Upload
alptekin-dag
View
221
Download
0
Embed Size (px)
Citation preview
7/30/2019 Liability of Construction Managers
http://slidepdf.com/reader/full/liability-of-construction-managers 1/2
I
n the last several years, construction managers
have taken on an increasingly larger share
o construction projects. Unlike general
contractors, which are generally at risk or all
aspects o the project—rom cost to schedule to
he quality o the work—the risk and responsibility
o a construction manager can vary greatly rom
project to project, depending on the nature o the
ontract. In this article, we will explore the key
aspects o construction management agreements
and present a sampling o relevant judicial
holdings.
The hallmark o construction management
s the total participation o the manager in the
onstruction process, oten beginning with the
onceptualization o the project. The construction
manager will work with the owner and the design
eam to produce a coordinated and cost efcient
et o construction documents. The construction
manager will then assist the owner in selecting
ubcontractors (or trade contractors) and, to
varying degrees, coordinate and administer the
actual construction.
Generally speaking, construction managers act
either in an advisory capacity, as agent or the
owner, or as a constructor, acting as an independent
ontractor, much like a general contractor. When
acting as advisor, the construction manager will
enter into trade contracts as agent or the owner;as a constructor, the construction manager will
enter into contracts directly with subcontractors.
The construction manager’s contractual liability
varies drastically depending on the nature o its
employment.
As an advisor, the construction manager is,
essentially, liable only or its own acts o negligence
or breach o contract. It is not considered to be
acting “at risk” with respect to the cost, time or
quality o perormance by the trade contractors.
Acting as a constructor, the construction manager
is generally responsible or the construction o
the project; however, the construction manager’s
ultimate liability or the key elements o the
project—cost, schedule and quality o the work—
can vary greatly based upon its agreement with
the owner.
Obligations of the Manager
Perhaps the only universal statement that can
be made about the obligations and liabilities o a
construction manager is: “it depends upon what
it says in the contract.” As with almost any other
legal relationship, the rights and obligations o
the construction manager (to the owner, to trade
contractors and to third-parties) are controlled
primarily by the language o the respective
agreements. While there are certain statutory and
common law rules regarding what can and cannot
be included in construction contracts, very ew
generalities can be made.
When the construction manager is acting only
as the owner’s advisor—also known as pure
construction management—the construction
manger typically does not assume any responsibility
or the cost, time or the quality o the work. The
construction manager may, as part o its contractwith the owner, agree to prepare estimates o the
cost o the work, but the estimates are typically not
guaranteed. The American Institute o Architects
most current Standard Form o Agreement Between
Owner and Construction Manager as Adviser (AIA
Document C132-2009) specifcally provides that
“the Construction Manager does not warrant or
represent that bids or negotiated prices will not
vary rom the budget proposed, established or
approved by the Owner, or rom any cost estimate
or evaluation prepared by the Construction
Manager.” (AIA Document A132-2009 §6.2).
The construction manager as advisor
o course, assume greater responsibilit
the cost o the work, but will typically i
on additional compensation to relect
added risk and will insist upon adeq
contingencies in its estimates to accoun
potential cost overruns and unoreseen c
The construction manager acting as constr
will be liable or the cost o the project i it a
to perorm the work or a guaranteed maxi
price (GMP) or a lump sum. This is not the
where the agreement is structured on a “
plus” basis. Under a cost plus arrangement
construction manager is reimbursed or all c
o the work and is paid a ee, generally determ
as a percentage o the cost o the work. U
a GMP, the construction manager will guar
the total cost o the project, which include
supervisory expenses and subcontract c
(usually based on drawings which are 80-90 pe
complete). A major component o a GMP i
establishment o a contingency, usually 3-5 pe
o the subcontract and general conditions
supervisory expenses) costs. The constru
manager can utilize the contingency to ose
cost o, or example, bid error, deective w
subcontractor deaults, scheduling con
delays, etc.
Where the construction management agreeprovides or a GMP, there is oten an arrange
or the sharing o any savings between the o
and the construction manager i the fnal
o the work is less than the GMP. Where t
is a sharing o savings, any unused conting
might likewise be shared. (The sharing o sa
both rom the GMP and the contingency inv
detailed business negotiations which are pr
specifc.)
The construction management agreemen
also determine the construction manager’s lia
or completion o the project in accordance
Volume 244—No. 63 wedNesday, september 29,
Liability of ConstructionManagers: Look to the Contract
ConstruCtion Law
eNNeth m. blocK and JohN-patricK curraN are partnersf Tannenbaum Helpern Syracuse & Hirschtritt.
©2010 ALMwww. NYL J.com
By
Keeh M.
Blck
And
Jh P
C
7/30/2019 Liability of Construction Managers
http://slidepdf.com/reader/full/liability-of-construction-managers 2/2
an agreed upon schedule. Generally speaking,
as a constructor, a construction manager is
esponsible or completing the project on time
and may be responsible to the owner or damages
ncurred as a result o delay. The extent o the
damages—whether they be liquidated, direct
or consequential—is a unction o the terms o
he construction management agreement. Even
n the absence o liquidated damages or delay,he construction manager may be obligated to
maintain the progress o the work in accordance
with the project schedule and be responsible
or the cost o overtime and additional shits in
order to maintain that schedule. Where there is a
ontingency, the construction manager may utilize
unds in the contingency to cover such additional
osts.
As a constructor, the construction manager is
also responsible or the quality o the work o its
ubcontractors. Where the construction manager
annot prevail upon the responsible subcontractor
o remedy the deective work, the construction
manager will be required to remedy the deects
at its expense; however, the contingency would
be available or that purpose.
As an advisor, the construction manager only
has an obligation to confrm generally that the
work o the trade contractors is being perormed in
accordance with the respective trade contracts. The
ypical construction manger as advisor agreement
will provide speciically that the construction
manager is not responsible or and has no control
over the means, methods and procedures o the
onstruction and is not responsible or the ailure
o the trade contractors to perorm the work in
accordance with the terms o their respective
ontracts.
Liability to Trade Contractors
The common assumption is that the construction
manager as advisor is acting solely as the owner’s
agent and, under standard principals o agency,
s not liable or the obligations o its disclosed
principal, the owner.
However, as the Court o Appeals wrote in Walls
. Turner Constr. Co., “the label o construction
manager versus general contractor is notnecessarily determinative.” 4 N.Y.3d 861, 864, 798
N.Y.S.2d 351 (2005). Simply calling itsel an agent
may not be sufcient to insulate the construction
manager rom an obligation to make payment to
he trade contractors. The construction manager
has to be careul not to create a contractual
elationship between itsel and the individual trade
ontractors perorming the work. I the contractors
are bound to the construction manager or the
proper perormance o the work, it may not matter
hat the construction manager has held itsel out
olely as the owner’s agent.
In Blandford Land Clearing Corp. v. National
Union Fire Insurance Company of Pittsburgh, Pa.,
260 A.D.2d 86, 698 N.Y.S.2d 237 (1st Dept. 1999),
a general contractor (claiming to be acting as the
agent o the owner) attempted to insulate itsel
rom an obligation to pay subcontractors on a
project by including language in its subcontract
agreements that read that “[]or the purposes o
payment only, Contractor is acting as agent oOwner.” 260 A.D.2d at 88. The court ound that,
since the subcontractors owed an obligation to
the general contractor to perorm the work, there
must be the corresponding obligation on the part
o the general contractor to pay the subcontractors
or the work.
While Blandford involved a general contractor,
as opposed to a construction manager, there is no
reason to think that the decision would be dierent
i a construction manager signed the contracts as
the owner’s agent. The lesson to be learned is that
in order or the construction manager to insulate
itsel rom any contractual obligation to make
payment to trade contractors, it must not enter
into direct agreements with the trade contractors.
When the construction manager is acting
as the constructor, it is typically assumed the
construction manager has the direct obligation
to make payment to the trade contractors or the
perormance o the work. This duty is ordinarily
independent o the owner’s obligation to make
payments to the construction manager, and the
construction manager has a payment obligation
to the trade contractors irrespective o whether
the construction manager has received payment
rom the owner. West-Fair Elec. Contractors v. Aetna
Cas. & Sur. Co., 87 N.Y.2d 148, 638 N.Y.S.2d 394
(1995) (a provision in a subcontract that provides
that the general contractor is only required to pay
the subcontractor i the owner pays the generalcontractor—a so-called pay when paid provision—
is unenorceable as against public policy).
Liability to Third Parties
With respect to tort liability, a construction
manager’s liability to third parties depends both
on the role that the construction manager assumes
and the ability o the construction manager to
control the activity that caused the injury.
In the pure construction management scenario,
where the construction manager does not have
control over the perormance o the work o the
contractors, the construction manager is typ
not liable to third parties or injuries resulting
the work. A construction manager “may noneth
become responsible or the saety o the wo
at a construction site i it has been delegate
authority and duties o a general contractor, o
unctions as an agent o the owner o the prem
Pino v. Irvington Union Free School District , 43 A
1130, 843 N.Y.S.2d 133 (3rd Dept. 2007). The arises requently in the context o claims o
liability under New York Labor Law Section 24
also known as the Scaolding Law.
In Walls, the Court o Appeals held that
lthough a construction manager o a work s
generally not responsible or injuries under L
Law § 240(1), one may be vicariously liable a
agent o the property owner or injuries susta
under the statute in an instance where the man
had the ability to control the activity which bro
about the injury.” 4 N.Y.3d 861 at 863-864
N.Y.S.2d 351 (2005).
The court ound that the construction man
had a duty, under its contract with the owner o
project, to enorce compliance by the indiv
trade contractors with applicable saety regula
and to direct trade contractors to correct u
conditions. The court wrote that the deen
Turner Construction Co., was not the “ty
construction manager,” but was instead the “
ears and voice o the owner.” 4 N.Y.3d 861 at
Accordingly, the court confrmed that Turne
vicariously liable as a statutory agent o the ow
4 N.Y.3d 861 at 864.
While Walls and the cases that have ollow
appear as an odd deviation rom the typica
o agency—that a disclosed principal is liab
actions o its agent perormed within the s
o the agency, not the other way around—
decisions make it clear that, at least in the co
o Labor Law §240(1) claims, the extent o
construction manager’s liability will be dictat
the scope o its authority. C. Kindlon v. Scho
Central School Dist ., 66 A.D.3d 1200, 887 N.Y
310 (3rd Dept. 2009) (no direct control as to s
matters shielded the construction manager
liability).
The obligations o a construction managas an advisor or constructor, as an agen
independent contractor—are a unction o
terms o its contract with the owner. So, too, w
liabilities o a construction manager to an ow
subcontractor or third party vary dependin
the agreement.
wedNesday, september 29,
Reprinted with permission from the September 29, 2010 edition of the NEW YOR JOURNAL © 2010. ALM Media Properties, LLC. All rights reserved. Further dwithout permission is prohibited. For information, contact 877-257-3382 or repricom. # 070-09-10-39
Perhaps the only universal statement
that can be made about the obligations
and liabilities of a construction manager
is: “it depends upon what it says in the
contract.”