4
Receipt of Sum Rupees One Hundred Thirty Four Thousand(Rs.134,000.00) only from PLP Constructions of Welimada as consultation fees, between June 2007 and May 2007 in respect of the dispute with Urban Development Authority, regarding Contract No 14/01/130C/01, Shopping Complex at Welimada is hereby acknowledged. 09 February 2015 Eng. Nissanka De Silva, 39, Gunasekara Garden, Rajagiriya. NIC No: 292770022V Receipt of Sum of Rupees Two Hundred and Five Thousand (RS.205,000.00) only from PLP Constructions of Welimada as Consultation Fees, Between June 2007 and May 2009 in respect of the dispute with Urban Development Authority regarding Contract No. 14/01/130C/01, Shopping Complex at Welimada is hereby acknowledged. ___ February 2015 Eng. D.F.M. Perera

Letter

Embed Size (px)

DESCRIPTION

htrssh

Citation preview

Page 1: Letter

Receipt of Sum Rupees One Hundred Thirty Four Thousand(Rs.134,000.00) only from PLP Constructions of Welimada as consultation fees, between June 2007 and May 2007 in respect of the dispute with Urban Development Authority, regarding Contract No 14/01/130C/01, Shopping Complex at Welimada is hereby acknowledged.

09 February 2015

Eng. Nissanka De Silva,39, Gunasekara Garden,Rajagiriya.NIC No: 292770022V

Receipt of Sum of Rupees Two Hundred and Five Thousand (RS.205,000.00) only from PLP Constructions of Welimada as Consultation Fees, Between June 2007 and May 2009 in respect of the dispute with Urban Development Authority regarding Contract No. 14/01/130C/01, Shopping Complex at Welimada is hereby acknowledged.

___ February 2015

Eng. D.F.M. Perera Anderson Road,Kalubowila,

Dehiwala.

Page 2: Letter

14th February 2015

Chairman,Urban Development Authority,No. 06 & 07,Sethsiripaya,Battaramulla.

Dear Sir,CONSTRUCTION OF SHOPPING COMPLEX AT WELIMADA

Contract No:14/01/130C/01APPLICATION FOR FINAL PAYMENT CERTIFICATE

The Performance Certificate tendered to the Commercial High Court, Colombo on 28 January 2015, is case No: HC(Civil) 72/2012/ARB is acknowledged

02) Hence, as required by sub clause 14.9 of the conditions of contract, three(03) copies of the draft final statement is submitted herewith, as follows:

(i) Draft Final Statement and Summary(ii) Interest due on delayed payments Sub- Clause 14.6 = Annex 01(iii) Additional expenses incurred, Sub Clause 19.1 = Annex 02 (a) (b)(iv) Addition of VAT = Annex 03(v) Payments Received = Annex 04(vi) WHT, 1/3 VAT retained and stamp fees recovered from Payments = Annex 05

03) When payments due a 04 June 2007 were delayed and several reminders had no response, ICTAD was requested by our letter date 18-10-2007 to appoint an adjudicator in terms of sub clause 19.2. However, at your request mediation was agreed to instead of adjudication, strictly on the four(04) conditions set out in our letter date 12-10-2007. One of the said conditions was that the cost of mediation would be borne by you.

04) Accordingly, the additional expenses incurred from 04 June 2006, when settlement of the statement of Completion was due in terms of Sub Clause 14.8, during the period of mediation,

Page 3: Letter

upto commencement of Arbitration under sub-clause 19.5, in December 2009, is claimed as Item 13 in the draft final statement, supported by Annexes 2(a) and 2(b)

We shall be thankful of receipt of the documents referred to in para 02 above are acknowledged and action taken in terms of sub clause 14.9 to enable submission of the final statement for settlement.

Yours Faithfully,