Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery RAYMOND E. LEVITT Professor of Civil and Environmental Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University Stanford, CA 94305-4020 Email: [email protected] WITOLD J. HENISZ UPS Visiting Associate Professor of Civil and Environment Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 305 Stanford University Stanford, CA 94305-4020 Email: [email protected] and DANIEL SETTEL Research Assistant Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University Submitted to 2009 CONFERENCE ON LEADERSHIP AND MANAGEMENT OF CONSTRUCTION Fallen Leaf Lake, Lake Tahoe, California November 5-8, 2009

Levitt_Henisz_Settel[1]

Embed Size (px)

DESCRIPTION

DANIEL SETTEL Research Assistant Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University RAYMOND E. LEVITT Professor of Civil and Environmental Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241 Stanford University Stanford, CA 94305-4020 Email: [email protected] and Abstract Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery Page 2

Citation preview

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

RAYMOND E. LEVITT

Professor of Civil and Environmental Engineering Jerry Yang and Akiko Yamazaki Energy and Environment Building

473 Via Ortega, Room 241 Stanford University

Stanford, CA 94305-4020 Email: [email protected]

WITOLD J. HENISZ UPS Visiting Associate Professor of Civil and Environment Engineering

Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 305

Stanford University Stanford, CA 94305-4020

Email: [email protected]

and

DANIEL SETTEL Research Assistant

Jerry Yang and Akiko Yamazaki Energy and Environment Building 473 Via Ortega, Room 241

Stanford University

Submitted to

2009 CONFERENCE ON LEADERSHIP AND MANAGEMENT OF CONSTRUCTION Fallen Leaf Lake, Lake Tahoe, California

November 5-8, 2009

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 2

Abstract

Prior research on the governance of large infrastructure projects has emphasized the question of who

should own and operate long-lived infrastructure assets, comparing public and private organizations with

respect to productive efficiency or the distribution of welfare. Our ongoing research seeks to shift the

focus of this research to the question of how public or private organizations can best manage two distinct

kinds of governance challenges that occur systematically during the project shaping, implementation and

operation phases of such projects: (1) opportunism in the presence of displaced agency – i.e., conflicts

between the incentives of parties leading decision making in each of the successive and interdependent

phases of design, construction and operations that lead to sub-optimal investment and may lead them to

pursue their self-interest with guile; and (2) political and regulatory risk – i.e., ex post political

interventions in operational decisions. A model that incorporates the efficiency and legitimacy

consequences of governance decisions over the life of an infrastructure project thus offers substantial

gains on more piecemeal disciplinary approaches. We seek to develop a new typology of hybrid

governance mechanisms designed to alter the incidence of opportunism by counterparties or stakeholders

to a series of interconnected transactions. This paper lays out the two key governance challenges of

infrastructure projects in some detail, with examples of each, and points the way toward research on a

broader governance framework for such projects. Our conference presentation and future publications

will focus in greater depth on examples of both existing and proposed new hybrid governance

arrangements that must be studied, refined and implemented to address these challenges.

KEYWORDS: Infrastructure; governance; transaction costs; socio-political governance; displaced

agency; partnering; lean construction.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 3

Introduction

Scholars have long expressed dissatisfaction with the “sharp delineation of markets vs. hierarchies”

especially in networked, project-based industries like construction ( Gunnarsson & Levitt 1982;

Stinchcombe 1985; Bradach and Eccles 1989:97) and have offered myriad calls to pay more attention to

hybrid forms of organization in which relational contracting governed by trust complements or dominates

the mechanisms of price or authority. We argue that despite a clear awareness of the importance of

interpersonal or inter-organizational trust and a growing body of evidence that this trust alters

transactional governance and performance, we lack a clear understanding of the mechanisms by which

trust is developed and sustained in project networks.

Our ongoing research seeks to identify and offer examples of the following kinds of socio-

political governance mechanisms that alter the incidence of opportunism: the cultivation of a desire for

social status and avoidance of social sanction; the development and reinforcement of a common identity;

the adherence to precepts of distributive or procedural justice; the adherence to participatory models of

engagement; the alignment of social and interpersonal interests as well as economic interests; and the

deployment of influence strategies. We develop our theoretical arguments in the context of infrastructure

services, where trillions of dollars of investment are organized under conditions of extreme contractual

hazards via governance mechanisms that are neither market nor hierarchy. However, we conclude by

noting the broad applicability of these governance challenges and socio-political governance mechanisms.

Points of Departure

Our aim is to extend the frameworks presented by Stinchcombe (1985), Ouchi (1980) and Bradach &

Eccles (1989) to encompass a broader set of socio-political governance mechanisms that can generate

trust thereby allowing for a clan form of organization. Ouchi (1980:131) introduces the clan form by

noting that clan forms of organization that rely on goal congruence coexist with market and bureaucratic

forms of organization that use distinct mechanisms to overcome goal incongruence between principals

and agents. Ouchi closes his article by identifying tradition or other means of crafting legitimate social

authority, norms of reciprocity and common values and beliefs as factors associated with an increased

efficacy of the clan form. He cites utopian communities, military units, high technology or medical work

teams and historical employment relations between Japanese workers and business groups as examples of

such contexts.

Bradach and Eccles (1989) seek to deepen the insight provided by Ouchi (1980) by focusing on

the governance or control mechanisms that support these organizational forms. Instead of market,

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 4

bureaucracy and clans, their emphasis is on the distinction between price, authority and trust. They

explicitly build on Zucker’s (1986) depiction of the “Production of Trust” to examine how “(a) diffuse

social norms of obligation and cooperation, and (b) personal relationships that overlap with economic

exchanges provide the basis for trust.” (Bradach and Eccles 1989:105). They cite an expansive body of

evidence using varied methods and contexts that all highlight the power of long-term relations, in which

counterparties repeatedly observe each other observing norms of fairness, to reduce the incidence of

opportunistic behavior. They next survey literature demonstrating that “where economic transactions are

embedded in personal relationships the hazards of opportunism are diminished and the need for elaborate

formal governance structures is reduced or eliminated entirely.

Much research has built upon the foundation of these two seminal articles, but with limited

emphasis on the specific governance mechanisms that change states of mind. Rather, the emphasis has

been on the exploration of the question of whether trust is a substitute or a complement to more traditional

forms of governance (Mayer and Argyres 2004; Poppo and Zenger 2002). Moreover the focus of virtually

all this work has been on trust in bilateral relationships. In contrast, we seek to build on the path of

development pursued by Bradach & Eccles (1989) in further explicating the control or governance

mechanisms that generate trust to undergird problematic contracts. In the context of infrastructure projects,

this process leads us to explore not only bilateral exchange relationships but the relationships between a

broader network of direct and indirect stakeholders in a project-based industrial supply chain, linked by a

series of temporally sequenced contracts. This dual broadening of scope —development of trust across a

network vs. in a dyad, and sets of transactions that occur in an interdependent, temporally sequenced set

of relationships— led us to consider a wider range of mechanisms drawing from disparate disciplines but

unified in their goal of reducing the incidence of opportunism among multiple stakeholders. Before

turning to the depiction of these mechanisms, we introduce the specific context in which we develop our

arguments.

The Context of Infrastructure Projects

Two characteristics of infrastructure projects make them ideal for the development of a deeper

understanding of socio-political governance. First, they are typically produced by multiple counterparties

through a complex sequence of interlinked transactions. Second, infrastructure projects are inherently

highly politically salient, both because of their catalytic role in the process of development and their

centrality to a nation’s security and well-being. Given these characteristics, the governance of

infrastructure projects faces an extremely high level of two related contractual hazards: (1) opportunism

in the presence of displaced agency – i.e., conflicts between the incentives of parties leading decision

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 5

making in each of the successive and interdependent phases of design, construction and operations that

leads to sub-optimal investment and may lead them to pursue their self-interest with guile; and (2)

political and regulatory risk – i.e., ex post political interventions in operational decisions.

Temporally the provision of infrastructure services typically proceeds through phases of project

shaping, detailed design, construction and operation. While transactions between counterparties in each of

these transactions may appear bilateral and discrete, they implicitly include counterparties to and

stakeholders in the full sequence of temporally linked transactions, and thus cannot be examined in

isolation from each other. So a more traditional transaction cost analysis, which would examine one

discrete transaction or a series of recurring transactions of a given type in isolation, is problematic.

Instead, we simultaneously analyze the series of temporally linked and bundled, distinct, sequential

transactions involved in the provision of infrastructure services. The supplier and buyer in any one

transaction can and do opportunistically shift the burden of costs and the distribution of benefits across

the sequence of related transactions. Furthermore, they appeal to political and regulatory actors to

intervene directly or at the behest of a counterparty or stakeholder in any of the related transactions (e.g.,

current and future end users, bearers of externalities, taxpayers, bondholders and other suppliers) in ex

post efforts to alter the distribution of rents resulting from ex ante investments. We next review specific

manifestations of opportunism within each phase of the lifecycle of infrastructure projects to illustrate the

magnitude of the governance challenge in infrastructure services.

Opportunism Across the Project Life-Cycle

Project Shaping. In the project shaping phase, planning consultants are typically paid a fixed fee or

reimbursable fee with fixed profit for their services by the project sponsors—the government agency

acting as the owner-developer or the private consortium providing the equity investment and management

of the project. If the projects go ahead based on planning stage estimates, these consultants are well

placed to receive much larger contracts for detailed design and construction supervision on these projects,

as well as future planning contracts from these and other sponsors. In the public sector, half-completed

infrastructure projects become such a source of public embarrassment that governments—typically future

governments—tend to find funds to complete them, blaming the cost overruns on their predecessors and

taking credit for rescuing the failed projects. In the private sector, equity holders can often renegotiate

terms with lenders to help them recover at least some of their potential losses from costs over-runs and

demand under-runs—as was done in the case of the Channel Tunnel. So there are typically strong

incentives for infrastructure planning consultants to align their behavior to serve the interests of

politicized public and private sector promoters—including local governments, engineers, contractors,

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 6

construction labor unions, local chambers of commerce, etc.—tending systematically to overestimate

demand and underestimate construction cost.

As a result, estimates of demand even for local public works projects in developed countries are

notoriously optimistic; and estimates of construction costs tend to be even more so, resulting in “Bridges

to Nowhere” that exceed their estimated costs by many times.1

The Channel Tunnel between England and France is a good example of a common pattern in

infrastructure projects. This project exceeded its cost estimate of £2.6 Billion by almost 80%; its

financing costs were 140% of estimated costs; and its passenger trip demand in the first year of operation

was just 18% of the forecasted demand (Flyvbjerg et al, 2003). As a result, the Channel Tunnel has gone

through multiple rounds of refinancing, and is just beginning to show a profit in 2009—some 15 years

after commencement of operations!

The true costs for these projects are

deferred to future users or taxpayers whereas the political benefit from potential future counterparties and

stakeholders for their announcement is received in the present. Thus, the current principals—the local or

regional development agencies or private sponsors and their agents (i.e., the planning consultants)

opportunistically collude—explicitly or implicitly—to initiate the development of myriad projects whose

long-run economic and political feasibility is sometimes dubious at best.

Design. Local governments, working with their design consultants during the detailed design

phase then intervene to “gold plate” (i.e., overdesign) the proposed facilities in order to create even

miniscule savings in operating costs that will be borne exclusively or largely by the local communities

that they represent at the expense of potentially drastic increases in the up-front construction costs borne

largely by grants from a regional or national infrastructure agency. For example, a study of design

decision-making on a major urban transit project, found that the local transit agency sought to eliminate

the operational cost of pumping water out of a tunnel by specifying that the tunnel should have zero

leakage. The engineers on this project, facing liability in the event of any leakage, specified a 12-inch

thick concrete lining for tunnels, far beyond what was needed for structural support, at a cost of millions

of dollars per mile (Levitt et al 1980). Private design consultants, or government professional engineers

have strong incentives to go along with such overdesign, and design conservatively in order to avoid

1 A large meta-study of dozens of large infrastructure projects worldwide confirmed this consistent overestimation of demand and underestimation of cost for transportation projects all around the globe by governments and their planning consultants— the “economic hit men”— over the last several decades (Flyvbjerg et al. 2003)

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 7

potential professional liability suits for failures of any kind (Levitt et al 1980; 1984). They have few

incentives to design aggressively to limit construction costs: they work on reimbursable fee contracts and

any overdesign tends to be imperceptible to taxpayers within or outside the project service area.

Construction. Construction under typical firm-fixed-price or fixed unit price contracts necessarily

creates an adversarial relationship between the client, often represented by the engineer as its agent, and

the contractor. The contractor is incentivized by such contracts to complete the project at minimal cost

while meeting —but not exceeding— the minimum design specifications. Conversely, the client and its

engineer are incentivized to insure that the contractor meets or exceeds the minimum design

specifications at the lowest cost to the client. Any ambiguity or discrepancy among the multiple sets of

plans and specifications produced by multiple, fragmented, specialist designers creates an opportunity for

honest or opportunistic “change order” negotiation by the contractor to increase payments and allowable

completion time. Contractors submit "Requests for Information" (RFIs) to clarify such inconsistencies;

these often escalate into "Change" requests by the contractor for extra time and money, which must be

formalized by the owner through negotiated “Change Orders” to the original contract. Negotiations about

the legitimacy and magnitude of change orders can then further escalate into arbitration or litigation

(“Claims”) if not settled to the contractor’s satisfaction. Thus, when contractors spot inconsistencies in

bidding documents, they are motivated not to raise questions about any perceived errors or omissions

prior to the bid, but rather use this information to bid low, capture the project, and then seek additional

compensation via change orders after work has commenced and they “discover” the discrepancies.

Operations. Whereas economic models clearly highlight the efficiency of market-based pricing

for infrastructure services, the political and social sustainability of such pricing models is an open

question even in countries where the sanctity of contracts is a widely supported norm. When prices or

shareholder returns are perceived to be “too high” relative to ability or willingness to pay of consumers or

stakeholder’s perception of “fairness” in the current economic environment, direct or indirect political

pressure to renegotiate the terms of the deal is likely to follow, irrespective of the formal independence of

the regulatory authority, sophistication of the contractual guarantees invoking security bonds in offshore

bank accounts, contractually required arbitration under foreign law, appeal to a bilateral investment treaty

or letter of comfort, or the sophistication of the financial hedges including public or private political and

regulatory risk insurance.

The drivers of these perceptions are not limited to the cost of service provision, the availability of

substitutes or the opportunity cost of capital. Rather, they include such peripheral factors as the degree of

economic hardship born by consumers or impacted stakeholders, the nationality of the service provider,

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 8

the past price history of the service and the reputation of the government and intermediaries associated

with the design, implementation and operation of the infrastructure provider. Both sides frequently invoke

public safety, fairness, and other broadly accepted norms in these disputes, seeking to build a coalition of

political and social support for their true desired position—i.e., a greater share of the rents at the expense

of their counterparty. Given a 30-year to 50-year lifespan of infrastructure assets that typically spans

multiple changes of governments, it is simply impossible for governments to credibly commit to contracts

that remove these political elements of market risk.

An infrastructure owner’s or operator’s foreign identity can also aggravate perceptions of

unfairness or illegitimacy by local stakeholders (Gomez-Ibanez et al. 2004). Consider the case of the

water supply project in Cochabamba, Bolivia where the government granted a concession to a consortium

of foreign companies for the city’s water services. As soon as the private concessionaire began operations

in November 1999, protests arose over the project. Tariffs had increased substantially by the new

operators to cover the full capital costs of supply improvements. Additionally, the concession granted the

consortium exclusive rights to all water resources in the city. As a result, well-established alternative

water sources including privately-owned wells and storage tanks and tanker-based vendors were to be

phased out over time. After six months of road blocks, strikes, and public demonstrations, the Bolivian

government cancelled the concession contract. Nickson and Vargas (2002) suggest that, for the Bolivian

population, the project represented “a preference for foreign capital over the national interest” in a

country with “a long tradition of anti-imperialist rhetoric.” Foreign firms delivering, treating and selling

water for profit and imposing limits on groundwater pumping by local farmers flew in the face of local

cognitive-cultural institutions (Scott 2001) that “water is a basic, natural right of citizens.” This “Yanqui

Imperialist” project became a lightning rod for many other East vs. West, urban vs. rural and

European/Mestizo vs. indigenous political fault lines in Bolivia, and helped to foment the revolution that

put Evo Morales in power in 2006.

These examples of displaced agency and lack of political legitimacy show some of the unique

governance challenges for these long-lived, highly asset-specific, near-natural monopoly projects. Next,

we draw out some theoretical limitations of conventional governance approaches in addressing these

challenges.

Limitations of Conventional Governance

The construction management literature has followed the logic of transaction cost economics in arguing

that a typical construction project, with its delayered system architecture and fragmented supply-chain,

has some of the characteristics of both markets and hierarchies (Eccles 1981; Gunnarson and Levitt 1982).

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 9

Opportunistic behavior can, it has been argued, be mitigated in hierarchical governance structures when

all of the lifecycle project costs and benefits of a project are born by a single entity—i.e. the local

government agency or private entity that will design, build, operate and maintain the facility over an

extended period. Alternatively, the opportunistic behavior can be mitigated through carefully specified

contractual incentives with appeal to neoclassical contracting. We argue that both of these governance

mechanisms are partial solutions that fail to fully address the underlying hazard of opportunistic behavior

by counterparties distant to the immediate transaction. At the extreme, a reliance on hierarchical

governance (typically by governments) or neoclassical contracting only shifts the burden of costs to

increasingly distant and diffuse actors who lack the capacity to assess the risks they are taking on or

monitor the underlying behavior of the counterparties and properly incentivize them to eschew

opportunistic behavior.

Hierarchy. A design-build construction contractor unifies detailed design and construction

services and tenders a proposal to the client to maximize the value that can be delivered for a given

budget. The client then picks the design-build tender —typically from a joint venture of one or more

construction firms and design firms— that appears to offer them the greatest value. In addition Design-

Build contracting allows construction to begin before design is complete, with the potential to save

considerable time over a more conventional, sequential Design-Bid-Build approach. However, only

relatively sophisticated construction buyers can specify their requirements well enough at the conceptual

design stage to pick a “Design-Build” or “Engineer, Procure and Construct” (EPC) contractor that will

optimally satisfy its needs and wants for the project. As a result, this approach tends to be used for

relatively well specified facilities like industrial plants, warehouses, standard office buildings, highway

segments or bridges by large manufacturing services companies (e.g., Dow, DuPont, Exxon-Mobil, Bank

or America, Google, Intel) or large governmental agencies (e.g., the General Services Administration in

the US that purchases or leases buildings for use by most Federal agencies; state highway agencies;

regional mass transit agencies; large school boards; and the like). These sophisticated construction buyers

develop a series of similar facilities over time, so they can develop the in-house expertise to specify their

requirements clearly and unambiguously enough to exploit this mode of contracting successfully. For

other buyers, the subsequent buyer’s remorse at what they have bought, or the ex post renegotiation costs

incurred with the Design-Build construction contractor can outweigh the savings in time and the increases

in value from alleviating the agency problem between the design vs. construction actors, if acting

independently.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 10

One solution to this problem is to further extend the scope of the Design-Build construction

organization both upstream and downstream so that the same entity finances, designs, builds, owns and

operates the facility. This further internalization, however, can generate yet another conflict in which the

ultimate costs of the project are passed onto third parties — the end users—who are unable to assess the

risks that they are bearing accurately, or have no choice but to accept them. When a contractor or

contractors that will design and build the project also represent part of the consortium financing the

project, they have two ways to make profit: payment for their design-construction services, and income

from their share of the investment returns for the operation of the facilities. The English Channel Tunnel

(“Chunnel”) project is an egregious example of this conflict of interest problem.

Neoclassical Contracting. Few if any public or private organizations are capable or willing to

internalize the full set of transactions involved in infrastructure provision. Thus, some form of market

exchange in which opportunistic behavior can arise seems inevitable. One means to mitigate opportunism

in such transactions is through the use of external commitment or bonding mechanisms such as an appeal

to the judicial system, financial guarantors such as surety bonding companies, or credible third party

dispute resolution of detailed contractual commitments. While in theory, the reliance on independent and

impartial third party rulings could resolve the inherent uncertainty in complex and always incomplete

contingent contracts, one or both parties may face incentives to tilt the playing field in its favor by

directly or indirectly stimulating political intervention in the dispute. The aim of such influence tactics is

typically to avoid the uncertainty of the dispute resolution process and use political or regulatory

intervention to secure a more favorable and potentially expeditious outcome. We offer three examples of

such opportunistic behavior below. Note, in each case, the shift from a focus on the legal elements of a

potential dispute to its perceived fairness or legitimacy.

The history of the State Route 91 (SR-91) express lanes in Orange County, California highlights

the implicit hazards of trilateral governance of infrastructure projects even in countries with well

developed legal systems and property rights. The bondholders of the project demanded a strong non-

compete clause in the PPP contract, which blocked the California State Transportation Department

(Caltrans) from making any improvements to the SR-91 free lanes that could increase their capacity, and

thereby undermine the revenue received by the toll road operator. The clause was invoked when Caltrans

proposed a number of improvements to the free lanes in order to "alleviate safety concerns." In response

to this proposal by Caltrans, CPTC filed a lawsuit against Caltrans in March 1999, claiming that the

improvements were actually disguised efforts to increase capacity and, therefore, constituted a violation

of the non-compete clause. Caltrans’ actual intentions remain unclear and, in practice, it is often difficult

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 11

to separate safety improvements from capacity increases. Although Caltrans and CPTC were able to

reach a settlement, the combination of the lawsuit and a steep increase in tolls for the use of the road at

peak commute times led to growing protests, and the labeling of the toll lanes as the “Lexus lanes”.

There were also allegations at the time that CPTC had filed the lawsuit in order to win the approval of

Caltrans for a sale of the express lanes, which were performing relatively poorly as an investment. The

rigid PPP agreement had failed to provide a means to renegotiate terms of the partnership as traffic

conditions evolved.

A more extreme case of the limits of external contractual support can be found in the case of

independent power projects in Southeast Asia, where many governments wooing private power investors

in the early and mid-1990s offered contracts that insulated investors from commercial risk, fuel supply

risk, exchange rate risk, currency conversion risk, regulatory risk and the risk of political force majeur.

When the East Asian financial crisis occurred in 1997, it brought private power investors’ favorable

treatment into sharp relief as currency values, share prices and electricity demand all plummeted. The

obligations that the governments of the struggling countries had previously undertaken to attract private

investors now had little apparent benefit, and political officials were left in the tenuous position of having

to choose between honoring the contracts, at the risk of compromising their own popular support, or

renegotiating contracts in order to maintain support. Despite the comprehensive set of covered risks it

became increasingly clear that, in the words of one interviewee, “the government has the ability to make

us healthy or unhealthy. It’s a government decision.” In September 1998, President Habibe announced his

intention to eliminate 13 of the 26 IPP contracts “without significant compensation” and six more “with

some compensation.” (Henisz and Zelner 2005a)

Discussion

The examples described above illustrate a series of severe and recurring challenges to traditional forms of

project governance for infrastructure development and delivery projects, arising from several underlying

attributes of these projects and the industry that develops and delivers infrastructure assets. Displaced

agency problems arise from the cycling in and out across successive project phases of the “project” of

multiple supply chain participants playing different roles, and whose interests can be in direct conflict

both within a project phase and across project phases. The broad scope of the potential counterparties

makes it extremely difficult to balance interests even at a single point in time; and it makes it especially

difficult to continually realign contractual terms to sustain the balance of interests among parties over the

decades-long lifecycle of such projects as global, regional and local technologies, economies and politics

change in important ways. Finally, the strategic impact of large infrastructure assets on communities and

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 12

whole countries invokes the intervening or moderating presence of governments in infrastructure disputes

such as those described above. This always present specter of governmental intervention—even in liberal

market economies like the US—overwhelms the power of contracts, whether backed by domestic courts

or international arbitration and dispute resolution even of the most sophisticated kind, when individuals or

groups can choose to appeal to political rather than legal resolution of perceived imbalances in costs and

benefits that may arise over time. Clearly a richer set of mechanisms than contracts and hierarchical fiat

is needed to make such projects predictably governable.

Investors and host governments grappling with the risks posed by such significant socio-political

governance challenges need to respond in kind. They need to complement legal, financial and

organizational mechanisms of governance with broader socio-political governance instruments. These

instruments can facilitate adaptation not only by explicit economic counterparties but also by implicit

economic, political and social counterparties. In addition to the power of legal fiat enjoyed by hierarchy

and the economic incentives enjoyed by market, we seek to draw attention to the power of social ties and

common identity in shaping the behavior of all parties in a manner that highlights collective interest,

develops real trust and attenuates opportunistic behavior, without incurring the administrative costs and

lost incentive intensity of full-scale vertical integration or the high transaction costs and ultimate failure

of complex contingent contracts with cross-national trilateral governance.

Toward Socio-Political Governance

Our ongoing research will draw upon complementary insights from multiple disciplines in the

development of enhanced governance frameworks. Future publications will present ideas from: social

exchange theory, which shares our focus on the relationship versus the transaction as the unit of analysis;

and social control and sanctioning mechanisms, such as the construction of a collective identity (Dutton et

al. 1994), restricted access to outsiders, socialization, sanctions and reputation (Jones et al. 1997), norms

of reciprocity (Adams 1965; Gouldner 1960), and adherence to principles of distributive justice (Blau

1964; Homans 1958) and procedural justice (Lind and Tyler 1988; Thibaut and Walker 1975).

Our conference presentation will describe the use of cooperatives to govern the operation of clean

water distribution infrastructure— historically one of the most challenging of all infrastructure sectors to

govern both efficiently and sustainably— as an example of a hybrid market, hierarchy and socio-political

governance framework that has recently experienced considerable success in the face of failures like the

one described in Cochabamba, Bolivia of traditional approaches, including Private-Public Partnership

(PPP) governance approaches, for this sector.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 13

REFERENCES

Adams, J.S. 1965. Inequity in Social Exchange. L. Berkowitz, ed. Advances in Experimental Social Psychology. Academic Press, New York, NY.

Anglo American PLC. 2003. SEAT Socio-Economic Assessment Toolbox. Anglo American PLC, London.

Arnstein, S.R. 1969. A Ladder of Citizen Participation. Journal of the American Institute of Planners 35 216-224.

Auty, R.M. 1993. Sustaining Development in Mineral Economies: The Resource Curse Thesis. Routledge, London.

Bailey, K., T. Grossardt, J. Ripy, L. Toole, J.B. Williams, J. Dietrick. 2007. Structured Public Involvement in Context-Sensitive Large Bridge Design Using Casewise Visual Evaluation: Case Study of Section 2 of Ohio River Bridges Project Transportation Research Record: Journal of the Transportation Research Board 2028(3) 19-27.

Barlow, J. 2000. Innovation and Learning in Complex Offshore Construction Projects. Res Policy 29 973-989.

Barnard, C.I. 1968. The Functions of the Executive, Thirtieth Anniversary Eddition ed. Harvard University Press, Cambridge.

Bayliss, R., S.-O. Cheung, H.C.H. Suen, S.-P. Wong. 2004. Effective Partnering Tools in Construction: A Case Study on MTRC TKE Contract 604 in Hong Kong. International Journal of Project Management 22 253-263.

Blau, P.M. 1964. Justice in Social Exchange. Sociological Inquiry 34(2) 193-206.

Bradach, J., R. Eccles. 1989. Price Authority and Trust: From ideal types to plural forms. Annual Review of Sociology 15 97-118.

Bresnen, M., N. Marshall. 2000a. Motivation, Commitment and the Use of Incentives in Partnerships and Alliances. Construction Management and Economics 18 587-598.

Bresnen, M., N. Marshall. 2000b. Partnering in Construction: A Critical Review of Issues, Problems and Dilemmas. Construction Management and Economics 18 229-237.

Chan, A.P.C., D.W.M. Chan, Y.H. Chiang, B.S. Tang, E.H.W. Chan, K.S.K. Ho. 2004. Exploring Critical Success Factors for Partnering in Construction Projects. Journal of Construction Engineering and Management 130(2) 188-198.

Cheng, E.W.L., H. Li, D.S. Drew, N. Yeung. 2001. Infrastructure of Partnering for Construction Projects. Journal of Management in Engineering 17(4) 229-237.

Cheung, S.-O., T.S.T. Ng, S.-P. Wong, H.C.H. Suen. 2003. Behavioral Aspects in Construction Partnering. International Journal of Project Management 21 333-343.

Chevalier, J.M., D. Buckles. 2007. SAS2 Process Management.

Choguill, C.L. 1996. Ten steps to sustainable infrastructure. Habitat International 20(3) 389-404.

Coleman, J.S. 1986. Social Theory, Social Research, and a Theory of Action. American Journal of Sociology 91 1309-1335.

Conner, K.R., C.K. Prahalad. 1996. A Resource-based Theory of the Firm: Knowledge Versus Opportunism. Organ Sci 7(5) 477-501.

Crane, T.G., J.P. Felder, P.J. Thompson, M.G. Thompson, S.R. Sanders. 1997. Partnering Process Model. Journal of Management in Engineering 13(3) 57-63.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 14

Crane, T.G., P.J. Thompson, M.G. Thompson, S.R. Sanders. 1999. Partnering Measures. Journal of Management in Engineering 15(2) 37-42.

Crowley, L., A. Karim. 1995. Conceptual Model of Partnering. Journal of Management in Engineering 11(5) 33-39.

Dal Bo, P., A. Foster, L. Putterman. 2008. Institutions and Behavior: Experimental Evidence on the Effects of Democracy. Brown University.

Dutton, J.E., J.M. Dukerich, C.V. Harquail. 1994. Organizational Images and Member Identification. Admin Sci Quart 39(2) 239-263.

Dyer, J.H., W. Chu. 2000. The Determinants of Trust in Supplier-automaker Relationships in the U.S., Japan and Korea. Journal of International Business Studies 21(2) 259-285.

Dyer, J.H., W. Chu. 2003. The Role of Trustworthiness in Reducing Transaction Costs and Improving Performance: Empirical Evidence from the United States, Japan, and Korea. Organ Sci 14(1) 57-68.

Eccles, R.G. 1981. The Quasi-Firm in the Construction Industry. Journal of Economic Behavior and Organization 94(Supplement) s17-s51.

Elsbach, K.D. 1994. Managing Organizational Legitimacy in the California Cattle Industry: The Construction and Effectiveness of Verbal Accounts. Admin Sci Quart 39 57-88.

Elsbach, K.D., M.A. Glynn. 1996. Believing Your Own "PR": Embedding Identification in Strategic Reputation. Advances in Strategic Management 13 65-90.

Fireman, B., W.H. Gamson. 1979. Utilitarian Logic in the Resource Mobilization Perspective. M.N. Zald, J.D. McCarthy, eds. The Dynamics of Social Movements. Winthrop Publishers, Cambridge, MA, 8-45.

Flyvbjerg, B., N. Bruzelius, W. Rothengatter. 2003. Megaprojects and Risk: Anatomy of Ambition. Cambridge University Press, New York, NY.

Ghoshal, S., P. Moran. 1996. Bad for Practice: A critique of the transaction cost theory. Academy of Management Review 21(1) 13-47.

Gomez-Ibanez, J.A., D. Lorrain, M. Osius. 2004. The Future of Private Infrastructure Taubman Center for State and Local Government. Kennedy School of Government, Cambridge, MA.

Gorst, I. 2006. Mission Improbable Financial Times, London.

Gouldner, A.W. 1960. The Norm of Reciprocity: A Preliminary Statement. American Sociological Review 25(2) 161-178.

Granovetter, M. 1985. Economic Action and Social Structure:

The Problem of Embeddedness. American Journal of Sociology 91(November) 481-510.

Granovetter, M. 1992. Problems of Explanation in Economic Sociology. N.N.a.R.G. Eccles, ed. Networks and Organizations: Structure, Form and Action. Harvard Business School Press, Cambridge, 25-56.

Gransberg, D.D., W.D. Dillon, L. Reynolds, J. Boyd. 1999. Quantitative Analysis of Partnered Project Performance. Journal of Construction Engineering and Management 125(3) 161-166.

Greif, A., P. Milgrom, B. Weingast. 1994. Coordination, Commitment and Enforcement: The case of the merchant guild. J Polit Econ 102(4) 745-776.

Gross, C. 2007. Community perspectives of wind energy in Australia: The application of a justice and community fairness framework to increase social acceptance. Energy Policy 35(5) 2727-2736.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 15

Gunnarson, S., R.E. Levitt. 1982. Is a Building Construction Project a Hierarcghy or a Market. Proceedings of the Seventh INTERNET Congress Copenhagen, Denmark 521-529.

Hall, R.E., C.I. Jones. 1999. Why do some countries produce so much more output per worker than others? Quarterly Journal of Economics 114(1) 83-116.

Harback, H.F., D.L. Basham, R.E. Buhts. 1994. Partnering Paradigm. Journal of Management in Engineering 10(1) 23-27.

Helper, S., J.P. MacDuffie, C. Sabel. 2000. Pragmatic Collaborations: Advancing knowledge while controlling opportunism. Industrial and Corporate Change 9(3) 443-487.

Henisz, W.J. 2009. Preferences, Structure and Influence: The Engineering of Consent.

Henisz, W.J., B.A. Zelner. 2005a. Legitimacy, Interest Group Pressures and Institutional Change in Emergent Institutions: The Case of Foreign Investors and Home Country Governments. Academy of Management Review 30(2) 361-382.

Henisz, W.J., B.A. Zelner. 2005b. PowerTrip or Powerplay: AES-Telasi. The Wharton School, Philadelphia, PA.

Homans, G. 1958. Social Behavior as Exchange. American Journal of Sociology 62 597-606.

International Finance Corporation. 2007. Stakeholder Engagement: A Good Practice Handbook for Companies Doing Business in Emerging Markets, Washington DC.

Jones, C., W.S. Hesterly, S.P. Borgatti. 1997. A general theory of network governance: Exchange conditions and social mechanisms. Academy of Management Review 22(4) 911-945.

Kelly, A. 2006. The elements of influence : introducing the Playmaker's Standard : the new essential system for managing competition, reputation, brand, and buzz. Dutton, New York.

Kim, W.C., R.A. Mauborgne. 1991. Implementing Global Strategies - the Role of Procedural Justice. Strategic Management Journal 12 125-143.

Kim, W.C., R.A. Mauborgne. 1993. Procedural Justice, Attitudes, and Subsidiary Top Management Compliance with Multinationals Corporate Strategic Decisions. Acad Manage J 36(3) 502-526.

Kim, W.C., R.A. Mauborgne. 1995. A Procedural Justice Model of Strategic Decision-Making - Strategy Content Implications in the Multinational. Organ Sci 6(1) 44-61.

Kim, W.C., R.A. Mauborgne. 1996. Procedural justice and managers' in-role and extra-role behavior: The case of the multinational. Management Science 42(4) 499-515.

Kim, W.C., R.A. Mauborgne. 1998. Procedural justice, strategic decision making, and the knowledge economy. Strategic Management Journal 19(4) 323-338.

Kogut, B., U. Zander. 1992. Knowledge of the Firm, Combinative Capabilities, and the Replication of Technology. Organ Sci 3(3) 383-397.

Kogut, B., U. Zander. 1993. Knowledge of the Firm and the Evolutionary Theory of the Multinational Corporation. Journal of International Business Studies 24(4) 625-645.

Kogut, B., U. Zander. 1996. What Firms Do? Coordination, Identity and Learning. Organ Sci 7(5) 502-518.

Krick, T., M.F. M, P. Monaghan, M. Sillanpää. 2006. The stakeholder Engagement Manual: The Practitioners Handbook on Stakeholder Engagement. AccountAbility, the United Nations Environment Programme, and Stakeholder Research Associates.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 16

Larson, E. 1997. Partnering on Construction Projects: A Study of the Relationship Between Partnering Activities and Project Success. IEEE Transactions on Engineering Management 44(2) 188-195.

Latham, M. 1994. Constructing the Team. HMSO, London.

Lazar, F.D. 2000. Project Partnering: Improving the Likelihood of Win-Win Outcomes. Journal of Management in Engineering 16(2) 71-83.

Levitt, R.E., D.B. Ashley, R.D. Logcher. 1980. Allocating Risk and Incentive in Construction. ASCE Journal of the Construction Division 106(CO3) 297-305.

Levitt, R.E., R.D. Logcher, N.H. Qaddumi. 1984. The Impact of Owner- Engineer Risk-Sharing on Design Conservatism. ASCE Journal of Professional Issues in Engineering 110(4) 157-168.

Lind, E.A., T.R. Tyler. 1988. The Social Psychology of Procedural Justice. Plenum Press, New York, NY.

Lubatkin, M., P.J. Lane, S. Collin, P. Very. 2007. An embeddedness framing of governance and opportunism: towards a cross-nationally accommodating theory of agency. Journal of Organizational Behavior 28(1) 43-58.

Mayer, K.J., N.S. Argyres. 2004. Learning to Contract: Evidence from the Personal Computer Industry. Organ Sci 15(4) 394-410.

Mesquita, B.B.d., J.D. Morrow, R.M. Siverson, A. Smith. 1999. Policy Failure and Political Survival: The Contribution of Political Institutions. Journal of Conflict Resolution 43(2) 147-161.

Moran, T.H. 1974. Multinational Corporatuions and the Politics of Dependence: Copper in Chile. Princeton University Press, Princeton, NJ.

Ng, S.T., T.M. Rose, M. Mak, S.E. Chen. 2002. Problematic Issues Associated with Project Partnering: The Contractor Perspective. International Journal of Project Management 20 437-449.

Nickson, A., C. Vargas. 2002. The Limitations of Water Regulation: The Failure of the Cochabamba Concession in Bolivia. Bulletin of Latin American Research 21(1) 99-120.

Ouchi, W.G. 1980. Markets, Bureaucracies and Clans. Admin Sci Quart 25 129-141.

Perkins, J. 2004. Confessions of an Economic Hitman. Berret-Koeler Publishers, San Francisco, CA.

Polletta, F. 1998. Contending Stories: Narrative in Social Movements Qualitative Sociology 21 419-446.

Poppo, L., T. Zenger. 2002. Do Formal Contracts and Relational Governance Function as Substitutes or Complements. Strategic Management Journal 23 707-725.

Richman, B.D. 2005. How Community Institutions Create Economic Advantage: Jewish Diamond Merchants in New York American Law & Economics Association Annual Meeting.

Ring, P.S., A.H.V.d. Ven. 1992. Structuring Cooperative Relationships Between Organizations. Strategic Management Journal 13 483-498.

Sarkar, M., P.S. Aulakh, S.T. Cavusgil. 1998. The Strategic Role of Relational Bonding in Interorganization Collaborations: An Empirical Study of the Global Construction Industry. Journal of International Management 4(2) 85-107.

Schrage, M. 2000. Serious Play: How the World's Best Companies Simualte to Innovate. Harvard Business School Press, Boston, MA.

Scott, R.W. 2001. Institutions and Organizations, Second ed. Sage Publications, Thousand Oaks, CA.

Defining and Mitigating the Governance Challenges of Infrastructure Project Development and Delivery

Page 17

Scott, S.G., V.R. Lane. 2000. A Stakeholder Approach to Organizational Identity. The Academy of Management Review 25(1) 43-62.

Shrage, M. 2000. Serious Play: How the World's Best Companies Simualte to Innovate. Harvard Business School Press, Boston, MA.

Stinchcombe, A.L. 1985. Contracts as Hierarchical Documents. A.L. Stinchcombe, C.A. Heimer, eds. Organizational Theory and Project Management. Norwegian University Press, Bergen.

Suchman, M.C. 1995. Managing Legitimacy: Strategic and Institutional Approaches. Academy of Management Review 20 571-610.

Taylor, V., N.E. Whittier. 1992. Collective Identity in Social Movement Communities: Lesbian Feminist Mobilization. A. Morris, C. Mueller, eds. Frontiers of Social Movement Theory. Yale University Press, New Haven, CT, 104-129.

Thibaut, J., L. Walker. 1975. Procedural Justuce: A Psychological Analysis. L. Erlbaum Associates, Hillsdale NJ.

Weston, D.C., E. Gibson. 1993. Partnering-Project Performance in U.S. Army Corps of Engineers. Journal of Management in Engineering 9(4) 410-425.

Wilson, R.A., A.D. Songer, J. Diekmann. 1995. Partnering: More than a Workshop, a Catalyst for Change. Journal of Management in Engineering 11(5) 40-45.

Zucker, L.G. 1986. Production of trust: Institutional sources of economic structure, 1840-1920. Research in organizational behavior 8(1) 53-111.