Local Area Planning Update – TRANSAC 6-19-14. Base Case Status - PowerPoint PPT Presentation

Citation preview

Page 1: Local Area Planning Update – TRANSAC 6-19-14

Local Area Planning Update – TRANSAC 6-19-14

1

Page 2: Local Area Planning Update – TRANSAC 6-19-14

Base Case Status• Base case study models representing the base

scenarios will be completed for four seasons: Heavy Summer (HS), Heavy Winter (HW), Light Autumn (LA), and Light Spring (LSP) for the present and future over the 15-year planning horizon… 2014, 2019, 2024, and 2029… 16 cases total.

Base Cases

2

Page 3: Local Area Planning Update – TRANSAC 6-19-14

Base Case Status – cont.• Existing system configuration will be modeled in 2014

HS, HW, LA and LSP cases; signed projects (GIA’s EP&C’s, TSR’s, etc.) and budgeted/approved system improvements are included in 2019 and later cases. Dispatch may depend on TSR’s.

• All heavy loading base cases will be based on a 1/10 load forecast.

• All light loading base cases will be based on 65% of the seasonal peak.

Base Cases

3

Page 4: Local Area Planning Update – TRANSAC 6-19-14

Contingencies to Study• System normal (N-0), single segment or element

outage (N-1), and selected “credible” double segment or element outage (N-2) contingency files will be developed/updated to facilitate simulation runs of the same system conditions through each base case.

• Outages include:– Lines– Transformers– Buses– Plants (Generation)

Contingencies

4

Page 5: Local Area Planning Update – TRANSAC 6-19-14

Criteria

5

Study Criteria• System normal and Outage conditions will be modeled

and studied for adequacy and system security.• Segment or element thermal loads >85% will be noted

under these conditions; loads above 100% of seasonal limits will be noted as overloads.– Overloaded segments will be “tripped” per standard relaying

practice (100% - 150% thermal on lines, 125% minimum thermal on transformers) to check for “cascading” outages;

– Changes in seasonal ratings will be considered. • Emergency ratings do not apply.• Existing OMS or RAS schemes will be considered.

Page 6: Local Area Planning Update – TRANSAC 6-19-14

Criteria

6

Study Criteria – cont.• Voltages outside of NWE planning criteria will be

noted (93%, 95%, or 97% low voltage limit depending on line voltage; 105% high voltage limit).– Load-serving bus voltages may fall above or below the tabled

value if conditions allow a higher/lower voltage without harm to NWE or customer equipment.

– Certain equipment ratings may dictate different limits (107% will be allowed on 100 kV systems where equipment is nameplate rated 102 kV or higher).

Page 7: Local Area Planning Update – TRANSAC 6-19-14

State of the System Studies System Normal and Outage studies will be completed on all seasons of the 2014 base cases to determine the present “state of the system” as it exists today.

7

Page 8: Local Area Planning Update – TRANSAC 6-19-14

Next Steps

8

Next Steps• Q3: Analysis of 2014 cases for normal and outage

conditions will be completed for state of the system review.

• Q4-Q5: Complete the analysis of 2019, 2024, and the 2029 cases.– Verification of new problems– Uncertainty scenarios

• Q5: Prioritize problems using Decision Rules• Q5-Q6: Begin Mitigation Studies

Page 9: Local Area Planning Update – TRANSAC 6-19-14

Local Area Planning Update

Questions?

9

Page 10: Local Area Planning Update – TRANSAC 6-19-14

10