Upload
wadi
View
218
Download
1
Embed Size (px)
Citation preview
Virtual Prototyping for
Automated, Rule-based Constructability Review
Li Jiang, PhD Candidate; Dr. Robert M. Leicht
L E A N A N D G R E E N: R E S E A R C H I N I T I A T I V E
Background
Constructability is defined as “the optimum use of construction
knowledge and experience in planning, design, procurement, and
field operation to achieve overall project objectives,” (CII,
1986). Frequently, a review of constructability concepts is
adopted by using a checklist and a lessons-learned system after
the design reaches a certain design stage, 30%, 60%, or 95%
design (Hancher and Goodrum, 2007).
However, the large amount of required resources, time and manpower, largely impedes constructability implementation
(Hancher and Goodrum, 2007); the rework in design caused by
the inefficient process (Arditi et al., 2002; Pulaski and Horman,
2005) cannot be ignored either.
As the idea of implementing integrated design methods to
enhance productivity and value in the industry, this research
examines the existing constructability review process and
addresses the research question:
What process changes with the help from integrated design
methods and tools can help to improve the current
constructability review process?
Research Goal & Objectives
To improve consistency, efficiency, and value of existing
constructability review process, by proposing an automated rule-
based constructability review with the implementation of
Building Information Modeling (BIM).
To investigate the feasibility of using available BIM
contents to represent constructability knowledge required
for a constructability review.
To define and validate the method of rule-based checking to
automate constructability review process.
To demonstrate the benefits of the proposed constructability
review process with the implementation of BIM, in terms of
automational, visual, informational, and transformational
effects.
Capturing Constructability Knowledge for Reinforced Concrete Structure
The elicitation of constructability knowledge from construction experts is the first and important step for the research to analyze the
feasibility of using available BIM contents to interpret the constructability knowledge required for a constructability review. Multiple
case studies are being to collect and analyze the knowledge.
Focusing on reinforced concrete structure, one case study, shown in Figure 1, is the Turkish-American Community Center at
Lanham, Maryland. This project has 5 buildings interconnected via an underground parking facility, including a mosque. The
complex has a gross floor area of approximately 316,000 square feet, more than 95% of which is constructed with cast-in-place concrete. One of the 5 buildings has a one-story steel structure, and thus is not considered in this study. Given cultural concerns, the
project design has incorporated traditional mosque features such as domes and minarets, resulting in a range of different formwork
systems used in the project.
As shown in Figure 1, the knowledge regarding formwork decisions captured from project team are compared with available BIM
contents accordingly, demonstrating the ability of using BIM to provide upfront feedback and facilitate early planning and decision-
making.
Conclusions
The automated rule-based constructability review process is
expected to produce significant potential benefits, in terms of
automational, informational, transformational, and visual effects
(based on Fox and Hietanen, 2007):
Visual: Unlike most of previous
constructability tools, BIM owns
strong capabilities of visualization.
With 3D graphic representations,
potential constructability issues can be
easily presented, understood, and
communicated among project
participants.
Automational: Instead of a manual check of printed plans
with a checklist, an automatic review process can be
systematic and comprehensive, reducing the required time
and resources for simpler concerns and allowing the
construction team to focus on future impacts and planning.
Informational: Integrated with 3D graphic representations,
the information embedded in BIM models can be extracted and shared among different project parties. The
informational effects of BIM
implementation allows designers to be
aware of design-related construction
concerns at corresponding design stages,
resulting in “proactive,” instead of
“reactive,” design feedback, and better
decision-making.
Transformational: As the “proactive” feedback is enabled in the
design process, the transformational effects will be through
the change in process. The proposed process is expected to
pull the constructability knowledge into the design process
and encourages designers to produce a more constructible
design.
Future Research
Acknowledgements
Bob Grottenthaler
Barton Malow Company
For additional information or questions regarding this research, contact:
Li Jiang, PhD Candidate
Dr. Robert M. Leicht, Director of PACE, Assistant Professor
Future work can focus on three directions:
Further investigation of constructability knowledge.
Based on limited case studies, the current research merely
investigates the relationship between BIM contents and
structural design-related constructability issues. A com-
prehensive acquisition of constructability knowledge can
be achieved by looking at more case studies or different
design disciplines.
Further development of design-related constructability
rule-sets. Considering the existing technical difficulties
regarding the rule checking platform, the rule-sets
developed and tested in the research are merely about form-
work selection. Further investigation is needed to develop a
comprehensive set of reasoning rules of design-related con-
structability issues.
Further exploration of the proposed process. As existing
technical issues may be solved and the rule-sets become
complete, the process needs to be detailed mapped out
and documented for better practices and collaboration
among different project participants.
Process
PeopleTechnology
Kurt Maldovan
Balfour Beatty Construction
Structural System
Superstructure
CIP Concrete
Seismic Applications
Non-Seismic Applications
Gravity Systems
Normal Reinforcing
Dimension (e.g. height, thickness, etc.)ReinforcingOthers
Sub-structure
Misc. Members and Items
BIM Contents
Architecture System
Technical Systems (i.e. mechnical, electrical, plumbing systems)
Database of Constructability
Rulesets
Lateral Systems
…...
2 Way Flat with Drop Panel
Location
Schematic Design
Design Development
Construction Documents
Figure 1: Implementing BIM for Automated Constructability Review
Knowledge Representation
The representation of knowledge involves analysis of how to
reason accurately and effectively and how to “write” and encode
the knowledge into a form that is understandable by humans and
behave like humans (Brachman and Levesque 2004).
The method of rule checking is applied in this research to
represent the constructability knowledge and to model the ways
of thinking as construction experts in a constructability review.
Figure 2 shows the formwork used in the case study project of
Turkish-American Community Center. In the form of decision
tree, Figure 3 represents the acquired knowledge for horizontal
formwork selection through an interview of project team. In
addition to design parameters such as slab slope and slab depth,
resource constraints such as crane, labor, and the layout density
have been considered in the decision-making of formwork use.
Based on the obtained knowledge, a set of design-related
constructability reasoning rules can be developed to represent the
knowledge and thereby to achieve an automated constructability
checking. Figure 3: Case study interview: horizontal formwork selection
Application: Formwork selection rule testing
An example of reasoning rule is written as (Hanna and
Sanvido, 1989):
“IF: Building size is small or medium (i.e. gross area
is no more than 25,000 sq. ft)
AND: Building height is between 10 to 13 floors
THEN: Use conventional aluminum forming system.”
The reasoning of conventional aluminum forming
system selection at Washington D.C. urban area requires two different attributes- building size and
building height. As a results, the reasoning process can
be divided into 2 parts: reasoning about building gross
area, and building height. As long as both of them
meet the target value, the formwork selection can be
achieved.
Solibri Model Checker, as a world-leading model review software based on rule-based checking, has
been applied as the platform to develop and run the
constructability reasoning rules. More detailed
information about Solibri can be found on http://
www.solibri.com/.
Figure 4, 5 and 6 are snapshots from Solibri, showing
the constitution of the rule-set, parameters of the two
separated reasoning rules, and corresponding target value of each parameter
respectively.
Figure 4: Formwork selection rule example
Rule Execution
As the reasoning rule-sets are defined by writing the acquired
constructability knowledge into machine-readable language, those
rules need to be executed in an appropriate rule checking
platform, in order to prove the validity of the innovative approach.
This part of research will use a case study to test the rule-sets of
formwork selection, as a test case with validated logic to support
means and methods rules. Solibri Model Checker will be used as
the platform for rule execution.
As an example, one case study
project, which is the Copping
State University Science &
Technology Center at
Baltimore, MD, is used here to
test the rule-set of “Horizontal
Formwork Selection.” Figure 7
shows the architectural
rendering and REVIT model of
the project. The rule execution
interface of “Slab Formwork
Selection” in Solibri is
displayed in Figure 8.
Process Modeling
Last, though far from least, a process protocol of an automated
constructability review with the implementation of BIM will be
developed. Based on Eastman et. al (2009), a typical rule-based
reasoning process has 4 stages (Figure 9):
Rule interpretation, which aims to translate the construction
knowledge acquired from industry experts into computer-
readable language, and to form logical structure of rules for
their application as human reasoning. Depending on different
project phase (i.e. SD, DD, CD, and Pre-Construction),
different level of detail of constructability knowledge are
interpreted into related rules and stored in the appropriate
rule checking platform.
Building model preparation, where necessary information
required for the automated rule-based reasoning is prepared.
As design develops (e.g. from SD to DD and then to CD),
appropriate level of detail of BIM contents should be
embedded into the design model at each phase.
Rule execution, which brings together the prepared building
model with the rules that apply to it. At different project
phase, the BIM contents captured by the reasoning rules will
be at different level of detail.
Reporting the reasoning results (i.e. constructability feedback) to designers. Depending on the timing of the
feedback, two types of constructability feedback are
expected to be obtained from the proposed process: reactive
and proactive feedback.
Reactive feedback is provided
by reacting a situation; whereas
proactive feedback is provided
in advance of a situation. For
example, the feedback
regarding the design changes
for fully developed concepts is “reactive;” the feedback that is
provided at the same phase but
mentions constructability
concerns for future design steps
is considered as “proactive.”
The automated rule-based
reasoning process enables
consistent proactive feedback
in the review process, adding
more value to the process.
Figure 7: Case Study Project: Coppin State Sci. & Tech. Center
Figure 9: Overall process of automated rule-based constructability reasoning (based on Eastman et. al, 2009)
Figure 5: Rule parameters of “Building Gross Area”
Figure 6: Rule parameters of “Building Height”
Figure 8: Rule execution for “Horizontal Formwork Selection”
DD CD
ConstructionKnowledge
ConstructionKnowledge
ConstructionKnowledge
Pre-ConSD
ConstructionKnowledge
Database of Rule-sets
Database of Rule-sets
Database of Rule-sets
Database of Rule-sets
EXPERT
USER
❶ Rule Interpretation
❷BIM Model Preparation
❸Rule Execution
❹Constructability Feedback
Reactive feedback
Potential Proactive feedback
SD: Schematic Design
DD: Design Development
CD: Construction Document
Pre-Con: Pre-Construction/Shop Drawing
Notes:
Figure 2: Formwork used in Turkish-American Community Center