Lkas11 Construction Contracts

  • Upload
    samaan

  • View
    228

  • Download
    0

Embed Size (px)

Citation preview

  • 8/12/2019 Lkas11 Construction Contracts

    1/15

    Uditha De Zoysa

    LKAS 11 ConstructionContracts

    rec or,

    12 June 2012

    22

  • 8/12/2019 Lkas11 Construction Contracts

    2/15

    Agenda

    Scope and definitions

    Segmenting and combining construction contracts

    Recognition of contract revenue and costs

    IFRIC 15 LKAS 11 Vs LKAS 18

    New developments on revenue recognition3

    Definition

    ... a contract specifically negotiated ...

    ... for the construction of an asset, or a combination of assets ...

    4

    ... that are closely interrelated or interdependent in terms of their

    design, technology and function or their ultimate purpose or use.

  • 8/12/2019 Lkas11 Construction Contracts

    3/15

    Type of contr acts

    Construction contracts

    Fixed price

    Contractor and customer agreed a fixed price or

    Cost plus

    Contractor is reimbursed for allowable or otherwise defined costs, plus

    5

    a percentage of these costs or a fixed fee

    Segmenting construction contracts

    One contract number of assets

    Separate propo sals for each asset?No

    No

    No

    Yes

    Yes

    Separate negotiatio n / acceptance foreach asset?

    6

    asset?

    SEPARATE constru ction contr act for eachasset

    One constructioncontract

    Yes

  • 8/12/2019 Lkas11 Construction Contracts

    4/15

    Combining construction contracts

    Group of contracts

    Negotiated as a singl e package?

    Interrelated overall profit margin?

    No

    No

    No

    Yes

    Yes

    7

    continuous sequence?

    SINGLE con tract Separatecontracts

    Yes

    Add it ion al ass et at cus tomer o pt ion

    Separate if:

    additional asset differs significantly from the asset(s) covered by the

    original contract in: design; technology; or function; or

    8

    price of the additional asset is negotiated without regard to the original

    contract price

  • 8/12/2019 Lkas11 Construction Contracts

    5/15

    Contract revenue

    Initial amount

    Variations

    Contract revenueto be measured at

    fair value of theconsideration received or

    receivableOnl if :

    9

    Claims

    Incentivepayment

    - Probable they willresult in revenue; and

    - revenue ismeasurable reliably

    Revenue Measured at Fair Value

    If revenue on a contract is recognized, but will be received only ,

    be imputed and expected cash receipt should be discounted todetermine the fair value of the amounts receivable.

    Eg: Retention

    10

  • 8/12/2019 Lkas11 Construction Contracts

    6/15

    Contract costs

    Include if: Related directly to specific contract

    Exclude if: Cannot be attributed to contract

    Attributable to contract activity ingeneral and can be allocated to thecontract

    Other specifically chargeable to thecustomer under the contract

    Incurred from the date of and inorder to secure the contract only if:

    relate directly to contract

    ac v y or canno e a oca e o acontract:

    general administration costs notreimbursable under the contract

    selling costs R&D costs not reimbursable

    under the contract depreciation of idle PPE not

    11

    identifiable separately measurable reliably probable that contract will be

    obtained not expensed previously

    used on a particular contract

    Recognition of c ontract revenue and expenses

    Outcome can beestimated reliably

    Outcome cannot beestimated reliably

    Recognise by reference to thestage of completion at the end ofthe reporting period:

    contract revenue contract costs

    Recognise immediately anyexpected loss as an expense

    Recognise revenue only to theextent of incurred contract costswith probable recovery

    Recognise contract costs as anexpense as incurred

    Recognise immediately anyexpected loss as an expense

    12

  • 8/12/2019 Lkas11 Construction Contracts

    7/15

    Reliable estimate of outcom e

    ALL condit ions should be met:

    Fixed price contract

    Total contract revenue measurablereliably

    Probable that economic benefits will flowto the entity

    Cost plus contract

    Probable that economic benefits will flowto the entity

    Attributable contract costs (whether ornot reimbursable specifically) identifiable

    13

    on rac cos s o comp e e an s a e ocompletion measurable reliably

    Attributable contract costs identifiableclearly and measurable reliably: actual vs.estimates

    Methods for determining stage of completion

    Measures

    Output

    Surveys of work performed

    Completion of a physical

    Input

    cost incurred to date

    total estimate costs %

    14

    NB! No specific method is mandated Progress payments and advances often do NOT reflect work performed

  • 8/12/2019 Lkas11 Construction Contracts

    8/15

    Recognition of cont ract revenue and expenses Example 1

    A enters into a contract to build a road for Rs.90 million. Asinitial estimate of contract costs is Rs.74 million. Thecon rac s ar s ear y n Scenario 1 - At the end of 2010 A can estimate reliably the outcome of the

    contract Stage of completion is determined based on the completion of

    physical proportion of the contract work Estimated to be 50% physically complete at end of 2010 Cost incurred to date Rs.37 million A reco nises at 31 December 2010:

    15

    revenue of Rs.45 million; and

    expenses of Rs.37 million.

    Recognition of contract revenue and expenses Example (continued)

    Scenario 2 - At the end of 2010 A cannot estimate reliably theoutcome of the contract

    Costs incurred Rs.30 million It is probable that the costs will be recovered A recognises at 31 December 2010:

    revenue of Rs.30 million; and

    expenses of Rs.30 million.

    16

  • 8/12/2019 Lkas11 Construction Contracts

    9/15

    Percentage of completion method - changes in estimates

    Percentage of completion method: application on cumulative basis in each period

    to the current estimates of contract revenue

    Effect of changes in estimates is accounted for under LKAS 8 - prospectively

    17

    Changes in estimates Example 2

    A enters into a contract to build a road for Rs.90 million. Asinitial estimate of contract costs is Rs.74 million. Thecon rac s ar s ear y n

    Stage of completion is determined based on the completionof physical proportion of the contract work

    Year-end 2009 estimated completed work 50% no changes to estimated costs to complete the work

    18

    ear-en estimated completed work 90% estimated total costs to complete the work Rs.80 million

  • 8/12/2019 Lkas11 Construction Contracts

    10/15

    Changes in estimates Example (continued)

    2009 2010 2011 TotalRs.m Rs.m Rs.m Rs.m

    Revenue 45 1 36 3 9 90Costs 37 2 35 4 8 80Profit 8 1 1 10GPM 17.7% 2.8% 11.1% 11.1%

    19

    an ge n es ma esa c u a ons:1. 90x50% = 45

    2. 74x50% = 373. 90x90% - 45 = 364. 80x90% - 37 = 35

    Expected losses Example 3

    A enters into a contract to build a road for Rs.90 million. As initial estimate of contract costs is Rs.74 million. Thecon rac s ar s ear y n

    At the end of 2010, the estimated costs to complete the work increase to Rs.95 million, with no increase incontract revenue . A has to recognise the expected loss of Rs.5 million immediately

    20

    Calculation

    Total revenue = 90

    Total estimated cost = (95)

    Estimated loss = 5

  • 8/12/2019 Lkas11 Construction Contracts

    11/15

    Issues and scope IFRIC 15

    Issues addressed by IFRIC 15 Applicable standard (LKAS 11 or

    LKAS 18) Timing of revenue recognition

    Scope Agreement for the construction of

    real estate Component for the construction

    of real estate identified within an

    21

    agreement that includes other components

    LKAS 11 or LKAS 18?

    Is buyer able to specify the major structur alelements of desi n and / ormajor structural changes?

    LKAS 11 LKAS 18

    YES NO

    22

    NOT an accounting policy choice!!!

  • 8/12/2019 Lkas11 Construction Contracts

    12/15

    When and how r ecognize revenue?

    Construction contract? LKAS 11

    NO

    Revenue recognition

    NO

    Stage ofcompletion

    Rendering o f servicesonly?

    LKAS 18Rendering of servicesYES

    23

    Sale of goods ? criteria met on acontinuous basis?

    Uponcompletion

    NO

    ICASL Ruling on Deferrin g Applicatio n of IFRIC 15

    O tion

    Defer application of IFRIC Apply IFRIC 15 with t head o t io n o f SL FRS

    24

    comes into effect

  • 8/12/2019 Lkas11 Construction Contracts

    13/15

    Contracts with Customers ED

    A new revenue recognition model that applies to revenue

    Single standard would replace: IAS 11 Construction contracts IAS 18 Revenue IFRIC 13 Customer Loyalty Programmes greemen s or e ons ruc on o ea s a e IFRIC 18 Transfers of Assets from Customers

    SIC31 Revenue Barter Transactions Involving Advertising Services

    25

    The 5-step model

    Step 1: Identify the contract Contract

    Step 2: Identify POs in the contract PO

    2PO 1

    Step 3: Determine the TP TP

    for the contract

    PO: Performance obligationTP: Transaction price

    Step 4: Allocate the TP to POs

    TP allocated to PO 2

    TP allocated to PO 1

    Step 5: Revenue as POs satisfied

    Revenue on PO 2

    Revenue on PO 1

  • 8/12/2019 Lkas11 Construction Contracts

    14/15

    Criteria for Recognizing Revenue Over Time

    Performancecreate or enhancean asset that the

    Performance does not create an asset withalternative use to the entity

    an asset that thecustomer controls ustomer

    receivebenefits asentity performs

    Task wouldnot need tobereperformed

    Entity hasthe right topayment forperformance

    Performance obligations satisfied over time

    27

    Eg Buildingconstructed on a

    customers land andcustomer retains thepartly completedbuilding if thecontract was terminated

    Eg Projectmanagements

    service

    Eg Partlyconstructed

    building thatcustomer retainsif contract isterminated early

    Eg Milestoneevents have been

    achieved

    u stions

    28

  • 8/12/2019 Lkas11 Construction Contracts

    15/15

    Contact details

    KPMG.

    P.O. Box 186, Colombo 03, Sri Lanka.

    Department of Professional Practice DPP

    Ms. Uditha de Zoysa +94 (0) 11 5 426 124

    Email [email protected]

    2929

    Web www.kpmg.com/lk

    Thank you.