Upload
hoyt-solomon
View
20
Download
0
Embed Size (px)
DESCRIPTION
LESSONS: RUSSIA URBAN TRANSPORT PROJECT. December 16, 2002 Brown-bag lunch seminar given by Slobodan Mitric on the occasion of the first-draft Implementation Completion Report for this project. LESSONS: RUSSIA URBAN TRANSPORT PROJECT. Original loan: $ 329 million Approved: 1995 - PowerPoint PPT Presentation
Citation preview
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
December 16, 2002
Brown-bag lunch seminar given by Slobodan Mitric on the occasion of the first-draft Implementation Completion Report for this project.
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Original loan: $ 329 millionApproved: 1995Effective: 1996Crisis: 1999Restructured: 2000Cancellations: $80 millionDisbursed: $249 million
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Acronyms, etc.:
– UPT urban public transport– PT public transport– UT urban transport– MoT Ministry of Transport– Oblast regional government
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Beneficiaries: PT companies in 14 citiesBorrower: Russian FederationSub-loan to cities, guaranteed by oblastsCities took foreign exchange riskAfter 1998-99 financial crisis, 6 cities
stepped out of the loan, unwilling or unable to service sub-loans
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Original components:– Bus/trolley-bus purchases $278.3 m (actual
$247.3m)– Vehicle rehabilitation: $40.90 million (actual
$44.75m)– Equipment: $8.9 million (actual $8.25)– Nat’l Spare Parts Program: $50 million
(canceled)– TA: $12.9 million (actual $7.97 m)
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Main physical outputs:– 1400 new buses– 38 new trolley-buses– 1400 vehicles rehabilitated– Misc equipment– Studies, workshops
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Objectives (nominal):– 1. Preserve essential UPT capacity in 14 cities by
linking financing of urgently needed vehicles and parts to the implementation of reforms
– 2. Strengthen UT institutions in client cities so as to improve efficiency of PT operations
– 3. Arrest decline of UPT throughout Russia through provision of spare parts
– 4. Provide restructuring advice to domestic bus industry
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Restated objectives:– 1a.Preserve essential UPT capacity in 14 cities– 1b. Shift the onus of financing UPT to passengers (cost
recovery to reach 40% in 1996)– 2a. Reform relation between public-owned UPT
operators & cities– 2b. Improve operations & maintenance of client
companies– 2c. Involve the private sector– 3. No change– 4. No change
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Unstated objectives:
5a. Assist MoT in preparing a national strategy for UPT sector
5b. Reform the vehicle procurement process
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Results:1a. UPT capacity: achieved (data lacking)1b. Cost recovery: achieved; results (49-105%)
exceed all expectations2a. Status of UPT operators (data lacking)2b. Efficiency of operators (data lacking)2c. Private sector involvement (data lacking)3. Canceled4. Bus manufacture: achieved
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Results (cont’d):– 5a. MoT-based UPT reform: achieved;
progress exceeding expectations– 5b. Vehicle procurement: achieved
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Overview of results:
- best results achieved re 1a and 1b, then 5a and 5b
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 1: ensure that formal objectives of the project include those linked to activities likely to require much time input during the supervision.
Example: work on vehicle specifications and
tender documents (objective 5a) took nearly all supervision budget in 1996-98 (but there was no nominal objective related to this)
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 2: (converse of Lesson 1) ensure that an objective is matched by supervision budget.
Example: all reform objectives (especially 2a,b,c) refer to cities, but working close with 14 cities was not feasible
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 3: ensure that institutional and policy objectives/covenants are matched with legal power to carry it out.
Example: cities in this project committed to carry out reforms for which they did not have the legal power
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 4: avoid weak and/or open-ended conditionality.
Example: “cities were to “take all the necessary measures to support the provision of transport services by private individuals or companies …”
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 5:Check whether any objectives may be conflicting?
Example: increasing cost recovery for public sector companies in this project turned out to be in conflict with increasing private PT operations (flight of paying passengers)
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 6: anticipate the peak in monitoring & evaluation needs at project’s end
Example: post-evaluation of bus investments at ICR stage not doable with available (Bank) budget, while the clients made no commitment to do it at their expense
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 7: do not let local sub-borrowers carry foreign-exchange risk in unstable macro conditions, when their revenues are in local currency
Example: due to ruble devaluation, bus contracts denominated in $ and DEM almost tripled in cities’ perception
LESSONS: RUSSIA URBAN TRANSPORT PROJECT
Lesson 8:
– Strive to end the project along an ascending curve to get a momentum in the reform process which will carry it well beyond the end of the loan