Line Arresters. 2012

Embed Size (px)

Citation preview

  • 7/30/2019 Line Arresters. 2012

    1/45

    Line Arrester Applications

    International Conference cum Tutorial on HV SA Technology & ApplicationsNew Delhi, 26th November, 2012Bengt Johnnerfelt

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    2/45

    26th November 2012

    Why Line Arresters?

    Lightning has been reported as the

    main cause of non-scheduled

    outages on overhead sub-transmission and transmission lines

    United States: 57%

    Brazil: 50 70% Japan: 70 80%

    Denmark: 57%

    Colombia: 47 69%

    Lightning is the most frequent cause

    of transmission outage and service

    interruption in the United States,accounting for about 30% of all

    power outages, and resulting in

    economic losses approaching $1billion annually http://www.epri.com

    http://www.epri.com/http://www.epri.com/
  • 7/30/2019 Line Arresters. 2012

    3/45

    Flashover due to Lightning on Transmission Lines

    Lightning may cause flashover of line insulators in three different ways:

    1.Strikes to shield wires or towers

    2.Direct strikes to the phase conductors

    Shielding failure

    Unshielded lines

    3.Flashovers due to induced voltages

    Rarely exceeding 300kV

    Limited to distribution andsub-transmission lines

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    4/45

    26th November 2012

    Shielded lines Back Flashover

    Current is typically shared between several towers and arresters

    Current travels from the tower to the phase conductor.

  • 7/30/2019 Line Arresters. 2012

    5/45

    Shielded lines Back Flashover Criteria

    VISi(t) Transient voltage on the insulators strings (kV)

    Vcrossarmi(t) Transient voltage on the cross arms (kV)

    Vinduced(t) Induced voltages (kV)VPFi Power frequency voltage (kV)

    ( ) ( ) ( )[ ]iii PFinducedicrossarmIS

    VtVtVtV

    ( ) ( )tVtVithstinsulatorwISi .

    Flashover when:

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    6/4526th November 2012

    Shielded Lines - Shielding FailureUnshielded Lines

    Shielding failure low current amplitudesUnshielded lines nearly all strikes leadto flashovers.

    Current travels from phase conductor tothe tower.

    ( ) ( )tVtVithstinsulatorwISi .

  • 7/30/2019 Line Arresters. 2012

    7/45

    Parameters Effecting Risk of Lightning Flashovers

    Ground flash density; Transient tower footing resistance and transient response of the

    tower;

    Lightning current amplitude; The electromagnetic coupling among shield wires and phase

    conductors;

    The effect of the adjacent towers and their footing resistances;

    26th November 2012

    Lightning strike: two traveling waves of= Z (Example: = 350 20 kA = 3.5 MV)

  • 7/30/2019 Line Arresters. 2012

    8/4526th November 2012

    Probability of Lightning Currents CIGRE Data

    ( )

    +

    =6.2

    311

    1

    I

    IIPd

  • 7/30/2019 Line Arresters. 2012

    9/4526th November 2012

    Shielded Lines Effect of Grounding System

    Transmission line lightning performance depends strongly on the

    transient grounding system response.

  • 7/30/2019 Line Arresters. 2012

    10/45

    Procedures to Improve the Transmission LinesLightning Performance

    Increase the line insulation;

    Improvement in the grounding system;

    Shield wire application on unshielded lines or improvement of the

    shielding angle for shielded lines;

    Line Arrester (LA)

    Externally Gapped Line Arresters - EGLA

    Non-Gapped Line Arresters - NGLA (TLA)

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    11/45

    Purpose of the Installed LA

    Protection againstfast front (lightning)overvoltages only.

    Protection against allovervoltages including

    slow front (switching) andfast front (lightning)overvoltages.

    or5000 s T1 20 s

    T1/T2 = 250/2500 s

    20 s T1 0.1 s

    T1/T2 = 1.2/50 s

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    12/45

    Line Arrester Applications

    Protecting line insulators from flashovers - reduced systeminterruption caused by lightning, improving system reliability;

    Protecting line insulators from flashovers substitute for shield wires

    Control switching surges along the lines substitutes for reclosing

    resistors;

    Extended substation protection - lowering/better protection of the BIL

    levels in substations;

    Upgrading system voltages with existing line insulation compact

    insulation lines;

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    13/45

    History of Line Arresters

    Distribution line arresters

    First installation of distribution line arresters in 1975 (Japan, 33 kV)

    Today several tens of millions of distribution line arresters assumedlyin service

    Transmission line arresters

    First installation of transmission line arresters around 1980 (Japan,66 kV, 77 kV and 138 kV)

    Today huge quantities of transmission line arresters in service

  • 7/30/2019 Line Arresters. 2012

    14/45

    Line Arrester Designs

    There are two basic designs;1. NGLA, non gapped line arresters, often called TLA (transmission line

    arresters):

    Can take higher energies & switching. Can be used on unshielded lines;

    Can be used instead of reclosing resistors;

    Need disconnector to facilitate fast reclosing;

    After disconnector operation possible swaying of the ground lead must be

    considered;

    2. EGLA, externally gapped line arresters:

    Shorter (& lighter) than NGLA. No COV or creepage requirements;

    Fast reclosing possible without disconnector;

    Difficult to find overloaded/failed EGLA in the field;

    Cannot handle switching surges or TOV, only used on shielded lines;

    Coordination of the spark gap;

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    15/45

    26th November 2012

    NGLA basic configuration for 245 kV system

  • 7/30/2019 Line Arresters. 2012

    16/45

    Typical EGLA Design IEC 60099-8

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    17/45

    Installation of EGLA & NGLA

    26th November 2012

    EGLANGLA

  • 7/30/2019 Line Arresters. 2012

    18/45

    Important Factors for Electrical Selection of LA forLI protection on Shielded LinesArrester rating;

    Higher than corresponding stationarresters - Avoid switching & TOVstresses.

    No need for very low protection levelsas BIL of line insulators is high.

    Arrester class;Lower than station arresters.Typically IEC class 2 will work up to245kV systems.

    How many and in which phases;Study needed in most cases.LA needed in a few towers on bothsides with normal footing resistanceafter LA installed in towers with highfooting resistance

    Desired outage rate

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    19/45

    Electrical Spark Gap Selection for EGLA

    Coordination of sparkover and flashover voltageSound arrester

    lightning impulse sparkover voltage

    must be lower than insulator's LIflashover voltage

    switching impulse sparkover voltagemust be higher than insulator's SI

    flashover voltage

    Failed arrester

    switching impulse sparkovervoltage must be higher thaninsulator's SI flashover voltage

    Insulator

    f/o voltage

    EGLA

    s/o voltage

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    20/45

    Special Pollution Consideration for EGLA

    Performance under pollution conditions:

    Follow current that partly flows on thepolluted arrester housing must be

    safely interrupted special, verycomplicated test in 60099-8

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    21/45

    Arrester class;

    Will see higher energies;

    System study needed;

    Selected based on the study

    result for the desired outage rate;

    Lower tower footing resistance not

    necessarily good as this may lead

    to that all current will be taken bytwo arresters only;

    26th November 2012

    Important Factors for Electrical Selection ofNGLA on Unshielded Lines

  • 7/30/2019 Line Arresters. 2012

    22/45

    26th November 2012

    Selection of LA System Studies

    Several commercial programs available.

    Basic Information Required for Modelling TLA for transmission lines:

    System voltage

    Basic configuration of the line & BIL of line insulators

    Tower type, phase-to-earth and phase-to-phase distances, shielded

    or unshielded line, phase conductors and shield wire sags, span

    length between towers, conductors diameters, etc. Short-circuit currents and temporary overvoltages conditions

    Ground Flash Density of the region crossed by the line

    Grounding system Existing station arresters electrical data

    Suggested LA data

  • 7/30/2019 Line Arresters. 2012

    23/45

    Installation Issues for Mechanical Selection of NGLA

    Disconnector installation;Weakest point of installation.Make room for swinging of the line.Consider lead lengths swaying afterarrester overloading.

    Check that operation times fits actualfault clearing times.

    Arrester classification;Check short-circuit capability. Is theLA allowed to fall down afteroverloading?

    Check mechanical data like vibration.

    Installation methods;Hot installation or not.Make sure that the arrester have pivotpoints so that it can move without too

    much stresses.

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    24/45

    Installation Issues for Mechanical Selection of EGLA

    Gap installation;Most critical point of installation.Need fixture/model to ensure properelectrode distance.

    Make sure that the gap electrodesalways keep the same distance evenduring high winds and/or vibrations.

    Different BIL/sparkover voltage for

    some towers?Arrester classification;

    Check short-circuit capability. Is partsof the EGLA allowed to fall down after

    overloading?Check mechanical data like vibration.

    Installation methods;Hot installation or not.

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    25/45

    LA Special Considerations after Overload &Short-Circuit

    Recommended requirementsexceeding those applicable to stationarresters:

    Mechanical integrity should be maintained

    after failure - Public access; Any open flames should not occur orself

    extinguish in a very short time Risk ofcausing fires;

  • 7/30/2019 Line Arresters. 2012

    26/45

    LA Special Considerations Regarding EnergyHandling Capability

    The only definition in IEC 60099-4: line discharge class not appropriate

    Based on long duration current impulses of

    Td = 2000, 2400, 2800, 3200 s

  • 7/30/2019 Line Arresters. 2012

    27/45

    IEC 60099-4, Ed. 2.2, Annex N:Test procedure to determine

    the lightning impulse dischargecapability

    IEC 60099-8, 8.6: Lightningdischarge capability test

    Typical test current,voltage and energy

    LA Special testing for Lightning Impulse DischargeCapability (1)

    current(A),

    voltage(V),energy(J)

    time

    Test applies to line arresters for system voltages exceeding 52 kV

    A sinusoidal impulse of200 microseconds time duration consideredas a suitable compromise to cover all kind of realistic stress (shielded

    and unshielded lines, multiple strikes)

  • 7/30/2019 Line Arresters. 2012

    28/45

    Required impulse current amplitudes for injecting the same energy intoan MO resistor as by one line discharge equivalent to LD classes 2 to 4.

    230 s current amplitudes will be in the range of15 kA 30 kA

    LA Special testing for Lightning Impulse DischargeCapability (2)

  • 7/30/2019 Line Arresters. 2012

    29/45

    Testing of LA

    NGLA EGLA

    52 kV > 52 kV

    IEC 60099-4no special

    requirements

    IEC 60099-4special requirements on

    energy testing mechanical testing

    IEC 60099-8

    Selection:IEC 60099-5, Ed. 2.0 (to be published 2013)Cigr TB 440 (2010)Software tools (commercially available)

    Testing:

    26th November 2012

  • 7/30/2019 Line Arresters. 2012

    30/45

    26th November 2012

    LA Applied on Sections of a Line, in One or TwoPhases

    Individual towers with higher footing resistance protected with TLA: Installing one TLA on an individual tower reduces the probability of

    flashover, installed on the bottom phase. If a second TLA is installedthe reduction in probability is minimal.

    - Installation of additional TLAs on adjacent towers reduces the probability offlashover.

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    Outa

    gesprobability

    58 59 60 61 62 65 66 70 72 76

    "Cambuci - Sto Antnio Pdua" 69 kV TL

    Current configuration 1 TLA per structure 2 TLA per structure

  • 7/30/2019 Line Arresters. 2012

    31/45

    Installation along Sections of Towers with HighFooting Resistance

    Typical examples are: River, lake, gorge crossings

    Mountain crossings

    Important considerations; System study

    LA should also be installed in 3-6 towers at each side with normal footing

    resistance Otherwise flashovers are pushed to these towers instead

    26th November 2012

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.080.0

    90.0

    100.0

    Ou

    tages

    probability

    58 59 60 61 62 65 66 70 72 76

    "Cambuci - Sto Antnio Pdua" 69 kV TL

    Current configuration 1 TLA per structure 2 TLA per strucuture

  • 7/30/2019 Line Arresters. 2012

    32/45

    LA Protection against Double Line TrippingSimultaneously

    26th November 2012

    NGLA in all three phase on one circuit

    reduces also the risk for flashover onthe other circuit.

  • 7/30/2019 Line Arresters. 2012

    33/45

    26th November 2012

    Installation of NGLA - Field Experience

    Norway 300 kV Brazil 145 kV

  • 7/30/2019 Line Arresters. 2012

    34/45

    26th November 2012

    Installations of NGLA - Field Experience

    Brazil 36 kV

  • 7/30/2019 Line Arresters. 2012

    35/45

    Installations of NGLA - Field Experience

    26th November 2012

    24 kV - Peru

    145 kV - Italy

  • 7/30/2019 Line Arresters. 2012

    36/45

    26th November 2012

    Installation of NGLA - Field Experience

    Brazil 145 kV

    TLA were installed on anew structure built inthe tower to allow TLA

    installation on hot line.This procedure has ashorter installation timecompared with the usual

    procedure used to installTLA on hot line.

  • 7/30/2019 Line Arresters. 2012

    37/45

    26th November 2012

    Installation of NGLA - Field Experience

    Peru 145 kV

  • 7/30/2019 Line Arresters. 2012

    38/45

    26th November 2012

    Field Performance after LA Installation

    Field experience of the Brazilian utilities Analysis and evaluation of the Brazilians overhead line lightning

    performance (average number of outages per 100 km & year) before

    and after transmission line arresters installation have shown a goodeffectiveness with average indexes for the improvement higher than

    70% for overhead lines from 36 kV to 145 kV.

    Average improvement of approximately 70% for 36 kV lines. Average improvement of approximately 79% for 72.5 kV lines.

    Average improvement of approximately 76% for 145 kV lines.

    There is not yet a reliable information for 245 kV lines. These indexes can be higher for overhead lines protected with

    line arresters in all three phases.

  • 7/30/2019 Line Arresters. 2012

    39/45

    26th November 2012

    Extended Station Protection (1)

    Back flashover at 600 m from the substation with one surge arrester

    installed

  • 7/30/2019 Line Arresters. 2012

    40/45

    26th November 2012

    Extended Station Protection (2)

    Back flashover at 600 m from the substation with two surge arresters

    installed

  • 7/30/2019 Line Arresters. 2012

    41/45

    26th November 2012

    Extended Station Protection

    Back flashover at 300 m from the substation with a set of TLA

    installed on the structure closest to the substation with one surge

    arresters installed

  • 7/30/2019 Line Arresters. 2012

    42/45

    26th November 2012

    Extended Station Protection

    Simulao_3.pl4: v:5SIMULAO_1.pl4: v:5SIMULAO_2.pl4: v:5

    0.0 1.5 3.0 4.5 6.0 7.5 9.0[us]0

    100

    200

    300

    400

    500

    600

    [kV]

    Back flashover at 600 m from thesubstation with one surge arrester

    installedBack flashover at600 m from thesubstation with twosurge arrestersinstalled

    Back flashover at 300 m fromthe substation with a set of TLA installed on the structure

    closest to the substation

    C ll d S i hi i h NGLA

  • 7/30/2019 Line Arresters. 2012

    43/45

    26th November 2012

    Controlled Switching with NGLA

    800 kV USA 800 kV Russia

    Only few sets of NGLA needed at 50% of line length or at 1/3 and 2/3for longer lines.Not sensitive to harmonics in the voltage.Works well in combination with controlled switching.

    Rated voltage - same as station arresters Arrester class - one class lower than station arresters

    C t Li ith t Shi ld Wi

  • 7/30/2019 Line Arresters. 2012

    44/45

    26th November 2012

    Compact Lines without Shield Wires

    Unshielded compact line 420 kV

    Source: Different Transmission Line Arrester Applications, Installations,and Designs MSA / ABB CIGR tutorial Rio de Janeiro 2005

  • 7/30/2019 Line Arresters. 2012

    45/45

    26th November 2012

    Thank You For Your Attention!