41
LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN CONSERVATION & HABITAT MANAGEMENT PLAN 27/11/2015 | Revision No: 5

LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

Embed Size (px)

Citation preview

Page 1: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 162

R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN 27/11/2015 | Revision No: 5

Page 2: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

Plan Revision Status

Date Revision

(in numbers) Purpose and Summary of Amendments Reviewed by Approved by

19/09/2014 1 Initial Draft

1/10/2014 1.1 Updated Phytophthora management

12/11/2014 2 Incorporated SEM comments

16/01/2015 3 Incorporated Dept of Defence Environmental Clearance Certificate requirements

16/03/2015 4 Incorporated ECC and EAR requirements

22/6/2015 5 Quarterly Review. No changes.

27/11/2015 5 Quarterly Review. No changes.

*Note that all printed paper/hard copies of this document and related procedures are uncontrolled. The controlled copy of this document is found either in Project Web, within the Project Management Plan section, or other project specific database/server approved by the Regional EHS Manager.

Page 3: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 3 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

CONSERVATION & HABITAT MANAGEMENT PLAN

Scope: This Conservation & Habitat Management Plan details protection and/or prevention measures to ensure that flora and fauna is managed appropriately during the construction phase. It defines mitigation measures to be implemented during relevant construction activities, a monitoring program that enables assessment of the impacts of construction activities on potentially affected areas, and contingency measures that may be implemented if required.

Objective:

To minimise any potential for impacts to the environment and/or natural habitats.

To conserve existing vegetation communities and native species present on site.

To protect any native fauna which may be identified on and/or adjacent to the site

To minimise the impact of any introduced fauna (i.e. vermin), or noxious flora (i.e. Weeds) or disease during construction.

Risks:

Native Vegetation

The project is situated at the Williamtown RAAF base, with components extending across a number of habitats.

The project footprint covers approximately 209 hectares, 81 hectares of which is largely cleared and modified grassland with minimal ecological value. The remaining naturally vegetated areas comprise an open forest / woodland and low woodland complex that are considered relatively high quality remnant natural bushland, both in terms of structure and the diversity of plant species. These areas provide food resources for a rich assemblage of nectivorous and insectivorous fauna including birds, mammals, reptiles and frogs. They also provide habitat (e.g. tree hollows) for a range of threatened fauna species known to occur in the area.

The project spans a number of native vegetation communities

Bro

ad-le

aved

Pap

erba

rk/

Sw

amp

Mah

ogan

y

Sw

amp

fore

st/w

oodl

and

Dro

opin

g R

ed

Gum

low

woo

dlan

d

com

plex

Reg

ener

atin

g

coas

tal d

une

fore

st

Scr

ibbl

y G

um

open

fore

st/

woo

dlan

d

Sm

ooth

-bar

ked

App

le/R

ed

Blo

odw

ood/

+-

Scr

ibbl

y G

um

open

fore

st/w

oodl

and

Tal

l ope

n sh

rub

land

Whi

te

Str

ingy

bark

low

open

fore

st

North-south access road (Zone A)

High explosives preparation facilities (Zone A)

Proposed Construction access road (Zone B)

NACC operational precinct (Zone C)

SE Runway Extension (Zone D)

NW Runway Extension (Zone G)

The northern ORP site (Zone G)

Page 4: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 4 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Threatened Flora:

Two threatened plant species have been identified in the project area, the Drooping Red Gum and Dwarf Kerrawang. Both are Commonwealth and NSW listed threatened species,

The Drooping Red Gum (Eucalyptus parramattensis subsp. Decadens) has been recorded throughout the Drooping Red Gum low woodland complex and as scattered trees across some areas of Smooth-barked Apple/Red Bloodwood and Scribbly Gum Open Forest and Scribbly Gum Open Forest. This species occupies an area of approximately 6 hectares within areas of the project footprint that require clearing. Within the operational area of the Base species were fragmented and located in highly modified vegetation communities.

Dwarf Kerrawang (Rulingia prostrata) has the potential to occur in the study area despite not being located during the field surveys. Previous field surveys recorded a number of individuals within the OLA footprint on land rehabilitated after sand mining.

Page 5: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 5 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Threatened Fauna:

Two threatened fauna species were positively recorded from the field investigations: the Koala (Phascolarctos cinereus) and Wallum Froglet (Crinia tinnula); both listed as vulnerable species under schedule 3 of the Threatened Species Conservation Act 1995 (NSW).

Koala (Phascolarctos cinereus) Status - Venerable NSW & Cwlth The Scribbly Gum, Drooping Red Gum and Swamp Mahogany are preferred habitat of Koalas. Field surveys within the confines of the Base identified evidence of one Koala individual, further studies will be required to assess koala numbers in the EO and NW runway sections of the project.

Wallum froglet (Crinia tinnula) Status - Venerable NSW The freshwater swamp habitat located to the north-west of the NACC Facilities and adjacent to the proposed access road support a large population of the threatened Wallum froglet (Crinia tinnula), as well as, a diversity of ground and tree-frogs. Freshwater swamp habitat occurs throughout lower lying areas of Low Woodland and Wet Shrubland Complex, with the size of the swamps varying from several square metres to several hectares. Water levels in the swamps are expected to fluctuate seasonally depending on rainfall. The Wallum froglet has also been recorded in flooded areas in the vicinity of the NACC Precinct during wet conditions.

Page 6: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 6 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Other threatened species that may be encountered include:

Grey-headed Flying-Fox (Pteropus poliocephalus) Status - Venerable NSW & Cwlth Occupy a wide range of habitats of tropical and sub-tropical forests and woodlands, as well as urban remnants and landscapes. Foraging habitat is widely distributed through the area and local records occur in proximity. Foraging individuals are expected to occur in the locality, although no roosting colonies recorded.

Squirrel Glider (Petaurus norfolcensis) Status - Venerable NSW Prefers forest and woodland habitats, particularly areas with a diversity of eucalypt species in the canopy and other suitable food resources (shrubs and small trees). Requires tree hollows for denning.

Long-nosed Potoroo (Potorous tridactylus) Status - Venerable NSW Preferred habitat is open forests and heath on sandy soils

Pests, weeds and disease

Several weed species of national significance including the Bitou Bush (Chrysanthemoides monilifera) and Lantana (Lantana camara) have been identified on the base

Pests occurring at the Base include rabbits, hares, foxes, cats, birds and rodents. Macropods (i.e. Red Neck Wallabies and Eastern Grey Kangaroos) are a problem for the safety of operating aircraft. Phytophthora cinnamomi (Pc) a soil borne fungus that can cause dieback of native vegetation has been identified at the Base. The Northwest ORP, elements of the proposed access road and EO area and NW runway take-off and landing clearance are located in high risk Pc areas Myrtle Rust, although not detected on the Base had been detected on the Central Coast and across eastern NSW. Myrtle Rust is an exotic fungus from South America which infects the leaves of plants from the Myrtaceae family (e.g. Gum trees (Eucalypts), Bottle Brush, Tea Tree etc.) leading to the loss of leaves and death of plant.

Page 7: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 7 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Work in areas of Pc risk requires a strict hygiene and management protocol to manage the risk of spreading the infection.

The key aspects of the Project that could result in adverse impacts on flora and fauna include:

clearing activities;

establishment of ancillary facilities such as stockpile sites, compounds and sediment basins;

construction of waterway crossings;

construction of drainage structures;

chemical usage near waterways and sensitive vegetation;

inadequate or absent erosion and sediment control devices;

exposure of disturbed areas;

delivery and movement of plant and equipment; and

changes in hydrology and drainage regimes.

The potential flora and fauna impacts that may occur during construction include:

loss of habitat value and biodiversity;

reduction in plant numbers and diversity;

barrier to normal fauna movement/migration;

direct mortality and injury to fauna;

damage or death of individual plants due to physical impact;

fragmentation of habitat and decrease in connectivity and fauna passage as a result of vegetation clearing;

disease and weed infestation;

aircraft bird / macropod strike,

increases in pest / vermin such as rabbits, rats and foxes

decline in aquatic habitat quality through changes in water course, decline in light penetration and inadequate erosion and sediment control.

Key Legislation / Standards / Guidance

Commonwealth:

Environmental Protection and Biodiversity Conservation Act 1999

Environmental investigations have concluded that the project is not likely to have significant adverse impacts on flora and fauna or indigenous and non-indigenous heritage; however a general permit under Section 201 of the EPBC Act is required for activities that may kill or injure a listed threatened species or ecological community.

State:

While state legislation does not apply to Defence activities, Defence aims to be good environmental stewards and comply with State government legislation and policies to the extent that these do not conflict with Commonwealth legislative obligations or compromise operational objectives or capability.

Page 8: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 8 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

NOTE: State Legislation does apply to Activities carried out outside of Defence land. The relevant State environmental legislation and planning instruments are described below.

Protection or the Environment Operations Act 1997 (POEO Act)

Regulates air, noise and water pollution and transport and disposal of waste in NSW

Threatened Species Conservation Act 1995 (TSC Act)

Provides for the protection of critical habitat and threatened species, populations and ecological communities and their habitats in NSW. Where significant impacts are likely the TSC Act requires a Species Impact Statement (SIS) be prepared. Assessments carried out for this project under TSC Act requirements concluded that no significant impacts on threatened species, populations, endangered ecological communities or their habitats as a result of the project provided mitigation measures were implemented. As such no SIS is required.

Native Vegetation Act 2003 The Native Vegetation Act 2003 (NV Act) aims to prevent broad scale clearing to protect native vegetation of high conservation value and to improve the conditions of existing native vegetation An assessment of the clearing required for the project was undertaken and concluded that there would be no significant impacts on native vegetation as a result of the project provided mitigation measures were implemented.

Noxious Weeds Act 1993 The Noxious Weeds Act 1993 (NW Act) provides for the classification and management of noxious weeds and places obligations on owners and occupiers of land to control and prevent the spread of such weeds.

National Parks and Wildlife Act 1974(NP&W Act) The National Parks and Wildlife Act 1974 provides for the establishment and management of National Parks, reserves, historic sites and for the protection of native fauna, flora and Aboriginal heritage. Under Part 7 it is an offence to harm protected fauna unless done so under a license, permit or in accordance with a conservation agreement. Under Part 8A, it is an offence to harm, pick, buy, sell or damage listed threatened species, populations and ecological communities and their habitats, or critical habitats without

approval. Under Section 90 of the Act, it is an offence to knowingly destroy, deface or disturb an Aboriginal object or place without approval.

SEPP 44: Koala Habitat SEPP 44 encourages the conservation and management of natural vegetation that provide habitat for koalas to ensure permanent free-living populations are maintained over their present range. Local councils cannot approve development in an area affected by the policy without an investigation of core koala habitat. Assessments have concluded that the project will not have a significant impact on the Koala.

Defence Policy and Procedures:

Ecologically Sustainable Development Strategy.

Defence Instructions aimed at ensuring compliance with the EPBC Act and other Standing Instructions and Standard Operating Procedures which address environmental management aspects associated with the project.

Environmental Management System (EMS).

Environmental Clearance Certificate

Page 9: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 9 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Site Control Measures:

The installation and maintenance of Conservation and Habitat controls during the construction and demolition phase shall be accordance with the following table.

All controls are to be, as a minimum, consistent with the Managing Contractor Building Means & Methods for Physical GMRs 8.4

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

General See Zoning Plan

Ecological studies of the project area will be carried out prior to construction, the findings of these studies will be incorporated into the EHS plan

Before construction

Ecological Consultants engaged to conduct surveys and produce report

CM Environmental Impact Assessment Reports and Ecological Impact Assessment

Reports completed and approved

All

Changes in design that may impact on threatened species, populations or endangered ecological communities will be notified to Defence Senior Environmental Manager (SEM)

At all times Consult with the Defence Senior Environmental Manager (SEM) if such design changes are proposed, eg changes to fence alignments in retained flora areas

Environmental Manager Design and environmental approval documentation

Consultation carried out as part of design and approval process

All

Training on the requirements of this plan will be provided to all personnel, including sub-Sub-contractors.

At all times Site induction, toolbox talks and targeted training

CM site induction, toolbox talk and training records

All personnel trained in relevant requirements of this plan

All

Relevant control measures from this plan will be included in SWMS and work method statements

At all times SWMS and work methods to consider conservation and habitat management requirements

SM/ Sub-contractor SWMS and WMS All approved SWMS and WMS include relevant environmental controls

All

Sensitive Area Plans (SAPs) will be developed for the project, showing sensitive areas including vegetation to be cleared and vegetation to be retained.

Before construction

SAPs developed based on findings of Environmental Impact Assessment and Ecological Impact Assessment

SM/ Sub-contractor SAPs SAP produced and updated as required.

Sensitive areas and clearing limits identified and managed effectively on site.

All

Any Threatened Species which are sighted during construction which have not been assessed and included in previous studies and are likely to be significantly impact, will be reported to the Defence SEM immediately.

At all times Where discovered during pre-clearing inspections or encountered during construction and identified by qualified ecologist

SM/ Environmental Manager

Pre-clearing inspection reports and unexpected find reports

Any previously unidentified Threatened Species encountered reported to SEM All

Page 10: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 10 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

Construction works which may directly impact the species will be ceased until advice is provided from Defence

Prior to construction

Where vegetation is to be retained within construction areas they will identified and protected by a fence and signposted ‘Vegetation Protection Zone’

Before construction

Consult Project Ecologist and this plan to identify Vegetation Protection Zone requirements

SM/ Sub-contractor Site Inspections, pre-clearing inspections

All relevant Vegetation Protection Zone fencing and signage in place prior to construction

C & D

The construction footprint is to be clearly delineated on the ground so that disturbance outside the footprint does not occur

Before construction

Consult clearing limit and design drawings to set out construction footprint and install delineation appropriate to the location

SM/ Sub-contractor Site Inspections, No disturbance beyond construction footprint

All

During construction - Flora

Clearing of vegetation will be strictly in accordance with the Clearing and Grubbing eWMS (Appendix A)

At all times See Clearing and Grubbing eWMS (Appendix A)

SM /Sub-contractor Pre-clearing Permit

Site Inspections

Survey reports of area cleared

Ecologist clearing report

Clearing limits clearly and accurately marked and understood by all involved.

Clearing only of approved vegetation.

No harm to fauna during clearing.

A, B,C,D & G

Work requiring removal of branches, roots etc. will be undertaken by or at the direction of a qualified arborist.

Removal of branches, or pruning by excavator bucket or similar is not permitted

At all times Arborist to inspect trees and perform work where required

SM/ Sub-contractor Pre-clearing Permit

Tree pruning / lopping performed in accordance with AS 4373-2007 Pruning of Amenity Trees

A, B,C,D,E & G

Materials or spoil are not to be stored or stockpiled in retained vegetation areas or Vegetation Protection Zones

At all times Stockpile and storage areas to be identified in the Erosion and Sediment Control Plans. Stockpile and storage only allowed in these approved areas

SM/ Sub-contractor Approved ESCP.

Weekly Environmental Inspections.

Environmental Audits

Stockpile and storage only in approved areas, and outside retained vegetation areas or Vegetation Protection Zones.

All

Driving or parking of plant and vehicles is not permitted within in retained vegetation areas or

At all times Access tracks and parking areas to be identified in the

SM/ Sub-contractor Approved ESCP. Access tracks and parking only in approved areas, and

All

Page 11: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 11 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

Vegetation Protection Zones Erosion and Sediment Control Plans.

Weekly Environmental Inspections.

Environmental Audits

outside retained vegetation areas or Vegetation Protection Zones.

Limit disturbance of vegetated areas. At all times Schedule works to retain vegetation cover for as long as possible, minimise disturbance of vegetation outside the construction footprint where ever possible

SM/ Sub-contractor Approved Environmental Control Plan.

Weekly Environmental Inspections.

Environmental Audits

Vegetation disturbance limits enforced as per the Environmental Control Plan.

All

Minimise risk of bush fire as a result of construction activities in vegetated areas

At all times Check fire danger rating and fire activity rating prior to mobilising plant. Restrict spark generating activities and plant with exposed hot parts (eg exhausts) in vegetated areas prone to easy ignition during periods of fire danger.

SM/ Sub-contractor Hot works permit

Weekly Environmental Inspections.

Hot works or plant do not cause fire in vegetated areas

All

During construction - Fauna

Ensure gates or fences are not left open such that animals, particularly kangaroos or wallabies, are let onto the airfield or RAAF Base

At all times Supervise open gates or openings in perimeter fences to prevent animal incursion. Close perimeter gates and fence openings as soon as possible and when ever unattended. Install some form of barrier underneath temporary perimeter fences and gates to prevent animals digging under the fence.

SM/ Sub-contractor Weekly Environmental Inspections.

Animals, particularly kangaroos or wallabies, are not let onto the airfield or RAAF Base due to construction activities specifically through breaks in the perimeter fence or open gates.

All

Encountered wildlife is to be protected and relocated by appropriately qualified and experienced handlers

At all times Work in the immediate area to stop, the animal is to be protected, and the Managing Contractor notified

Follow Fauna Recovery Procedure

SM/ Sub-contractor Fauna Recovery Procedure

Fauna is protected and relocated by appropriately qualified and experienced wildlife handlers All

Page 12: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 12 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

Project Ecologist to be available during vegetation clearing.

Construct and manage trenches to limit accidental overnight trapping of fauna, and enable trapped fauna to escape.

At all times Where possible cover trenches left open overnight.

Trenches and excavations not covered overnight to be inspected each morning for captured fauna.

Where trenches are to be left overnight, if possible construct with shallow sloping ends to allow natural escape of trapped fauna

SM/ Sub-contractor Fauna Recovery Procedure

Trapped fauna reported to the Managing Contractor to arrange relocation

Limit accidental trapping of fauna

Trapped fauna not harmed and reported to the Managing Contractor

All

Construction Areas to be kept clean and tidy, to limit attraction of fauna to the site.

At all times All waste is placed in appropriate bins (as per Waste Management Sub-Plan).

Lids kept closed on bins containing food waste.

Work areas to be cleared of waste at the end of each day/shift

SM/ Sub-contractor Site Inspections Work areas clean and tidy, fauna not attracted to waste or food scraps on the site

All

Pre-Clearing

Habitat trees to identified and marked in areas to be cleared

Pre - clearing Areas to be cleared to be inspected by a qualified ecologist to identify, mark and record potential habitat trees (hollow bearing) as per Clearing and Grubbing eWMS (appendix A)

SM/ Sub-contractor Ecologist Reports

Pre-Clearing Permit

Habitat Trees identified and managed as per Clearing and Grubbing eWMS

A,B,C,D & G

Sensitive areas and protected vegetation to be identified and protected

Pre-clearing Sensitive areas and protected vegetation described in the SAP to be located and fenced / signposted

SM/ Sub-contractor Pre-Clearing Permit

Environmental Inspections

All sensitive areas identified and protected.

No harm to sensitive areas.

A,B,C,D & G

Page 13: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 13 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

Vegetation to be cleared to be identified and clearly delineated.

Pre - clearing Surveyor to mark out approved clearing limits as per the Environmental Clearance Certificate, as per Clearing and Grubbing eWMS (appendix C)

Delineation will be durable, highly visible and signposted where sensitive areas are to be protected

SM/ Sub-contractor Survey records / Clearing Drawing

Pre-Clearing Permit

Environmental Inspections

Clearing only of approved vegetation.

No harm to vegetation outside approved clearing limits

A,B,C,D & G

All vegetation clearing and lopping / pruning must be approved prior to starting.

Pre - clearing Pre-clearing inspections and signoff as per Pre-Clearing Permit (See Appendix B) to be completed before clearing starts

Approval by the Managing Contractor

SM/ Sub-contractor Pre-Clearing Permit

Clearing Drawing

No unapproved clearing of vegetation

A,B,C,D & G

Proposed erosion and sediment controls to be identified prior to clearing

Pre-clearing A progressive Erosion and Sediment Control Plan for the area to be cleared to be submitted for approval prior to the clearing activity

SM/ Sub-contractor Approved ESCP Appropriate erosion and sediment controls identified and resources allocated A,B,C,D & G

Identify and rescue fauna in the clearing area Pre-clearing No more than 24hrs prior to clearing the project ecologist is to survey the clearing area to identify and if possible capture and relocate fauna as per the Clearing and Grubbing eWMS.

SM/ Sub-contractor Ecologists report

Pre-Clearing Permit

Records of inspection and fauna relocation

A,B,C,D & G

Capture and relocate frogs and other fauna from potential Wallum Froglet habitat (i.e. inundated or wetland)

Qualified ecologist captures and relocates frogs and other fauna to adjacent suitable habitat.

Progressively fill or drain the inundated areas to encourage any remaining fauna to move

SM/ Sub-contractor Ecologists report

Site inspections

Work areas cleared of Wallum Froglet prior to construction

A,B,C& G

Page 14: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 14 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

to other adjacent habitat.

This activity will be carried out under the supervision of a qualified ecologist, and will have the additional benefit of reducing the potential for reoccupation post the inspection and clearing.

Clearing

Manage erosion and sediment run off risk from disturbed areas as per Stormwater and Erosion Management Plan

Clearing If possible install erosion and sediment controls before clearing. Where this is not possible install controls progressively as clearing progresses, and for all cleared areas in advance of forecast rain.

SM/ Sub-contractor Approved ESCP

Environmental Inspections

No uncontrolled sediment runoff from cleared areas.

A,B,C,D & G

All clearing will be undertaken in accordance with the Clearing and Grubbing eWMS (Appendix A)

Clearing All Clearing plans to be consistent with the Clearing and Grubbing eWMS, and all personnel involved will be toolboxed in the requirements of the Clearing and Grubbing eWMS

SM/Sub-contractor Pre-Clearing Permit

Clearing Drawing

All clearing and lopping carried out as per the Clearing and Grubbing eWMS

No unapproved clearing/lopping, harm to Native Fauna avoided, erosion and sediment run off controlled, Pc infection risks managed.

A,B,C,D & G

Where possible retain shrub and ground cover in gully / drainage lines to minimize erosion and sediment run off

Clearing Fell trees in gully lines by chainsaw, retaining stump and roots until erosion and sediment controls, including drainage are in place.

Where shrub and ground cover can be retained within a gully line, it will be identified during pre-clearing inspections and delineated by

SM/ Sub-contractor Pre-Clearing Permit

Clearing Drawing

Ground disturbance of gully or drainage lines minimised.

A,B,C,D & G

Page 15: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 15 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

helicopter tape

Manage Phytophthora cinnamomi infection risk Clearing Clearing for the EO areas (Zone A) and access track (Zone B), and NW runway extension (Zone G) to follow the Phytophthora cinnamomi hygiene procedure described in Appendix C

SM/ Sub-contractor Environmental Inspections

Clearing Report

No transfer of Phytophthora cinnamomi contaminated material into the construction site, or from cleared areas to other locations (on or off the construction site)

A, B & G

Check felled trees for fauna and relocate where found

Clearing Project Ecologist to check felled trees and arrange capture and relocation of fauna as per the Clearing and Grubbing eWMS

Record and report fauna found

Sub-contractor Clearing report

Ecologists report

Records of Capture / relocation of fauna

A,B,C,D & G

Employ the two stage clearing process to prevent injury to Fauna in Habitat Trees

Clearing Leave identified Habitat Trees upstanding for a minimum of 24hrs after clearing surrounding vegetation.

Where possible trap and remove fauna from the Habitat Tree prior to felling

Create minor disturbance around the habitat tree to encourage fauna to leave.

Check felled habitat Trees for presence of fauna, arrange capture and relocation where found.

Record and report relocated, injured or killed fauna

SM/ Sub-contractor Clearing report

Ecologists report

Records of two stage clearing, and capture / relocation and fauna

A,B,C,D & G

Lopping

Vegetation to be lopped to be identified clearly marked and recorded.

Pre - lopping Arborist to work with surveyor to identify trees within the approved lopping footprint requiring lopping.

SM/ Sub-contractor

D & G

Page 16: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 16 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

Trees to be lopped will be visually marked and location picked up and recorded by the Surveyor

Identify and rescue fauna in trees to be lopped Pre - lopping No more than 24hrs prior to lopping the project ecologist is to survey the trees to be lopped to identify hollows, and if possible capture and relocate fauna. Hollows cleared of fauna will be blocked to prevent reoccupation

SM/ Sub-contractor Ecologists report

Pre-Clearing Permit

Records of inspection and fauna relocation

D & G

All vegetation lopping must be approved by Managing Contractor prior to starting.

Pre - lopping Pre-lopping inspections and signoff as per Pre-Clearing Permit (See Appendix D) to be completed before clearing starts

SM/ Sub-contractor Pre-Clearing Permit

Clearing Drawing

No unapproved lopping of vegetation

D & G

Manage Phytophthora cinnamomi infection risk Lopping Lopping within the proposed HIAL footprint (Zone G) to follow the Phytophthora cinnamomi hygiene procedure described in Appendix C

SM/ Sub-contractor Environmental Inspections

Clearing Report

No transfer of Phytophthora cinnamomi contaminated material into the construction site, or from cleared areas to other locations (on or off the construction site)

G

Minimise harm to Fauna Lopping Avoid lopping of hollow bearing branches where possible. Where hollow bearing vegetation must be lopped, under the direction of the Project Ecologist, and where safe to do so, check the hollow for fauna prior to lopping / and or carefully drop the section of vegetation to minimise potential harm

SM/ Sub-contractor Ecologists report

Pre-Clearing Permit

No harm to native fauna

D & G

Check felled vegetation for fauna and relocate where found

Lopping Project Ecologist to check felled branches and arrange

Sub-contractor Clearing report

Ecologists report

Records of Capture / relocation of fauna D & G

Page 17: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 17 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

capture and relocation of fauna as per the Clearing and Grubbing eWMS

Record and report fauna found

Minimise ground disturbance during tree lopping

Lopping Vegetation lopping within the proposed HIAL footprint would be undertaken manually to ensure the ground and shrub layer is not disturbed.

All native vegetation debris from lopping would be manually removed.

SM/ Sub-contractor Environmental Inspections

Clearing Report

Ground cover and shrub disturbance is minimised

D & G

Mulch and Woody Debris

Where possible, place felled hollow bearing trunks, branches and Coarse Woody Debris (CWD) outside the clearing limit to create fauna habitat

Clearing / lopping

Under the direction of a qualified Ecologist, carefully place felled hollow bearing trunks and branches outside the clearing limit.

Note Felled vegetation is only to be placed outside the clearing limit where it can be done without further clearing, without damage to retained vegetation and without machinery tracking outside the clearing limit.

SM/ Sub-contractor Clearing Report

Ecologists Report

Suitable hollow bearing logs and branches and CWD are placed beyond the clearing limit to create habitat.

A,B,C,D & G

Maximise beneficial reuse of cleared vegetation Clearing / lopping

Cleared vegetation not used for CWD, habitat creation or offsite beneficial reuse will be mulched and stockpiled in approved locations for reuse on site for landscaping and ERSED controls.

SM/ Sub-contractor Clearing Report

No cleared vegetation is disposed of to landfill.

All cleared vegetation will be beneficially reused

A,B,C,D & G

Post Clearing / Mulch that is surplus to the SM/ Sub-contractor Clearing Report No cleared vegetation is A,B,C,D & G

Page 18: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 18 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

lopping projects requirements will be offered for local beneficial reuse to organisations such as the Base landscape management Sub-contractors, Newcastle Airport and Port Stephens City Council.

Monthly Report disposed of to landfill.

All cleared vegetation will be beneficially reused

Mulch will be stockpiled in a manner that does not cause harm to waterways

Post Clearing / lopping

Mulch will be stockpiled away from waterways and drainage lines and the length of stockpile timeframes minimised where possible to reduce tannin generation

SM/ Sub-contractor Environmental Inspections

Tannin produced by mulch stockpiles does not contaminate waterways or drainage lines

A,B,C,D & G

Topsoil Management

Prior to excavation, topsoil will be stripped and stockpiled for later reuse

During excavation works

Topsoil to be stripped and stockpiled for later reuse.

Where ever possible topsoil will be reused in the vegetation zone from which it was stripped to encourage regeneration of locally endemic species.

SM/ Sub-contractor Environmental Control Plans

Environmental Inspections

Environmental Audits

Topsoil stockpiled and reused

All

To encourage rapid ground cover regeneration, where trenching for services installation (or similar short term excavations) in areas of native vegetation, set aside excavated topsoil and use to cover the excavation it came from.

Temporary excavations / trenches

Set aside groundcover vegetation and topsoil separate from the subsoil. Place the topsoil and followed by the stripped vegetation back as the final layer over the excavation it came from so as to preserve the fertility and seed bank of the topsoil layer and provide a ground cover layer to encourage rapid vegetation regeneration and limit soil erosion.

SM/Sub-contractor Environmental Control Plans

Environmental Inspections

Stripped topsoil and vegetation managed so as to promote rapid vegetation regeneration and limit erosion

All

Where trenching for services installation (or During short Prior to excavating the SM/ Sub-contractor Environmental Control Reuse of stripped turf to All

Page 19: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 19 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

similar short term excavations) in turfed areas, strip and reuse turf where ever possible to re-establish ground cover over backfilled trenches and excavations.

term excavation / trenching

topsoil, retain the turf / groundcover vegetation layer to be placed back over the excavation

Plans

Environmental Inspections

minimise erosion and promote ground cover regeneration.

Weed management

A survey of weeds will be conducted prior to construction to identify weed infested areas.

Prior to clearing Qualified Ecologist to inspect the site to identify and record weed infested areas.

Noxious weeds will be sprayed prior to clearing to prevent spread of weed propagules with mulched vegetation

Weed spraying to only use glyphosate herbicide

CM / SM Ecologists weed infestation report

Herbicide use register

Weed infested areas identified

All

The construction areas will be managed to control noxious weeds.

Ongoing Weed spraying to only use glyphosate herbicide

CM/ SM weekly inspections

Herbicide use register

Noxious weeds are identified and controlled to prevent spread of weeds to the rest of the base or adjacent National Park land

All

Seed Management

If required by Defence, seed will be collected from a selection of native trees prior to clearing, in order to preserve the local genetic diversity.

Prior to and during clearing

If required by Defence, Seed collection and propagation will be carried out by experienced seed collectors

Seed will be cleaned and sorted and offered to Defence for subsequent revegetation works.

Collected seed will be labelled and stored under appropriate conditions, reflective of the nature of the seed collected, until propagation or seed

SM/ Sub-contractor Ecologists Report Records of seed collection.

(weight, species, viability test results)

A,B,C,D & G

Page 20: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 20 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

distribution is to be initiated.

Post Clearing If required by Defence, collected seed will be propagated to provide native trees of local provenance for revegetation / rehabilitation works.

SM/ Sub-contractor Monthly Report Propagated trees of local provenance

NA

Rehabilitation

On completion of construction, areas to returned to original or better condition to the satisfaction of Defence.

After construction is completed in an area

Includes removal of waste spoil, earth bunds and any other soil / rehabilitation requirements

SM/ Sub-contractor Environmental Inspections / audits

All construction areas rehabilitated to satisfaction of Defence prior to handover

All

Stabilise disturbed areas as soon as possible As soon as possible

Disturbed areas will be stabilised either by the permanent landscape planting, or using a cover crop / turf seed mix approved by the Base Senior Environmental Manager

SM/ Sub-contractor

Approved Seed Mix Landscape plans ESCP

Disturbed areas stabilised in a timely manner to minimise erosion potential

All

All landscape or stabilisation (i.e. cover crop / turf) planting will be maintained and watered to ensure promote good growth and ongoing survival

At all times Landscape and stabilisation plans / contracts to include maintenance and watering requirements

SM/ Sub-contractor Landscape and stabilisation plans / contracts

ESCP

Site Inspections

Good growth and long-term survival of landscaping and revegetation stabilisation works.

All

Where possible and consistent with the approved Landscaping plan, use native flora species for re-vegetation as a natural control to

After construction is completed in an

If required by Defence and the approved Landscape plan, native flora will be used

SM/ Sub-contractor Landscape plans

Native flora used for revegetation / rehabilitation works where required

All

Page 21: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 21 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Control Measures Timing Methodology Responsibility Monitoring and Reporting

Performance Measure Relevant Zones

weed infestation. area for revegetation / rehabilitation works.

Page 22: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 22 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

Appendix A

ENVIRONMENTAL WORK METHOD STATEMENT

CLEARING AND GRUBBING

BACKGROUND

1.0 SUMMARY/PURPOSE OF ACTIVITY:

Clearing and grubbing involves the clearing of vegetation and the removal (grubbing) of roots and stumps. Timbers suitable for reuse are salvaged for milling, reused as construction materials or mulched for use in landscaping activities. Clearing and grubbing activities involves the use of an excavator, dozer, chainsaw, chipper, tub-grinder, backhoe and trucks. A two stage clearing process will be carried out on this project.

2.0 OBJECTIVES OF THIS WMS:

The objective of this eWMS is to provide specific control measures so that the minimum possible area of land is cleared, to minimise impacts on endangered ecological communities and threatened species, and minimise the risk of spread of Phytophthora cinnamomi infection. Also the area cleared must be within the limits specified.

3.0 AREA/LOCATION OF ACTIVITY/SITE:

Within the boundaries of the NACC-Williamtown project and as per approvals.

4.0 APPROVALS REQUIRED

Environmental Clearance Certificate (ECC) issued by Senior Environmental Manager - RAAF Williamtown

5.0 CONSULTATION REQUIREMENTS:

Clearing on Defence land - Senior Environmental Manager - RAAF Williamtown

Clearing in State Conservation Area for Access Road construction – National Parks and Wildlife Service

Consultation with external stakeholders, such community groups, Representative Aboriginal Parties (RAPs), Hunter Water Corporation and NSW Office of Water will be carried out by the Stakeholder Manager as required

6.0 INCIDENT RESPONSE:

In the event of an incident such as clearing beyond the approved clearing limits or damage to protected vegetation or heritage item/area the Foreman or Environmental Officer will give directions to stop work and contact the Environmental Manager immediately. If the Environmental Manager is not available then the Project Director shall be contacted.

Page 23: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 23 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

RISK ASSESSMENT

LIKELIHOOD (L) CONSEQUENCE (C) - IMPACT RISK RANKING (R)

1 2 3 4 5

A Almost Certain Expected (almost certain) outcome in most cases 91 - 100% probable without control measures in place; regular incident trend.

5 Very Large Multiple fatalities due to occupational injury/illness, permanent long term and extensive environmental damage.

A (A1)

5 (A2) 10

(A3) 15

(A4) 20

(A5) 21+

B Likely

Will probably occur (likely) in most circumstances 51 - 90% probable without control measures in place; regular incident trend but not almost certain as an outcome or recurrence.

4 Large Fatality due to occupational injury or illness, permanent but localised environmental harm.

B (B1)

4 (B2)

8 (B3) 12

(B4) 16

(B5) 20

C Possible May occur sometime, 31 - 50% probable without control measures in place, infrequent incident trend.

3 Medium Occupational injury or illness that results in permanent disability. Long term damage or pollution or degradation; clean up remediation or rehabilitation will require greater than 1 month.

C (C1)

3 (C2)

6 (C3)

9 (C4) 12

(C5) 15

D Unlikely Could occur, but would not be expected - 10 - 30% probable without control measures in place; irregular incident trend on a few occasions.

2 Small

Occupational injury or illness that results in offsite medical treatment or lost time injury that result in a temporary disability. Short term localised damage or pollution or degradation; clean up remediation or rehabilitation will require up to 1 month.

D (D1)

2 (D2)

4 (D3)

6 (D4)

8 (D5) 10

E Rare Rare (highly unlikely) that this event would occur in the identified circumstances without any control measures in place; < 10% probable.

1 Very Small

Occupational injury or Illness that results in on site First Aid treatment. Minor on site environmental damage, pollution or degradation event; clean up remediation or rehabilitation will require less than 24 hours

E (E1)

1 (E2)

2 (E3)

3 (E4)

4 (E5)

5

Risk Ranking Summary

Critical (21+) -These risks are Unacceptable. The work activity or process should be halted until Control Measures are implemented which reduce the risk to significant or less using the Hierarchy of Control. Detailed research, planning & critical control measures review is required with actions consistent with legal and GMR compliance by key stakeholders to eliminate or reduce risk ranking to high or lower consistent with the Hierarchy of Control.

High (15-20) - These risks must be reduced wherever possible by implementing higher level Control Measures using the Hierarchy of Control. Detailed review of Critical Control Measures by supervisory staff and workplace managers including consultation with work crew and training in revised system of work. Monitoring of key control measures allocated to specific responsibilities.

Moderate (9 -14) Identified Control Measures must be capable of reducing the risk by eliminating or minimising to an acceptable level. Monitoring of key control measures allocated to specific responsibilities.

Low (3-8) -The work is relatively safe and can be managed by routine Control Measures outlined in Means & Methods, routine procedures, guidelines, pre-starts/restarts, Builder's Brief and Project EHS Rules. No further action is required, unless additional impacts or hazards arise during the work.

Negligible (1-2) - No further control measures are required Monitor to ensure risk does not escalate

Page 24: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 24 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

WORK METHOD AND RISK ASSESSMENT

#

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Risk

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Prior to commencement of works

1 ECC Approval Approval not granted Moderate (C3)

ECC to be consistent with the Habitat and Conservation Management Plan and this eWMS.

Produce Clearing drawing and Erosion and Sediment Control Plan (ESCP) Environmental Officer

2 Stakeholder / Community Notification

Stakeholders and Community are exposed to impacts without prior notice

Low (D3)

Notification Stakeholder Manager detailing works required. At least 5 days’ notice is required prior to the commencement of construction.

Notify relevant Stakeholders at least 5 working days prior to the commencement of clearing.

Project Engineer

Foreman/Site Engineer

Stakeholder Manager

3 Safe work method statements

Unsafe work practices Moderate (C3)

SWMS for work activity to be completed,

Site foreman manages the site and checks in all visitors.

External Plant Checklist, Operator assessment, tickets/licenses, Insurances to be checked and completed.

Foreman/Project Engineer

4 Permit to Excavate and Permit to Work Under Power lines

Damage to services. Moderate (C4)

Complete a Permit to Excavate and Permit to Work Under Power lines if relevant to works. Foreman/Project

Engineer

5 Provide training to personnel and sub-Sub-contractors involved

Non-compliance with work methods.

Moderate (C3)

Conduct planning meetings with subSub-contractors to identify and communicate clearing limits.

Toolbox field operators on the requirements of this eWMS, the ESCP and SAPs.

Produce Clearing drawings

Include heritage issues, clearing limits and no-go zones in induction.

Foreman / Surveyor / Environmental Officer

6

Mark out environmental and Heritage sensitive areas within or adjacent to works.

Damage to flora, fauna and/or heritage items.

Moderate (C4)

Survey and fence any sensitive areas that require protecting within/adjacent to the works area in accordance with the sensitive area plans and in consultation with the Project Ecologist.

Foreman / Surveyor / Environmental Officer

7 Mark out limit of clearing for the footprint

Clearing beyond the approved clearing limits or unauthorised damage to items of significance

Moderate (C4)

Limit of clearing to be marked with pegs/red and white danger tape at a maximum of 50m centers. Pegs marked to clearly indicate clearing side.

Limits of clearing to be set out by survey

Limits of Clearing markers and tape to be checked, and repaired as required, with in 24 hrs. of clearing commencing in an area.

Survey

Page 25: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 25 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

#

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Risk

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

8

Identify vegetation to be retained and rescue identified flora and fauna.

Unnecessary removal of vegetation/ habitat.

Moderate (C4)

Identify any native animals in the clearing area.

Where recommended by the project ecologist conduct spotlighting / night surveys

Identify and clearly mark out habitat trees (e.g. those containing hollows etc.) as per section 5 of the Flora and Fauna Management Sub Plan with appropriate flagging/marking.

Check habitat trees (and hollows where necessary) for the presence of fauna using an infrared camera where possible or a cherry picker or tree climbers, immediately prior to the removal of the trees.

A qualified ecologist, appropriately licensed by NPWS, will, where possible, capture native animals identified within the clearing limits and relocate them to suitable habitat in the local area.

A qualified ecologist using appropriate means will exterminate pests such as mice and rats found during the pre-clearing inspection.

Check latest Sensitive Area Plans against identified clearing limits prior to commencing clearing and grubbing operations.

Environmental Officer / Ecologists

Clearing

9

Clearing operations using chainsaws, Bulldozers mulchers, tub grinders, shredders, excavators as required

Damage to retained vegetation.

Moderate (C4)

Ensure that Pre-Clearing Permit is completed and approved prior to clearing commencing.

The Pre-clearing permit is to be approved at the Toolbox each morning by one of the following (or delegate):

General Superintendent

Environmental Manager

Construction Manager

Earthworks Project Manager

To confirm that all required checks have been completed and clearing limits understood the permit is to be signed on to by:

1) Project ecologist

2) Environmental officer

3) Surveyor and

4) Clearing Foreman

Project Engineer / survey / Environmental / Sub Sub-contractor / Foreman

Injury to fauna. Low (C2) Create a minor level of disturbance adjacent to the occupied habitat tree to encourage fauna to leave. Use the two stage clearing, leaving hollows upstanding minimum 24 – 48 hours

Foreman

Clear habitat trees of fauna using appropriate trapping methods such as mist nest, bags tied over openings and other appropriate methods as specified by the project ecologist.

Environmental Officer / Ecologists

Page 26: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 26 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

#

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Risk

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Injury to fauna. Low (C2) Check felled habitat trees for the presence of fauna and arrange for the capture and relocation of fauna where found. Report any live, injured or killed fauna to the project ecologist.

Environmental Officer / Ecologists

Waste/loss of resources with reuse value.

Low (C2) If required, salvage millable logs. Stockpile all tree heads and stumps for mulching and later reuse in landscaping works. Stockpiling shall be in an approved location away from residents and watercourses.

Foreman / Sub-contractor

Risk spreading weeds through job site

Low (D3) Remove identified noxious and/or invasive weeds and stockpile separately. DO NOT incorporate this material into mulch.

Foreman / ecologists / Environmental Officers

Risk Spreading Phytophthora between clearing areas

Follow plant cleaning and decontamination instructions as per Phytophthora cinnamomi hygiene procedure (Appendix C)

Foreman / Sub-contractor

Risk Spreading Phytophthora in stockpiled mulch

Follow clearing and mulching requirements of the Phytophthora cinnamomi hygiene procedure (Appendix C) Foreman / Sub-contractor

Risk of fire Low (D2) Limit mulch stockpiles to less than 3m high.

Foreman / Sub-contractor

Ground disturbance resulting in pollution of waterways after rain.

Low (D3) Implement ERSED control measures progressively and maintain ERSED controls as required following daily/weekly checks and after rain events.

Damage to watercourses and wetland areas.

Moderate (C3)

Locate stockpiles clear of wetlands and away from watercourses where possible. Avoid vegetative material from falling into or entering any creek or retained wetland. Where construction activities allow, only remove the upright trunk part of the tree within riparian zones, leaving the stump and roots within the ground to minimise disturbed areas. Access along identified paths and tracks. Transport of clearing plant and equipment across waterways and wetland areas to be undertaken at an approved established crossing point only.

Foreman / Sub-contractor

Noisy activities causing disturbance to residents / Base personnel

Low (D2)

Works are only to occur as per approved hours of operation. Ensure plant / equipment is fitted with appropriate silencers and is maintained in an efficient condition. All noise complaints to be recorded and actioned. Equipment that is not in use will be switched off. Daily checking to, where possible, avoid the coincidence of noisy plant working simultaneously close together and adjacent to sensitive receivers. Where possible, the offset distance between noisy plant items and nearby noise sensitive receivers will be as great as possible. Unloading and loading will be carried out away from sensitive receivers and the selection of site access points will take into account the proximity to residents.

Interaction with traffic Low (A1) Clearing near roadways will have traffic control plans and measures in place prior to any interactions with traffic. Plant movements across roads will only occur when adequate traffic control is in place.

Project Engineer

Page 27: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 27 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

#

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Risk

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

10 Grubbing operations using dozer and rake. Damage to services.

Moderate (C4)

Use Dial Before You Dig, Permit to Excavate and where necessary undertake service pot holing to determine exact location of services before removing stump. Remove stumps as a separate operation in areas near services. Cut roots between the stump and any service prior to digging the stump out.

Foreman

11 Mulching activities using tub grinder.

Noise causing annoyance to sensitive receivers.

Low (B2)

Locate plant and equipment as far away as practical from residences and orientate tub grinder so that the noisiest side is operating away from residences. Avoid parking near residents where possible. Consolidate mulch stockpiles in a central location as far away as practical from local residences. Keep the tub grinder bowl full.

Foreman Sub-Sub-contractor Sub-Sub-contractor

12 Commence mulching activities.

Potential fire spreading outside of the clearing area

Low (D3) Ensure fire extinguishers are available at all times during tubbing. Locate stockpiles with access available now and in the future for fire control and reuse.

Foreman Foreman

Page 28: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 28 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 DOC ISSUE: 1.0 DOC #R8000-MUL-00-MP-MN-00-104

TOOLBOX

Role and responsibilities: o Foremen: Manage day to day works in the field. Ensure activities are undertaken in accordance with this eWMS. o Engineers: Provide technical support and management of scope and program of works. Manage quality. o Environmental Officer: Undertake inspections and conduct planning to ensure that no environmental incidents occur. o Surveyor: Mark out works in accordance with design. o Safety Officer: Review of SWMS, undertakes safety inspections and audits to ensure safe work methods are being practiced.

Work hours – Discuss approved construction hours.

Pre-clearing surveys have been completed to identify the areas to be protected. These areas are fenced and signposted.

Be aware of habitat trees still within the footprint to be cleared. These trees are marked with red tape for easy identification.

All potential habitat trees must be checked for native fauna by a qualified person prior to clearing (as far as practical)

If native animals are observed in any tree to be felled, stop work immediately and contact the Environmental Officer who will arrange for the animal to be removed

If an injured animal is found, advise the Environmental Officer immediately.

The limit of clearing is identified with red and white danger tape.

DO NOT clear outside these limits without prior approval from the Environmental Officer

Clear only that vegetation within the limit of clearing.

No haul roads, access tracks, laydown, stockpiles etc. is permitted within vegetation protected areas.

Ensure that all stock piles are placed away from residents, creek and fenced vegetation protection areas (EEC). Maintain clear access to mulch stockpiles in case of fire

Inspect fallen habitat trees for the existence of fauna

Minimise ground disturbance near creek banks. Where possible, chainsaw trees at ground level leaving stump within the ground to aid in stabilisation of the bank area and faster regeneration. Maintain ground cover around watercourses to avoid the creation of large exposed areas (i.e. limit disturbance where practical)

All vegetation cleared will be re-used where possible. It will be either stockpiled for milling purposes/construction materials or mulched for re-use in landscaping. Follow directions of Foremen

Locate mulching machinery as far away from residents as practical to avoid un-necessary noise complaints.

Water sprays, sprinklers and water carts will be employed to adequately dampen stockpiles, work areas and exposed soils to prevent the emissions of dust from the site.

• Check the clearing plan attached each time a new area is to be cleared – so you are familiar with the area and the protection areas

Page 29: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 29 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Appendix B – Pre-clearing Permit

Pre-Clearing Permit

Project: Date Inspected:

Project Area: Chainage area enveloped:

SubSub-contractor:

List of machinery used:

Date work is to start:

Construction Stage/Activity:

Date work is to cease:

Compliance

# Control Measure Yes No N/A Comments

1. Are all sensitive areas noted on the attached to the Survey Drawings

2. Has the sensitive area mapping been checked for accuracy

3. Are the locations of sensitive areas included in the CEMP and site induction?

4. Have the clearing limits shown in design drawings (Drainage) (SAP’s) been checked for accuracy?

5. Have all sensitive areas been clearly identified with signage and protected with exclusion fencing?

6. Have threatened plants which are not permitted to be cleared been identified with parrawebbing and signposted?

7. Has the Area clearly marked out by the Survey team and clearly understood by Abigroup / Clearing Sub-contractor Foreman

8. Have the signatories to this permit walked the area concerned and confirmed the sensitive areas are clearly demarcated?

9. Has a survey for any known threatened species been carried out prior to clearing?

10. Has the project ecologist undertaken a pre-clearing survey?

11. Has the project ecologist been notified to attend the site every morning for the duration of this clearing permit?

12. Has a clearing Work method statement (WMS) been prepared and toolboxed?

13. Have all personnel involved been instructed / toolboxed on the sensitive area locations and signed an acknowledgement toolbox sheet? This is to include the clearing subSub-contractor.

14. Have all personnel involved been given a description of the threatened species to be alert for?

15. Have all personnel been instructed / toolboxed on the process to follow if it is necessary to enter a no-go area?

Page 30: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 30 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Brief description of sensitive areas / sites or threatened species within clearing zone:

Permit signatories:

Name Company Position Signature Date

Foreman

Foreman

Surveyor

Project Engineer

Environmental Coordinator

Project Ecologists

Permit Approved by:

Name: Position: Manager Date: Signature: Attached:

Drawings (SAP’s) (Drainage)

Toolbox and Sign Off sheet.

Page 31: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 31 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Appendix C - Phytophthora cinnamomi hygiene procedures

1. BACKGROUND:

Phytophthora cinnamomi (Pc) has been detected in areas of the RAAF Williamtown. Phytophthora (pronounced fy-TOFF-thora) is a water mould that survives in water, soil and plant roots and kills plants by attacking and rotting their roots.

Phytophthora is spread naturally in water and via infected roots, and faster and further by humans moving contaminated soil or plant material. It can remain dormant for long periods during dry weather and is virtually impossible to remove from infected areas. Phytophthora Dieback attacks many native plants and can also impact on native animals, including marsupials, birds, reptiles and insects, by reducing or eliminating vegetation they rely on for survival.

Even plants that are not highly susceptible will succumb during long periods of dry weather. The loss of root mass limits the amount of water and nutrients a plant can absorb, leaving it susceptible to insect attack, plant diseases and drought stress. Early symptoms of dieback in plants include wilting, yellowing and drying out of leaves

The spores of Phytophthora can persist indefinitely in an area protected in the roots of plants, even those that are not susceptible to Phytophthora Dieback. Disease depends on three essential components: plant host, environment and the pathogen. Phytophthora is most active when the soil is moist and warm. It can also survive for long periods in plant tissue and soil during dry soil conditions. The only effective way to limit it’s spread by managing water and soil movement. Typically infection is restricted to the roots and bottom 1 – 2m of the trunk.

High Risk Activities for Pc introduction and spread include: • earthworks • situations where more than one access point into any given work area is required • heavy vehicles and machines involved - increased risk of contamination spread and complexity and cost of clean down • vegetation clearing

2. Pc MANAGEMENT STRATEGY

Management Strategies to prevent introduction of Pc infected material to uncontaminated areas of the Base, or spread of Pc infected material between areas of the Base or to off site areas will include: Preventing introduction — keep it out

Hygiene Procedures - o All plant, equipment and people (footwear) coming into site is free of dirt and vegetation o All plant, equipment and people (footwear) coming into High or Medium Pc risk areas is to be disinfected. o Provide washdown bays and disinfection sprays / footwash stations at entry and exit points

Page 32: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 32 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Use only uninfected raw materials.

Limiting the spread - preventing cross-contamination

Plan work packages to reduce movement of plant and equipment in and out of High or Medium Pc risk areas.

Limiting the points of access to High or Medium Pc risk areas, using fencing to physically segregate High or Medium Pc risk areas

Hygiene Procedures - o All plant, equipment and people (footwear) moving between or leaving High or Medium Pc risk area is free of dirt and vegetation, and is disinfected o Provide washdown bays and disinfection sprays / footwash stations at entry and exit points

Reuse excess soil within the area from which it came.

Manage clearing to keep potentially contaminated root balls, ground cover (grubbing) material and soil separate from uncontaminated trunk and crown vegetation.

Mulch uncontaminated vegetation for reuse within the area of origin or within Low Pc Risk areas, and dispose of potentially contaminated material to an appropriately licensed waste facility

3. OBJECTIVES OF THIS eWMS:

Minimize the risk of spread or introduction of Pc in areas not affected by Pc on RAAF Base Williamtown and external to RAAF Base Williamtown.

4. AREA/LOCATION OF ACTIVITY/SITE:

For the purposes of this eWMS all areas shown on the attached Pc risk assessment map as High or Medium Pc risk will be known as Pc Control Areas, unless otherwise indicated by a Pc testing program.

5. TIMING OF WORKS/EXPECTED DURATION:

At all times working in areas of High or Medium Pc risk (see Risk Map below)

6. APPROVALS REQUIRED:

Environmental Clearance Certificate approved by Defence.

7. CONSULTATION REQUIREMENTS:

Consultation with Managing Contractor and RAAF Williamtown SEM prior to entry to High or Medium Pc risk.

Page 33: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 33 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

PROTOCOL

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Prior to commencement of works in Pc Control Areas

Plan works in Pc Control Areas

Work not planned to minimise risk of cross contamination between areas

• Package work activities that are a significant risk for Pc spread or introduction (based on Pc risk map and activity type) within an area to minimise movement of plant, equipment and personnel between areas during that activity.

• Conduct planning meetings with personnel and sub-Sub-contractors to communicate Pc risks and develop management measures consistent with this plan.

• Include Pc control measures on the location / activity specific ESCP • Plan to include limit to access points to Pc Control Area and provide appropriate hygiene controls. • Planning may include a program of testing designed by a competent party to demonstrate absence of Pc

in an area. In the absence of this testing, as discussed above, all Medium and High Pc Risk areas will be considered as Pc contaminated and designated Pc Control Areas.

Project Manager Supervisor

ECC Approval Works not approved • Consider Pc risk in ECC application • Include proposed mitigations and location / activity specific ESCP showing proposed controls

Project Manager Environmental Coordinator

Provide training to personnel and sub-Sub-contractors involved

Non compliance with the eWMS

• Toolbox personnel and sub-Sub-contractors on the Pc Risks and the requirements of this eWMS.

Install all required Pc controls

Risk of introduction or spread of Pc before controls are established

• Install Pc controls as shown on the approved ESCP. • Where controls are to be introduced progressively this should be recorded on the ESCP

Bringing Plant, Equipment and Vehicles to site

Ensure all plant, equipment, materials and footwear is free of dirt and vegetation

Introducing Pc to previously unaffected areas

• All vehicles and plant should be as free of soil, mud and vegetation before arriving at the base – to be confirmed at Plant prestart inspection.

• Where plant is not free of soil, mud and vegetation it should be removed from site and cleaned, or if available, cleaned at the nearest wash bay (see wash-down procedure)

• Footwear needs to be free of mud or soil. • All materials such as pipes etc. need to be free of mud and soil.

Project Manager Supervisor

Page 34: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 34 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Moving into or out of Pc Control Areas Risk areas

Ensure all plant, equipment, materials and footwear is free of dirt and vegetation

Introducing Pc to previously unaffected areas

• All vehicles and plant should be cleaned of dirt and vegetation at the washdown bay before entering or leaving a Pc Control Area. (See wash-down procedure)

• Tracks, Tires and any part of the machine that comes into contact with soil should be disinfected a per the disinfection procedure.

• Footwear needs to be free of mud or soil and disinfected before entering or leaving the Pc Control Area • All materials such as pipes etc. need to be free of mud and soil.

Project Manager Supervisor

Page 35: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 35 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Working in Pc Control areas

Whilst working in Pc Control areas – General conditions

Spreading Pc to further areas.

• Ensure equipment is clean • Ensure raw materials are Pc Free. • Where ever possible

o Avoid leaving formed areas. o Avoid working in wet weather. o Avoid sites prone to flooding or ponding. o Work downhill of vegetation. Pc moves rapidly downhill on surface water runoff, while uphill

movement occurs much more slowly • Stay within cleared areas, avoid disturbing native vegetation. • Any water used needs to be drawn from a source that is Pc f r e e – mains water is best • Do not drive vehicles through drainage lines, creek lines or puddles. • Do not drive over vegetation to turn vehicles. • Do not enter vegetation without disinfecting footwear – Pc can be carried on a very small amount of

soil. • Always disinfect tools prior to beginning works and when moving from one area to another. • Wash down vehicles when moving between work sites, or leaving the Pc Control Area • Always work in areas where there is no infection before moving to infected areas

Project Manager Supervisor

During Earthworks Spreading Pc to further areas.

• Plan erosion and sediment controls to prevent runoff from worksite into surrounding vegetation. • Apply adequate dust suppression to minimise dust generation, however avoid excess water application

generating runoff to surrounding vegetation. • Only mains water, or standing water from within the Pc Control Area should be used for dust

suppression, surface or groundwater collected from outside the Pc Control Area must not be used. • All activities must be carried out to minimise soil movements and transport of soil and water.

Fill Materials Import of Pc contaminated materials

• Sources of fill should be certified Pc free before use.

Working in drains / culverts and wet areas

• Keep tyres / tracks on roadways /hardstand at all times and do not drive over vegetation or into drains. • Drains and culverts should only be cleared in dry conditions.

Excess Spoil and stockpiles Spreading Pc to further areas.

• Spoil should be reused within the Pc Control Area it came from. • Where reuse within the Pc Control Area is not possible the material must be tested and confirmed Pc

free before reuse in other areas, or disposed of to an appropriately licenced waste facility. • Stockpiled material should not be placed near native vegetation and should be contained by a silt fence

to minimise erosion by run on water and sediment transport into vegetation.

Parking and laydown • Never in vegetated road verges (including slashed road verges) or within vegetation. • Where possible down slope of vegetated areas and on constructed hard stand areas.

Page 36: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 36 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Clearing, Grubbing and Mulch

Clearing within Pc Control Areas

Spreading Pc to further areas.

• Trees should be stump cut, leaving 1 to 1.5m of the trunk upstanding. • The felled section of trunk and crown should be kept as soil free as possible and mulched as soon as

possible. • The mulch should be stockpiled on hardstand if available to minimise soil contamination and should be

protected with a sediment fence. If managed this way this mulch is considered low risk for Pc transfer and can be used for ERSED control or landscaping within the Pc Control Area it originated from or in the low Pc infection risk areas (see Risk Map)

• The remaining stumps, root-balls and grubbed up ground cover should by collected up, placed in a covered skip bin or truck and taken to a suitably licenced waste facility for disposal (NOTE the waste facility must be aware of the potential for Pc contamination and must not mulch this material).

• Alternatively where the stumps, root-balls and grubbed up ground cover can be mulched in a separate area within the Pc Control Area, away from native vegetation and managed by appropriate sediment controls, and a suitable number of lab tests are negative for Pc infection, this material may be reused within the Pc Control Area from which it originated.

• Alternative disposal options, such as firewood, may be considered where the risk of Pc infection transfer can be demonstrated to be low.

• Where it is not practical to stump cut trees, and a dozer or other mechanical means are proposed to push the trees over, the resulting vegetation must be either tested to demonstrate absence of Pc or disposed of to a suitably licenced waste facility.

Project Manager Supervisor

Wet Weather

During Wet Weather While working in Pc Control areas

Spreading Pc to further areas.

• Whenever possible avoid work earthwork or work involving contact with the soil during wet weather, or when soils are still wet/damp after rain.

• If rains begin when working, then works should stop and you should contact the Managing Contractor for advice.

• If you are not working in an area where you are likely to move mud or soil around on vehicles or boots then it is likely that work can continue.

• Grading of roads can occur if the surface is damp, but not wet. • Do not, under any circumstances, enter vegetation when it is raining, or just after rains, or if soils

are damp – even if you have cleaned your boots / tools. • No revegetation or rehabilitation activities should be undertaken in wet weather.

Project Manager Supervisor

Page 37: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 37 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Washdown / cleaning Procedures

Plant / vehicles prior to entering or leaving Pc Control areas

Spreading Pc to previously unaffected areas

• Safely park vehicle or plant in the wash-down area. Ensure engine is off and vehicle is immobilised. • Look over vehicle to locate any soil. Pay attention to underside, tracks, tyres (inc. the spare) axles and

bumper bars etc. • Knock off large clods of soil - use crow bar if required, sweep out cabin and other areas. • Use broom or air hose to remove as much soil as possible. Brush off any remaining dry soil. • Start with underside of vehicle, wheel arches, wheels (including spare). Next do sides, radiator, tray,

bumper bars etc., finishing with upper body. Tracked machinery may need to be moved during wash down.

• Clean any associated implements, tools, footwear and equipment. Check there is no loose soil remaining.

• Spray with quaternary ammonia solution e.g.: Phytoclean® • Wash away effluent. Do not drive through effluent. Note: Wash-down water is to be captured and disposed of to an appropriately licenced waste facility. Collected soil can be reused as fill within the Pc Control Area, or disposed of to an appropriately licenced waste facility, it is not to be reused outside the PC Control Area it came from.

Project Manager Supervisor

Page 38: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 38 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Sequence of Work Activities

(How will work be done?)

Potential Hazards

(What harm can occur?)

Safeguards/controls

(How can the risk be minimised?)

Responsibility

(Who will direct works to ensure compliance?)

Footwear prior to entering or leaving Pc Control areas

Spreading Pc to previously unaffected areas

Some personnel will require a personal Pc hygiene kit to work on the base. Keeping footwear clean is vital in minimizing the risk of spreading Pc. Footwear should be cleaned prior to entering and upon leaving a works area and immediately before and after going off tracks or entering vegetation (even slashed road verges), although this should be avoided wherever possible.

Ensure you disinfect your boots where they will not pick up soil again once you put them down. Personal Pc hygiene kits should contain: • Hard brush to clean footwear. • Spray bottle containing Phytoclean* The spray bottle should be adequate in removing the soil from

your footwear. Cleaning Procedure:

1. Select a hard well-drained site – (or sitting in your vehicle); 2. Remove all plant and soil from one boot with the brush (if necessary); 3. Do not put that boot on the ground or onto surfaces where there is soil; 4. Disinfect the entire sole with the disinfectant (and any other areas of the shoe with soil). The nozzle

of the spray bottle should be on ‘direct’ so that as much soil as possible is physically removed by the spray;

5. Allow the sole of the shoe to dry – for Phytoclean 30 seconds is enough; 6. Step forward to avoid recontamination (do not step onto areas where you will recollect soil); 7. Repeat steps 2 to 6 with other boot; 8. Disinfect the brush.

Alternatively a cleaning station may be provided including boot scrappers and footbath for personnel to pass through when entering and leaving the work area.

Tools and equipment prior to entering or leaving Pc Control areas

Spreading Pc to previously unaffected areas

Tools should be treated in the same manner as footwear –

• once works have finished in an area, remain in that area, • use the brush to remove any large amounts of soil from each tool, • disinfect with Phytoclean, allow to dry for 30 seconds. • Repeat this measure if tools come into contact with soil after disinfecting, or in vehicles.

*Phytoclean® is a hard surface application treatment which is classified a non- hazardous product. Phytoclean® is high in detergency and washability ensuring there is no residue when used in washdown situations and is effective in as little as 30 seconds. Phytoclean® is a quaternary ammonium solution.

Page 39: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

environmental Work Method Statement

PHYTOPHTHORA CINNAMOMI (PC) HYGIENE REV: 0

DATE: 10 SEP 2014

EWMS 002

PROJECT: NACC - RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 39 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Page 40: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 40 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

Appendix D

Fauna Rescue and Release Guideline

Introduction

Construction projects invariably interact with local fauna species during clearing of vegetation or ongoing construction works. This guideline has been developed to ensure that any fauna encountered during clearing or ongoing works are treated in the most appropriate manner to ensure their safe handling and release back to their natural habitat.

This guideline is therefore split into 2 sections, being:

1. Fauna Rescue; and

2. Fauna Release

1. Fauna Rescue Guidelines

It is assumed that fauna encountered during selected habitat searches and recovery will, in most cases, comprise commonly occurring native vertebrates.

Immediately prior to clearing, the project Ecologist will conduct pre-clearing fauna surveys within each area to be cleared. Where hollow bearing trees

(HBT) are present a two-stage clearing protocol will be implemented to provide maximum opportunity for fauna to relocate to nearby retained vegetation and minimise fauna injury.

However, if an animal (including injured, shocked or juvenile) or eggs are discovered during the pre-clearing survey, during clearing itself or at any time during construction, the following guidelines should be followed:

1a. Planning for Rescue

Basic equipment for fauna rescue (cotton bags, canvas bags, gloves) will be kept in on site for emergency use by site staff if required. The Project Ecologist or wildlife handler will also carry appropriate fauna rescue kit whilst on site.

The Environmental Manager will hold the contact details of fauna rescue services, local veterinary surgeons and the Project Ecologist. Contact details will be made readily available to site staff at all locations where clearing is to be undertaken.

1b. Fauna Rescue

If fauna require handling, this will be done with care and by the licensed fauna handler where available. In emergencies fauna may also be handled by the Environment Coordinator or other nominated personnel.

Provide appropriate temporary housing for rescued fauna that is species-dependent. This includes:

Gliders, possums, bats, snakes, lizards and frogs can be held individually in a cotton bag until release in adjacent habitat.

Nestling birds and eggs are best placed in a covered cardboard box equipped with soft cloth.

For large animals it is best to cover the animal with a towel or blanket first to minimise stress and firmly but gently place it in a cardboard box, or natural fibre bag.

Smaller animals, can be placed in a cotton bag, tied at the top.

Any fauna which cannot be released immediately or by the evening of the day clearing occurred will be handed to wildlife rescue personnel.

Rescued fauna must be protected from exposure to heat and removed from the areas undergoing clearing or construction activities to minimise exposure to noise. Keep the animal in a quiet, cool, ventilated and dark place.

If the animal is seriously injured and requires immediate attention, as determined by the Project Ecologist or Wildlife Handler, the rescue agency should be contacted immediately or taken directly to a veterinary practice.

If the Project Ecologist or Wildlife Handler is not present when an injured/juvenile animal is found, the rescue agency should be called immediately.

If the animal does not require immediate attention, as determined by the Project Ecologist or Wildlife Handler, the rescue agency should be called in the afternoon and they would collect any animals requiring attention.

If the animal is reluctant to move away or is injured, then it should not be released and a fauna rescue agency should be contacted.

Some animals require particular handling (e.g. venomous reptiles, raptors) and should not be handled by site personnel. If the animal cannot be handled, record the exact location of the animal and contact the rescue agency. If possible a spotter should monitor the location of the animal from a safe distance.

Once the rescue agency arrives at the site, they would be responsible for the animal. Any decisions regarding the care of the animal would be made by the rescue agency.

Page 41: LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 ... LEASE BUILDING PTY LIMITED | ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

CONSERVATION & HABITAT MANAGEMENT PLAN Page 41 of 41

LLB ISSUE: 5 ISSUE DATE: 27/11/2015 ev

If the rescue agency cannot be contacted, the Project Ecologist or Wildlife Handler would deliver the injured/captured animal to the agency as soon as practically possible.

Any drivers of vehicles in recently cleared areas are to be made aware that fauna may still be in the area (e.g. koalas, kangaroos), and are at risk from vehicle collisions.

Identified local fauna rescue agencies and contacts as at November 2014 include:

Organisation Phone Number

Native Animal Trust Fund – Wildlife Rescue Service 0418 628 483

1c. Post Fauna Rescue

After the completion of fauna relocation, a brief record detailing the findings of the survey and relocation will be prepared, including details of:

Any live animals that are sighted, captured, released, injured, shocked or killed as a result of clearing operations and fauna rescue.

Tree species being used for breeding or roosting by fauna, including tree locations, sizes, heights and depths of hollows.

2. Fauna Release

If the animal is not injured, it may be released nearby in an area that is not to be disturbed by the road construction in accordance with the following guidelines:

Prior to any clearing works, several sites within or near the project site would be identified as suitable release points by the Project Ecologist or Wildlife Handler.

The Project Ecologist or Wildlife Handler would be primarily responsible for undertaking any release, or advising site personnel on release processes if not present on site.

If the species is nocturnal, release would be carried out at dusk.

No release would take place during periods of heavy rainfall, unless the Project Ecologist or Wildlife Handler determines that the animal is too stressed to be held any longer.

Any fauna which cannot be released immediately or by the evening of the day clearing occurred will be handed to wildlife rescue personnel.