Land in Tanzania
Only 10% of Land in Tanzania is
surveyed and titled
It can take up to 7 years for an investor to gain title to land
70% village land
28% reserve land
2% general land
All information relating to land
tenure and ownership in
Tanzania is held in paper form
Consultation is ad hoc and awareness of rights and laws
is poor
‘Land insecurity is
killing people and
the economy in Tanzania’
•Development of Country Partnership Agreement
May 2013
•Presentation at G8
June 2013•Programme design mission
September 2013
•Draft report•Follow-up visit
November 2013 •Final report
•Funding approved
April 2014
• Implementation begins
May 2014
Land Tenure Support Programme in Tanzania
BRN
$15 million – 3 years
Publish data
Benefit sharing
Land acquisition
Institutions/ legislation
Stakeholder group
Dispute resolution
Tenure regularisationParticipatory
LUP
LIS
$500 million
– 15 years
But BRN says: ‘10,000,000 land
parcels registered and titled by end 2016!’