Layout Strtgy 3 1
Embed Size (px)
344 x 292
429 x 357
514 x 422
599 x 487
DESCRIPTION
Facilities Planning
Citation preview
Layout StrategiesDetermine the cost of this layout
Try to improve the layout
Prepare a detailed plan
*
30 50 10 0
Assembly (1)
Painting (2)
*
*
+ $30 + $50 + $10
+ $40 + $100 + $50
= $570
+ $60 + $50 + $10
+ $40 + $100 + $50
= $480
*
Medium Production Quantities
Batch production – A batch of a given product is produced, and then
the facility is changed over to produce another product
Changeover takes time – setup time
Typical layout – process layout
Cellular manufacturing – A mixture of products is made without
significant changeover time between products
Typical layout – cellular layout
Work Cells
Reorganizes people and machines into groups to focus on single
products or product groups
Group technology identifies products that have similar
characteristics for particular cells
Volume must justify cells
*
Reduced direct labor
Increased use of equipment and machinery
Reduced investment in machinery and equipment
*
Improving Layouts Using Work Cells
Current layout - workers in small closed areas. Cannot increase
output without a third worker and third set of equipment.
Improved layout - cross-trained workers can assist each other. May
be able to add a third worker as additional output is needed.
Figure 10 (a)
Improving Layouts Using Work Cells
Current layout - straight lines make it hard to balance tasks
because work may not be divided evenly
Improved layout - in U shape, workers have better access. Four
cross-trained workers were reduced.
Figure 10 (b)
*
A high level of training, flexibility and empowerment of
employees
Being self-contained, with its own equipment and resources
Test (poka-yoke) at each station in the cell
*
Total work time available
*
Mirror production scheduled for 8 hours per day
From a work balance chart
total operation time
Mirror production scheduled for 8 hours per day
From a work balance chart
total operation time
= .8 mins = 48 seconds
Total operation time required
Can help identify bottleneck operations
Flexible, cross-trained employees can help address labor
bottlenecks
Machine bottlenecks may require other approaches
*
High Production
Quantity production – Equipment is dedicated to the manufacture of
one product
Standard machines tooled for high production (e.g., stamping
presses, molding machines)
Typical layout – process layout
Product requires multiple processing or assembly steps
Product layout is most common
© 2008 Prentice Hall, Inc.
Volume is adequate for high equipment utilization
Product demand is stable enough to justify high investment in
specialized equipment
Product is standardized or approaching a phase of life cycle that
justifies investment
Supplies of raw materials and components are adequate and of
uniform quality
Organized around products or families of similar high-volume,
low-variety products
*
Machine-paced
Assembly line
Paced by work tasks
Balanced by moving tasks
*
Low material handling costs
Work stoppage at any point ties up the whole operation
Lack of flexibility in product or production rates
Disadvantages
© 2008 Prentice Hall, Inc.
Product variety
Soft product variety = differences between models of products
Product and part complexity
© 2008 Prentice Hall, Inc.
Total number of product units Qf = PQ
Total number of parts produced npf = PQnp
Total number of operations nof = PQnpno
© 2008 Prentice Hall, Inc.
Manufacturing capability - the technical and physical limitations
of a manufacturing firm and each of its plants
Three dimensions of manufacturing capability:
Technological processing capability - the available set of
manufacturing processes
Physical size and weight of product
Production capacity (plant capacity) - production quantity that can
be made in a given time
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
Computer programs are available to solve bigger problems
Computer Packages are in two domain
Construction Programs
Inputs
CRAFT Algorithm
Start with an initial layout with all departments made up of
individual square grids (Note: each grid represents the same amount
of space)
Estimate the best two-way department exchange assuming department
centroids exchange exactly
Departments i and j exchange
New centroid i = centroid j
New centroid j = centroid i
Only consider exchanging adjacent departments
Execute the exchange if the estimated cost of the best exchange in
(2) is lower than the best cost found so far
The actual result of the exchange is problem-dependent
If the estimated cost of the best exchange in (2) is higher than
the best cost found so far, stop
Else, go to 1
© 2008 Prentice Hall, Inc.
1 A A A A B B
2 A A A A B B
3 D D D D D D
4 C C D D D D
5 F F F F F D
6 E E E E E D
PATTERN
1 D D D D B B
2 D D D D B B
3 D D D E E E
4 C C D E E F
5 A A A A A F
6 A A A F F F
PATTERN
1 A A A A B B
2 A A A A B B
3 D D D D D D
4 C C D D D D
5 F F F F F D
6 E E E E E D
PATTERN
1 D D D D B B
2 D D D D B B
3 D D D E E E
4 C C D E E F
5 A A A A A F
6 A A A F F F
PATTERN
handling,
efficiency,
Flexible Manufacturing System
A Flexible manufacturing system is a system that is able to respond
to changed conditions.
Where to Apply FMS Technology
The plant presently either:
Produces parts in batches or
Uses manned GT cells and management wants to automate the
cells
It must be possible to group a portion of the parts made in the
plant into part families
The part similarities allow them to be processed on the FMS
workstations
Parts and products are in the mid-volume, mid-variety production
range
© 2008 Prentice Hall, Inc.
Flexible Manufacturing System - Defined
A highly automated GT machine cell, consisting of a group of
processing stations (usually CNC machine tools), interconnected by
an automated material handling and storage system, and controlled
by an integrated computer system
The FMS relies on the principles of GT
No manufacturing system can produce an unlimited range of
products
An FMS is capable of producing a single part family or a limited
range of part families
© 2008 Prentice Hall, Inc.
Flexibility Tests in an Automated Manufacturing System
To qualify as being flexible, a manufacturing system should satisfy
the following criteria (“yes” answer for each question):
Can it process different part styles in a nonbatch mode?
Can it accept changes in production schedule?
Can it respond gracefully to equipment malfunctions and
breakdowns?
Can it accommodate introduction of new part designs?
© 2008 Prentice Hall, Inc.
9 – *
Automated manufacturing cell with two machine tools and robot. Is
it a flexible cell?
Automated Manufacturing Cell
Part variety test
Can it machine different part configurations in a mix rather than
in batches?
Schedule change test
© 2008 Prentice Hall, Inc.
Error recovery test
Can it operate if one machine breaks down?
Example: while repairs are being made on the broken machine, can
its work be temporarily reassigned to the other machine?
New part test
As new part designs are developed, can NC part programs be written
offline and then downloaded to the system for execution?
© 2008 Prentice Hall, Inc.
Number of machines (workstations):
Flexible manufacturing cell (n = 2 or 3)
Flexible manufacturing system (n = 4 or more)
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
Designed to produce a limited variety of part styles
The complete universe of parts to be made on the system is known in
advance
Part family likely based on product commonality rather than
geometric similarity
Random-order FMS
New part designs will be introduced
Production schedule is subject to daily changes
© 2008 Prentice Hall, Inc.
Computer control system
Manual or automated
Includes communication interface with worker to specify parts to
load, fixtures needed, etc.
CNC machine tools in a machining type system
CNC machining centers
Milling machine modules
Capability to handle a variety of part styles
Standard pallet fixture base
Temporary storage
Compatibility with computer control
© 2008 Prentice Hall, Inc.
Secondary handling system - functions:
Transfers work from primary handling system to workstations
Position and locate part with sufficient accuracy and repeatability
for the operation
Reorient part to present correct surface for processing
Buffer storage to maximize machine utilization
© 2008 Prentice Hall, Inc.
Five Types of FMS Layouts
The layout of the FMS is established by the material handling
system
Five basic types of FMS layouts
Inline
FMS In-Line Layout
Straight line flow, well-defined processing sequence similar for
all work units
Work flow is from left to right through the same workstations
No secondary handling system
© 2008 Prentice Hall, Inc.
FMS In-Line Layout
Linear transfer system with secondary parts handling system at each
workstation to facilitate flow in two directions
© 2008 Prentice Hall, Inc.
FMS Loop Layout
One direction flow, but variations in processing sequence possible
for different part types
Secondary handling system at each workstation
© 2008 Prentice Hall, Inc.
FMS Rectangular Layout
Rectangular layout allows recirculation of pallets back to the
first station in the sequence after unloading at the final
station
© 2008 Prentice Hall, Inc.
Loop with rungs to allow greater variation in processing
sequence
© 2008 Prentice Hall, Inc.
© 2008 Prentice Hall, Inc.
Suited to the handling of rotational parts and turning
operations
© 2008 Prentice Hall, Inc.
Central intelligence required to coordinate processing at
individual stations
Production control
© 2008 Prentice Hall, Inc.
Traffic control
Management of the primary handling system to move parts between
workstations
Shuttle control
Workpiece monitoring
© 2008 Prentice Hall, Inc.
Tool life monitoring
Monitoring usage of each cutting tool and determining when to
replace worn tools
Performance monitoring and reporting
Diagnostics
© 2008 Prentice Hall, Inc.
Loading and unloading parts from the system
Changing and setting cutting tools
Maintenance and repair of equipment
NC part programming
Overall management of the system
© 2008 Prentice Hall, Inc.
Assembly
Inspection
Forging
© 2008 Prentice Hall, Inc.
Automatic tool changing
Queues of parts at stations to maximize utilization
Dynamic scheduling of production to account for changes in
demand
Fewer machines required
© 2008 Prentice Hall, Inc.
Lower manufacturing lead times
© 2008 Prentice Hall, Inc.
Part family considerations
Based on part similarity
Based on product commonality
Physical characteristics of workparts
Size and weight determine size of processing equipment and material
handling equipment
© 2008 Prentice Hall, Inc.
Production volume
Types of workstations
Machine loading
Part routing
© 2008 Prentice Hall, Inc.
Which parts should be on the system at one time
Tool management
When to change tools
Pallet and fixture allocation
Limits on fixture types may limit part types that can be
processed
© 2008 Prentice Hall, Inc.
Just-In-Time Production
Production and delivery of exactly the required number of each
component to the downstream operation in the manufacturing sequence
just at the moment when the component is needed
Minimizes:
Work-in-process
Setup time reduction for smaller batch sizes
Stable and reliable production operations
© 2008 Prentice Hall, Inc.
Pull System of Production Control
A system in which the order to make and deliver parts at each
workstation in the production sequence comes from the downstream
station that uses those parts
JIT is based on a pull system of production control
Alternative is a push system in which parts are produced at each
station irrespective of the immediate need for those parts at the
downstream station
© 2008 Prentice Hall, Inc.
Setup Time Reduction
Starting point in setup time reduction is recognition that the work
elements in setup are of two types:
Internal elements – can only be done while the production machine
is stopped
External elements – do not require the machine to be stopped
© 2008 Prentice Hall, Inc.
Strategy:
Design the setup tooling and plan the changeover procedure to
permit as much of the setup as possible to consist of external
elements
Examples:
Assemble tools for next job
Reprogram machine for next job
© 2008 Prentice Hall, Inc.
Internal Work Elements
Use time & motion study and methods improvement to minimize the
sum of the internal work element times
Use two workers rather than one to accomplish the changeover
Eliminate adjustments in the setup
Use quick-acting fasteners rather than bolts and nuts
Use U-shaped washers instead of O-shaped washers
Design modular fixtures consisting of a base plus insert tooling
that can be quickly changed for each new part style
Base part remains attached to production machine
© 2008 Prentice Hall, Inc.
Production Operations
Production leveling - distribute changes in product mix and
quantity as evenly as possible over time
On-time delivery of components
Defect-free components and materials
Dependable supplier base
Quality at Source
© 2008 Prentice Hall, Inc.
Automotive
Assembly-Line Balancing
Objective is to minimize the imbalance between machines or
personnel while meeting required output
Starts with the precedence relationships
Determine cycle time
Wing Component Example
This means that tasks B and E cannot be done until task A has been
completed
Performance Task Must Follow
40 units required
Units required per day
2. Most following tasks
Choose the available task with the largest number of following
tasks
3. Ranked positional weight
Choose the available task for which the sum of following task times
is the longest
4. Shortest task time
5. Least number of following tasks
Choose the available task with the least number of following
tasks
I
G
F
C
D
H
B
E
A
10
11
12
5
4
3
7
11
3
40 units required
40 units required
40 units required
Efficiency =
= 91.7%
LOAD MORE