +5.2 No

    1

    2

    3TS = Traffic Signal; CSS = Cross Street Stop; AWS = All Way Stop

    4

    5Install Protected-Permitted Phasing at the east and west approaches.

    Table 12

    General Plan Buildout Intersection Delay and Level of Service

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Alder Avenue (NS) at:

    Locust Avenue (NS) at:

    Intersection

    Intersection Approach Lanes1General Plan Buildout Peak Hour Delay-LOS2

    Sign

    ifica

    ntIm

    pact

    ?Change inNorthbound Southbound Eastbound Westbound Without Project With Project Delay

    Though this intersection experiences a delay of over 120 seconds at one of its approaches,there is no impact because only vehicles exiting the proposed project will experience this delay. Vineyard Avenue does not extend past the eastern project boundary and there are currently no plans to do so.

    Cedar Avenue (NS) at:

    When a right turn lane is designated, the lane can either be striped or unstriped. To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes.L = Left; T = Through; R = Right; d = De Facto Right Turn; > =Right Turn Overlap; >> = Free Right Turn; BOLD = Improvement

    Delay and Level of Service has been calculated using the following analysis software: Vistro, Version 5.00-00. Per the 2010 Highway Capacity Manual, overall average intersection delay and Level of Service are shown for intersections with traffic signal or all way stop control. For intersections with cross street stop control, the delay and Level of Service for the worst individual movement (or movements sharing a single lane) are shown.

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    Locust Avenue (NS) at:

    58

  •  

    58 

    VII.  MITIGATION MEASURES AND COST ESTIMATES  Improvements that will eliminate all anticipated roadway operational deficiencies throughout the study area have been  identified  for General Plan Buildout  (With Project) traffic conditions.   The improvements were determined through the operations analysis of Section VI.  The  approximate  costs  for  the General Plan Buildout  (With Project)  improvements have either been taken from the Renaissance Specific Plan Amendment Traffic Impact Analysis or have been estimated using cost guidelines in the Congestion Management Program Handbook (see Appendix E).  It should be noted that any dollar figures are rough order of magnitude estimates only.  They are intended only  for  the discussion purposes of  this  traffic  impact analysis, and do not  imply any legal responsibility or formula for contributions or mitigation.  A.  Intersection Improvements 

     The needed intersection improvements and resulting costs are summarized in Table 13 for the  study  area  intersections.    The  total  cost  of  needed  and  unfunded  intersection improvements for the existing roadway network is $1,037,858.  The  project  fair  share  contributions  have  also  been  calculated  for General  Plan Buildout (With  Project)  intersection  improvement  locations.    The  project  share  of  cost  has  been based  on  the  proportion  of  project  peak  hour  traffic  contributed  to  the  improvement location  relative  to  the  total  new  peak  hour General  Plan  Buildout  (With  Project)  traffic volume.  Table 14 presents a summary of  improvement cost and project cost shares at the General Plan Buildout (With Project) intersection improvement locations.  The intersection fair share cost calculations are  typically based on  the higher of  the morning and evening peak hour traffic  volumes.   As  shown  in  Table  14,  the  project’s  fair  share  of  identified  intersection costs is $68,244.  As mitigation  for  the potential  traffic  impacts  to  intersections,  the proposed project  shall contribute  through  an  adopted  traffic  impact  fee  program  in  addition  to  any  fair  share contributions shown within the traffic study which is not covered within this fee program.  

    B.  Roadway Segment Improvements  The  needed  study  area  roadway  segment  improvements  and  resulting  costs  are summarized in Table 15.  The total cost of needed and unfunded intersection improvements for the existing roadway network is $140,637.  The  project  fair  share  contributions  have  also  been  calculated  for General  Plan Buildout (With  Project)  roadway  segment  improvement  locations.    The  project  share  of  cost  has been  based  on  the  proportion  of  project  daily  traffic  contributed  to  the  improvement location relative to the total new daily General Plan Buildout (With Project) traffic volume. 

    59

  •  

    59 

     Table  15  also  includes  project  cost  shares  at  the  General  Plan  Buildout  (With  Project) roadway  segment    improvements.    As  shown  in  Table  15,  the  project’s  fair  share  of identified roadway segment improvement costs is $2,050.  As mitigation  for the potential traffic  impacts to roadway segments, the proposed project shall contribute through an adopted traffic impact fee program in addition to any fair share contributions shown within the traffic study which is not covered within this fee program. 

    60

  • Restripe to Provide Additional WB Left Turn Lane and WB Through/Right Turn Lane 10,000$         ‐                          10,000$        Construct NB Right Turn Lane w/ Overlap Phasing 182,245$       $157,150 25,095$       Construct EB Right Turn Lane w/ Overlap Phasing 182,245$       ‐                          182,245$      

    Restripe to Provide Additional NB Left Turn Lane $      125,000  $29,875 95,125$       

    Restripe to Provide Additional WB Left Turn Lane and WB Through/Right Turn Lane $      125,000  $29,875 95,125$       Widen SB Approach OC to Provide Channelized, Dedicated  Right Turn Lane 125,000$       $29,875 95,125$        

    Bohnert Avenue (EW) ‐ #4 Rialto Install Traffic Signal 250,000$       ‐                          250,000$      Construct Additional WB Left Turn Lane 72,898$        ‐                         72,898$       Construct Additional EB Left Turn Lane 72,898$        $76,475 ‐                    Construct Additional SB Right Turn Lane 72,898$        ‐                         72,898$       Restripe to Provide One SB Right Turn Lane and On SB Through/Right Turn Lane 10,000$         ‐                          10,000$        Re‐stripe SB Right Turn Lane to Shared Through/ Right Turn Lane 10,000$         ‐                          10,000$        

    Re‐stripe to provide One NB Through Lane and One Shared NB Through/Right Turn Lane 10,000$         ‐                          10,000$        Install Protected‐Permitted Phasing at the East and West Approaches 109,347$       ‐                          109,347$      

    Total 1,357,531$    1,037,858$   

    1  Cost estimates based on Renaissance Specific Plan Amendment Traffic Impact Analysis, LSA (December 2015).

    Rialto

    Caltrans2

    Alder Avenue (NS) at:

    Sierra Lakes Parkway/Casmalia Street (EW) ‐ #1

    Locust Avenue (NS) at:

    Casmalia Street (EW) ‐ #8

    Renaissance Parkway (EW) ‐ #9

    SR‐210 Freeway WB Ramps (EW) ‐ #2

    Rialto

    Caltrans2

    Table 13

    Summary of Intersection Improvements and Costs

    Intersection Jurisdiction Improvement Total Cost

    Included in Renaissance Specific Plan Fee Program

    Unfunded Cost

    61

  • Year 2035 (Buildout) Project

    With Total % ofExisting Project Project New New Project

    Total Peak Traffic Traffic Traffic Traffic Traffic CostJurisdiction Cost Hour Volumes Volumes Volumes Volumes Volumes Share

    Morning 1,342 4,269 93 2,927 3.2%Evening 1,654 4,434 96 2,780 3.5%Morning 1,693 4,740 87 3,047 2.9%Evening 1,885 5,333 92 3,448 2.7%

    Rialto Morning 602 2,124 170 1,522 11.2%Evening 829 2,136 177 1,307 13.5%

    Rialto Morning 797 3,730 164 2,933 5.6%Evening 1,322 4,048 173 2,726 6.3%

    Rialto Morning 1,063 3,487 164 2,424 6.8%Evening 874 4,525 173 3,651 4.7%

    Total 1,037,858$ 68,244$

    Table 14

    Project Fair Share Intersection Contribution

    Intersection

    Rialto 217,340$ 7,607$

    Caltrans

    8,796$ 129,347$

    155,796$

    250,000$ 33,750$

    285,375$ 8,276$

    9,815$ Locust Avenue (NS) at:

    Bohnert Avenue (EW) - #4

    Casmalia Street (EW) - #8

    Renaissance Parkway (EW) - #9

    Alder Avenue (NS) at:

    Casmalia Street (EW) - #1

    SR-210 Freeway WB Ramps (EW) - #2

    62

  • Per Lane Per Mile Total

    Roadway Jurisdiction From To Miles Cost1 Cost Percentage Cost

    Rialto 0.04 2 1,457,960$    116,637$    0.9% 1,032$  0.12 02 n/a 6,000$        0.9% 53$       

    Rialto Vineyard Avenue Casmalia Street 0.36 02 n/a 18,000$      5.4% 964$      Total 140,637$   2,050$ 

    2  This roadway segment needs to be restriped to provide 4 travel lanes.  A conservative cost of $50,000 per mile was assumed.

    1  Cost estimates based on Renaissance Specific Plan Amendment Traffic Impact Analysis, LSA (December 2015).

    Bohnert Avenue Vineyard Avenue

    Table 15

    Project Fair Share Roadway Segment Contribution

    Added Lanes

    Project Fair ShareSegment

    Locust Avenue

    63

  •  

    63 

    VIII. CONCLUSIONS  A.  Off‐Site Mitigation Measures 

     The  proposed  project  shall  contribute  on  a  fair  share  basis  through  an  adopted development impact fee program, or in dollar equivalent in lieu mitigation contributions, in the implementation of the improvements identified in Section VI and summarized  in Table 13 and Table 15.  

    B.  On‐Site/Access Recommendations  Site‐specific circulation and access recommendations are depicted on Figure 32. 

     The  proposed  project  driveways  shall  be  constructed  in  conformance with  City  of  Rialto standards, including provisions for sight distance and truck turning path requirements.  Locust Avenue along the project boundary shall be constructed at  its ultimate half‐section width, including landscaping and parkway improvements in conjunction with development, as necessary.  Vineyard  Avenue  along  the  project  boundary  shall  be  constructed  at  its  ultimate  half‐section  width,  including  landscaping  and  parkway  improvements  in  conjunction  with development, as necessary.  On‐site  traffic  signing  and  striping  shall  be  submitted  for  City  of  Rialto  approval  in conjunction with detailed construction plans for the project.  Off‐street parking shall be provided to meet City of Rialto parking code requirements. 

    64

  • 64

  • APPENDICES Appendix A – Glossary of Transportation Terms Appendix B – Scoping Agreement Appendix C – Intersection Turning Movement Count Worksheets Appendix D – Intersection Delay and Level of Service Worksheets Appendix E – Preliminary Construction Cost Estimates for Congestion Management Program

    Apx-1

  • APPENDIX A

    Glossary of Transportation Terms

    Apx-2

  • GLOSSARY OF TRANSPORTATION TERMS COMMON ABBREVIATIONS AC: Acres ADT: Average Daily Traffic Caltrans: California Department of Transportation DU: Dwelling Unit ICU: Intersection Capacity Utilization LOS: Level of Service TSF: Thousand Square Feet V/C: Volume/Capacity VMT: Vehicle Miles Traveled TERMS AVERAGE DAILY TRAFFIC: The total volume during a year divided by the number of days in a year. Usually only weekdays are included. BANDWIDTH: The number of seconds of green time available for through traffic in a signal progression. BOTTLENECK: A constriction along a travelway that limits the amount of traffic that can proceed downstream from its location. CAPACITY: The maximum number of vehicles that can be reasonably expected to pass over a given section of a lane or a roadway in a given time period. CHANNELIZATION: The separation or regulation of conflicting traffic movements into definite paths of travel by the use of pavement markings, raised islands, or other suitable means to facilitate the safe and orderly movements of both vehicles and pedestrians. CLEARANCE INTERVAL: Nearly same as yellow time. If there is an all red interval after the end of a yellow, then that is also added into the clearance