Upload
scarlett-sherman
View
217
Download
0
Embed Size (px)
Citation preview
LMC 27 November 2013
Status of LBDS LS1 activities and plans for 2014 reliability run
Jan Uythoven for the many, many people working on the mentioned equipment
2Jan Uythoven, Status LBDS LS1 & plans
New TCDQ absorber Protects the machine in case of asynchronous dump Upgraded version robust to 2.5×1011 p+/b @ 25 ns The cross section of the upgraded TCDQ is identical to the present
system. The graphite absorber is being replaced by a sandwich of graphite and carbon reinforced carbon fibre (CfC)
New VMTAB bellows to allow large movement (TE/VSC) Production started
LMC, 27/11/2013
Old sandwich vs. new sandwich
M. Atanasov, J. Borburgh
3Jan Uythoven, Status LBDS LS1 & plans
New TCDQ and related All 6 tanks are installed and aligned Modification of measurement tables ongoing (01/2014) Spare tank will be finished by the end of 2014 Related to asynch dump protection
The new TCDQ position will be interlocked by the BETS (N.Voumard) New BPMS electronics (T. Lefevre, C. Boccard) Installation of TCSGP – jaw BPMs (S.Redaelli & project)
LMC, 27/11/2013
4
Abort Gap Cleaning Automatic procedures of
the BSRA to make the system more reliable To be launched
automatically by sequencer or ‘internal timer’ when in physics
Aim is to automatically start the abort gap cleaning or dump the beam, without intervention of the operator
Re-assessed quench levels of Q4 and Q5 with new TCDQ
Improvements cleaning by the ADT New cables and hardware New cleaning algorithms
being studied
LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans
See MPP 25/10/2013
S. Mazzoni, E.Bravin, S.Bart-Pederson
W. Hofle, D.Valuch, E. Gianfelice-Wendt
5
Direct link BIS – LBDS re-triggering
LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans
BIS CIBM
BIS CIBM
BIS CIBG
Loop A
Loop B
Cour
tesy
E. C
arlie
r, S.
Gab
orui
n
BIS CIBDSRTB
Use
r pe
rmit
(B1
conf
ig)
200us
250us
Presented MPP 19/07/2013
S.Gabourin, R.Denz, E.Carlier, N.Magnin, M.Zerlauth, D.Wollmann, A.Apollonio
Asynchronous trigger
6Jan Uythoven, Status LBDS LS1 & plans
Direct link BIS – LBDS re-triggering
False Asynchronous beam dumps Specified: 2 in 10 years Calculated: 0.025 in 10 years
False Synchronous beam dumps Specified: 2 per year Calculated: 0.011 per year
Status Ordering components VHDL test bench ‘now’ Series of 5 boards to be
launched December Install machine March 2014
LMC, 27/11/2013
V. Vatansver
S. Gabourin
7
Dilution kickers MKB Installation of the nominal system (staged to spread costs) Add two MKB magnets per beam = 1 tank: 4 H + 6 V magnets
LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans
V.Senaj, L.Ducimetière
8
Extraction kicker MKD - Generator
During LS1 operational energy was limited to 5 TeV Installation of HV insulators between GTO switches HV
deflectors and return current rods
LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans
V.Senaj, L.Ducimetière
9Jan Uythoven, Status LBDS LS1 & plans
Add shielding to MKD & MKB cable ducts
Additional shielding between UA and RA for MKD and MKB systems
LMC, 27/11/2013
V.Senaj
10Jan Uythoven, Status LBDS LS1 & plans
Extraction kicker MKD Power Trigger Unit
Increase PTU maximum voltage from 3 kV to 4 kV (replacement of HVPS)
Replace 1.2 kV IGBT with equivalent 1.7 kV type=> better resistance to SEB
Operate PTU at ~3500 V constant voltage,=> Increase GTO gate current=> Increase GTO lifetime=> Reduce kicker rise time=> Stabilise pulse delay over energy range
LMC, 27/11/2013
V.Senaj, M. Stjepic, E.Carlier
11
LBDS Controls
Upgrade of Trigger Synchronisation Units cards (TSU) Distribute TSU over three different crates Motivation
External review of TSU v2 cards (2010) Internal review of LBDS Powering (2012) VME crate +12V problem (2012) CIBU powering filters problems (2011) Improvement of surveillance & diagnosis
LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans
A. Patsouli, A. Antoine, N. Voumard
12
LBDS Powering Modifications
• Third UPS (backup) added everywhere• Added a separated connection to a second UPS (US65) for LBDS• Individual circuit breaker for each crate PSU• Software monitoring of crate redundant PSU• The aim is to improve safety
Jan Uythoven, Status LBDS LS1 & plansLMC, 27/11/2013
Tests to take place at end of AUG tests
Prefer to test before starting run with local BIS loop -> end of May
Test option with F3 and F4 off simultaneously
V.Chareyre, H.Thiesen, I.Romera, M.Zerlauth
E.Carlier, N.Magnin, A.Antoine
Split in three crates
13Jan Uythoven, Status LBDS LS1 & plans
MKB Vacuum
Number of ‘false beam dumps’ due to LBDS in 2010 – 2012
Too many dumps triggered by MKB vacuum, without having a real vacuum problem
Problems with noisy vacuum signals
LMC, 27/11/2013
14Jan Uythoven, Status LBDS LS1 & plans
MKB Vacuum
MKB vacuum gauges being replaced Problems with regular vacuum spikes (every 7 / 9 minutes) being
investigated in detail Installation of test gauge outside beam vacuum Effect not visible outside the vacuum chamber Seems to be real and not a controls issue inside the chamber Source to be identified at start-up
ABT prefers to maintain present 2 oo 3 interlock logic per individual MKB tank
LMC, 27/11/2013
Not only this
device !
F. Antoniotti, JP. Boivin, P. Gomes
15Jan Uythoven, Status LBDS LS1 & plans
LBDS Reliability Runs Local Reliability Run
12 weeks, system in local Test the voltage holding of generators and magnets, erratic switching
(without radiation), switch surveillance, cooling, stability, energy scans Remote Reliability Run
6 weeks, system in Remote Run sequencer for arming, local BIS loop and BETS-SIM Including energy ramps etc. Test new link between BIS – LBDS: get statistics Test operational software and diagnostics, XPOC etc.
Risks to be a moving target with developments of FESA3, CMW etc.
Followed by regular running until first beams Tests with beam (2015)
Standard commissioning tests with beam Effective rise time measurement of the MKD (never done) Test dump with BLMDD (never done)
LMC, 27/11/2013
16Jan Uythoven, Status LBDS LS1 & plans
Commissioning / Reliability Runs / Dry runs
LMC, 27/11/2013
Nov – Dec 2013 Commissioning individual MKDs and MKBs
Local (ABT)
06/01/2014– 14/02/2014 System tests LBDS Beam 1 and Beam 2
Local (ABT)
17/02/2014- 09/05/2014 Reliability run Local (ABT)March 2014 Install new BIS – LBDS link (MPE) March – April 1/day week Tests from CCC, parallel to
reliability runRemote 1 day/week (OP)
12/05/2014 – 23/05/2014 Install new TSU on LBDS & tests in local and from CCC
(MPE / ABT / OP)
26/05/2014 – 04/07/2014 Reliability run in remote, local BIS loop and BETSIM. From CCC. UPS tests.
Remote
07/07/2014 Weekly testing during dry runs / check on FESA(3) updates and added functionalities
Remote
Date to be determined by OP
Remove local BIS and BETSIM, start testing machine wide and close BIS loop. Weekly testing.
Remote
End 2014 (OP) BIS loop closed, inject and dump under real machine conditions
Remote
Safety OK
before summer
Keep system
working / software
17Jan Uythoven, Status LBDS LS1 & plans
Conclusions
Many important changes to the LHC Beam Dumping System and related equipment To allow for higher beam energies and intensities To improve safety To increase availability
Extensive testing is required to guarantee safety Reliability run in local, 12 weeks: generators and magnets Reliability run in remote, 6 weeks: BIS-LBDS, TSU To be finished before the summer holidays: back to bussiness Tests with beam at start-up
Running in remote involves many equipment groups and requires coordination by the OP group
LMC, 27/11/2013