Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 D1
APPENDIX D MITIGATION OPTIONS MAPPING
FIGURES
Figure D1: Location of Investigated Mitigation Options
Figure D2: Peak Flood Level Impact – Option B - 1% AEP Event
Figure D3: Peak Flood Level Impact – Option C - 1% AEP Event
Figure D4: Peak Flood Level Impact – Option F - 1% AEP Event
Figure D5: Peak Flood Level Impact – Options G & J – 1% AEP Event
Figure D6: Peak Flood Level Impact – Option I – 1% AEP Event
Figure D7: Peak Flood Level Impact – Options L, M & K – 1% AEP Event
Figure D8: Peak Flood Level Impact – Option N – 1% AEP Event
Figure D9: Peak Flood Level Impact – Option P – 1% AEP Event
Figure D10: Peak Flood Level Impact – Option D – 1% AEP Event
ArthurByrne
Reserve
JohnShorePark
Maroubra BayPrimary
Broadarrow Reserve
MAROUBRA
Maroubra Bay
RifleRange
F
G
I
J
K
L M
N
P
B
C D
H
A
MAROUBRA RD
ANZACPDEANZACPDE
BERN
IE KE
LLY D
R
THE CAUSEWAYNICOL AV
BYNG ST
ANZAC PDE
SCOTT ST
KYOG
LE ST
MARINEPDE
DUNC
ANST MA
LABA
RRD
TYRWHITT ST
SACKVILLE ST
WISEST
ANZA
CPD
E
BEATTY ST
MONS AVMALABAR
RD
FRENCH ST
FORD RD
WADE ST
MURRAY ST
MARINE PDE
FITZGERALD AV
ASTORIACCT
DUNCAN ST
HAIG ST
CHAPMAN AV
NEW ORLEANS CR
DUNCAN L
BROOME ST
THOMPSON AV
BENT L
MALA
BAR
RD
MONS AV
BROWNRD
MCKEON ST
RODMAN AV
LITTLE LFLOW
ER ST
FITZGERALD AV
RUSSELLCT
MORRIS PL
MARINE PDE
CHICAGO AV
BENNETT PL
FENTON AV
MAROUBRA RD
YORKTOWN PDE
CHES
TER A
V
MALABAR RD
HEREWARD ST
BEAUCHAMP RD
DAN AV
ROSSITER L
COLLIER PL
OSPREY CT
SCOTT L
COOPER L
BOND ST
BYNG L
BOUGAINVILLE CT
WHITE A
V
SEVERN ST
NEOSHO WY
DUNCAN ST
PERKINS WY
FITZG
ERAL
D L
CURT
IN C
R
ANZAC PDEBE
LLEVU
E ST
HARGRAVES PL
MARINEPDE
DEWEY CT
PETERS PL
MCIVER PL
FLOWER L
BONA
VIST
A AV
MINNEAPOLIS CR
BOYCE L
LITTL
E ST
LEXINGTON PL
GLENUGIE ST
BYRNE CR
MEAGHER AV
BEAU
MOND AV
SIMS L
SIMS GR
PORTLAND CR
ASTORIA CCT
BEATTY L
WRIDE ST
KITCHENER ST
MALA
BAR R
D
MIDWAY DR
MARINE PDE
FIGURE D1LOCATION ON INVESTIGATED
MITIGATION OPTIONS
Existing PitsExisting PipesHotspotCatchment Area
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD1_
Overv
iew_o
f_Hots
pots.
mxd
E
O
0 200 400 600100Meters
ArthurByrne
Reserve
JohnShorePark
Maroubra BayPrimary
Broadarrow Reserve
MAROUBRA
Maroubra Bay
DUNC
AN ST
MONS AV
FITZGERALD AV
BOND ST
MAROUBRA RD
FRENCH ST
MARINE
PDE
WRIDE ST
MALA
BAR
RD
YORKTOWN PDE
SACKVILLE ST
THE CORSO
KYOGLE ST
HAIG ST
FLOW
ER ST
BOYCE RD
NEW
ORLE
ANS C
R
FIRST AV
SIMS L
BROO
ME ST
MCKEON ST
LITTL
E ST
NICOL
L
SCOTT ST
SECOND AV
SIMS GR
PORT
LAND
CR
BONA V
ISTA A
V
THE C
AUSE
WAY
FENTON AV
BELL
ST
FITZG
ERAL
D L
CAMI
RA ST
ROSSITER L
BOYCE L
HEREWARD ST
BRIDGES ST
MINN
EAPO
LIS CR
BERN
IE KE
LLY D
R
CHAPMAN AV
BELLE
VUE S
T
FLOWER L
BEAU
MOND AV
GLENUGIE ST
GALVIN ST
LEXINGTON PL
SEVERN ST
NEOSHO WY
NICOL AV
LITTLE L
BENT L
COLLIER PL
MORRIS PL
SCOTT L
MAXW
ELL A
V
RUSSELL CT
MULC
RAY A
V
DUNCAN L
MAROUBRA RD
MONS AV
DUNCAN ST
0 0.250.125Km
FIGURE D2PEAK FLOOD LEVEL IMPACT
OPTION B1 % AEP EVENT
Pits/ NodesPipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD2_
100y
earIm
p_Sc
eB.m
xd
Hotspot B:Flood retarding basin in Muraborah Reserve (Wride Street)
B
ArthurByrne
Reserve
JohnShorePark
Maroubra BayPrimary
Broadarrow Reserve
MAROUBRA
Maroubra Bay
DUNC
AN ST
MONS AV
FITZGERALD AV
BOND ST
MAROUBRA RD
FRENCH ST
MARINE
PDE
WRIDE ST
MALA
BAR
RD
YORKTOWN PDE
SACKVILLE ST
THE CORSO
KYOGLE ST
HAIG ST
FLOW
ER ST
BOYCE RD
NEW
ORLE
ANS C
R
FIRST AV
SIMS L
BROO
ME ST
MCKEON ST
LITTL
E ST
NICOL
L
SCOTT ST
SECOND AV
SIMS GR
PORT
LAND
CR
BONA V
ISTA A
V
THE C
AUSE
WAY
FENTON AV
BELL
ST
FITZG
ERAL
D L
CAMI
RA ST
ROSSITER L
BOYCE L
HEREWARD ST
BRIDGES ST
MINN
EAPO
LIS CR
BERN
IE KE
LLY D
R
CHAPMAN AV
BELLE
VUE S
T
FLOWER L
BEAU
MOND AV
GLENUGIE ST
GALVIN ST
LEXINGTON PL
SEVERN ST
NEOSHO WY
NICOL AV
LITTLE L
BENT L
COLLIER PL
MORRIS PL
SCOTT L
MAXW
ELL A
V
RUSSELL CT
MULC
RAY A
V
DUNCAN L
MAROUBRA RD
MONS AV
DUNCAN ST
0 0.250.125Km
FIGURE D3PEAK FLOOD LEVEL IMPACT
OPTION C1 % AEP EVENT
Pits/ NodesPipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD3_
100y
earIm
p_Sc
eC.m
xd
Hotspot C:Flood retarding basin in John Shore Park
C
Coral SeaPark
AB
Re
JohnShorePark
Broadarrow Reserve
MAROUBRA
FITZGERALD AV
PORTLAND CR
MALABAR RD
YORKTOWN PDE
BROO
ME ST
MONS AV
NEW
ORLE
ANS C
R
MIDWAY DRMI
NNEA
POLIS
CR
KYOGLE ST
SIMS L
SCOTT ST
SIMS GR
TYRWHITT ST
CURTIN CR
CHESTER AV
CHICAGO AV
FITZG
ERAL
D L
CAMI
RA ST
ROSSITER L
BRIDGES ST
BERN
IE KE
LLY D
R
SCOTT L
DEWEY CT
GLENUGIE ST
LEXINGTON PL
MEAGHER AV
BYRNE CR
PERKINS WY
NEOSHO WY
COLLIER PL
OSPREY CT
MORRIS PL RUSSELL CT
MONS AV
CHESTER AV
0 0.250.125Km
FIGURE D4PEAK FLOOD LEVEL IMPACT
OPTION F1 % AEP EVENT
Pits/ NodesPipesOption F PitsOption F PipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD4_
100y
earIm
p_Sc
eF.m
xd
Hotspot F:Added 3 new 1.2m pipes
F
JohnShorePark
Maroubra BayPrimary
Broadarrow Reserve
MAROUBRA1.2
1.2
1.2
1.2 1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.21.2
1.2
1.2
1.2
1.2
1.2
1.2
MONS AV
DUNCAN ST
FITZGERALD AV
FRENCH ST
MARINE PDE
MAROUBRA RD
WRIDE ST
YORKTOWN PDE
KYOGLE STMA
LABA
R RD
BOND ST
HAIG ST
MCKEON STLIT
TLE S
T
FLOW
ER ST
FENTON AV
CAMI
RA ST
ROSSITER L
SIMS GR
NICOL
L
BOYCE L
HEREWARD ST
THE C
AUSE
WAY
CHAPMAN AV
BELLE
VUE S
T
FLOWER L
BONA V
ISTA A
V
NEW
ORLE
ANS C
R
FIRST AV
GLENUGIE ST
GALVIN ST
SECOND AV
SIMS L
SEVERN ST
MINN
EAPO
LIS CR
BRIDGES ST
FITZG
ERAL
D L
NICOL AV
BROO
ME ST
LITTLE L
BENT L
BELL
ST
MAXW
ELL A
V
ROSS
ITER A
V
COLLIER PL
MULC
RAY A
V
DUNCAN L
BERNIE KE
LLY DR
PORT
LAND
CRDUNCAN ST
MAROU
BRA R
D
MONS AV
0 0.250.125Km
FIGURE D5PEAK FLOOD LEVEL IMPACT
OPTION G & J1% AEP EVENT
PitsPipesOption GJ PipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD5_
100y
earIm
p_Sc
eGJ.m
xd
J
G
Hotspot GJ:Increased pipe sizes to 1.2m fromGalvin Street to Fitzgerald Avenue
Hotspot GJ:Increased number of pipes to 2 alongFitzgerald Avenue and Marine Parade
1.2
BOND ST
MARINE
PDE
MAROUBRA RD
BONA V
ISTA A
V
BEAU
MOND AV
SACKVILLE ST
SEVERN ST
HEREWARD ST
DUNCAN ST
MCKEON ST
BELLE
VUE S
T
0 0.250.125Km
FIGURE D6PEAK FLOOD LEVEL IMPACT
OPTION I1% AEP EVENT
PitsPipesOption I PipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD6_
100y
earIm
p_Sc
eI.mx
d IHotspot I:Pipe size was changed from 0.6m to 1.2m
Coral SeaPark
MAROUBRA
0.9
1.05
0.6
0.9
0.9
1.05
FITZGERALD AV
MONS AV
ANZAC PDE
YORKTOWN PDE
CHESTER AV
MINNEAPOLIS CR
MIDWAY DR
KYOGLE ST
NEW ORLEANS CR
BEATTY L
SIMS L
PORT
LAND
CR
SIMS GR
KITCHENER ST
ASTORIA CCT
BEATTY ST
WADE ST
LEXINGTON PL
PERKINS WY
NEOSHO WY
COLLIER PL
MORRIS PL
MALABAR RD
GLENUGIE ST
FRENCH ST
RUSSELL CT
CHIC
AGO
AV
DUNCAN ST
ANZAC PDE
MALABAR RD
MONS AV
0 0.250.125Km
FIGURE D7PEAK FLOOD LEVEL IMPACT
OPTION L, M & K1% AEP EVENT
PitsPipesOption LMK PitsOption LMK PipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD7_
100y
earIm
p_Sc
eLMK
.mxd L
M
K
Hotspot LMK:Added 6 new circular pipes (sizes as labelled)
WHITE
AV
BROO
ME ST
BEAUCHAMP RD
RODMAN AV
BENNETT PL
THOMPSON AV
HARGRAVES PL
0 0.250.125Km
FIGURE D8PEAK FLOOD LEVEL IMPACT
OPTION N1% AEP EVENT
PitsPipesOption N PipeHotspotOutside The Study Area
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD8_
100y
earIm
p_Sc
eN.m
xd
N
Hotspot N:Increased pipe size from 0.6m to 0.9m
ArthurByrne
Reserve
RifleRange
2
BROO
ME ST
MALABAR RD
SCOTT ST
CURTIN CR
TYRWHITT ST
MEAGHER AV
BERNIE KELLY DR
BYRN
E CR
FORD RD
DAN AV
SCOTT L
PORT
LAND
CR
RODMAN AV
RUSSELL CT
BROWN RD
PETERS PL
FITZG
ERAL
D L
MALABAR RD
0 0.250.125Km
FIGURE D9PEAK FLOOD LEVEL IMPACT
OPTION P1% AEP EVENT
PitsPipesOption P PipesHotspot
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD9_
100y
earIm
p_Sc
eP.m
xd
Hotspot P:Increased number of existing pipes to 2along Curtin Crescent Hotspot P:
Added a new pipe from ByrneCrescent to Arthur ByrneReserve
P
JohnShorePark
Broadarrow Reserve
MarB
MONS AV
MARINE PDE
MALA
BAR
RD
DUNCAN ST
FITZGERALD AV
MCKEON ST
FENTON AV
CAMI
RA ST
ROSSITER L
HEREWARD ST
BRIDGES ST
CHAPMAN AV
BROO
ME ST
FITZG
ERAL
D L
MAROUBRA RD
SEVERN ST
BERN
IE KE
LLY DR
MAXW
ELL A
V
LITTL
E ST
ROSS
ITER A
V
YORKTOWN PDE
BONA V
ISTA A
V
GLENUGIE ST
DUNCAN ST
MONS AV
0 0.20.1Km
FIGURE D10PEAK FLOOD LEVEL IMPACT
OPTION D1 % AEP EVENT
Option D PipesHotspotPits/ NodesPipes
Peak Flood Level Impact (m)No Longer Flooded< -0.5-0.5 - -0.25-0.25 - -0.1-0.1 - -0.01-0.01 - 0.010.01 - 0.10.1 - 0.25> 0.25Newly Flooded
´
J:\Jo
bs\11
3044
\ArcG
IS\Ar
cMap
s\_FR
MS_O
ption
s\Figu
reD10
_100
yearI
mp_S
ceD.
mxd
Hotspot D:Replaced existing trunk system with 1.9 m x 1.05 mpipes from Fenton Avenue to Northease of Marine ParadeReplaced trunk system with 5.6 m x 1.68 m outlet pipealong Maroubra Beach
D
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 E1
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 E1
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 E2
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 E3
SUBMISSIONS AND RESPONSES FROM PUBLIC EXHIBITION OF DRAFT REPORTS
Comments Response
The Maroubra study and plan only mentions acid sulfate soils in the glossary. Council's own fact sheet on this issue states that acid can form and cause damage after such soils are drained, so I suggest that this risk should be considered when Council proposes additional drainage works
The acid sulfate soils issue will be added into the report and will be taken into account when conducting drainage works that require excavation.
The drains in Chapman Av Maroubra are regularly blocked by leaves from the street trees. Thought needs to be given to catching water higher up around Maroubra Bay Public School and above. The ground in John Shore reserve does not absorb water readily. The soil has been compacted by it's previous use as a carpark for The Seals Club. Remedial work should be done to aerate the soil and provide adequate drainage, including unblocking the existing drain in this reserve. Thanks
Cleaning of pits and pipes is regularly undertaken by Council in this area as it is a known hot spot for flooding. There was a recurrent issue with the Gross Pollutant Trap located at the corner of Marine Parade and McKeon Street. It was creating backwatering in the drainage network and increasing flooding issues. Work is currenltly undertaken by Council to solve this issue. Regarding John Shore Park, the comment is noted and it will be taken into account when further investigating this option.
Thank you for the opportunity to meet representatives from council on Tuesday, 18th October. Option A Lowering Promenade This could be done easily enough and if landscaped well could pass community scrutiny. To the laymen it appears you would have to remove a fair amount of soil to lower the promenade increasing the risk of ingress of sea water higher into McKeon Street. Is there opportunity to capture water at the junction of McKeon and Marine Parade and pipe it underneath the existing promenade? Option B Muraborah Reserve Basin This is acceptable option. In my opinion we could make this basin more effective in capturing and retaining water by having it deeper, fencing it and incorporating a community garden into the basin reserve. An idea like this provides amenity to the area as well assisting in flood mitigation. Option C John Shore Park Basin Again this is an acceptable part solution, although it depends upon landscaping channels and higher islands to create a park with high amenity value. The park incorporates a number of maturing and established trees that should be kept as part of the basin design. Option D Fenton Avenue Drainage Upgrade Option G&J Upgrade Drainage from Galvin Street to Beach outlet These are the most promising options for controlling storm and floodwaters. However it appears little chance of happening unless the Maroubra Beach council masterplan is adopted. My conversations with neighbours and residents discussing the extra beach outfall produces mixed results. Many agree that it would prevent property damage but are unsure of the siting and appearance of the outfall on the beach.
Comments are noted.
Parking on weekends is a problem. Could the Park between Mons Avenue and Fitzgerald Avenue be used as a carpark on Sundays? Also why not use the park at South Maroubra for the Kingsford Markets now that they can't be held at Kingsford anymore?
Both of these suggestions will be forwarded to the Open Space Assets team for consideration and response.
If John Shore Park is used as a retention basin it is important that residents can still access it. Basin will have to be landscaped. If the lowering of the promenade is investigated in more details, the impact of king tides needs to be taken into account.
During detail investigations both these points will be taken into account. Residents will be consulted regarding these projects.
There is always rubbish and gravel in the driveway at 1 Fenton Avenue (access to the Maroubra SEALS). These debris are increasing the risk of blockage in the surrounding pits and pipes.
Council has opened discussions with the Maroubra SEALS club regarding the condition of the driveway.
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 F1
SITE SPECIFIC INFORMATION FOR RESIDENTIAL DAMAGE CURVE DEVELOPMENT
Version 3.01 June 2011 plus 2014 LW Edits Queries to [email protected]
PROJECT DETAILS DATE JOB No.
Maroubra Residential Only 12/05/2014 113048
BUILDINGS
Regional Cost Variation Factor 1.00 From Rawlinsons
Post late 2001 adjustments 1.50 Changes in AWE see AWE Stats Worksheet
Post Flood Inflation Factor 1.00 1.0 to 1.5
Multiply overall structural costs by this factor
Judgement to be used. Some suggestions
below
Regional City Regional Town
Houses Affected Factor Houses Affected Factor
Small scale impact < 50 1.00 < 10 1.00
Medium scale impacts in Regional City 100 1.20 30 1.30
Large scale impacts in Regional City > 150 1.40 > 50 1.50
Typical Duration of Immersion 1.00 hours
Building Damage Repair Limitation Factor 0.85 due to no insurance short duration
long
duration
Suggested range 0.85 to 1.00
Typical House Size 240 m^2 240 m^2 is Base
Building Size Adjustment 1.0
Total Building Adjustment Factor 1.28
CONTENTS
Average Contents Relevant to Site $
60,000
Base for 240 m^2 house $
60,000
Post late 2001 adjustments 1.50 From above
Contents Damage Repair Limitation Factor 0.75 due to no insurance short duration
long
duration
Sub-Total Adjustment Factor 1.13 Suggested range 0.75 to 0.90
Level of Flood Awareness LOW low or high only. Low default unless otherwise justifiable.
Effective Warning Time 0 hour
Interpolated DRF adjustment (Awareness/Time) 1.00 IDRF = Interpolated Damage Reduction Factor
Typical Table/Bench Height (TTBH) 0.90 0.9m is typical height. If typical is 2 storey house use 2.6m.
Total Contents Adjustment Factor AFD <= TTBH 1.13 AFD = Above Floor Depth
Total Contents Adjustment Factor AFD > TTBH 1.13
Most recent advice from Victorian Rapid Assessment Method
Low level of awareness is expected norm (long term average) any deviation needs to be justified.
Basic contents damages are based upon a DRF of 0.9
Effective Warning time (hours) 0 3 6 12 24
RAM Average IDRF Inexperienced (Low awareness) 0.90 0.80 0.80 0.80 0.70
DRF (ARF/0.9) 1.00 0.89 0.89 0.89 0.78
RAM AIDF Experienced (High awareness) 0.80 0.80 0.60 0.40 0.40
DRF (ARF/0.9) 0.89 0.89 0.67 0.44 0.44
Site Specific DRF (DRF/0.9) for Awareness level for iteration 1.00 0.89 0.89 0.89 0.78
Effective Warning time (hours) 0 3 0
Site Specific iterations 1.00 0.89 1.00
ADDITIONAL FACTORS
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 F2
Post late 2001 adjustments 1.50 From above
10050
External Damage $ 6,700 $6,700 recommended without justification
Clean Up Costs $ 4,000 $4,000 recommended without justification
Likely Time in Alternate Accommodation 3 weeks
Additional accommodation costs /Loss of Rent $ 220
$220 per week recommended without
justification
TWO STOREY HOUSE BUILDING & CONTENTS FACTORS
Up to Second Floor Level, less than 2.6 m 70% Single Storey Slab on Ground
From Second Storey up, greater than 2.6 m 115% Single Storey Slab on Ground
Base Curves AFD = Above Floor Depth
Single Storey Slab/Low Set 13164 + 4871 x AFD in metres
Structure with GST AFD greater
than 0.0 m
Validity Limits AFD less than or equal to 6 m
Single Storey High Set 16586 + 7454 x AFD
Structure with GST AFD greater
than -0.100 m
Validity Limits AFD less than or equal to 6 m
Contents 20000 + 20000 x AFD
Contents with GST AFD greater than
0
Validity Limits AFD less than or equal to 2
SITE SPECIFIC INFORMATION FOR RESIDENTIAL DAMAGE CURVE DEVELOPMENT
Version 3.01 June 2011 plus 2014 LW Edits Queries to [email protected]
PROJECT DETAILS DATE JOB No.
Maroubra Commercial\Industrial
Only (uses same curve as Residential)
12/5/2014 113048
BUILDINGS
Regional Cost Variation Factor 1.00 From Rawlinsons
Post late 2001 adjustments 1.50 Changes in AWE see AWE Stats Worksheet
Post Flood Inflation Factor 1.00 1.0 to 1.5
Multiply overall structural costs by this factor
Judgement to be used. Some suggestions below
Regional
City Regional Town
Houses Affected Factor Houses Affected Factor
Small scale impact < 50 1.00 < 10 1.00
Medium scale impacts in Regional City 100 1.20 30 1.30
Large scale impacts in Regional City > 150 1.40 > 50 1.50
Typical Duration of Immersion
hours
Building Damage Repair Limitation Factor 0.85 due to no insurance short
duration
long duration
Suggested range 0.85 to 1.00
Typical House Size 500 m^2 240 m^2 is Base
Building Size Adjustment 2.1
Total Building Adjustment Factor 2.66
CONTENTS
Average Contents Relevant to Site $
125,000
Base for 240 m^2
house
$
60,000 $ 187,500.00
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 F3
Post late 2001 adjustments 1.50 From above
Contents Damage Repair Limitation Factor 0.75 due to no insurance short
duration
long duration
Sub-Total Adjustment Factor 1.13 Suggested range 0.75 to 0.90
Level of Flood Awareness LOW low or high only. Low default unless otherwise justifiable.
Effective Warning Time 0 hour
Interpolated DRF adjustment (Awareness/Time) 1.00 IDRF = Interpolated Damage Reduction Factor
Typical Table/Bench Height (TTBH) 0.90 0.9m is typical height. If typical is 2 storey house use 2.6m.
Total Contents Adjustment Factor AFD <= TTBH 1.13 AFD = Above Floor Depth
Total Contents Adjustment Factor AFD > TTBH 1.13
Most recent advice from Victorian Rapid Assessment Method
Low level of awareness is expected norm (long term average) any deviation needs to be justified.
Basic contents damages are based upon a DRF of 0.9
Effective Warning time (hours) 0 3 6 12 24
RAM Average IDRF Inexperienced (Low awareness) 0.90 0.80 0.80 0.80 0.70
DRF (ARF/0.9) 1.00 0.89 0.89 0.89 0.78
RAM AIDF Experienced (High awareness) 0.80 0.80 0.60 0.40 0.40
DRF (ARF/0.9) 0.89 0.89 0.67 0.44 0.44
Site Specific DRF (DRF/0.9) for Awareness level for iteration 1.00 0.89 0.89 0.89 0.78
Effective Warning time (hours) 0 3 0
Site Specific iterations 1.00 0.89 1.00
ADDITIONAL FACTORS
Post late 2001 adjustments 1.50 From above
External Damage $ 6,700 $6,700 recommended without justification
Clean Up Costs $ 9,000 $4,000 recommended without justification
Likely Time in Alternate Accommodation 3 weeks
Additional accommodation costs /Loss of Rent $ 220
$220 per week recommended without justification (for residential)
TWO STOREY HOUSE BUILDING & CONTENTS FACTORS
Up to Second Floor Level, less than 2.6 m 70% Single Storey Slab on Ground
From Second Storey up, greater than 2.6 m 115% Single Storey Slab on Ground
Base Curves AFD = Above Floor Depth
Single Storey Slab/Low Set 13164 + 4871 x AFD in metres
Structure with GST AFD greater
than 0.0 m
Validity Limits AFD less than or equal to 6 m
Single Storey High Set 16586 + 7454 x AFD
Structure with GST AFD greater
than -0.100 m
Validity Limits AFD less than or equal to 6 m
Contents 20000 + 20000 x AFD
Contents with GST AFD greater than
0
Validity Limits AFD less than or equal to 2
Maroubra Bay Floodplain Risk Management Study and Plan
WMAwater: 113044:Maroubra_FRMSP: 7 December 2016 F4
Diagram F1: Residential Flood Damages Curves for Maroubra Bay Catchment
Diagram F2: Commercial / Industrial Residential Flood Damages Curves for Maroubra Bay
Catchment
WMAwater Pty Ltd (Formerly Webb McKeown and Associates) ABN 14 600 315 053
DIRECTORS ASSOCIATES Level 2, 160 Clarence St, SYDNEY NSW 2000
M K Babister BE(Hons), MEngSc GradDipMgt, FIEAust R Hardwick Jones BE(Hons), MEngSc, MIEAust Phone: 02 9299 2855 Fax: 02 9262 6208 R W Dewar BSc(Hons), MEngSc, MAIG, MIEAust M E Retallick BE(Hons), BSc, MIEAust Email: [email protected] E J Askew BE(Hons), MIEAust Website: wmawater.com.au S D Gray BE, MEng
Randwick City Council
j:\jobs\113044\admin\byrnecrescent\141218_byrnecres_floodasessment_issued.docx
30 Frances Street Randwick NSW 2031
18 December 2014
Attention: Parissa Ghanem Drainage Engineer
Dear Parissa,
Re: Byrne Crescent Investigation for Maroubra Bay FRMS&P
1 INTRODUCTION
This flood impact assessment has been prepared in relation to the localised flooding of Byrne
Crescent, Maroubra. WMAwater have developed a TUFLOW hydraulic model of the catchment
for the Flood Study and FRMS&P for the Maroubra Bay area. This model has been modified to
investigate four options in an attempt to reduce the flood impacts in Byrne Crescent. It should
be noted that the hydraulic modelling system was established to cater for large design events
and thus has limitations in its use for small design events.
2 BACKGROUND
No. 11 Byrne Crescent is subject to above floor inundation on a frequent basis (possibly as
much as three times a year from discussions with the resident). A site visit was undertaken in
September 2014 during which WMAwater spoke with local residents. The resident has sand
bags ready to divert flow and opens doors to allow the free flow of water through the house.
This causes significant disruption, inconvenience and some internal house and yard damages.
The front door of the house is at ground level and runoff which overtops the kerb will largely flow
directly to the front door.
A CDS GPT unit was installed in 2005 in the cul-de-sac adjacent to No. 11 and residents report
that runoff emanates from the lid of the unit during heavy rain. There are reports of flooding in
the area from both before and after the installation of the CDS unit. There is a very steep
gradient from the intersection with Broome Street to Byrne Crescent and after the low point the
gradient flattens significantly. A 1050 mm diameter pipe runs from Broome Street to the CDS
unit in Byrne Crescent and then out towards open land at the rear of No. 15 Byrne Crescent on
a significantly flatter gradient. An approximately 2.5 m wide drainage easement is present
between Nos. 11 and 15. A smaller 375 mm diameter pipe also takes local flows from the other
side of Byrne Crescent into the CDS unit.
Flooding occurs as water flowing down the 1050 mm steep pipe, emanating from Broome
Street, suddenly meets a gentle gradient pipe and the change in gradient causes a slowing of
2
velocities and the CDS to surcharge. Since the CDS unit has been installed both the central
access shaft cover and diversion chamber cover have been known to pop off. The larger
central access shaft has been bolted down, and as a result this causes the diversion chamber
cover to pop. Reports from residents are of both covers “floating” or “hovering” during flooding.
Not only is there risk from flooding but there is also a significant hazard posed by the exposure
of a deep hole and the floating cover.
Council wish to resolve the flooding issue in the area and also the issue of the two CDS unit
covers surcharging. It is understood that there is a DA currently submitted at No. 15 and
Council would like to undertake any works, if required, at the time of reconstruction of No. 15.
3 METHODOLOGY
WMAwater has previously developed a TUFLOW hydraulic model for the Maroubra Bay area,
which is being used to determine design flood levels for the Maroubra Bay FRMS&P. Byrne
Crescent lies within the domain of this model and, as such, this model was used in the
assessment.
To assess the hydraulic effect of the proposed works, the existing model was firstly rerun to
establish base case results. The model was run for the 1 EY (approximately one year ARI), 0.5
EY (approximately two year ARI), 0.2 EY (approximately five year ARI), 10% AEP and 5% AEP
events.
Four options were considered in this study, namely:
1) Local kerbside modifications to prevent flood water flowing through the building at No. 11:
Raising area in grass verge in front of No. 11 and modifying local ground levels to
encourage water to flow through the easement area rather than through the building
at No. 11.
2) Increase capacity of downstream pipe:
Doubling the number of pipes downstream and a review of ALS ground levels to see
if it would be possible to increase the pipe gradient.
3) Addition of a second pipe which discharges to the open area of land immediately
downstream of Nos. 11 and 15.
4) Create an overland flow path through No. 15 (over existing easement):
Run as an addition to option one.
Should this option be feasible in terms of reducing flood risk, Council would need to
enter discussions with the owner of the land regarding a flow path easement through
the property.
4 ASSESSMENT
4.1 OPTION 1 – LOCAL PROPERTY AND KERBSIDE MODIFICATIONS
Option 1 assessed the construction of a bund that extends from the southern corner of No. 11
Byrne Crescent, into the footpath reserve before turning northwest and running along the street
reserve. The crest of the bund was modelled as 17.3m AHD (approximately the 1% AEP level).
The bund would continue at the same elevation and terminate in the vicinity of No. 9 Byrne
Crescent at the point where the natural ground surface elevation of 17.3m AHD was met. It is
estimated from the LiDAR data that the wall length would be in the order of 25 m. For reference
the surface levels in both the cul-de-sac and the front of No. 11 Byrne Crescent are in the order
of 17±0.1m AHD and hence the bund would be around 300mm above the existing ground.
3
Option 1 reduced localised flooding to the extent that flooding is unlikely to occur through the
building at No. 11 Byrne Crescent for events up to the 10 % AEP, as shown in Figures 1A
through D. At the 5 % AEP level, shown in Figure 1E, depths in the front yard are reduced in
the order of 200 mm. Thus, this option would considerably reduce the frequency of flooding
through the house at No. 11. However, this benefit to No. 11 increases ponding depths within
the road reserve of Byrne Crescent by the order of 10-50 mm with the impacts largely contained
within the road reserve.
This option provides a relatively failure proof means of reducing the incidence of runoff entering
No. 11 Byrne Crescent at low cost (say $10,000)and with no significant environmental,
aesthetic or social adverse impacts.
4.2 OPTION 2 – INCREASED CAPACITY OF DOWNSTREAM DRAINAGE
Option 2 is designed to reduce the localised surface flooding by providing additional
underground pipe capacity from the CDS unit in Byrne Crescent downstream to the existing
ocean outfall. Each of the pipes downstream of the CDS was doubled from one to two.
Option 2 is effective at reducing the localised stormwater inundation within and between Nos.
11 and 15 Byrne Crescent. At the 0.2 EY level the localised flooding in the front gardens of
Nos. 11 and 15 was reduced in the order of 10 to 20 mm such that flooding is unlikely to occur,
as shown in Figure 2C. For the 10 % and 20 %AEP events flooding will still occur within these
lots, however the peak inundation depths are likely to be reduced by at least 20 mm, as shown
in Figures 2D and 2E, respectively. These small reductions in peak level are likely to make little
difference to the magnitude of flood damages at No. 11 Byrne Crescent, or the considerable
inconvenience experienced by the resident during floods.
This option has the added benefit of reducing the depth of inundation in the adjacent reserve
and surf club car park by at least 10 mm, for the 0.2 EY through 5% AEP events, as shown in
Figures 2C to 2E, respectively.
An inspection of the ALS surface levels shows that the ground elevation at the rear of No. 11
Byrne Crescent is approximately 14.4 mAHD, whereas the ocean outfall, some 480 m
downstream, is at an elevation of 3.3 mAHD. Theoretically, this results in a potential 2.3 %
average grade, however due to variations in the above ground topography it is unlikely that this
grade would be achieved. Therefore, it is highly unlikely that works could be undertaken to
effectively improve the existing pipe gradients to increase their capacity.
This option is likely to be prohibitively expensive in terms of the associated earth and pipe
works as well as require significant negotiation with neighbouring landholders. Further, it is
unlikely that a cost benefit analysis would support this expenditure given the projected
reductions in localised stormwater inundation.
4.3 OPTION 3 – ADDITION OF A SECOND PIPE THAT DISCHARGES DOWNSTREAM
Option 3 assessed the addition of a 60 m length of 1050 mm diameter pipe that would run from
the existing kerbside pit in front of No. 15 Byrne Crescent and discharge into the land
immediately downstream of No. 11. Pipe duplication was explicitly not simulated between the
kerb pit and the CDS unit to minimise the volume of work to be executed within the road
reserve. This configuration will likely still result in surcharging of the CDS and adjacent pit,
however increased capacity of the kerbside pit and pipe network will not only capture the
surcharged flows but also the overland flows that already arrive at the cul-de-sac. While the
length of the pipe run along the boundary between Nos. 11 and 15 is in the order of 45 m, the
additional 15 m of run is required to reach a point where the natural surface elevation is
sufficiently low to maintain pipe grade and still discharge onto the natural surface.
4
It should be noted that there is likely to be little space within the existing easement to install a
second 1050mm diameter pipe and Council would need to investigate this further if they were to
pursue this option. This option assumes that all runoff in the cul-de-sac enters the pipe system
via new kerb inlet pits. In practice this is unlikely to occur due to blockage (leaves, parked
vehicle etc.) or the runoff bypassing the pits.
Option 3 will reduce the localised stormwater inundation within Byrne Crescent by at least
20 mm. At the 0.2 EY event localised ponding is largely eliminated, as shown in Figure 3C.
With the 10 % and 20 % AEP events, flooding is reduced within the front yards of Nos. 11 and
15 as well as the cul-de-sac of Byrne Crescent in the order of 10-20 mm, as shown in Figures
3D and E. However, it is likely that for these events, as well as less frequent events, that there
will still be some localised flooding that may still enter the building at No. 11 Byrne Crescent.
Unfortunately the results indicated that if this option was implemented the downstream lands in
the adjacent reserve and surf club car park will be subject to increased flood depths.
Specifically, for all events areas of flooding in the surf club car park increase by over 100 mm
depth.
4.4 OPTION 4 – PROVISION OF FORMAL OVERLAND FLOW PATH AND KERB
MODIFICATIONS
Option 4 is a superset of Option 1 in which the kerb modifications are combined with a formal
overland flow path defined along the boundary between Nos. 11 and 15 Byrne Crescent. There
is currently an informal vegetated overland flow path and it is anticipated that the provision of a
formalised overland flow path would increase the conveyance as well as define a known zone
of inundation and correspondingly reduce the associated risks and possibly external damages.
Option 4 reduces localised flooding within the front of No. 11 Byrne Crescent to such an extent
that localised flooding is unlikely to occur for events up to the 5 % AEP, as shown in Figures 4A
though E. Similarly there is a reduction in flow depth along the formalised flow path in the order
of 20 mm for all events simulated, although this reduction will depend on the assumed flow path
dimensions. As with Option 1, the ponding depth within Byrne Crescent increases in the order
of 10-50 mm. There was no measureable impact on downstream lands from this option.
4.5 IMPACT OF OPTIONS ON CDS UNIT FLOWS
With respect to the performance of the CDS unit there is essentially no change across all the
scenarios, as shown in Table 1 and Table 2.
Table 1 Peak Upstream Inflows to CDS (m3/s)
Option 1 EY 0.5 EY 0.2 EY 10% AEP 5% AEP
Base 0.44 1.34 1.44 1.44 1.43 1 0.44 1.34 1.44 1.44 1.43 2 0.44 1.35 1.60 1.62 1.64 3 0.40 1.23 1.54 1.61 1.64 4 0.44 1.34 1.44 1.43 1.43
Table 2 Peak Pipe Outflows Downstream of CDS (m3/s)
Option 1 EY 0.5 EY 0.2 EY 10% AEP 5% AEP
Base 0.47 1.42 1.51 1.51 1.51 1 0.47 1.42 1.51 1.51 1.51 2 0.47 1.46 1.75 1.77 1.81 3 0.42 1.33 1.69 1.76 1.79 4 0.47 1.42 1.51 1.51 1.51
5
5 CONCLUSIONS
An inspection of the ALS survey data indicated that it is unlikely that the pipe gradients
downstream of Byrne Crescent could be significantly increased.
From an examination of the impacts of the four options, Options 2 and 3 are both effective at
reducing the localised stormwater inundation in the locality of the Byrne Crescent cul-de-sac
and Nos. 11 and 15 Byrne Crescent. However, as both these options involve significant
construction works and associated costs they are unlikely to be feasible to implement.
Option 1 provides a relatively straightforward and cost effective measure to eliminate inundation
of No. 11 Byrne Crescent, to the crest of the embankment. This measure could be further
enhanced with formalisation of the overland flow easement (Option 4) but this would require
negotiation with the property owners.
The performance of the CDS unit was examined and it was found that there was little or no
change to the flows through the CDS unit for the options tested. The key factors that contribute
to the flooding issue at the Byrne Crescent cul-de-sac are likely to be a combination of the
relatively steep topography leading into the cul-de-sac, and where stormwater is partially
trapped in the cul-de-sac at an enclosed low point. Removal of the CDS unit would not
eliminate the problem. If the CDS unit lids were 100% sealed then water would still surcharge
at the kerb inlet pits.
However, in very small events the CDS unit is likely to restrict the capacity of the pipe system
and thus slightly increase the frequency of surcharging. This issue cannot be investigated in
the TUFLOW model as it would require a greater understanding of the hydraulics of the specific
CDS unit and how it performs under pressure.
Yours Sincerely,
WMAwater
Richard Dewar
Director
Enclosed Figures:
Figure 1A-E: Peak Flood Impact, Option 1 Property/Kerbside Modification, 1 EY Event to
5 % AEP event, respectively
Figure 2A-E: Peak Flood Impact, Option 2, Pipe Duplication Downstream, 1 EY Event to
5 % AEP event, respectively
Figure 3A-E: Peak Flood Impact, Option 3, Addition of Second Pipe, 1 EY Event to 5 %
AEP event, respectively
Figure 4A-E: Peak Flood Impact, Option 4, Overland Flow Path and Kerbside
Modification, 1 EY Event to 5 % AEP event, respectively
Existing Pipes
Kerbside Modification
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 1APEAK FLOOD IMPACT
OPTION ONE: PROPERTY/KERBSIDE MODIFICATION1EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure01a_Impact_001yr_Opt1.mxd
Bund raised to 17.3 mAHD
MAROUBRA
MALABAR
Existing Pipes
Kerbside Modification
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 1B
PEAK FLOOD IMPACTOPTION ONE: PROPERTY/KERBSIDE MODIFICATION
0.5EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure01b_Impact_002yr_Opt1.mxd
Bund raised to 17.3 mAHD
MAROUBRA
MALABAR
Existing Pipes
Kerbside Modification
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 1C
PEAK FLOOD IMPACTOPTION ONE: PROPERTY/KERBSIDE MODIFICATION
0.2EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure01c_Impact_005yr_Opt1.mxd
Bund raised to 17.3 mAHD
MAROUBRA
MALABAR
Existing Pipes
Kerbside Modification
Impact (m)
< - 0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 1D
PEAK FLOOD IMPACTOPTION ONE: PROPERTY/KERBSIDE MODIFICATION
10% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure01d_Impact_010yr_Opt1.mxd
Bund raised to 17.3 mAHD
MAROUBRA
MALABAR
Existing Pipes
Kerbside Modification
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 1EPEAK FLOOD IMPACT
OPTION ONE: PROPERTY/KERBSIDE MODIFICATION5% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure01e_Impact_020yr_Opt1.mxd
Bund raised to 17.3 mAHD
Existing Pipes
Pipe Upgraded
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 2APEAK FLOOD IMPACT
OPTION TWO: DOUBLING PIPES DOWNSTREAM1EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure02a_Impact_001yr_Opt2.mxd
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1200mm pipe
Option - 2 x 1200mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
MAROUBRA
MALABAR
Existing Pipes
Pipe Upgraded
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 2B
PEAK FLOOD IMPACTOPTION TWO: DOUBLING PIPES DOWNSTREAM
0.5EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure02b_Impact_002yr_Opt2.mxd
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1000mm pipe
Option - 2 x 1000mm pipes
Existing - 1 x 1200mm pipe
Option - 2 x 1200mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
MAROUBRA
MALABAR
Existing Pipes
Pipe Upgraded
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 2C
PEAK FLOOD IMPACTOPTION TWO: DOUBLING PIPES DOWNSTREAM
0.2EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure02c_Impact_005yr_Opt2.mxd
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1200mm pipe
Option - 2 x 1200mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
MAROUBRA
MALABAR
Existing Pipes
Pipe Upgraded
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 2D
PEAK FLOOD IMPACTOPTION TWO: DOUBLING PIPES DOWNSTREAM
10% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure02d_Impact_010yr_Opt2.mxd
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1200mm pipe
Option - 2 x 1200mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
MAROUBRA
MALABAR
Existing Pipes
Pipe Upgraded
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 2EPEAK FLOOD IMPACT
OPTION TWO: DOUBLING PIPES DOWNSTREAM5% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure02e_Impact_020yr_Opt2.mxd
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1050mm pipe
Option - 2 x 1050mm pipes
Existing - 1 x 1200mm pipe
Option - 2 x 1200mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Existing - 1 x 1500mm pipe
Option - 2 x 1500mm pipes
Additional Pipe
Existing Pipes
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 3APEAK FLOOD IMPACT
OPTION THREE: ADDITION OF SECOND PIPE1EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure03a_Impact_001yr_Opt3.mxd
Outlet for additional pipe
into open land. Invert level 12.9m
Second 1.05m pipe
added to existing pit
Additional Pipe
Existing Pipes
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 3B
PEAK FLOOD IMPACTOPTION THREE: ADDITION OF SECOND PIPE
0.5EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure03b_Impact_002yr_Opt3.mxd
Outlet for additional pipe
into open land. Invert level 12.9m
Second 1.05m pipe
added to existing pit
0 50 100 150 20025m
FIGURE 3C
PEAK FLOOD IMPACTOPTION THREE: ADDITION OF SECOND PIPE
0.2EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure03c_Impact_005yr_Opt3.mxd
Outlet for additional pipe
into open land. Invert level 12.9m
Second 1.05m pipe
added to existing pit
Additional Pipe
Existing Pipes
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
Additional Pipe
Existing Pipes
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 3D
PEAK FLOOD IMPACTOPTION THREE: ADDITION OF SECOND PIPE
10% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure03d_Impact_010yr_Opt3.mxd
Outlet for additional pipe
into open land. Invert level 12.9m
Second 1.05m pipe
added to existing pit
Additional Pipe
Existing Pipes
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 3EPEAK FLOOD IMPACT
OPTION THREE: ADDITION OF SECOND PIPE5% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure03e_Impact_020yr_Opt3.mxd
Outlet for additional pipe
into open land. Invert level 12.9m
Second 1.05m pipe
added to existing pit
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 4APEAK FLOOD IMPACT
OPTION FOUR: OVERLAND FLOW PATH AND KERBSIDE MODIFICATION1EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure04a_Impact_001yr_Opt4.mxd
Bund raised to 17.3 mAHD
Kerbside Modification
Overland Flow Path
Existing Pipes
Newly created swale through existing drainage easement.
Approximate width - 1 m
Approximate average depth - 250 mm
Length - 36 m
Note: Existing 1050 mm pipe to remain in situ.
MAROUBRA
MALABAR
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 4B
PEAK FLOOD IMPACTOPTION FOUR: OVERLAND FLOW PATH AND KERBSIDE MODIFICATION
0.5EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure04b_Impact_002yr_Opt4.mxd
Bund raised to 17.3 mAHD
Kerbside Modification
Overland Flow Path
Existing Pipes
Newly created swale through existing drainage easement.
Approximate width - 1 m
Approximate average depth - 250 mm
Length - 36 m
Note: Existing 1050 mm pipe to remain in situ.
MAROUBRA
MALABAR
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 4C
PEAK FLOOD IMPACTOPTION FOUR: OVERLAND FLOW PATH AND KERBSIDE MODIFICATION
0.2EY EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure04c_Impact_005yr_Opt4.mxd
Bund raised to 17.3 mAHD
Kerbside Modification
Overland Flow Path
Existing Pipes
Newly created swale through existing drainage easement.
Approximate width - 1 m
Approximate average depth - 250 mm
Length - 36 m
Note: Existing 1050 mm pipe to remain in situ.
MAROUBRA
MALABAR
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 4D
PEAK FLOOD IMPACTOPTION FOUR: OVERLAND FLOW PATH AND KERBSIDE MODIFICATION
10% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure04d_Impact_010yr_Opt4.mxd
Bund raised to 17.3 mAHD
Kerbside Modification
Overland Flow Path
Existing Pipes
Newly created swale through existing drainage easement.
Approximate width - 1 m
Approximate average depth - 250 mm
Length - 36 m
Note: Existing 1050 mm pipe to remain in situ.
MAROUBRA
MALABAR
Impact (m)
< -0.02
-0.02 - -0.01
No Impact
0.01 - 0.05
0.05 - 0.1
> 0.1
No Longer Flooded
Newly Flooded
0 50 100 150 20025m
FIGURE 4EPEAK FLOOD IMPACT
OPTION FOUR: OVERLAND FLOW PATH AND KERBSIDE MODIFICATION5% AEP EVENT
J:\Jobs\113044\ArcGIS\ArcMaps\BryneCresent\Figure04e_Impact_020yr_Opt4.mxd
Bund raised to 17.3 mAHD
Kerbside Modification
Overland Flow Path
Existing Pipes
Newly created swale through existing drainage easement.
Approximate width - 1 m
Approximate average depth - 250 mm
Length - 36 m
Note: Existing 1050 mm pipe to remain in situ.