Learning plan from past incidents

Embed Size (px)

Citation preview

  • 8/17/2019 Learning plan from past incidents

    1/27

  • 8/17/2019 Learning plan from past incidents

    2/27

    2 3

    Table of Contents

    1 Foreword 4

    2 Introduction 5

    3 Accident Types 6

    3.1 Fall from height fatal accident at Plant 27 63.2 Fall from Crane 8

    3.3 Dropped object accident at Installations Area 10

    3.4 Fall from height during Train 1 Shutdown 12

    3.5 Fall from height in ADGAS Main Stores 14

    3.6 Injury due to incorrect work practice 16

    3.7 Crane Failure Incident – ADGAS Ofce Building 18

    3.8 Crush injury due to unsafe work practice 20

    3.9 Injury during Maintenance at STOREX Tank Farm 24

    3.10 Fire and Equipment Failure 26

    3.11 Injury due to incorrect work practice during construction work 28

    3.12 Injury during construction work at Train 3 Sub-station #7 323.13 Fall from height injury 34

    3.14 Property damage due to crane runaway – Pentane Line 36

    3.15 Injury to construction worker due to ying object 38

    3.16 H2S Gas release leading to fatal from height 40

    3.17 Severe injury to multiple workers due to Electrical Flash 44

    4 Learning from our past mistakes 47

  • 8/17/2019 Learning plan from past incidents

    3/27

    4 5

     Abu Dhabi Liquefaction Company

    (ADGAS) owns and operates an

    LNG Plant at Das Island located

    approximately 160 km North West

    of Abu Dhabi City. The plant con-

    sists of two identical Trains (Trains1 and 2) and a third Train (Train

    3) and associated facilities. The

    plant was originally commissioned

    in 1977 with two Trains and the

    third Train was commissioned in

    the third quarter of 1994. It is de-signed to liquefy the associated

    gas produced from Umm Shaif,

    Zakum and Bunduq offshore eldsthat are operated by ADMA-OP-

    CO. The associated facilities of

    the plant are utilities, tanks and

    product loading facilities through

    two separate jetties, one for LNG

    / LPG / Parafnic Naphtha and the

    other for molten Sulphur.

     As such, ADGAS recognize the

    need to share safety knowledge inorder to achieve its vision through

    the safe and efcient execution of

    its operations. ADGAS has a well

    established HSE ManagementSystem (HSEMS) in place, which

    provides the necessary guidance

    on managing HSE aspects of our

    operations and therefore provide asafe working environment for all of

    us.

    Ever since we began operations

    on Das there have been number

    of incidents over the years, vary-

    ing from plant shutdowns to rst

    aid cases, to fatalities involving ourcolleagues and friends. Our inci-

    dent investigations have identied

    that many of these incidents are of

    a repetitive nature

    The purpose of this booklet is

    to further enhance our efforts in

    meeting the standards and expec-

    tations we have set for ourselves

    by learning from our past mistakes,taking the necessary steps to pre-

    vent reoccurrence and cascadingthese learning’s to our employees

    and contractors.

    1. Foreword

    The oil and gas industry processes,

    stores and exports large quantities

    of hazardous substances including

    flammable and toxic materials, and

    the potential for serious incidents

    to evolve is highly probable.The inherent risks associated within all

    areas of the industry, from construc-

    tion and commissioning, maintenance

    and production, and now increasingly

    so, decommissioning of assets re-

    quires the employment of competent

    people who adopt a positive safety

    behavioural attitude in their daily lives

    and embrace the management proc-

    esses and systems to aid us in assur-

    ing safe and efcient operations.

    When incidents do occur, the result-

    ant surveys and investigations have

    revealed that human factors, such

    as failure to implement procedures

    properly, are often a cause. These

    failures may in turn be attributable to

    root causes such as a lack of training,instruction, communication or under-

    standing of either the purpose or prac-

    tical application of an organisations

    Safety Management System and the

    supporting Safe Systems of Work.

    Investigations into many other inci-

    dents within the industry, from Piper

     Alpha to the Sonatrach Skikda plant

    in Algeria (2004) and BP’s Texas City

    Renery (2005) have revealed that

    a third of all accidents were mainte-

    nance-related with the largest single

    cause being a lack of, or deciency

    in the deployment of safe systems of

    work, primarily, risk assessment, per-

    mit to work and the strict adherence

    to such systems. Indeed, here in theUAE, many incident investigations

    have revealed failures within these

    systems as a root or contributory

    cause, including incidents in our plant.

    Safe systems of work, together with

    the legislation that governs them and

     ADNOC Codes of Practices / com-

    pany guidelines that guide us in the

    development of such systems, associ-

    ated training programs and operation

    manuals have all evolved over the

    years to cope with larger, more com-

    plex sites and operations. This has re-

    sulted in most systems being regularly

    reviewed and revised to form robust

    safe systems of work. So why do we

    still have incidents occurring?

    The kinds of pressure that can com-promise any safe system of work are

    all too familiar – the volume of paper-

    work such as permits, poor planning,

    unrealistic or tight deadlines, inap-

    propriate risk assessment and poor

    safety behaviour.

     Appropriate selection of personnel

    with the required competency is also

    crucial to assuring safe operations, as

    is a deep routed safety culture within

    our workforce.

    2. Introduction

  • 8/17/2019 Learning plan from past incidents

    4/27

    6 7

    On Sunday 22nd October 1995 a

    scaffolder was part of a team erect-

    ing a scaffold extension to an exist-

    ing structure around the piping ris-

    er of LNG Storage Tank 27-D-103

    to enable access for painting.

    He was working approximately 40

    metres above ground level when

    he released his safety harness tobend under a handrail extension,

    and then as he stepped and turned

    on the scaffold extension, the oor

    board platform collapsed and he

    fell to the ground, rst striking the

    piping 3 metres above ground

    level.

    Despite prompt emergency medi-

    cal attention rstly by the on-sit

    Safety Ofcer administrating CPR

    and then the Das Medical Emer-

    gency Team, the casualty died al-

    most instantly as a result of the falland was pronounced dead on ar-

    rival at the Das Medical Centre.

    3. Accident Types

    Two root (or essential factors)causes were identied by theinvestigation team:Mechanical failure: The exten-sion bracket became detachedfrom the upright of the mainscaffold structure due to thescaffold team not being familiar

    with the Layer system.Incorrect work practice and un-derestimation of hazard: Thesafety harness was not securedto a xed structure and misjudg-ing the risks associated with thistype of activity.

    Root Cause

    1. All Supervisors and scaffolders are to be reminded of the need to use

    safety harnesses attached to xed points at all times.

    2. Ensure that all personnel connected with the work attend the Toolbox

    Talk and that it adequately addresses the specic task at hand. In this

    case it did not address the potential hazards/failings associated with the

    locking pin of extension brackets.

    3. Conduct refresher training to all scaffolding staff on Layer scaffolding

    and maintain training record.

    3.1. Fall from height fatal accident at Plant 27

    Overview of Incident

    The resulting investigation identi-

    ed that for a variety of reasons

    there were several delays to the

    maintenance work being conduct-

    ed that resulted in a mixed contrac-

    tor workforce being deployed to

    complete the works within a speci-

    ed time-frame, and with an ex-

    tended workscope than originallyplanned. This also resulted in two

    different scaffold systems being

    utilised, tube and ttings, and the

    Layer supplied system scaffolding.

    Lessons Learned

    Inadequate Leadership or Supervi-

    sion: This was very much lacking

    particularly with respect to the in-

    creased workscope.

    Inadequate competency: Some

    members of the scaffold team were

    not familiar with the Layer system.

    Inadequate Toolbox Talk: The

    Toolbox Talk did not adequately

    address the potential hazards as-

    sociated with the Layer system

    scaffold.

    Contributory Causes

    Tube & Fitting Scaffold 

    Layer Scaffold System

  • 8/17/2019 Learning plan from past incidents

    5/27

    8 9

    Lessons Learned

    1. Ensure that all crane operators are familiar with the crane they are

    required to operate and reinforce the message that the purpose built ac-

    cess routes must always be used whilst conducting routine maintenance

    activities on the crane.

    2. Large sign to be stencilled on the front windshield ledge ‘NO STEP –

     ACCESS FOR CABIN ROOF WINDOW AT REAR OF CABIN’.

    3. Warning sign to be posted at a highly visible location within the crane

    cabin ‘Access to crane platform is only from front and rear at grade level’.

    Root Cause

    On Monday the 22nd April 1996 at

    approximately 07:20, a crane op-

    erator 

    drove his mobile crane to the South

    side of Plant 2, Train 2, where he

    parked awaiting permit authorisa-

    tion.

    Whilst waiting for the required Per-

    mit, the crane operator decided toclean the outside of the crane wind-

    shield and roof window. He left the

    cabin and climbed onto the crane

    chassis to clean the windshield

    then stepped up onto a ledge (be-

    low the windshield) to clean the

    roof window however, upon

    descending back to chassis level,

    he lost his balance. He tried to

    grasp the crane front grab rail but

    failed to hold on and fell approxi-

    mately 2 metres to ground level.

    The casualty was given immedi-

    ate rst aid treatment before being

    carried by stretcher to Marshalling

    Point No.3 before being taken byambulance to the Das Medical

    Centre for immediate treatment for

    a deep laceration of the scalp and

    multiple rib fractures, before being

    transferred to Abu Dhabi Mafreq

    Hospital by helicopter.

    Overview of Incident

    Typical Mobile Crane

    3.2. Fall from Crane

    Hazard underestimated: The

    Crane Operators underestimation

    of the potential hazards whilst con-

    ducting routine maintenance and

    losing his balance in the process

    was identied as the root cause of

    this incident.

    Incorrect work practice: The Crane

    Operator did not use the desig-

    nated access routes, which areprovided with anti-slip pads. The

    access to the roof window is also

    at the rear of the cab.

    Contributory Causes

  • 8/17/2019 Learning plan from past incidents

    6/27

    10 11

    On the morning of Monday the

    22nd April 1996 a small team of

    scaffolders and labourers were

    dismantling scaffolding on the

    West side of LNG Tank 27-D-104

    following a suspension of the work

    to allow inspection activities to take

    place to lower sections of the shell.

    Two scaffolders were removing a

    bracket and pulley wheel assem-

    bly from a vertical scaffold pole

    at the 13th lift (approx 26 metres

    above ground) in preparation for

    using it at a lower level of the scaf-

    fold structure.

    During the process of lowering

    the combined pulley wheel and

    bracket over the scaffold structure

    handrail, the bracket became de-

    tached from the pulley wheel and

    fell, striking a labourer who was

    working at ground level, within the

    exclusion area, collecting loose

    scaffold ttings.

    The labourer suffered severe facial

    lacerations and was transferred by

    ambulance to Das Medical Centre

    for immediate treatment before be-

    ing evacuated by helicopter to Abu

    Dhabi Mafreq Hospital.

    Inadequate Leadership or Super-

    vision: The inspection of the work-

    site and workscope following the

    suspension was not conducted.

    Inadequate Leadership or Super-

    vision: The inspection of the work-

    site and workscope following the

    suspension was not conducted.Inadequate procedure, practic-

    es or guidelines:  There was no

    formal procedure in place for low-

    ering the combined pulley wheel

    and bracket, nor did the contractor

    have adequate systems in place to

    address the potential hazards for

    the task at hand.

    Inadequate Toolbox Talk: Thereas no record of a Toolbox Talk be-

    ing conducted to address the spe-

    cic task at hand.

    3.3. Dropped object accident at Storex Area

    Overview of Incident

    Root Cause

    Dropped objects can be fatal 

    Lessons Learned

    1. Install and use securing devices on all pulley gin wheel support hooks.

    2. Develop and issue a formal procedure for lowering pulley arrange-

    ments during scaffold activities, addressing aspects of potential hazards.

    3. Re-enforce adequate exclusion zones.

    4. Ensure that all personnel connected with the work attend the Toolbox

    Talk and that it adequately addresses the specic task at hand.

    5. Establish frequency and scope of site inspections, particularly with

    respect to recommencing work following a period of suspension,

    Incorrect work practice and haz-

    ard underestimated: The lowering

    of the combined pulley wheel and

    bracket without a securing de-

    vice and the fact that a man was

    present within the exclusion zone

    whist work was in progress over-

    head were identied as the root

    causes of this incident.

    Contributory Causes

  • 8/17/2019 Learning plan from past incidents

    7/27

    12 13

    In the afternoon of the 2nd May

    1998, a contract Mechanical Su-

    pervisor fell from approximately 7

    metres off a rope ladder whilst at-

    tempting to exit a Butane Treater

    Vessel (9-C-102b) via the top noz-

    zle, after completing inspection of

    the vessel internals with a third

    party inspector.

    The Mechanical Supervisor lost

    his grip on the rope ladder and as

    he was not wearing the prescribed

    safety harness (as required by the

    PTW) the fall resulted in fractures

    to his pelvis, vertebra and right fe-

    mur.

     Although the Mechanical Supervi-

    sor was an experienced contrac-

    tor, the resultant investigation into

    this incident identied that his age

    (57), bulky physique and unt con-

    dition may have caused him to

    lose his footing on the rope lad-

    der due to exhaustion through the

    effort of climbing the rope ladder.

    He subsequently lost his grip ashe was unable to support his full

    weight. If he had been wearing the

    safety harness as per the PTW re-

    quirements then the severity of this

    accident would have been greatly

    reduced.

    During the incident investigation,

    the following also came to light:

    • The onsite Safety Advisor did not

    have any means to raise the alarm

    and entered the conned space to

    aid the injured party without due

    consideration for his own safety.

    • The incident area became con-

    gested with Fire and Rescue ve-

    hicles, unauthorised Police and

    State Security and Medical vehi-

    cles. Additionally, these people en-

    tered the area without appropriate

    PPE.

    3.4. Fall from height during Train 1 Shutdown

    Incorrect work practice and un-

    derestimation of hazard: The

    Mechanical Supervisors underes-

    timation of the potential hazards

    whilst ascending the rope ladder,

    coupled with his lack of physical

    tness, and the failure to wear a

    safety harness were identied as

    the root cause of the incident.

    Root Cause

    1. Due consideration to a persons physical age, size and tness must

    be taken into account before assigning him to tasks involving restricted

    or difcult access.

    2. Suitable safety harnesses must be worn by all persons using rope

    ladders.

    3. Safety Assistants must be provided with adequate and appropriate

    means to raise the alarm in the event of an emergency.

    4. Work procedures and associated training programs must address the

    roles and responsibilities of Safety Assistants during conned space en-try activities.

    5. Site safety induction training should be given periodically to person-

    nel who do not normally work within plant areas, for example the Police,

    State Security and Medical personnel, to ensure that they are familiar

    with the potential site hazards.

    6. The Operations Shift Superintendent is responsible for assuming and

    maintaining full control of the situation and for directing resources to en-

    sure the incident is effectively brought under control.

    Lessons Learned

    Non adherence to ADGAS PTW

    requirements: PTW conditions with

    respect to the use of a full body

    harness were not followed.

    Inadequate Leadership or Supervi-

    sion: This was very much lacking

    in the build-up to the incident and

    during the emergency response,

    whereby the Police, State Security

    and Medical personnel entered the

    site without adequate PPE.

    Contributory Causes

    Overview of Incident

    Butane Treater Vessel 

  • 8/17/2019 Learning plan from past incidents

    8/27

    14 15

    On Tuesday 3rd November 1998

    at 09:15 a contract rigger fell from

    a height of 2 metres whist work-

    ing within the ADGAS Main Stores

    area and suffered multiple rib frac-

    tures as a result of the fall.

    On the day of the incident, the rig-

    ger was involved in the transfer of

    boxes within the stores area. The

    boxes were covered with tarpaulinwhich was held in place by wood-

    en crates. To remove the wooden

    crates the rigger climbed atop the

    boxes and during the removal of

    the crates, lost his balance when

    he stepped unknowingly between

    the boxes and fell to the ground.

     Although employed as a rigger, the

    contractor was not qualied for this

    role.

    3.5. Fall from height in ADGAS Main Stores

    1. Contract documents to clearly specify the requirement of Third Party

    Riggers and Rigging Supervisors.

    2. Contractors to be instructed that all their personnel must attend the

     ADGAS Safety Induction Course before working in industrial and non-

    industrial areas of ADGAS facilities on Das Island.

    3. The requirements of the ADGAS PTW system must be adhered to atall times.

    4. The practice of holding down tarpaulin covers (on top of boxes) by

    utilising wooden crates (or similar) should be discontinued.

    5. Standing Instructions should be developed and issued for the safe

    handling of boxes and containers within the ADGAS Stores and Harbour

    areas. This should also be part of the tender and contract documents.

    Lessons Learned

    NonadherencetoADGASPTWsys-

    temrequirements: NoPTWwas-

    raisedfor working at height, no risk

    assessment was conducted and

    therefore the potential hazards

    were not addressed and inade-quate work planning was evident.

    Lack of Safety Training: The rig-

    ger had not attended the ADGAS

    Safety Induction Course.

    Inadequate Leadership or Supervi-

    sion: The rigging team were carry-

    ing out the activities with no lead-

    ership or supervision at site.

    Incorrect work practice: The prac-

    tice of holding down tarpaulin with

    wooden crates is considered sub-standard as it introduces further

    risk into the job when it needs to

    be removed for whatever reason.

    Root Cause

    Improper assignment of person-

    nel: The rigger was not qualied

    or experienced in this type of work

    and therefore was not aware of the

    potential hazards when conducting

    such duties.

    Contributory Causes

     All falls from height can cause damage to the human body 

    Overview of Incident

  • 8/17/2019 Learning plan from past incidents

    9/27

    16 17

    On the morning of the 31st De-

    cember 1999, a contractor em-

    ployee was assisting six other men

    in erecting the steel frame of the

     ADGAS Ofce Building signboard,

    which comprised 4” carbon steel

    pipe weighing 1016 KG.

     As a crane was not available, the

    site Surveyor and Foreman de-

    cided to manually lift the structureonto an ‘Easy Fix’ scaffold platform

    at Level 2 with the aid of twenty

    (20) labourers. Upon completion of

    the welding, the frame was brought

    down to Level 1 of the scaffold plat-

    form with the aid of six (6) labour-

    ers. During this activity, the Welder

    (casualty) was asked to assist

    by raising the frame by 3” - 4” by

    means of a scaffold tube in order to

    place packers under the frame so

    that the supporting transom could

    be removed and the whole struc-

    ture lowered by the six labourers

    with the aid of ropes. As the welder

    was doing this, he lost his balance

    and twisted his right foot. However,

    he completed the activity but within

    30 minutes he complained of pain

    in his right ankle and was trans-ferred to Das Clinic for treatment

    and later referred to hospital in Abu

    Dhabi where it was ascertained

    that he had suffered a fractured

    bone (distal end of bula).

    3.6 Injury due to incorrect work practice Overview of Incident

    Overview of Incident

    Incorrect work practice and inad-

    equate competency: Neither the

    casualty nor the six labourers were

    qualied riggers and had no ration-

    ale or reasoning to lift the frame

    manually.

    Root Cause

     ADGAS Ofce Building 

    1. All lifting operations must be conducted using appropriately qualied

    riggers.

    2. Mechanical lifting equipment to be used for handling heavy/awkward

    structures, and conducted under the strict supervision of appropriately

    qualied supervision.

    3. Method statements to be provided for all heavy lift operations for re-

    view by ADGAS HSE Dept.

    Inadequate work planning: A meth-

    od statement was not submitted by

    the contractor and therefore not re-

    viewed by the HSE Dept.

    Page 14 of 45

    Inadequate procedure, practices

    or guidelines: The contractor had

    no written procedure for the lifting

    operation.

    Inadequate Leadership or Supervi-

    sion: Full mobilisation of the con-

    tractor had not been completed

    and no contractor management

    was on site, thereby resulting in no

    clear chain of command for execu-

    tion of the work activity.

    Contributory Causes

    Lessons Learned

  • 8/17/2019 Learning plan from past incidents

    10/27

    18 19

    On the morning of the 6th Decem-

    ber 2000, a tower crane failed and

    dropped its load onto scaffolding,

    resulting in damage to the scaf-

    fold but fortunately no one was

    harmed.

    The crane was being utilised in

    construction work for the new

     ADGAS Ofce Building and the

    team comprising Crane Driver,Banksman and Riggers conducted

    their work well. An ADGAS Safety

    Representative was also in attend-

    ance.

    The crane was loaded with an

    empty steel bucket, having just

    been emptied of concrete blocks

    on a platform near the top of the

    building. On completion of the lift,

    the crane driver changed from 2nd

    gear to neutral, when the brake

    would normally have engaged. It

    then slewed anti-clockwise and

    travelled the radial bogie inwards.

    The crane driver realised some-

    thing was wrong but was help-less as the hoist rapidly dropped

    uncontrollably, landing on an un-

    manned scaffold approximately 3

     – 4 metres from the original hoist

    position and where two men were

    previously standing.

    3.7. Crane Failure Incident – ADGAS Ofce Building

    Overview of Incident

    Mechanical failure: the cause of

    the accident was indentied as the

    failure of the splined drive shaft.

    Contributory Cause

    Incorrect work practice and in-

    adequate competency: Although

    the Contractor site Mechanic had

    serviced the crane previously and

    had been instructed to have a look

    at the gearbox at regular interval,

    it appears he was unaware as to

    what he was looking for. Further-

    more, there were no recorded de-

    tails of previously conducted main-

    tenance servicing or indeed, any

    proper maintenance procedures.

    Root Causes

    During the course of the investi-

    gation, a number of irregularities

    were found, including:

    • The crane purchased second

    hand in 1995 (manufactured in

    1979) and brought to Das in Feb-

    ruary 2000. No maintenance man-

    ual or drawings were available.

    • There was no written mainte-

    nance history available. Weekly

    checks were made but these were

    considered dubious as the exact

    wording was used every week.

    • The gearbox inspection revealed

    excessive play of the internals,

    missing lock-washers, heavily

    worn gear teeth and the bearing

    housing had been welded in two

    places, which suggests severe

    damage in the past.

    Tower Crane dropped load on to scaffolding

    Tower Crane

    Lessons Learned

    1. Future contracts should consider stating a minimum age for cranes

    and associated components, and have the service history made avail-

    able.

    2. Prior to award of a contract, companies must demonstrate that they

    have a sound HSE Management System.

    3. Mechanics must be adequately trained and assessed as competent.

    4. Proper maintenance schedules for the different inspections must be

    provided and maintained

  • 8/17/2019 Learning plan from past incidents

    11/27

    20 21

    The scaffold platform around

    the exchanger was cleared of

    al l non-essential personnel, leav-

    ing the:

    • Rigging Supervisor, who was in

    charge of the lifting operations and

    positioned at the North end of the ex-

    changer, ready to adjust the two off

    chain blocks to level the exchang-

    er on the horizontal plane. A single

    sling was tted to the South end

    of the exchanger and Tirfor lines

    were attached to restrain lateral

    movement.

    • Rigging Foreman was stationed

    at the East side of the exchanger

    on the same level.

    • Banksman was positioned at the

    South side, with a clear vision of

    the other two and would commu-

    3.8. Crush injury due to unsafe work practice

    Overview of Incident

    Root Cause

    Position of Rigger when he sustained Crush Injury at his left hand

    On Thursday 24th May 2001, a third party contractor work team

    were preparing to change out a Propane De-superheater Exchang-

    er (weighing approx 18 tons), located at the top of the exchanger

    bank on Plant 6, approx 7 metres above ground level.

    The removal of the leaking exchanger was to be effected by utilising a

    32 ton capacity Liebherr mobile crane, together with an arrangement of

    chain blocks and ‘Tirfor’ lines to control any lateral movement.

    Unsafe work practices: The unsafe act committed by the Banksman in-

    dicates a low level of behavioural safety.

    nicate with the crane driver by

    means of hand signals.

    The Rigging Supervisor gave the

    instruction to the Banksman to

    commence the lift slowly and lift

    the exchanger by only 5mm.

    The exchanger lifted approximate-

    ly 5mm only at the South end and

    immediately slewed slowly to the

    West, towards the sister exchanger.

    In an attempt to restrain the move-

    ment, the Banksman, with his left

    hand on the outer rim of the ex-

    changer suffered severe crush in-

     juries when contact between the

    two exchangers occurred. He was

    escorted from the worksite and

    was transported to Das Clinic by

    car where he received initial medi-

    cal treatment before being trans-

    ferred to the Central Hospital in

     Abu Dhabi for further treatment to

    a severed index nger, crushed

    second and third ngers and lac-

    erations to the back and palm of

    the left hand.

    Mobile crane

  • 8/17/2019 Learning plan from past incidents

    12/27

    22 23

    1. Safety behaviour training for all contractors is essential to assuring

    safe operations and contractors are to ensure that this type of training

    forms an inherent element to their training program.

    2.The assigned Banksman must always stand clear of the lift and be

    dedicated to to providing the communications link with the crane driver

    only, leaving the hands on control of the lift to other members of the rig-ging team.

    3. Rigging Procedure / Instructions to indicate correct positioning of all

    lifting equipment involved in any lift, with the Rigging Supervisor carrying

    out a check that all is in order prior to the lift.

    4. Contractors must arrange a joint meeting to discuss critical lifting op-

    erations with ADGAS Rigging Supervisor and HSED.

    Lessons Learned

    Contributory Causes

    Incorrect work practices:  The

    incorrect positioning of the lifting

    sling and crane hook not aligned

    in a plumb position. Additionally,

    there were an insufcient number

    of correctly positioned restraining

    lashes (Tirfor wires) to prevent lat-

    eral movement of the exchanger

    during the initial stages of the lift,

    with no tag lines secured to con-

    trol lateral movement thereafter.

     Also, the Banksman should not be

    involved in the ‘hands on’ activities

    of controlling the lift.

    Inadequate work planning:  A

    critical situation arose late in the

    maintenance period which neces-

    sitated removal of the exchanger

    in a limited time frame, resulting

    in the work not being thoroughly

    thought through.

    Poor safety behaviour: The con-

    tractor exercised poor safety be-

    haviour during the lifting operation

    with regard to their actions.

    Poor coordination: Poor co-

    ordination and cooperation

    between ADGAS/Contractor Rig-

    ging Departments prior to the lift-

    ing operation was identied as a

    contributory factor which formed

    the background to the chain of

    events leading to the accident.

  • 8/17/2019 Learning plan from past incidents

    13/27

    24 25

    On the 5th November 2001, con-

    tract Scaffolders were erecting

    platforms to enable overhaul ac-

    tivities to be carried out on the

    personnel elevators on Tank 27-D-

    103 and 27-D-105.

    Three PTW’s were issued for work

    on 27-D-105, one Cold Work PTW

    for scaffolding, one Hot Work PTW

    for routine instrument maintenance

    on the tank level gauges and oneCold Work PTW for routine me-

    chanical work on an air hoist.

    During the execution of the works,

     ADGAS Mechanical personnel

    used the elevator to ascend to the

    top of the tank to commence work

    on the air hoist and left the elevator

    at the top level.

     An ADGAS Senior Instrument

    Technician, on returning from his

    tea-break found the elevator was

    at the top level and pressed the call

    button for the elevator however, a

    scaffolder was working close to the

    elevator well and his foot became

    trapped between a support struc-ture and the side of the elevator

    when it started to descend. The el-

    evator emergency brake activated,

    securing the elevator and defeat-

    ing normal operation.

    The alarm was raised, the elevator

    electrically isolated and ADGAS

    mechanical personnel attempted

    to free the scaffolder by levering

    the elevator car by means of a

    scaffold tube. This proved unsuc-

    cessful and they eventually freed

    him by cutting through the eleva-

    tor structure cross beam using a

    hacksaw. The injured scaffolder

    was pulled clear and treated at the

    scene by medical personnel and

    administered a pain killing injection

    before being transferred to ground

    level by stretcher via the stairs andtransported to Das Clinic.

    3.9. Injury during Maintenance at STOREX Tank Farm

    Overview of IncidentRoot Cause

    Elevator at 27-D-105 

    Location at the platform where the

    scaffolder had his foot trapped 

    Poor safety behaviour: The

    scaffolder exercised poor safety

    behaviour by standing on the

    elevator structure cross mem-

    ber in the knowledge that the

    elevator was live. Additionally,

    the contractor Safety Ofcer,

    who had direct responsibility to

    be present at the worksite, was

    located at ground level.

     storex earea

  • 8/17/2019 Learning plan from past incidents

    14/27

    26 27

    Inappropriate risk assessment:The Risk Assessment was con-ducted by the contractor in AbuDhabi and no site visit was con-ducted. Additionally, the change inthe work process invalidated theRisk Assessment.Poor coordination:  There waspoor coordination and cooperationbetween ADGAS and Contractorpersonnel. At the kick-off meeting,most of the attendees were una-

    ware of the detailed work area inrelation to the operational elevator,and the Senior Instrument Techni-cian was unaware of the on-goingwork adjacent to the elevator.Inadequate PTW preparation: 

    The PTW conditions were ambigu-ous, stating “elevator to be rackedout if required”. Also, the PTW wasprepared by the night shift, hadno detailed drawing or associateddocumentation, and no site visitwas conducted prior to approv-al. Additionally, liaison between

     ADGAS Mechanical Supervisorand contractor Site Supervisor wasidentied as virtually non-existentwith respect to the PTW.

    1. Safety behaviour training for all contractors is essential to assuring

    safe operations, with the ADGAS Advanced Safety Awareness scheme

    being adopted by contractors.

    2. The ADGAS method for Risk Assessments to be adopted with a site

    visit being a mandatory requirement.

    3. ADGAS to review PTW procedure with respect to specic roles andresponsibilities, and the policy regarding the allowance of accepting Per-

    mits by ADGAS personnel for one discipline on behalf of another dis-

    cipline. PTW training should also highlight the risks involved in adding

    ambiguous precautions to Permits.

    4. Review procedures for work on elevator structures and dene when

    elevator should be racked out.

    5. Ensure that all personnel connected with the work attend the Toolbox

    Talk and that it adequately addresses the specic task at hand.

    Lessons Learned

    Contributory Causes

  • 8/17/2019 Learning plan from past incidents

    15/27

    28 29

    Following the completion of

    maintenance the pump was

    returned to service and re-

    streamed following normal op-erational procedures and the

    standby pump shutdown.

     After approximately 25 minutes

    of running, the pump experi-

    enced, in quick succession, ab-

    normal vibrations, high bearing,

    shaft and coupling tempera-

    tures, which resulted in a re at

    the inboard turbine bearing, fol-

    lowed rapidly by a catastrophic

    failure of the shaft and coupling.

     Although the re was quickly

    extinguished using portable re-ghting appliances, attempts to

    re-start the standby pump failed

    due to an electrical permissive

    (design feature) that prevents

    the pump from being restarted

    within 30 minutes of shutdown.

    The rst attempt to restart was

    attempted at 26 minutes after

    shutdown. The failure to main-

    3.10. Fire and Equipment Failure

    Overview of Incident

    Component failure: The speed indication probe failure was iden-

    tied as the most likely cause of bearing failure.

    Incorrect sensor setting: The turbine air purge pressure was setfar in excess of the recommended setting.

    Contributory Causes

    Inadequate working conditions: The presence of grit blast mate-

    rial, prevailing wind conditions and exposed bearings was identi-

    ed as a contributing cause of the bearing failure.

    Root Cause

    On Thursday 31st January 2002, HP Lean Carbonate Pump 2-G-

    104A was released for 6-monthly routine maintenance activities

    to be carried out, which involved bearing inspections but did not

    require uncoupling of the pump.

    1. Ensure that maintenance activities and sensor settings strictly

    adhere to manufacturers recommendations.

    2. Ensure that meticulously clean working areas are maintained

    during invasive maintenance activities. The fact that grit blast-ing activities had been recently carried out in the proximity of the

    pump, and the high winds experienced during the maintenance

    activity would have made it very difcult to keep the bearings clean

    during the procedure.

    Lessons Learned

    tain either pump on-line result-

    ed in a plant shutdown and loss

    of production.

     A fault tree analysis method of

    investigation was applied which

    identied two root causes with a

    contributory cause. However, it

    should be noted that the investi-

    gation was hampered due to the

    large extent of damage caused

    by the re and catastrophic me-

    chanical failure.

    Carbonate Pump

  • 8/17/2019 Learning plan from past incidents

    16/27

    30 31

    On 30th July 2005, a Mechani-

    cal Helper was working for the

    Boil-off Gas (BOG) project when

    he fell from ground level to the

    base of a 2.8 metre deep exca-

    vated trench. The team was en-

    gaged preparatory works asso-

    ciated with the rewater tie-ins

    for the BOG Plant.

    The accident happened when

    the injured person was in the

    process of moving a PVC con-

    duit containing electrical/instru-

    ment cables to one side of the

    trench so that a section of the

    new rewater piping could be

    laid within the trench. The PVC

    conduit protecting the under-

    ground electrical services was

    suspended by means of a rope

    to a 6 metre long scaffold tube,

    which traversed the excavation.

    Despite being told to wait at

    the worksite until the Foremancould provide him with addi-

    tional help to assist with the

    task, the Mechanical Helper

    proceeded on his own to pull

    one end of the scaffold tube to-

    wards him. As a result, the op-

    posite end of the scaffold tube

    dropped into trench and the end

    which he was holding swung

    upwards and struck him on the

    thigh, causing him to lose bal-

    ance and fall to the base of the

    excavation.

    3.11. Injury due to incorrect work practice during construction work

    Overview of Incident

    To complicate matters, the in-

     jured person was helped from

    the trench and then left the

    scene of the accident and as-

    sisted by colleagues to the

    Contractor Site Ofce to see the

    Deputy HSE Manager however,

    he was not there and it was de-

    cided he should go to Das Clin-

    ic, whereupon he was admitted

    for treatment. The following day

    he was transported by helicop-

    ter to hospital in Abu Dhabi but

    discharged himself later that

    day. He was then taken to the

    Contractor ofce in Abu Dhabi

    and assigned ofce duties.

    This pipe was not inside the trench dur-

    ing the accident.The injured person was pulling the scaffolding

    bar to clear the area for the crane to put the

     pipe inside the trench.

  • 8/17/2019 Learning plan from past incidents

    17/27

    32 33

    Non adherence to ADGAS Emergency procedures:  No

    attempt was made to inform the Shift Superintendent or the Con-

    trol Building to request medical assistance, even though the in-

     jured person was complaining of lower back pain.

    1. Performing Authorities (ADGAS or Contractor) must ensure that

    all work is carried out in accordance with ADGAS procedures.

     Additionally, all work must stop should conditions change at the

    worksite, and a re-assessment of the risks undertaken as per

     ADGAS procedures.

    2. Ensure that all work party members attend the Toolbox Talk and

    that it adequately addresses the specic task at hand, and covers

    the topic of the correct actions to take in calling for medical assist-

    ance and handling of any casualty.

    3. Advanced Safety Audits (ASA) must cover the subject of job

    specic Toolbox Talks.

    4. The practice of dropping down dismantled scaffold material to

    the ground, thereby making the work area an unsafe place is con-

    sidered a dangerous and unacceptable activity. These should be

    properly handled and deposited into containers or bags to ensure

    correct and safe handling procedures.

    5. All Contractor Job Ofcers must verify that unskilled employees

    have a minimum of one year’s experience in their line of work.

     Additionally, Contractor HSE Auditors must also verify this require-

    ment.

    Lessons LearnedRoot Cause

    Incorrect work practice: The arrangement in adopted in secur-

    ing the PVC conduit to protect the underground electrical services

    was substandard.

    Contributory Causes

    Lack of communication: Poor communication between Mechan-

    ical Helper (injured person), Foreman and Mechanical Supervisor.

    Lack of experience: It became

    evident that the injured person’s

    construction work experience

    was extremely limited and thatprior to this particular incident

    he was observed working in

    the trench alone and was ques-

    tioned by the Safety Ofcer,

    where it was noted that he was

    totally unaware of the inherent

    dangers of working alone in aconned space and within close

    proximity to a live gas plant.

    Non conformance to Task Risk Assessment: Although the Task

    Risk Assessment adequately addressed the potential hazards, the

    associated control measures were not enforced.

    Inadequate Toolbox Talk: 

    There as no record of a Tool-

    box Talk being conducted to ad-

    dress the specic task at hand.

    Change of worksite condi-

    tions: The removal of the cer-

    tied walkway across the exca-

    vation forced the Contractor to

    look at alternatives ways to com-

    plete the task and the method

    of suspending the conduit by a

    length of rope to a scaffold tube

    was employed, and later identi-

    ed as a major contributory fac-

    tor to the incident occurring.

  • 8/17/2019 Learning plan from past incidents

    18/27

    34 35

    The onsite contract Foreman admin-

    istered rst aid at the worksite and

    utilised a dust mask to dress the in-

     jury. The Foreman then contacted

    the on site contract Supervisor to

    inform him of the incident before

    driving the labourer to the contrac-

    tor onsite ofce for further medical

    treatment. This was conducted by

    the ofce boy (who did not hold a

    valid rst-aid certicate) by applying

    Savlon cream and a cleansing so-

    lution to the injured nger. He later

    informed his Manager that the injury

    was not serious.

    The onsite Project Manager then in-

    formed the injured labourer to rest in

    his room before granting him com-

    passionate leave and travel to Abu

    Dhabi.

    Whilst waiting for his ight at Das

     Airport, he was spotted by the Police

    covering his left hand with a scarf.

    When questioned, the labourer in-

    formed the Police of the accident

    and he was requested to attend

    Das Police Station before being

    transferred to Das Clinic for proper

    medical treatment. He was detained

    overnight and released the following

    morning.

    3.12. Injury during construction work at Train3 Sub-station#7

    Overview of Incident

    Inappropriate method state-

    ment and risk assessment:

     Although a Method Statement

    and Risk Assessment were

    conducted, neither addressed

    the hazards posed by the U-

    shaped reinforced steel barsthat protruded from the ground

    during the demolition works.

    Inadequate Supervision: Dur-

    ing the interview sessions as

    part of the incident investigation

    it was noted that the contractor

    line management were aware of

    the potential hazards posed by

    the U-shaped reinforced steel

    bars and indeed, the mitigation

    measures but they did not dis-

    seminate this to personnel actu-

    ally performing the work.

    Inadequate work brieng: Al-though the brieng session cov-

    ered general topics such as the

    use of PPE and housekeeping,

    it did not highlight the specic

    risks to the actual task at hand

    to those conducting the work.

    Root Cause

    On the 12th November 2005, a contract Labourer was working with a

    pneumatic jack hammer conducting demolition work on a concrete foun-

    dation when the hammer drill bit became stuck in the concrete. The la-

    bourer managed to forcefully free the drill bit but by applying a rocking

    motion and in doing so, his left hand ring nger was jammed between

    the jack hammer handle and a U-shaped reinforcement steel bar (Refer

    Fig 5), resulting in a minor injury.

    1. A more in-depth, detailed Method Statement to be developed

    and used as the basis for the Risk Assessment with all potential

    hazards addressed.

    2. Contractor management and supervision must review the ap-

    propriate project plan and become fully conversant with ADGAS

    procedures.

    3. Conduct daily work brieng sessions that address the specic

    task at hand with reference to the associated Method Statement

    and Risk Assessment.

    4. Ensure that all contractors are aware of the correct actions to

    take in the event of any accidents occurring at the worksite.

    5. Nominated rst-aiders are to be appropriately trained and a

    list of qualied rst aiders displayed at Contractor Ofce notice

    boards.

    U shaped reinforcement steel bar hazard U shaped reinforcement steel bar hazard 

    Unsafe work practices: The unsafe use of the pneumatic jack ham-mer by the Labourer indicates a low level of behavioural safety when

    using pneumatically operated equipment.

    Contributory Causes

    Lessons Learned

  • 8/17/2019 Learning plan from past incidents

    19/27

    36 37

    The injured scaffolder along with his

    team of 3 persons was engaged in the

    dismantling of the scaffold, under a

    General Cold Work Permit.

    The accident occurred when the in-

     jured scaffolder was dismantling the

    scaffold at approximately 2.16 me-

    tres and was un-doing a Beam Clamp

    (Gravelock). During the process, thespanner slipped, he lost balance and

    fell backwards and collided with the

    1.2 metre high guard rail behind him.

    The guard unfortunately had loose t-

    tings and the force of the impact dis-

    lodged the guard rail from the scaffold

    structure and it fell to the ground. Sub-

    sequently, with the backwards motion

    the injured person fell to the ground,

    landing on his back atop the fallen

    guard rail and scaffold clamps, which

    had previously been removed in the

    dismantling process.

    The injured scaffolder was immedi-ately transported by ambulance to

    Das hospital the later medivac to Abu

    Dhabi by helicopter for further medical

    treatment.

    3.13. Fall from height injury

    Overview of Incident

    Inadequate work planning: A specic Toolbox Talk for the activity, out-

    lining the potential risks and hazards was not evident.

    Non conformance to procedures/standing instructions: CITB certi-

    ed scaffolders are a mandatory requirement yet this was compromised

    with a parallel process to carry out the certication as soon as possi-

    ble. This is a wholly inadequate process and appropriate steps must be

    made to ensure this is not repeated.

    Non adherence to ADGAS PTW requirements:  PTW conditions

    with respect to the use of a full body harness were not followed.

    Root Cause

    Workers on a scaffold structure

      Beam Clamp

    On 15th April 2008, a scaffolder fell from the scaffold structure located

    beneath the Blowdown to Plant 19 Pipe Rack.

    1. Engaged scaffolder certication and records are checked and veried

    by ADGAS prior to them being mobilised to site.

    2. Ensure that all work party members attend the Toolbox Talk and that i t

    adequately addresses the specic task at hand.

    3. The practice of dropping down dismantled scaffold material to the

    ground, thereby making the work area an unsafe place is considered a

    dangerous and unacceptable activity. These should be properly handled

    and deposited into containers or bags to ensure correct and safe han-

    dling procedures.

    4. PTW conditions to be adhered to at all times.

    Incorrect work practice and un-

    derestimation of hazard:  The

    safety harness was not secured

    to a xed structure and misjudging

    the risks associated with this type

    of activity. Complacency had also

    crept into the way the work was

    performed.

     Additionally, the practice of drop-

    ping down dismantled scaffold

    material to the ground, thereby

    making the work area an unsafe

    place is considered a dangerous

    and unacceptable activity, which

    aggravated the injuries sustained.

    Contributory Causes

    Lessons Learned

  • 8/17/2019 Learning plan from past incidents

    20/27

    38 39

    The crane operator was instructed to

    drive his crane (60 tons) by his banks-

    man to Second Street, which was

    temporarily designated as a ‘waiting’

    area for heavy vehicles due to the nor-

    mal heavy vehicle parking areas beingheavily congested. Upon arrival the

    crane operator noticed that Second

    Street was congested with three other

    cranes parked ahead, and the banks-

    man was not there to meet him.

    The crane operator then left the crane

    unattended with the engine run-

    ning and without applying the brake

    to meet with other crane operators.

    He assumed that the crane was bal-

    anced and at an equilibrium position

    but moments later noticed the crane

    roll down the sloped road and hitting

    the parafnic naphtha loading line of

    Plant 21 pipe rack. Additionally, the

    impact of the accident shifted the pipe

    to the North side and caused damageto the adjacent access platform and

    civil foundation.

    It was found that the banksman who

    was supposed to be at Second Street

    with the crane operator was given an

    additional task to submit a Permit to

    another trailer driver located in Area

    502, which caused a delay for him

    getting to Second Street on time to

    instruct the crane operator and the

    cranes movements.

    3.14. Property damage due to crane runaway – Pentane Line

    Overview of Incident

    Inappropriate risk assessment: Sec-ond Street was designated as a tem-porary parking area and waiting areafor heavy vehicles for the Turnaroundactivities without conducting an ad-equate risk assessment.Lack of supervision: There was no co-ordinator assigned at Second Streeton the day of the accident to monitorthe movement of heavy vehicles. Additionally, the assigned banksmanwho was supposed to be at SecondStreet with the crane operator wasgiven an additional task which de-

    layed his arrival at Second Street toinstruct the crane operator and moni-tor his movement.Lack of training: The crane operatorwas recruited by a Contractor in Octo-ber 2008 but the Contractor providedonly one training certicate and thatwas for HSE and breathing apparatus.Inappropriate property protection: Theimpact of the accident shifted the pipeto the North side and caused damageto the adjacent access platform andcivil foundation as there was no bar-rier protection provided.

    Root Cause

    On 15th November 2008, an unmanned crane rolled down a sloped

    (approx 1.6 degrees) road and hit the parafnic naphtha loading line of

    Plant 21 pipe rack, causing damage to the pipe work and ange, which

    resulted in a minor leak.

    Incorrect work practice and underestimation of hazard:  Thecraneoperator

    stopped his crane and left the vehicle unattended with the engine running, with-

    out securing the crane and without applying the parking brake.

    Lessons Learned

    1. Third party certication and competency of crane operators, banksmen andriggers must be assessed and assured during the recruitment process. ADGAS

    should also be involved in the interviewing and selection process before they

    arrive at Das to assure adequate competency of personnel.

    2. Ensure that an adequate risk assessment is conducted to ensure that all

    work and site hazards have been properly addressed.

    3. The assigned banksman should not be given more than one task dur-

    ing shutdown activities and an adequate number of banksmen must be avail-

    able on site at all times.

    4. Removable concrete barriers should be erected at all industrial roads in

     ADGAS Plant areas to protect pipe work and civil foundations to mitigate the

    potential of collision damage.

    Contributory CausesDamage to the Crane loading line & structure

    Damage to parafnic naphtha

  • 8/17/2019 Learning plan from past incidents

    21/27

    40 41

    3.15. Injury to construction worker due to yingobject

    Overview of IncidentLack of hazard awareness: Al-

    though a risk assessment was

    completed for the works that iden-

    tied and documented the control

    measures for this type of work,

    they were not communicated at

    site nor was it present at the work-

    site.

    Lack of training: The injured con-

    tractor had received no training in

    the use of angle grinders.

    Inadequate Toolbox Talk: A toolboxtalk was conducted for the activity

    ten days prior to the incident and

    no reminder or refresher toolbox

    talk was conducted for the task at

    hand.

    Inadequate PPE: Had the contrac-

    tor been wearing the proper PPE

    then he would not have suffered

    injuries to his right jaw.

    Use of substandard/inappropriate

    tools: There was no evidence that

    the angle grinder was purchased

    from a known manufacturer or had

    been subjected to any form of in-tegrity checks.

    Root Causes

    Lessons Learned

    1. Establish training programs to cover:a. Hazard awareness

    b. Effective toolbox talk for supervisorsc. ASA training to supervisorsd. Use of air powered tools, including associated risk and consequencesof failure to all who use them.

    2. Ensure that toolbox talks are job specic and effectively communi-cated to all concerned at the start of each shift.

    3. All powered tools to be procured from known manufacturers and meet

     ADGAS requirements. They must also undergo preventative mainte-

    nance checks at regular intervals to assure integrity.

    4. Post Safety Flashes and HSE posters at strategic locations through-

    out all plant areas. This provides valuable communication of ‘lessons

    learned’.

    5. ADGAS trained personnel to conduct ASA on regular basis to reinforce

    safety messages and ensure that the correct PPE is worn at all times.

    6. Introduce a mechanism for measuring and rewarding HSE perform-

    ance on project sites in addition to the incentive scheme already in place.

    Underestimation of risk: The de-

    gree of risk associated with us-

    ing the unproven methodology of

    smoothing the concrete with inad-

    equate machine tools (angle grind-

    er) was totally underestimated by

    the Foreman on site. The injured

    contractor was given a brief famil-

    iarisation on the use of the angle

    grinder but not the associated risks

    he was exposed to.

    Contributory Causes

    On the 15 March 2008, civil project

    work was being conducted by

    the assigned contractor and sub-

    contractor, which included the

    preparation and smoothing of the

    concrete surface on the Pre-as-

    sembled Rack (PAR) 102 foun-

    dation footing. This is done by

    the use of a stone cup disc and

    pneumatic powered angle grinder

    prior to water-proong or protec-tive coating application. As part of

    civil works, concrete surfaces must

    be smoothed prior to application

    of water-proong and protective

    coating.

    During execution of the works, the

    contractor was injured with rotating

    ying object from the broken stone

    cup disc assembly striking his

    lower jaw whilst conducting grind-

    ing work on the concrete founda-

    tion. The injured contractor was

    initially treated at Das Hospital and

    then transferred to hospital in AbuDhabi for further treatment.

    grinding machine

  • 8/17/2019 Learning plan from past incidents

    22/27

    42 43

    The key activity was to de-spade the

    Sour and Liquid Flare and Blow-down

    systems, which during streaming

    was isolated from Train 1. After de-

    spading, the system isolation valves

    were to be opened thus making the

    system operational, and thereby link-

    ing the are systems of Trains 1 and

    2. The de- spading was being carried

    out on a platform 10 metres long and

    accessed via an 8 metres high caged

    vertical ladder.

     At approximately 05:25 the next day

    (Day 31 of the overhaul), a Supervi-

    sor and Fitter from the assigned con-

    tractor began to de-bolt the spade on

    the verge of breaking containment,

    they donned their breathing apparatus

    while a Safety Assistant and another

    Fitter were present without BA. A BA

    Technician was also located at ground

    level and operated the BA line.

     At the same time, and in contravention

    of the Operations Procedure, the are

    valves were opened whilst the de-

    spading activities were taking place.

    This resulted in sour gas from Train 1

    being admitted to the Train 2 system,

    up to the crossover at the de-spading

    location.

    3.16. H2S Gas release leading to fatality from height

    Overview of Incident

    Immediate Causes

    Release of high concentration of toxic H2S gas: Acid gas at low pres-

    sure from Train 1 Sulphur Plant containing a high concentration of H2S

    was released during de-spading activities. The release was a result ofthe decision by ADGAS Night Shift Operations Coordinator to open the

    isolation valves before the completion of de-spading activities.

     Access ladder De-spading activities on Platform 10 metresabove ground 

     At the start of the night shift of 21st November 2008, day 30 of the major over-

    haul of LNG Train 2, the Maintenance and Operations Teams were preparing

    for the last shift of mechanical work and including some hot work, after which

    activities related to re-streaming the train for gas-in, was to commence.

    This particular incident was thoroughly investigated and the Board of

    Enquiry identied that the accident was a result of multi causes and cat-

    egorised as follows:

      • Immediate cause

      • Root causes

      • Indirect contributory causes

    The BA Technician (at ground level)

    smelled gas and observed that one

    of the Fitters and the Safety Assist-

    ant had started to descend the caged

    ladder and at a point of about half-

    way down the Fitter suddenly fell to

    the ground at the base of the ladder,

    immediately followed by the Safety

     Assistant, striking his head fatally

    against the ladder cage during the fall

    and landing atop the Fitter.

    The BA Technician at ground level

    was initially overcome by H2S before

    recovering enough to make his es-

    cape. Another Fitter located close-bywas also overcome by H2S and col-

    lapsed unconscious.

     At 0531, gas alarms were activated by

    the escaping gas and then the emer-

    gency alarm was raised, Yellow A

    alert was instituted, Fire and Rescue

    crews mobilised, the deceased Safety

     Assistant, injured Fitter (broken leg)

    and the two individuals overcome with

    H2S where taken to Das Clinic. The

    accident site was cordoned off and

    the Incident Command Centre (Das)

    and Crisis Management Centre (Abu

    Dhabi HQ) were manned until the ‘all

    clear’ was declared at 10:08.

  • 8/17/2019 Learning plan from past incidents

    23/27

    44 45

    Inadequate wearing of PPE: 

    Only two of the four contractors

    present at the elevated platform

    were wearing BA, while the

    other two were exposed to high

    concentrations of H2S.

    Falling from height:  The two

    contractors exposed to high

    concentrations of H2S lost con-

    sciousness whilst descending

    the caged ladder. This resulted

    in them falling, which caused

    one fatality and one serious in-

     jury.

    Non adherence to Operating Procedure: The re-commissioning of the

    Flare system was not carried out by the ADGAS Night Shift Operations

    Coordinator as per the prescribed procedure.

    Non adherence to Safety Procedures: The Contractor Supervisor did

    not ensure that the area was prepared as per the requirements of the

    PTW.

    Lack of hazard awareness: The ADGAS Night Shift Operations Coordi-

    nator was not aware that Train 1 Sulphur Plant was not operational and

    as a result 15 tons of gas, containing high concentrations of H2S was

    being continuously ared.

    Non adherence to PTW: The ADGAS Senior Operator (as instructed

    by the ADGAS Night Shift Operations Coordinator) signed the PTW al-

    lowing work to commence without checking the worksite to ensure site

    readiness as per PTW requirements.

    Root Causes

    1. Review and amend Operational Procedures to address associated

    hazards when de-spading activities are taking place.

    2. Review and amend the PTW process / procedure so that it is the

    Performing Authority that raises the PTW and collates the associated at-

    tachments such as the Task Risk Assessment and not Operations as is

    the case. The PTW close-out process must also be improved to ensure

    that all PTW’s are closed out prior to conducting ‘gas-in’.

    3. Revise roles and responsibilities during Turnaround activities.

    4. Review and improve H2S Hazard Awareness training.

    5. Conduct competency assessment for safety technicians with BA

    standby role, including his responsibilities.

    6. Key critical operations such as de and re-streaming the process train

    to be conducted by ADGAS Maintenance personnel.

    7. Conduct a comprehensive review of the Emergency Response Proce-

    dure to clearly dene roles and responsibilities.

    8. Develop adequate safety training and site hazard awareness pro-

    grammes to ensure safety compliance of Contractor safety personnel

    prior to site work. Training objectives should be set to ensure that the

    training delivers sufcient knowledge transfer to full the training needs

    of the organisation and the individual.

    Lessons Learned

    Lack of H2S awareness:  It was

    evident from the behaviour of all

    Contractor Labour personnel in-

    cluding the Safety Assistant that

    the potential consequence of H2S

    inhalation was not well known to

    them.

    Pressure to meet Turnaround

    completion target:  There was

    a perceived sense of urgency to

    complete the job quickly as ‘gas-in’

    had been planned for the next shift

    and there appeared to be pressure

    on the Operations nightshift crew

    to complete all necessary activi-

    ties.

    Inadequate work practice:  Dur-

    ing the investigation, it became ev-

    ident that this particular contractor

    had been the subject of a number

    of Near Miss Reports (700), PTW

    violations (over 100).

    Indirect Contributory Causes

  • 8/17/2019 Learning plan from past incidents

    24/27

    46 47

    Root Cause

    On the 2nd March 2009, two Hot

    Work Permits were issued to the

    Electrical Maintenance Depart-

    ment (Electrical Technician and

    Electrical Trainee) to carryout rou-

    tine maintenance on Substation

    6, 3.3 kV switchgear. After part of

    the work was completed the per-

    mit was extended up to the 10th

    March 2009.

    Following completion of the rst

    motor feeder, the switchgear was

    tested but the 110V AC auxiliary

    test supply MCB tripped. The Elec-

    trical Technician assumed the trip

    was due to an inrush of current

    and repeated the test several more

    times until they noticed smoke

    emitting from the switchboard

    cubicle, which consequently acti-

    vated the smoke detection system.

    The testing was halted and the

    technician began trouble shooting

    along with the Electrical Supervi-

    sor, who had at this point, arrived

    at the scene.

    By mistake, the Electrical Techni-

    cian connected the multi-pin plug

    in reverse orientation (this was lat-

    er identied as a design fault). This

    caused a short circuit in the control

    wiring, leading to a ow of heavy

    current and ultimately burning the

    PVC wires and generating a lot of

    smoke/soot.

    vestigation, the technician reAs

    3.17. Severe injury to multiple workers due to Electrical Flash

    Overview of Incident Inadequate competence:  TheElectrical Supervisor and Elec-

    trical Technician were not fully

    aware of the bus bar arrange-

    ments, which in turn led them to

    believe that the bus bar was iso-

    lated. Furthermore, they did not

    fully realise the consequences

    when smoke/soot is generated in

    live switchgear.

    Switchboard cubical after the the flash

    reSwitchboard cubical before flash

    re

    Effect of the flash re on bus bars

    Note:

    The Electrical Supervisor and Electrical Technician were given skin

    grafting surgery after 48Hours of being admitted to hospital following

    sterilisation. The Supervisor was discharged from hospital some 21 days

    later. The Technician was discharged after 23 days in hospital. Both re-quired a period of time to attend hospital on a weekly basis for further

    consultation treatment.

  • 8/17/2019 Learning plan from past incidents

    25/27

    48 49

    Inadequate design:  The control

    multi-pin socket in the switchgear

    was found to have a design weak-

    ness, which caused the unintend-

    ed reverse connection in the rst

    instance.

    Non adherence to safety warn-

    ing sign: The Electrical Supervi-

    sor and Electrical Technician both

    ignored warning signs and opened

    the protective barriers/panels,

    thereby exposing themselves di-

    rectly to the live bus bars.

    Lack of hazard awareness: Non

    adherence to Electrical and PTW

    procedures: These procedures

    were not strictly followed. The work

    activity was extended out-with the

    limit of the PTW without evaluating

    the associated risk and communi-

    cating this to the concerned Engi-

    neer.

    1. Review the design of the switchgear and replace with new, safer de-

    sign. ADGAS procurement procedures should ensure that adequately

    manufactured equipment is sourced, supplied and installed by ade-

    quately competent contractors.

    2. Fix new warning signs to all removable plates with clear message in

     Arabic and English. Work procedures should also clearly warn of the

    hazards of removing such panels.

    3. Competency of all Electrical Technicians/Supervisors to be re-evalu-

    ated. Those supervising work must have the same or higher kV authori-

    sation.

    4. Review and revise electrical procedures to ensure that they are ap-

    propriate.

    5. Ensure that toolbox talks are job specic and effectively communi-

    cated to all concerned at the start of each shift.

    Contributory Causes

    Lessons Learned

     As you have seen, from the various examples provided in this booklet,

    our work activities have resulted in a number of incidents occurring over

    the years we have been in operation, all with similar root and contribu-

    tory causes.

    We now need to ask ourselves, why? Why is it that an incident that oc-

    curred last year had similar root and contributory causes to an incident

    that occurred 12 years ago for example? Firstly, let’s identify the top six

    failings or root causes from the incidents we have highlighted in this

    booklet and discuss each one a little more detail. They are:

    • Inadequate training

    • Inadequate work practices• Non adherence to ADGAS Procedures

    • Lack of hazard awareness/Risk Underestimated

    • Inadequate work planning including Toolbox Talks

    • Inadequate supervision.

    4. Learning from our past mistakes

    Despite great effort being placed

    upon the identication and deliv-

    ery of various training programs,

    inadequate training is often iden-

    tied as either a root or contribu-

    tory cause in any incident. How-

    ever, many training events fail at

    the rst stage by failing to identify

    appropriate learning objectives.

    Whether the training is conducted

    by traditional classroom methods,e- learning or on-the-job-training,

    learning objectives must be spe-

    cic and measurable as they pro-

    vide the means on which to base

    the course assessment, which in

    turn, helps to determine the ef-

    fectiveness of the training and as-

    sure that the desired learning out-

    come’s, are consistently achieved.

     A properly trained and competent

    workforce is the rst step in assur-

    ing safe operations in any eld but

    the word ‘competent’ is often mis-

    understood. Competence is the

    ability to undertake responsibilities

    and to perform activities to a rec-

    ognised standard on a regular ba-

    sis. Competence is a combination

    of practical and thinking skills, ex-

    perience and knowledge, and alsoincludes a willingness to undertake

    work activities in accordance with

    standards, rules and procedures.

  • 8/17/2019 Learning plan from past incidents

    26/27

    50 51

    Inadequate work practices can

    be attributed to a lack of ad-

    equate training or quite often

    due to personnel circumventing

    the proper processes or proce-

    dures, or indeed, complacency.

    We have already addressed the

    subject of Training above, so

    how do we overcome the prob-

    lem of people taking short-cuts

    and removing complacency

    from the workplace? Education

    and continual learning is the

    answer, coupled with changing

    people’s hearts and minds to

    embrace a safety behavioural

    attitude.

    Our systems and processes are

    comprehensive and have been

    developed and implemented for

    your protection and to guide you

    in the correct work practices.

    Remember also that a PTW

    does not guarantee the job is

    safe – it is the attitude of the

    individuals concerned that pro-

    vide this. As you have seen from reading

    this booklet, falling from height

    have resulted in many of our

    friends and colleagues suffer-

    ing major injuries and in some

    cases, fatalities have resulted,

    which can be easily attributed to

    inadequate work practices and

    complacency, thinking that it

    won’t happen to me but sooner

    or later luck runs out.

    If people are properly trained

    and deemed competent for the

    work that they are employed to

    do then the non adherence to

     ADGAS Procedures is a clear

    and blatant disregard to safe

    working practices. ADGAS has

    dedicated a great deal of ef-

    fort over the years in develop-

    ing safe systems of work, which

    meet international standards,

    are continuously reviewed and

    updated to reect our continu-

    ous learning’s from industry.

     ADGAS have also been at the

    forefront in implementing safety

    initiatives to further improve the

    working environment for staff

    and contractors alike. In return,

     ADGAS expects each and eve-

    ry individual to adhere to its poli-

    cies and procedures, and adopt

    a safety behavioural approach

    to the work they do.

    Inadequate work planning isalso an area that appears all

    too often in our incident reports,

    particularly when plant upsets

    necessitate prompt actions to

    rectify faults and this is often

    used as an excuse when things

    go wrong. Our systems and

    processes are designed to ca-

    ter for the unexpected and if you

    follow the associated rules and

    guidelines you will complete the

     job safely.

    Pre-job safety meetings or Tool-

    box Talks, as they are com-

    monly referred to are part of

    the planning process and full a

    crucial function in ensuring any

    task is conducted safely. They

    are mandatory requirement for

    any work on Das and must be

    attended by all persons involved

    in the task, and must cover the

    specic task at hand. It is equal-

    ly important that the supervisor

    / foreman who delivers the tool

    box talks is adequately trained

    to effectively communicate haz-

    ard knowledge and the associ-

    ated risk.

     A Lack of hazard awareness/

    Risk Underestimated is quite

    common ndings during in-

    cident investigations even

    amongst experienced person-

    nel. The ability to be aware of

    potential hazards and effec-tively assess the risks is directly

    related to proper training and

    competency.

    Competence is a combination

    of practical and thinking skills,

    experience and knowledge, and

    also includes a willingness to

    undertake work activities in ac-

    cordance with standards, rules

    and procedures.

    Lastly and most importantly

    whether you are a Manager,

    Supervisor, Foreman or indeed

    the senior person in charge

    of a work party, you have cer-

    tain responsibilities in provid-

    ing leadership and supervision

    functions that require good

    communication skills to guide

    and advice, thus ensuring that

    the work is completed to the

    required standards. Failure to

    achieve this will result in inad-

    equate supervision, which al-

    ways leads to dangerous situa-

    tions arising at the worksite.

    Working safely must be para-

    mount to everything we do

  • 8/17/2019 Learning plan from past incidents

    27/27

    Not just a business priority, but rather a high human value

    Safety at the workplace is a mandatory business priority for everyorganization, as it ensures the integrity of assets and optimized

    hassle-free performance.

    For ADGAS, safety is one of the highest human values. It involves the

    very life of our most valued asset: our people.

    This booklet investigates 17 past incidents to pinpoint their root caus-

    es and provide our staff with insights to how they should assimilate

    these lessons and enhance their immunity against similar mishaps.

    S a f e t y