Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Land At Englishcombe Lane Bath
Public Exhibition EventJanuary 2018
LAND AT ENGLISHCOMBE LANE BATH AND NOSOMERSET C
Transport
POINTS RAISED AT PREVIOUS PUBLIC CONSULTATION:
1. Confi rmation that the traffi c count and surveys are current and consider the current use of Englishcombe Lane.
2. Has the 60 possible cars leaving and entering the site at peak times been considered.
3. The owners of the houses opposite the entrance raised the fact that by bringing the pavement out how this aff ects them access and leaving their drive way.
RESPONSE:
1. A full transport assessment has been carried out and will be submitted as part the planning application.
2. See point 1.
3. The new access will re-provide all existing vehicle access points.
PREVIOUS TRAFFIC PLAN
NEW TRAFFIC PLAN
REFUSE VEHICLE ENTERING SITE FROM EAST
REFUSE VEHICLE ENTERING SITE FROM WEST
REFUSE VEHICLE LEAVING SITE FROM EAST
REFUSE VEHICLE LEAVING SITE FROM WEST
REFUSE VEHICLE SPECIFICATION
Land At Englishcombe Lane Bath
Public Exhibition EventJanuary 2018Site Investigation and Drainage Strategy
POINTS RAISED AT PREVIOUS PUBLIC CONSULTATION:
1. Had there been proper assessments of the Mud slip areas and do the proposal have proper engineering design and back up?
2. Have the new drainage surveys been carried out in the wet season rather than the dry season as the original ones?
3. Has there been surveys of the existing system in Englishcombe Lane to confi rm it has capacity to take all the new drainage, in the wet season the road fl oods with water coming up out of the road gulley’s, the school has fl ooded in the past from the fl ooding of Englishcombe Lane.
4. How is all the new drainage on the site going to be maintained as, if the current land is in council ownership and they have been complaining for years and nothing has happened ?
5. Concerns over fl ooding of gardens?
6. The ground is too wet to walk on some winters, how will building on this will not create a problems, soakaways won’t work, can we see your test results?
7. Will my garden dry up?
8. Subsidence- what safeguards will be provided?
RESPONSE:
1. There have been extensive site investigations to include a combination of a total of 36 trail pits and boreholes. A geotechnical consultant has also been providing specialist advice.
2. We used a tractor towed bowser which carried 10,000 litres of water and repeated the test 3 times at each location. This is to mimic a prolonged period of rainfall and in line with current design guidance.
3. Surface water drainage will be managed within the site boundary and we will not be discharging any additional surface water into the sewers in Englishcombe Lane. With regards to the foul, we have liaised with Wessex Water who have confi rmed there adequate capacity in the foul drainage network.
4. There will be a service charge on each property which will go into a fund which will be administrated by a management company to include routine maintenance of the drainage system.
5. We have been developing an engineered solution so that there is no increase in risk of fl ooding to the downstream properties. This has included catchment and surface water fl ow modelling by a hydrologist. The surface water drainage strategy includes a southern cut off ditch to intercept surface water passing through the site and soakaways to discharge water into the underlying permeable soils. As an additional precautionary measure there will a cut off drain along the northern boundary, to prevent surface water existing the site.
6. Although the surface soils are clay, the underlaying soil is weathered inferior oolite, with high permeability and water collected within the soakaways will discharge into this material.
7. The drainage that is being proposed will intersect high intensity overland fl ows and avoid the increasing risk of fl ooding downstream.
8. The existing properties will not be aff ected by the proposed development.
Cut off ditches to intercept overland water entering site
Cut off drain
Soakaway draining into underlying highly permeable limestone
Connection point for foul drainage
Existing drain to Englishcombe Lane to be cleared
PREVIOUS LANDSCAPE AND ECOLOGY CONSIDERATIONS
PROPOSED SITE DRAINAGE APPROACH
SITE INVESTIGATION / TRAIL PITS AND BOREHOLES
MATERIAL FROM TRAIL PIT PERMEABLE WEATHERED INFERIOR OOLITE
METHOD USED FOR SOAKAWAY TESTING 10,000 LITRE BOWSER RAPIDLY DIS-CHARGED INTO TRAIL PITS AND REPEAT-ED THREE TIMES
Land At Englishcombe Lane Bath
Public Exhibition EventJanuary 2018Sustainability
SUSTAINABILITY OBJECTIVES
Comfortable & aff ordable.
Thermal comfort, by minimizing the risk of gaining heat in summer.
Providing good air quality, and avoid droughts.
Provide a good level of daylight.
Minimize the energy bills.
Potential for renewable energy generation from solar PV panels.
Achieve 35-45% improvement on a Building Regulation compliant dwelling.
HOW TO ACHIEVE THE OBJECTIVES
Reduce energy consumption.
Effi cient use of energy.
Energy recovery methods.
Renewable methods.
ENVIRONMENTAL DESIGN STRATEGIES
The opposite graph shows windows as the fi rst element for energy loss. Therefore, it is recommended to use glazing with a good U value, which will reduce overheating through fenestration.
Heat loss through walls, fl oor and roof will be improved by using high levels of insulation to the building fabric. Materials like wood fi bre, mineral wool and recycled newspaper are recommended.
Provide high level of air tightness to the fabric, to avoid draughts and heat losses.
To avoid heat loss through uncontrolled ventilation, a ventilation mechanical system with Heat Recovery (MVHR) will be recommended. This system provides fresh air without the draughts caused by typical systems. In the meantime, it controls humidity levels, pollution and pollen, however, provides fresh air with an improved temperature to avoid cold air. This is achieved by recovering heat from the warm moist air coming from bathrooms.
PV solar panels will be used to generate electricity and reduce the energy bills from grid.
Electric car charging points will be provided, to encourage the use of this type of cars.
FURTHER IMPROVEMENT TOWARDS OUR ENVIRONMENT
Reduce the amount of water consumption , by using effi cient sanitary fi ttings.
Potential to use innovative technologies such as heat recovery from showers.
Ecology conscious lighting by providing dark zones and reduce light spill.
INSULATION MATERIALS
SUSTAINABLE APPROACH
HEAT GAINS/ LOSSES ELEMENTS
PV SOLAR PANELS MECHANICAL VENTILATION
CAR CHARGING POINT
ENVELOPE RESPONSE TOWARDS ACTIVITIES AND SURROUNDING
OPENABLE WINDOW
Land At Englishcombe Lane Bath
Public Exhibition EventJanuary 2018Planning
POINTS RAISED AT PREVIOUS PUBLIC CONSULTATION:
As part of the Council’s plan-making, there have been several stages of formal public consultation:
Bath and North East Somerset Local Plan (formally adopted in 2007) including:
Public consultation on the Issues and Options and
Draft Plan
Examination in Public hearings
Placemaking Plan (formally adopted July 2017), including:
Launch Document Public Consultation (September 2013)
Options Public Consultation (November 2014 – January 2015)
Draft Plan Public Consultation (December 2015 – February 2016)
Examination in Public hearings (Summer 2016)
The project team also undertook a public consultation event in July 2017 to inform the evolution of the scheme design. Residents will also have the opportunity to provide their comments on the scheme once the full planning application is submitted.
Numerous surveys and assessments have been undertaken to understand the site and its suitability. These have informed the design scheme as it has emerged. Surveys which have been undertaken since 2006 include:
Geophysical & Ground Condition Investigations
Topographical Surveys
Habitat and Protected Species Surveys
Transport Statements
Arboricultural Surveys
Flood Risk and Drainage Assessments
A suite of surveys and technical reports will be submitted alongside the formal planning application. These will include:
Planning Statement (incorporating Aff ordable Housing Statement)
Design and Access Statement (incorporating Heritage Statement and Statement of Community Involvement)
Biodiversity Assessment (including habitat and species surveys)
Flood Risk Assessment & Drainage Strategy
Transport Statement
Tree Survey / Arboricultural Assessment
0
5
10
15
20
25
Impact to wildlifeand Ecology
Increased trafficand insufficient
parking
Flooding togardens, Flood Risk
and drainageconcerns
Conservation area /world heritage site
needs to be leftalone
Developmentjunction not
suitable -safetyconcerns
MAIN CONCERNS RAISED
Englishcombe Lane, Bath Lighting Impact Assessment – Baseline Survey Report
LAND AT ENGLISHCOMBE LANE
TRANSPORT STATEMENT
April 2017
Reptile Translocation Method Statement Englishcombe Lane J00128 Version 1.0 DRAFT
Author: Jasmine Walters BSc GradCIEEM
Reviewed: Ben Mitchell BSc (Hons) MCIEEM
Client No: 13789/56700
GREENHALGH LANDSCAPE ARCHITECTS
PRE-DEVELOPMENT TREE SURVEY AND CONSTRAINTS
LAND TO THE REAR ENGLISHCOMBE LANE, BATH.
Date: November 2017
Unit 60, Aston Down Gloucestershire GL6 8GA
Tel: 01285 760466 Fax: 01285 760983
Email: [email protected]
developing the environment of the future
PHASE 1 AND PHASE 2 SURVEYS OF LAND TO THE REAR OF
89-123 ENGLISHCOMBE LANE, BATH
CLIENT: BATH & NORTH EAST SOMERSET COUNCIL
SELECTION OF REPORTS
Land At Englishcombe Lane Bath
Public Exhibition EventJanuary 2018Revised Site Plan
PROPOSED SITE PLAN
Hig
h Co
mm
on 2
.74K
m
Cath
edra
l 2.2
2Km
Alexan
dra Pa
rk 1.6
6Km
Roya
l Cre
scen
t 2.
35Km
Prim
rose
Hill
3.2
6Km
HARD STA
NDING FOR
BINS
Hig
h Co
mm
on 2
.74K
m
HARDSTANDINGFOR BINS
Cath
edra
l 2.2
2Km
Alexan
dra Pa
rk 1.6
6Km
Roya
l Cre
scen
t 2.
35Km
Prim
rose
Hill
3.2
6Km
25m FO
RWAR
D VISIB
ILITY
25m
FORW
ARD
VISIBI
LITY
96.55
96.05
95.55
95.05
94.55
97.70
98.30
99.10
95.30
99.70
96.90
96.30
94.70
93.25
92.25
93.25
92.25
92.80
92.80
94.45
PLOT 37Type 4
91.00
PLOT 33Type 4
PLOT 36Type 4
PLOT 35Type 4
PLOT 34Type 4
PLOT 32Type 4
PLOT 05Type 3
PLOT 03Type 3
PLOT 04Type 3
PLOT 06Type 3
SUBST-ATION
PLOT 11Type 7
PLOT 22-31
PLOT 38Type 1
PLOT 09Type 7
PLOT 10Type 7
PLOT 08Type 7
PLOT 07Type 7
PLOT 12Type 6
PLOT 21Type 5
PLOT 13Type 6
PLOT 14Type 6
PLOT 15Type 6
PLOT 16Type 6
PLOT 17Type 6
PLOT 18Type 5
PLOT 19Type 5
PLOT 02Type 8
PLOT 01Type 2
94.95
94.95
95.80
95.80
93.70
93.70
94.10
94.10
94.55
94.25
94.25
93.8093.80
93.25
93.25
99.2599.67
99.70
99.95
99.55
99.00
98.60
93.40
92.80
PLOT 20Type 5
93.30
AERIAL VIEW LOOKING SOUTH