Upload
shashank11
View
222
Download
0
Embed Size (px)
Citation preview
7/30/2019 Line Arresters. 2012
1/45
Line Arrester Applications
International Conference cum Tutorial on HV SA Technology & ApplicationsNew Delhi, 26th November, 2012Bengt Johnnerfelt
26th November 2012
7/30/2019 Line Arresters. 2012
2/45
26th November 2012
Why Line Arresters?
Lightning has been reported as the
main cause of non-scheduled
outages on overhead sub-transmission and transmission lines
United States: 57%
Brazil: 50 70% Japan: 70 80%
Denmark: 57%
Colombia: 47 69%
Lightning is the most frequent cause
of transmission outage and service
interruption in the United States,accounting for about 30% of all
power outages, and resulting in
economic losses approaching $1billion annually http://www.epri.com
http://www.epri.com/http://www.epri.com/7/30/2019 Line Arresters. 2012
3/45
Flashover due to Lightning on Transmission Lines
Lightning may cause flashover of line insulators in three different ways:
1.Strikes to shield wires or towers
2.Direct strikes to the phase conductors
Shielding failure
Unshielded lines
3.Flashovers due to induced voltages
Rarely exceeding 300kV
Limited to distribution andsub-transmission lines
26th November 2012
7/30/2019 Line Arresters. 2012
4/45
26th November 2012
Shielded lines Back Flashover
Current is typically shared between several towers and arresters
Current travels from the tower to the phase conductor.
7/30/2019 Line Arresters. 2012
5/45
Shielded lines Back Flashover Criteria
VISi(t) Transient voltage on the insulators strings (kV)
Vcrossarmi(t) Transient voltage on the cross arms (kV)
Vinduced(t) Induced voltages (kV)VPFi Power frequency voltage (kV)
( ) ( ) ( )[ ]iii PFinducedicrossarmIS
VtVtVtV
( ) ( )tVtVithstinsulatorwISi .
Flashover when:
26th November 2012
7/30/2019 Line Arresters. 2012
6/4526th November 2012
Shielded Lines - Shielding FailureUnshielded Lines
Shielding failure low current amplitudesUnshielded lines nearly all strikes leadto flashovers.
Current travels from phase conductor tothe tower.
( ) ( )tVtVithstinsulatorwISi .
7/30/2019 Line Arresters. 2012
7/45
Parameters Effecting Risk of Lightning Flashovers
Ground flash density; Transient tower footing resistance and transient response of the
tower;
Lightning current amplitude; The electromagnetic coupling among shield wires and phase
conductors;
The effect of the adjacent towers and their footing resistances;
26th November 2012
Lightning strike: two traveling waves of= Z (Example: = 350 20 kA = 3.5 MV)
7/30/2019 Line Arresters. 2012
8/4526th November 2012
Probability of Lightning Currents CIGRE Data
( )
+
=6.2
311
1
I
IIPd
7/30/2019 Line Arresters. 2012
9/4526th November 2012
Shielded Lines Effect of Grounding System
Transmission line lightning performance depends strongly on the
transient grounding system response.
7/30/2019 Line Arresters. 2012
10/45
Procedures to Improve the Transmission LinesLightning Performance
Increase the line insulation;
Improvement in the grounding system;
Shield wire application on unshielded lines or improvement of the
shielding angle for shielded lines;
Line Arrester (LA)
Externally Gapped Line Arresters - EGLA
Non-Gapped Line Arresters - NGLA (TLA)
26th November 2012
7/30/2019 Line Arresters. 2012
11/45
Purpose of the Installed LA
Protection againstfast front (lightning)overvoltages only.
Protection against allovervoltages including
slow front (switching) andfast front (lightning)overvoltages.
or5000 s T1 20 s
T1/T2 = 250/2500 s
20 s T1 0.1 s
T1/T2 = 1.2/50 s
26th November 2012
7/30/2019 Line Arresters. 2012
12/45
Line Arrester Applications
Protecting line insulators from flashovers - reduced systeminterruption caused by lightning, improving system reliability;
Protecting line insulators from flashovers substitute for shield wires
Control switching surges along the lines substitutes for reclosing
resistors;
Extended substation protection - lowering/better protection of the BIL
levels in substations;
Upgrading system voltages with existing line insulation compact
insulation lines;
26th November 2012
7/30/2019 Line Arresters. 2012
13/45
History of Line Arresters
Distribution line arresters
First installation of distribution line arresters in 1975 (Japan, 33 kV)
Today several tens of millions of distribution line arresters assumedlyin service
Transmission line arresters
First installation of transmission line arresters around 1980 (Japan,66 kV, 77 kV and 138 kV)
Today huge quantities of transmission line arresters in service
7/30/2019 Line Arresters. 2012
14/45
Line Arrester Designs
There are two basic designs;1. NGLA, non gapped line arresters, often called TLA (transmission line
arresters):
Can take higher energies & switching. Can be used on unshielded lines;
Can be used instead of reclosing resistors;
Need disconnector to facilitate fast reclosing;
After disconnector operation possible swaying of the ground lead must be
considered;
2. EGLA, externally gapped line arresters:
Shorter (& lighter) than NGLA. No COV or creepage requirements;
Fast reclosing possible without disconnector;
Difficult to find overloaded/failed EGLA in the field;
Cannot handle switching surges or TOV, only used on shielded lines;
Coordination of the spark gap;
26th November 2012
7/30/2019 Line Arresters. 2012
15/45
26th November 2012
NGLA basic configuration for 245 kV system
7/30/2019 Line Arresters. 2012
16/45
Typical EGLA Design IEC 60099-8
26th November 2012
7/30/2019 Line Arresters. 2012
17/45
Installation of EGLA & NGLA
26th November 2012
EGLANGLA
7/30/2019 Line Arresters. 2012
18/45
Important Factors for Electrical Selection of LA forLI protection on Shielded LinesArrester rating;
Higher than corresponding stationarresters - Avoid switching & TOVstresses.
No need for very low protection levelsas BIL of line insulators is high.
Arrester class;Lower than station arresters.Typically IEC class 2 will work up to245kV systems.
How many and in which phases;Study needed in most cases.LA needed in a few towers on bothsides with normal footing resistanceafter LA installed in towers with highfooting resistance
Desired outage rate
26th November 2012
7/30/2019 Line Arresters. 2012
19/45
Electrical Spark Gap Selection for EGLA
Coordination of sparkover and flashover voltageSound arrester
lightning impulse sparkover voltage
must be lower than insulator's LIflashover voltage
switching impulse sparkover voltagemust be higher than insulator's SI
flashover voltage
Failed arrester
switching impulse sparkovervoltage must be higher thaninsulator's SI flashover voltage
Insulator
f/o voltage
EGLA
s/o voltage
26th November 2012
7/30/2019 Line Arresters. 2012
20/45
Special Pollution Consideration for EGLA
Performance under pollution conditions:
Follow current that partly flows on thepolluted arrester housing must be
safely interrupted special, verycomplicated test in 60099-8
26th November 2012
7/30/2019 Line Arresters. 2012
21/45
Arrester class;
Will see higher energies;
System study needed;
Selected based on the study
result for the desired outage rate;
Lower tower footing resistance not
necessarily good as this may lead
to that all current will be taken bytwo arresters only;
26th November 2012
Important Factors for Electrical Selection ofNGLA on Unshielded Lines
7/30/2019 Line Arresters. 2012
22/45
26th November 2012
Selection of LA System Studies
Several commercial programs available.
Basic Information Required for Modelling TLA for transmission lines:
System voltage
Basic configuration of the line & BIL of line insulators
Tower type, phase-to-earth and phase-to-phase distances, shielded
or unshielded line, phase conductors and shield wire sags, span
length between towers, conductors diameters, etc. Short-circuit currents and temporary overvoltages conditions
Ground Flash Density of the region crossed by the line
Grounding system Existing station arresters electrical data
Suggested LA data
7/30/2019 Line Arresters. 2012
23/45
Installation Issues for Mechanical Selection of NGLA
Disconnector installation;Weakest point of installation.Make room for swinging of the line.Consider lead lengths swaying afterarrester overloading.
Check that operation times fits actualfault clearing times.
Arrester classification;Check short-circuit capability. Is theLA allowed to fall down afteroverloading?
Check mechanical data like vibration.
Installation methods;Hot installation or not.Make sure that the arrester have pivotpoints so that it can move without too
much stresses.
26th November 2012
7/30/2019 Line Arresters. 2012
24/45
Installation Issues for Mechanical Selection of EGLA
Gap installation;Most critical point of installation.Need fixture/model to ensure properelectrode distance.
Make sure that the gap electrodesalways keep the same distance evenduring high winds and/or vibrations.
Different BIL/sparkover voltage for
some towers?Arrester classification;
Check short-circuit capability. Is partsof the EGLA allowed to fall down after
overloading?Check mechanical data like vibration.
Installation methods;Hot installation or not.
26th November 2012
7/30/2019 Line Arresters. 2012
25/45
LA Special Considerations after Overload &Short-Circuit
Recommended requirementsexceeding those applicable to stationarresters:
Mechanical integrity should be maintained
after failure - Public access; Any open flames should not occur orself
extinguish in a very short time Risk ofcausing fires;
7/30/2019 Line Arresters. 2012
26/45
LA Special Considerations Regarding EnergyHandling Capability
The only definition in IEC 60099-4: line discharge class not appropriate
Based on long duration current impulses of
Td = 2000, 2400, 2800, 3200 s
7/30/2019 Line Arresters. 2012
27/45
IEC 60099-4, Ed. 2.2, Annex N:Test procedure to determine
the lightning impulse dischargecapability
IEC 60099-8, 8.6: Lightningdischarge capability test
Typical test current,voltage and energy
LA Special testing for Lightning Impulse DischargeCapability (1)
current(A),
voltage(V),energy(J)
time
Test applies to line arresters for system voltages exceeding 52 kV
A sinusoidal impulse of200 microseconds time duration consideredas a suitable compromise to cover all kind of realistic stress (shielded
and unshielded lines, multiple strikes)
7/30/2019 Line Arresters. 2012
28/45
Required impulse current amplitudes for injecting the same energy intoan MO resistor as by one line discharge equivalent to LD classes 2 to 4.
230 s current amplitudes will be in the range of15 kA 30 kA
LA Special testing for Lightning Impulse DischargeCapability (2)
7/30/2019 Line Arresters. 2012
29/45
Testing of LA
NGLA EGLA
52 kV > 52 kV
IEC 60099-4no special
requirements
IEC 60099-4special requirements on
energy testing mechanical testing
IEC 60099-8
Selection:IEC 60099-5, Ed. 2.0 (to be published 2013)Cigr TB 440 (2010)Software tools (commercially available)
Testing:
26th November 2012
7/30/2019 Line Arresters. 2012
30/45
26th November 2012
LA Applied on Sections of a Line, in One or TwoPhases
Individual towers with higher footing resistance protected with TLA: Installing one TLA on an individual tower reduces the probability of
flashover, installed on the bottom phase. If a second TLA is installedthe reduction in probability is minimal.
- Installation of additional TLAs on adjacent towers reduces the probability offlashover.
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
Outa
gesprobability
58 59 60 61 62 65 66 70 72 76
"Cambuci - Sto Antnio Pdua" 69 kV TL
Current configuration 1 TLA per structure 2 TLA per structure
7/30/2019 Line Arresters. 2012
31/45
Installation along Sections of Towers with HighFooting Resistance
Typical examples are: River, lake, gorge crossings
Mountain crossings
Important considerations; System study
LA should also be installed in 3-6 towers at each side with normal footing
resistance Otherwise flashovers are pushed to these towers instead
26th November 2012
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.080.0
90.0
100.0
Ou
tages
probability
58 59 60 61 62 65 66 70 72 76
"Cambuci - Sto Antnio Pdua" 69 kV TL
Current configuration 1 TLA per structure 2 TLA per strucuture
7/30/2019 Line Arresters. 2012
32/45
LA Protection against Double Line TrippingSimultaneously
26th November 2012
NGLA in all three phase on one circuit
reduces also the risk for flashover onthe other circuit.
7/30/2019 Line Arresters. 2012
33/45
26th November 2012
Installation of NGLA - Field Experience
Norway 300 kV Brazil 145 kV
7/30/2019 Line Arresters. 2012
34/45
26th November 2012
Installations of NGLA - Field Experience
Brazil 36 kV
7/30/2019 Line Arresters. 2012
35/45
Installations of NGLA - Field Experience
26th November 2012
24 kV - Peru
145 kV - Italy
7/30/2019 Line Arresters. 2012
36/45
26th November 2012
Installation of NGLA - Field Experience
Brazil 145 kV
TLA were installed on anew structure built inthe tower to allow TLA
installation on hot line.This procedure has ashorter installation timecompared with the usual
procedure used to installTLA on hot line.
7/30/2019 Line Arresters. 2012
37/45
26th November 2012
Installation of NGLA - Field Experience
Peru 145 kV
7/30/2019 Line Arresters. 2012
38/45
26th November 2012
Field Performance after LA Installation
Field experience of the Brazilian utilities Analysis and evaluation of the Brazilians overhead line lightning
performance (average number of outages per 100 km & year) before
and after transmission line arresters installation have shown a goodeffectiveness with average indexes for the improvement higher than
70% for overhead lines from 36 kV to 145 kV.
Average improvement of approximately 70% for 36 kV lines. Average improvement of approximately 79% for 72.5 kV lines.
Average improvement of approximately 76% for 145 kV lines.
There is not yet a reliable information for 245 kV lines. These indexes can be higher for overhead lines protected with
line arresters in all three phases.
7/30/2019 Line Arresters. 2012
39/45
26th November 2012
Extended Station Protection (1)
Back flashover at 600 m from the substation with one surge arrester
installed
7/30/2019 Line Arresters. 2012
40/45
26th November 2012
Extended Station Protection (2)
Back flashover at 600 m from the substation with two surge arresters
installed
7/30/2019 Line Arresters. 2012
41/45
26th November 2012
Extended Station Protection
Back flashover at 300 m from the substation with a set of TLA
installed on the structure closest to the substation with one surge
arresters installed
7/30/2019 Line Arresters. 2012
42/45
26th November 2012
Extended Station Protection
Simulao_3.pl4: v:5SIMULAO_1.pl4: v:5SIMULAO_2.pl4: v:5
0.0 1.5 3.0 4.5 6.0 7.5 9.0[us]0
100
200
300
400
500
600
[kV]
Back flashover at 600 m from thesubstation with one surge arrester
installedBack flashover at600 m from thesubstation with twosurge arrestersinstalled
Back flashover at 300 m fromthe substation with a set of TLA installed on the structure
closest to the substation
C ll d S i hi i h NGLA
7/30/2019 Line Arresters. 2012
43/45
26th November 2012
Controlled Switching with NGLA
800 kV USA 800 kV Russia
Only few sets of NGLA needed at 50% of line length or at 1/3 and 2/3for longer lines.Not sensitive to harmonics in the voltage.Works well in combination with controlled switching.
Rated voltage - same as station arresters Arrester class - one class lower than station arresters
C t Li ith t Shi ld Wi
7/30/2019 Line Arresters. 2012
44/45
26th November 2012
Compact Lines without Shield Wires
Unshielded compact line 420 kV
Source: Different Transmission Line Arrester Applications, Installations,and Designs MSA / ABB CIGR tutorial Rio de Janeiro 2005
7/30/2019 Line Arresters. 2012
45/45
26th November 2012
Thank You For Your Attention!