Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks 1 M/s. WCL Patansaongi Expansion Underground Mine, Vill- Patansaongi, Tal- Saoner, Dist - Nagpur 34.89 Crs Renewal with amalgamation JD(APC) 1 to 17 1 M/s. Mont Vert Associates,S. No. 239(p), CTS No. 725 to 742,945, 956, 957, Wakad, Mulshi 111.79 Crs. Renewal RO(HQ) 18 to 25 2 M/s. Pulse Mall Maintenance LLP, S. No. 206. A/1. Plot No. 88/4, Next to Aagrkhan Palace, Pune-Nagar Road, Pune 109.50 Crs. Renewal RO(HQ) 26 to 33 3 M/s. Shri Balaji Society, Survey No. 55/2-7, Tathwade, Opp. Mumbai-Bangalore Bypass, Pune 95.96 Crs. Establish RO(HQ) 34 to 43 4 M/s. Sai Essen Properties, Gut No. 1169, 1170, NearSane Chowk, Akurdi-Chikhali Road, Pune 65.00 Crs. Establish RO(HQ) 44 to 52 5 M/s. Puranik Buildcon Pvt. Ltd., ALDEA ESPANOLA, S.No. 12/3, 12/4, 12/5, 12/5/1, 12/12, 12/13, 12/14 12/16/2, Mhalnge near Balewadi Sport Complex, Tal. Mulshi, Dist. Pune 53.46 Crs. 1st Operate RO(HQ) 53 to 58 6 M/s Shreeniwas Westside County, Darode Jog Builders Pvt Ltd S. No. 72/1A+ 72/3, Pimple Gurav, Tal-Haveli, Dist-Pune. 103.10 Crs. 1st Operate RO(HQ) 59 to 64 7 M/s. Dorf Ketal Chemicals (I) Pvt. Ltd.,W- 165(B), 166(B), 167(B),J-10/2 & 3 & J-13, MIDC Taloja, Dist. Raigad 57.00 Crs. Renewal of two consent with amalgamation & increased C.I. AS(T) 65 to 81 8 M/s. Dr. Acharya Laboratories Pvt. Ltd., Plot No.N-42, MIDC Addl., Ambernath, Dist. Thane 31.83 Crs. 1st Operate AS(T) 82 to 90 9 M/s. VVF Ltd., Opp. Sion Fort Garden, Plot No. 109, 19B, Sion (E), Mumbai 48.22 Crs. Renewal AS(T) 91 to 101 List of Cases to be submitted before 1st Consent Committee Meeting (Part-I) of 2013 scheduled on 05.04.2013 at 15:00 Hrs. Resubmitted Agenda Fresh Agenda

List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

Embed Size (px)

Citation preview

Page 1: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

Sr. No. Name & Address Capital

Investment Applied

For Section Page No. Remarks

1 M/s. WCL Patansaongi Expansion Underground Mine, Vill- Patansaongi, Tal-Saoner, Dist - Nagpur

34.89 Crs Renewal with amalgamation

JD(APC) 1 to 17

1 M/s. Mont Vert Associates,S. No. 239(p), CTS No. 725 to 742,945, 956, 957, Wakad, Mulshi

111.79 Crs. Renewal RO(HQ) 18 to 25

2 M/s. Pulse Mall Maintenance LLP, S. No. 206. A/1. Plot No. 88/4, Next to Aagrkhan Palace, Pune-Nagar Road, Pune

109.50 Crs. Renewal RO(HQ) 26 to 33

3 M/s. Shri Balaji Society, Survey No. 55/2-7, Tathwade, Opp. Mumbai-Bangalore Bypass, Pune

95.96 Crs. Establish RO(HQ) 34 to 43

4 M/s. Sai Essen Properties, Gut No. 1169, 1170, NearSane Chowk, Akurdi-Chikhali Road, Pune

65.00 Crs. Establish RO(HQ) 44 to 52

5 M/s. Puranik Buildcon Pvt. Ltd., ALDEA ESPANOLA, S.No. 12/3, 12/4, 12/5, 12/5/1, 12/12, 12/13, 12/14 12/16/2, Mhalnge near Balewadi Sport Complex, Tal. Mulshi, Dist. Pune

53.46 Crs. 1st Operate RO(HQ) 53 to 58

6 M/s Shreeniwas Westside County, Darode Jog Builders Pvt Ltd S. No. 72/1A+ 72/3, Pimple Gurav, Tal-Haveli, Dist-Pune.

103.10 Crs. 1st Operate RO(HQ) 59 to 64

7 M/s. Dorf Ketal Chemicals (I) Pvt. Ltd.,W-165(B), 166(B), 167(B),J-10/2 & 3 & J-13, MIDC Taloja, Dist. Raigad

57.00 Crs. Renewal of two consent with

amalgamation & increased

C.I.

AS(T) 65 to 81

8 M/s. Dr. Acharya Laboratories Pvt. Ltd.,Plot No.N-42, MIDC Addl., Ambernath, Dist. Thane

31.83 Crs. 1st Operate AS(T) 82 to 90

9 M/s. VVF Ltd., Opp. Sion Fort Garden, Plot No. 109, 19B, Sion (E), Mumbai

48.22 Crs. Renewal AS(T) 91 to 101

List of Cases to be submitted before 1st Consent Committee Meeting (Part-I) of 2013 scheduled on 05.04.2013 at 15:00 Hrs.

Resubmitted Agenda

Fresh Agenda

Page 2: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

10 M/s. Mastek Ltd., (IT Software Development Activity)Mastek Millenium Centre, Plot No. A-7, Millenium Business Park, Sector 1, Off Thane Belapur Road, Mahape Navi Mumbai

107.04 Crs. Renewal RO(HQ) 102 to 120

11 M/s. Mastek Ltd., (IT Software Development Activity)New Development Centre, Plot No. 136,136/1, Millenium Business Park, Sector 1, Off Thane Belapur Road, Mahape, Navi Mumbai.

61.15 Crs. Renewal RO(HQ) 121 to 141

12 M/s. Varieties Builders and Tustees Pvt. Ltd., Authorised tustee of Gold Cest Reality Trust, Plot No. 43/1, 43/2, 44/2, S. No. 199, 204, 205, 206/1, 209/1, Lohgaon, Viman Nagar, Pune

36.61 Crs. Renewal RO(HQ) 142 to 153

13 M/s. Shweta Infra & Housing (I) Pvt. Ltd., S. No. 44, Andhavali, Nashik

83.77 Crs. Establish RO(HQ) 154 to 160

14 M/s. Ivory Properties & Hotels Pvt. Ltd., Prism Tower, Bldg no.4, (Wing A&B), CTS no. 41406A/28 A, Vill Malad(S), Mindspace Layout, Mumbai-64.

25.23 Establish & Operate

RO(HQ) 161 to 170

15 M/s. Marathon Realty Pvt. Ltd., Marathon Futurex (commercial Building), CS no. 166, Lower Parel Division, Mumbai.

294.53 first Operate (part)

RO(HQ) 171 to 183

16 M/s. Jayaswal Neco Industries Ltd., (ECD), Plot No. T-41/42, MIDC Hingna, Dist - Nagpur

50.58 Crs operate for expansion and

renewal

JD(APC) 184 to 200

17 M/s. MMP Industreis Ltd., (formerlyknown as M/s. Maharashtra Metal Powders Ltd., Vill- Maregaon, Po- Shajpur, Tal & Dist - Bhandara

28.74 Crs Renewal with amalgamation

JD(APC) 201 to 212

18 M/s. Menon Piston Rings Pvt. Ltd., (Expansion), 197/A, Sambhapur-Kasarwadi Wadi, Top, Tal- Hatkanangale, Dist - Kolhapur

39.89 Crs operate for expansion

JD(APC) 213 to 219

19 M/s. Menon Bearings Ltd., MIDC Gokul Shirgaon, Tal- Karveer, Dist - Kolhapur

31.95 Crs Renewal JD(APC) 220 to 226

20 M/s. HSBC Software Development India Pvt. Ltd., 25A Raheja woods, Riverside, Kalyaninagar, Pune.

46.64 Crs. Renewal RO(HQ) 227 to 235

21 M/s. HSBC Software Development India Pvt. Ltd., 25B Raheja woods, Riverside, Kalyaninagar, Pune.

46.64 Crs. Renewal RO(HQ) 236 to 246

Review Item

Page 3: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

1 AS(T) 247 to 271

JD(WPC) 0AS(T) 4RO(HQ) 14JD(APC) 5Total 23

M/s. Inventys Research Company Pvt. Ltd., Plot No. K-38, MIDC Butibori, Dist. Nagpur

Page 4: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    1 

 

PART-I CC-Resubmission Agenda no. 1 Name of the Industry: M/s. WCL Patansaongi Expansion Underground Mine,

Vill: Patansaongi Tal: Saoner Dist: Nagpur

• Applied for consent to Operate for expansion from 0.25 MTPA to 0.3 MTPA

• Existing unit consent for production of coal 0.23 MTPA was valid up to 31.5.2011.

• Inspite of repeated reminders SRO Nagpur/RO Nagpur has not submitted the requisite

information about the compliance of Consent conditions, EC conditions, results and

other details. In view of non-receipt of information we may issue show cause notice for

refusal of consent.

• Earlier the case was discussed in C.C. meeting held on 18.01.2013 and it was decided to keep the case in abeyance till information received from R.O. /SRO, Nagpur-I. SRO. Nagpur-I vide letter dated 16.03.2013 has submitted the report and recommended renewal of consent with amalgamation of Consent to Operate expansion.

• In view of above and R.R.Z. satisfaction, we may grant Consent to Operate for 0.3 MT/A capacity for period up to 31.05.2014 with Operational Bank Guarantee of Rs.5/- lakhs.

 

Page 5: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    2 

 

CC-Fresh Agenda

Agenda no. 1

Name of the Applicant: M/s.Mont Vert Associates,

S.No.239(p),CTS No.725 to 742,

945,956,957,Wakad,Mulshi

• Application for Renewal of Consent for Residential Project for,

Total Plot Area :38,996.55 Sq.mtrs. Total Construction BUA :38,983.55 Sq.mtrs.

• Application received at SRO, Pune, dt: 30/08/2012 and at HQ on dt: 18/12/2012.

• Applicant has obtained EC from GOI Dated 28/9/2007

Total Plot Area :38,996.55 Sq.mtrs. Total Construction BUA :38,983.55 Sq.mtrs.

• Board has issued C to O for same which valid upto 30/4/2012

Total Plot Area :38,996.55 Sq.mtrs. Total Construction BUA :38,983.55 Sq.mtrs.

• Letter issued to RO Pune/Applicant for submission details information dated 28/1/2013 but reply is awaited from applicant.

• We may place the application in CC for further decision. 

 

 

 

 

 

Page 6: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    3 

 

Agenda no. 2 Name of the Applicant:

M/s.Pulse Mall Maintainace LLP, S.No.206 A/1,Plot No.88/4, Next to Aagrkhan Palace, Pune-Nagar Road,Pune-411 006

• Application for C to Renewal for Retail Mall Project in name of M/s.Pulse Mall Maintainace LLP for, Total Plot Area :16,916.49 Sq.mtrs. Total Construction BUA :19,463.35 Sq.mtrs.

• Application received at SRO, Pune, dt: 18/10/2012 and at HQ on dt: 23/11/2012.

• Applicant has obtained EC from GOI Dated 24/7/2007 in name of ISTA Hotel & Mall

Total Plot Area :25,168.26 Sq.mtrs. Total Construction BUA :32,668.57 Sq.mtrs

• Board has issued C to O for same which valid upto 31/5/2012 in name of M/s.G-Corp Properties Pvt. Ltd. Total Plot Area :16,916.49 Sq.mtrs. Total Construction BUA :19,463.35 Sq.mtrs.

• Letter issued to RO Pune/Applicant for submission details information dated 3/12/2012 but reply is awaited from applicant.

• RO recommended Renewal of Consent for change in name for period upto 31/5/2014.

• We may place the application in CC for further decision. 

              

Page 7: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    4 

 

 

Agenda no. 3 Name of the Applicant:

M/s. Shri Balaji Society. Survey no- 55/2-7, Tathwade, Opp. Mumbai- Benglore Bypass, Pune-411033.

Application received for grant of Consent to Establish for group Housing Project. Total plot Area – 50385.90 sq.M, Total construction BUA-29140.10 Sq.M. Application received at RO, Pune, dt: 11/06/2012 and at HQ on 27/09/2012.

Applicant has submitted Undertaking stating project cost is Rs. 95.96Cr. Total Bio- degradable waste generation -160.87 Kg/Day. Total non- Biodegradable

waste-generation-143.04 Kg/dat. STP sludge-53.64 Kg/day. Septic tank followed by gravity sand filtration & activated carbon filtration system &

chemical disinfection system is provided. Treated sewage partly used for plantation in

premises & excess disposed into PCMC drainage system. PP has not obtained EC & some of the construction work is completed without

Board’s consent (N-6). Board has called information from RO Pune vide letter dated-31/10/2012.

RO/SRO-Pune Since the project is not having EC & some of the construction work is

completed without Boards consent. Decision for grant of consent may be taken at higher

level. Recommendation of HQ- May be considered with B.G as per protocol. 

 

Page 8: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    5 

 

Agenda no. 4 Name of the Applicant:

M/s. Sai Essen Properties. Gut no. 1169, 1170, Near Sane Chowk, Akurdi-Chikhali Road, Pune

Applied for Consent to establish for residential cum commercial Project.

Total plot Area – 45800.0 sq.M, Total permissible Area 58938 Sq.M, Proposed BUA-58936.38 Sq.M.(C-25) .

C.I of the project-Rs.65.0 Cr Not obtained E.C. Bio-Degradable waste generation- 1507.14 Kg/day will be disposed by composting. Non- Bio

degradable waste generation-1004.76 Kg/Day will be disposed by sale. Proposed STP of capacity 678.0 CMD comprising of Primary, Secondary & Tertiary treatment PP has started construction work before obtaining EC. Board has issued Directions u/s-33A dated-26/12/2012 (C-27). RO- Pune- Decision regarding grant of consent to establish may be taken at HQ level.

Recommendation of HQ- Distance of River needs to be verified since 1.0 Km is mentioned. 

 

Page 9: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    6 

 

Agenda no. 5 Name of Industry:  M/s. Puranik Buildcon Pvt. Ltd., ALDEA ESPANOLA, S.No.

12/3, 12/4,12/5,12/5/1, 12/12, 12/13, 12/14, 12/15, 12/16/2, Mhalunge near Balewadi Sport Complex, Village-Mhalunge,Tal-Mulshi, Dist: Pune

1. Application for consent to 1st Operate.

2. Application received at SRO on 04/01/2013 at HQ on 20/02/2013

3. Applied for;

Plot area - 18,240.00 Sq. mtrs.

Total Built up Area – 32894.12Sq. Mtrs.

4. Water Balance in CMD

Water consumption 203

Sewage generation 183

STP Provided 200

5. Solid Waste generation details kg/D.

Bio degradable 473

Non Bio degradable 203

Vermicomposting facility provided.

6. RO has recommended the case for 1st operate subject to condition of obtaining BG

7. The consent may be granted with BG of Rs. 10 lacs for O & M of STP and MSW processing plant.

Page 10: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    7 

 

Agenda no. 6 Name of Industry:      M/s. Shreeniwas Westside County.

M/s. Darode Jog Builders Pvt. Ltd.

S. No. 72/1A + 72/3, Plimplae Gurav,

Tal. Haveli, Dist. Pune

1. Application for consent to 1st Operate.

2. Application received at SRO on 13/12/2012 at HQ on 23/01/2013

3. Applied for;

Total Plot Area - 18,240.00 M2

Total BUA - 50,041.00 M2

4. Water Balance in CMD

Water consumption 327

Sewage generation 285

STP Provided STP of 325 CMD capacity.

5. Solid Waste generation details kg/D.

Bio degradable 640

Non Bio degradable 317

STP sludge 080

Treatment facility not provided.

6. SRO has reported that decision for grant of consent to 1st Operate may be taken at HQ level.

7. The consent may be granted with BG of Rs. 10 lacs for O & M of STP and for provision of MSW processing plant within three months period.

Page 11: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    8 

 

Agenda no. 7 Name of Industry:

M/s. Dorf Ketal Chemicals (I) Pvt Ltd.

W-165 (B), 166(B), 167 (B), J-10/2 & 3 & J-13, MIDC, Taloja, Dist-Raigad

1. Application received at RO Pune on 03/01/2013 and at HQ on 24/1/2013

2. Industry engaged in mfg Chemicals.

3. Existing both consent were valid up to 31.12.2012.

4. Applied for renewal of both consents with amalgamation & increased CI.

5. IE:68.1, DE: 17.6 CMD.

6. Unit provided full-fledged ETP comprising primary, secondary and tertiary system.

Disposal: CETP.

7. JVS reports are sometime exceeds the consented limits.

8. CI increased due to replacement of old plant machineries & infrastructure.

9. RO NM has issued ID on 26.11.2012 with conditions.

10. Industry has commissioned of RO system, submitted BG of Rs 1 lakhs and the entire

trade effluent should be recycled and CETP disposal is kept option as standby.

11. Industry submitted HW return in Form IV, Env Statement.

12. Industry submitted reply along with required details about plant establish on plot No J-

10/3 & J-11, viz C to E date, Balance sheet, CA certificate. (copy attached)

13. RO Navi Mumbai has recommended for grant of renewal of consent by amalgamating both the consents with change in CI.

o The proponent has two consents on same plot i.e J10/2 and J-11, needs clarification from RO

o Similarly justification about the points raised on NS/15 to be called from industry/RO.

We may consider the case for renewal by amalgamation of both the consents with change in CI by forfeiting existing BG of Rs 1 lakhs and imposing fresh BG of Rs 2 lakhs towards O & M of ETP.

Page 12: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    9 

 

Agenda no. 8 Name of Industry: - M/s. Dr. Acharya Laboratories Pvt. Ltd.

Plot No. N-42, MIDC Addl. Ambernath,

Dist. Thane.

1. Application for 1st Consent to Operate 2. Product- API & Speciality Chemicals. C to E granted on 28/09/2010 which is

valid up to COU. 3. Application received at SRO on 17/02/2013 and at HQ on 18/03/2013 4. Industry has obtain C to E vide letter dtd. 28.09.2010 with EC condition. Industry

proposes to manufacture API and Speciality chemicals. 5. IE generation is 92 m3/d. Industry has provided primary, secondary and tertiary

treatment. Industry is a member of CETP & CHWTSDF. 6. Industry has provided Scrubbers to control process emissions. 7. SEIAA accorded approval for grant of EC in 55th meeting dated 21 and 22

January 2013. However actual EC is not granted yet. 8. As per C to E CI was Rs. 13.99 Crore Now applied with CI of RS. 31.13 Crore. It

is new entry to CC list.

In view of above, we may consider 1st Consent to Operate subject to submission of EC.

Page 13: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    10 

 

Agenda no. 9 Name of Industry: M/s VVF Ltd, Opp Sion Fort Garden, Plot No.109, 19B, Sion E, Mumbai-

22

• Application received at Mumbai on 13/06/2012

• Application received at HQ on 21/02/2013.

• Industry is engaged in manufacturing of Fatty acid, Stearic acid & Glycerin & Toilet soaps holding consent valid up to 31/12/2011.

• Applied for renewal.

• I.E generation has reduced from 32.5 to 20 CMD. ETP consisting of primary, secondary

& tertiary treatment. JVS results are within limit. Disposal to MCGM sewerage system

• D.E generation has reduced from 45 to 25 CMD. Septic tank provided.

• Natural gas consumption has reduced from 42000 to 15000 SCM /day. LSHS and FO are used in case Natural gas is not available.

• Out of consented 4 Boilers & 4 Thermic fluid heaters, only one boiler & one thermic fluid heater are running. Others boilers & thermic fluid are not in use & removed from site.

• Industry is a member of MWML, CHWTSDF at Taloja.

• Annual Returns of Hazardous waste submitted for the period April 11- March 12.

• RO has recommended for renewal of consent for the period up to 31/12/2016

We may recommend for renewal of Consent valid upto the period 31/12/2016.

Page 14: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    11 

 

Agenda no. 10 Name of Industry M/s.Mastek Ltd., (IT Software Development Activity) Mastek Millenium Centre Plot No.A-7,Millenium Business Park,Sector 1,offThane Belapur Road, Mhape,Navi Mumbai

• Application for Renewal of Consent for construction of (IT Software Development Activity)for,

Total Plot Area - 2,05,577.51 Sq.mtrs. Permissible Built Up Area - 1,56,790.55 Sq.mtrs

• Application Received at SRO Navi Mumbai on 16/7/2012 and at HQ on 19/11/2012.

• Board has issued C to O Dated 23/10/2008 which is valid upto 31/3/2012 and having

C.I.19.63 Cr and total plot Area and Construction BUA is not mentioned in the consent.

• Hence letter issued to RO Dated 23/11/2012 for submission of 1)Area Statement. 2)Visit Report. 3)Justification regarding increased C.I. from Applicant along with CA Certificate. 4)Solid Waste details/WPC/APC Details. 5)Copy of Commencement Certificate.

• RO has submitted reply which is received in HQ Dated 2/3/2013(Copy attached) 1)Area Statement. 2)Commencement and occupation Certificate not submitted by Applicant. 3)Justification of increased C.I. (Copy of Applicant letter regarding justification is

attached)

• RO has submitted reply along with above details, which is received in HQ Dated 2/3/2013.

• We place the place the Application in CC Meeting for further decision.

 

 

Page 15: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    12 

 

Agenda no. 11  

Name of Industry M/s.Mastek Ltd., (IT Software Development Activity) New Development Centre, Plot No.136,136/1,Millenium Business Park,Sector 1,offThane Belapur Road Mhape,Navi Mumbai

• Application for Renewal of Consent for construction of (IT Software Development Activity)for, Total Plot Area - 5366.00 Sq.mtrs. Total Construction Built Up Area - 10,715.93.25 Sq.mtrs.

• Application Received at SRO Navi Mumbai on 29/6/2012 and at HQ on 19/11/2012.

• Board has issued C to O Dated 13/11/2008 which is valid upto 31/3/2012 and having

C.I.34.21 Cr and total plot Area and Construction BUA is not mentioned in the consent.

• Accordingly, letter issued to RO Dated 23/11/2012 for submission of 1)Area Statement. 2)Visit Report. 3)Justification regarding increased C.I.from 34.21Cr to 61.15 Cr from Applicant along with CA Certificate. 4)Solid Waste details/WPC/APC Details. 5)Copy of Commencement Certificate.

• RO has submitted reply along with above details, which is received in HQ Dated

2/3/2013.

• We place the place the Application in CC Meeting for further decision.

 

 

 

 

 

Page 16: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    13 

 

Agenda no. 12 Name of Industry Varieties Builders and Tustees Pvt. Ltd. ,

Authoised tustee of Gold Cest Reality Trust,

Plot No. 43/1, 43/2 44/2, S. No. 199, 204,

205, 206/1, 209/1, Lohgaon, Viman Nagar, Pune 411014

• Application for Renewal of Consent for Total Built Up Area 6073.92 Sq.Mtrs

• Application Received at SRO Pune 29/8/2012 and at HQ on 18/10/2012.

• Water Consumption-52CMD Sewage Geneation-44 CMD

No STP Provided.

• Previous consent was valid upto 31/3/2012.

• RO Pune issued amendment in the existing consent dated 27/12/2010 in which mentioned that Applicant has submitted the papers regarding sewage Connection to PMC Sewer line alongwith drainage charges receipt. This indicates that PMC has no objection for treating the sewage from said IT Park to their STP. The said IT Park has been installed in 2004. ie.prior to enforcement of the policy hence wave the condition No.12 ie.to install and commission of STP.

• Hazardous Waste:E-Waste and used oil send to Authorized dealer.

• Industry has paid consent with delay charges,

• RO Pune recommended Renewal of Consent with condition to install STP within time period.

• We may place the application in CC for further decision.

Page 17: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    14 

 

Agenda no. 13 Name of the Applicant M/s.Shewta Infra & Housing (I) Pvt. Ltd.,

S.No.44,Andhavali,Nashik

• Application for C to Renewal for Retail Mall Project in name of M/s.Pulse Mall

Maintainace LLP for, Total Plot Area :16,916.49 Sq.mtrs. Total Construction BUA :19,463.35 Sq.mtrs.

• Application received at SRO, Pune, dt: 18/10/2012 and at HQ on dt: 23/11/2012.

• Applicant has obtained EC from GOI Dated 24/7/2007 in name of ISTA Hotel & Mall

Total Plot Area :25,168.26 Sq.mtrs. Total Construction BUA :32,668.57 Sq.mtrs

• Board has issued C to O for same which valid upto 31/5/2012 in name of M/s.G-Corp Properties Pvt. Ltd. Total Plot Area :16,916.49 Sq.mtrs. Total Construction BUA :19,463.35 Sq.mtrs.

• Letter issued to RO Pune/Applicant for submission details information dated 3/12/2012 but reply is awaited from applicant.

• RO recommended Renewal of Consent for change in name for period upto 31/5/2014.

• We may place the application in CC for further decision. 

 

 

Page 18: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    15 

 

Agenda no. 14 Name of the Applicant:

M/s.Ivory Properties and Hotels Pvt. Ltd., Bldg.No.3 being a part of larger land bearing CTS No.1406 A/28 A,Village:Malad(S),Mumbai:64 Remarks:

• Application for C to Establish & Operate for construction of Commercial Mall Building for,

Built Up Area for Bldg. No.3(As per FSI)-11,608.85 Sq.mtrs. Total plot Area is not mentioned.

• Application received at RO, Mumbai, dt: 10/1/2013 and at HQ on dt: 28/1/2013

• Applicant has obtained Commencement Certificate dated 11/4/1996 and Occupation Certificate dated 16/3/2006.

• RO Recommended C to Operate for period upto 31/12/2016 and Applicant has

submitted C to E & C to O Fee.

• We may place the application in CC for further decision.  

 

Page 19: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    16 

 

Agenda no. 15 Name of Industry M/s. Marathon Realty Pvt. LTD., Marathon Futurex(Commercial Building), CS No.166,Lower Parel Division,Mumbai HOD Remarks:

• Application for Consent to Operate for Construction IT Park M/s.Marathon Reality Pvt.Ltd for, Total Plot Area - 27,163.00 Sq.mtrs. Total Construction Built Up Area -44,355.97 Sq.mtrs.

• Application Received at SRO Mumbai on 20/11/2012 and at HQ on 4/12/2012.

• Board has granted C to E in name of M/s.Maftlal Industries Ltd dated 5/4/2006 (C-62)for Total Plot Area - 27,163.00 Sq.mtrs.

• Application has obtained EC from GOI dated 16/10/2006 in name of M/s.Mafatlal Industries Ltd Total Plot Area - 27,163.38 Sq.mtrs. Total Construction Built Up Area – 44,355.97 Sq.mtrs.

• Letter issued letter to applicant dated 7/12/2012 regarding submission of 1)Area Statement. 2)Visit Report with present construction status. 3)Approved Map.

• SRO Mumbai has submitted above details which is received in HQ Dated 18/2/2013,in which SRO Reported Area statement that Total Plot Area - 27,163.00 Sq.mtrs. Total Permissible BUA - 44,370.38 Sq.mtrs Total Construction Area upto 26th Floor-1,25,525.08 Sq.Mtrs.

• SRO Reported that project proponent has completed 3 basement, ground floor,1to 7 floor Parking,8th to 23rd floors are completed and 24th floor is in progress. project proponent has obtained MCGM approval upto 25th floor. Project proponent has occupied 70% of 8th floor and 10% of 10th floor from last 6 month.EC obtained for BUA of 44,355.97 Sq.mtrs.

• Applicant has applied for C to Operate in name of M/s.Marathon Reality Ltd but Applicant has

obtained EC and C to E in name of Mafatlal Industry Ltd SRO Mumbai has submitted Copy of ‘SALE DEED’ between M/s. Mafatlal Industry Ltd and M/s.Marathon Reality Ltd and PhotoCopy of PROPERTY CARD which showing property transfer in them

• We place the place the Application in CC Meeting for further decision.

 

Page 20: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    17 

 

Agenda no. 16 Name of the Industry: M/s. Jayaswal Neco Industries Ltd. (ECD),

Plot No.T-41/42, MIDC Hingna, Dist: Nagpur.

• Applied for consent to Operate for expansion and renewal of consent of existing unit (amalgamation).  

• Rs.50.58 Crores. (Capital investment of the existing unit is Rs.32.70 Croes and expansion project is Rs.17.88 Crores).

• Existing unit consent was valid up to 28.2.2013. Obtained consent to establish for Expansion .

• Wet scrubber provided to cupola furnace and dust collector provided to induction furnace.

• Analysis results of AAQM and stack are exceeding the standards.

We may grant renewal of consent with expansion for period up to 31.12.2013 with the Bank Guarantee of Rs.5/- Lakhs.

Page 21: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    18 

 

Agenda no. 17 Name of the Industry: M/s. MMP Industries Ltd.,

(Formerly known as M/s. Maharashtra Metal Powders Ltd.),

Vill: Maregaon, Post: Shajpur, Tal & Dist.: Bhandara.

• Applied for renewal of consent with amalgamation and additional products.

• Capital investment of the industry is Rs.28.74 Crores.

• Existing unit consent for production of Alluminium Power and Nitrogen Gas was valid up to

31.12.2012

2 AAQM results out of 9 are exceeding the standards. As mentioned by SRO that they

have provided necessary pollution control system.

In view of above, we may grant renewal up to 31.12.2013 with operational Bank Guarantee of

Rs.3/- Lakhs towards O & M of pollution control system.

Page 22: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    19 

 

Agenda no. 18 Name of the industry: - M/s. Menon Piston Rings Pvt. Ltd., (Expansion),         197/A, Sambhapur‐Kasarwadi Road,         Top‐ Tal‐ Hatkanangale, Dist ‐ Kolhapur

• Case for consent to operate for expansion, existing consent is valid upto 31/12/2013, which is granted on 23/02/2012 for CI casting 30 MT/M. Expansion is CI Casting 1000 MT/M.

• CI for expansion is Rs.10 Crs and existing is Rs.29.89 Crs.

• Existing furnace is provided with dust collector, new furnace not provided with APC. Hence, SRO recommended refusal of consent. Now this office is in receipt of e-mail dated 27/02/2013 from SRO kolhapur and reported that the industry have installed the fume extraction system followed by cyclone dust collector to the furnace.

• Now we may consider grant of consent to operate for expansion with amalgamation of existing consent upto 31/12/2013 with condition of board resolution & BG of Rs.2/- Lakhs as O & M.

• We may place the consent application before CC for further consideration.

Page 23: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    20 

 

Agenda no. 19 Name of the industry: - M/s. Menon Bearings Ltd.,         MIDC Gokul Shirgaon, Tal‐ Karveer, 

Kolhapur.

• Case for renewal of consent. No change in product and its quantities.

• CI is Rs.39.95 Crs and existing CI was Rs.23.04 Crs the increase of Rs.8.11 Crs is due to installation of copper stripping furnace, modernization and modification in plant and replacing existing ETP.

• Provided ETP and JVS results are within limit.

• Provided cyclone dust collector to sandling unit, scrubber to LTC plating section ,dust collector to aluminum and copper melting furnace.

• Complied with PD issued by RO. Existing BG of Rs. 5/- Lakhs is valid upto 25/05/2013.

• Cess paid upto July, 2011 and returns filed upto Nov- 2012. Submitted Environmental statement for the year 2011-12.

• SRO recommended grant of consent upto 31/12/2014.

• We may place the consent application before CC for further consideration.

Page 24: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    21 

 

Agenda no. 20 Name of the Applicant:

M/s.HSBC Software Development India Pvt.Ltd., 25 A Raheja woods,Riverside,Kalyaninagar Pune

• Application for Plain Renewal of Consent for IT & ITES Activity for Total Construction Built Up Area-1,77,715 Sq.mtrs.

• Application received at RO, Mumbai, dt: 12/01/2012 and at HQ on dt: 12/10/2012.

• Previous Consent was valid upto 31/3/2010 for Total Construction Built Up Area-1,77,715 Sq.mtrs.

• SRO Recommended Renewal of Consent subject to provision of STP .

• We may Place the application in CC for further decision.

 

Page 25: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    22 

 

Agenda no. 21 Name of the Applicant:

M/s.HSBC Software Development India Pvt.Ltd., 25 B Raheja woods,Riverside,Kalyaninagar Pune

• Application for Plain Renewal of Consent for IT & ITES Activity for Total Construction Built Up Area-1,04,823 Sq.mtrs.

• Application received at RO, Pune, dt: 4/02/2012 and at HQ on dt: 12/10/2012.

• Previous Consent was valid upto 31/3/2010 for Total Construction Built Up Area- 1,04,823 Sq.mtrs.

• Said project is 0.20 Km from Mula-Mutha River and SRO Reported that applicability of RRZ Policy may be decided at Higher level.

• SRO Recommended Renewal of Consent for period upto 31/3/2014.

• We may Place the application in CC for further decision.

 

 

   

 

 

 

 

 

 

 

 

 

Page 26: List of Cases to be submitted before 1st Consent …mpcb.gov.in/consentappraisal/pdf/CCmeetingagenda...Sr. No. Name & Address Capital Investment Applied For Section Page No. Remarks

 

Web agenda of Part‐I of 1st CC meeting of 2013‐14 dtd 05.04.2013    23 

 

 

CC-REVIEW ITEM

Name of Industry: M/s. Inventys Research Company Pvt Ltd,

Plot no- K-38, MIDC Butibori,

Dist-Nagpur.

1. Application for Amendment in Consent with increase in C.I for GMP.(Good

Manufacturing Practice)

2. Existing consent is valid upto-31/07/2013 for manufacturing of s-Methyl phenyl Glycine

Metyl Ester & By product-s-Methyl 5-Phenyl imidazolidine 2, 4 Dione.

3. Application received at SRO on 15/09/2012 and at HQ on 20/11/2012.

4. Industry was issued SCN for operating the industry without E.C.

5. Industry replied that the previous consent was issued for products which are basically

synthetic amino acids & thus comes under the category of specialty chemicals and thus

IIT Mumbai has given certificate of non-applicability of E.C.

6. Industry now has requested that if E.C is applicable, they will get the same for which 12

to 18 months period is required. Hence requested not to take any action against the

industry till then.

7. The case was submitted before committee dtd-18/01/2013 for taking suitable decision

about grant of consent as proposed by the proponent.

8. The Consent Committee decided to refer the case to Law & Policy division. (Minutes of

meeting enclosed).

9. Accordingly the case was referred to Law & Policy division.

10. In reply to the letter dtd-18/02/2013 from Law & Policy division, industry submitted the

copy of certificate issued by IIT Mumbai, along with their explanation saying that their

unit does not fall under Schedule 5 of the EIA Notification, 2006. (Copy enclosed).

11. As per the approval of Member Secretary of the Board, it was decided to call the industry

representative before Consent Committee for presentation and decision in the matter.

12. Submitted for further decision.