LHCb planning for DataGRID LHCb planning for DataGRID testbed0testbed0
Eric van HerwijnenEric van Herwijnen
Thursday, 10 may 2001 Thursday, 10 may 2001
OverviewOverview
Information & organization Information & organization Testbed0 Testbed0 Procedure for participating institutes:Procedure for participating institutes:
Planning of tests: admin Planning of tests: what to test Planning of tests: how to do it
Status so farStatus so far TimescaleTimescale
Information and Information and organizationorganization
Mailing list:Mailing list: [email protected] [email protected]
CVS repository:CVS repository: to get Java production tools:to get Java production tools:
cvs -d $NEWCVSROOT co GRID/productiontools
to get the DataGRID LHCb installation kits:to get the DataGRID LHCb installation kits: cvs -d $NEWCVSROOT co GRID/installationkits
to get sample script and .dat files:to get sample script and .dat files: cvs -d $NEWCVSROOT co GRID/scripts
Testbed0Testbed0
Objective: deploy basic Globus services and test themObjective: deploy basic Globus services and test them
Site OS/machines Batch system Operational LHCb contactCERN 5 PIII's, Linux LSF yes Eric van HerwijnenIN2P3 Lyon ? ? ? ?IN2P3 Marseille 2 PIII's, Linux Condor ? Andrei TsaregorodtsevIN2P3 Clermont-Ferrand
10 PIII's,Linux
? ? Vincent Breton
INFN-CNAF Bologna 5 PII/PIII,Linux
PBS yes Domenico Galli/Umberto Marconi
RAL 10 PIII's,Linux
PBS yes Glenn Patrick
Liverpool ? ? yes Girish Patel/Martin McCubbinEdinburgh/Glasgow ? ? ? Akram KahnImperial College ? Condor yes David CollingBristol ? ? ? Nick BrookNIKHEF ? PBS ? Sander Klous
Procedure for participating Procedure for participating institutesinstitutes
CERN, Lyon, Marseille, RAL, INFN Bologna, CERN, Lyon, Marseille, RAL, INFN Bologna, Liverpool, Edinburgh, Imperial, NikhefLiverpool, Edinburgh, Imperial, Nikhef
others interested please contact meothers interested please contact me
Planning of tests: adminPlanning of tests: admin
Complete your entry in previous table and Complete your entry in previous table and contact me (find out exactly what your local contact me (find out exactly what your local testbed0 is from local WP6 contact)testbed0 is from local WP6 contact)
Decide which tests you want to do (e.g. Submit Decide which tests you want to do (e.g. Submit jobs from Bologna to Liverpool)jobs from Bologna to Liverpool)
Get a national Grid certificate following the Get a national Grid certificate following the procedure on http://marianne.in2p3.frprocedure on http://marianne.in2p3.fr
Get local accounts on the testbeds that you Get local accounts on the testbeds that you want to testwant to test
WP6 will add people to Grid map filesWP6 will add people to Grid map files
Planning of tests: what to testPlanning of tests: what to test
Objective: Objective: run bb-bar inclusive generation and reconstruction job via
Globus if possible send data to CERN update the bookkeeping database
For sites wishing to become part of LHCb For sites wishing to become part of LHCb production:production:
installation of java production tools automate file transfer to CERN
Planning of tests: how to do itPlanning of tests: how to do it
Check out GRID files from cvs repositoryCheck out GRID files from cvs repository uncompress (gunzip *.tar.z) and untar (tar -xvf *.tar) uncompress (gunzip *.tar.z) and untar (tar -xvf *.tar)
the installation kitsthe installation kits run the bbincl.job script, modify it until it works run the bbincl.job script, modify it until it works
(don’t worry about java to start with)(don’t worry about java to start with) when it works, do e.g.:when it works, do e.g.:
globus-job-submit csflnx01.rl.ac.uk/jobmanager-pbs bbincl.job
try to recover output with other globus commands try to recover output with other globus commands or ftp by handor ftp by hand
to install production tools (requires servlet runner) to install production tools (requires servlet runner) contact mecontact me
Status so farStatus so far
RAL CSF and CERN testbed0 integrated with RAL CSF and CERN testbed0 integrated with LHCb production toolsLHCb production tools
Jobs with 5 events run fineJobs with 5 events run fine Larger jobs can be run one at a time, problems Larger jobs can be run one at a time, problems
with gass_cache under investigationwith gass_cache under investigation Problems interfacing to pbs (jobs always end Problems interfacing to pbs (jobs always end
up in M queue)up in M queue) Problems with using sh or cshProblems with using sh or csh
TimescaleTimescale
Tests of testbed0 should be done before Tests of testbed0 should be done before september 2001 (testbed1 release)september 2001 (testbed1 release)
LHCb Grid meeting Bologna 13-15 june 2001LHCb Grid meeting Bologna 13-15 june 2001 progress on testbed0 tests security issues for testbed1 LHCb analysis model