11
Title: Product User Guide Issue: Date: Page: Introduction to Light Duty Manhole Box 2.5m + 3.0m: Proshore’s User Guide aims to provide all the necessary information required to allow for safe, effective and well- informed use of Proshore’s Light Duty Manhole Box 2.5m + 3.0m. The guide will cover aspects of practical handling, assembly, installation and systems of best practice. Aspects of the guide will assume general competence within the field, however item specifics such as design components and planning for lifting operations will be comprehensively described. The Light Duty Manhole Box is designed to enable the shoring of excavations for works with SMALL excavators, which do not have the lifting capacity to work with heavier trench box systems. A complete understanding of handling advice, lifting points and practice for safe slinging is advised before undertaking such works. Although general competence is assumed, Operatives should ensure that the length and selected width of the box is sufficient for the intended works and should be aware that Light Duty Manhole Boxes are not suitable for use in water bearing soils or excavations containing frequent services. Proshore’s Manhole Box should only be used under the aforementioned circumstance and is not recommended for any other operative purpose. User Guide Contents: Light Duty Manhole Box 2.5m & 3.0m 1 Nov 16' Design: Please see diagram aside, which shows the typical pressures that Proshore’s Manhole Box can sustain. Although methods of estimating lateral earth pressures may vary, the present calculations should allow for the majority of working situations faced by the product. However, if you have any doubts, please speak to your company’s Proshore contact. This item is designed to carry a lateral earth pressure of 20kN/m 2 . Users should check that their excavation arrangement will not impose a greater working pressure. Actions, plans or conditions that may increase the likelihood of exceeding this pressure include; the close proximity of structures, excavated materials, construction materials, roads, services or railways. Users should also note that settlement of the reinstated ground and ground adjacent to the item is likely to occur after backfilling. 1/ 11 Light Duty Manhole Box 2.5m & 3.0m: Page 1: Design Page 2: Component Drawing Page 3: Assembly & Site Handling Page 7: Installation of Extension Page 9: Operational Guidance Page 11: User Summary 2900 100

Lightweight Manhole Backhoe Box 2.0m + 2.5m + 3.0m ... top lifting eyes Attach hooks to top lifting eyes Attach hooks to slinging holes Liethefirst!basepanelflatonthegroundwithitswings!

  • Upload
    vohanh

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

Title:  

Product  User  Guide  Issue:   Date:  

Page:      

Introduction  to  Light Duty  Manhole  Box  2.5m  +  3.0m:  Proshore’s  User  Guide  aims  to  provide  all  the  necessary  information  required  to  allow  for  safe,  effective  and  well- informed  use  of  Proshore’s  Light Duty  Manhole  Box  2.5m  +  3.0m.  The  guide  will  cover  aspects  of  practical  handling,   assembly,  installation  and  systems  of  best  practice.  Aspects  of  the  guide  will  assume  general  competence  within  the  field,  however  item  specifics  such  as  design  components  and  planning  for  lifting  operations  will  be  comprehensively  described.    

The  Light Duty  Manhole  Box  is  designed  to  enable  the  shoring  of  excavations  for  works  with  SMALL  excavators,   which  do  not  have  the  lifting  capacity  to  work  with  heavier  trench  box  systems.  A  complete  understanding  of  handling  advice,  lifting  points  and  practice  for  safe  slinging  is  advised  before  undertaking  such  works.  

Although  general  competence  is  assumed,  Operatives  should  ensure  that  the  length  and  selected  width  of  the  box  is  sufficient  for  the  intended  works  and  should  be  aware  that  Light Duty Manhole  Boxes  are  not  suitable  for  use  in   water  bearing  soils  or  excavations  containing  frequent  services.  Proshore’s  Manhole  Box  should  only  be  used  under  the  aforementioned  circumstance  and  is  not  recommended  for  any  other  operative  purpose.  

User  Guide  Contents:  

Light Duty Manhole Box 2.5m & 3.0m 1   Nov 16'

Design:  

Please  see  diagram  aside,  which  shows  the  typical  pressures  that  Proshore’s  Manhole  Box  can  sustain.  Although  methods  of  estimating  lateral  earth  pressures  may  vary,  the  present  calculations  should  allow  for  the  majority  of  working  situations  faced  by  the  product.  However,  if  you  have  any  doubts,  please  speak  to  your  company’s  Proshore  contact.    

This  item  is  designed  to  carry  a  lateral  earth  pressure  of  20kN/m2.  Users  should  check  that  their  excavation  arrangement  will  not  impose  a  greater  working  pressure.  

Actions,  plans  or  conditions  that  may  increase  the  likelihood  of  exceeding  this  pressure  include;  the  close  proximity  of  structures,  excavated  materials,  construction  materials,  roads,  services  or  railways.  Users  should  also  note  that  settlement  of  the  reinstated  ground  and  ground  adjacent  to  the  item  is  likely  to  occur  after  backfilling.    

1/  11  

Light Duty Manhole  Box 2.5m & 3.0m:  

• Page  1:  Design• Page  2:  Component  Drawing• Page  3:  Assembly  &  Site  Handling• Page  7:  Installation  of  Extension• Page  9:  Operational  Guidance• Page  11:  User  Summary

2900

100

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

Component  Drawings:  

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Length

'L'

'W'

545

'S'

545

'E'

'C'

When closing off the endsof the box ensure side loadingsare taken on the 30mm pads.DO NOT allow the struts to carryside loadings

64

2000

Length

1000

Length

Dimensions  of  Manhole  Boxes2.5  Manhole  Backhoe  Box  is  suitable  for  Manhole  ring  sizes  of  1050,  1200  &  1350mm.  

3.0  Manhole  Backhoe  Box  is  suitable  for  Manhole  ring  sizes  of  1500,  1800  &  2100mm.  

Note  for  Operatives,  Planning  &  Design  - The  weights  above  are  theoretical  and  therefore  do  not  take  into  consideration  Debris  or  Repairs:  Add  5%  for  such  effects.  

1000  

2000  

1200mm  

Clear  

‘L’  

Pin  with  ‘R’  Clip  

Weight:  0.5kg  

2/11

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

1   Nov 16'

Assembly  &  Site  Handling:  

• Operatives:  MHSW  legislation  requires  that  all  operatives  that  use  this  item  are  experienced,suitably  trained  and/or  supervised  by  a  competent  person.  All  lifting  operations  required  todeploy  this  item  are  to  be  controlled  by  and  appointed  person  and  all  acts  are  to  be  inaccordance  with  British  Standard:  BS7121  and  LOLER  regulations.

• Plant  required:  Suitable  appliances  are  required  for  offc loading  and  assembly  of  this  item.Before  lifting  a  comprehensive  understanding  of  the  size  and  weight  of  the  item  should  bechecked  against  the  item  of  plant’s  lifting  capacity  and  site  clearance.

• Additional  hire/tools  required:  Lifting  chains  of  suitable  length  and  capacity  are  requiredalongside  proof  of  current  certification. Speak  to  your  company’s  Proshore  contact  for  furtheradvice  or  item  hire.

• Access  required:  A  suitable  area  to  offload  the  lorry  and  to  assemble the  Box,  suitable  hardstanding  ground  required  for  the  lift  machine  to  operate,  Ladders  or staging  suitable  for  accessto  attach  required  chains  and  to  provision  safe  access  in  and  out  of trench/excavation.

• Supply  &  Return  of  Equipment:  Clients  should  ensure  that  the  equipment  is  returned  insections  and  state  as  supplied  and  should  not  be  required  to  assemble  or  dismantle  aspectswithout  previous  consent.

Light Duty Manhole Box 2.5m & 3.0m:

When  NOT  IN  USE  dismantle  all  extension  boxes  to  store  as  per  diagram.  Boxes  should  not  be  stored  on  uneven  or  sloped  ground,  or  exposed  to  extreme  wind  loading.    

• Stacking,  Handling  &  Transportation:  Baseand  extension  panels  should  be  stacked  as  shownwith  suitable  timber  dunnage.  Panels  should  bepacked  with  in  a  maximum  stack  of  4  and  all  components  and  pins  should  be  kept  in  separate  skips/containers.  During  any  form  of  transportation  all  stacks  should  be  securely  restrained  to  the  vehicle.    

Light Duty Manhole Box 2.5m & 3.0m:

Plywood Strips

Firm LevelDry Ground

1000

3/11  

Title:  

Product  User  Guide  Issue:   Date:  

Page:      

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Attach hooksto top liftingeyes

Attach hooksto top liftingeyes

Attach hooksto slinging holes

Lie  the  first  base  panel  flat  on  the  ground  with  its  wings  pointing  upwards  

Pin  4  No.  fixed  length  Strut  to  the  base  panel  using  pins  and  ‘R’  clips  

Turn  the  other  base  panel  over  using  2  legs  of  the  four  leg  sling  

Re-­‐sling  this  panel  with  the  wings  downwards  (use  all  4  legs  of  the  lifting  chain)  

Complete  assembly  of  the  base  box  on  its  side  by  pinning  the  stuts  to  the  upper  panel  before  removing  the  4  leg  sling.  

Site  Assembly  

4/11  

Title:  

Product  User  Guide  Issue:   Date:  

Page:      

After  standing  upright,  ensure  that  all  pins  and  safety  clips  are  checked  to  be  in  place.  Next  lift  the  box  using  the  four  leg  chain  sling,  attached  to  the  lifting  points  at  the  top  of  each  panel.  

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Trench Width

Attach  two  chains  of  the  sling  to  the  upper  lifting  eyes  of  the  uppermost  panel  and  two  chains  of  the  sling  to  the  upper  lifting  eyes  on  the  lower  panel.  Next  stand  the  box  on  its  cutting  edges  (operatives  note:  take  care  to  not  damage  the  struts  during  movement).  Ensure  that  the  weights  and  radius  are  within  the  lifting  capacity  of  the  machine,  to  allow  for  impact  and  effects  of  lurching,  as  the  box  is  turned  upright.    

Site  Assembly  

Installation  of  Base  

5/11  

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Dig  the  manhole  approximately  600-­‐1000mm  deep  to  the  correct  width,  and  using  the  four  leg  sling,  place  the  box  into  the  excavation.  The  box  can  now  be  installed  to  the  correct  depth,  by  digging  between  the  box  panels  and  pushing  down  on  the  ends  of  the  panels.  (Operative  note:  Always  dig  below  the  panels  before  pushing  down  -­‐  Push  only  on  the  corners  of  each  panel  and  

never  in  the  middle.)  

When  pushing  the  box  panels  down,  always  push  down  in  the  sequence  shown  and  never  diagonally  across  corners.  

Example  Sequence  –  A  then  B  –  Followed  by  C  then  D.  

DO  NOT  complete  in  a  sequence  –  A  then  C  or  B  then  D.  

During  the  ‘dig  and  push’  operation,  restrict  the  advance  of  one  panel  over  the  other  to  a  maximum  of  6%  of  the  box  width.  

When  the  required  excavation  level  is  reached  and  the  box  has  reached  its  full  depth,  operatives  must  ensure  that  the  struts  are  horizontal  at  right  angles  to  the  panels  before  entering  the  excavation.  

DO  NOT  use  any  unsupported  part  of  the  excavation  for  access.  Leave  the  top  of  the  box  100mm  above  the  surrounding  ground  level.  

Push in thesecorners

D   C  

B  A  

6/11  

+ 6%

of

Exc

avat

ion

Wid

th

Excavation Width

100

90°

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

300

mm

100

mm

90°

Dig  and  push  the  base  box  to  stay  within  approximately  300mm  from  the  top  of  the  base  box  

Lift  one  extension  panel  upright  using  two  of  the  4-­‐leg  chain  sling  and  pin  two  No.  fixed  length  struts  to  the  panel  using  pins  

and  R  clips.  

Lift  the  second  extension  panel  upright  using  2  of  the  4-leg   chain  sling  and  lower  on  the  other  base  panel.  Whilst  doing  this,  operatives  should  locate  the  two  number  struts  into  the  panel.  Secure  the  panel  to  the  base  box  using  pins  and  R  clips.  

DO  NOT  use  any  unsupported  part  of  the  excavation  for  access.  Leave  the  top  of  the  box  100mm  above  the  surrounding  ground  

level.  

Lift  the  extension  panel,  complete  with  struts,  to  lower  onto  one  side  of  the  base  box.  Secure  the  panel  onto  the  base  box  using  

pins  and  R  Clips.  

Continue  the  dig  and  push  operation  until  the  required  excavation  level  is  reached.  Ensure  all  the  struts  are  horizontal  

and  at  right  angles  with  the  panels  before  entering  the  excavation.  

Installation  of  Extension  

7/11  

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Ensure  that  there  are  NO  gaps  between  the  box  panel  and  the  trench  sides  as  this  may  cause  the  box  to  move  sideways  

DO  NOT  leave  the  base  of  the  box  ‘flying’  above  the  trench  level.  

When  stopping  off  the  end  of  the  trench,  steel  walers  should  be  used  to  support  the  sheets  off  the  end  of  the  panels.  

N.B  –  NEVER  use  the  struts  as  supports  for  the  trench  sheets.

Correct   Incorrect  

8/11  

Struts MaintainClearance

Waling and Trench Sheetsor alternatively, End Panels

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

300 300

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Operating  within  a  support  excavation  

• Use  suitable  access  (Ladder)  to  enter  the  working  space.  At  no  point  should  an  operative  climbup  and  down  the  struts  of  the  Manhole Box;  additional  access  required  at  all  times.

• DO  NOT  use  unsupported  parts  of  working  area  for  access.• DO  NOT  move/lift  the  Manhole  Box  whilst  operatives  are  inside.• Full  PPE  in  accordance  with  clients  working  best  practice  to  be  worn  and  MUST  include  a

safety  helmet.• Ensure  that  all  works  are  effectively  planned  and  that  site  operatives  are  made  aware  of  said

planning

Extraction  of  Light Duty  Manhole  Box  Due  to  the  consolidation  of  the  ground  against  the  modules,  operatives  MUST  BE  AWARE  that  it’s  more  difficult  to  extract  Manhole  boxes,  than  to  insert  them.  Operatives  MUST  take  guidance  from  below,  ensuring  that  all  lifting  operations  use  the  recommended  lifting  points  provided.    

NO  OPERATIVES  CAN  BE  INSIDE  THE  MANHOLE  BOX  DURING  EXTRACTION/LIFTING  OPERATIONS.  

Method  for  extraction  in  Normal  Conditions  

After  the  initial  backfilling  and  compaction,  lift  the  base  box,  complete  with  extension  box  (if  fitted)  from  the  manhole  using  the  4  leg  lifting  chain  attached  to  ALL  4  upper  lifting  points.  Continue  backfilling  as  the  removal  of  the  box  proceeds.    

If  the  extension  box  is  to  be  removed  from  the  base  box,  lift  as  per  previous  description,  until  the  top  of  the  base  is  approximately  300mm  above  ground  level.  Then  remove  the  corner  pins  used  to  secure  one  of  the  extension  panels  to  the  base  and  the  other  pins  used  to  secure  the  other  extension  to  the  base.  Then  lift  this  whole  panel,  complete  with  struts,  from  the  base.  Finally  remove  the  struts  from  the  extension  panel  and  stack  the  panels  and  struts,  as  per  previous  stacking  guidance.    

DO  NOT  –  remove  the  extension  panels  before  the  top  of  the  base  is  above  ground  level  &  DO  NOT  remove  the  extension  box  as  a  complete  item  from  the  base  box.    

9/11  

Light Duty Manhole Box 2.5m & 3.0m:

Title:  

Product  User  Guide  Issue:   Date:  

Page:    

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m:

Method  for  extraction  in  Wet  or  Heavy  Ground  Conditions  

In  such  conditions,  it  may  be  necessary  to  pull  one  corner  of  the  box  at  a  time,  to  initiate  the  lifting  process.  To  do  so,  connect  the  single  leg  connector  chain  to  the  upper  lifting  points  of  each  BASE  panel,  pull  each  panel  vertically  in  turn  in  order  to  lift  the  box  free.    

ALWAYS  fit  the  connector  chain  to  the  BASE  panels  of  the  Manhole  Backhoe  box  and  NEVER  to  the  extension  panels.  

Once  the  box  is  free,  attach  two  legs  of  the  chain  sling  to  the  upper  lifting  points  (as  per  diagram  a)  to  pull  this  panel  up.  Repeat  the  operation  on  the  remaining  BASE  panel.  

DO  NOT  exceed  the  advancing  of  one  panel  over  the  other  by  6%  of  the  box  width;  this  is  as  per  installation  guidance.  Any  advice  required,  speak  to  your  company’s  Proshore  contact.    

The  box  can  now  be  lifted  from  the  Manhole  using  the  4-­‐leg  chain,  attached  to  all  four  lifting  points  on  the  base  box  (as  per  diagram  b).  

Maintenance  Guidance:  

Ensure  regular  checks  on  all  pins  and  connections.  Avoid  laterally  loading  struts,  this  could  be  effected  by  handing  or  propping  from  them  or  by  accidental  striking  by  site  plant  operations.    

N.B  –  Damaged  struts  should  NEVER  be  operated  with  and  all  staff  should  be  made  aware  of  anydamage  to  items.

10/11

Lifting  Lug  

Snatch  Chain  

a)   b)  

Title:  

Product  User  Guide  Issue:   Date:  

Page:      

User  Summary  –  Light Duty Manhole  Box  2.5m  +  3.0m:  

✗ -­‐  Move  the  item  with  Operatives  inside

✗ -­‐  Use  the  lifting  points  for  uses  other  than  loading/unloading  or  assembly

✗ -­‐  Use  unsafe  lifting  equipment

✗ -­‐  Enter  unsupported  parts  of  the  Working  Area/Trench/Excavation

✓ - Ensure  that  all  operatives  have  been  briefed  and  have  confirmed  familiarity  with  the  User  

Guide.

✓ - Follow  basic  maintenance  instructions.

✓ - Ensure  all  works  are  in  accordance  with  design  and  do  not  overstress  the  boxes.

✓ - Ensure  that  all  access  is  per  recommendation  e.g.  Using  a  ladder  to  enter  working  area.

✓ - Ensure  that  all  operatives  have  recommended  PPE.

✓ - Ensure  that  when  not  in  use  –  Manhole  Box  is  stored  on  its  side.

✓ - Ensure  that  a  safe  batter  of  the  unsupported  parts  of  the  trench  is  maintained.  

11/11

1   Nov 16'Light Duty Manhole Box 2.5m & 3.0m:

Light Duty Manhole Box 2.5m & 3.0m: