Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page iThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
LAND ACQUISITION MANAGEMENT SYSTEM
June 2009
Uganda Na tional Roads AuthorityPlot 11 Yusuf Lule RoadP.O Box 28487K AM P AL A - U G AN D A
Te l: +256 312 233100 414 318000Fax: +256 414 232807 414 347616
http://www.unra.go.ug
8/11/2019 Land Aqusition Management System Uganda
2/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page iiThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
Document Control
LAMS ItemRevision Date
20-3-09 14-4-09 21-4-09 13-6-09
Part A: Quality Management
1. Introduction
2. Quality Management
3. Management Responsibility
4. Measurement, Analysis, Improvement
Part B: Detailed Procedures
LP1. Preliminary Valuation
LP2. Survey and Valuation
LP3. Compensation and Expropriation
LP4. Quality Management
LP5. Resource Management
APPENDICES:
A. Policy and Legal Framework
B. Institutional Framework
C. Standard Forms / Templates
D. Donor Requirements
Authorisation:
Land Acquisition Specialist
Executive Director
Signed copy to be held by the Land Acquisition Specialist.
Summary of Most Recent Revision:
20-03-09: First Draft distributed for comment (Appendix B, C and D not yet prepared)
14-04-09: Draft distributed prior to field testing.
21-04-09: Final Draft issued for field testing
8/11/2019 Land Aqusition Management System Uganda
3/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page iiiThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
Contents
Document Control ......................................................................................................................... ii
Contents........................................................................................................................................iii
Abbreviations and Glossary ........................................................................................................vi
Abbreviations ................................ ................................ ................................ .............................. vi
Glossary of terms used in LAMS................................................................................................ vii
Part A: Quality Management for Land Acquisition ................................ ........................ 1
1 Introduction............................................................................................................................2
1.1 Background......................................................................................................................2
1.2 Purpose and Feedback....................................................................................................2
1.3 Structure of the LAMS......................................................................................................3
2 Quality Management ..............................................................................................................3
2.1 Quality Policy...................................................................................................................3
2.2 Objectives........................................................................................................................4
2.3 Scope of LAMS................................................................................................................4
2.4 Processes........................................................................................................................4
2.5 Control of LAMS Documents and Records.......................................................................6
3 Management Responsibility..................................................................................................6
3.1 Management Responsibility.............................................................................................6
3.2 Planning...........................................................................................................................7
3.3 Responsibility, Authority, Communication ........................................................................7
3.4 Management Review.......................................................................................................8
4 Measurement, Analysis, Improvement .................................................................................8
Part B: Detailed Procedures for Land Acquisition ................................ ...................... 10
Introduction to the Land acquisition Procedures (LPs) ...........................................................11
LP1. Initial Assessment.........................................................................................................13
LP1.1. Desk Study ....................................................................................................................14LP1.2. Notices and Consultations .............................................................................................15
LP1.3. Field Survey...................................................................................................................16
LP1.4. Mitigation Measures.......................................................................................................17
LP1.5. Compensation Strategy .................................................................................................18
LP1.6. Implementation Plan ......................................................................................................19
8/11/2019 Land Aqusition Management System Uganda
4/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page ivThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP1.7. Cost Estimates...............................................................................................................19
LP1.8. Initial Assessment Report ..............................................................................................19
LP2. Survey and Valuation....................................................................................................21
LP2.1. Review Initial Assessment .............................................................................................22
LP2.2. Survey and Display Strip Maps......................................................................................22LP2.3. Compensation Principles and Rates ..............................................................................22
LP2.4. Valuation Assessments..................................................................................................23
LP2.5. Snag list.........................................................................................................................24
LP2.6. Valuation Report ............................................................................................................24
LP3. Compensation and Expropriation of Land ..................................................................26
LP3.1. Review and Update Valuation Report ............................................................................27
LP3.2. Verify and Pay Compensation........................................................................................27
LP3.3. Grievances and Appeals................................................................................................28
LP3.4. Land Expropriation.........................................................................................................28
LP3.5. Accountability Report .....................................................................................................28
LP4. Quality Management .....................................................................................................30
LP4.1. Maintain LAMS ..............................................................................................................30
LP4.2. Audit Programme...........................................................................................................31
LP4.3. Management Reviews ...................................................................................................32
LP5. Resource Management.................................................................................................34
LP5.1. Training..........................................................................................................................34
LP5.2. Procurement of Consultants...........................................................................................35
LP5.3. Contract Management ...................................................................................................36
Part C: Appendices ................................ ................................ ................................ ........ 37
Appendix A. Policy and Legal Framework .............................................................................38
A.I) Policy Framework ................................ ................................ ................................ ..........38
A.II) Legal Framework ................................ ................................ ................................ ...........39
Appendix B. Institutional Framework .....................................................................................50
B.I) Ministry of Lands, Housing and Urban Development......................................................50
B.II) Uganda Land Commission.............................................................................................51
B.III) District Level Institutions ................................................................................................51
Appendix C. Standard Forms and Templates ........................................................................54
Appendix D. Donor Requirements ..........................................................................................55
8/11/2019 Land Aqusition Management System Uganda
5/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page vThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
D.I) World Bank (WB) ...........................................................................................................55
D.II) European Union (EU).....................................................................................................56
D.III) African Development Bank (AfDB).................................................................................56
D.IV) Japan Bank for International Cooperation (JBIC) and Japan International CooperationAgency (JICA)................................................................................................ ............................57
8/11/2019 Land Aqusition Management System Uganda
6/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page viThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
Abbreviations and Glossary
Abbreviations
CBO Community Based Organisation
CfLS Commissioner for Land and Surveys
CGV Chief Government Valuer
CoS Commissioner of Surveys
EU European Union
JBIC Japan Bank for International Cooperation
JICA Japan International Cooperation Agency
ISO International Standards Organisation
LAMS Land Acquisition Management System
LC1 Local Councillor Grade 1
LP Land acquisition Process / Procedure
NGO Non Government Organisation
MoWT Ministry of Works and Transport
PAPs Project Affected People
RAFU Roads Agency Formation Unit (now UNRA)
RAP
UK
Resettlement Action Plan
United Kingdom
TOR Terms of Reference
UNRA Uganda National Roads Authority
WB World Bank Group
8/11/2019 Land Aqusition Management System Uganda
7/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page viiThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
Glossary of terms used in LAMS
The table below provides a brief explanation of the meaning of some of the terms used in this Land
Acquisition Management System, which may be unfamiliar to the user or to clarify the
understanding of the term as meant in this LAMS.
The definitions used have been obtained from the Encarta English (UK) Dictionary online
(http://uk.encarta.msn.com/), from the relevant Act or other official document that primarily uses
that term.
Term Definition
Audit a systematic check or assessment, especially of the efficiency or effectiveness
of an organization or a process, typically carried out by an independent assesso
Client(1) a person or organization to whom goods or services are provided and sold : a
user of the services offered by an agency
Customary
Tenure
Characterised by local customary regulation and management allowing
individual and household ownership, use and occupation of land, and any
transactions in that land. It also provides for communal ownership and use of
land, including subdivision into parcels belonging to individuals, families or
traditional institutions. The land is owned in perpetuity
Displaced For the purposes of this document, a displaced person is one whose residual
land, after land acquisition, is too small for them to live on and they have tomove in entirety to a different location.
Expropriate to take property or money from somebody, either legally for the public good or
illegally by theft or fraud
Freehold legal ownership of a property giving the owner unconditional rights, including the
right to grant leases and take out mortgages;
Land Act interpretation the holding of registered land in perpetuity subject to
statutory and common law qualifications
Injurious
Affection
Depreciating effect on/damage to, land and property as a consequence of
project works.ISO 9001:2000 Part of a family of international quality management standards maintained by
ISO, the International Organisation for Standardisation. Certification to an ISO
9001 standard does not guarantee any quality of end products and services;
rather, it certifies that formalized business processes are being applied
Leasehold the holding of a property through a lease;
8/11/2019 Land Aqusition Management System Uganda
8/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page viiiThis is not a controlled document.
The controlled document is held electronically (see section 2.5)
Land Act interpretation the holding of land for a given period from a specified
date of commencement, on such terms and conditions as may be agreed upon
by the lessor and lessee and includes a sublease.
Mailo Land Act interpretation the holding of registered land in perpetuity and having
roots in the allotment of land pursuant to the 1900 Uganda Agreement and
subject to statutory qualifications
Residual (land) The residual of the asset is the portion remaining in the claimants possession
after land acquisition.
Marginal (land) Very small in scale or importance; for example:
(i) when the residual of the asset being taken is not economically viable
Severance Severance occurs when part of the claimants land is taken. It is not necessary
that the claimants retained land be divided, although this would possibly serve
to increase the damage sustained.
Damage due to severance arises when the land acquired contributes to the
value of the retained land and the loss of the land acquired reduces the value of
the land retained.
Snag a minor problem or obstacle to progress
Vulnerable includes people who, by virtue of gender, ethnicity, age, physical or mental
disability, economic disadvantage or social status may be more diversely
affected by displacement than others and who may be limited in their ability to
claim or take advantage of resettlement assistance and related development
benefits. This includes those communities or other displaced persons who may
not be protected through national land compensation or land titling.
Notes:(1) In this LAMS, Client may refer to roadside communities affected by land acquisition and / orexternal implementation partners such as Donors, the Chief Government Valuers office, theCommissioner of Surveys office, the Commissioner of Land Registrations office, District and localgovernment offices, etc. In some contexts it may also include UNRAs suppliers.
8/11/2019 Land Aqusition Management System Uganda
9/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 1This is not a controlled document.
The controlled document is held electronically (see section 2.5)
PART A: QUALITY MANAGEMENTFOR LAND ACQUISITION
8/11/2019 Land Aqusition Management System Uganda
10/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 2This is not a controlled document.
The controlled document is held electronically (see section 2.5)
1 Introduction
1.1 Background
The Uganda National Roads Authority (UNRA) is responsible for managing, maintaining and
developing the national road network across Uganda. UNRA became a legal entity in 2006, but
officially began operations on 1st July 2008.
UNRAs Mission is to develop and maintain a national road network that is responsive to the
economic development needs of Uganda, to the safety of all road users, and to the environmental
sustainability of the national roads corridors.
To achieve this Mission, UNRA intends to focus on optimising the quality, timeliness and cost
effectiveness of its road projects. This includes its management of land acquisition along the road
corridors.
Historically, the Government of Uganda relied on restricting the use of the road reserve through
provisions in the Roads Act. However, over time the boundaries of the road reserve became
indistinguishable from the adjacent land and, due to population increases, especially in urban
areas, encroachment has occurred. UNRA has therefore decided that it shall legally acquire the
land within the road reserves, starting with current and pipeline projects and expanding to cover
the entire national road network over time. This is a massive undertaking, totalling approximately
10,800 km of road.
The recent experience on UNRA (formerly RAFU) projects is that the Land Acquisition preparation
and implementation has been ineffectual and the cause many problems on road development
projects. This is primarily because UNRA and its suppliers have limited experience in managing
and implementing land acquisition. The private sector is further constrained by limited humanresources capacity there are simply not enough trained and experienced personnel to implement
such a nationwide land acquisition programme.
This Land Acquisition Management System (LAMS) has been prepared to provide a
comprehensive guide to the management of land acquisition of the road reserve for UNRA and its
suppliers, to clarify the roles and responsibilities of all parties, and to give step by step guidance to
the implementation process.
It is based on the requirements of ISO 9001:2000, with a view to improving management,
monitoring and continual improvement of land acquisition processes by UNRA and its suppliers.
1.2 Purpose and Feedback
The purpose of this LAMS is to support the achievement of UNRAs Mission Statement to
improve the quality, timeliness and cost effectiveness of land acquisition on its road development
projects.
8/11/2019 Land Aqusition Management System Uganda
11/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 3This is not a controlled document.
The controlled document is held electronically (see section 2.5)
The LAMS is intended to be:
Simple, clear and easy to understand and implement,
A live system that is to be regularly reviewed and revised as necessary,
A practical tool that helps UNRA staff in their work rather than being an administrativeburden.
Feedback on the LAMS and its implementation is not only encouraged but considered necessary.
All feedback, comments and suggestions for improvement should be sent to the Land Acquisition
Specialist at UNRA.
1.3 Structure of the LAMS
The LAMS is divided into three parts.
Part A is the Quality Manual, which describes the overall management system, how it is managed
and maintained, policy statements and strategic objectives.Part B contains the detailed procedures a step by step guide to each aspect of land acquisition
and the management controls to be applied, and which define responsibilities, standard forms to
be used, records to be maintained, etc.
Part C contains the appendices, which provide further information to support parts A and B,
including a list of the standard forms and templates.
2 Quality Management
2.1 Quality Policy
The acquisition of land and any other associated activities are to be carried out in accordance with
UNRAs, Vision, Mission and Values; with the laws of Uganda and, where practicable, with
international best practice.
UNRAs Vision is to operate a safe, efficient and well developed national roads network.
UNRAs Mission is to develop and maintain a national road network that is responsive to the
economic development needs of Uganda, to the safety of all road users, and to the environmental
sustainability of the national roads corridors.
UNRAs Core Values are:
Customer Focus: We exist because of our customers and they come first,
Corporate Identify: The public image of our organisation is a mirror of our professionalethics, moral conduct and commitment to deliver better services,
Accountability: We are accountable for our actions,
8/11/2019 Land Aqusition Management System Uganda
12/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 4This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Transparency: We shall maintain an open door policy and consult with our customers asfrequently as possible to ensure that we serve them better,
Excellence: We intend to achieve our goals through hard work, innovation, creativity,prudence and exemplary leadership
Integrity: We are dedicated to serving with honesty, high professional standards and good
ethical conduct.This Land Acquisition Management System has been developed following the principles and
requirements of ISO 9001 to assist UNRA staff and suppliers to comply with this policy statement.
2.2 Objectives
The quality objectives relating to land acquisition are defined in the relevant procedures in Part B.
The objectives are intended to measure UNRAs success in terms of delivering a quality product in
an efficient and effective manner.
The Land Acquisition Specialist shall monitor achievement against these objectives and submitannual monitoring reports to the Director of Planning as part of UNRAs internal planning process.
2.3 Scope of LAMS
This LAMS applies to all aspects of the land acquisition process managed by UNRA for all road
development projects on the national road network. Any supplier (consultant) providing services to
UNRA relating to land acquisition shall carry out these services in accordance with this LAMS.
It does not apply to injurious affection claims outside of the road reserve and resulting from the
activities of Works Contractors implementing UNRA projects.
It does not (and can not) apply to the aspects of land acquisition managed by external
implementation partners such as the Chief Government Valuers office, the Commissioner of
Surveys office, District and local government offices, etc.
2.4 Processes
Land acquisition comprises three different stages, which are represented by three technical
processes in this LAMS. These are:
Initial Assessment which includes a review of the legal and institutional framework,community consultations and field surveys, development of mitigation measures,compensation strategy, implementation plan, and cost estimates (LP1)
Survey and Valuation which includes defining compensation principles and rates,identifying affected persons, preparing detailed strip maps and valuation assessments(LP2)
8/11/2019 Land Aqusition Management System Uganda
13/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 5This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Compensation and Expropriation which includes obtaining necessary approvals, verifyingand paying compensation to affected persons, expropriating land for UNRA (transferringtitles and revising deed plans) (LP3)
In addition, this LAMS includes two supporting processes which help UNRA to manage the above
technical processes. These are:
Quality Management which includes maintaining this LAMS, quality auditing of allprocesses in the land acquisition management cycle, and management reviews to promotecontinual improvement (LP4)
Resource Management which includes training, procurement of consulting services andcontract management relating to land acquisition (LP5)
The diagram below shows schematically the sequence and interaction of the processes. Each
process is given a unique reference number with the identifier LP for Land acquisition Process.
The detailed procedures are organised using the same referencing system and colour coding.
The Products relating to the land acquisition process, from an ISO 9001 perspective, include:
LP1. Initial Assessment Report
LP2. Valuation Report
LP3. Titles and Deed Plans, Accountability Report
The relevant procedures include the controls needed to ensure the quality of these products, and
include information on:
8/11/2019 Land Aqusition Management System Uganda
14/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 6This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Planning resource allocation, standards and authorisations
Control of Production responsibilities, internal reporting and monitoring, quality reviewand authorisations
Client Care determination and review of client needs, client communication and feedback
Records documentation and records to be maintained
Suppliers procurement and verification of services and goods from external suppliers
2.5 Control of LAMS Documents and Records
The control of documents and records forming part of this LAMS are described in the procedures
under LP5 Quality Management in Part B.
Records are documentary evidence of actions taken and are required to provide evidence of
conformity with the requirements of this LAMS. Records shall remain legible, readily identifiable
and retrievable.
The controlled version of this LAMS is available on the UNRA server under the restricted folder
managed by the Directorate of Planning. The Land Acquisition Specialist will maintain a printed
controlled version, which will be clearly marked as such and shall include the authorising
signatures for the issue of this and any future revisions. No other printed documents are
controlled.
3 Management Responsibility
3.1 Management ResponsibilityUNRA are committed to the implementation of the Policy Statement, and the achievement of their
Vision and Mission in accordance with their Core Values.
Land Acquisition comes under the responsibility of the Directorate of Planning, which is committed
to the implementation of this LAMS, achievement of the associated quality objectives, and in
continually improving the management and implementation of the land acquisition process.
The Land Acquisition Specialist shall receive the assistance and support necessary to:
Implement a LAMS familiarisation programme to ensure that all UNRA staff and suppliers
are aware of their responsibilities under the LAMS and in improving its effectiveness tomeet client needs,
Conduct management reviews of the LAMS, incorporating feedback from staff, suppliersand clients, and focusing on meeting client requirements and enhancing client satisfaction,
Ensure the availability of resources to manage, implement, review and update the LAMS.
8/11/2019 Land Aqusition Management System Uganda
15/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 7This is not a controlled document.
The controlled document is held electronically (see section 2.5)
3.2 Planning
Management Reviews, including staff and client feedback, shall form the basis for deciding the
need for future updates and revisions to this LAMS, and for associated familiarisation programmes.
A LAMS Continual Improvement Plan shall be prepared and updated to reflect the outcomes of
Management Reviews, as described in Part B, LP5 Quality Management.
3.3 Responsibility, Authority, Communication
The diagram below shows the organisation of UNRA with respect to the management of land
acquisition issues on its projects. UNRAs Land Acquisition Specialist, supported by a Land
Acquisition Officer, has primary responsibility for the implementation, review and improvement of
this LAMS.
The Land Acquisition Specialist reports directly to the Director of Planning, who in turn reports to
the Executive Director. Land Acquisition activities should be completed before Works Contractors
begin on site; hence it is considered part of the planning process. In reality, many land acquisition
issues, in particular the management of appeals and injurious claims, continue after the project has
started, and so the Land Acquisition Specialist also works closely with the Director of Projects and
the Project Managers to resolve these issues.
The Land Acquisition Specialist has the authority to liaise with external parties on matters relating
to the LAMS. Representatives from the Directorates of Planning and Projects shall participate in
8/11/2019 Land Aqusition Management System Uganda
16/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 8This is not a controlled document.
The controlled document is held electronically (see section 2.5)
the Management Reviews, to seek consensus, approval and authorisation for the LAMS and its
revision.
The Directors of Planning and Projects shall ensure their managers and suppliers are familiar with
the content of the LAMS as necessary.
3.4 Management Review
The Land Acquisition shall ensure that a Management Review is held at least once a year to
ensure its continuing suitability, adequacy and effectiveness, and to assess opportunities for
improvement and the need for revisions.
A record of the findings of the Management Review shall be maintained by the Land Acquisition
Specialist.
Inputs to the management review shall include:
Results of audits,
Client and staff feedback,
Status of preventive and corrective actions,
Follow up actions from previous management reviews,
Changes that could affect the LAMS,
Recommendations for improvement.
Review output shall include any decisions and actions related to:
Improvement of the effectiveness of LAMS and its processes,
Improvement of product (Initial Assessment Report, Valuation Report, AccountabilityReport) related to client requirements,
Resource needs.
The review outputs shall be fed into the LAMS Continual Improvement Plan
4 Measurement, Analysis, Improvement
The procedures in Part B includes for the monitoring, measurement, analysis and improvement
processes needed to:
Demonstrate conformity of the product to client and LAMS requirements
Ensure conformity of the LAMS to ISO 9001
Continually improve the effectiveness of the LAMS
8/11/2019 Land Aqusition Management System Uganda
17/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 9This is not a controlled document.
The controlled document is held electronically (see section 2.5)
These include an annual programme of internal audits covering all aspects of the LAMS. The
purpose of these audits is to:
Demonstrate that the LAMS is being effectively implemented and maintained,
Demonstrate the ability of the LAMS procedures to achieve planned results,
Provide feedback for the Management Review.
A number of staff shall be trained and appointed as auditors and shall be responsible for delivering
the audit programme.
The management responsible for the area being audited shall ensure that actions are taken
without undue delay to eliminate detected non conformities and their causes. Follow up activities
shall include the verification of the actions taken and the reporting of verification results.
A record of all detected non conformances shall be maintained by the Land Acquisition Specialist.
8/11/2019 Land Aqusition Management System Uganda
18/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 10This is not a controlled document.
The controlled document is held electronically (see section 2.5)
PART B: DETAILED PROCEDURESFOR LAND ACQUISITION
8/11/2019 Land Aqusition Management System Uganda
19/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 11This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Introduction to the Land acquisition Procedures (LPs)
The flow chart overleaf shows the main tasks or steps to be taken for each process, and how they
link together. These are expanded upon in the Land acquisition Procedures (LPs) defined in the
following sections. The following sections use headings coloured to match those used in the
diagram for easy identification.
The procedures are written to comply with Government of Uganda requirements. For donor
funded projects, some modifications may be required. See Appendix D Donor Requirements for
further information.
Each of the Land acquisition Procedures is summarised by the ISO Plan-Do-Check-Act model,
which defines the objectives, inputs, process, output, controls and measures relevant to that
procedure. These summaries provide the basis for routine monitoring, formal quality audits, and
management reviews as part of the continual improvement process.
PLAN
Objective:
Define delivery objectives that are clear and achievement can be measured
Input:
Define the items required for implementing the services and delivering the outputs
DOProcess:
The tasks / steps to be completed when implementing the services and delivering the outputs
CHECK
Output:
Define the output of the process, e.g. reports and deliverables
Controls:
Define the controls established to ensure the process (implementation) is done correctly and meets
defined standardsMeasures:
Define measures or performance indicators that are used to measure achievement of the objectives
ACT CONTINUAL IMPROVEMENT
In the main text for each task or step in the process, boxes are used to highlight where approvals
are to be sought and formal records are to be maintained.
8/11/2019 Land Aqusition Management System Uganda
20/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 12This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Flow Chart showing major steps in land acquisition technical and support process
Outline SchemeApproval
Draft AlignmentDesign
LP1.8Initial Assessment
Report
LP1.Initial
Assessment
LP1.1Desk Study
LP1.2Notices &
Consultations
LP1.3Field Survey
LP1.4MitigationMeasures
LP1.7Cost Estimates
LP1.6Implementation
Plan
LP1.5Compensation
Strategy
LP2.3Compensation
Principles & Rates
LP2.Survey &Valuation
LP2.1Review InitialAssessment
LP2.2Survey & Display
StripMapsLP2.4
ValuationAssessments
LP2.5Snaglist
LP2.7Valuation Report
LP5.Resource
Management
LP5.1Training
LP5.2Procurement of
Consultants
LP5.3Contract
Management
LP3.Compensation&Expropriation of
Land
LP3.1Review & UpdateValuation Report
LP3.2Verify & Pay
Compensation
LP3.4Land
Expropriation
LP3.4Accountability Report
LP4.Quality
Management
LP4.1Maintain LAMS
LP4.3Management
Reviews
LP4.2Audit Programme
Detailed SchemeApproval
Project Planning Feasibility Study Final Alignment
Design Approved Funding Secured
Project Planning Tasks(Not part of land acquisition)
Land Acquisition Tasks
LP3.3Grievancesand
Appeals
8/11/2019 Land Aqusition Management System Uganda
21/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 13This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP1. Initial Assessment
Objective:
To provide an initial assessment of mitigation measures and cost estimates for land acquisitionInput:
Alignment Design, Base Maps (physical features), Deed Plans
Process:
LP1.8Initial Assessment
Report
LP1.Initial
Assessment
LP1.1Desk Study
LP1.2Notices &
Consultations
LP1.3Field Survey
LP1.4MitigationMeasures
LP1.7Cost Estimates
LP1.6Implementation
Plan
LP1.5Compensation
Strategy
Output:
Approved Initial Assessment Report
Controls:
Terms of Reference, Template for Initial Assessment Report
Measures:
% Reports submitted to UNRA on time
% Reports approved by UNRA on first submission
% Variation between initial cost estimate and valuation report total
The Initial Assessment should normally be carried out during feasibility study and preliminary
design stage, and should aim to provide an accurate estimate of the compensation to be paid, thenumbers of people affected and to identify and develop any necessary mitigation measures.
The Initial Assessment only be completed once a preliminary road alignment (and earthworks)
design has been prepared, and at least most of the alignment is known. Where alignment options
have been identified and a decision has yet to be made, the initial assessment should include
these options and clearly identify the impacts of each option separately.
Responsibility for completing the initial assessment lies with the Consultant contracted to
undertake the work, usually as part of the Feasibility Study and Preliminary Design contract. See
LP5 Resource Management for further information.
If, for some reason, the initial assessment takes place later, it may overlap or coincide with theValuation process. Where this is the case, the Initial Assessment should focus primarily on the
development of mitigation measures, and the consultant should liaise with those carrying out the
Valuation process to summarise the compensation strategy, cost estimates and implementation
plan in their Initial Assessment Report.
8/11/2019 Land Aqusition Management System Uganda
22/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 14This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP1.1. Desk Study
Policy and Legal Framework
A summary of the policy and legal framework is provided in Appendix A Policy and Legal
Framework. The desk study should include:
A review of the summary policy and legal framework and advise UNRA of any errors,
omissions or suggestions for improvement,
Identification of any recently issued policy documents or legislation that may affect the land
acquisition process,
Identification of any local legislation that may affect land acquisition of the project road.
Where it is found that Appendix A needs to be revised and / or updated, this shall be done in
accordance with the document control procedures defined in LP4 Quality Management.
Institutional Framework
A summary of the institutional framework is provided in Appendix B Institutional Framework. The
desk study should include:
A review of the summary institutional framework and advise UNRA of any errors, omissions
or suggestions for improvement,
Identification of any recent institutional changes that may affect the land acquisition
process,
A stakeholder analysis and identification of the organisations and individuals to be involved
in the land acquisition process at central, district and local levels,
Where it is found that Appendix B needs to be revised and / or updated, this shall be done in
accordance with the document control procedures defined in LP4 Quality Management.
The stakeholder analysis shall include identification of all persons and organisations (formal and
informal) that:
Will be directly affected by the road project and the land acquisition process (e.g.
roadside communities and their livelihood sources, utility providers, socio-economic
service providers, communal facilities providers)
Have a legal requirement to be involved in the land acquisition process (e.g. central
and local government bodies)
Could help ensure smooth implementation of the land acquisition process (e.g.
community leaders, local NGOs / CBOs)
8/11/2019 Land Aqusition Management System Uganda
23/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 15This is not a controlled document.
The controlled document is held electronically (see section 2.5)
The analysis should include preparation of a stakeholder matrix, which identifies different
organisations and social groups, the extent to which the project is likely to impact on them, and
their importance in ensuring the LA process runs smoothly.
A project specific Institutional Framework should be prepared which clearly defines the tasks and
responsibilities for the entire process, and should include an organisation chart or similar, including
the names of the individuals concerned. This should include an assessment of the willingness and
capacity of those organisations and individuals to fulfil their responsibilities and to identify where
capacity building / technical assistance may be required.
Participation Strategy
The participation strategy shall define how each stakeholder will be consulted and how they will be
involved in making decisions on issues that affect them.
The participation strategy shall include:
A District Information Pack, that explains the roles and responsibilities of district level
officers in the land acquisition process,
A Community Information Pack, that provides affected communities with all the information
they need to understand the land acquisition process, how it may affect them, their
entitlements, and what they need to do to make sure they get paid their compensation on
time.
Proposed Road Reserve
The consultants shall, in accordance with UNRAs strategy for land acquisition and in liaison with
the road design engineers, propose the boundaries for the road reserve, in accordance with the
policy framework. This shall include:
A review of the alignment design and assessment of the road reserve width to be applied
along the route, taking into account any requirements for additional land take, for example
due to high cut / fill slopes and major junctions,
Obtaining copies of Deed Plans and base maps (showing physical features), and
superimposing on the proposed alignment centreline and road reserve boundaries.
The proposed road reserve should include all land take needed for permanent works, including
drainage and river protection measures.
LP1.2. Notices and Consultations
Official notices, in accordance with the legal framework, should be issued to notify those living in
the affected areas of the intent to acquire land for the road and of the need to access land for
survey purposes. A copy of all notices should be held on file by UNRA along with information on
when and where they have been displayed.
8/11/2019 Land Aqusition Management System Uganda
24/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 16This is not a controlled document.
The controlled document is held electronically (see section 2.5)
The exact form of the notices will depend on whether the land is already within the existing road
reserve and whether the outline scheme has been submitted and approved by the Commissioner
for Physical Planning, and the intended project area declared and gazetted.
The consultant should identify the need for all future public notices associated with the land
acquisition process and agree with the district and UNRA the locations where these are to be
displayed.
The consultations should follow the participation strategy, and should include as a minimum:
District level meetings to obtain information on compensation rates, to complete the
stakeholder analysis, and to distribute the district information packs to ensure all parties
fully understand their responsibilities
Village level meetings to:
Raise awareness and distribute the community information packs to explain the land
acquisition process in detail
Discuss the compensation strategy
Allow affected communities to raise any concerns relating to land acquisition
Obtain information on livelihood strategies, market prices for land and property,
current mailo rents and incomes, etc.
Interaction between surveyors and land owners / occupiers to
Identify and estimate quantities of land and assets likely to be affected
Identify plots where difficulties are likely to arise, e.g. absentee or recently deceased
title holders, ongoing land disputes
Identify plots where people are likely to be displaced (i.e. dont have enough
residual land to rebuild their homes on it) and discuss with them whether they want
to be paid compensation or whether they want assistance in resettlement.
A record of all consultations shall be maintained. Ideally these will be signed by the parties
involved in the consultation as a fair and accurate record of the discussions held.
LP1.3. Field Survey
The field survey involves, as a minimum, a walkover survey and consultation with land owners /
occupiers, by a registered land surveyor and / or registered valuation surveyor to provide a socio-
economic baseline for monitoring and evaluation, and an initial assessment of:
8/11/2019 Land Aqusition Management System Uganda
25/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 17This is not a controlled document.
The controlled document is held electronically (see section 2.5)
land use and tenure systems, for estimating compensation costs
current market prices and district approved rates for estimating compensation costs
livelihoods sources and need for livelihoods protection / mitigation measures
community infrastructure and other items likely to be affected and for which
mitigation measures will need to be developed
the number of owners / occupiers affected and estimated quantities of their assets
for which compensation will need to be paid
the number of families and individuals that will be displaced
A record of the field survey findings shall be maintained. Ideally these will be signed by the
relevant owner / occupier or district officer as a fair and accurate record of the situation.
The output of the field survey should include:
i. Maps showing road reserve boundary, registered plots, and residual land that may need to
be acquired,
ii. Indicative Land Inventory, including different land tenure systems, location and size of plot
and proportion affected, land type and use,
iii. Indicative Property Inventory, including structures (e.g. homes, animal pens, stores),
infrastructure (e.g. water supply and sanitation, utilities connections), and other assets
(trees, crops)
iv. Community Infrastructure inventory, including all socio-economic and communal services
and facilities, utility services and religious / cultural facilities that may be affected,
v. Indicative Livelihoods Inventory, including identification of vulnerable groups (e.g. female or
child headed households, elderly, disabled, minority groups), income sources and
estimated values, cash and in-kind incomes, access to natural resources, etc.
Note that this is NOT a full cadastral survey; a cadastral survey is undertaken as part of the Survey
and Valuation exercise in LP2.
LP1.4. Mitigation Measures
The findings from the field survey should identify where negative impacts are likely to occur which
monetary compensation will not adequately resolve, and for which alternative mitigation measures
are required.
Mitigation measures may include:
8/11/2019 Land Aqusition Management System Uganda
26/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 18This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Moving or reconstructing personal and community infrastructure (including access to a
road) and structures,
Reconnecting to water supply, sanitation and utilities,
Identifying alternative livelihood opportunities and providing appropriate training,
Facilitating access to social and economic service providers,
Resettlement of families and providing support to families and communities during the
resettlement process.
Where mitigation measures involve construction works, the Consultant shall ensure they are
included in the detailed design and contract documents for the works contractor.
Where mitigation measures involve support and development, the Consultant shall liaise with the
local government and NGO service providers to develop plans to implement the mitigation
measures.
LP1.5. Compensation Strategy
The Compensation Strategy shall define the principles to be adopted in estimating the
compensation costs. This shall include eligibility principles for compensation, copies of the latest
district rates, analysis of current market prices for land and property, proposed rates for
compensation for all asset types for each area along the project road, payment mechanisms and
responsibilities, the documentary evidence necessary to allow payments to be made, etc.
Eligibility principles and proposed rates should take into account:
the governments position on using district approved rates, depreciated prices and
disturbance allowances,
how to ensure fair division of compensation between owners and occupiers, especially on
mailo land,
how to price for acquiring land where the existing road is (i.e. carriageway, shoulders and
drainage ditches).
The compensation strategy should define the payment mechanisms and thresholds for cash
payments, stating whether larger sums are to be paid by cheque, bankers draft or by electronic
fund transfer.
The draft compensation strategy should be submitted, via UNRA, to the Chief Government Valuer
for review and approval in principle. A record of the CGVs comments and approval shall be
maintained.
8/11/2019 Land Aqusition Management System Uganda
27/66
8/11/2019 Land Aqusition Management System Uganda
28/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 20This is not a controlled document.
The controlled document is held electronically (see section 2.5)
The report should follow the standard template prepared by UNRA, and be submitted to UNRA for
approval. A record of UNRAs comments and approval shall be maintained. UNRA may send a
copy to the CGV for information.
The Consultants responsibility for the initial assessment ends with approval of the report by
UNRA.
8/11/2019 Land Aqusition Management System Uganda
29/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 21This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP2. Survey and Valuation
Objective:
To prepare a Valuation Report and Strip Maps to the satisfaction of the Chief Government Valuer and the Commissioner for Land
and Surveys
Input:
Initial Assessment Report, Alignment Design, Base Maps (physical features), Deed Plans
Process:
LP2.3Compensation
Principles & Rates
LP2.Survey &Valuation
LP2.1Review InitialAssessment
LP2.2Survey & Display
Strip MapsLP2.4
ValuationAssessments
LP2.5Snaglist
LP2.7Valuation Report
Output:
Approved Valuation Report
Controls:
Terms of Reference, Template for Valuation Report, Government of Uganda Requirements
Measures:
% Reports submitted to UNRA on time
% Reports approved by UNRA on first submission
% Reports approved by CGV / Surveys approved by CoS on first submission
Length of time between first submission and CGV / CfLS approval
The Valuation should normally be carried out during detailed design stage, and should provide a
detailed and accurate inventory of all affected property and a detailed valuation for compensating
those affected properties.
The Valuation process should only start once the final alignment and earthworks design has been
approved, in phases if appropriate, and the necessary public notices issued.
Responsibility for completing the initial assessment lies with the Consultant contracted to
undertake the work. This will usually be a separate contract for Valuation, Compensation and
Expropriation. See LP5 Resource Management for further information.
The Valuation Report must be approved by the Chief Government Valuer before commencing with
LP3 Compensation and Expropriation
8/11/2019 Land Aqusition Management System Uganda
30/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 22This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP2.1. Review Initial Assessment
This involves a review of the work already done during the Initial Assessment (or work done to date
if there is any overlap), in particular the desk study findings, the compensation strategy,
implementation plan and cost estimates.
It also includes a review of the alignment and earthwork designs, to identify whether there have
been any significant changes since the initial assessment was prepared. Where any design
changes affect the mitigation measures developed under the initial assessment, the consultant
should advise UNRA and the design consultants to address these in the Environmental and Social
Impact Assessment (ESIA).
LP2.2. Survey and Display Strip Maps
This requires a full cadastral survey, in accordance with the requirements of the Commissioner for
Lands and Surveys and the Chief Government Valuer, to plot land boundaries, affected property
and large trees or other significant features eligible for compensation payment.
The purpose of the maps is to:
i. Provide supporting evidence for the valuation exercise,
ii. Provide the plans for transfer of titles and revising deed plans.
In carrying out the survey, the survey team should place physical markers at plot boundaries and
to show the boundary of the land to be acquired for the road reserve.
The plans to support valuation should show the boundaries of all land by owner / occupier,
including on customary land, and all affected assets that can be plotted.
The plans for transfer of titles and revising deed plans only need to show the registered land
boundaries and the proposed boundaries of land to be acquired. The survey data, including
information on the control points used and physical markers placed to demarcate the property,
should be submitted to the Commissioner for Lands and Surveys for approval. A record of the
Commissioners approval of the plans shall be maintained.
The plans, also known as strip maps, should be displayed in the locations identified in the Initial
Assessment.
LP2.3. Compensation Principles and Rates
This requires liaison with district officers and Government Valuers to develop the principles and
rates to be proposed for all items eligible for compensation, including:
Current district approved rates for non-permanent property,
8/11/2019 Land Aqusition Management System Uganda
31/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 23This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Assessment of market rates proposed for land and permanent property,
Payment for land where existing carriageway and shoulders are,
Payment for owners and occupiers of mailo land,
Disturbance allowances,
Attendance allowances and expenses for local government officials to be present for
verification, compensation and expropriation.
The Consultant should also review the payment mechanism and thresholds defined in the Initial
Assessment.
The proposed rates must be submitted at the earliest opportunity, via UNRA, to the Chief
Government Valuer for review and approval. A record of the CGVs comments and approval shall
be maintained.
LP2.4. Valuation Assessments
Walkover Survey
The valuation exercise includes a walkover survey, in the presence of the owner / occupier, of
each plot shown on the strip map, to quantify the crops and other assets eligible for compensation,
including an accurate description of affected property. The walkover survey team should include
both a valuer and land surveyor.
A Valuation Assessment Form should be completed and signed by the surveyor and the owner /
occupier to confirm the quantities.
The valuation should include identification of residual land and marginal property, and discussion
and proposals as to how to deal with these. This information will be detailed on the separate Early
Warning Form, which shall be appended to the Valuation Assessment Form.
An Assessment Team shall be compiled to make the final decision on how to deal with residual
land and marginal property and shall include representatives from UNRA Projects and Planning
Directorates, the Detailed Design Consultants, the Commissioner for Physical Planning, the Chief
Government Valuer and the District Land Office
Theirwritten recommendation shall be entered on to the Early Warning Form.
At the time of assessment, the Assessment Officer should obtain photocopies of registered titles,
certificates of tenancy, occupancy, customary ownership, etc.
8/11/2019 Land Aqusition Management System Uganda
32/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 24This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Valuation Assessment and Inquiry
A hearing shall be held in each village affected by land acquisition, to validate the quantities on the
valuation assessment forms and to hold an inquiry into any objections.
An assessment board, comprising the Assessment Officer and a representative from the local
council (LC1) shall preside over the hearing.
Each person with a claim to compensation, who wishes to raise an objection, shall attend the
hearing in person or by authorised agent. The assessment board shall carry out an inquiry and
confirm the valuation in accordance with the Valuation Assessment Form or any necessary
revisions resulting from the inquiry.
Details of the final award should be recorded on a Valuation Schedule Form. The form shall
confirm the quantities, the rates (based on the approved compensation principles and rates) and
calculate the total amounts to be paid in compensation.
These forms will be included as an Appendix to the final Valuation Report.
A Valuation Schedule shall be prepared that summarises all the valuation awards and providestotals by property type and by location. .
LP2.5. Snag list
A snag list shall be prepared to identify any property where there may be potential difficulties or
obstacles that may delay completion of the acquisition process. These include property where:
The registered title holder is absent and cannot be easily contacted,
The registered title holder is recently deceased and legal proceedings to transfer the
property to the intended beneficiary have not been completed,
The title or certificate of ownership / occupancy has been lost,
There is an ongoing or potential dispute over the property,
Any other event or concern may delay acquisition.
The snag list shall be in matrix form identifying the problem, the options considered to solve the
difficulty, the recommended solution, who is responsible for implementing and overseeing the
solution and the timescale for doing so. The snag list shall be updated regularly as items are
resolved.
LP2.6. Valuation Report
The Valuation Report shall summarise all the above tasks, with supporting documentation provided
in Appendices. It should also include a completion report of the Consultants activities, including
8/11/2019 Land Aqusition Management System Uganda
33/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 25This is not a controlled document.
The controlled document is held electronically (see section 2.5)
team inputs, actual against planned costs and implementation, difficulties encountered, lessons
learned, etc.
The report should follow the standard template prepared by UNRA, and be submitted to UNRA for
review and approval. UNRA will then submit the report to the CGV for final approval. A record of
the CGVs comments and approval shall be maintained.
The Consultants responsibility for Valuation ends with approval of the report by UNRA and the
Chief Government Valuer.
8/11/2019 Land Aqusition Management System Uganda
34/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 26This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP3.Compensation and Expropriation of Land
Objective:
To compensate PAPs, expropriate land and clear road reserve ready for Contractors possession of site
Input:
Approved Valuation Report
Process:
LP3.Compensation &
Expropriation ofLand
LP3.1
Review & UpdateValuation Report
LP3.2Verify & Pay
Compensation
LP3.4Land
Expropriation
LP3.4
AccountabilityReport
LP3.3
Grievances andAppeals
Output:
Land Titles, Accountability Report
Controls:
Terms of Reference, Template for Accountability Report, Government of Uganda Requirements
Measures:
% PAPs paid and land plots expropriated on time
% PAPs lodge valid grievance / appeal
% Reports submitted on time and approved by UNRA on first submission
% Contracts have delayed start due to land acquisition, and number of days delayed
The payment and expropriation process may only start after approval of the Valuation Report by
the Chief Government Valuer and once funds are secured to make the compensation payments.
Ideally, the process should be completed before procurement of the works contractors, to allow at
least 6 months for affected families to move off the acquired land before the contractor starts work
on site.
Responsibility for completing the payment and expropriation process lies with the Consultant
contracted to undertake the work under a contract for Valuation, Payment and Expropriation. See
LP5 Resource Management for further information.
8/11/2019 Land Aqusition Management System Uganda
35/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 27This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP3.1. Review and Update Valuation Report
This involves a review of the Valuation Report, in particular to identify whether there are any
appeals and / or items on the snaglist still to be resolved. The review should also update the
implementation schedule as necessary, in particular setting the dates of planned meetings for
verification and payment.
LP3.2. Verify and Pay Compensation
The implementation plan should include for at least a one day meeting in each village where
people are to be paid compensation. The purpose of these meetings is to verify the identify of
those entitled to compensation, to make payment by the appropriate means, and to obtain the titles
/ certificates to register the transfer of land.
The following people need to be present:
Assessment Officer (Consultant) to confirm amounts to be paid, maintain the appropriaterecords, and coordinate / oversee the verification and payment process,
LC1 Representative to verify the identity of those entitled to compensation and to witness
the payment,
District Representative to witness the payment,
District Land Office Representative to receive the titles / certificates for subsequent
processing.
Those entitled to compensation need to present the following documentation to enable payment to
be made:
Valid identify papers (ID Card, Driving Permit, Voters Card, Passport); if no valid
identification can be produced a signed letter from the LC1, approved by the Sub-County
Chief and District Chief Administrative Officer, confirming identify will be accepted;
2 Passport style photos (for identify verification and payment confirmation);
Land title / certificate, where land is to be transferred to UNRA;
Bank account details, where payment is to be made by electronic fund transfer.
Payments should be made in accordance with the payment mechanisms and thresholds defined in
the Valuation Report. An Identify Verification Form and a Payment Receipt Form shall be
completed for all transactions.
8/11/2019 Land Aqusition Management System Uganda
36/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 28This is not a controlled document.
The controlled document is held electronically (see section 2.5)
A record of all titles / certificates deposited with the district registrar or representative shall be
maintained.
LP3.3. Grievances and Appeals
Any objection or contest to a claim or any objection, grievance or appeal against an award made,
may be submitted in writing to the Assessment Officer (via local and district representatives) duringan appeal period of 60 days from the date of the inquiry and award. The claimant may use a
standard record of appeal form, which will be logged and tracked in a spreadsheet held by the
Assessment Officer.
The appeals shall be considered by the Assessment Officer and the Chief Government Valuer,
who shall decide on the award to be made. If an individual is still not satisfied with the award, they
may start legal proceedings through the Land Tribunal.
The Assessment Officer shall maintain a record of any grievances or appeals submitted, including
information on how they are being addressed and of their final resolution.
LP3.4. Land Expropriation
The land titles / certificates deposited with the District Land Board Representative during the
verification and payment meetings shall be processed by the Registrar in accordance with the
Registration of Titles Act, and the requirements of the Commissioner for Land Registration.
Responsibility for this lies primarily with the Commissioner and his authorised assistants and
registrars. The Consultant shall provide whatever assistance is required by the Commissioner to
facilitate the process, especially in relation to preparation of revised Deed Plans.
The land acquired shall be registered under the Uganda National Roads Authority, to be held by
the Uganda Land Commission.
The Consultant shall ensure that revised titles / certificates for residual land are returned to the
owner / occupier, and acknowledgement of their return recorded.
LP3.5. Accountability Report
The Accountability Report shall summarise all the above tasks, with supporting documentation
provided in Appendices. The report should include details of:
Any outstanding appeals,
Any legal action being taken,
Any refusals to accept payment or handover titles / certificates.
8/11/2019 Land Aqusition Management System Uganda
37/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 29This is not a controlled document.
The controlled document is held electronically (see section 2.5)
It should also include a completion report of the Consultants activities, including team inputs,
actual against planned costs and implementation, difficulties encountered, lessons learned, etc.
The report should follow the standard template prepared by UNRA, and be submitted to UNRA for
review and approval. A record ofUNRAs comments and approval shall be maintained. UNRA
may send a copy to the CGV for information.
The Consultants responsibility for Payment and Expropriation ends with approval of the report by
UNRA.
8/11/2019 Land Aqusition Management System Uganda
38/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 30This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP4.Quality Management
Objective:
To manage land acquisition process effectively and in accordance with Government of Uganda requirements, with a focus on Client
satisfaction and continual improvement
Input:
Land Acquisition Management System, quality Records
Process:
LP4.Quality
Management
LP4.1Maintain LAMS
LP4.3Management
Reviews
LP4.2Audit Programme
Output:
Client Satisfaction
Controls:
LAMS, Legal Framework, Templates for, Audit Plan, Audit Reports, Non-conformance Reports, Management Reviews
Measures:
% Audits / Reviews completed as planned
%Audits identify no Non-Conformances
% Tasks in continual improvement plan completed within two months of target date
Quality Management is a continual process and applies across all the procedures. UNRAs and
their consultants are responsible for ensuring they implement land acquisition processes in
accordance with the relevant procedures, maintain the necessary records and obtain the
necessary approvals.
Responsibility for overall quality management lies with UNRA, in particular the Land Acquisition
Specialist and the Land Acquisition Officer. In particular this involves maintaining the Land
Acquisition Management System, managing an Audit Programme and the Management Reviews.
LP4.1. Maintain LAMS
Document Control
The LAMS comprises this document (the Land Acquisition Management System) and the forms /
templates to be used for keeping records. The Land Acquisition Specialist and Executive Director
shall approve all LAMS documents and subsequent revisions.
8/11/2019 Land Aqusition Management System Uganda
39/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 31This is not a controlled document.
The controlled document is held electronically (see section 2.5)
The document control sheet at the front of this document and the page footers provide a record of
the current revision date for the LAMS. A similar table for the forms and templates to be used is
given in Appendix C Standard Forms and Templates.
Changes shall not be applied retrospectively.
The controlled version of the LAMS is stored electronically on the UNRA server under the Planning
Directorates restricted folders. Only the Land Acquisition Specialist maintains a printed controlled
version, which includes the signed copy of the document control sheet. No other printed
documents are controlled.
All LAMS documents, forms and templates shall show the current version date at the bottom of the
page (all pages), to ensure the current version is clearly identified.
When revisions are made to the LAMS, the Land Acquisition Specialist shall contact all approved
consultants to inform and relevant UNRA staff to explain how the changes affect them and their
operations.
All LAMS documents shall be reviewed on a regular basis as part of the Management Reviewprocess.
Record Control
The records identified in the procedures are required to provide evidence of conformity to the
LAMS and ISO 9001 requirements. Records shall remain legible, readily identifiable, and
retrievable.
The records to be maintained shall be in the standard format provided by UNRA in Appendix C
Standard Forms and Templates, where available. If no standard format is available, the consultant
shall propose a format for UNRA approval.
In general, records for land acquisition procedures shall be bound into the relevant reports in
appendices. All reports relating to land acquisition shall be held by the Land Acquisition Specialist
and shall be retained, archived and disposed of in accordance with UNRAs Records and Archives
policy.
The records for quality management and resource management shall be stored by the Land
Acquisition Specialist, retained for at least 1 full year after completion of the related activity, after
which they may be disposed of. A copy of all resource management records shall be given to
UNRAs Human Resources Department for staff related records, and the Director of Planning for
Consultant related records.
LP4.2. Audit Programme
An audit plan shall be prepared annually, to ensure that each procedure is audited at least once a
year, and that each project / contract is audited at least once. The Land Acquisition Specialist is
responsible for preparing and maintaining / updating the audit plan.
8/11/2019 Land Aqusition Management System Uganda
40/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 32This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Only personnel (UNRA or Consultants staff) that have attended a quality auditors training event
shall carry out the LAMS audits. The Land Acquisition Specialist shall assign an auditor for each
audit in the plan such that no one shall audit their own area.
It shall be the responsibility of the assigned auditor to consult with the relevant project / office
representatives to set a date and time for the audit that suits all necessary parties. Audits may be
undertaken in more than one sitting if required. No official audit notification is required.
Audit Reports and any associated Non-Conformance Reports shall be prepared as soon as
possible after completion of the audit, signed by the auditor, and submitted to the Land Acquisition
Specialist.
Audits shall identify opportunities for continual improvement and preventive actions. These will
feed into the Management Review process.
The audit is the main mechanism for identifying non-conformances. A non-conformance shall be
recorded using the standard form and issued to the individual responsible for the project / office
where the non-conformance has occurred. The closure of non-conformances does not simply
require the specific item to be corrected, it requires analysis of the root cause of the non-
conformance and identifying actions that will prevent recurrence. This analysis and identification of
an appropriate solution is the responsibility of the individual receiving the non-conformance report,
though it should be completed in consultation with the Land Acquisition Specialist to ensure the
response is to UNRAs satisfaction and the proposed action is thought adequate to prevent
recurrence.
The Land Acquisition Specialist shall maintain a register of non-conformances to monitor their
status. Analysis of trends, the root causes and solutions to prevent recurrence shall feed into the
Management Review process.
Any follow up action required shall be undertaken by the Land Acquisition Specialist.
LP4.3. Management Reviews
The purpose of Management Reviews is to ensure the continuing suitability, adequacy and
effectiveness of the LAMS, to assess opportunities for improvement and the need for changes,
including the quality policy and objectives. Approximate dates for Management Reviews are
shown on the Audit Plan.
The Management Review should include representatives from the Directorates of Planning and
Projects, and the Land Acquisition Specialist and Officer. Other stakeholders may be invited to
participate in the Management Review, for example relevant central government officers or
Consultant representatives, if considered appropriate by UNRA.
The Land Acquisition Specialist shall liaise with key stakeholders to obtain feedback and
suggestions for improvement from key stakeholders and clients, and shall prepare an Agenda and
8/11/2019 Land Aqusition Management System Uganda
41/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 33This is not a controlled document.
The controlled document is held electronically (see section 2.5)
a LAMS Report for the Management Review. The report shall summarise the issues to be
reviewed including:
Follow up of recommendations from previous management reviews
Results of monitoring against quality objectives for each procedure
Feedback from key stakeholders and clients
Findings and recommendations from audits
Status of corrective actions
Achievements against the Continual Improvement Plan
Any other significant issues relating to management of land acquisition
The output of the review shall include a detailed record of the meeting, in particular any decisions
made and actions assigned. The Land Acquisition Specialist will revise the Continual Improvement
Plan accordingly.
The Continual Improvement Plan shall record the actions arising from the Management Review,
and assign responsibilities and timeframes for completion. The Land Acquisition Specialist will
monitor progress against the plan and update the plan as necessary.
8/11/2019 Land Aqusition Management System Uganda
42/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 34This is not a controlled document.
The controlled document is held electronically (see section 2.5)
LP5.Resource Management
Objective:
To procure and manage consulting services to complete land acquisition to the satisfaction of UNRA and their Clients
Input:
PPDA Act and Regulations, Pipeline Project Plans
Process:
LP5.Resource
Management
LP5.1Training
LP5.2Procurement of
Consultants
LP5.3Contract
Management
Output:
Satisfactory completion of land acquisition processes
Controls:
LAMS, TOR, Approved Suppliers List, Training Plan
Measures:
% Consultant contracts completed on time
% Consultant contracts completed to satisfaction of UNRA
% Consultant contracts resulting in complaints from UNRA or its Clients
Resource Management is about making sure that all necessary personnel involved in
implementing the LAMS are adequately trained in the procedures and understand the
requirements. This includes ensuring that Terms of Reference (TOR) for consultants are clear and
progress targets are achievable.
Responsibility for resource management lies with UNRA. It is coordinated by the Land Acquisition
Specialist, but requires input from staff in the Directorate of Planning and the Human Resources
Department. In particular this involves maintaining the Land Acquisition Management System,
managing an Audit Programme and the Management Reviews.
LP5.1. Training
The Land Acquisition Specialist shall be responsible for ensuring the following training events are
held:
Familiarisation of the LAMS to all UNRA staff involved in or whose work is affected by land
acquisition activities,
8/11/2019 Land Aqusition Management System Uganda
43/66
8/11/2019 Land Aqusition Management System Uganda
44/66
Uganda National Roads AuthorityDirectorate of Planning Land Acquisition Management System
Version: 13 June 2009 Page 36This is not a controlled document.
The controlled document is held electronically (see section 2.5)
Detailed Engineering Design
LP2.Valuation
Final AlignmentDesign
Darft Alignment /Earthworks
Design
Final Design &Bidding
Documents
Procurement of Works Contractors (min 6 months)
Issue BidDocuments
Evaluate Bids Award Contract
LP3.Payment &
ExpropriationSite Cleared
Start on Site
A model Terms of Reference for the Valuation, Payment and Expropriation will be prepared by the
Land Acquisition Specialist, which are to be included in the Standard Bidding Documents for Land
Acquisition Consulting Services. The procurement process usually takes a minimum of 6 months.
As the alignment design and road reserve area will not be complete when preparing the bidding
documents, it may not be possible to define accurate quantities. The Land Acquisition Specialist
should prepare a Schedule of Rates to cover all items likely to arise, which will be used for the
financial evaluation of bids. The bids should be based on estimated quantities, but with provision
for revision at the time of contract award.
LP5.3. Contract ManagementThe Land Acquisition Specialist shall be responsible for monitoring the performance of the
appointed consultants in accordance with the Terms of Reference.
A copy of the Land Acquisition Management System, and the relevant forms and templates, shall
be given to the consultant at the start of their assignment. The Land Acquisition Specialist shall
ensure they are working to the latest version, including any revisions made during the period of
their assignment.
The standard reports include a requirement for the consultant to include their completion report for
each process. In addition, they shall submit an Inception Report and Interim Progress Reports in
accordance with