DANIEL SETTEL Research Assistant Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University RAYMOND E. LEVITT Professor of Civil and Environmental Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University Stanford, CA 94305-4020 Email: [email protected] and Abstract Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery Page 2
Citation preview
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
RAYMOND E. LEVITT
Professor of Civil and Environmental Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building
473 Via Ortega, Room 241 Stanford University
Stanford, CA 94305-4020 Email: [email protected]
WITOLD J. HENISZ UPS Visiting Associate Professor of Civil and Environment Engineering
Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 305
Stanford University Stanford, CA 94305-4020
Email: [email protected]
and
DANIEL SETTEL Research Assistant
Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241
Stanford University
Submitted to
2009 CONFERENCE ON LEADERSHIP AND MANAGEMENT OF CONSTRUCTION Fallen Leaf Lake, Lake Tahoe, California
November 5-8, 2009
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 2
Abstract
Prior research on the governance of large infrastructure projects has emphasized the question of who
should own and operate long-lived infrastructure assets, comparing public and private organizations with
respect to productive efficiency or the distribution of welfare. Our ongoing research seeks to shift the
focus of this research to the question of how public or private organizations can best manage two distinct
kinds of governance challenges that occur systematically during the project shaping, implementation and
operation phases of such projects: (1) opportunism in the presence of displaced agency – i.e., conflicts
between the incentives of parties leading decision making in each of the successive and interdependent
phases of design, construction and operations that lead to sub-optimal investment and may lead them to
pursue their self-interest with guile; and (2) political and regulatory risk – i.e., ex post political
interventions in operational decisions. A model that incorporates the efficiency and legitimacy
consequences of governance decisions over the life of an infrastructure project thus offers substantial
gains on more piecemeal disciplinary approaches. We seek to develop a new typology of hybrid
governance mechanisms designed to alter the incidence of opportunism by counterparties or stakeholders
to a series of interconnected transactions. This paper lays out the two key governance challenges of
infrastructure projects in some detail, with examples of each, and points the way toward research on a
broader governance framework for such projects. Our conference presentation and future publications
will focus in greater depth on examples of both existing and proposed new hybrid governance
arrangements that must be studied, refined and implemented to address these challenges.
KEYWORDS: Infrastructure; governance; transaction costs; socio-political governance; displaced
agency; partnering; lean construction.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 3
Introduction
Scholars have long expressed dissatisfaction with the “sharp delineation of markets vs. hierarchies”
especially in networked, project-based industries like construction ( Gunnarsson & Levitt 1982;
Stinchcombe 1985; Bradach and Eccles 1989:97) and have offered myriad calls to pay more attention to
hybrid forms of organization in which relational contracting governed by trust complements or dominates
the mechanisms of price or authority. We argue that despite a clear awareness of the importance of
interpersonal or inter-organizational trust and a growing body of evidence that this trust alters
transactional governance and performance, we lack a clear understanding of the mechanisms by which
trust is developed and sustained in project networks.
Our ongoing research seeks to identify and offer examples of the following kinds of socio-
political governance mechanisms that alter the incidence of opportunism: the cultivation of a desire for
social status and avoidance of social sanction; the development and reinforcement of a common identity;
the adherence to precepts of distributive or procedural justice; the adherence to participatory models of
engagement; the alignment of social and interpersonal interests as well as economic interests; and the
deployment of influence strategies. We develop our theoretical arguments in the context of infrastructure
services, where trillions of dollars of investment are organized under conditions of extreme contractual
hazards via governance mechanisms that are neither market nor hierarchy. However, we conclude by
noting the broad applicability of these governance challenges and socio-political governance mechanisms.
Points of Departure
Our aim is to extend the frameworks presented by Stinchcombe (1985), Ouchi (1980) and Bradach &
Eccles (1989) to encompass a broader set of socio-political governance mechanisms that can generate
trust thereby allowing for a clan form of organization. Ouchi (1980:131) introduces the clan form by
noting that clan forms of organization that rely on goal congruence coexist with market and bureaucratic
forms of organization that use distinct mechanisms to overcome goal incongruence between principals
and agents. Ouchi closes his article by identifying tradition or other means of crafting legitimate social
authority, norms of reciprocity and common values and beliefs as factors associated with an increased
efficacy of the clan form. He cites utopian communities, military units, high technology or medical work
teams and historical employment relations between Japanese workers and business groups as examples of
such contexts.
Bradach and Eccles (1989) seek to deepen the insight provided by Ouchi (1980) by focusing on
the governance or control mechanisms that support these organizational forms. Instead of market,
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 4
bureaucracy and clans, their emphasis is on the distinction between price, authority and trust. They
explicitly build on Zucker’s (1986) depiction of the “Production of Trust” to examine how “(a) diffuse
social norms of obligation and cooperation, and (b) personal relationships that overlap with economic
exchanges provide the basis for trust.” (Bradach and Eccles 1989:105). They cite an expansive body of
evidence using varied methods and contexts that all highlight the power of long-term relations, in which
counterparties repeatedly observe each other observing norms of fairness, to reduce the incidence of
opportunistic behavior. They next survey literature demonstrating that “where economic transactions are
embedded in personal relationships the hazards of opportunism are diminished and the need for elaborate
formal governance structures is reduced or eliminated entirely.
Much research has built upon the foundation of these two seminal articles, but with limited
emphasis on the specific governance mechanisms that change states of mind. Rather, the emphasis has
been on the exploration of the question of whether trust is a substitute or a complement to more traditional
forms of governance (Mayer and Argyres 2004; Poppo and Zenger 2002). Moreover the focus of virtually
all this work has been on trust in bilateral relationships. In contrast, we seek to build on the path of
development pursued by Bradach & Eccles (1989) in further explicating the control or governance
mechanisms that generate trust to undergird problematic contracts. In the context of infrastructure projects,
this process leads us to explore not only bilateral exchange relationships but the relationships between a
broader network of direct and indirect stakeholders in a project-based industrial supply chain, linked by a
series of temporally sequenced contracts. This dual broadening of scope —development of trust across a
network vs. in a dyad, and sets of transactions that occur in an interdependent, temporally sequenced set
of relationships— led us to consider a wider range of mechanisms drawing from disparate disciplines but
unified in their goal of reducing the incidence of opportunism among multiple stakeholders. Before
turning to the depiction of these mechanisms, we introduce the specific context in which we develop our
arguments.
The Context of Infrastructure Projects
Two characteristics of infrastructure projects make them ideal for the development of a deeper
understanding of socio-political governance. First, they are typically produced by multiple counterparties
through a complex sequence of interlinked transactions. Second, infrastructure projects are inherently
highly politically salient, both because of their catalytic role in the process of development and their
centrality to a nation’s security and well-being. Given these characteristics, the governance of
infrastructure projects faces an extremely high level of two related contractual hazards: (1) opportunism
in the presence of displaced agency – i.e., conflicts between the incentives of parties leading decision
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 5
making in each of the successive and interdependent phases of design, construction and operations that
leads to sub-optimal investment and may lead them to pursue their self-interest with guile; and (2)
political and regulatory risk – i.e., ex post political interventions in operational decisions.
Temporally the provision of infrastructure services typically proceeds through phases of project
shaping, detailed design, construction and operation. While transactions between counterparties in each of
these transactions may appear bilateral and discrete, they implicitly include counterparties to and
stakeholders in the full sequence of temporally linked transactions, and thus cannot be examined in
isolation from each other. So a more traditional transaction cost analysis, which would examine one
discrete transaction or a series of recurring transactions of a given type in isolation, is problematic.
Instead, we simultaneously analyze the series of temporally linked and bundled, distinct, sequential
transactions involved in the provision of infrastructure services. The supplier and buyer in any one
transaction can and do opportunistically shift the burden of costs and the distribution of benefits across
the sequence of related transactions. Furthermore, they appeal to political and regulatory actors to
intervene directly or at the behest of a counterparty or stakeholder in any of the related transactions (e.g.,
current and future end users, bearers of externalities, taxpayers, bondholders and other suppliers) in ex
post efforts to alter the distribution of rents resulting from ex ante investments. We next review specific
manifestations of opportunism within each phase of the lifecycle of infrastructure projects to illustrate the
magnitude of the governance challenge in infrastructure services.
Opportunism Across the Project Life-Cycle
Project Shaping. In the project shaping phase, planning consultants are typically paid a fixed fee or
reimbursable fee with fixed profit for their services by the project sponsors—the government agency
acting as the owner-developer or the private consortium providing the equity investment and management
of the project. If the projects go ahead based on planning stage estimates, these consultants are well
placed to receive much larger contracts for detailed design and construction supervision on these projects,
as well as future planning contracts from these and other sponsors. In the public sector, half-completed
infrastructure projects become such a source of public embarrassment that governments—typically future
governments—tend to find funds to complete them, blaming the cost overruns on their predecessors and
taking credit for rescuing the failed projects. In the private sector, equity holders can often renegotiate
terms with lenders to help them recover at least some of their potential losses from costs over-runs and
demand under-runs—as was done in the case of the Channel Tunnel. So there are typically strong
incentives for infrastructure planning consultants to align their behavior to serve the interests of
politicized public and private sector promoters—including local governments, engineers, contractors,
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 6
construction labor unions, local chambers of commerce, etc.—tending systematically to overestimate
demand and underestimate construction cost.
As a result, estimates of demand even for local public works projects in developed countries are
notoriously optimistic; and estimates of construction costs tend to be even more so, resulting in “Bridges
to Nowhere” that exceed their estimated costs by many times.1
The Channel Tunnel between England and France is a good example of a common pattern in
infrastructure projects. This project exceeded its cost estimate of £2.6 Billion by almost 80%; its
financing costs were 140% of estimated costs; and its passenger trip demand in the first year of operation
was just 18% of the forecasted demand (Flyvbjerg et al, 2003). As a result, the Channel Tunnel has gone
through multiple rounds of refinancing, and is just beginning to show a profit in 2009—some 15 years
after commencement of operations!
The true costs for these projects are
deferred to future users or taxpayers whereas the political benefit from potential future counterparties and
stakeholders for their announcement is received in the present. Thus, the current principals—the local or
regional development agencies or private sponsors and their agents (i.e., the planning consultants)
opportunistically collude—explicitly or implicitly—to initiate the development of myriad projects whose
long-run economic and political feasibility is sometimes dubious at best.
Design. Local governments, working with their design consultants during the detailed design
phase then intervene to “gold plate” (i.e., overdesign) the proposed facilities in order to create even
miniscule savings in operating costs that will be borne exclusively or largely by the local communities
that they represent at the expense of potentially drastic increases in the up-front construction costs borne
largely by grants from a regional or national infrastructure agency. For example, a study of design
decision-making on a major urban transit project, found that the local transit agency sought to eliminate
the operational cost of pumping water out of a tunnel by specifying that the tunnel should have zero
leakage. The engineers on this project, facing liability in the event of any leakage, specified a 12-inch
thick concrete lining for tunnels, far beyond what was needed for structural support, at a cost of millions
of dollars per mile (Levitt et al 1980). Private design consultants, or government professional engineers
have strong incentives to go along with such overdesign, and design conservatively in order to avoid
1 A large meta-study of dozens of large infrastructure projects worldwide confirmed this consistent overestimation of demand and underestimation of cost for transportation projects all around the globe by governments and their planning consultants— the “economic hit men”— over the last several decades (Flyvbjerg et al. 2003)
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 7
potential professional liability suits for failures of any kind (Levitt et al 1980; 1984). They have few
incentives to design aggressively to limit construction costs: they work on reimbursable fee contracts and
any overdesign tends to be imperceptible to taxpayers within or outside the project service area.
Construction. Construction under typical firm-fixed-price or fixed unit price contracts necessarily
creates an adversarial relationship between the client, often represented by the engineer as its agent, and
the contractor. The contractor is incentivized by such contracts to complete the project at minimal cost
while meeting —but not exceeding— the minimum design specifications. Conversely, the client and its
engineer are incentivized to insure that the contractor meets or exceeds the minimum design
specifications at the lowest cost to the client. Any ambiguity or discrepancy among the multiple sets of
plans and specifications produced by multiple, fragmented, specialist designers creates an opportunity for
honest or opportunistic “change order” negotiation by the contractor to increase payments and allowable
completion time. Contractors submit "Requests for Information" (RFIs) to clarify such inconsistencies;
these often escalate into "Change" requests by the contractor for extra time and money, which must be
formalized by the owner through negotiated “Change Orders” to the original contract. Negotiations about
the legitimacy and magnitude of change orders can then further escalate into arbitration or litigation
(“Claims”) if not settled to the contractor’s satisfaction. Thus, when contractors spot inconsistencies in
bidding documents, they are motivated not to raise questions about any perceived errors or omissions
prior to the bid, but rather use this information to bid low, capture the project, and then seek additional
compensation via change orders after work has commenced and they “discover” the discrepancies.
Operations. Whereas economic models clearly highlight the efficiency of market-based pricing
for infrastructure services, the political and social sustainability of such pricing models is an open
question even in countries where the sanctity of contracts is a widely supported norm. When prices or
shareholder returns are perceived to be “too high” relative to ability or willingness to pay of consumers or
stakeholder’s perception of “fairness” in the current economic environment, direct or indirect political
pressure to renegotiate the terms of the deal is likely to follow, irrespective of the formal independence of
the regulatory authority, sophistication of the contractual guarantees invoking security bonds in offshore
bank accounts, contractually required arbitration under foreign law, appeal to a bilateral investment treaty
or letter of comfort, or the sophistication of the financial hedges including public or private political and
regulatory risk insurance.
The drivers of these perceptions are not limited to the cost of service provision, the availability of
substitutes or the opportunity cost of capital. Rather, they include such peripheral factors as the degree of
economic hardship born by consumers or impacted stakeholders, the nationality of the service provider,
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 8
the past price history of the service and the reputation of the government and intermediaries associated
with the design, implementation and operation of the infrastructure provider. Both sides frequently invoke
public safety, fairness, and other broadly accepted norms in these disputes, seeking to build a coalition of
political and social support for their true desired position—i.e., a greater share of the rents at the expense
of their counterparty. Given a 30-year to 50-year lifespan of infrastructure assets that typically spans
multiple changes of governments, it is simply impossible for governments to credibly commit to contracts
that remove these political elements of market risk.
An infrastructure owner’s or operator’s foreign identity can also aggravate perceptions of
unfairness or illegitimacy by local stakeholders (Gomez-Ibanez et al. 2004). Consider the case of the
water supply project in Cochabamba, Bolivia where the government granted a concession to a consortium
of foreign companies for the city’s water services. As soon as the private concessionaire began operations
in November 1999, protests arose over the project. Tariffs had increased substantially by the new
operators to cover the full capital costs of supply improvements. Additionally, the concession granted the
consortium exclusive rights to all water resources in the city. As a result, well-established alternative
water sources including privately-owned wells and storage tanks and tanker-based vendors were to be
phased out over time. After six months of road blocks, strikes, and public demonstrations, the Bolivian
government cancelled the concession contract. Nickson and Vargas (2002) suggest that, for the Bolivian
population, the project represented “a preference for foreign capital over the national interest” in a
country with “a long tradition of anti-imperialist rhetoric.” Foreign firms delivering, treating and selling
water for profit and imposing limits on groundwater pumping by local farmers flew in the face of local
cognitive-cultural institutions (Scott 2001) that “water is a basic, natural right of citizens.” This “Yanqui
Imperialist” project became a lightning rod for many other East vs. West, urban vs. rural and
European/Mestizo vs. indigenous political fault lines in Bolivia, and helped to foment the revolution that
put Evo Morales in power in 2006.
These examples of displaced agency and lack of political legitimacy show some of the unique
governance challenges for these long-lived, highly asset-specific, near-natural monopoly projects. Next,
we draw out some theoretical limitations of conventional governance approaches in addressing these
challenges.
Limitations of Conventional Governance
The construction management literature has followed the logic of transaction cost economics in arguing
that a typical construction project, with its delayered system architecture and fragmented supply-chain,
has some of the characteristics of both markets and hierarchies (Eccles 1981; Gunnarson and Levitt 1982).
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 9
Opportunistic behavior can, it has been argued, be mitigated in hierarchical governance structures when
all of the lifecycle project costs and benefits of a project are born by a single entity—i.e. the local
government agency or private entity that will design, build, operate and maintain the facility over an
extended period. Alternatively, the opportunistic behavior can be mitigated through carefully specified
contractual incentives with appeal to neoclassical contracting. We argue that both of these governance
mechanisms are partial solutions that fail to fully address the underlying hazard of opportunistic behavior
by counterparties distant to the immediate transaction. At the extreme, a reliance on hierarchical
governance (typically by governments) or neoclassical contracting only shifts the burden of costs to
increasingly distant and diffuse actors who lack the capacity to assess the risks they are taking on or
monitor the underlying behavior of the counterparties and properly incentivize them to eschew
opportunistic behavior.
Hierarchy. A design-build construction contractor unifies detailed design and construction
services and tenders a proposal to the client to maximize the value that can be delivered for a given
budget. The client then picks the design-build tender —typically from a joint venture of one or more
construction firms and design firms— that appears to offer them the greatest value. In addition Design-
Build contracting allows construction to begin before design is complete, with the potential to save
considerable time over a more conventional, sequential Design-Bid-Build approach. However, only
relatively sophisticated construction buyers can specify their requirements well enough at the conceptual
design stage to pick a “Design-Build” or “Engineer, Procure and Construct” (EPC) contractor that will
optimally satisfy its needs and wants for the project. As a result, this approach tends to be used for
relatively well specified facilities like industrial plants, warehouses, standard office buildings, highway
segments or bridges by large manufacturing services companies (e.g., Dow, DuPont, Exxon-Mobil, Bank
or America, Google, Intel) or large governmental agencies (e.g., the General Services Administration in
the US that purchases or leases buildings for use by most Federal agencies; state highway agencies;
regional mass transit agencies; large school boards; and the like). These sophisticated construction buyers
develop a series of similar facilities over time, so they can develop the in-house expertise to specify their
requirements clearly and unambiguously enough to exploit this mode of contracting successfully. For
other buyers, the subsequent buyer’s remorse at what they have bought, or the ex post renegotiation costs
incurred with the Design-Build construction contractor can outweigh the savings in time and the increases
in value from alleviating the agency problem between the design vs. construction actors, if acting
independently.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 10
One solution to this problem is to further extend the scope of the Design-Build construction
organization both upstream and downstream so that the same entity finances, designs, builds, owns and
operates the facility. This further internalization, however, can generate yet another conflict in which the
ultimate costs of the project are passed onto third parties — the end users—who are unable to assess the
risks that they are bearing accurately, or have no choice but to accept them. When a contractor or
contractors that will design and build the project also represent part of the consortium financing the
project, they have two ways to make profit: payment for their design-construction services, and income
from their share of the investment returns for the operation of the facilities. The English Channel Tunnel
(“Chunnel”) project is an egregious example of this conflict of interest problem.
Neoclassical Contracting. Few if any public or private organizations are capable or willing to
internalize the full set of transactions involved in infrastructure provision. Thus, some form of market
exchange in which opportunistic behavior can arise seems inevitable. One means to mitigate opportunism
in such transactions is through the use of external commitment or bonding mechanisms such as an appeal
to the judicial system, financial guarantors such as surety bonding companies, or credible third party
dispute resolution of detailed contractual commitments. While in theory, the reliance on independent and
impartial third party rulings could resolve the inherent uncertainty in complex and always incomplete
contingent contracts, one or both parties may face incentives to tilt the playing field in its favor by
directly or indirectly stimulating political intervention in the dispute. The aim of such influence tactics is
typically to avoid the uncertainty of the dispute resolution process and use political or regulatory
intervention to secure a more favorable and potentially expeditious outcome. We offer three examples of
such opportunistic behavior below. Note, in each case, the shift from a focus on the legal elements of a
potential dispute to its perceived fairness or legitimacy.
The history of the State Route 91 (SR-91) express lanes in Orange County, California highlights
the implicit hazards of trilateral governance of infrastructure projects even in countries with well
developed legal systems and property rights. The bondholders of the project demanded a strong non-
compete clause in the PPP contract, which blocked the California State Transportation Department
(Caltrans) from making any improvements to the SR-91 free lanes that could increase their capacity, and
thereby undermine the revenue received by the toll road operator. The clause was invoked when Caltrans
proposed a number of improvements to the free lanes in order to "alleviate safety concerns." In response
to this proposal by Caltrans, CPTC filed a lawsuit against Caltrans in March 1999, claiming that the
improvements were actually disguised efforts to increase capacity and, therefore, constituted a violation
of the non-compete clause. Caltrans’ actual intentions remain unclear and, in practice, it is often difficult
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 11
to separate safety improvements from capacity increases. Although Caltrans and CPTC were able to
reach a settlement, the combination of the lawsuit and a steep increase in tolls for the use of the road at
peak commute times led to growing protests, and the labeling of the toll lanes as the “Lexus lanes”.
There were also allegations at the time that CPTC had filed the lawsuit in order to win the approval of
Caltrans for a sale of the express lanes, which were performing relatively poorly as an investment. The
rigid PPP agreement had failed to provide a means to renegotiate terms of the partnership as traffic
conditions evolved.
A more extreme case of the limits of external contractual support can be found in the case of
independent power projects in Southeast Asia, where many governments wooing private power investors
in the early and mid-1990s offered contracts that insulated investors from commercial risk, fuel supply
risk, exchange rate risk, currency conversion risk, regulatory risk and the risk of political force majeur.
When the East Asian financial crisis occurred in 1997, it brought private power investors’ favorable
treatment into sharp relief as currency values, share prices and electricity demand all plummeted. The
obligations that the governments of the struggling countries had previously undertaken to attract private
investors now had little apparent benefit, and political officials were left in the tenuous position of having
to choose between honoring the contracts, at the risk of compromising their own popular support, or
renegotiating contracts in order to maintain support. Despite the comprehensive set of covered risks it
became increasingly clear that, in the words of one interviewee, “the government has the ability to make
us healthy or unhealthy. It’s a government decision.” In September 1998, President Habibe announced his
intention to eliminate 13 of the 26 IPP contracts “without significant compensation” and six more “with
some compensation.” (Henisz and Zelner 2005a)
Discussion
The examples described above illustrate a series of severe and recurring challenges to traditional forms of
project governance for infrastructure development and delivery projects, arising from several underlying
attributes of these projects and the industry that develops and delivers infrastructure assets. Displaced
agency problems arise from the cycling in and out across successive project phases of the “project” of
multiple supply chain participants playing different roles, and whose interests can be in direct conflict
both within a project phase and across project phases. The broad scope of the potential counterparties
makes it extremely difficult to balance interests even at a single point in time; and it makes it especially
difficult to continually realign contractual terms to sustain the balance of interests among parties over the
decades-long lifecycle of such projects as global, regional and local technologies, economies and politics
change in important ways. Finally, the strategic impact of large infrastructure assets on communities and
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 12
whole countries invokes the intervening or moderating presence of governments in infrastructure disputes
such as those described above. This always present specter of governmental intervention—even in liberal
market economies like the US—overwhelms the power of contracts, whether backed by domestic courts
or international arbitration and dispute resolution even of the most sophisticated kind, when individuals or
groups can choose to appeal to political rather than legal resolution of perceived imbalances in costs and
benefits that may arise over time. Clearly a richer set of mechanisms than contracts and hierarchical fiat
is needed to make such projects predictably governable.
Investors and host governments grappling with the risks posed by such significant socio-political
governance challenges need to respond in kind. They need to complement legal, financial and
organizational mechanisms of governance with broader socio-political governance instruments. These
instruments can facilitate adaptation not only by explicit economic counterparties but also by implicit
economic, political and social counterparties. In addition to the power of legal fiat enjoyed by hierarchy
and the economic incentives enjoyed by market, we seek to draw attention to the power of social ties and
common identity in shaping the behavior of all parties in a manner that highlights collective interest,
develops real trust and attenuates opportunistic behavior, without incurring the administrative costs and
lost incentive intensity of full-scale vertical integration or the high transaction costs and ultimate failure
of complex contingent contracts with cross-national trilateral governance.
Toward Socio-Political Governance
Our ongoing research will draw upon complementary insights from multiple disciplines in the
development of enhanced governance frameworks. Future publications will present ideas from: social
exchange theory, which shares our focus on the relationship versus the transaction as the unit of analysis;
and social control and sanctioning mechanisms, such as the construction of a collective identity (Dutton et
al. 1994), restricted access to outsiders, socialization, sanctions and reputation (Jones et al. 1997), norms
of reciprocity (Adams 1965; Gouldner 1960), and adherence to principles of distributive justice (Blau
1964; Homans 1958) and procedural justice (Lind and Tyler 1988; Thibaut and Walker 1975).
Our conference presentation will describe the use of cooperatives to govern the operation of clean
water distribution infrastructure— historically one of the most challenging of all infrastructure sectors to
govern both efficiently and sustainably— as an example of a hybrid market, hierarchy and socio-political
governance framework that has recently experienced considerable success in the face of failures like the
one described in Cochabamba, Bolivia of traditional approaches, including Private-Public Partnership
(PPP) governance approaches, for this sector.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 13
REFERENCES
Adams, J.S. 1965. Inequity in Social Exchange. L. Berkowitz, ed. Advances in Experimental Social Psychology. Academic Press, New York, NY.
Anglo American PLC. 2003. SEAT Socio-Economic Assessment Toolbox. Anglo American PLC, London.
Arnstein, S.R. 1969. A Ladder of Citizen Participation. Journal of the American Institute of Planners 35 216-224.
Auty, R.M. 1993. Sustaining Development in Mineral Economies: The Resource Curse Thesis. Routledge, London.
Bailey, K., T. Grossardt, J. Ripy, L. Toole, J.B. Williams, J. Dietrick. 2007. Structured Public Involvement in Context-Sensitive Large Bridge Design Using Casewise Visual Evaluation: Case Study of Section 2 of Ohio River Bridges Project Transportation Research Record: Journal of the Transportation Research Board 2028(3) 19-27.
Barlow, J. 2000. Innovation and Learning in Complex Offshore Construction Projects. Res Policy 29 973-989.
Barnard, C.I. 1968. The Functions of the Executive, Thirtieth Anniversary Eddition ed. Harvard University Press, Cambridge.
Bayliss, R., S.-O. Cheung, H.C.H. Suen, S.-P. Wong. 2004. Effective Partnering Tools in Construction: A Case Study on MTRC TKE Contract 604 in Hong Kong. International Journal of Project Management 22 253-263.
Blau, P.M. 1964. Justice in Social Exchange. Sociological Inquiry 34(2) 193-206.
Bradach, J., R. Eccles. 1989. Price Authority and Trust: From ideal types to plural forms. Annual Review of Sociology 15 97-118.
Bresnen, M., N. Marshall. 2000a. Motivation, Commitment and the Use of Incentives in Partnerships and Alliances. Construction Management and Economics 18 587-598.
Bresnen, M., N. Marshall. 2000b. Partnering in Construction: A Critical Review of Issues, Problems and Dilemmas. Construction Management and Economics 18 229-237.
Chan, A.P.C., D.W.M. Chan, Y.H. Chiang, B.S. Tang, E.H.W. Chan, K.S.K. Ho. 2004. Exploring Critical Success Factors for Partnering in Construction Projects. Journal of Construction Engineering and Management 130(2) 188-198.
Cheng, E.W.L., H. Li, D.S. Drew, N. Yeung. 2001. Infrastructure of Partnering for Construction Projects. Journal of Management in Engineering 17(4) 229-237.
Cheung, S.-O., T.S.T. Ng, S.-P. Wong, H.C.H. Suen. 2003. Behavioral Aspects in Construction Partnering. International Journal of Project Management 21 333-343.
Chevalier, J.M., D. Buckles. 2007. SAS2 Process Management.
Choguill, C.L. 1996. Ten steps to sustainable infrastructure. Habitat International 20(3) 389-404.
Coleman, J.S. 1986. Social Theory, Social Research, and a Theory of Action. American Journal of Sociology 91 1309-1335.
Conner, K.R., C.K. Prahalad. 1996. A Resource-based Theory of the Firm: Knowledge Versus Opportunism. Organ Sci 7(5) 477-501.
Crane, T.G., J.P. Felder, P.J. Thompson, M.G. Thompson, S.R. Sanders. 1997. Partnering Process Model. Journal of Management in Engineering 13(3) 57-63.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 14
Crane, T.G., P.J. Thompson, M.G. Thompson, S.R. Sanders. 1999. Partnering Measures. Journal of Management in Engineering 15(2) 37-42.
Crowley, L., A. Karim. 1995. Conceptual Model of Partnering. Journal of Management in Engineering 11(5) 33-39.
Dal Bo, P., A. Foster, L. Putterman. 2008. Institutions and Behavior: Experimental Evidence on the Effects of Democracy. Brown University.
Dutton, J.E., J.M. Dukerich, C.V. Harquail. 1994. Organizational Images and Member Identification. Admin Sci Quart 39(2) 239-263.
Dyer, J.H., W. Chu. 2000. The Determinants of Trust in Supplier-automaker Relationships in the U.S., Japan and Korea. Journal of International Business Studies 21(2) 259-285.
Dyer, J.H., W. Chu. 2003. The Role of Trustworthiness in Reducing Transaction Costs and Improving Performance: Empirical Evidence from the United States, Japan, and Korea. Organ Sci 14(1) 57-68.
Eccles, R.G. 1981. The Quasi-Firm in the Construction Industry. Journal of Economic Behavior and Organization 94(Supplement) s17-s51.
Elsbach, K.D. 1994. Managing Organizational Legitimacy in the California Cattle Industry: The Construction and Effectiveness of Verbal Accounts. Admin Sci Quart 39 57-88.
Elsbach, K.D., M.A. Glynn. 1996. Believing Your Own "PR": Embedding Identification in Strategic Reputation. Advances in Strategic Management 13 65-90.
Fireman, B., W.H. Gamson. 1979. Utilitarian Logic in the Resource Mobilization Perspective. M.N. Zald, J.D. McCarthy, eds. The Dynamics of Social Movements. Winthrop Publishers, Cambridge, MA, 8-45.
Flyvbjerg, B., N. Bruzelius, W. Rothengatter. 2003. Megaprojects and Risk: Anatomy of Ambition. Cambridge University Press, New York, NY.
Ghoshal, S., P. Moran. 1996. Bad for Practice: A critique of the transaction cost theory. Academy of Management Review 21(1) 13-47.
Gomez-Ibanez, J.A., D. Lorrain, M. Osius. 2004. The Future of Private Infrastructure Taubman Center for State and Local Government. Kennedy School of Government, Cambridge, MA.
Gorst, I. 2006. Mission Improbable Financial Times, London.
Gouldner, A.W. 1960. The Norm of Reciprocity: A Preliminary Statement. American Sociological Review 25(2) 161-178.
Granovetter, M. 1985. Economic Action and Social Structure:
The Problem of Embeddedness. American Journal of Sociology 91(November) 481-510.
Granovetter, M. 1992. Problems of Explanation in Economic Sociology. N.N.a.R.G. Eccles, ed. Networks and Organizations: Structure, Form and Action. Harvard Business School Press, Cambridge, 25-56.
Gransberg, D.D., W.D. Dillon, L. Reynolds, J. Boyd. 1999. Quantitative Analysis of Partnered Project Performance. Journal of Construction Engineering and Management 125(3) 161-166.
Greif, A., P. Milgrom, B. Weingast. 1994. Coordination, Commitment and Enforcement: The case of the merchant guild. J Polit Econ 102(4) 745-776.
Gross, C. 2007. Community perspectives of wind energy in Australia: The application of a justice and community fairness framework to increase social acceptance. Energy Policy 35(5) 2727-2736.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 15
Gunnarson, S., R.E. Levitt. 1982. Is a Building Construction Project a Hierarcghy or a Market. Proceedings of the Seventh INTERNET Congress Copenhagen, Denmark 521-529.
Hall, R.E., C.I. Jones. 1999. Why do some countries produce so much more output per worker than others? Quarterly Journal of Economics 114(1) 83-116.
Harback, H.F., D.L. Basham, R.E. Buhts. 1994. Partnering Paradigm. Journal of Management in Engineering 10(1) 23-27.
Helper, S., J.P. MacDuffie, C. Sabel. 2000. Pragmatic Collaborations: Advancing knowledge while controlling opportunism. Industrial and Corporate Change 9(3) 443-487.
Henisz, W.J. 2009. Preferences, Structure and Influence: The Engineering of Consent.
Henisz, W.J., B.A. Zelner. 2005a. Legitimacy, Interest Group Pressures and Institutional Change in Emergent Institutions: The Case of Foreign Investors and Home Country Governments. Academy of Management Review 30(2) 361-382.
Henisz, W.J., B.A. Zelner. 2005b. PowerTrip or Powerplay: AES-Telasi. The Wharton School, Philadelphia, PA.
Homans, G. 1958. Social Behavior as Exchange. American Journal of Sociology 62 597-606.
International Finance Corporation. 2007. Stakeholder Engagement: A Good Practice Handbook for Companies Doing Business in Emerging Markets, Washington DC.
Jones, C., W.S. Hesterly, S.P. Borgatti. 1997. A general theory of network governance: Exchange conditions and social mechanisms. Academy of Management Review 22(4) 911-945.
Kelly, A. 2006. The elements of influence : introducing the Playmaker's Standard : the new essential system for managing competition, reputation, brand, and buzz. Dutton, New York.
Kim, W.C., R.A. Mauborgne. 1991. Implementing Global Strategies - the Role of Procedural Justice. Strategic Management Journal 12 125-143.
Kim, W.C., R.A. Mauborgne. 1993. Procedural Justice, Attitudes, and Subsidiary Top Management Compliance with Multinationals Corporate Strategic Decisions. Acad Manage J 36(3) 502-526.
Kim, W.C., R.A. Mauborgne. 1995. A Procedural Justice Model of Strategic Decision-Making - Strategy Content Implications in the Multinational. Organ Sci 6(1) 44-61.
Kim, W.C., R.A. Mauborgne. 1996. Procedural justice and managers' in-role and extra-role behavior: The case of the multinational. Management Science 42(4) 499-515.
Kim, W.C., R.A. Mauborgne. 1998. Procedural justice, strategic decision making, and the knowledge economy. Strategic Management Journal 19(4) 323-338.
Kogut, B., U. Zander. 1992. Knowledge of the Firm, Combinative Capabilities, and the Replication of Technology. Organ Sci 3(3) 383-397.
Kogut, B., U. Zander. 1993. Knowledge of the Firm and the Evolutionary Theory of the Multinational Corporation. Journal of International Business Studies 24(4) 625-645.
Kogut, B., U. Zander. 1996. What Firms Do? Coordination, Identity and Learning. Organ Sci 7(5) 502-518.
Krick, T., M.F. M, P. Monaghan, M. Sillanpää. 2006. The stakeholder Engagement Manual: The Practitioners Handbook on Stakeholder Engagement. AccountAbility, the United Nations Environment Programme, and Stakeholder Research Associates.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 16
Larson, E. 1997. Partnering on Construction Projects: A Study of the Relationship Between Partnering Activities and Project Success. IEEE Transactions on Engineering Management 44(2) 188-195.
Latham, M. 1994. Constructing the Team. HMSO, London.
Lazar, F.D. 2000. Project Partnering: Improving the Likelihood of Win-Win Outcomes. Journal of Management in Engineering 16(2) 71-83.
Levitt, R.E., D.B. Ashley, R.D. Logcher. 1980. Allocating Risk and Incentive in Construction. ASCE Journal of the Construction Division 106(CO3) 297-305.
Levitt, R.E., R.D. Logcher, N.H. Qaddumi. 1984. The Impact of Owner- Engineer Risk-Sharing on Design Conservatism. ASCE Journal of Professional Issues in Engineering 110(4) 157-168.
Lind, E.A., T.R. Tyler. 1988. The Social Psychology of Procedural Justice. Plenum Press, New York, NY.
Lubatkin, M., P.J. Lane, S. Collin, P. Very. 2007. An embeddedness framing of governance and opportunism: towards a cross-nationally accommodating theory of agency. Journal of Organizational Behavior 28(1) 43-58.
Mayer, K.J., N.S. Argyres. 2004. Learning to Contract: Evidence from the Personal Computer Industry. Organ Sci 15(4) 394-410.
Mesquita, B.B.d., J.D. Morrow, R.M. Siverson, A. Smith. 1999. Policy Failure and Political Survival: The Contribution of Political Institutions. Journal of Conflict Resolution 43(2) 147-161.
Moran, T.H. 1974. Multinational Corporatuions and the Politics of Dependence: Copper in Chile. Princeton University Press, Princeton, NJ.
Ng, S.T., T.M. Rose, M. Mak, S.E. Chen. 2002. Problematic Issues Associated with Project Partnering: The Contractor Perspective. International Journal of Project Management 20 437-449.
Nickson, A., C. Vargas. 2002. The Limitations of Water Regulation: The Failure of the Cochabamba Concession in Bolivia. Bulletin of Latin American Research 21(1) 99-120.
Ouchi, W.G. 1980. Markets, Bureaucracies and Clans. Admin Sci Quart 25 129-141.
Perkins, J. 2004. Confessions of an Economic Hitman. Berret-Koeler Publishers, San Francisco, CA.
Polletta, F. 1998. Contending Stories: Narrative in Social Movements Qualitative Sociology 21 419-446.
Poppo, L., T. Zenger. 2002. Do Formal Contracts and Relational Governance Function as Substitutes or Complements. Strategic Management Journal 23 707-725.
Richman, B.D. 2005. How Community Institutions Create Economic Advantage: Jewish Diamond Merchants in New York American Law & Economics Association Annual Meeting.
Ring, P.S., A.H.V.d. Ven. 1992. Structuring Cooperative Relationships Between Organizations. Strategic Management Journal 13 483-498.
Sarkar, M., P.S. Aulakh, S.T. Cavusgil. 1998. The Strategic Role of Relational Bonding in Interorganization Collaborations: An Empirical Study of the Global Construction Industry. Journal of International Management 4(2) 85-107.
Schrage, M. 2000. Serious Play: How the World's Best Companies Simualte to Innovate. Harvard Business School Press, Boston, MA.
Scott, R.W. 2001. Institutions and Organizations, Second ed. Sage Publications, Thousand Oaks, CA.
Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery
Page 17
Scott, S.G., V.R. Lane. 2000. A Stakeholder Approach to Organizational Identity. The Academy of Management Review 25(1) 43-62.
Shrage, M. 2000. Serious Play: How the World's Best Companies Simualte to Innovate. Harvard Business School Press, Boston, MA.
Stinchcombe, A.L. 1985. Contracts as Hierarchical Documents. A.L. Stinchcombe, C.A. Heimer, eds. Organizational Theory and Project Management. Norwegian University Press, Bergen.
Suchman, M.C. 1995. Managing Legitimacy: Strategic and Institutional Approaches. Academy of Management Review 20 571-610.
Taylor, V., N.E. Whittier. 1992. Collective Identity in Social Movement Communities: Lesbian Feminist Mobilization. A. Morris, C. Mueller, eds. Frontiers of Social Movement Theory. Yale University Press, New Haven, CT, 104-129.
Thibaut, J., L. Walker. 1975. Procedural Justuce: A Psychological Analysis. L. Erlbaum Associates, Hillsdale NJ.
Weston, D.C., E. Gibson. 1993. Partnering-Project Performance in U.S. Army Corps of Engineers. Journal of Management in Engineering 9(4) 410-425.
Wilson, R.A., A.D. Songer, J. Diekmann. 1995. Partnering: More than a Workshop, a Catalyst for Change. Journal of Management in Engineering 11(5) 40-45.
Zucker, L.G. 1986. Production of trust: Institutional sources of economic structure, 1840-1920. Research in organizational behavior 8(1) 53-111.