PROGRESS REPORTPROYEK PEMBANGUNAN MESS NON STAFF PASAR PANASNo SPK (Surat Perintah Kerja) & SPP (Surat Perjanjian Pemborongan)
Minggu - 5
Periode : 29 Maret - 4 April 2010
Packet of Work :Sipil, Struktur, Arsitektur dan PlumbingLocation : KONTRAKTOR PT. PAMAPERSADA NUSANTARAJl. Hauling Km. 35, PT. Pamapersada Nusantara District Adaro Site Manager Pelaksana Proyek Civil Construction OfficerContractor :PT. Banua Sejahtera Bersama
Sutrisno Surono Andri T. Kamil
NO JENIS PEKERJAANBOBOT
YANG LALU SAAT INI KUMULATIFPROGRESS BOBOT PROGRESS BOBOT PROGRESS BOBOT
( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % )I PEKERJAAN PERSIAPAN 3.46 52.61 1.82 2.94 0.10 55.56 1.92
II MESS NON STAFF1 PEKERJAAN TANAH 1.08 77.97 0.84 14.14 0.15 92.11 0.99 2 PEKERJAAN STRUKTUR BETON 28.86 29.59 8.54 11.84 3.42 41.42 11.96 3 PEKERJAAN DINDING 15.40 - - - - - - 4 PEKERJAAN LANTAI 5.90 - - - - - - 5 PEKERJAAN PLAFOND 4.23 - - - - - - 6 PEKERJAAN PENGECATAN 6.39 - - - - - - 7 PEKERJAAN RANGKA + PENUTUP ATAP 13.98 - - - - - - 8 PEKERJAAN PINTU, JENDELA & VENTILASI 6.86 - - - - - - 9 PEKERJAAN ALAT SANITAIR 4.67 - - - - - -
10 PEKERJAAN INSTALASI AIR KOTOR DAN BERSIH 1.40 - - - - - - 11 PEKERJAAN LAIN - LAIN 2.90 - - - - - - 12 PEKERJAAN EXTERIOR 4.85 - - - - - -
ACTUAL PROGRESS 100.00 11.20 3.67 14.87 PLAN PROGRESS 8.05 5.24 13.28
DEVIASI ( + / - ) 3.16 (1.57) 1.59
REKAPITULASI
PROYEK PEMBANGUNAN MESS NON STAFF PASAR PANAS
HAL : 1
PROGRESS REPORTPROYEK PEMBANGUNAN MESS NON STAFF PASAR PANASNo SPK (Surat Perintah Kerja) & SPP (Surat Perjanjian Pemborongan)
Minggu - 6
Periode : 5 - 11 April 2010
Packet of Work :Sipil, Struktur, Arsitektur dan PlumbingLocation : KONTRAKTOR PT. PAMAPERSADA NUSANTARAJl. Hauling Km. 35, PT. Pamapersada Nusantara District Adaro Site Manager Pelaksana Proyek Civil Construction OfficerContractor :PT. Banua Sejahtera Bersama
Sutrisno Surono Andri T. Kamil
NO JENIS PEKERJAANBOBOT
YANG LALU SAAT INI KUMULATIFPROGRESS BOBOT PROGRESS BOBOT PROGRESS BOBOT
( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % )I PEKERJAAN PERSIAPAN 3.46 55.56 1.92 6.20 0.21 61.76 2.14
II MESS NON STAFF1 PEKERJAAN TANAH 1.08 92.11 0.99 7.89 0.08 100.00 1.08 2 PEKERJAAN STRUKTUR BETON 28.86 41.42 11.96 3.05 0.88 44.47 12.84 3 PEKERJAAN DINDING 15.40 - - 11.09 1.71 11.09 1.71 4 PEKERJAAN LANTAI 5.90 - - 17.35 1.02 17.35 1.02 5 PEKERJAAN PLAFOND 4.23 - - - - - - 6 PEKERJAAN PENGECATAN 6.39 - - - - - - 7 PEKERJAAN RANGKA + PENUTUP ATAP 13.98 - - - - - - 8 PEKERJAAN PINTU, JENDELA & VENTILASI 6.86 - - - - - - 9 PEKERJAAN ALAT SANITAIR 4.67 - - - - - -
10 PEKERJAAN INSTALASI AIR KOTOR DAN BERSIH 1.40 - - 5.87 0.08 5.87 0.08 11 PEKERJAAN LAIN - LAIN 2.90 - - - - - - 12 PEKERJAAN EXTERIOR 4.85 - - - - - -
ACTUAL PROGRESS 100.00 14.87 3.99 18.86 PLAN PROGRESS 13.28 5.24 18.52
DEVIASI ( + / - ) 1.59 (1.24) 0.35
REKAPITULASI
PROYEK PEMBANGUNAN MESS NON STAFF PASAR PANAS
HAL : 1
PROGRESS REPORTPROYEK PEMBANGUNAN MESS NON STAFF PASAR PANASNo SPK (Surat Perintah Kerja) & SPP (Surat Perjanjian Pemborongan)
Minggu - 7
Periode : 12 - 18 April 2010
Packet of Work :Sipil, Struktur, Arsitektur dan PlumbingLocation : KONTRAKTOR PT. PAMAPERSADA NUSANTARAJl. Hauling Km. 35, PT. Pamapersada Nusantara District Adaro Site Manager Pelaksana Proyek Civil Construction OfficerContractor :PT. Banua Sejahtera Bersama
Sutrisno Surono Andri T. Kamil
NO JENIS PEKERJAANBOBOT
YANG LALU SAAT INI KUMULATIFPROGRESS BOBOT PROGRESS BOBOT PROGRESS BOBOT
( % ) ( % ) ( % ) ( % ) ( % ) ( % ) ( % )I PEKERJAAN PERSIAPAN 3.46 61.76 2.14 2.94 0.10 64.70 2.24
II MESS NON STAFF1 PEKERJAAN TANAH 1.08 100.00 1.08 - - 100.00 1.08 2 PEKERJAAN STRUKTUR BETON 28.86 44.47 12.84 5.37 1.55 49.84 14.38 3 PEKERJAAN DINDING 15.40 11.09 1.71 2.77 0.43 13.86 2.14 4 PEKERJAAN LANTAI 5.90 17.35 1.02 - - 17.35 1.02 5 PEKERJAAN PLAFOND 4.23 - - - - - - 6 PEKERJAAN PENGECATAN 6.39 - - - - - - 7 PEKERJAAN RANGKA + PENUTUP ATAP 13.98 - - - - - - 8 PEKERJAAN PINTU, JENDELA & VENTILASI 6.86 - - 2.89 0.20 2.89 0.20 9 PEKERJAAN ALAT SANITAIR 4.67 - - - - - -
10 PEKERJAAN INSTALASI AIR KOTOR DAN BERSIH 1.40 5.87 0.08 2.93 0.04 8.80 0.12 11 PEKERJAAN LAIN - LAIN 2.90 - - - - - - 12 PEKERJAAN EXTERIOR 4.85 - - - - - -
ACTUAL PROGRESS 100.00 18.86 2.32 21.18 PLAN PROGRESS 18.52 5.36 23.88
DEVIASI ( + / - ) 0.35 (3.05) (2.70)
REKAPITULASI
PROYEK PEMBANGUNAN MESS NON STAFF PASAR PANAS
HAL : 1