FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Locational Based Marginal PricingGina CraanManager, Market Training, NYISO
Market Overview CourseMarch 8, 2018Rensselaer, NY 12144
1
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Locational Based Marginal Pricing Attendees will be able to
• Explain the Basics Behind LBMP• Complete Simple LBMP Examples• Identify the Impacts of Congestion
2
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
LBMP – The Basics
LBMP is
Cost to provide the Next MW of Load at a Specific Location in the grid
3
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
LBMP – The Basics LBMP is established for the Day Ahead Market and the Real Time
Market• Day Ahead Market
• Security Constrained Unit Commitment (SCUC)• Hourly Prices
• Real Time Market• Real Time Dispatch (RTD)• 5 Minute Interval Prices
4
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
CO-OPTIMIZATION FOR LOWEST TOTAL
PRODUCTION COST$
LBMP: Co-Optimized Based on Bids and Offers
NYISO ForecastLoad BidsGenerator OffersTransactionsAncillary ServicesVirtualsDemand ResponseConstraints
INPUT-BIDS AND OFFERS OUTPUT-
SCHEDULES
PRICES
NYISOSCUC/RTD
55
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
LBMP – The Basics LBMP is made up of three components:
• Marginal Energy Price • Basic Component of LBMP, calculated at Marcy
• Marginal Loss Price• Captures Losses along path to Load
– Transmission Losses
• Marginal Congestion Price• Costlier units Dispatched to avoid exceeding Transmission Limits
6
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
LBMP-Three Components, An Analogy
7
Delivery
Associated Cost $ AmountCapital –Zone F
$ AmountNYC – Zone J
Similar to
Base price to make Billboard(cost to manufacture sign)
$40 $40 Energy Price Component(cost to produce power)
Shipping and Handling(cost to deliver the billboard)
$1 $1 Loss Price Component(cost to get energy to
destination)
Potential for added cost(cost to purchase/rent a location)
$40 $100 Congestion Price Component(cost to ensure load need is
met)
Total Cost for Product $81 $141 LBMP
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Generators – Gen Bus LBMP LBMP for Generators
• Based on Generator Bus• LBMP calculated at Bus where Generator injects power
8
Gen Bus
NYSTransmission
System
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Load Serving Entity – Zonal LBMP LBMP for Load
• Based on Zone where Load is Located• One Zonal LBMP for entire Zone• Load Weighted Average IESO
Zone O
HQZone M
ISO-NEZone N
PJMZone P
NYCA Load ZonesA- West E- Mohawk Valley I- DunwoodieB- Genesee F- Capital J- NYCC- Central G- Hudson Valley K- Long IslandD- North H- Millwood
9
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Example 1: Energy OnlyNo Losses and No Congestion
Total Load = 150 MW10
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’100 MW, Bid @$20/MW
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
Gen ‘Full Steam’ 150 MW, Bid @$35/MW
Gen ‘Energy’ 100 MW, Bid @$30MW
Gen ‘Lights On’ 200 MW, Bid @$40/MW
Total Load150 MW
Limit150 MW
Example 1: Energy Only
11
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’100 MW, Bid @$20/MW
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
Gen ‘Full Steam’ 150 MW, Bid @$35/MW
Gen ‘Energy’ 100 MW, Bid @$30MW
Gen ‘Lights On’ 200 MW, Bid @$40/MW
Total Load150 MW
Limit150 MW
Example 1: Energy Only
100 MW
12
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’100 MW, Bid @$20/MW
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
Gen ‘Full Steam’ 150 MW, Bid @$35/MW
Gen ‘Energy’ 100 MW, Bid @$30MW
Gen ‘Lights On’ 200 MW, Bid @$40/MW
Total Load150 MW
Limit150 MW
Example 1: Energy Only
100 MW
50 MW
13
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’100 MW, Bid @$20/MW
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
Gen ‘Full Steam’ 150 MW, Bid @$35/MW
Gen ‘Energy’ 100 MW, Bid @$30MW
Gen ‘Lights On’ 200 MW, Bid @$40/MW
Total Load150 MW
Limit150 MW
Example 1: Energy Only
100 MW
50 MW
30 MW
70 MW
14
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’100 MW, Bid @$20/MW
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
Gen ‘Full Steam’ 150 MW, Bid @$35/MW
Gen ‘Energy’ 100 MW, Bid @$30MW
Gen ‘Lights On’ 200 MW, Bid @$40/MW
Total Load150 MW
Limit150 MW
Example 1: Energy Only - Results
West Zone LBMP $30.00 East Zone LBMP $30.0015
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’ ,100 MW Bid $20, Paid $20
East ZoneWest Zone
Gen ‘Full Steam’ ,150 MWBid $35, Paid $0
Gen ‘Energy’ ,100 MW Bid $30, Paid $30
Gen ‘Lights On’, 200 MW Bid $40, Paid $0
Example 1: Energy Only - Results
Generators receive $30/MW (LBMP)16
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Example 1: Energy Only - Results
Loads Charged $30/MW (LBMP)
East ZoneLoad B
120 MW
West ZoneLoad A30 MW
17
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Congestion Congestion occurs when the Power flow reaches the Transmission Limit
At Limit Congestion
18
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Congestion To maintain efficient and reliable Transmission system
• Transmission limits cannot be exceeded• When Transmission limits reached, generators from different
buses are dispatched to meet load When there is congestion, LBMPs can differ between buses
19
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Example 2: Energy and Congestion No Losses
Total Load400 MW
20
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
21
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
100 MW
22
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
100 MW300 MW
23
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
100 MW300 MW
40 MW260 MW
24
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
100 MW190 MW
40 MW150 MW
25
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion
100 MW190 MW
40 MW150 MW
110 MW
26
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’310 MW, Bid @$30/MW
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Gen ‘Energy’ 350 MW, Bid @$40/MW
Gen ‘Lights On’ 100 MW, Bid @$25/MW
Gen ‘Full Steam’ 350 MW, Bid @$35/MW
Total Load400 MW
Limit150 MW
Example 2: Energy and Congestion- Results
West Zone LBMP =$30 East Zone LBMP =$3527
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Gen ‘Power Up’ ,310 MW Bid $30, Paid $30
East ZoneWest Zone
Gen ‘Energy’ ,350 MWBid $40, Paid $0
Gen ‘Lights On’ ,100 MW Bid $25, Paid $35
Gen ‘Full Steam’, 350 MW Bid $35, Paid $35
Example 2: Energy and Congestion - Results
Generators West of interface receive $30/MW (LBMP)Generators East of interface receive $35/MW (LBMP)
28
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Example 2: Energy and Congestion - Results
Loads in West ZoneCharged $30/MW (LBMP)
East ZoneLoad B
360 MW
West ZoneLoad A40 MW
Loads in East ZoneCharged $35/MW (LBMP)
29
© COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED. FOR TRAINING PURPOSES ONLY
Let’s ReviewLBMP is the cost to provide the:
a) Last MW of Load at a specific location in gridb) Next MW of Load at a specific location in grid
LBMP is established through:a) Economic Dispatch Processb) Random Generation Selection Process
LBMP is comprised of:a) One Single Price Componentb) Three Separate Price Components
30
© COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED. FOR TRAINING PURPOSES ONLY
Let’s ReviewLBMP for Load is
a) Established at each LSE’s locationb) Established at a Zonal level
LBMP for Generator isa) Established at a Zonal levelb) Established at the Generator Bus
31
FOR TRAINING PURPOSES ONLY©COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED
Tariffs - OATT & MST
Day Ahead Scheduling Manual
Transmission and Dispatching Operations Manual
Market Participant User’s Guide
Technical Bulletins
Additional Resources
** Images provided by Google Images @ https://www.google.com , February 7, 2017
32