Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
11111111
`
Locomotive Shutdown
A Fuel Conservation Project
Locomotive Shutdown
A Fuel Conservation Project
Notes
22222222
A New Day Dawns for Fuel Conservation at CSXA New Day Dawns for Fuel Conservation at CSXA New Day Dawns for Fuel Conservation at CSXA New Day Dawns for Fuel Conservation at CSX
Welcome,
Over the next thirty minutes our team will be walking you through our fuel conservation project.
33333333
Some historical information about Diesel Electric L ocomotives operations:
• locomotives were left idling when not being utilized (not moving)
• water cooled engine, not antifreeze mixture – can freeze – catastrophic damage
• if shutdown long enough gaskets would dry out causing engine leaks
• fuel usage for an idling locomotive ~4 gallons of fuel per hour
• fuel prices were much lower
• fuel was a smaller portion of operating costs
We will be discussing a project dealing with locomotive shutdown.
Locomotive shutdown may not sound like a big deal but historically locomotives were never shutdown.
The utilization levels of the equipment, the size and type of gaskets used, and the relative cost of fuel made it more economical to design an engine that was not intended to be shutdown.
As fuel costs rose, this changed, but habits are hard to break.
In addition, Locomotive diesel engines are water cooled. This prevents shutdown in cold weather because water expands as it freezes causing catastrophic engine damage.
44444444
Team Members:Operations Process Excellence: Andy John - General Manager,
Wayne Seguin – Director
Purchasing: Bill Legant - Director of Fuel Purchasing
Locomotive Engineering: Don Robey – Director, Mike Drylie - Electrical Engineer , Tim Healey - Mechanical Engineer
Locomotive Productivity: Josh Putterman – AVP, John Kissinger – Director
System Road Foreman of Engines: Dean Menefee
Division Senior Road Foreman of Engines:Dennis Biegel – Chicago
Greg Clevenger – LouisvilleCharlie Crownover – Nashville
Bill Diamond – BaltimoreDennis Merrell – JacksonvilleRodney Saunders – Atlanta
Stan Shadrix – FlorenceSteve Skaruppa – Great Lakes
Jim Ward – HuntingtonRodney Wilson – Albany
From the start the project was managed by a broad cross-functional team because it required insight from many perspectives. This involved both labor and management, but we’ll get into that, let’s first talk about the birth of the project.
55555555
1.A Methods Used to Choose Project
Top Down Approach
Broad StakeholderInvolvement
Waste Focused
Data Driven
Organizational Need
This project was generated by organizational needs, using a top down approach, that focused on waste elimination, based on solid data, and broad stakeholder involvement.
We will review the reasons the project was selected and the involvement of stakeholders; then address item (1 Aa) the types of data used for project selection.
66666666
Launched a Strategic Initiative to Improve Producti vityand Reduce Operating Ratio
Early in 2004 the Fuel Initiative was launched as a PIT+ initiative
• CSX lagged other Class I RRs and had degraded from ’96-97’ levels of 78%
• CSX had success with PIT (Process Improvement Teams) in the past
• Plus (+) now added the methodology of Six Sigma (6s)
• PIT+ initiatives were developed to address efficiency and effectivenessgaps in our key processes
1.A.b Reasons why Project was Selected
NS – direct geographic competitor
CN – best in industry
Class I Operating Ratio's
5060708090
100
1996
1997
1998
1999
2000
2001
2002
2003
Exp
ense
as
a %
of R
even
ue
CSX
NS
CN
In early 2004 CSX looked at some brutal facts.
Our operating ratio – operating expense as a percentage of revenue had degraded significantly and was lagging the industry.
In the early 90’s the company had success with Performance Improvement Teams or PITs
We decided to re-launch this process adding our newest tool -Six Sigma – this launched PIT+
77777777
PIT+ Accountability Structure
ChampionsVP
Transportation
•Crew Costs•LocomotiveProductivity
•Fuel
VPService Design
•Car Utilization•Shipment
Mgmt
VPEngineering
•Track•Train Control
VPHuman Resr.
•G&A•Non-ops
•Labor
VPLocomotives
•Loco R&M•Car R&M
1.A.c Involvement of Stakeholders
Sr. VP Mechanical / Engineering
Chief FinancialOfficer
Chief Operating Officer
PITs
Champion’sFunctionalAreas ofResponsible
•LocomotiveMaintenance
•Locomotive Service
•ShopManagement
•NetworkOperations
•CrewManagement
•Locomotive Management
•AdvancedEngineering
•Research &Planning
•ServicePlanning
•Maintainedof Way
•Design &Construction
•Fixed PlantEngineering
•CustomerAccounting
•TerminalReporting
•CustomerService
Senior Leadership Team (SLT)
PIT+ was a structured effort to look at all our business processes and major cost areas
In PIT+ functional department leaders worked across the organization
as they championed process focused teams that reported out on a scheduled basis
88888888
PIT+ Accountability Structure
ChampionsVP
Transportation
•Crew Costs•LocomotiveProductivity
•Fuel
VPService Design
•Car Utilization•Shipment
Mgmt
VPEngineering
•Track•Train Control
VPHuman Resr.
•G&A•Non-ops
•Labor
VPLocomotives
•Loco R&M•Car R&M
1.A.c Involvement of Stakeholders
Sr. VP Mechanical / Engineering
Chief FinancialOfficer
Chief Operating Officer
PITs
Champion’sFunctionalAreas ofResponsible
•LocomotiveMaintenance
•Locomotive Service
•ShopManagement
•NetworkOperations
•CrewManagement
•Locomotive Management
•AdvancedEngineering
•Research &Planning
•ServicePlanning
•Maintainedof Way
•Design &Construction
•Fixed PlantEngineering
•CustomerAccounting
•TerminalReporting
•CustomerService
Senior Leadership Team (SLT)
- Stakeholder groups involved in project design and/or implementation
The locomotive shutdown project was germinated out of the Fuel PIT but
reached across the functional organization involving a broad and diverse group of stakeholders
99999999
Support Corporate Goals & Vision:
• Lower Operating Ratio• Emissions Reductions• Improved Productivity • Support culture change
By Reducing Diesel Fuel Consumption
1.A.b. Reasons why Project was Selected
Although consumption remained relatively level, diesel fuel prices Were anticipated to increase andwe expected total cost to climb past our 2002 cost of ~$450M
0%
5%
10%
1999 2000 2001 2002 2003
Fuel as a % of total Expense
CSX Fuel Consumption & Price/Gallon
500
550
600
650
1999 2000 2001 2002 2003
Con
sum
ptio
n
$0.50
$0.67
$0.83
$1.00
Pric
e
Gallons Price/Gallon
Fuel was almost 10% of our total operating expense
and fuel price was anticipated to increase in the coming years
1010101010101010
Fuel Cost is a Function of These Key Drivers:Volume, Productivity, Engine Idling, Price, and Log istics Costs
Total Fuel Costs
Gallons
Cost/Gal
Gals/KGTM
KGTM
Base Price/Gal(including taxes)
DistributionCost/Gal
NonproductiveUse (sitting)
Productive Use(pulling freight)
Gallon/Hr
Idle Time
1.A.a Types of Data Used for Selection1.A.b Reasons why Project was Selected
(KGTM = thousand gross ton miles)
The Fuel Pit developed a “driver tree” to focus in on high impact areas that could have rapid implementation
1111111111111111
Fuel Cost is a Function of These Key Drivers:Volume, Productivity, Engine Idling, Price, and Log istics Costs
Total Fuel Costs
Gallons
Cost/Gal
Gals/KGTM
KGTM
Base Price/Gal(including taxes)
DistributionCost/Gal
Largely exogenous,reflects purchasing,tax efficiency and physical facility locations
NonproductiveUse (sitting)
Productive Use(pulling freight)
Gallon/Hr
Idle Time
(KGTM = thousand gross ton miles)
1.A.b. Reasons why Project was Selected
We knew we were not going to be able to impact price
1212121212121212
Fuel Cost is a Function of These Key Drivers:Volume, Productivity, Engine Idling, Price, and Log istics Costs
Total Fuel Costs
Gallons
Cost/Gal
Gals/KGTM
KGTM
Base Price/Gal(including taxes)
DistributionCost/Gal
Diesel engine productivity
NonproductiveUse (sitting)
Productive Use(pulling freight)
Gallon/Hr
Idle Time
Engine idleefficiency
(KGTM = thousand gross ton miles)
Largely exogenous,reflects purchasing,tax efficiency and physical facility locations
1.A.b. Reasons why Project was Selected
In the short term we could not impact the physics of a diesel engines efficiency
1313131313131313
Fuel Cost is a Function of These Key Drivers:Volume, Productivity, Engine Idling, Price, and Log istics Costs
Total Fuel Costs
Gallons
Cost/Gal
Gals/KGTM
KGTM
Base Price/Gal(including taxes)
DistributionCost/Gal
Diesel engine productivity
Measure of volume
NonproductiveUse (sitting)
Productive Use(pulling freight)
Gallon/Hr
Idle Time
Engine idleefficiency
(KGTM = thousand gross ton miles)
Largely exogenous,reflects purchasing,tax efficiency and physical facility locations
1.A.b. Reasons why Project was Selected
And volume was a function of the market and our commercial teams efforts
1414141414141414
Fuel Cost is a Function of These Key Drivers:Volume, Productivity, Engine Idling, Price, and Log istics Costs
Total Fuel Costs
Gallons
Cost/Gal
Gals/KGTM
KGTM
Base Price/Gal(including taxes)
DistributionCost/Gal
Measure of volume
NonproductiveUse (sitting)
Productive Use(pulling freight)
Gallon/Hr
Idle Time Waste = ~30M gals(~6% of total usage)
Engine idleefficiency
Largely exogenous,reflects purchasing,tax efficiency and physical facility locations
Diesel engine productivity
(KGTM = thousand gross ton miles)
1.A.b. Reasons why Project was Selected
This led us to focus on fuel consumed in nonproductive uses
when locomotives were setting idle
1515151515151515
5 10 15 20 25 3035 40 45 50 55 60 65 70 75 8085 90 95100
0
1000
2000
Duration Not moving < 100 hours
Freq
uenc
y
Median time not-moving was 13 hours. This was consistent across geography and type of service, but different by day of week. Weekday median 12 hours. Weekend median 14-16 hours.
How much waste – is it worth attacking?
Initial look using readily available data (8hrs not moving report )
Histogram of “Length of Idle Time”
1.A.a Types of Data Used for Selection1.A.b Reasons why Project was Selected
But was it worth attacking?
We tapped into available data that was used for exception reporting on locomotive dwell times.
1616161616161616
How much waste – is it worth attacking?
Initial look using readily available data to capture opportunity of8hrs not moving = ~ 1.9 million gallons of opportunity
Then looked at raw data to capture opportunity of 1 or more hours not moving = ~ 30M gallons of opportunity
How much waste – is it worth attacking?
1.A.b. Reasons why Project was Selected
A quick analysis led us to a more detailed review of locomotive movement data.
The answer was that we consumed 30M gallons / year while locomotives were sitting and running
1717171717171717
How much waste – is it worth attacking?
Initial look using readily available data to capture opportunity of8hrs not moving = ~ 1.9 million gallons of opportunity
Then looked at raw data to capture opportunity of 1 or more hours not moving = ~ 30M gallons of opportunity
How much waste – is it worth attacking?
YES
1.A.b. Reasons why Project was Selected
Yes – it was worth attacking
1818181818181818
1.A.c Involvement of Stakeholders
Potential Stakeholders and Their Perspectiveat Project Inception
Senior Leadership Team
Locomotive Mgt and shop employees
Transportation Mgt and T&E employees
Finance & Purchasing
Environmental
Communities Served
Stakeholders: Key Measures:
Effectiveness& Efficiency
Effectiveness:shop production
Effectiveness:cars processed,train originations
EfficiencyDollars
Effectiveness: regulationsEfficiency: compliance
EffectivenessQuality of life
Stake:
Benefits, financials
Willing to help,don’t delay production
Willing to help, don’t delay production
Willing to help, sees costs continue to climb
Supportive, want emissionreductions
Support noise and emission reductions
While the “fuel pit” drove the project definition
Several potential stakeholders participated in the effort to define and launch the project, each bringing valuable perspectives, insights, and tradeoff concerns.
1919191919191919
1.A.a Types of Data / Quality Tools Used for Selection
• Analysis of historical, current, and projected data all supportedthe opportunities and need to reduce fuel consumption
• CSX uses 6 sigma, DMAIC methodology to support our core valuesFact Based, Right, Results the Right Way
• PIT+, 6s, BPMS, and other processes were utilized in the project selection, which are consistent with corporate goals.
• The project selection included:
These considerations: These measures:- Data availability and quality - locomotive idle time in hours- Projected benefits/savings - gals/hr consumed while idling- Sponsor commitment (burn rate)- Structural vs actionable gaps - shutdown performance- Internal and external % hours shutdown customer impact - historical total idle time
- Impact on existing initiatives - $/gal = cost of fuel
Recapping – project selection was done through a systematic look at existing process gaps and opportunities through CSX’s standard method of finding solutions to complicated problems, 6 sigma and DMAIC discipline.
The 6 Sigma team members and team training would allow us to select the most powerful analytic tool to apply against our data
to determine validity and potential, with the participation and involvement of a broad group of stakeholders.
2020202020202020
1.B Impact on Organizational Goals
Core Values:
• It Starts with the Customer – success dependent on satisfying needsof internal customers
• People Make the Difference – success from behavioral change
• Safety is a Way of Life – safe procedures for positive impact
• Fact Based – data driven
• Right Results, Right Way – process rigor
CSXT Vision:
To be the safest, most progressive North American railroad, relentless in the pursuit of customer and employee excellence.
Purpose:
To capitalize on the efficiency of rail transportation to serve America.
Organizational Goals
CSX has a clearly defined and articulated mission statement consisting of a Corporate Vision, Purpose, and Core Values.
Let’s take a look at how this project supports and aligns with our companies mission and key measures.
2121212121212121
1.B.a Affected Goals
Company Goals, Strategies, ObjectivesProject Impact How this project affects the objective
Company Vision: To be the safest, most progressive North American railroad, relentless in the pursuit of customer and employee excellence.
Inovative approach to measuring performance of a traditionally un-measured activity. Continuous improvement approach.
Company Purpose:To capitalize on the efficiency of rail transportation to serve America.
Increased efficiency by lowering fuel consumption and expense
Company Values:
It starts with the customer.Needs and behavior of internal customers will drive the success of the project
People make the difference.Requires engagement of broad team and locomotive user community
Safety is a way of life. Customer and data drivenFact based. Use of 6 Sigma tools
Right results, right way.Positive impact on the comunities we serve and the environment
Key Performance measuresOperating Ratio Lowering fuel consumption will reduce expense
On time departuresWill track starting issues to ensure train originations are not impacted
% of time Locomotives Out of ServiceReduced engine run times will lesson wear on locomotive components
Locomotive Fuel productivity (Gallons/KGTM) Reduced fuel consumption will reduce gallons/KGTMRight Car Right Train (RCRT) No impact on RCRTTrain Veleocity No impact on system train velocity Crew Availability Does not impact crew availablity
KEY: Positive impactPotential negative impact
White No impact
Corporate Metrics
When comparing the project objectives to our mission and key measures we found strong alignment and support.
Members of the team had concerns that as more units were shutdown we may see failures restarting them that could delay train departures – delaying train departures has customer impact and we must control this risk.
2222222222222222
1.B.b Type of Impact Corporate Impacts
Company Goals, Strategies, Objectives P
roje
ct
Impa
ct How this project affects the objective
Methods or Tools used to assess the types of impact the
project would have
Vision: To be the safest, most progressive North American railroad, relentless in the pursuit of customer and employee excellence.
Inovative approach to measuring performance of a traditionally un-measured activity. Continuous improvement approach.
Six sigma, PIT, periodic reviews of relevant data
Purpose: To capitalize on the efficiency of rail transportation to serve America.
Increased efficiency by lowering fuel consumption and expense PIT+ process and Driver trees
Company Values:
It starts with the customer.
Needs and behavior of internal customers will drive the success of the project
Cross-functional team, FMEA - recognize and prevent any colateral effects
People make the difference.Requires engagement of broad team and locomotive user community Change Accerleration Process (CAP) tools
Safety is a way of life. Project reduces exposure to emissionsGovernment emissions credits
Fact based. Use of 6 Sigma tools
MSA on primary measurement system / DMAIC approach
Right results, right way.Positive impact on the comunities we serve and the environment
Validated measurement system that is consistant and actionable at applicable levels
Key Performance measures
Operating RatioLowering fuel consumption will reduce expense Shutdown performance
On time departuresWill track starting issues to ensure train originations are not impacted
Team FMEA. Track train originations & field feedback
% of time Locomotives Out of ServiceReduced engine run times will lesson wear on locomotive components Team conclusion of "subject matter experts"
Locomotive Fuel productivity (Gallons/KGTM)Reduced fuel consumption will reduce gallons/KGTM Shutdown performance, KGTM / tracking
These three columns are carried over from the previous slide with methods
and tools added to the matrix
Multiple tools were used when we assessed the types of impact the project could have.
The tools included subjective tools such as SME input / FMEA / change acceleration process or CAP tools and Driver Trees.
and analytical tools to validate the Measurement System and review historical and ongoing performance of the project and the companies key performance measures.
2323232323232323
1.B.c Methods /Tools Determining Degrees of Impact
The Shutdown Performance MeasurementPercent of Locomotive Shutdown Using GPS Ping Data
for Non-moving Events
Data downloaded every 24 hrs and reports generated daily (24hr delay)for all GPS equipped locomotives. Data used by this project includesevents > or = one hour.
GPS = Global Positioning SystemPing = Data Transmission Event
GPS equipped Locomotive
(78%)
Satelliterelay
Receiving station
Data processingcenter
An example of one method used to track the degrees of impact the project would have was the development of the shutdown performance measurement.
78% of our locomotive fleet is equipped with the GE pinpoint TM system.
This system generates an automated transmission each hour that provides information about the status of the locomotive and whether it has moved since the last transmission.
2424242424242424
1.B.c Methods /Tools Determining Degrees of Impact
Locomotive IDTime-locationMilepost of reportingGPS message typeCity of reportingState of reportingLatitude of reportingLongitude of reportingFuel level in gallonsHours since last movementLoco running or shutdown
0 = main engine shutdown; APU ok1 = main engine running isolated; APU ok2 = main engine running with power; APU ok3 = main engine shutdown; APU failed4 = main engine running isolated; APU failed5 = main engine running with power; APU failed
GPS interface statusFuel monitor interface statusGPS antenna status
Equipment failure alarm0 = no equipment failure1 = maintenance mode2 = equipment failure
GPS Ping Data Conversion – What Does it Mean
GE Harris Data CenterGE Harris Data CenterMelbourne, FloridaMelbourne, Florida
CSX SystemsCSX Systems
The hourly message contains several pieces of information, but for this project we focused on 4 items.
2525252525252525
1.B.c Methods /Tools Determining Degrees of Impact
Locomotive IDTime-locationMilepost of reportingGPS message typeCity of reportingState of reportingLatitude of reportingLongitude of reportingFuel level in gallonsHours since last movementLoco running or shutdown
0 = main engine shutdown; APU ok1 = main engine running isolated; APU ok2 = main engine running with power; APU ok3 = main engine shutdown; APU failed4 = main engine running isolated; APU failed5 = main engine running with power; APU failed
GPS interface statusFuel monitor interface statusGPS antenna status
Equipment failure alarm0 = no equipment failure1 = maintenance mode2 = equipment failure
GPS Ping Data Conversion – What Does it Mean
GE Harris Data CenterGE Harris Data CenterMelbourne, FloridaMelbourne, Florida
CSX SystemsCSX Systems
Locomotive I.D. it’s location, the number of hours since last movement and whether the unit was running or shutdown.
After validating that the pinpoint equipped fleet had the same mix of engine type and service as the overall fleet.
We treated the hourly message or “ping” as an unbiased sampling of the fleet.
Looking only at the pings where the locomotive had not moved for an hour or more – we measured the percentage of these pings where the locomotive was shutdown.
This gave us an unbiased measurement to gauge our shutdown performance and to measure the projects impact and value.
2626262626262626
1.B.c Methods / Tools Determining Degrees of Impact
26M Gals
Cumulative % of locomotive idle time by TemperatureDrives Savings Opportunity
32º - 24.80%
40º - 37.63%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
-31
-20
-13 -5 2 9 16 22 28 34 41 47 53 60 67 73 81
28 - 19.91%
Opportunity > or = 40= ~20M Gals
Opportunity < or = 40= ~10M Gals
Opportunity in Gallons for Percent of Idle Time by Temperature
Once the measurement was defined, we used our archive of pinpoint data to establish an historical baseline.
Then tied in temperature data from the NOAA to understand our historical capability and size the projects opportunity.
2727272727272727
1.C Impact on Stakeholders
Potential Stakeholders
SLT and Champions
Locomotive Mgt and shop employees
Transportation Mgt and T&E employees
Finance and Purchasing
Environmental
Communities Served
Stakeholders: Key Measures:
EffectivenessEfficiency
Effectiveness
Effectiveness
Efficiency
Effectiveness
Effectiveness
Impact:
Savings opportunity $30M.No decrease in on-time departures
Requires behavioral change and decrease in locomotive maintenance
Requires behavioral changes and reduces fuel expense
Less fuel needed
Potential emissions reductioncredits. Stewardship of naturalresources
Reduced noise and emissions
You’ll recall from our earlier discussion of potential stakeholders that the project had received initial stakeholder support – after all they were involved in it’s germination and selection.
2828282828282828
Supplier(s) Inputs Process Step
Outputs Customers
Dwell event
S I P O C
Identify the need
for shutdown
Manual shutdown
and secure
1.C.a Identification of Stakeholders
Ambient temperature
Length ofdwell
Health of locomotive
Need for compressedair source
Shutdownand secure
Allow locomotiveto idle
T&Eemployee
T&EMgt.
LocoShop Mgt.
LocoShop
employee
Savingfuel
SLTChampion
Finance
Communities
Fieldmgt
Purchasing
Environment(Government)
Team Identification of Potential Stakeholders
Team final validation of potential stakeholders was conducted by using a SIPOC, with the Suppliers and Customers included as project stakeholders.
Let’s look at the stakeholders’ perspectives and how they will be impacted.
2929292929292929
Finance / Purchasing:•Validates savings•Current budgets•Future plan
TransportationDepartment.
LocomotiveDepartment
Communityand
EnvironmentalIssues
Team with 6σ Support
SLT / Champion:•Soften resistance•Allocate resources•Performance metrics•Air cover•Goals
1.C.a Identification of Stakeholders
= Involvement shown onfollowing pages
The Senior Leadership Team and project champion are very supportive and critical for the projects success. They will address resistance, allocate resources, and ensure project goalscascade through the organization.
The finance and purchasing stakeholders will track and validate savings, ensuring budgeting activity reflects project success –tying in the budget process will further commit functional departments to the project.
3030303030303030
1.C.a Identification of Stakeholders1.C.b Types of Impact on Stakeholders
Locomotive shop and service center management and employeesagree that idle reduction can and should be improved – but:
• Concerned that locomotive will not restartonce they are shutdown
• Production will suffer if a restart (jump start) isrequired of a previously shutdown locomotive
The employees that manage and work in our locomotive shops and service centers agree with the project aim – reducing fuel consumption while locomotives are non-productive is a great concept – but they have concerns.
Success means they will need to shutdown and restart locomotives more often. This is more work particularly if locomotives don’t restart and need to be assisted. Re-starting problem can hurt their facility throughput and take resources away from their primary tasks.
3131313131313131
Transportation management and T&E employees are fue lconscious, and want to help – but:
• Concerned that a restart of theirlocomotives may cause yard delays
• Initial start-up takes more time than having an idling locomotive waiting
• Why shutdown locomotives for a short period of time, lunch, coffee,phone call, etc.
• At outlying points they may not start, no locomotive maintenance assistance
1.C.a Identification of Stakeholders1.C.b Types of Impact on Stakeholders
Employees in train and engine service or T&E operate our trains and provide the value added service that is our companieseconomic engine, they are very fuel conscious.
But – they too have concerns that locomotives won’t restart easily - delaying trains, hurting production and degrading service to our customers.
3232323232323232
� Hanson, Massachusetts Residents Say Train Rest Stop Leaves Engine Idlingat Night, Disturbing their SleepHanson, Massachusetts residents have complained that a Railroad locomotive makes regular rest-stop breaks at night, stopping the loudly idling engine near their homes and disturbing their sleep.
� Judge Gives Railroad Another Month to Address Noise Complaints from IdlingEngines at Franklin Lakes, New Jersey; Railroad Uns ure If Adding AdditionalTracks Elsewhere Is Feasible
� Diesel Fumes Disturb Residents From Two More Commun ities in Quebec; Join Class Action Suit Against Two Canadian Railway s
Additional Benefits in the Form of Reduced Noise an d Air Pollution:
Community & Environmental Issues
1.C.a Identification of Stakeholders1.C.b Types of Impact on Stakeholders
Our environmental group is a project supporter. They envision fewer noise and air pollution complaints and opportunity to gain emission reduction credits.
The environmental group serves as the internal voice for the communities we serve. Increased sensitivity to noise and air pollution from idling locomotives allows this constituency to benefit from improved locomotive shutdown.
3333333333333333
1.C.b Types of Impact on Stakeholders
Stakeholders
SLT &Champion
LocomotiveMgt / ShopEmployees
TransportationMgt / T&EEmployees
Finance &Purchasing
Environmental
Communities
StrongAgainst
ModeratelyAgainst
X
Neutral
X
ModeratelySupportive
Y
X Y
X Y
X Y
StrongSupportive
X
Y
Stakeholder Analysis (Black belt feedback to champion)
Key:X = CurrentY = Proposed
Discussions with the cross-functional team, field visits, and interviews led to our stakeholder analysis summarized here.
The next step was an influence strategy.
3434343434343434
1.C.b Expected Resistance
Influence StrategyLevels of Resistance:Low = no impactMedium = project delay likelyHigh = possible project failure
Key Stakeholder
Impact Reasons for Resisting Change
Level of Resistance (High, Medium, Low)
Strategy for Dealing with Resistance
SLT and Champion
Savings opportunity $30M No decrease for on-time originations Higher priorities Low
Celebrate success and reinforce Leverage high level support
Locomotive Mgt / Shop Employees
Potential decrease in locomotive maintenance
More work Not important to locomotive Medium
Leverage high level support Track performance & reward successes
Transportation Mgt / T&E Employees
Neutral to current measures
More work Fear that units won't restart - impacting key process High
Leverage high level support. Track performance & reward successes
Finance & Purchasing Less fuel needed None None NoneEnvironmental Air pollution standards None None NoneCommunities Less noise polution None None None
To be successful we would need to maintain and leverage the support of the SLT while increasing support from two key stakeholder groups:
Locomotive shop and service center employees
and
Our train and engine or (T&E) personnel
We not only needed the support of these groups, but we needed them to change behavior.
3535353535353535
1.C.c Stakeholder Validation of Impact
Team concurred after reviewing X’s that Risk Priori ty Number(RPN) > 200 required action
Developed Stakeholder Concerns & Current Controls
Failure Modes and Effects Analysis (FMEA)
Process Step/Input
Potential Failure Modes (process defects)
Potential Failure
Effects (Y's)
SEV
Potential Causes of Failure (X's)
OCC
Current Process Controls
DET
RPN
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9 Not able to determine sit time, when will
locomotive be needed again
6
Direction by employee in charge, yardmaster, train dispatcher, or other proper authority
7 378
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel 9
Needed to maintain air pressure 6 Rule 5401
6 324Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel 9
Units tagged with starting system failures 5
Educational memos
7 315
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9
Lack of current and anticipated weather information, ambient
temp
6 Engineer reading file / rule 5401
5 270
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9Confusion about
automated shutdown systems
4 Location specific information
6 200
Shutdown decision
Employee does not shutdown locomotive Wasted fuel 9
Rule knowledge, attitude 6
Engineer reading file / rule 5401
5 270
Our project team worked through an FMEA to understand the degree of impact the project would have on stakeholders and the causes for potential resistance.
At this point we’ve seen that the project was selected based on process gaps and opportunities, it clearly aligns and supports the companies’ mission, strategies, and measures and has broad stakeholder support and participation.
We now have a better understanding of the type and degree of impact the project will have on stakeholders and some expectations for where resistance will arise.
Now it’s time to start the work!
3636363636363636
2.A Potential Root Causes
• Process map of locomotive shutdown process• Ownership at all process steps• GPS Ping data by location, time of day, temperature, and length of dwell
Locomotive
Transportation
Process Approach
The team began by walking the process, understanding the decision points and the information available at those decision points, recognizing ownership at each process step, and slicing the historical data for clues as to where the process was weakest.
Let’s take a look…
3737373737373737
2.A.a Root Causes / Opportunities
SME Insights to Potential Root Causes from FMEA
• Employee knowledge and attitude
• Current and expected ambient temperature
• Dwell time of locomotive
• Actionable opportunities
• Applicable Rule regarding when to shut down
• Health of locomotive
The project team’s FMEA provided initial insight into potential root causes
3838383838383838
Questionnaire Mailed to all Locomotive Engineers Ho mes2.A.a Root Causes / Opportunities
Achieved: Affirmation of shutdown compliance and fuel saving feedback and ideas
A questionnaire was sent out to all engineers to serve as a fuelshutdown reminder and affirmation.
And to gain their feedback and ideas.
The responses generated some new ideas and affirmed the results in our FMEA.
3939393939393939
Shutdownand Secure
DwellEvent
YesYes
Isolate and Secure
No No
Needed to Maintain Air
Pressure
HealthyStartingSystem
AmbientTemp> 35
Not Needed
> 15 Mins
Yes
Yes
Isolate and Secure
Isolate and Secure
Isolate and Secure
No
No
CTQ: Locomotives are to be shutdown when not used for thirty (30) minutes or longer, ambient temperature is anticipated to beforty (40) degrees or higher; not required as an air supply
Who: T&ELoco Ops
T&ELoco Ops
Loco Ops T&E
Process Ownership2.A.a Root Causes / Opportunities
The process we are dealing with appears fairly simple.
To be successful we must improve the locomotive operators decision and their willingness to execute that decision as they finish use and step off the locomotive.
This is the critical decision point where they either shutdown the locomotive or allow it to idle.
To be successful we must effect the behavior of over 8,000 employees in hundreds of locations, spread over the eastern half of the country.
These operators may be locomotive operations employees working within the confines of a shop / service center,
in a major yard or outlying points.
4040404040404040
Shutdownand Secure
DwellEvent
YesYes
Isolate and Secure
No No
Needed to Maintain Air
Pressure
HealthyStartingSystem
AmbientTemp> 35
Not Needed
> 15 Mins
Yes
Yes
Isolate and Secure
Isolate and Secure
Isolate and Secure
No
No
Team concurred after reviewing X’s that Risk Priority Number (RPN)greater than 200 required action
Burn rate at idle = ~4 gallons/Hr45% of the time locomotive at idle = $30M
378 270 315 324RPN score:
FMEA / RPN Driven Focus
2.A.a Root Causes / Opportunities
The team looked at which steps in the process had the highest RPN scores to continue the identification of root causes.
4141414141414141
Cause & Effects Matrix
2.A b Team Analysis of Data
Team Participation in Root Cause Analysis
• Transportation – operations management, support management, and labor• Locomotive – operations management and support management and labor• Finance / Purchasing – support management • Six sigma – master black belt and black belts• Environmental – support management • Community – silent partner
Rating of Importance to Customer 10 10 10 10 9 81 2 3 4 5 6
Process Step Left
Idle
Shu
tdow
n
Aut
omat
ed S
hutd
own
Sys
tem
On-
time
Dep
artu
res T
empe
rat
ure
Rul
es
Kno
wle
dge Total
1 Dwell Period Starts Train Arrival 9 0 1 0 3 3 151" Time left to work 3 3 0 0 9 0 141
" Idle locomotive coordination9 9 9 9 9 9 513
" Train Schedule 1 9 0 9 0 3 2142 Not needed for > 15 minutes Time left to work 3 9 0 0 3 0 147
" Idle locomotive coordination9 3 0 0 3 9 219
" Train Schedule 1 1 0 0 9 0 101
" Locomotive Plan 9 9 1 0 3 0 217
3 Ambient Temp > 40 degrees FahrenheitIdle locomotive coordination
9 9 9 9 9 9 513
" Scheduled Trains 9 3 0 0 3 9 219
" Weather source 9 9 9 9 9 1 449
The FMEA was used to identify issues of critical importance to the stakeholders and to view the issues in context with all stakeholder’s involvement.
The team also worked through a C&E matrix to validate the insights from our FMEA, relate the inputs to customer requirements and prioritize potential root causes.
4242424242424242
Example of Ping Data from GPS equipped locomotives – 2003Shutdown engines by hours running and not moving by location
Team Review of Location vs Location
Region (All)Division (All)Location (All)
APU equipped vs non APU equipped - Year over Year Shutdown performance for the System% Shut down Year APU Year over Year Shutdown performance for the System
2003 2003 Total 2004 2004 Total
Week N Y N Y WeekNo APU -
20031 12.9% 61.3% 26.7% 14.9% 62.7% 36.6% 01 12.91%2 12.6% 58.0% 26.1% 15.5% 60.4% 36.3% 02 12.62%3 11.3% 55.1% 25.0% 12.6% 55.9% 33.3% 03 11.26%4 12.3% 52.9% 24.8% 13.4% 54.3% 32.4% 04 12.33%5 15.0% 55.1% 27.6% 13.3% 50.9% 30.5% 05 14.99%6 16.9% 62.2% 31.1% 14.3% 52.1% 32.1% 06 16.85%7 15.2% 61.5% 30.3% 15.4% 52.4% 32.5% 07 15.22%8 13.9% 62.3% 28.8% 15.3% 55.5% 34.0% 08 13.89%9 17.1% 63.8% 32.5% 17.4% 54.6% 34.6% 09 17.13%
The graphs will change to reflect the values selected for Location, Division or Region.
Drill-down of data from a system level to a specific location (terminal)How used: team identified differences among locations
2.A b Team Analysis of Data
While we developed SME insights from our C&E and FMEA, we investigated hard data sources to confirm our SME insights.
The hard data we used was the GPS Ping data on our locomotive fleet
4343434343434343
Year over Year Shutdown performance for the System - all pinpoint equipped units
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Validated Ping Data Supports Performance Outcomes
System
Region Year over Year Shutdown performance for the Norther n Region
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for the Albany Division
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Division
2.A b Team Analysis of Data
Year over Year Shutdown performance for Buffalo, Ny
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003Terminal
In our review of GPS data, we were able to drill down to identify shutdown practices & activities by location.
4444444444444444
2.A.c Stakeholder Involvement
Stakeholder Roles, Involvement and Impact ofContribution to Root Cause Analysis
SLT and Champion
Locomotive Mgt and shop employees
Transportation Mgt and T&E employees
Finance andPurchasing
Environment /Communities served
Black Belt support
Who: Role:
Secure resources
Locomotive Engineering support
Advise on issues perceived byend users
Finance / budgetanalysis
Help identify “other’occasions of shutdown opportunity
Data analysis
Responsibility:
Monthly champion reviews and oversight
Validate impropershutdownsEvaluate starting systemissues and failures
Evaluate failuresIdentify exceptions for missed opportunities
Not process ownersProvide cost per gallon
Support through ideageneration
Perception on process variationEffectiveness of current controls
Impact:
Low
High
High
Medium
Low
High
Levels of Impact:Low = support roleMedium = validationHigh = SME’s
During this process each team member contributed as his expertise provided.
Field officers contributed process steps and helped us evaluate failures and understand location differences.
The finance / purchasing representatives validated savings estimates.
The black belts developed validation of SME insights and beliefs
SLT provided timelines and expectations of success.
4545454545454545
2.B Team Analysis
Team Analysis of Root Causes
� SLT / Champions – monthly meetings – oversight, resource support
� Cross functional team - SME / FMEA / process map / C&E / benchmarking – develop issues list
� MBB / BB – ANOVA, Regression, Moods Median – provide statistically relevant data
� Project team – manage analysis, agree on root causes
� Finance – validate dollars / impact
The identification and analysis of root causes started with subjective insights followed by data collection and analysis.
Providing the facts that led to team agreement around root causes.
All team members contributed.
4646464646464646
2.B.a Methods & ToolsRoot Cause Roadmap
Why:Who:
Process map
FMEA
C&EA
Questionnaire / survey
MSA
Statistical tests (ANOVARegression, Mood Median)
Team agreementon results
Full team
Full team
Full team
Sent by sub teamFull team review
BB & team support
MBB / BB
Full team
Tool (How):
Understand process& potential failure points
Develop customer concernsPrioritize suspect key drivers
Further validate SME insights
Get operators perspective to support / refute SME insights
Validate GPS data
Validate SME insights & finetune solution set of individualtools selected based on mostpowerful test data allowed
Affirmation of results – lockIn commitment
The process involved a wide variety of tools based on the type of information and data available.
The process also created a common perspective and commitment within the team.
4747474747474747
2.B.b Team Analysis to Final Root Causes
Measurement System Analysis (MSA) of GPS Ping Data
Set up live scenarios using a GPS equipped locomotives:
• At four (4) specific locations (terminals)• Shutdown or idling for a specific period of time• Moved to various locations within the terminal• All data recorded
Validated field data with GPS Ping data:30 locomotives / 250 samplesResults = 100% agreement
Unit Date TimeObserved Running
Observed Hrs Since Movement
Ping Data Running
Ping Data Hrs Since Movement Agreement
132 20-Jun 10:30 No 0 No 0 Yes5754 24-Jun 9:00 No 1 No 1 Yes8832 15-Jul 13:30 Yes 0 Yes 0 Yes707 16-Jul 13:30 No 2 No 2 Yes202 16-Jul 16:00 Yes 1 Yes 1 Yes
" " " " " " " Yes" " " " " " " "
An MSA of the GPS data validating location and shutdown status allowed us to use this data and provide the team with detailed information on individual location’s shutdown activities.
4848484848484848
Rule 5401 - Conserving Fuel
� A. Using fuel conservation methods
— Use fuel conservation methods at all times, as follows:
� Place reverser lever in the CENTER position anytime the locomotive is stationary.
� To the extent possible, avoid using the stretch braking method of speed control.
� Avoid having more locomotives on-line than those required to maintain the maximum speed permitted.
� Empty coal train movements will use only the locomotives necessary to move the train. Trailing locomotives will be isolated and, when weather permits, shut down.
� When handling lite locomotive movements, use only the lead locomotive for power. Trailing locomotives will be isolated and, when weather permits, shut down.
� Unless instructed otherwise by train dispatcher or yardmaster, shut down diesel engines in locomotives when:
− The locomotive will not be used for (30) minutes, and
− Ambient temperature is above forty (40) degrees Fahrenheit
� Engineers must ask the train dispatcher, yardmaster, or work train employee-in-charge to determine the anticipated length of time the locomotive will not be used.
� If necessary to do so, you may allow one diesel engine to idle in order to maintain an air supply to the train.
CSXTransportation Fuel Conservation Rule (pre proje ct)
2.B.b Team Analysis to Final Root Causes
Key Issues
At CSX rules drive behavior, they are our Standard Operating Procedures or SOP’s.
We needed to look at the rule that governed fuel conservation.
We believed idle time and ambient temperature were the key variables in the rule.
4949494949494949
Benchmark – Locomotive Shutdown Temperature
2.B.b Team Analysis to Final Root Causes
Compared CSX’s Shutdown Rule 5401 to Other Class I Rail Roads
Established comfort level that thresholds of lower temperatureand shorter periods of time are attainable, but wit h additional RISK
Standards BNSF CN CP NS UP CSX
Temperature Threshold > 40 > 40 > 40 >32 > 40 >40
Idle Time Threshold
1hr. or longer
10 mins. or longer
30 mins. or longer
30 mins. or longer 1hr. or longer
30 mins. or longer
Lower Temperature Opportunities None
> 1hr. but < 8 hrs. at or above
34 None
< 12 hrs. temp not to drop below 28 None None
Shutdown Rule Comparisons
The team benchmarked other railroads shutdown practices to determine what risk levels our railroad brothers would accept.
Practices at other railroads supported lower temperature and time thresholds.
The team felt it was worth studying further.
5050505050505050
Solution Tree
Process Variation Measurement Variation
EmployeeEmployee
LocationLocation
Length ofDwell
SeasonSeason
TempTemp
Day of Week
2.B.b Team Analysis of Final Root Causes
Data Integrity
audit = 100%
P = 0.00P = 0.00 P = 0.00 P = 0.00 P = 0.00
Fuel Conservation
Rule 5401
ABTH Rule 5401 governs allconditions for manual shutdown
Regression QuestionnaireSME
ANOVA GPS /ANOVA
Mood’sMedian
ANOVA
CTQ: Locomotives are to be shutdown when not used for thirty (30) minutes or longer, ambient temperature is anticipated to beforty (40) degrees or higher; not required as an air supply
The team’s solution tree identified several factors that had statistical significance to shut down performance, most were constrained by our fuel conservation rule.
5151515151515151
OneOneOneOne----way ANOVA: Percent versus Region (Ping Data)way ANOVA: Percent versus Region (Ping Data)way ANOVA: Percent versus Region (Ping Data)way ANOVA: Percent versus Region (Ping Data)
P value = 0.00 P value = 0.00 P value = 0.00 P value = 0.00
Individual 95% CIs For MeanBased on Pooled StDev
Level N Mean StDev -------+---------+---------+---------BUS UNIT 767 7.15 22.10 (-*-) CASO 605 34.84 44.28 (-*-) CENTRAL 4032 17.98 36.21 (*) MIDWEST 2254 17.08 35.01 (*) NORTHEAS 3475 13.35 31.74 (*) OFFLINE 1310 40.96 46.66 (*-) SHOPPED 1507 19.93 34.13 (-*) SOUTHERN 5807 16.41 34.91 (* WESTERN 3978 14.06 32.08 (*)
-------+---------+---------+---------Pooled StDev = 34.89 12 24 36
Location Statistically Significant
2.B.b Team Analysis of Final Root Causes
Here is one example of the analysis that shows clear differencesin performance by location.
5252525252525252
Daily low temperature - AlbanyJan 1 - Dec 31, 2003
-20
-10
0
10
20
30
40
50
60
70
80Te
mpe
rature
Weather Affects Shutdown Performance
% of Idle time shutdown - Albany Division in 2003
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
02 05 08 11 14 17 20 23 26 29 32 35 38 41 44 47 50
Week
2.B.b Team Analysis of Final Root Causes
It was also clear that shutdown performance was impacted by temperature.
5353535353535353
Minimum Temperature during dwell event
Shutdown Performance
806040200
1.0
0.8
0.6
0.4
0.2
0.0
S 0.138058
R-Sq 64.7%
R-Sq(adj) 64.6%
Fitted Line PlotSD Perf = 0.01828 + 0.008694 MINT
Temperature Affects Shutdown Performance
2.B.b Team Analysis of Final Root Causes
And the regression results gave us clues that individuals had different interpretation s as to what the temperature was.
There was not a steep jump in performance as temperature hit 40 degrees, but a linear increase as temperatures climbed.
5454545454545454
EmployeeEmployee
LocationLocation
Day of Week
SeasonSeason
Length of Dwell
TempTemp
2.B.c Root Causes & Validation
Manual shutdown performance declines as temperature lowers• US weather service / GPS Ping shutdown data /
Employees take the most conservative approach as temperaturevaries (avoid restart issues)• SME / employee questionnaire
Largest amount of variation (location to location)• ANOVA / GPS Ping shutdown data
Data confirms that we are not always able to know / predict dwellThe longer a unit sits at a specific location, the more likely we are to shut it down. • GPS Ping shutdown data / ANOVA
Confounded with length of dwell (Sat & Sun experience longer dwell)• GPS Ping shutdown data / ANOVA
Seasonality a key driver to Manual shutdown – confounded by temperature • US weather service / GPS Ping shutdown data / Mood’s Median
Team Analysis of Data:Validated through statistical tests and SME input
Validation involved statistical tests, questionnaire, benchmarking, and SME support.
- we learned a lot.
Location to location had the greatest variation, this and employee to employee differences validated SME insights that rule reinforcement and knowledge variation were paramount in this process.
Mood’s Median test supported seasonality, with ANOVA tests supporting temperature, length of dwell and location as key drivers.
And our rule constrained many of these variables
5555555555555555
2.B.c Final Root Causes & Validation
Why are Idle Locomotives Left Running
• ABTH Rule 5401 � our SOP for manual shutdown
• Rule compliance & knowledge� supported by employee, seasonality, location and day of the week data
• Health of the locomotive� is dependent upon employees, temperature, and length of dwell
• Uncertain knowledge of current conditions� is driven by temperature and length of dwell
LocationLocation
Day of Week
EmployeeEmployee
TempTemp
EmployeeEmployee
Length of Dwell
SeasonSeason
ABTH Rule 5401 is SOP
TempTemp
Length of Dwell
The outcome of our analysis as to “why locomotives are left running” was:
Provisions of our rule.
Rule compliance and knowledge by the responsible individual
Health of the locomotive (can we ensure the locomotive will restart)
And accurate information about current conditions
5656565656565656
3.A Possible Solutions3.A.a Methods & Tools
Possible solutions:• Rule change (time & temperature variables)• Increase employee awareness & rule adherence (training,
communication and auditing)• Reduce locomotives used to maintain air• Improve starting system health (address resistance)• Standardize delivery system of temperature information
Team Identified Final Root Causes – Generated Possib le Solutions
Identified need to have rule and behavioral changes
Improve FMEA
Process Step/Input
Potential Failure Modes (process
defects)
Potential Failure
Effects (Y's)
SEV
Potential Causes
of Failure (X's)
OCC
Current Process Controls
DET
RPN
Actions Recommended
Responsible Party
Action Taken
SEV
OCC
DET
RPN
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9Not able to
determine sit time, when will locomotive be needed again
6
Direction by employee in charge, yardmaster, train dispatcher, or other proper authority
7 378
Identify responsible party for consistant message
Yardmaster Train dispatcher
9 5 4 180
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9Needed to
maintain air pressure
6
Rule 5401
6 324 Install additional yard airplants
Local management
Outside of project scope
9 6 6 324
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9 Units tagged with starting system
failures
5
Educational memos
7 315Evaluate SOP for charging system issues
Locomotive management
Oversight team established
9 4 4 144
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9
Lack of current and anticipated
weather information,
ambient temp
6
Engineer reading file / Rule 5401
5 270
Provide weather source and updates for crews
Operations center
Weather service contract in place
9 4 5 180
Shutdown decision
Employee not permitted to shut down locomotive Wasted fuel
9
Confusion about automated shutdown systems
4Location specific
information
6 200
Now that we have causes the team brainstormed possible solutions and used an improve FMEA to begin to gauge their potential value.
Possible solutions fell into two buckets
Increasing our shutdown opportunities and
Improving shutdown performance where the opportunity existed
Let’s walk through one example of the analysis.
5757575757575757
Water Temperature Decay Recorded on Sample Shutdown LocomotivesWater Temperature Decay Recorded on Sample Shutdown LocomotivesWater Temperature Decay Recorded on Sample Shutdown LocomotivesWater Temperature Decay Recorded on Sample Shutdown Locomotives
Water temperature decay for units shutdown at vario us outside temperatures (all samples were EMD units)
0º
20º
40º
60º
80º
100º
120º
140º
160º
180º
0.0 2.0 4.0 6.0 8.0 10.0
12.0
14.0
16.0
18.0
20.0
22.0
24.0
26.0
28.0
30.0
32.0
Time in hours since shutdown
Wat
er te
mpe
ratu
re a
t the
dum
p va
lve
1º 14º-1º 19º-21º 24º-17º
28º-21º 32º-27º 54º-28º 55º-37º
34º-39º 71º-39º 39º-51º Model at 28º
Outside temperature during shutdown period
3.A.b Teams Analysis of Data
Team review of temperature options; acceptable shutdownrisk for possible rule change
We believed we could increase shutdown opportunity by adjusting the parameters of the rule, but needed to understand the risk.
We collected data from temperature gauges installed in the water return system on a sample of units in colder weather.
Each of the units had a dump valve installed so that the engine water would automatically drain when it reached 40 degrees preventing any possible freeze damage.
5858585858585858
Temperature decay for unit 2614 with outside temp dropping to 37º
0
50
100
150
200
0 2 4 6 8 10 12 14 16 18 20
Time in hours
Wat
er te
mp
at d
ump
valv
e
2614 Model Model @ 28
Regression hit 40º after 14 hours @ 28º
Locomotive Cooling System Temperature DecaySupports Lower Shutdown Threshold
The two units that
indicate a 14 hour
timeline to 40º
3.A.b Teams Analysis of Data
Temperature decay for unit 6204 with outside temp dropping to 39º
020406080
100120140160
0 2 4 6 8 10 12 14 16 18 20 22 24
Time in hours
Wat
er te
mp
at d
ump
valv
e
6204 Model Model @ 28
Regression hit 40º after 14 hours @ 28º
This data was modeled to predict behavior at different air temperatures.
5959595959595959
� A regression of the sample units indicates:
— At 28º ambient temperature, it should take 32 hours for water temperature to reach 40º
— At 28º ambient temperature, it should take 52 hours for the water temperature to reach freezing
� However, each locomotive has a different heat transfer rate
— The data on two of the units indicates they would reach 40º in as quickly as 14 hours and begin freezing at 25 hours
� While some variation in unit to unit exists, we can tolerate risk at 35ºfor shutdown without unusual risk of locomotive (engine & components) damage
� At 35º ambient temperature, locomotive cooling water will never reach freezing
What Did we Learn / What are our Concerns What Did we Learn / What are our Concerns What Did we Learn / What are our Concerns What Did we Learn / What are our Concerns
3.A.c Criteria for Final Solutions
Higher risk,would needmonitoredat 28º
Tolerablerisk at35º
The regression model from the temperature data detailed the risk exposure at different temperature levels.
6060606060606060
High
Low High
Ease of Implementation
Val
ue to
Impl
emen
tatio
nTeam Review of Final Root Causes / Solutions
3.A.c Criteria for Final Solutions
Reducelocomotives
used to maintain
air
Time &TemperatureThresholds
Healthy Locomotive
StartingSystem
Behavior &Knowledge
RuleChange
In a similar manner, the team reviewed other potential solutionsand the relationship between ease of implementation and expected value.
6161616161616161
3.B Determining Final Solutions
Relevant Issues
• 28º shutdown possible at specific shop locations
• Heat loss stable @ 35º with acceptable risk
• Manual shutdown is time and temperature sensitive
• Employee knowledge of ABTH Rule 5401 and their knowledge ofcurrent conditions drives behavior
The teams good work has identified several actionable items.
•Rule drives behavior
•Shutdown is time & temperature sensitive
•We can tolerate lower temperature shut down practices
And employees knowledge of the rule and current conditions drives the results.
We believed a rule change and increasing employee awareness would drive the results, but needed to finish the analysis and make sure we had broad support.
6262626262626262
Cumulative % of locomotive idle time by Temperature
35º - 30.44%
28º - 19.91% 32º - 24.80%
40º - 37.63%
0%10%
20%30%
40%50%60%
70%80%
90%100%
-31
º
-20
º
-13
º
-5º
3º
10º
17º
23º
29º
35º
42º
48º
55º
62º
69º
77º
84º
WhatWhatWhatWhat’’’’s it worth to lower our shutdown temperature from 40s it worth to lower our shutdown temperature from 40s it worth to lower our shutdown temperature from 40s it worth to lower our shutdown temperature from 40ºººº to 28to 28to 28to 28ºººº ????
Outside temperature at start of not moving period
% of to
tal not m
ovin
g time at o
r belo
w th
is temp
eratu
re
17.7% of our locomotive not moving time occurs between 28ºand 40º. This equates to an annual opportunity of ~ 4.6M gallons.
3.B.a Methods & Tools
We looked at the expected fuel savings impact of a lower shutdown temperature threshold.
6363636363636363
3.B.b Team Analysis of Data
Ris
kAt 40º dump valve can drain cooling water –operational disruption
At 32 water freezes – significant engine damage
How rapidly does the water temperature at the dump valve decay after the unit is shutdown?
Outside temperature
40º 35º 28º
40º39.5
Hours36.5
hours32.5
hours
32º never never 53 hoursHow
long
bef
ore
wat
er
tem
pera
ture
rea
ches
:
Risk
And further evaluated the risks based on water temperature decay regressions, the team developed Risk / Reward data to support the solution of lower temperature shutdown.
6464646464646464
Ris
kOutside temperature
40º 35º 28º
40º39.5
Hours36.5
hours32.5
hours
32º never never 53 hours
How
long
bef
ore
wat
er
tem
pera
ture
rea
ches
:
Add
edO
ppor
tuni
ty
Opp
ortu
nity None –
currentrule
4.6Mgallons
3Mgallons
Reward
Additional opportunities at lower shutdown temperat ures3.B.b Team Analysis of Data
Reward opportunities were developed based on our cumulative frequency chart reviewed earlier.
6565656565656565
Suggested Changes
• At selected locomotive shops / service centers that are manned 24 X 7,the shutdown temperature threshold would be decreased from 40º F to28º F
• ABTH Rule 5401 would have a temperature decrease from 40º F to 35º Fand also reduce the time element from thirty (30) minutes to fifteen (15)minutes
• Both changes are based on benchmarking and validated by temperaturedecay regressions
3.B.b Team Analysis of Data
The team supports two rule changes with savings expectations well documented
And they recognized the need to improve rule compliance through a strong communication plan.
6666666666666666
3.B.c Stakeholder Involvement
Agree to Accept and
Manage Risk @ 35º
Finance / Purchasing6σ support
LocomotiveSelect locations
28SLT / Champion
TransportationEnvironmental /
Community
YES YES
YES YES
Stakeholder involvement in final decision
Team progressed rule change recommendation to Senior Leadership Team /Champion for adoption and implementation
YESYES
º
(monitor shift in performance)
(approve rule change)
(see improvement)
(validate savings)
(specific rule application)
(education of engineers)
These solutions were selected with the involvement of all stakeholders through both individual contribution and team concurrence.
The team universally endorsed the rule changes and the risk reward analysis, and jointly presented the proposal to the SLT for adoption.
6767676767676767
3.C Team Solutions
Final Team Solutions
Solutions:
Rule change from40º to 35º and from30 to15 minutesidle time
Additional opportunityat specific locomotiveshops / service centerLocations allowing formonitored shutdown to 28º
Improve employeerule compliance
Validation:
% of locomotiveidle shutdownpost rule change
% of locomotiveidle shutdownpost rule change
% of locomotiveidle shutdownpost rule change
Benefits:
Gallons savedNo impact ofon-time originations
Gallons savedNew measurement established
Gallons savedImproved rules compliance
The team’s solution set, analysis, and validation virtually guaranteed benefit generation.
6868686868686868
Cumulative % of locomotive idle time by Temperature
35º - 30.44%
28º - 19.91% 32º - 24.80%
40º - 37.63%
0%10%
20%30%
40%50%60%
70%80%
90%100%
-31
º
-20
º
-13
º
-5º
3º
10
º
17
º
23
º
29
º
35
º
42
º
48
º
55
º
62
º
69
º
77
º
84
º
Outside temperature at start of not moving period
% of to
tal not m
ovin
g time at o
r belo
w th
is temp
eratu
re
3.C.a Final Solution Validation
Final Solution Opportunities
3,800 locomotives subjectto temperature variation
The cumulative frequency chart validated the opportunity expectations that would come by lowering the temperature threshold in the fuel conservation rule.
6969696969696969
5401. CONSERVING FUEL
A. USING FUEL CONSERVATION METHODS
USE FUEL CONSERVATION METHODS AT ALL TIMES, AS FOLLOWS:
UNLESS INSTRUCTED OTHERWISE BY A TRAIN DISPATCHER, YARDMASTER, OR OTHER PROPER AUTHORITY, SHUT DOWN A LOCOMOTIVE'S DIESEL ENGINE WHEN
* THE LOCOMOTIVE WILL NOT BE USED FOR FIFTEEN (15) MINUTES.
* WHEN CURRENT AND EXPECTED TEMPERATURE DURING THE SHUTDOWNPERIOD IS ABOVE THIRTY FIVE (35) DEGREES FAHRENHEIT.
* IN COMPLYING WITH THIS RULE, PERFORM A MANUAL SHUTDOWN ON ALLLOCOMOTIVES CONSISTENT WITH ABTH RULE 5352 B, EXCLUDING THOSELOCOMOTIVES EQUIPPED WITH AN AUTOMATIC ENGINE START AND STOP(AESS) SYSTEM. AESS EQUIPPED LOCOMOTIVE/S NEED ONLY BE ISOLATED FOR COMPLIANCE.
* THIS INSTRUCTION APPLIES TO ALL ASSIGNMENTS INCLUDING YARDPOWER TYING UP FOR LUNCH AND AT THE COMPLETION OF THEIR SHIFT.
1. IF NECESSARY TO DO SO, YOU MAY ALLOW ONE DIESEL ENGINE TO IDLEIN ORDER TO MAINTAIN AN AIR SUPPLY TO THE TRAIN.
Key ABTH Rule 5401 changes September 2004Time and Temperature Thresholds
Key Changes:Time and TemperatureThresholds
3.C.a Final Solution Validation
The key elements of the rule change where:
1. Changing the temperature threshold from 40 degrees to 35 degrees.
and
2. Changing the expected shutdown time from 30 minutes to 15 minutes
7070707070707070
2. WHEN A TRAIN OR LOCOMOTIVE(S) ARE STOPPED, THE ENGINEER MUST CENTER THE REVERSER HANDLE TO ACTIVATE THE LOW IDLE FEATURE AND ALLOW THE AUXILIARYPOWER UNIT (APU) OR AUTOMATIC ENGINE START STOP (AESS) SYSTEM TO OPERATE ON EQUIPPED UNITS.
3. AVOID HAVING MORE LOCOMOTIVES ON-LINE THAN THOSE REQUIRED TO MAINTAIN THEMAXIMUM SPEED PERMITTED. HANDLE THE TRAIN IN A SAFE AND FUEL-EFFICIENTMANNER. USE DYNAMIC BRAKING AND THROTTLE MODULATION AS THE PREFERRED METHOD FOR SPEED CONTROL. AVOID USING THE STRETCH BRAKING METHOD WHEREVER POSSIBLE. NOTE: EMPTY COAL TRAIN MOVEMENTS WILL USE ONLY THE LOCOMOTIVES NECESSARY TO MOVE THE TRAIN.
4. WHEN HANDLING LITE LOCOMOTIVE MOVEMENTS, USE ONLY THE LEAD LOCOMOTIVEFOR POWER. NOTE: HELPER ENGINES MUST SHUT DOWN OR ISOLATE LOCOMOTIVES AT THE FIRSTSTOP, AFTER DETERMINING POWER IS NOT NEEDED.
5. WHEN ADVISED BY THE TRAIN DISPATCHER THAT THERE WILL BE A DELAY OF 30 MINUTES OR MORE FOR A LINE-OF-ROAD TRAIN, ALL LOCOMOTIVES EXCEPT THE CONTROLLING LOCOMOTIVE WILL BE SHUT DOWN OR ISOLATED. LOCOMOTIVES WILLBE RESTARTED PRIOR TO THE END OF THE DELAY TO ENSURE THE TRAIN IS READY TO PROCEED WHEN AUTHORIZED. (5 MINUTES PER LOCOMOTIVE WILL BE USEDAS A GUIDELINE FOR CALCULATING THE TIME NEEDED TO RESTART THE LOCOMOTIVES IN THE CONSIST).
6. WHEN A TRANSFER TRAIN, WORK TRAIN, YARD ASSIGNMENT, OR PUSHER LOCOMOTIVE WILL BE DELAYEDIN EXCESS OF 30 MINUTES, ALL LOCOMOTIVES WILL BE SHUT DOWN, OR ISOLATED. TRAIN AND LOCOMOTIVESMUST BE PROPERLY SECURED.
7. AFTER YARDING A TRAIN, ALL WORKING LOCOMOTIVES EXCEPT THE CONTROLLING UNIT WILL BE SHUT DOWN,OR ISOLATED. UPON ARRIVAL AT A LOCOMOTIVE SERVICING TRACK WHERE MECHANICAL DEPARTMENT PERSONNEL CANNOT TAKE IMMEDIATE CHARGE OF THE LOCOMOTIVES, ALL LOCOMOTIVES WILL BE SHUT DOWN, OR ISOLATED AND PROPERLY SECURED.
Key ABTH Rule 5401 changes September 2004 (continue d) 3.C.a Final Solution Validation
But this is just one element of the larger rule.
While we anticipate a significant impact, this is a relatively small change and could go un-noticed.
We will need to consider the communications plan as we implement.
7171717171717171
3.C.b Intangible & Tangible Benefits
Benefits Expected:
• Reduced noise and air pollution
• 3M gallons of fuel saved from Rule adherence of lower temperature thresholdand shorter time till shutdown given historic locomotive fuel consumption
• Track impact of fuel change to percentage of shutdown with GPS Ping dataand financial expense data
Savings = 4gallons/hour x idle locomotive shutdown hours x cost per gallon
Done with the locomotive?Temperature > = 35ºNot needed > 15 minutesShut It Down! Save Fuel!
Our intangible benefits, noise and emissions reductions
are a direct result of locomotives being shutdown.
The tangible benefits are clear and easily tracked with our GPSdata and financial reports.
We can measure the number of shutdown hours we gain and multiply by the burn rate and the price of fuel.
The burn rate of interest is the gallons of fuel consumed per hour when the locomotive throttle is in idle.
7272727272727272
MODEL LOW DYN
TYPE IDLE BRAKE
GP15 87.9 75.1 61.9 48.3 35.8 24.1 13.6 5.8 3.8 N/AGP15T 79.6 69.1 52.9 41.8 31.4 23.1 12.5 6.4 1.9 6.4MP15 87.9 75.1 61.9 48.3 35.8 24.1 13.6 5.8 3.8 3
MP15AC 87.9 75.1 61.9 48.3 35.8 24.1 13.6 5.8 3.8 3MP15T 79.6 69.1 52.9 41.8 31.4 23.1 12.5 6.4 1.9 6.4SD38 122 102 83 63 46 31 16 7 5 15
SD38-2 122 102 83 63 46 31 16 7 5 15SD40 167 145 108 79 57 41 24 7 5.5 21
SD40-2 167 145 108 79 57 41 24 7 5.5 21SD45-2 194 171 127 91 67 47 28 9 6 25SW1500 93 75 59 45 33 23 14 6 3.5 15B30-7 149 122 96 72 49 31 17 9 5 26
GP38-2 122 102 83 63 46 31 16 7 5 15GP39 128.8 107.5 78.5 59.3 44.8 32.2 19 6 4 16
GP39-2 128.8 107.5 78.5 59.3 44.8 32.2 19 6 4 16GP40 167 145 108 79 57 41 24 7 5.5 21
GP40-2 167 145 108 79 57 41 24 7 5.5 21B36-7 189 157.3 125.7 97.3 68.9 45.4 20.7 10.1 3.6 12.4B40-8 193 162 129.5 99.8 72 47.3 22.7 16.1 3.4 3.9SD50 178.2 162.5 125.7 96.2 79.3 51.9 23.9 15.1 2.9 4.3
4 3 2 18 7 6 5
Gallons of Fuel Consumed per Hour / Throttle Positi on
Fuel Burn Rate Table by Locomotive Class
Some differences among Locomotive types – fleet weighted average is 4 gal/hr in idle
3.C.b Intangible & Tangible Benefits
Not all locomotives have the same burn rate.
Our fleet weighted average was 4 gal/hr
The data indicated that model type was not a factor in shutdown performance so we used the fleet average fuel consumption rate to simplify tracking of benefits.
7373737373737373
3.C.c Solution Justification
Fuel Price:
2003 ~ $0.9562004 ~ $1.0952005 ~ $1.3132006 ~ $2.036
Gal Used:
591,400604,390595,491603,740
KGTM:
445,206459,144463,665473,642
Fuel Efficiency:
1.331.321.281.27
Benefits Tracked Monthly / Quarterly / Annually(snapshot of annual plan)
SLT – expecting results converted to dollars saved
Finance / Purchasing – tracks results and adjusts budgets
Transportation – individual goals tied to fuel efficiency
Locomotive – individual goals tied to fuel efficiency
Environmental Stewardship – reduced emissions
We would track improvements in the shutdown performance measure to validate savings and gage location performance.
At the same time we would ensure these benefits were linked to and fell through to the bottom line by tracking overall fuel efficiency.
7474747474747474
Opportunity Costs Opportunity Savings� Risk of service failure- Low based on data� Cost of educationand compliance- Low ; change in existingSOP (rule)
� $3M per year- High chance for successchange in existing SOP� Environmental Stewardship- High chance for success:Shutdowns reduce noise and emissions
3.C.c Solution Justification
Team Developed Cost / Benefit Analysisfor Senior Leadership Team
Presentation delivered to SLT:SLT approves proposed solutions - “savings” outweighs “costs”
Team prepared a presentation to the SLT providing a risk / benefit analysis.
With risk low and opportunities great,
SLT said go!!!!
7575757575757575
Manual ShutdownConfirm rule/procedure
Get management & laborcommitment
Inform and track
Yard location maps(Concentration
diagrams)
Performancerecognition
Targeting specific
terminals
Specific terminal reports
Daily performanceBy location
Daily detail performance
Bi-Weekly graphs
4.A Implementation Buy-in
Team Recognized Need for Culture Shift and Developed Strategy to Impact
We had solid stakeholder support of the team recommendations – implementation success would require buy-in from our 6,000 plus operators;
we needed a solid communication plan to drive a cultural shift to support appropriate shutdown.
7676767676767676
4.A.a Stakeholder Involvement
Stakeholders:
SLT / Champion
TransportationManagement
LocomotiveManagement
Finance / Purchasing
Six SigmaBlack Belt
Involvement:
Support culturechange
Drive ruleCompliance
Monitor & correctlocomotive health(starting issues)
Provide financial expectations &guidance
Establishperformancemetrics
Solutions:
Establish Performance Managementgoals for managersSchedule metric reviewsEducation of workforce
Operational testing (rules compliance)Communications: educate & coach
Mechanical Help Desk 24/7 tracking & reacting to engine startup issues
Monthly budget report
Measure culture shiftControl charts: GPS & rule complianceAssist with education of workforce
Implementation Support
Again the team looked at where support was needed, who could influence, and how they could drive a culture change.
7777777777777777
4.A.b Addressing Resistance
Identified Resistance and Team ResponseTeam Brainstorming Exercise – Major Issue:
Transportation Resistance:“I don’t want to shut down the locomotive if there is a possibility of restartdelay leading to production loss and/or missed on time origination”.
Team Response: • Mechanical desk to monitor and react to locomotive restart failures• Measure shut down compliance at all locations • Hold area managers accountable through performance evaluation
and bonus opportunity
Transportation team members were concerned if engines did not restart after shutdown train performance would be impacted.
Particularly - on-time originations.
The mechanical team members agreed to aggressively addressed re-start issues, and did so.
We established a go-team for fixes and enlisted support of field managers.
7878787878787878
Year over Year Shutdown performance for the System - all pinpoint equipped units
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for the Norther n Region
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for the Albany Division
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for Buffalo, Ny
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Validated Ping Data Supports Performance OutcomesDrilldown Allows Identification of Performance by L ocation
System
Division
Region
Terminal
4.A.b Addressing Resistance4.B.c
The team developed “drill down” capabilities to allow individual managers to monitor performance.
These reports also allowed mid level managers to set goals and measure individual terminals
– cascading accountability through the organization.
7979797979797979
4.A.b Addressing Resistance4.A.c Assuring Stakeholder Buy-in
Team recognized rule change alone not adequateto cause shift in locomotive shutdown percentages
Educational campaign developed and implemented
Target Audience:
Transportation and mechanical officers
Transportation contract &non-contract employees
Locomotive contract &non-contract employeesengineer
Mechanical trouble desk
How:
Staff meeting presentations
Pay stub message
Automated voice response
Intranet dedicatedemail address
Local performancemetrics via emails
Employee bulletins
Engineer reading files
When (revised):
Quarterly
Quarterly
Quarterly
As needed
Bi-weekly
Monthly
As needed
The team had knew that rule changes, if not supported by educational efforts, did not always have the intended impact.
So we developed and delivered a comprehensive communications and education campaign to increase awareness of the rule changes .
8080808080808080
Work Orders
Identified Manual Shutdown Improvement ApproachIdentified Manual Shutdown Improvement ApproachIdentified Manual Shutdown Improvement ApproachIdentified Manual Shutdown Improvement Approach
• Improvement efforts focus on reminding and increasing compliance to fuel conservation rule
• Shutdown communication campaign
- E-mail address FuelConservation @ CSX.com to enlist ideas
- Reminders and progress will be communicated in multiple ways:
Inform and Involve
System notice
Crew Management interactive
Voice response system
Employee G
ateway
Payroll
earni
ngs s
tatem
ent sc
reen
Pay check stub
Engineer’s reading file
This week @ CSX
You can help by making fuel conservation part of: • daily job briefings • safety observations• efficiency tests • staff meetings• other contacts with operating personnel
(crews, yardmasters, mechanical etc.)Help motivate your employees to shutdown idle locomotives !
4.A.b Addressing Resistance4.A.c Assuring Stakeholder Buy-in
While the rule changes were communicated through traditional means – bulletins and employee reading files
The broader communications campaign was designed with multiple delivery mechanisms to increase awareness.
Everything from pay stubs, our corporate web site, our crew management interactive voice response system, daily job briefings, employees’ earnings statements and the crews daily work orders contained reminders of the rule change and of the need for fuel conservation.
Multiple messages delivered multiple ways!
8181818181818181
4.A.c Assuring Stakeholder Buy-in
Gain Buy-in for Locomotive Shutdown – Why?
Target audience are employees whophysically performs locomotive shutdownand those whodirectly supervise them
DAILY MESSAGEII NNFFOORRMM && II NNVVOOLL VVEE It Starts with the CustomerPeople Make the DifferenceSafety is a Way of LifeFact BasedRight Results, Right Way
Core Values
CSX Fuel Conservation
When the locomotive is not being used, it is not important to stop the diesel engine from unnecessary idling. FALSE
IF CSXT employees stopped the diesel engine on each of our
3,600 locomotives from unnecessary idling for:
1 hour per day X 4 gallons per hour X 3,600 locomotives =
CSXT savings of 14,400 gallons
of fuel/day or $16,704.00 per day
This could be a newGE ES44DC locomotive
every 100 days!
CSXT must consume diesel fuel to provide service to our customers.Your job is to use it wisely. Practice fuel conser vation at all times.
The communications plan targeted the employees who are responsible for locomotive shutdown, the locomotive engineers and locomotive shop and service track employees
8282828282828282
4.B Implement Solutions / Ensure Results
Plans to Achieve:
• System rollout of rule change
• Shops identified for 28º shutdown opportunities
• Educate workforce including supervisors
• Supervisor expectations formalized in performance management
• Financial savings realized in budget preparations and monthly reviews
• MBB / BB prepare actionable list to first line supervision
The team engaged different approaches based on different change requirements to ensure success.
A system wide approach for the rule changes and employee education with local reinforcement, measurement and emphasis on rule compliance.
8383838383838383
4.B.a Implementation Plan
Team Strategy for Implementation
Team:
SLT and Champion
Locomotive Mgt and shop employees
Transportation MgtAnd T&E employees
Finance / Purchasing
Six Sigma support
Action:
Empower rule change
Ongoing education /coachingSpecific shops, specific rules
Ongoing education /Coaching across CSX
Track savings & fuelreductions built into budgets
Develop metrics for accountability by location
Impact:
Set system expectations / targetsAccountability model
Rule compliance (35º shutdown)additional opportunity @ 28ºfor select shop locations
Rule compliance (35º shutdown)
Measurable result
Shutdown shift measurableby location and performance
The team recognized each stakeholder could contribute in the implementation.
The SLT would agree to rule changes and set clear expectations.
Locomotive management and shops would support improvements and educate their locations on a 28 degree threshold at 14 select shop locations.
Transportation management and T&E employees would support system wide rule compliance for shutdown at 35 degrees
Finance would ensure that the savings were captured.
And Six Sigma support would measure the shift, terminal by terminal.
8484848484848484
4.B.b Implementation / Deployment
Gain Buy-in for Locomotive Shutdown
Gain employee involvement:
Rule enforcement &education through multipleoutlets
Target audience:
Employees – successor failure point
Managers – significance ofInvolvement reinforced
Through Continuing Education
While the rule change is permanent,
the team understood the need for continuing education to ensure the message was clear,
“shut them down”.
8585858585858585
HELP CONSERVE FUEL
28º OR HIGHER SHUTLOCO’S DOWN
27º OR LOWERLET LOCO’S RUN
Unique Reminder at Shop / Service Locations
4.B.b Implementation / Deployment
Large obvious indicators were built at locomotive shops to reinforce when to shutdown and when to leave the locomotive running.
This eliminated performance variation that resulting from workers making individual judgment calls on temperature.
8686868686868686
4.B.b Implementation / Deployment
Gain Buy-in for Locomotive Shutdown
Corporate-widecommunicationsof Annual FuelConservationkickoff!
DAILY MESSAGEII NNFFOORRMM && II NNVVOOLL VVEE It Starts with the CustomerPeople Make the DifferenceSafety is a Way of LifeFact BasedRight Results, Right Way
Core Values
CSX Fuel Conservation
When the locomotive is not being used, it is not important to stop the diesel engine from unnecessary idling. FALSE
IF CSXT employees stopped the diesel engine on each of our
3,600 locomotives from unnecessary idling for:
1 hour per day X 4 gallons per hour X 3,600 locomotives =
CSXT savings of 14,400 gallons
of fuel/day or $16,704.00 per day
This could be a newGE ES44DC locomotive
every 100 days!
CSXT must consume diesel fuel to provide service to our customers.Your job is to use it wisely. Practice fuel conser vation at all times.
II NNFFOORRMM && II NNVVOOLL VVEE DAILY
Right Results, Right Way
CSX Fuel Conservation
When the locomotive is notbeing used, it is notimportant to stop the dieselengine from unnecessaryidling. FALSE
IF CSXT employees stopped the diesel engine on each of
our 3,800 locomotives from unnecessary idling for:
1 hour per day X 4 gallons per hour X 3,800 locomotives =
CSXT savings of15,200 gallons of fuel/day
or $31,160.00 per day
This could be a new GE ES44DC locomotive every
100 days!
CSXT must consume diesel fuel to provide
service to our customers.
Your job is to use it wisely.
PracticePracticePracticePractice
fuel conservationfuel conservationfuel conservationfuel conservation
at all times.at all times.at all times.at all times.
DAILY MESSAGEII NNFFOORRMM && II NNVVOOLL VVEE It Starts with the CustomerPeople Make the DifferenceSafety is a Way of LifeFact BasedRight Results, Right Way
Core Values
CSX Fuel Conservation
Fuel Waste to Go Under the GunRecord-setting 2005 fuel prices are hitting pocketbooks at home and on the job. That’s why wasted fuel through idling locomotives will be the target of a CSX fuel conservation initiative that kicks off April 1.
CSX’s fuel conservation policies are outlined clearly in the Air Brake And Train Handling (ABTH) rule book. The biggest source of waste: idling locomotives. In 2004 idling locomotives used 30 million gallons of fuel.
operate a EMD SD-40-2 class locomotive at full throttle for 20.7 years or
operate a GE CW44AC class locomotive at full throttle for 16.4 years or
operate a GE CW60AC class locomotive at full throttle for 12.3 years or
purchase 20 new GE ES44 DC locomotives
A Process Improvement Team will be working with field
employees to help reinforce our fuel conservation policies, and to
monitor locomotive shutdown performance using Event
Recorder downloads, GPS data and Efficiency testing.
CSX is calling upon employees to act aggressively.
Take the opportunity to refresh your understanding of ABTH Rule 5401-A revised and published as item 8-2 in System Bulletin 001, effective 0001 hours January 1, 2005.
Totaled up for 2003, the gallons going up in smoke had the potential to:
CSX is looking for your help to reduce that waste.
Apply fuel conservation
principles at every opportunity during
2005.
Top story from theCSX Employee Gateway
Again multiple education venues were used.
Communications was targeted to hit where and when it would have the greatest impact.
As weather warmed, fuel conservation reminders increased.
8787878787878787
LOCOMOTIVE SHUTDOWN PERFORMANCE YESTERDAY - 11/15/06
ONGOING NOT NOT
NEW NOT NOT NOT MOVING MOVING
MOVING MOVING MOVING TIME - TIME - % SHUT
REGN DIVN EVENTS EVENTS TIME RUNNING SHUTDOWN DOWN
---- ---- ------- ------- ------ ------- -------- ------
NORTHERN ALBANY 338 77 1813.2 932.3 880.9 48.58
BALTIMORE 416 88 2459.5 588.8 1870.7 76.06
CHICAGO 353 87 2101.1 1233.6 867.5 41.29
GREAT LAKES 275 60 1495.9 660.1 835.8 55.87
LOUISVILLE 202 38 886.5 381.7 504.8 56.94
*TOTAL NORTHERN 1584 350 8756.1 3796.5 4959.7 56.64
Daily Scorecard of Previous 24 HoursPercent Shutdown Report
4.B.c Measuring & Sustaining Results
Daily score cards for each location and division were and continue to be issued
to provide responsible field officers with current, relevant actionable data.
8888888888888888
Rolling 12 Month Average of Shutdown
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
2004
01
2004
08
2004
15
2004
22
2004
29
2004
36
2004
43
2004
50
2005
04
2005
11
2005
18
2005
25
2005
32
2005
39
2005
46
2006
01
2006
08
2006
15
2006
22
Manual Shutdown
New Fuel ConservationRule 5401 effective 9/04
Positive Shift in Percentage of Shutdown FollowingABTH Rule Change & Education Campaign
Continuing Education
4.B.c Measuring & Sustaining Results
Impact was tracked using a rolling 12 month shutdown performance.
This graphical perspective eliminated the seasonality impact and made it easier to share the success with the broader workforce,
It became clear improvements were being attained.
Each 1% change in shutdown performance generates over a half of a million gallons of fuel annually
- equating to over a million dollars in savings for each percent.
8989898989898989
Tracking Fuel Dollars / Monthly Budget Report-out
Values inMillions
DataScenario Initiative 1 2 3 4 5
Actual Savings ALL OTH FUEL EFFICIENCY 1.6$ (1.2)$ 1.0$ 1.5$ (0.2)$ SHUTDOWN 0.3$ 0.4$ 0.8$ 0.3$ 0.4$ ERAD 0.4$ 0.4$ 0.9$ 0.5$ 0.6$ FLANGE LUBE 0.5$ 0.5$ 0.7$ 0.3$ 0.3$ NEW UNITS 0.3$ 0.3$ 0.4$ 0.4$ 0.5$
Actual Savings Total 3.0$ 0.5$ 3.8$ 2.9$ 1.6$ PLAN SAVINGS ALL OTH FUEL EFFICIENCY -$ -$ -$ -$ -$
SHUTDOWN 0.3$ 0.3$ 0.5$ 0.0$ 0.0$ ERAD -$ -$ -$ 0.2$ 0.2$ FLANGE LUBE 0.5$ 0.5$ 0.7$ 0.3$ 0.3$ NEW UNITS 0.3$ 0.3$ 0.4$ 0.4$ 0.5$
PLAN SAVINGS Total 1.1$ 1.2$ 1.6$ 0.9$ 1.0$ VARIANCE TO PLANNED SAVINGS ALL OTH FUEL EFFICIENCY 1.6$ (1.2)$ 1.0$ 1.5$ (0.2)$
SHUTDOWN (0.0)$ 0.0$ 0.3$ 0.3$ 0.3$ ERAD 0.4$ 0.4$ 0.9$ 0.3$ 0.4$ FLANGE LUBE -$ -$ -$ -$ -$ NEW UNITS -$ -$ -$ -$ -$
4.B.c Measuring & Sustaining Results
The success in fuel expense reduction was institutionalized through the monthly budget process.
With annual year over year targets included in the following year’s productivity plan and budget.
9090909090909090
Year over Year Shutdown performance for the System - all pinpoint equipped units
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for the Norther n Region
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for the Albany Division
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Year over Year Shutdown performance for Buffalo, Ny
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01 04 07 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
2004 2003
Validated Ping Data Supports Performance OutcomesDrilldown Allows Identification of Performance by L ocation
System
Division
Region
Terminal
4.B.c Measure/Sustain results
A drilldown, by location, measuring performance over time is sent weekly to our operating officers and these measurements are used for annual employee performance evaluations.
9191919191919191
4.C Results Achieved
Team:
SLT and Champion
Locomotive Mgt and shop employees
Transportation MgtAnd T&E employees
Finance / Purchasing
Environment / Community
Effort:
Set and drive expectationsAssumption of locomotive damage risk with rule change
Shutdown enforced to 28º
Educate / coach 8,000 T&E employees
Track history & savingsassociated with project
Collect community complaintsContribute to general welfare& support governmentemissions standards
Results:
$3.6M in benefits 2004No significant freezedamage to locomotiveReplicated project model
Additional savings atspecific shop locations
Manager meets formalincentive goals Train originations notnegatively impacted
Track & document savingsImproved plan for following years
Corporate citizenship& recognition
Manual Locomotive Shutdown Project Impacts
The project has had significant results felt throughout the organization.
The SLT was key in supporting the project, shouldering the risk, sharing and celebrating project success.
They have placed an ever increasing number of productivity efforts into the same accountability model used by this project.
Operations management, both mechanical and transportation have seen the improvements in their shutdown performance numbers without any collateral damage.
Our workforce has taken pride in improved fuel efficiency at a time when fuel costs were escalating.
And CSX was the first class 1 railroad in the United States to join the EPA’s Greenhouse Gas Initiative.
9292929292929292
4.C.a Tangible / Intangible Results
Savings From Project: Annual Plan and Actual with C umulative Total
Year over Year improvement Cumulative Plan Actual Project benefits
2004 $2.5M $3.6M $ 3.6M 2005 $4.0M $7.2M $14.4M2006 $1.5M $3.4M $28.8M
14.4M Gallons and $28.8M saved over 3 years
Tangible – Fuel Savings:
Intangible – Blue Skies & Happy Neighbors:
Tangible savings exceeded expectations with more than 14M gallons and over $28M dollars in cumulative savings over the three year span of the project!
Intangible savings included – better stewardship of our natural resources by reducing emissions and noise that has led to happy neighbors and recognition of our achievements.
9393939393939393
March 2 Press release - CSXT Joins Call for Cleaner Air
At the invitation of the U.S. Environmental Protection Agency, CSX Transportation (CSXT) today joined EPA Administrator Stephen Johnson and other stakeholders at Port Newark, N.J., to support the agency's overall goal of reducing diesel locomotive emissions. CSXT's Chief Operating Officer Tony Ingram spoke as part of the U.S. Environmental Protection Agency announcement to support reduction of diesel locomotive emissions.
Shown in the photo with EPA Administrator Stephen Johnson (at left) and other stakeholders (at right).
CSXT is the first class 1 railroad in the United States to join the EPA’s Greenhouse Gas Initiative.
4.C.a Tangible / Intangible Results
External Stakeholder Buy-in and Benefits
One indication of the intangible results, is that the US EPA invited one railroad (CSX) to host their public announcement on diesel locomotive emission reduction efforts.
Intangible results, but clearly in support of the CSX vision.
9494949494949494
4.C.b Project Linked to Goals
CSXT Vision:To be the safest, most progressive North American railroad,
relentless in the pursuit of customer and employee excellence.Employee excellence drove project success through
continued education and rule compliance
Purpose:To capitalize on the efficiency of rail transportation to serve America.
Saved 14.4 M Gallons of Diesel Fuel
Corporate Goals and Values
Starts Withthe Customer
Successful Project
People Makethe Difference
Safety is a Way of Life Fact Based
Right ResultsRight Way
(Team)(Extensive internal customerParticipation- no externalCustomer impact)
(Accurate Data)
(Engaged Employees)
(Rule Compliance)
Core Values:
As we reviewed earlier the team used our corporate goals, vision, and values to guide our success.
9595959595959595
Company Goals, Strategies, ObjectivesProject Impact How this project affects the objective
Company Vision: To be the safest, most progressive North American railroad, relentless in the pursuit of customer and employee excellence.
Inovative approach to measuring performance of a traditionally un-measured activity. Continuous improvement approach.
Company Purpose:To capitalize on the efficiency of rail transportation to serve America.
Increased efficiency by lowering fuel consumption and expense
Company Values:
It starts with the customer.Needs and behavior of internal customers will drive the success of the project
People make the difference.Requires engagement of broad team and locomotive user community
Safety is a way of life. Customer and data drivenFact based. Use of 6 Sigma tools
Right results, right way.Positive impact on the comunities we serve and the environment
Key Performance measuresOperating Ratio Lowering fuel consumption will reduce expense
On time departuresWill track starting issues to ensure train originations are not impacted
% of time Locomotives Out of ServiceReduced engine run times will lesson wear on locomotive components
Locomotive Fuel productivity (Gallons/KGTM) Reduced fuel consumption will reduce gallons/KGTMRight Car Right Train (RCRT) No impact on RCRTTrain Veleocity No impact on system train velocity Crew Availability Does not impact crew availablity
KEY: Positive impactPotential negative impact
White No impact
4.C.b Results Shared
Corporate Metrics – Post Implementation
The team tracked key performance measures to ensure there was no impact to railroad operations.
If you recall we had a yellow in our initial matrix in on time departures.
Careful attention to the restart issue eliminated this concern.
9696969696969696
4.C.c Results Shared
Share Victory With Stakeholders
Stakeholders:
SLT and Champion
Locomotive Mgt and shop employees
Transportation Mgtand T&E employees
Finance / Purchasing
Environment / Community
Project Results:
Fuel savingsEPA credits
Financial results
Financial results
Fuel savings info
Less emissionsLess noise
How:
Financial results Annual budget
Performance bonusRegular communications
Performance bonusRegular communications
Greater savingsthan expected
Governmentrecognition
StakeholderFeedback:
Corporate success
Spot awardsto team membersMet or exceededbonus target
Spot awardsto team membersMet or exceededbonus target
Budget room
Good stewardship
The team recognized that sharing success would reinforce future desired behavior as much as it rewards past behavior.
So...
9797979797979797
4.C. c. Results Achieved Communicated
Manual Locomotive Shutdown Results Communication Pl an
MediaMessage Stakeholders Who When / Where
Impact of shutdownin Fuel Savings
Locomotive Engrs(T&E)
Letters to Home Addresses
Sr. Road Foreman Annual Results
Location Impactof shutdownSavings
Locomotive Engrs(T&E) Management
Cash Award in Person Sr. LeadershipAfter Success atLocation
Fuelconsumption
Finance/Budgets Financial Reporting Purchasing Monthly
Success of Project
Senior LeadershipChampions
Presentation TeamQuarterly Checkpoints
Improved SDPerformance;Less Noise; Emissions
Communities(individuals)
Telephone Call T&E Manager When Received
Success/ImpactOf Project
EnvironmentGovernment
MeetingsSenior OperatingStaff
As opportunity presents
The team developed and implemented a comprehensive communication plan
to ensure our Stakeholders understood our success and our appreciation
Including;
Letters to individual engineers
Spot or Cash awards to line managers
Promotion opportunities for team members
Setting up a toll free number, “877 Tell CSX” to better address community concerns
9898989898989898
4.C.c Results Shared
Results Communicated / Employees Commended
In addition to the many internal communications we looked at earlier; appreciation letters were sent to over 5,000 locomotiveoperators homes.
9999999999999999
4.C.c Results Shared
Results Communicated / Employees Commended
2006 Spot award winners were selected from the most improved Divisions versus same period 2005
And cash spot awards were granted to the Managers that led their division to success with locomotive shutdown
In addition, four original team members progressed to assignments of greater responsibility within the company.
100100100100100100100100
This Week's Message:
Hello, this is Michael Ward.
Today I'd like to talk to you about an important public policy issue facing our country - carbon dioxide or CO2 - and how decisions likely to be made in Washington around this issue could affect CSX and our nation's economy.
Many of you have heard about global warming and the theory that man-made production of CO2 may be contributing to global climate change. In Washington, our political leaders are starting to discuss legislative changes to limit CO2 production in the United States.
Before we talk about the impact of these possible changes to CSX, first it's important to understand that CO2 is not a pollutant as we usually think about pollution. As I'm sure we all learned in science classes early in school, humans and animals breathe in oxygen and breathe out CO2, then plants take in CO2 and release oxygen. It's a very natural process. The issue arises because CO2 also absorbs warmth from the sun.
At CSX, we think it would be better to put increased emphasis onimproved fuel efficiency in all modes of transportation. Since railroads are 3-4 times more fuel efficient than trucks, and produce as little as a fourth of the CO2 to move the same amount of freight, CSX has a good news story to tell here.
Our country is going to have to make some important decisions in the near future about CO2. Many of our elected officials are rightfully concerned that any rush to judgment on regulation of CO2 emissions could adversely affect our economy and our quality of life. Still, the decisions that have to be made are difficult and there is no guarantee that mistakes won't be made in the political process. I will be watching what happens closely and will keep you informed in the months ahead about this important debate.
Thanks for listening, have a safe productive day, and I'll talk to you again next week.
Results Communicated / Chief Executive Officer supports in weekly phone message:
4.C.c Results Shared
Recently, our CEO communicated the impact CSX has on the environment and the air we breath
in his weekly phone broadcast
101101101101101101101101
5.A Team Selection / Involvement
Team Selection & Involvement Criteria
Team Selected by SLT / Champion:• Who can impact project• Who has required training• Who has insight needed• How much depth is needed
PIT+ Structure Incorporating Six Sigma Methodology:• Accountability (PIT+)• Project rigor (Six Sigma)• Project management (Six Sigma)• 20% of team make up are Black Belts and
one Master Black Belt• All team members are SME’s
The team was selected by the SLT & Champion with Project leader input.
The criteria was designed to select team members that could impact results, would provide diverse insights, or managed areas that would be effected by process change.
The project was to be completed with structured accountability.
102102102102102102102102
5.A Team Selection / Involvement
Task Owner Due Contact Phone What Obstacle Status Completed
New hire / recurrent engr training program Seguin 1-Dec
M. Chapman
426-6234
new hire & recurrent training
photos / dialogue
Pilot / REDI 17-Nov
System RFE meeting Seguin 14-Oct
D. Menefee 7541
review APU procedures, feedback from RFE 14-Oct
This week @ CSX & Employee Gateway Seguin K. Okie 1509
set up / shutdown 21-Oct
Instructions for APU / EST to engineers reading file Seguin 7-Oct
D. Menefee 7541
new operational instructions to reading file 1-Oct
Senior RFE to sample their engrs Seguin 21-Oct
D. Menefee 7541
solicit feedback from engrs 31-Oct
This week @ CSX & Employee Gateway Seguin K. Okie 1509
Yr round fuel consr / APU vs Manual S/D 25-Nov
Q&A for supervisors Seguin
M. Chapman / D. Menefee
426-6234 / 7541
3 -5 questions that handout (card) should answer
Sr. RFE do not report to Dean 10-Dec
Mech Desk APU Training Seguin
week of 11/14 M. Drylie 3631
What should be reported
Mech Desk accountability 21-Dec
Mech Desk APU Training - Survey Seguin B. McCall
388 2125
Training effectiveness 10-Jan
Fuel Conservation
Weekly Team Work Assignments
The accountability model required documentation of who is responsible for what by when.
This included monthly feedback from the team to the member owning departments with meeting attendance
records and minutes detailing assignments.
Early team meetings included a template of current activities and timelines as part of the agenda.
103103103103103103103103
Six Sigma Drives Fuel conservation InitiativeSix Sigma Drives Fuel conservation InitiativeSix Sigma Drives Fuel conservation InitiativeSix Sigma Drives Fuel conservation Initiative
Control
Improve
Analyze
Measure
Define•Determined project purpose (VOC & VOB)•Identified stakeholders / resistance•Planned for project communication•Completed phase deliverables
•Identified project key X's and Y's•Validated and collected data•Determined improvement goal•Completed phase deliverables
•Determined X's significant to CTQ's•Completed phase deliverables
•Identified and tested solution/improvement•Gained business case approval•Completed phase deliverables
•Established control plan•Completed handoff to Sponsor•Closed and leveraged project
5.B Team Preparation for Work
Our touchstone for project management was the use of the six sigma DMAIC process.
104104104104104104104104
Fuel Conservation Team Trained in DMAIC & Six Sigma (6σ) σ) σ) σ) Techniques
• Applied 6σ methodology of one day overview training for team- Data driven decision making – team included one MBB and 2 BB’s- Additional training at each phase as project milestones reached
Project phases:
Define Measure Analyze Improve Control
•What is theproblem?•What are the project goalsand scope?•Have all key players been identified and engaged?
•What is the currentprocess?•How welldoes that process meet customerexpectations?
•What are specific rootcauses?•Where willimprovement efforts befocused?
•What actionswill driveperformance?•Who willimplement? •When willthey be completed?•Is therebuy-in?
•Has controlplan beendocumentedand implemented?•Are stakeholderexpectations being met?
5.B Team Preparation for Work
All team members received at least one day of Six sigma overview training and additional training with specific tool use, FMEA,
C&E matrix, process mapping, etc.
In addition 20% of the team are six sigma black belt or master black belt certified.
105105105105105105105105
5.C Team Effectiveness
Weekly Team Meetings:
• Meetings scheduled with agenda• Meeting minutes sent in timely fashion• An accountability or “to do” list of assignments• “To do” list updated as necessary
Monthly Champion Reviews:
• Go – no/go• Maintenance of applied resources• Feedback to “Owning Departments”
Quarterly Senior Leadership Reviews (SLT) Reviews:
• Maintained alignment with corporate vision, purpose, and values
Team Effectiveness Continues
The timelines for meetings, expectations for attendance and contribution, were established at the project onset.
Monthly report outs were established, with feedback to each team members owning departments and quarterly reviews by the SLT
During this process several key members were identified for performance and rewarded with spot awards
This has been a terrific project
The individuals on the team increased their familiarity and understanding of process improvement tools,
106106106106106106106106
our workforce developed more disciplined behavior,
107107107107107107107107
we reduced noise and emissions becoming better corporate neighbors,
recognized by government agencies,
108108108108108108108108
Doing our part to conserve fuel – 650K barrels to date
CSX saved $28M over the 3 year life of the project,
And, at 42 gallons per barrel, we have saved over 650,000 barrels of a scarce non-renewable resource.
Thank you for the opportunity to share our project with you.
109109109109109109109109
There is no End in Sight for Fuel Conservation Opportunities!
Thank You!