Upload
rajfab
View
260
Download
2
Tags:
Embed Size (px)
DESCRIPTION
Lake Challa
Citation preview
Coast Development Authority
THE LAKE CHALLA WATER RESOURCES
INTEGRATED DEVELOPMENT PROJECT
FINAL ENGINEERING REPORT
MAY 2012
Coast Development Authority
Contents
LOCATION MAP
PROJECT SUMMARY
CHAPTER 1: INTRODUCTION
1.1 BACKGROUND .................................................................................................................................. 1-14
1.2 OBJECTIVES OF THE PROJECT ...................................................................................................... 1-14
1.3 SCOPE AND OBJECTIVES OF THE CONSULTANCY SERVICES ............................................. 1- 15
1.4 SCHEDULED OUTPUTS ................................................................................................................... 1-15
1.5 SCOPE OF THIS REPORT ................................................................................................................ 1- 16
CHAPTER 2: DESIGN OF IRRIGATION COMPONENT
2.1 INTRODUCTION ........................................................................................................................... 2-7
2.2 GENERAL ....................................................................................................................................... 2-7
2.3 EVAPOTRANSPIRATION............................................................................................................. 2-7
2.4 THE PROJECT AREA .................................................................................................................... 2-8
2.5 CURRENT AGRICULTURAL PRODUCTION .......................................................................... 2-21
2.6 PROPOSED CROPPING PATTERN FOR PROJECT AREA ..................................................... 2-22
2.7 IRRIGATION METHODS ............................................................................................................. 2.22
2.8 CHOICE OF IRRIGATION METHOD ........................................................................................ 2-28
2.9 COMPARISONS OF VARIOUS IRRIGATION METHOD(S) ................................................... 2-30
2.10 PREFERRED IRRIGATION METHOD(S) .................................................................................. 2-30
2.11 CROP AND IRRIGATION WATER REQUIREMENTS ............................................................ 2-34
2.12 PROPOSED IRRIGATION SYSTEMS COMPONENTS ............................................................ 2-59
CHAPTER 3: DESIGN OF WATER SUPPLY SYSTEMS
3.1 GENERAL .......................................................................................................................... 3-4
3.2 SOURCES OF WATER ..................................................................................................... 3-4
3.3 INTAKE .............................................................................................................................. 3-5
Coast Development Authority
3.4 LAKE CHALLA TANK ..................................................................................................... 3-6
3.5 TIMBILLA TANK .............................................................................................................. 3-7
3.6 TRANSMISSION PIPELINES ............................................................................................ 3-7
3.7 DOMESTIC WATER SUPPLY .......................................................................................... 3-8
3.8 ANCILLARY WORKS ....................................................................................................... 3-9
3.9 MATERIALS SPECIFICATIONS .................................................................................... 3-10
CHAPTER 4: COST ESTIMATES AND PROJECT PHASING
4.1 GENERAL ................. ……………………………………………………………………..4-3
4.2 BASIS FOR ESTIMATION OF COSTS ............................................................................. 4-3
4.3 SUMMARY OF ESTIMATED COSTS .............................................................................. 4-3
4.4 ITEMISED WORKS COST ESTIMATES ......................................................................... 4-5
4.5 PROJECT PHASING ......................................................................................................... 4-8
Coast Development Authority
PROJECT SUMMARY
Project Location:
Lake Challa Water Resources Integrated Development Project is primarily located in the Taveta District which
forms part of the bigger Taita-Taveta County. The project also covers some areas in the lower Mwatate District
(Mwaktau Division) and the western part of Kinango District.
Objective of the Project
The main objective of the Lake Challa Water Resources Integrated Development Project is to improve the living
standards of Taveta residents through Poverty Alleviation and Sustainable Development. This shall be
accomplished by;
Provision of water for domestic, irrigation and livestock uses.
Increasing food production for domestic use, export market and Income generation.
Enhancement of environment conservation and sanitation.
Promotion of eco-tourism.
Creation of employment for youth and women.
Lake Challa
Lake Challa is situated on the western side of Taveta District. It is a volcanic crater fresh water Lake on the South
Eastern slopes of the Kilimanjaro Range 45 km south of the summit and about 10 km North of Taveta town on the
Kenya – Tanzanian border. It is a volcanic crater fresh water lake.
Latitude: - 3015’ and 3
025 ‘S; Longitudes: - 37
0 40' and 37
045’E; Surface Area: - 3.44 km
2 Depth = 100 m
Volume of water in the lake is approximately 300 to 350 million cubic meters.
KEY FINDINGS, RESULTS, RECOMMENDATIONS
Mean Monthly Climatical Data for Project area
Item Description Item Description
Temp.(Max) (0C) 30.4 Daily Wind Run (km/day) 141
Temp.(Min) (0C) 16.6 Sunshine hours (h) 12
Open Water Surface Evaporation (mm/day) 5.28 Mean Rainfall (mm) 673
Relative Humidity (%) 61.2
Soil Chemical Characteristics of Project Area
Area Remarks
Kilanga The soils are well suited for irrigation on the account of their very favourable
chemical and physical characteristics.
Challa (near Market)
Soils are well suited for irrigation due to their lack of salinity, high fertility
and good physical properties.
Nakuruto
Soils not suited for irrigation due to their very shallow depth in spite of having
good chemical properties.
Timbila
Based on the available physical and chemical characteristics, the soils are
suited for irrigation.
Jipe The soils in the upper areas are well drained and are irrigable. However, the
soils close to the lake have high salinity and sodicity levels, and would not be
easy to drain.
Mwaktau Based on the available physical and chemical characteristics, the soils are
suited for irrigation.
Coast Development Authority
Water Resources
Two options were identified as potential sources of water for irrigation and domestic use.
Option 1; Lake Challa and Lake Jipe
Option 2; Groundwater from boreholes
From analysis, it was found that;
Over 7,000,000 m3 of water per year can be abstracted from Lake Challa without negatively
affecting the lake levels.
3 boreholes (2 at Kilanga Scheme and one situated at Nakuruto Kasokoni producing 400 m3
per hour each and 100 m3 per hour respectively) can in combination provide over 7.0 million
m3 per year.
Quality of Irrigation Water
The water quality is satisfactory and suitable for irrigation purposes and can be used on most soils and crops. It’s
the main raw material required for the operation of the irrigation and domestic water supply system.
Electricity
The electric power will be sourced from the national power grid with a connection being done from the HT power
line running along the Taveta – Challa Road. Electricity will be supplied by the Kenya Power Company (KPC) on
a commercial basis.
RECOMMENDATIONS:
The major output of the Lake Challa Water Resources Integrated Development will be;
Development of an irrigation system that will cover 1020 ha at (five) 5 sites. These are Kilanga site,
Challa Irrigation Scheme, Timbila Scheme, Jipe Settlement Scheme and Mwaktau. Nakuruto/Kasokoni
area will also be supplied with raw water whose uses will be determined by residents.
Setting up of a domestic water supply system for households, livestock, fisheries and forestry.
Provision of water for wildlife within the park.
SALIENT FEATURES OF THE DESIGNED PROJECT
Population of Taveta District: 67,023; Land area: 4,205.63(Taveta District).
Major economic activities of Taveta District: Farming, Fishing, Quarrying and small scale trade.
Recharge/Discharge of the lake
Lake Challa is recharged by aquifers between 817m and 698m above sea level. The aquifers benefit from the
groundwater flows from the Kilimanjaro Region in the west and bounded by the fresh Basement System of rocks
in the East. Water flows in and out of the lake through these aquifers.
The groundwater basin is recharged by precipitation on Mt Kilimanjaro and local rainfall. The nearby springs also
get their recharge from the ground water basin.
Aerial Extent of the groundwater basin is approximately 10,500 Square Kilometres. Recharge in the basin
approximates 5,250 million Cubic Metres per year.
Coast Development Authority
Table: Lake Challa Water Balance
No. Component Abbreviation Measurement in m3
1 Groundwater inflow Gin
8,115,279
2 Groundwater outflow Gout 122,095
3 Precipitation falling in the lake Pl 3,197,136
4 Precipitation falling in the entire Watershed Pw 15,084,162
5 Evaporation from the lake El 3,612,000
6 Change in storage ΔS 7,578,320
Pumping from the Lake at a rate of 30,000cubic metres per day will have minimal effect on the Lake water level.
Boreholes
From the Hydrogeological study of the Lake Challa Watershed Area and the simulation results of the exploratory
boreholes in the Challa Irrigation Scheme and at Nakuruto Kasokoni, sustainable discharges for each borehole
within the Challa/Kilanga area were estimated to be 400 m3/h and 100 m
3/h at Kasokoni.
Based on the above, water will be sourced and abstracted from three boreholes to be developed in the Kilanga,
Challa and Nakuruto/Kasokoni areas. The total available water from the boreholes will be 1,200 m3/h.
Hydrogeological and Geological Setting of Lake Challa Watershed
Hydro-geology of Lake Challa catchment area is defined by the Kilimanjaro aquifer. The aquifer includes the
volcanic pyroclastic and volcanic alluvium deposits found at the base of Mount Kilimanjaro and extending across
the Kenyan-Tanzanian border. These deposits form basins which extend outward from the mountain and are
limited by the surrounding Precambrian Basement rocks.
Lake Challa is part of the aquifer and its recharge and discharge is strongly linked to the volcanic pyroclastic and
volcanic alluvium deposits which allow percolation through the faults, fractures and weathered zones. The
surrounding Precambrian Basement rocks, which are impermeable zones, enhance groundwater storage and
transmission within the aquifer by preventing transmission out of the aquifer.
IRRIGABLE LAND, PLANNED AREAS
Five sites i.e. Kilanga, existing Challa Irrigation Scheme, Timbila, Jipe and Mwaktau have been identified as
being suitable for development of the irrigation schemes based on agricultural suitability, soil profile,
flooding conditions and topography of the site.
Kilanga Site
Situated next to Lake Challa and between Taveta – Loitoktok road to the east and Kenya Tanzania
border to the west.
Land presently occupied by about 120m households and used for farming and rearing of livestock.
Size of the scheme will be 140 ha. With 100 ha being used as a demonstration farm and the rest used
for construction of a reservoir, administration block and processing and value addition facilities.
Land is flat to very gently undulating with slopes ranging from 0.5% to 2% towards the west.
Soils are well suited for irrigation on the account of their favourable chemical and physical
characteristics.
Coast Development Authority
Challa Scheme
Located in an alluvial plain North- west of Challa market and about 20 km north east of
Lake Challa. It is an existing irrigation scheme approximately 1680 Ha, owned by Challa Co-operative Society. It
relies on water supplied from Lumi River. The water is however not enough and more water to
compensate for the deficiency needs to be supplied.
The area is flat with slopes ranging from 0.5% to 1% towards the North.
There are no settlements within the Scheme, but people are settled within the surrounding areas.
Timbila Site
The Timbila site is located approximately 12 km south of Lake Challa and 4 km east of Taveta Town
The area has a gentle north-south slope of about 1% and there is a significant topographical height
difference of about 100 m between the site and Lake Challa.
The project area covers 2500 acres and has a population of approx. 300 households.
Jipe Settlement Scheme
The Scheme is located approximately 10 km southeast of Timbila and stretches from Voi-Taveta road
to the northern shores of Lake Jipe in the south and borders Tsavo West National Park to the east. It has
an area is about 10,000 ha.
The area was designated by the Kenyan Government as part of a new rural development area and was
subdivided into several plots to individuals ranging from 15 to 25 acres. There are about 600
households resident in the scheme but most of the plots are yet to be settled. The area is woodland
currently being used for grazing.
The topography is flat to very gently undulating with slopes ranging from 0 to 2% towards South and
South west.
Based on their physical and chemical characteristics, the soils on the upper part of the scheme are
suitable for irrigation, but are susceptible to gully erosion.
Mwaktau
The Mwaktau Site is located approximately 50 km from Timbila site (about halfway between Taveta
and Voi by road) and has a population of about 10,000 people.
The area is flat to gently undulating with slopes ranging from 0.5% to 2% towards the East and South
East.
The physical and chemical characteristics of these soils indicate that they are suitable for irrigation.
Nakuruto
This area is located on the eastern slopes of Challa crater.
The area is undulating with slopes ranging from 5 to10% towards the east.
The vegetation in the area is wooded grassland most of which is used for cultivation or grazing.
The soils are good for agricultural purposes.
Coast Development Authority
Proposed Annual Irrigable Areas
Site Status Remarks Mode of irrigation Area (ha)
Kilanga Pilot Project Proposed New Development Drip (80 ha)
Sprinkler(120 ha) 200
Challa (Existing Scheme) Existing Extension Surface Irrigation 200
Nakuruto Proposed New Development Surface Irrigation 90
Timbilla(Existing Scheme) Existing Extension Surface Irrigation 200
Jipe Settlement Scheme Proposed New Development Surface Irrigation 930
Mwaktau Proposed New Development Surface Irrigation 400
Total 2,020
Proposed Cropping Pattern by Project Areas
Season Crop Area (ha) Total
Kilanga
Pilot
Scheme
Challa
Scheme
Nakuruto Timbila
Scheme
Jipe
Scheme
Mwaktau
Scheme
(ha)
Season
One
(March
to July
Maize - 20 10 20 100 40 190
Beans - - - - 45 15 60
Green grams - - - - 30 15 45
Cowpeas - 10 5 10 20 15 60
Tomatoes 20 10 10 - - 40
Kales 10 10 5 10 - - 35
Sunflower - - - - 25 15 40
Bananas 20 10 5 10 100 40 185
Melons 10 10 5 10 10 5 50
paw paws 20 10 5 10 75 25 145
Onions 10 10 5 10 50 25 110
Chillies 10 10 5 10 10 5 50
Sub-total 100 100 45 100 465 200 1,010
Season
Two
(Sept’
to Jan)
Maize - 20 10 20 100 40 190
Beans - - - - 45 15 60
Green grams - - - - 30 15 45
Cowpeas - 10 5 10 20 15 60
Tomatoes 20 10 10 - - 40
Kales 10 10 5 10 - - 35
Sunflower - - - - 25 15 40
Bananas 20 10 5 10 100 40 185
Melons 10 10 5 10 10 5 50
Paw paws 20 10 5 10 75 25 145
Onions 10 10 5 10 50 25 110
Chillies 10 10 5 10 10 5 50
Sub-total 100 100 45 100 465 200 1,010
TOTAL 200 200 90 200 930 400 2,020
DOMESTIC WATER SUPPLY
Domestic water supply has also been incorporated in the project for areas that experience acute water shortages.
These are Kasaani in Jipe, Kidongu, Nakuruto/Kasokoni, Mwaktau Trading Centre and Kwa Mnengwa.
Coast Development Authority
Forestry
The forest and tree establishment will be done along the following areas;
Rehabilitation of Lake Challa escarpment - This covers the outskirt of Lake Challa crater which is steep with
high vegetation degradation and soil erosion. 255 ha and a perimeter of 10km have been identified.
Rehabilitation of Kedong Hill – This is situated within Timbila scheme, and covers an area of 130 ha and a
perimeter of 4km.
Rehabilitation of Salaita Hill – The hill has an area of 11 ha and a boundary of 1km.
Agroforestry in proposed Challa, Timbila and L. Jipe Irrigation Schemes – At each of these schemes, 10%
of the area will be put under tree cover. This will be done in different configurations including strip tree planting,
boundary tree planting, planting along canals, woodlots, pockets of forest, rehabilitation of degraded areas and
roadside tree planting.
River - line and springs – Rehabilitation of 30% of the river line with a total length of 12km shall be done.
Natural springs will be rehabilitated to ensure integrity.
Farmland - Fast growing trees species which yield required wood and non wood products will be introduced.
Fisheries
Fish ponds, dams and rehabilitation of wetlands such as rivers, Lake Jipe and springs shall be done, to increase
fish farming in the project area by 30%.
IRRIGATION WATER DEMAND, DOMESTIC WATER DEMAND & DOMESTIC & IRRIGATION
WATER SUPPLY
Water demand requirements of various project areas for irrigation, domestic needs and others;
No. Site Total Demand (m3/year)
Irrigation
Water
Demand
(m3/year)
Average
Irrigation
Water Demand
(m3/day)
Domestic
Water
Demand
(m3/year)
Domestic
Demand
(m3/day)
Total Demand
(m3/year)
1 Kilanga 810,307 2,214 0
810,307
2 Challa 881,823 2,410 0
881,823
3 Nakuruto/Kasokoni 404,834 1,107 58,552 160 463,386
4
Timbilla/
Kidong’u 881,823 2,410 44,297 121 926,120
5 Jipe 4,692,931 12,823 53,351 146 4,746,282
6 Mwaktau 1,935,868 5,290 120,400 330 2,056,268
7 Msorongo
125,369 343 125,369
8
Environment
Conservation
45,000 123 45,000
9
Wildlife (Tsavo
National Park)
91,250 250 91,250
10 Fisheries
20,000 55 20,000
Total 9,607,587
558,219 1,528 10,145,806
Coast Development Authority
Water demand tabulation is based on a projection up to the ultimate year of 2035. This was derived from
population projection using population growth of 1.8%.
Water Supply
Water will be sourced from Lake Challa and two boreholes. The water abstracted will then be used for irrigation,
domestic, livestock and wildlife within the Taveta – Mwaktau corridor.
The following table shows amounts of abstractions considered from the two sources;
Recommended Abstraction Rates from Sources
Source Capacity in
m3/hr
Pumping
Hours
No. of
Boreholes
Abstraction
(m3/day)
No. of working
days
Volume
(m3/year)
Lake Challa 400 20 8,000 330 2,640,000
Boreholes 400 20 3 24,000 330 7,920,000
Total water supply for entire project 32,000 10,560,000
The system;
Intake: Will consist of two submersible pumps, one on duty and one standby, in a pump house built on girders on
a floating pontoon.
Raw water pipeline: Two main pipelines have been designed for. One will convey water from Lake Challa and
the other from the boreholes. The two pipelines merge to deliver water to 1000m3 reinforced concrete tank to be
located at the top rim of Lake Challa.
Lake Challa tank: The tank with a capacity of 1000m3 is strategically located to command flow of water via
gravity to the entire project save for Mwaktau which is at a higher ground level.
Reservoirs: The project is designed to hold three major water storage earth-fill reservoirs as follows: Kilanga -
75,000 m3; Jipe - 75,000m3; Mwaktau - 65000m3.
Timbila tank: The 1000m3 reinforced concrete tank will hold water for irrigation in the Timbila area.
Transmission pipelines: Water will be conveyed in all the pipelines by gravity except for Jipe – Mwaktau –
KwaMnegwa pipeline which is a pumping mains from Jipe to Mwaktau.
Domestic water supply: Elevated steel water tanks of capacity 200m3 have been provided for in Mwaktau and
Kasaani area, a 250m3 concrete tank provided for at Kwa Mnengwa and Kidong’u and a 1000m
3 elevated steel
tank at Nakurito. The location and design of the tanks allow the supply in the respective area by gravity.
Ancillary Works: These include administration building and laboratory, staff houses, site drainage,
workshop, pump house, access road and power supply.
Cost Estimate and financial aspects for important components;
Development and equipping of three boreholes - KSH 73.74 million
Intake Works at Lake Challa - KSH 73.80 million
Transmission Pipelines - KSH 1,076.05 million
Civil Works including reservoirs - KSH 976.24 million
Project Phasing
For speedy implementation of the Project, it proposed that the project be implemented in three phases as described
below;
Coast Development Authority
1. Phase One – to cover Kilanga Pilot Irrigation Project and the existing Challa Irrigation Scheme
2. Phase Two – to include Timbila and Jipe Irrigation Schemes (including provision of domestic water within the
areas covered by the pipelines)
3. Phase Three – to include Mwaktau Irrigation Schemes (including provision of domestic water within the areas
covered by the pipelines)
Coast Development Authority
CHAPTER 1- INTRODUCTION
Coast Development Authority
Table of Contents
CHAPTER 1- INTRODUCTION ............................................... 1-12
1.1 BACKGROUND .............................................................................................................. 1-14
1.2 OBJECTIVES OF THE PROJECT .................................................................................. 1-14
1.3 SCOPE AND OBJECTIVES OF THE CONSULTANCY SERVICES .......................... 1-15
1.4 SCHEDULED OUTPUTS ............................................................................................... 1-15
1.5 SCOPE OF THIS REPORT ............................................................................................. 1-16
Coast Development Authority
CHAPTER 1- INTRODUCTION
1.1 BACKGROUND
Coast Development Authority (CDA) is one of the six Regional Development Authorities in
Kenya under the Ministry of Regional Development Authorities (MoRDA). Its mandate is to
promote socio-economic development, within the Coastal Region and other areas of its
jurisdiction, through initiation and implementation of integrated programmes and projects
such as provision of energy, flood control, water supply for irrigation, domestic and industrial
use, as well as environmental conservation, among others.
The Authority is mandated to improve the welfare of the people in the region in particular
and the country in general, through sustainable utilization of the natural resources such as
water, minerals, wind etc. in its area of jurisdiction.
Towards this end, CDA intends to assist the communities within its area of jurisdiction
through implementation of the Lake Challa Water Resources Integrated Development
Project.
When the project is fully implemented, it would have positive benefits and improvements on
the community’s poor state of health, education, enhance food production, promotion of
ecotourism development economy and the environment in general. It would also contribute to
curbing of the rural urban migration problem, as employment opportunities will be created
with the enhanced agricultural development and related facilities.
Lake Challa Water Resources Integrated Development Project is one of the flagship projects
of Vision 2030 and is slated for implementation during the first Medium Plan (2008 – 2012).
1.2 OBJECTIVES OF THE PROJECT
The main objective of the Lake Challa Water Resources Integrated Development Project is to
improve the living standards of Taveta residents through Poverty Alleviation and Sustainable
Development.
Specific objectives include;
Provision of water for irrigation, domestic and livestock uses,
Increasing food production (for domestic use and export markets) and Income,
Enhancement of environment conservation and sanitation
Promotion of eco-tourism,
Creation of employment for youth and women
Coast Development Authority
1.3 SCOPE AND OBJECTIVES OF THE CONSULTANCY SERVICES
The Consulting Services are intended for the implementation of Lake Challa Water
Resources Integrated Development Project with the following as the main components:-
Review of Previous Studies /Reports
Feasibility Study, Preliminary Designs and Implementation Programme
Environmental and Social Impacts Assessments
Detailed Engineering Designs
Preparation of Tender Documents and assistance in the Tendering Process
Institutional Development / Capacity Building
1.4 SCHEDULED OUTPUTS
The Consultant was required to prepare and submit the following reports:-
1. Inception Report
2. Interim Report
3. Feasibility Study Report & Preliminary Design Report
4. Environmental Impact Assessments – Project Environmental Management
Reports
5. Resettlement Plan
6. Detailed Design Report
7. Tender Documents
8. Final Study Report
This Report forms the sixth output.
Coast Development Authority
1.5 SCOPE OF THIS REPORT
Reports Nos. 1, 2, and 3 have already been submitted and accepted by CDA. Subsequently,
the Consultants carried out the field work in detail such as topographic survey, geological &
geotechnical investigations, agricultural, environmental and socio-economic surveys, etc. The
detailed desk studies such as hydrological studies, water demand studies, simulation studies,
irrigation planning, cost estimate and financial & economic analysis have also been carried
out to arrive at the feasibility of the project which has already been submitted and accepted
by the Client.
The survey, investigations, studies, project configuration, cost estimates and financial &
economic analysis are covered in the feasibility report. Design of irrigation systems and water
supply components were included in the Preliminary Design Report submitted to CDA earlier
and accepted by the client.
Report No. 4 (Environmental Impact Assessments – Project Environmental Management
Report) is submitted together with this Report (Detailed Design Report). Also submitted with
this Report is the;
A. Tender Documentation comprising of;
Tender documents for civil works.
Tender documents for pumps.
Tender documents for electrical supply & control equipment, power lines and sub-
station equipment
Tender documents for irrigation equipment/system.
B. Final Estimates & Financial requirements
As per the Terms of Reference (ToR), this is Report No. 6 i.e. Detailed Report and comprises
of the following;
1. Detailed Design Report
1.4 Chapter 1; Introduction
1.5 Chapter 2; Design of Irrigation Systems
1.6 Chapter 3; Design of Water Supply Systems
1.7 Chapter 4; Cost Estimates
2. Tender documents
2.1 Conditions of Billing/contract – Volume 1
2.2 Works Requirements – Volume 2
2.3 Book of Drawings – Volume 3
Coast Development Authority
CHAPTER 2: DESIGN OF IRRIGATION COMPONENT
Table of Contents
List of Tables ........................................................................................................................................ 2-20
List of Figures ...................................................................................................................................... 2-21
Coast Development Authority
List of Abbreviations and Acronyms ................................................................................................... 2-21
List of Symbols .................................................................................................................................... 2-22
CHAPTER 2 DESIGN OF IRRIGATION COMPONENT ........................................................... 2-23
2.1 INTRODUCTION ................................................................................................................... 2-23
2.2 GENERAL ............................................................................................................................... 2-23
2.3 EVAPOTRANSPIRATION..................................................................................................... 2-23
2.3.1 Evaporation .......................................................................................................................... 2-23
2.3.2 Transpiration ........................................................................................................................ 2-24
2.4 THE PROJECT AREA ............................................................................................................ 2-24
2.4.1 General Climatic Data .......................................................................................................... 2-24
2.4.2 Project Sites ......................................................................................................................... 2-26
2.4.3 Soils in the Project Area ....................................................................................................... 2-29
2.4.4 Quality of Irrigation Water .................................................................................................. 2-34
2.5 CURRENT AGRICULTURAL PRODUCTION .................................................................... 2-37
2.5.1 Agriculture and Land Use ........................................................................................................... 2-37
2.5.2 Crop Production .......................................................................................................................... 2-37
2.5.3 Conclusions ................................................................................................................................. 2-38
2.6 PROPOSED CROPPING PATTERN FOR PROJECT AREA ............................................... 2-38
2.7 IRRIGATION METHODS ...................................................................................................... 2-40
2.7.1 Surface Irrigation ................................................................................................................. 2-41
2.7.1.2 Furrow Irrigation .............................................................................................................. 2-41
2.7.1.3 Basin Irrigation ................................................................................................................ 2-41
2.7.1.4 Border Strip Irrigation ...................................................................................................... 2-41
2.7.2 Sprinkler Irrigation ............................................................................................................... 2-42
2.7.3 Drip (Or Trickle) Irrigation .................................................................................................. 2-43
2.8 CHOICE OF IRRIGATION METHOD(S) ............................................................................. 2-43
2.8.1 Natural Conditions ............................................................................................................... 2-44
2.8.2 Type(S) of Crop(S) .............................................................................................................. 2-45
2.8.3 Type and Level of Technology ............................................................................................ 2-45
2.8.4 Previous Experience with Irrigation..................................................................................... 2-45
2.8.5 Required Labour Inputs ....................................................................................................... 2-46
2.8.6 Costs and Benefits ................................................................................................................ 2-46
2.9 COMPARISONS OF VARIOUS IRRIGATION METHOD(S) ............................................. 2-46
2.10 PREFERRED IRRIGATION METHOD(S) ............................................................................ 2-48
2.11 CROP AND IRRIGATION WATER REQUIREMENTS ...................................................... 2-50
2.11.1 Crop Water Requirements (ETCROP)................................................................................. 2-50
2.11.2 Net Irrigation Water Requirements (NIR) ....................................................................... 2-55
2.11.3 Gross Irrigation Water Requirements (GWR) ........................................................................... 2-65
2.12 PROPOSED IRRIGATION SYSTEMS COMPONENTS ...................................................... 2-72
2.12.1 Introduction ...................................................................................................................... 2-72
Coast Development Authority
2.12.2 Design Criteria and Data .................................................................................................. 2-72
2.12.3 Project Components ......................................................................................................... 2-75
Coast Development Authority
LIST OF TABLES
Table 2.1 - Mean Monthly Climatical Data for Taveta District
Table 2.2 - Saturated Hydraulic Conductivity Classification
Table 2.3 -Basic Infiltration Rates for Various Soil Types
Table 2.4 - Physical Characteristics of Soils in Taveta District
Table 2.5 – Salinity and Sodicity of Soils
Table 2.6 - Values for Volumetric Water Content of Soils in Taveta District
Table 2.7– Soils Suitability for Irrigation
Table 2.8 - Guidelines for Interpretation of Water Quality for Irrigation
Table 2.9 - The pH and ECw of Water from the Proposed Sources
Table 2.10 - Food Crop Production Statistics, Taveta District- 2009/2010
Table 2.11 - Proposed Overall Cropping Pattern
Table 2.12- Proposed Cropping Pattern by Project Areas
Table 2.13 - Comparison of Irrigation Methods
Table 2.14 - Preferred Method(s) of Irrigation for Various Crops
Table 2.15 - Estimated Reference Evapotranspiration (ETo
Table 2.16 - Crop Coefficients
Table 2.17 - Cropping Calendar and Applicable Crop Coefficients
Table 2.18 - Estimated Crop Water Requirements (ETcrop)(mm)
Table 2.19 - Estimated Annual Crop Water Requirements (ETcrop)(mm)
Table 2.20 - Effective Soil Storages
Table 2.21 - Estimated Effective Rainfall (REFF) (mm)
Table 2.22 -Estimated Net Irrigation Water Requirements (NIR)(mm)
Table 2.23 -Net Monthly Irrigation Water Requirements per Crop
Table 2.24 -Net Monthly Irrigation Water Requirements per Site
Table 2.25- Irrigation Systems Efficiencies
Table 2.26 - Gross Irrigation Water Requirements (m3)
Coast Development Authority
Table 2.27- Summary of Gross Irrigation Water Requirements (m3)
Table 2.28 - Proposed Annual Irrigable Areas
Table 2.29 - Design Parameters for Drip Irrigation System
Table 2.30 - Design Parameters for Overhead Sprinkler Irrigation System
Table 2.31 - Design Parameters of Straight Furrow Irrigation
LIST OF FIGURES
Figure 2.1- Annual Rainfall Pattern in the Project Area
Figure 2.2– Comparison of Rainfall and Evaporation
Figure 2.3 – Typical Potable Lateral Move Overhead Sprinkler System
LIST OF ABBREVIATIONS AND ACRONYMS
oC - Degree Centigrade
cm3 - cubic centimetre
dS/m - deciSemens per metre
ECw - electrical conductivity
FAO - Food and Agricultural Organization
G - gramme
GS - Galvanised Steel
ha - Hectare
HDPE - High Density Polyethylene
HP - Horsepower
km - kilometer
Ksh. - Kenya Shilling
KVA - kilo Volt Ampere
lps - litres per second
m - metre
m2
- square metre
Coast Development Authority
m3
- cubic metre
me/l - milliequivalent per litre
mg/l - milligrams per litre
mm - millimeter
mm/h - millimeter per hour
m/s - metre per second
mS/cm - milliSiemems per centimetre
No. or nr - Number
PE - Polyethylene
PE 63 Class 2 - 63 mm diameter Polyethylene Class 2
SAR - Sodium Adsorption Ratio
TDS - Total Dissolved Solids
µPVC - Un-plasticized Polyvinyl Chloride
µPVC 110 A - 110 mm diameter Un-plasticized Polyvinyl Chloride Class A
List of Symbols
o - Degree
Ø - Diameter
≈ - approximately
“ - inch
% - per cent
Coast Development Authority
CHAPTER 2 DESIGN OF IRRIGATION COMPONENT
2.1 INTRODUCTION
The irrigation systems design for the various sites within Lake Challa Integrated Water
Resources Development Project include the following components:
Estimation of crop and irrigation water requirement
Availability of Irrigation Water
Efficient Irrigation Water Distribution Systems
2.2 GENERAL
Irrigation is generally defined as the artificial application of water to the soil to supplement
natural rainfall in supplying the moisture essential for plant growth. Irrigation is desirable
where natural rainfall does not meet the plant water requirements for all or part of the year.
The most positive impact of irrigation compared to rain-fed agriculture is the improved food
security, followed by a rise in income, wellbeing, and empowerment.
2.3 EVAPOTRANSPIRATION
Evapotranspiration is the loss of water through the combined effort of evaporation from the
soil surface and transpiration from the crop. Weather parameters, crop characteristics,
management and environmental conditions are the major factors affecting evaporation and
transpiration.
The principal weather parameters affecting evapotranspiration are radiation, air temperature,
humidity and wind speed. The crop type, variety and development stage also affect the rate of
evapotranspiration.
Management and environmental factors such as soil salinity, poor land fertility, limited
application of fertilizers, the presence of hard or impenetrable soil horizons, the absence of
control of diseases and pests and poor soil management may limit the crop development and
reduce the evapotranspiration.
2.3.1 Evaporation
Evaporation is the process whereby liquid water is converted to water vapour and
subsequently removed from the evaporating surface. Apart from the water availability in the
topsoil, the evaporation from a cropped soil is mainly determined by the fraction of the solar
radiation reaching the soil surface. This fraction decreases over the growing period as the
crop develops and the crop canopy shades more and more of the ground area. When the crop
is small, water is predominately lost by soil evaporation, but once the crop is well developed
and completely covers the soil, transpiration becomes the main process.
Coast Development Authority
2.3.2 Transpiration
Transpiration is the process by which plants remove moisture from the soil and release it to
the air as vapour. It consists of the vapourisation of liquid water contained in plant tissues and
the vapour removal to the atmosphere.
Crops predominately lose their water through stomata which are small openings on the plant
leaf.
2.4 THE PROJECT AREA
2.4.1 General Climatic Data
2.4.1.1 DATA COLLECTION
Meteorological data was mainly acquired from Taveta Water Development Station of the
Ministry of Water and Irrigation. However, data for the sunlight hours is based on the
guidelines provided by the FAO (Food and Agricultural Organization) irrigation and
Drainage Paper No. 56.
2.4.1.2 TEMPERATURES, EVAPORATION AND HUMIDITY
The mean monthly maximum and minimum temperatures vary between 27.4 to 33.1C, and
13.5 to 18.4C, respectively. The daily evaporation varies from 4.35 to 6.25 mm per day. The
coldest period is between June and September while the hottest months are October, January,
February and March (Table 2.1).
The average annual open water surface evaporation and relative humidity are estimated to be
1930 mm and 61%, respectively.
2.4.1.3 RAINFALL
The total annual rainfall is about 673 mm. In general the project area has a bi-modal rainfall
pattern as it experiences two rain seasons; the long rains between the months of March and
May and the short rains between November and December.
The rainfall pattern presented in Figure 2.1, below, distinctly shows the occurrence of long
and short rainy seasons in the project area.
Coast Development Authority
Figure 2.1- Annual Rainfall Pattern in the Project Area
2.4.1.4 SUMMARY OF CLIMATIC DATA
In general, the rainfall is very erratic in terms of amount and distribution and hence is not
reliable for successful production of crops. The mean annual pan evaporation is 1930 mm is
three times higher than the annual rainfall of 673 mm. Therefore, irrigation is necessary for
the development of agricultural production.
A comparison between the average rainfall and evaporation is graphically shown in Figure
2.2 below.
Figure 2.2– Comparison of Rainfall and Evaporation
Coast Development Authority
The long term mean monthly temperature, evaporation, relative humidity, wind speed,
sunshine hours and rain data for Taveta Town, which could be considered as representing the
project area climate characteristics, are given in the table below.
Table 2.1 - Mean Monthly Climatical Data for Taveta District
Month Temp.
(Max)
(0C)
Temp.
(Min)
(0C)
Open Water
Surface
Evaporation
(mm/day)
Relative
Humidity
(%)
Daily Wind
Run
(km/day)
Sunshine
hours
(h)
Mean
Rainfall
(mm)
Jan 32.4 16.2 5.65 57.5 195 12.2 57
Feb 33.0 17.0 6.25 56.5 178 12.1 42
Mar 33.1 17.9 5.65 59.5 148 12.0 95
Apr 30.6 18.4 5.00 68.0 103 11.9 143
May 28.8 17.3 4.52 67.5 106 11.8 64
Jun 27.7 15.8 4.50 62.5 126 11.8 19
Jul 27.4 15.1 4.35 61.0 123 11.8 12
Aug 27.6 15.0 4.68 61.5 105 11.9 12
Sep 29.4 13.5 5.50 58.0 118 12.0 12
Oct 31.5 16.9 5.97 52.0 134 12.1 21
Nov 31.6 18.2 5.83 60.0 160 12.2 120
Dec 31.5 18.0 5.65 70.0 195 12.2 76
Total/Average 30.4 16.6 5.28 61.2 141 12.0 673
2.4.2 Project Sites
Six sites were identified as being suitable for development of irrigation projects based on the
following aspects:-
Agricultural suitability
Soil profile
Flooding conditions
Topography of the site
2.4.2.1 KILANGA
The Kilanga area is situated next to Lake Challa and falls between Taveta- Loitoktok road to
the east and Kenya-Tanzania international border to the west and is currently occupied by
about 120 households. Much of the land is used for farming and rearing of animals.
However, most of the parcels near the international boundary are vacant. A demonstration
plot measuring 140 ha has been identified out of which 100 ha would be used to set up a
demonstration farm, leaving the rest for other uses – reservoir, adminstration block,
processing and value addition facilities etc. About 115 land owners will be affected by the
acquisition of the demonstration plot.
Coast Development Authority
This proposed irrigation scheme is located in an alluvial plain west of Challa market. The
area is flat to very gently undulating with slopes ranging from 0.5 to 2% towards the west.
The area is low lying without an obvious drainage system but ultimately excess water drains
into Lumi River.
The soils are well drained, extremely deep, very dark reddish brown clays with weak
prismatic structure breaking into moderate to weak fine sub-angular blocky structure. The
topsoil is dark brown clay. These soils are slightly acid to medium alkaline and are non-
saline. Available physical and chemical characteristics indicate that the soils are well suited
for irrigation on the account of their very favourable chemical and physical characteristics.
2.4.2.2 CHALLA IRRIGATION SCHEME
The Challa site is located in an alluvial plain North- west of Challa market and about 20 km
north east of Lake Challa.
This is an existing irrigation scheme of approximately 1,680 Ha and is owned by the Challa
Co-operative Society whose members own plots in the range of 4 and 6 acres. It relies on
water supplied from the Lumi River to supplement rainfed irrigation. The farmers are,
however, demanding more water to compensate for a critical decrease in the volume of water
flowing in the Lumi.
The area is flat with slopes ranging from 0.5 to 1% towards the North. The area is low lying
with slow surface drainage into Lumi River. Soils of the area are extremely deep, brownish
black clays.
There are no settlements within the scheme but people are settled within the surrounding
areas. Though the area is secured by means of fencing, it is prone to human/wildlife conflict.
2.4.2.3 NAKRUTO
This area is located on the eastern slopes of Challa crater. The area is undulating with slopes
ranging from 5 to10% towards the east. The area is drained by Lumi River and its seasonal
tributary, Kirimeri River. The vegetation in the area is wooded grassland most of which is
used for cultivation or grazing.
Soils of the area are developed on volcanic ash and are well drained, very shallow to
moderately deep, dark reddish brown clays and are chemically good for agricultural purposes.
2.4.2.4 TIMBILA
The Timbila site is located approximately 12 km south of Lake Challa and 4 km east of
Taveta Town. The area is demarcated by Taveta – Voi Road to the south, the railway line to
the north,Lumi River to the west and the Road to Ziwani Sisal Estate to the east
The area has a gentle north-south slope of about 1% and there is a significant topographical
height difference of about 100 m between the site and Lake Challa.
The area covered is about 2,500 acres, with a population of approx. 300 households and the
average land size ranges between a quarter (¼) and five (5) acres, although there are some
larger plots of 18 acres. Some of the households are involved in farming and livestock
Coast Development Authority
keeping. The land sizes held by the people are generally small, thus the area is densely
populated.
The area is flat to very gently undulating with slopes ranging from 0.5 to 2% towards South
east. The area is drained by the perennial Lumi River. The original vegetation in the area is
riverline forest which has been cleared for human settlement and cultivation. Farmers
produce rain fed food crops and horticultural crops under irrigation.
Soils of the area are well drained, extremely deep, dark reddish brown silt loam to clay. The
topsoil is dark brown clay and is moderately saline. High salinity occurs only in the topsoil
leading to the suspicion that the soils are being salinized through irrigation with water from
River Lumi. Based on physical and chemical characteristics, the soils are well suited for
irrigated agriculture and are currently under furrow irrigation. However they have high
porosity and low bulk density leading to high infiltration rates and internal permeability.
2.4.2.5 JIPE
The Jipe Settlement Scheme is located approximately 10 km southeast of Timbila and
stretches from Voi-Taveta road to the northern shores of Lake Jipe in the south and borders
Tsavo West National Park to the east and has an area is about 10,000 ha.
The area was designated by the Kenyan Government as part of a new rural development area
and was subdivided into several plots to individuals ranging from 15 to 25 acres. There are
about 600 households resident in the scheme but most of the plots are yet to be settled.
The area is woodland currently being used for grazing. Wildlife-human conflicts were
common here in the past but have now reduced significantly since an electric fence was
erected by the Kenya Wildlife Services.
The topography is flat to very gently undulating with slopes ranging from 0 to 2% towards
South and South west. The area is drained by the Lumi River.
Based on their physical and chemical characteristics, the soils on the upper part of the scheme
are suitable for irrigation, but are susceptible to gully erosion. As noted in Section 2.4.2.5 of
this report, the soils in the scheme are susceptible to gully erosion. There are two major
gullies draining the waters from Salaita Hills and Tsavo West National Park to Lake Jipe.
2.4.2.6 MWAKTAU
Mwaktau is located approximately 50 km from Timbila site (about halfway between Taveta
and Voi by road) and has a population of about 10,000 people.
This proposed irrigation area will be located about 400 m east of Mwaktau Secondary School
along Mwaktau-Msorongo road on the Tsavo Plain. The area is flat to very gently undulating
with slopes ranging from 0.5 to 2% towards East and South east. The area is drained by a
seasonal stream on the eastern border.
Soils of the area are well drained to excessively drained, extremely deep, red to dark reddish
brown sandy clay loam to clay with ‘murrum’ starting at depths of 80-110cm. The topsoil is
reddish brown to dark reddish brown sandy clay loam to sandy clay. The physical and
chemical characteristics of these soils indicate that they are suitable for irrigation.
Coast Development Authority
2.4.3 Soils in the Project Area
2.4.3.1 INTRODUCTION
Soils play an important role in plant growth because they are a source of nutrients and water.
Soils determine the suitability of the land for irrigation by influencing rooting depth for
crops, aeration status, nutrients availability, salinity and sodicity.
The soil physical and chemical characteristics are important in the determination of the
suitability of land for irrigation. The findings of the studies carried out during the Feasibility
Study stage are summarised below.
2.4.3.2 SOIL PHYSICAL CHARACTERISTICS
Texture
Soil texture refers to its composition in terms of the sizes of soil particles. The texture of a
soil has an influence on several important soil characteristics including infiltration rate and
available water capacity and may be broadly classified as below;
a. Coarse textured soils - sand predominant - "sandy soils
b. Medium textured soils - silt predominant - "loamy soils"
c. Fine textured soils - clay predominant - "clayey soils"
The depth of soil is particularly important where water harvesting systems are proposed.
Deep soils have the capacity to store the harvested runoff as well as providing a greater
amount of total nutrients for plant growth.
Bulk Density
Soil bulk density is an indicator of the packing of soil particles and it influences the amount
of water retention and transmission. Soil bulk density changes in response to management. It
is influenced by land use, especially in the surface horizons.
Hydraulic Conductivity
Hydraulic conductivity is a measure of the ease with which water moves through a soil. It is
determined by size and continuity of water filled pores. Saturated hydraulic conductivity,
Ksat, is an indication of the ability of pores to conduct water maximally when water is not
limiting and describes water movement through saturated soil.
Saturated soil hydraulic conductivity plays an important role in soil drainage i.e. removal of
excess water and salts. Table 2.2 gives the classification of soils in relation to the saturated
soil hydraulic conductivity.
Coast Development Authority
Table 2.2 - Saturated Hydraulic Conductivity Classification
Classification Saturated Hydraulic Conductivity (mm/h)
Extremely slow 4.167E-05
Very slow 0.0041667
Slow 0.42
Moderate 41.67
Fast 416.67
Very fast 4166.67
Soil Water Infiltration Rate
The infiltration rate is the velocity or speed at which water enters into the soil. It is usually
measured by the depth (in mm) of the water layer that can enter the soil in one hour. In dry
soil, water infiltrates rapidly. This is called the initial infiltration rate. As more water replaces
the air in the pores, the water from the soil surface infiltrates more slowly and eventually
reaches a steady rate. This is called the basic infiltration rate.
The infiltration rate depends on soil texture (the size of the soil particles) and soil structure
(the arrangement of the soil particles) and is a useful way of categorizing soils from an
irrigation point of view. A very low infiltration rate can be detrimental because of the
possibility of waterlogging in the cultivated area. The soils of the cropped area should,
however, be sufficiently permeable to allow adequate moisture to the crop root zone without
causing waterlogging problems.
The infiltration rate of a soil depends primarily on its texture. Typical comparative figures of
infiltration rates are as given below;
Table 2.3 -Basic Infiltration Rates for Various Soil Types1
Soil Type Basic infiltration Rate (mm/h)
Sand more than 30
Sandy Loam 20- 30
Loam 10- 20
Clay Loam 5 - 10
Clay 1 -5
A summary of the physical characteristics of soils in various sites is given in Table 2.4.
Table 2.4 - Physical Characteristics of Soils in Taveta District2
1 Ministry of Water and Irrigation, 2005 .Practice Manual for Water Supply Services in Kenya: Part B. Irrigation
2 Feasibility Study and Preliminary Design -Lake Challa Water Resources Integrated Development
Project- August 2011
Coast Development Authority
2.4.3.3 SOIL CHEMICAL CHARACTERISTICS
Salinity/Sodicity
A salinity problem exists if salt accumulates in the crop root zone to a concentration that
causes a loss in yield. In irrigated areas, these salts often originate from a saline, high water
table or from salts in the applied water. Yield reductions occur when the salts accumulate in
the root zone to such an extent that the crop is no longer able to extract sufficient water from
the salty soil solution, resulting in a water stress for a significant period of time. If water
uptake is appreciably reduced, the plant rate of growth is slowed down.
Salts that contribute to a salinity problem are water soluble and readily transported by water.
Salt content of the root zone varies with depth. It varies from approximately that of the
irrigation water near the soil surface to many times that of the applied water at the bottom of
the rooting depth. Salt concentration increases with depth due to plants extracting water but
leaving salts behind in a greatly reduced volume of soil water.
Sodic soils, which have a high exchangeable sodium percentage and saline soil which have
excess soluble salts, should be avoided for irrigation systems. These soils can reduce
moisture availability directly, or indirectly, as well as exerting direct harmful influence on
plant growth.
Classification
Salinity in a soil influences different plants differently and classification for suitability needs
to be plant specific. However, a general indication of salinity and sodicity for some sites is
shown in Table 2.5.
Area
Depth
(mm)
Preliminary
Classification
Bulk
Density
(g/cm3)
Saturated
Hydraulic
conductivity
(mm/ h)
Conductivity
Class
Infiltration
Rate
(mm/ h)
Infiltration
Class
Kilanga
0-300
Chromic
CAMBISOLS
1.23
6.1
Very slow 72.6 Moderately
rapid
300-900 1.39 6.1 Very slow
Challa
0-300
Chromic
LUVISOLS
1.18
6.0
Very slow 56.1 Moderately
rapid
300-900 1.40 2.4 Very slow
Timbila 0-300 Chromic
CAMBISOLS 0.94 18.0 Slow 31.6 Moderate
300-900 1.41 0.6 Very slow
Jipe 0-300 Rhodic/ orthic 1.60 16.7 Slow 22.5 Moderate
300-900 FERRALSOLS 1.46 6.0 Very slow
Mwaktau 0-300 Rhodic/ orthic
FERRALSOLS 1.48 13.4 Slow 19.1 moderate
300-900 1.73 4.0
Very slow
Coast Development Authority
Table 2.5 – Salinity and Sodicity of Soils3
Area Salinity Sodicity
Kilanga Non-saline Non- sodic
Challa Severely saline Medium-sodic
Timbilla moderate Medium-sodic
Jipe Non-saline Non-sodic
2.4.3.4 SOIL WATER
Available Water Capacity (AWC)
Soil water influences plant growth and crop production. The water in the soil is from
precipitation, irrigation or groundwater. It is either taken up by plants, lost through direct soil
evaporation or deep drainage beyond the rooting zone.
The capacity of soils to hold, and to release adequate levels of moisture to plants are vital to
irrigation. AWC is a measure of this parameter, and is expressed as the depth of water in mm
readily available to plants after a soil has been thoroughly wetted to "field capacity".
Field capacity refers to the water content in a field soil after the drainage rate has become
small and it is an estimate of the amount of water that may be temporarily stored in the soil
profile for plant use. On the other hand, the permanent wilting point or percentage is the soil
water content below which plants growing in that soil remain wilted even when transpiration
is nearly eliminated.
The amount of water released by the soil between field capacity and permanent wilting is
called the available water.
Generally, the available water for various types of soils is given as4;
Heavy textured soil : 200 mm/m
Medium textured soil : 140 mm/m
Coarse textured soil : 60 mm/m
The relationship between soil water potential and the amount of water in the soil (on the basis
of volumetric water) was determined during the Feasibility Study Stage. The values for the
volumetric water content of soils in potential irrigation sites are summarised in Table 2.6.
3 Feasibility Study and Preliminary Design -Lake Challa Water Resources Integrated Development
Project- August 2011
4 Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Table 2.6 - Values for Volumetric Water Content of Soils in Taveta District
Site
Volumetric water content (cm3/cm
3) Available water
Soil layer
(mm)
Available
water
content
at field
capacity
Water
content at
permanent
wilting
point
Available
water
capacity
In layer
(mm)
In profile
(total mm/m)
Kilanga 0-300 0.25 0.017 0.24 7.2 117
300-900 0.16 0.014 0.15 4.5
Challa 0-300 0.28 0.012 0.27 8.1 177
300-900 0.33 0.012 0.32 9.6
Kilanga 0-300 0.25 0.017 0.24 7.2 117
300-900 0.16 0.014 0.15 4.5
Timbila 0-300 0.4 0.017 0.39 11.7 204
300-900 0.3 0.011 0.29 8.7
Jipe 0-300 0.19 0.011 0.18 5.4 126
300-900 0.25 0.007 0.24 7.2
Mwaktau 0-300 0.36 0.006 0.35 10.5 189
300-900 0.29 0.006 0.28 8.4
The soils with highest and lowest available soil water were at Timbila and Kilanga,
respectively.
2.4.3.5 SUMMARY OF SOILS SUITABILITY FOR IRRIGATION
The suitability of the various soils for irrigation purposes is summarised and tabulated below;
Table 2.7– Soils Suitability for Irrigation
Area Remarks
Kilanga The soils are well suited for irrigation on the account of their very
favourable chemical and physical characteristics.
Challa
Soils are well suited for irrigation due to their lack of salinity, high
fertility and good physical properties.
Nakuruto
Soils not suited for irrigation due to their very shallow depth in spite of
having good chemical properties.
Timbila
Based on the available physical and chemical characteristics, the soils
are suited for irrigation.
Jipe The soils in the upper areas are well drained and are irrigable. However,
the soils close to the lake have high salinity and sodicity levels, and
would not be easy to drain.
Mwaktau Based on the available physical and chemical characteristics, the soils
are suited for irrigation.
Coast Development Authority
2.4.4 Quality of Irrigation Water
2.4.4.1 GENERAL
The suitability of water, from quality point of view, is determined by its potential to cause
problems and its relation to the special management practices needed.
The quality of irrigation water influences various aspects of irrigation; including infiltration
rates, salinity and sodicity of soil which affects crop yields and land productivity. It is
therefore imperative to assess water quality to ascertain its quality for irrigation. The criteria
mostly used for rapid assessment includes electrical conductivity (ECw) and sodium
adsorption ratio (SAR) of the water intended for irrigation.
2.4.4.2 INFILTRATION
Infiltration problem related to water quality occurs when the rate of water infiltration into and
through the soil is reduced (because of water quality) to such an extent that the crop is not
adequately supplied with water and yield is reduced. A low infiltration rate makes it more
difficult to supply the crop with adequate water and may greatly add to cropping difficulties
through crusting of seed beds, waterlogging of surface soil and accompanying diseases,
salinity, weed, oxygen and nutritional problems.
Infiltration problems are evaluated through the following parameters;
Total salts in the water (ECw):
Total salts in water are indicated by the electrical conductivity of the water (ECw).
Low salt content in water causes low soil infiltration due to the tremendous
capacity of pure water to dissolve and remove calcium and other solubles in the
soil.
Sodium Adsorption Ratio (SAR) is the relative content of sodium to calcium and
magnesium in the water.
Where: Na, Ca and Mg represent the concentration in milli-equivalents per litre
(Me/l).
The SAR determines the exchangeable sodium (ESP) of a soil. A high ESP defines a soil
which has a high degree of saturation with exchangeable sodium – or an alkali soil.
Carbonates and bicarbonates can also affect infiltration and must be evaluated.
Bicarbonates and carbonates in irrigation water increase the potential for problem by reacting
with soil calcium and magnesium to form insoluble compounds. Removing calcium and
magnesium from soil creates room for sodium to accumulate on the soil colloids.
Coast Development Authority
The above three factors interact in determining the long-term influence of water on the soil
infiltration rate.
2.4.4.3 SALINITY
Salinity problem occurs in soils when the total quantity of salts in the irrigation water is high
enough for the salts to accumulate in the crop root zone to the extent that yields are affected.
Excessive soluble salts in the root zone inhibit water uptake by plants. The plants suffer from
salt-induced drought. Plants respond more critically to salinity in the upper part of the soil
profile than to the salinity levels at depth.
2.4.4.4 TOXICITY
Toxicity problem occurs when harmful ions in the water are taken up by the crop and
accumulate in amounts that reduce crop yield. In arid and semi-arid areas the toxic specific
ions in water include boron, chloride and sodium.
2.4.4.5 MISCELLANEOUS
Various other problems may occur including excessive nitrogen in the water supply, white
deposits on fruit due to high bicarbonate in sprinkler applied water, and suspected
abnormalities indicated by water with unusual pH.
2.4.4.6 GUIDELINES ON CLASSIFICATIONS SUITABILITY OF IRRIGATION WATER
The criteria for assessing the suitability of irrigation water as recommended by FAO and
shown in Table 2.8 was used to classify suitability of the three main sources of irrigation
water in the Taveta area.
Table 2.8 - Guidelines for Interpretation of Water Quality for Irrigation5
Potential Irrigation Problem Restriction on Use
Units None Slight to
Moderate
Severe
Salinity (affects crop water availability)
ECw dS/m <0.7 0.7 - 3.0 >3.0
TDS mg/l <450 450 - 2 >2 000
Infiltration (affects infiltration rate of water into
the soil. Evaluate using ECw and SAR together)
SAR =0-3 and ECw
= 3 - 6 = >1.2 1.2 - 0.3 <0.3
= 6 - 12 = >1.9 1.9 - 0.5 <0.5
= 12 - 20 = >2.9 2.9 - 1.3 <1.3
= 20 - 40 = >5.0 5.0 - 2.9 <2.9
Specific Ion Toxicity (affects sensitive crops)
Sodium (Na)
Surface irrigation SAR <3 3 - 9 >9
Sprinkler irrigation me/l <3 >3
5 Adapted from University of California Committee of Consultants, 1974
Coast Development Authority
Chloride (Cl) V
Surface irrigation me/l <4 4 - 10 >10
Sprinkler irrigation me/l <3 >3
Boron (B) mg/l <0.7 0.7 - 3.0 >3.0
Miscellaneous Effects (affects susceptible crops)
Nitrogen (NO3-N) mg/l <5 5 - 30 >30
Bicarbonate (HCO3) (overhead sprinkling only) me/l <1.5 1.5 - 8.5 >8.5
pH (Normal Range 6.5 - 8.4)
Notes:
1. ECw means electrical conductivity, a measure of the water salinity, reported in
deciSemens per metre at 25°C (dS/m).
2. TDS means total dissolved solids, reported in milligrams per litre (mg/l).
3. 1SAR means sodium adsorption ratio. SAR is sometimes reported by the symbol Tte. At
a given SAR, infiltration rate increases as water salinity increases. Evaluate the potential
infiltration problem by SAR as modified by EC. Adapted from Rhoades 1977; and Oster
and Schroer 1979
4. NO3-N means nitrate nitrogen reported in terms of elemental nitrogen. (NH4-N and
Organic-N should be included when wastewater is being tested).
Chemical and physical characteristics of water from the proposed water sources are shown
Table 2.9.
Table 2.9 - The pH and ECw of Water from the Proposed Sources
Parameter
Water Source
Lake Challa
Challa Irrigation
Scheme Borehole
Nakuruto
Borehole
pH 8.19 8.13 7.62
Electrical Conductivity
mS/cm 0.26 0.27 0.26
Sodium (me/l) 0.56 0.56 0.46
Potassium (me/l) 0.06 0.06 0.03
Calcium (me/l) 2.06 1.93 3.50
Magnesium (me/l) 1.58 1.21 1.27
Carbonates (me/l) Not Detected Not Detected Not Detected
Bicarbonates (me/l) 4.34 4.35 4.05
Chlorides (me/l) 3.50 3.75 3.38
Sulphates (me/l) 0.42 0.35 2.19
Sodium Adsorption Ratio 0.42 0.45 0.30
2.4.4.7 SUMMARY OF WATER QUALITY
The water quality is satisfactory and suitable for irrigation purposes and can be used on most
soils and crops.
Coast Development Authority
2.5 CURRENT AGRICULTURAL PRODUCTION
2.5.1 AGRICULTURE AND LAND USE
Agriculture is the mainstay of majority of rural communities in Kenya and as such, people in
Taveta derive their livelihoods directly or indirectly from agriculture.
The agricultural potential of the arable land in the district is estimated to be 33,550 ha. The
area under cultivation is estimated to be 9,721 ha out of which 3,943 ha is under irrigation.
About 356,160.7 ha of land is covered by the National Park and forests.
The major land uses in the Lake Challa project area are subsistence rain-fed agriculture and
livestock keeping. Due to the harsh climatic conditions livestock production systems are
more extensively practiced than crop production. This is also aggregated by crop invasion by
wildlife particularly elephants. Other land uses include forest cover, bush land.
2.5.2 CROP PRODUCTION
Crop production in Taveta and Mwatate Districts is dominated by:
Food crops, which comprise cereals, pulses and root crops;
Horticultural crops, which include vegetables, fruits and fruit trees; and
Industrial crops, which include the factory processed crops such as sunflower, sisal
and tobacco.
Crop production is largely dependent on rainfall with a few acreages of horticultural crops
under irrigation. The major cropping season is the long rains and farming systems are
characterized by low levels of input use and are labour intensive.
Table 2.10 gives the statistics food crop production in Taveta District during the- 2009/2010
financial year.
Table 2.10 - Food Crop Production Statistics, Taveta District- 2009/2010
Crop
LONG RAINS
(2009 crop)
SHORT RAINS
(2009/10 crop)
Total
(ha) Yield/ha Total
Production
Area
(ha)
Target
Yield /ha
Total
Production
Maize 1,071 18 20, 992 3,115 18 25,330 46,322
Sorghum 40 10 400 16 0 0 400
Rice 178 8 1,680 107 8 886 2,566
Millet 22 10 160 0 0 0 160
Beans 337 8 3,200 335 8 2,037 5,237
Pigeon
peas
22 8 176 1 8 2 178
Coast Development Authority
Green
Grams
101 8 812 55 8 162 974
Cowpeas 117 8 1,448 39 8 154 1,601
Sweet
Potatoes
21 12 253 5 12 59 312
Cassava 39 12 451 21 12 181 632
Arrow
roots
11 12 128 4 12 20 147
Source: Farm Management Guidelines, Taveta District, 2009/2010
From the table above, it is evident that the yields of most crops are low compared to the
potential/ recommended yields. The low crop yields could be attributed to among others lack
of water and harsh climatic conditions.
2.5.3 CONCLUSIONS
The present agricultural production is largely under rain-fed conditions. The rainfall is not
sufficient to meet the water requirement of crops and this result in extremely low crop yields.
Irrigation farming is, therefore, the most reliable source of livelihood in the District.
2.6 PROPOSED CROPPING PATTERN FOR PROJECT AREA
Water availability, climate and type of crops grown at present are considered as key factors in
determining the proposed cropping pattern for the project area. Other factors such as farmers’
preference, labour availability during peak season, cash requirement, market conditions and
the likes were also considered in the determination of cropping pattern.
The following selection criteria were taken into consideration for determining the cropping
pattern for the project area.
Adaptability of the crops to the general conditions of soil and climate of the
area.
Intended objectives of the project which among others include :
- To bring about a state of sustainable food security in the target area in
particular and the whole region in general.
- Promote the production of high value and market oriented crops.
- Promote increased production of industrial and export crops
Availability of improved production technologies.
Existing market demand around the project area and in the neighbouring areas
in general.
Based on the results of an agro-economic baseline survey undertaken by the Consultants,
during which various agronomic and socio-economic issues were considered, major and
minor existing and proposed irrigated food security and commercial crops were accordingly
Coast Development Authority
ranked. In addition, recommendations were sought from various stake holders. The list of
crops and acreages to be considered under irrigated agriculture is presented in the Table 2.11
below.
Table 2.11 - Proposed Overall Cropping Pattern
Season Type of
Crop
Area
(ha)
%
Area
Individual
Crops
Irrigated Area
per Season
(ha)
% Area
Season One
(March to
July
Cereal 190 19 Maize 190 19
Legumes
165
17
Beans 60 6
Green Grams 45 4
Cowpeas 60 6
Vegetables
285
28
Tomatoes 40 4
Kales 35 3
Water Melons 50 5
Onions 110 11
Chillies 50 5
Fruits
330 32
Bananas 185 18
Pawpaws 145 14
Oil Crop 40 4 Sunflower 40 4
Sub-total 1,010 100 1,010 100
Season Two
(September
to January)
Cereal 190 19 Maize 190 19
Legumes
165
17
Beans 60 6
Green Grams 45 4
Cowpeas 60 6
Vegetables
285
28
Tomatoes 40 4
Kales 35 3
Water Melons 50 5
Onions 110 11
Chillies 50 5
Fruits
330 32
Bananas 185 18
Pawpaws 145 14
Oil Crop 40 4 Sunflower 40 4
Sub-total 1,010 100 1,010 100
TOTAL 2,020 100 2,020 100
Coast Development Authority
Table 2.12- Proposed Cropping Pattern by Project Areas
Season Crop Area (ha) Total
Kilanga
Pilot
Scheme
Challa
Scheme
Nakuruto Timbila
Scheme
Jipe
Scheme
Mwaktau
Scheme
(ha)
Season
One
(March
to July
Maize - 20 10 20 100 40 190
Beans - - - - 45 15 60
Green
grams - -
- - 30 15 45
Cowpeas - 10 5 10 20 15 60
Tomatoes 20 10 10 - - 40
Kales 10 10 5 10 - - 35
Sunflower - - - - 25 15 40
Bananas 20 10 5 10 100 40 185
Melons 10 10 5 10 10 5 50
Pawpaws 20 10 5 10 75 25 145
Onions 10 10 5 10 50 25 110
Chillies 10 10 5 10 10 5 50
Sub-total 100 100 45 100 465 200 1,010
Season
Two
(Sept’
to Jan)
Maize - 20 10 20 100 40 190
Beans - - - - 45 15 60
Green
grams - -
- - 30 15 45
Cowpeas - 10 5 10 20 15 60
Tomatoes 20 10 10 - - 40
Kales 10 10 5 10 - - 35
Sunflower - - - - 25 15 40
Bananas 20 10 5 10 100 40 185
Melons 10 10 5 10 10 5 50
Pawpaws 20 10 5 10 75 25 145
Onions 10 10 5 10 50 25 110
Chillies 10 10 5 10 10 5 50
Sub-total 100 100 45 100 465 200 1,010
TOTAL 200 200 90 200 930 400 2,020
2.7 IRRIGATION METHODS
There are three methods of irrigation commonly practiced in the country;
Surface Irrigation
Sprinkler Irrigation
Drip (Trickle Irrigation)
Coast Development Authority
2.7.1 Surface Irrigation
Surface irrigation refers to a broad class of irrigation methods in which water is distributed
over the field by overland flow. A flow is introduced at one edge of the field and covers the
field gradually. The rate of coverage (advance) is dependent almost entirely on the
differences between the discharge onto the field and the accumulating infiltration into the
soil.
In surface irrigation systems, water moves over and across the land by simple gravity flow in
order to wet it and to infiltrate into the soil. Surface irrigation can be used for all types of
crops and may be commonly classified into furrow, border-strip or basin irrigation.
2.7.1.2 Furrow Irrigation
Furrows are small, parallel channels, made to carry water in order to irrigate the crop. The
crops are usually grown on the ridges between the furrows which must be carefully dug to
ensure an even distribution of water. Water is applied to the upper end of each furrow and
flows down the furrow with water infiltrating into the beds or ridges between the furrows on
which the crop is grown.
The flow of water into a furrow should be large enough to reach the end, but small enough
not to cause erosion, flooding or excessive tail losses. The size of the flow must be adjusted
to the infiltration rate of the soil, land slope, furrow length, erosion hazard and depth to be
applied. Depending on available water, and skill of irrigator, several furrows are irrigated at
the same time.
2.7.1.3 Basin Irrigation
Water is applied from a small canal by gravity to fill a level basin surrounded by earth buds.
The design is based on rapid application of water over the entire basin at a rate of least 2 to 4
times the infiltration rate of the soil6. The method is suitable for very flat and level land and
soils with low infiltration rates.
The cultivation of paddy rice is normally done using basin irrigation.
2.7.1.4 Border Strip Irrigation
Borders are usually long, uniformly graded strips of land, separated by earth bunds. In
Contrast to basin irrigation these bunds are not to contain the water for ponding but to guide
it as it flows down the field.
The field to be irrigated is divided into a number of level strips between ridges. Water is
applied from one end and, in flowing downslope, progressively covers the entire strip with a
thin sheet of water. Length and width of the strip depend on soil and land characteristics.
6 Civil Engineer’s Reference Book – Fourth Edition (Blake, L. S.)
Coast Development Authority
2.7.2 Sprinkler Irrigation
In the sprinkler method of irrigation, water is sprayed into the air and allowed to fall on the
ground surface, somewhat resembling rainfall. Water is distributed through a system of pipes
and then sprayed into the air through sprinklers so that it breaks up into small water drops
(between 0.5 and 4.0 mm in size) which fall to the ground. The spray is developed by the
flow of water under pressure through small orifices or nozzles.
The small drops fall close to the sprinkler whereas the larger ones fall close to the edge of the
wetted circle. Large drops can damage delicate crops and soils and so in such conditions it is
best to use the smaller sprinklers. Drop size is also controlled by pressure and nozzle sizes.
When the pressures are low, drops tend to be much larger as the water jet does not break up
easily.
Sprinkler irrigation can be used for almost all crops (except rice and jute) and on most soils. It
is, however, not usually suitable in very fine textured soil (heavy clay soils), where the
infiltration rates are very low, less than about 4 mm/h, and is particularly suited to sandy soils
that have a high infiltration rate.
Sprinkler irrigation is suited for most row, field and tree crops and water can be sprayed over
or under the crop canopy. Sprinkler irrigation is adaptable to any farmable slope, whether
uniform or undulating.
The application of water by overhead sprinklers takes many forms which include the
following.
1. Permanent and Solid Set
This consists of a network of pipes and sprinklers which covers the whole area to be
irrigated. This is the most expensive form of sprinkler irrigation.
2. Lateral Move Sprinklers
This consists of sprinklers on a lateral line that is moved by hand after each irrigation
application to the next area of irrigation to be irrigated. This is the most widely used system.
3. Traveller Systems
These are motorized methods of moving sprinklers and include:
Side roll - lateral pipe and sprinklers on wheels pushed by hand or small motor
from one position to the next irrigation position;
Mobile rain gun – single gun winched across field whilst irrigating and fed
from a hose reel;
Centre pivot – overhead lateral with sprinklers which rotates about centre
whilst irrigating;
Linear move – similar to centre pivot but moves laterally across the field.
The most common system in developing countries is the lateral move sprinkler system.
Coast Development Authority
Figure 2.3 – Typical Portable Lateral Move Overhead Sprinkler System
2.7.3 Drip (Or Trickle) Irrigation
Drip irrigation works by applying water slowly, directly to the soil. Water is delivered at or
near the root zone of plants, drop by drop to individual trees, groups of plants or plant rows
through a system of small diameter plastic pipes fitted with outlets called drippers or emitters,
placed on laterals delivering a flow of between 2 to 20 1/h each.
Water is applied close to plants so that only part of the soil in which the roots grow is wetted,
unlike surface and sprinkler irrigation, which involves wetting the whole soil profile.
Drip Irrigation is the most expensive, but most water-efficient, method.
2.8 CHOICE OF IRRIGATION METHOD(S)
The choice of an appropriate irrigation method is determined by the following factors;
a. Natural conditions
b. Type(s) of crop(s)
c. Type and level of technology
d. Previous experience with irrigation
e. Required labour inputs
Coast Development Authority
f. Costs and benefits.
2.8.1 Natural Conditions
The natural conditions such as soil type, slope, climate, water quality and availability, have
the following impact on the choice of an irrigation method.
Soil Type
On loam or clay soils all three irrigation methods can be used, but surface irrigation is more
commonly used.
Sprinklers are best suited to sandy soils with high infiltration rates although they are
adaptable to most soils. Sprinklers are not suitable for soils which easily form a crust. If
sprinkler irrigation is the only method available, then light fine sprays should be used. The
larger sprinklers producing larger water droplets are to be avoided.
Furrows can be used on most soil types. However, as with all surface irrigation methods, very
coarse sands are not recommended as percolation losses can be high. Soils that crust easily
are especially suited to furrow irrigation because the water does not flow over the ridge, and
so the soil in which the plants grow remains friable. Clay soils with low infiltration rates are
ideally suited to surface irrigation.
When a variety of different soil types is found within one irrigation scheme, sprinkler or drip
irrigation are recommended as they will ensure a more even water distribution.
Slope
Sprinkler or drip irrigation are preferred over furrow irrigation on steeper or unevenly sloping
lands as they require little or no land levelling. Sprinkler irrigation is adaptable to any
farmable slope, whether uniform or undulating. The lateral pipes supplying water to the
sprinklers should always be laid out along the land contour whenever possible. This will
minimize the pressure changes at the sprinklers and provide a uniform irrigation.
Uniform flat or gentle slopes are preferred for furrow irrigation. These should not exceed
0.5%. Usually a gentle furrow slope is provided up to 0.05% to assist drainage following
irrigation or excessive rainfall with high intensity.
On steeper sloping land, contour furrows can be used up to a maximum land slope of 3%. On
undulating land furrows should follow the land contours
Climate
Strong wind can disturb the spraying of water from sprinklers. Under very windy conditions,
drip or surface irrigation methods are preferred. In areas of supplementary irrigation,
sprinkler or drip irrigation may be more suitable than surface irrigation because of their
flexibility and adaptability to varying irrigation demands on the farm.
Coast Development Authority
Water Availability and Quality
Water application efficiency is generally higher with sprinkler and drip irrigation than surface
irrigation
Surface irrigation is preferred if the irrigation water contains much sediment. The sediments
may clog the drip or sprinkler irrigation systems.
A good clean supply of water, free of suspended sediments, is required to avoid problems of
sprinkler nozzle blockage and spoiling the crop by coating it with sediment
Low-quality water (high in salts) should not be used, unless filtered, due to potentially
devastating effects of clogged emitters. Also, the use of water high in soluble salts will result
in localized soil salinity buildup around plants, since drip irrigation is an ineffective leaching
method.
2.8.2 Type(s) of Crop(s)
Sprinkler and drip irrigation, because of their high capital investment per hectare, are mostly
used for high value cash crops, such as vegetables and fruit trees. They are seldom used for
the lower value staple crops.
Sprinkler irrigation is suited for most row, field and tree crops and water can be sprayed over
or under the crop canopy. However, large sprinklers are not recommended for irrigation of
delicate crops because the large water drops produced by the sprinklers may damage the crop.
Furrow irrigation is best used for irrigating the following crops:
Row crops such as maize and vegetables;
Crops that would be damaged by inundation, such as tomatoes, vegetables, potatoes,
beans;
Fruit trees such as citrus, mangoes, bananas
2.8.3 Type and Level of Technology
The type of technology affects the choice of irrigation method. In general, drip and sprinkler
irrigation are technically more complicated methods. The purchase of equipment requires
high capital investment per hectare. To maintain the equipment a high level of 'know-how'
has to be available.
Surface irrigation systems, in particular small-scale schemes, usually require less
sophisticated equipment for both construction and maintenance (unless pumps are used). The
equipment needed is often easier to maintain.
2.8.4 Previous Experience with Irrigation
The choice of an irrigation method also depends on the irrigation tradition within the region
or country. Introducing a previously unknown method may lead to unexpected complications.
It is not certain that the farmers will accept the new method. The servicing of the equipment
may be problematic and the costs may be high compared to the benefits.
Coast Development Authority
2.8.5 Required Labour Inputs
Furrow irrigation requires, regular maintenance and a high level of farmers' organization to
operate the system than sprinkler or drip irrigation systems
Sprinkler and drip irrigation require little land leveling and the systems operations and
maintenance are less labour-intensive.
2.8.6 Costs and Benefits
Sprinkler irrigation methods are more expensive than furrow irrigation, but are more efficient
at using water.
The drip irrigation method is the most water-efficient but the most expensive.
Construction/installation, operation and maintenance costs are compared with the expected
benefits (yields) to determine the most profitable method.
2.9 COMPARISONS OF VARIOUS IRRIGATION METHOD(S)
In order to choose an appropriate irrigation method(s), some of the advantages and
disadvantages of the various methods should be considered to determine the one which suits
the local conditions best. A comparison of the various irrigation methods, based on ten
important parameters, is presented in the table below.
Table 2.13 - Parameters Affecting the Choice of Irrigation Methods
No Parameter Surface Irrigation Sprinkler Irrigation Drip Irrigation
1 Initial
Investment
Cost
Relatively inexpensive
(where water costs are low)
method per given area.
These systems can be
developed at the farm level
with minimal capital
investment. The control and
regulation structures are
simple, durable and easily
constructed with
inexpensive and readily-
available materials like
wood, concrete, brick and
mortar, etc.
Initial cost per given
area is higher than
surface irrigation.
High water pressure
required (>25 m
head)
More expensive than
a more traditional
sprinkler system per
given area
2 Operations Surface systems tend to be
labour-intensive. Labour
engaged per irrigation is
higher than sprinkler and
drip.
Labour engaged per
irrigation is higher
than drip.
A drip irrigation
system can be
automated.
Labour required only
for starting and
stopping the system.
Coast Development Authority
3 Ground
Topograph
y
Not suitable for undulating
ground and slopes of more
than 3%.
Suitable for
undulating ground
and slopes of up to
16%
Suitable for steep/
undulating land.
Pressure
compensating emitters
are available, so the
field does not have to
be level.
Table 2.13 - Parameters Affecting the Choice of Irrigation Methods (continued)
No Parameter Surface Irrigation Sprinkler Irrigation Drip Irrigation
4 Land
Preparation
Perfect land smoothening
and levelling required.
(May be difficult to use on
irregular slopes as
considerable land levelling
may be required to achieve
the required land gradients).
Only land
smoothening is
required
Only land
smoothening is
required
5 Depth and
Porosity of
soil
Not suitable for shallow
and porous soils- Deep
percolation is more in light
soils while Runoff loss is
more in heavy soils.
Not suitable for coarse sand
(with an infiltration rate of
more than 30 mm/h)
Suitable for shallow/
deep and all types of
soils except fine
textured soils (heavy
clay soils), where the
infiltration rates are
less than about 4
mm/h.
Adaptable to nearly
all irrigable soils
since sprinklers are
available in a wide
range of discharge
capacity.
Suitable for shallow/
deep and all types of
soils as flow rates can
be controlled.
Table 2.13 - Parameters Affecting the Choice of Irrigation Methods (continued)
No Parameter Surface Irrigation Sprinkler Irrigation Drip Irrigation
6 Water Use
and
Application
efficiency
Losses occur due to
percolation, runoff,
and evaporation.
Application efficiency
of
50-60%
Higher water
application efficiency
(75-85%)
No channels for
conveyance, therefore
no conveyance loss.
Uneven water
distribution due to
high winds -difficulty
in irrigation during
wind in sprinkler
Evaporation loss when
operating under high
Runoff and deep
percolation losses are
minimal with an
application efficiency of
90-95%
Coast Development Authority
temperatures.
7 Weeds
Infestation
Weeds infestation is
very high.
Weeds infestation is
high.
Enhance weed control
by keeping much of the
soil surface dry.
8 Diseases
and Pests
Infestation
High Problems due to foliar
moisture-some
diseases can arise if
over watering occurs.
Relatively less because
of less atmospheric
humidity and reduced
contact of water with
crop leaves, stems, and
fruit.
Table 2.13 - Parameters Affecting the Choice of Irrigation Methods (continued)
No Parameter Surface Irrigation Sprinkler
Irrigation
Drip Irrigation
9 Quality of
water
Saline water cannot be
used for irrigation.
Saline water cannot
be used for
irrigation.
Frequent irrigation
avoids the built up of
salt concentration
within root zone by
pushing salts away
from root zone.
10 Application
of
Chemicals
(Fertilisers,
Herbicides,
Insecticides,
and
Fungicides
Not suitable for
application of agricultural
chemicals
Not suitable for
application of
agricultural
chemicals
Agricultural
chemicals(herbicides,
insecticides, and
fungicides can be
applied more
efficiently with drip
irrigation
(Fertigation)
2.10 PREFERRED IRRIGATION METHOD(S)
Based on the factors enumerated in sections 2.8 and 2.9 of this report, above, the following
observations and recommendations were made in the project areas;
1. Water application efficiency is generally higher with sprinkler and drip irrigation than
surface irrigation methods. The drip irrigation method is the most water-efficient but
the most expensive.
2. Sprinkler and drip irrigation, because of their high capital investment per hectare, are
mostly used for high value cash crops, such as vegetables and fruit trees. They are
seldom used for the lower value staple crops.
3. Sprinkler or drip irrigation methods are preferred over furrow irrigation on whether
uniform or undulating loping lands as they require little or no land levelling. On the
other hand while surface irrigation methods can be used for all types of crops, they
may be difficult to use on irregular slopes as considerable land levelling may be
required to achieve the required land gradients.
Coast Development Authority
4. The type of technology affects the choice of irrigation method. In general, drip and
sprinkler irrigation are technically more complicated methods. The purchase of
equipment requires high capital investment per hectare. To maintain the equipment a
high level of 'know-how' has to be available. The choice of an irrigation method also
depends on the irrigation tradition within the region. Introducing a previously
unknown method may lead to unexpected complications. It is not certain that the
farmers will accept the new method. Servicing of the required equipment may be
problematic and the costs may be high compared to the benefits. Surface irrigation
systems, in particular small-scale schemes, usually require less sophisticated
equipment for both construction and maintenance
5. The use of water high in soluble salts will result in localized soil salinity buildup
around plants, since drip irrigation is an ineffective leaching method. This method is
not recommended on any of the sites.
6. A combination of the drip and overhead sprinkler system is recommended for the
Kilanga Scheme. The fact that the farm is expected to be a pilot scheme which will be
managed by CDA who in a position to engage qualified personnel to operate and
maintain the required equipment.
7. For Nakuruto, Jipe and Mwaktau Schemes, the preferred method of irrigation would
be the furrow irrigation. The people in the region are already practicing it in the
nearby Challa and Timbila Schemes. Furthermore, the use of the overhead sprinkler
systems would incur additional capital, operational and maintenance costs. The initial
cost per given area is higher for sprinkler than surface irrigation as high water
pressure of at least 25 m head is required.
The preferred methods of irrigation for different proposed crops are given in Table 2.14
below;
Table 2.14 - Preferred Method(s) of Irrigation for Various Crops
Area Crop Mode of irrigation
Kilanga Pilot Project
Tomatoes Drip
Kales Sprinkler
Bananas Drip
Melons Sprinkler
Pawpaws Sprinkler
Onions Sprinkler
Chillies Sprinkler
Challa (Existing Scheme) All crops Surface (Furrow) Irrigation
Timbila(Existing Scheme) All crops Surface (Furrow) Irrigation
Jipe All crops Surface (Furrow) Irrigation
Mwaktau All crops Surface (Furrow) Irrigation
Coast Development Authority
2.11 CROP AND IRRIGATION WATER REQUIREMENTS
2.11.1 Crop Water Requirements (ETCROP)
2.11.1.2 DEFINITION
Crop water requirement, ETcrop, is defined as the depth of water required by the crop to meet
the water loss through evapotranspiration. The modified Penman Method (FAO paper No.56,
1998) is a globally accepted empirical method for estimating the crop water requirement
utilizing the available climatological data for a particular location. The Modified Penman
equation is given by;
ETcrop = ETO x KC…………………………………………………………………….. (1)
Where
ETcrop is the Crop water requirement (mm)
ETo is the Reference Evapotranspiration (mm) and
KC is the Crop Coefficient (dimensionless).
2.11.1.3 REFERENCE EVAPOTRANSPIRATION (ETo)
The evapotranspiration rate from a reference surface, not short of water, is called the
reference crop evapotranspiration or reference evapotranspiration. A large uniform grass field
with specific characteristics is considered worldwide as the reference surface. ETo expresses
the evaporating power of the atmosphere at a specific location and time of the year and does
not consider the crop characteristics and soil factors.
The only factors affecting ETo are climatic parameters. Consequently, ETo is a climatic
parameter and can be computed from weather data.
For Kenya7, ETo can be found by multiplying the evaporation from a free water surface (Eo)
by an adjustment factor, this one being;
· For highlands (above 1,100m) = 0.75
· For hot and dry low areas (below 1,100m) = 0.80
Hence for Taveta Area,
ETo = 0.8 x
Eo……………………………………………………………………………………(2)
Values for Eo (open water surface evaporation) found in “Studies of Potential Evaporation in
Kenya” by T. Woodhead8, alongside the computed values of ETo, are shown in the Table 2.15
below.
7 Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
8 Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Table 15 - Estimated Reference Evapotranspiration (ETo)
Month
Eo -Open Water
Surface evaporation
(mm/month)9
Eo -Open Water
Surface evaporation
(mm/day)
ETo Estimated
Reference
Evapotranspiration
(mm/day)
January 175 5.65 4.52
February 175 6.25 5.00
March 175 5.65 4.52
April 150 5.00 4.00
May 140 4.52 3.61
June 135 4.50 3.60
July 135 4.35 3.48
August 145 4.68 3.74
September 165 5.50 4.40
October 185 5.97 4.77
November 175 5.83 4.67
December 175 5.65 4.52
2.11.1.4 CROP COEFFICIENT (Kc)
Factors affecting the value of KC are mainly crop characteristics, crop planting data, crop
development, length of growing season and climate considerations. Crop transpiration
increases over the growing season with the growth of the canopy surface while the soil
evaporation decreases proportionally over the growing season as the ground surface is
increasingly shaded by the crop canopy. There are four distinguishable crop growth stages
1. The initial stage: when the crop uses little water;
2. The crop development stage, when the water consumption increases;
3. The mid-season stage, when water consumption reaches a peak;
4. The late-season stage, when the maturing crop once again requires less water
The effect of both crop transpiration and soil evaporation are integrated into a single crop
coefficient KC incorporating crop characteristics and average effects of evaporation from the
soil.
The table below shows the crop coefficients of the selected crops at various stages of
development while the next table superimposes the applicable crop coefficients with the
proposed cropping calendar.
9 Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Table 2.16 - Crop Coefficients10
(Kc)
No.
Crop
Type
Crop
Growing Period
(Days)
Initial
Stage
Crop
Development
Mid
Season
Late
Season
At
Harvest
1 Cereals Maize 120 - 140 0.40 0.80 1.15 0.90 0.60
2
Legumes
Beans 90-110 0.35 0.75 1.15 0.70 0.30
Green Grams 90-110 0.35 0.75 1.15 0.70 0.30
Cowpeas 90-110 0.35 0.75 1.15 0.70 0.30
3
Vegetables
Tomatoes 90-110 0.45 0.75 1.15 0.90 0.60
Kales 75-100 0.45 0.75 1.05 0.95 0.90
Water Melons 125-145 0.45 0.75 1.0 0.85 0.70
Onions 90-110 0.50 0.80 1.1 0.90 0.80
Chillies 90-110 0.35 0.70 1.1 1.0 0.85
4
Fruits
Bananas >365 0.60 0.85 1.1 1.1 0.1
Pawpaw >365 0.60 0.85 1.1 1.1 1.1
5 Oil crops Sunflower 120-140 0.305 0.75 1.15 0.75 0.40
Table 2.17 - Cropping Calendar and Applicable Crop Coefficients
Crop Mar Apr May Jun Jul Aug
Maize 0.4 0.8 0.8 0.8 1.15 1.15 1.15 0.9 0.6
Beans 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Green Grams 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Cowpeas 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Tomatoes 0.45 0.75 0.75 1.15 1.15 0.9 0.6
Kales 0.45 0.75 1.05 1.05 0.95 0.9
Water Melons 0.45 0.75 0.75 0.75 1.0 1.0 0.85 0.85 0.7
Onions 0.5 0.8 0.8 1.1 1.1 0.9 0.8
Chillies 0.35 0.7 0.7 1.1 1.1 1.0 0.85
Bananas 0.6 0.6 0.6 0.6 0.85 0.85 0.85 0.85 1.1 1.1 1.1 1.1
10
Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Crop Mar Apr May Jun Jul Aug
Pawpaw 0.6 0.6 0.6 0.6 0.85 0.85 0.85 0.85 1.1 1.1 1.1 1.1
Sunflower 0.35 0.75 0.75 1.15 1.15 1.15 0.75 0.75 0.4
Crop Sep Oct Nov Dec Jan Feb
Maize 0.4 0.8 0.8 0.8 1.15 1.15 1.15 0.9 0.6
Beans 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Green Grams 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Cowpeas 0.35 0.75 0.75 1.15 1.15 0.7 0.3
Tomatoes 0.45 0.75 0.75 1.15 1.15 0.9 0.6
Kales 0.45 0.75 1.05 1.05 0.95 0.9 0.6
Water Melons 0.45 0.75 0.75 0.75 1 1 0.85 0.85 0.7
Onions 0.5 0.8 0.8 1.1 1.1 0.9 0.8
Chillies 0.35 0.7 0.7 1.1 1.1 1 0.85
Bananas 0.6 0.6 0.6 0.6 0.85 0.85 0.85 0.85 1.1 1.1 1.1 1.1
Pawpaw 0.6 0.6 0.6 0.6 0.85 0.85 0.85 0.85 1.1 1.1 1.1 1.1
Sunflower 0.35 0.75 0.75 1.15 1.15 1.15 0.75 0.75 0.4
Key to Table 2.17
Season
One
Annual crops Season
Two
Coast Development Authority
2.11.1.5 ESTIMATION OF CROP WATER REQUIREMENTS (ETcrop)
The applicable CROP WATER REQUIREMENTS (ETcrop) have been computed by applying
equation (1) and using the values of ETo and applicable crop coefficients (KC) as determined
in Sections 6.1.2 and 6.1.3 and tabulated in the Table below.
Table 2.18 - Estimated Crop Water Requirements (ETcrop)(mm)
Crop Mar Apr May June July Aug Total
Season
One
Maize 83.1 96.0 128.8 110.7 33.4 - 452.0
Beans 76.1 114.0 104.4 16.2 - - 310.7
Green
Grams 76.1 114.0 104.4 16.2 - - 310.7
Cowpeas 76.1 114.0 104.4 16.2 - - 310.7
Tomatoes 83.3 114.0 115.3 32.4 - - 345.0
Kales 83.3 126.0 103.7 - - - 313.0
Water
Melons 83.3 90.0 112.0 91.8 - - 416.1
Onions 90.3 114.0 112.4 43.2 - - 359.9
Chillies 72.7 108.0 117.8 45.9 - - 344.4
Bananas 119 102 123.2 118.8 64.8 69.6 597.4
Pawpaw 119 102 123.2 118.8 64.8 69.6 597.4
Sunflower 76.1 114.0 128.8 81.0 22.3 - 422.2
Crop Sept Oct Nov Dec Jan Feb Total
Season
Two
Maize 79.2 118.4 161.0 144.1 43.4 - 546.0
Beans 72.6 139.6 129.5 21.7 - - 363.4
Green
Grams 72.6 139.6 129.5 21.7 - - 363.4
Cowpeas 72.6 139.6 129.5 21.7 - - 363.4
Tomatoes 79.2 139.6 143.5 43.4 - - 405.7
Kales 79.2 155.4 129.5 0 - - 364.1
Water
Melons 79.2 111.0 140.0 119.0 50.6 - 499.8
Onions 85.8 139.9 140.0 57.8 - - 423.5
Chillies 69.3 132.2 147.0 61.4 - - 410.0
Bananas 112.2 125.8 154.0 154.0 84.0 87.0 717.0
Pawpaw 112.2 125.8 154.0 154.0 84.0 87.0 717.0
Sunflower 72.6 139.6 161.0 105.0 28.9 - 507.1
Worked Example 1
Estimation of Crop Water Requirements
ETcrop = ETO x KC as per equation (1)
For Maize in the month of March,
ETo = 4.52 mm/day and KC= 0.4 (16 days) and KC = 0.8 (15 days)
Coast Development Authority
Therefore; ETcrop = 4.52 x [(0.4 x 16) + (0.8 x 15)] = 83.097 mm…………(3)
Other detailed calculations are tabulated in Table 2.18.
Table 2.19 - Estimated Annual Crop Water Requirements (ETcrop) (mm)
Long Rains Short Rains Total
Maize 452.0 546.0 998.0
Beans 310.7 363.4 674.1
Green Grams 310.7 363.4 674.1
Cowpeas 310.7 363.4 674.1
Tomato 345.0 405.7 750.7
Kales 313.0 364.1 677.1
Water Melons 416.1 499.8 915.9
Onions 359.9 423.5 783.4
Chilies 344.4 410.0 754.4
Bananas 597.4 717.0 1314.4
Pawpaw 597.4 717.0 1314.4
Sunflower 422.2 507.1 929.3
2.11.2 Net Irrigation Water Requirements (NIR)
2.11.2.2 DEFINITION
The Net Irrigation Water Requirement (NIR) is defined as the amount of water needed to
meet the Crop Water Requirement (ETCROP) less portion of rainfall stored in soil and
effectively utilised by the crop. Basically, the irrigation water requirement basically
represents the difference between the crop water requirement and effective precipitation.
Hence NIR = ETCROP - REFF ………………………………………………….…… (4)
Where, NIR = Net Irrigation Requirement (mm)
ETCROP = Crop Water Requirement (mm)
REFF = Effective Rainfall (mm)
2.11.2.3 EFFECTIVE RAINFALL
Crop water needs can be fully or partly met by rainfall. Not all rainfall that falls is effective
(for the crops), as part of it may be lost by run-off, deep percolation or evaporation, hence the
term effective rainfall. The amount of effective rainfall mainly depends upon intensity of
rainfall, crop water requirements, soil type, and root depth of plant.
The average monthly effective rainfall is obtained based on its empirical relationship with the
mean monthly rainfall (Table 2.1) for different values of average monthly ETCROP (Crop
Coast Development Authority
water requirements) (Table 2.18). A storage factor is applied when effective storage in the
root in the root zone differs from 75mm.11
The average available water in soil profile for all the project sites, as per the Soils Report in
the Feasibility Study, is 162.6 mm/m.12
Table 2.20 gives the effective soil storages and the applicable factors for the various crops as
extracted from the Practice Manual for Water Services in Kenya– Ministry of Water and
Irrigation (October 2005). An adjustment factor of 1.06 is applicable where the effective
storage is greater or less than 75 mm.
Table 2.20 - Effective Soil Storages
Crop
Average Root
Zone13
(m)
Effective Storage
(mm)
Adjustment Factor14
Maize 1 162.6 1.06
Beans 0.6 97.6 1.02
Green grams 0.6 97.6 1.02
Cowpeas 0.6 97.6 1.02
Tomatoes 0.7 113.8 1.03
Kales 0.3 48.8 0.93
Water Melons 0.8 130.1 1.04
Onions 0.3 48.8 0.93
Chillies 0.5 81.3 1
Bananas 0.5 81.3 1
Pawpaws 0.5 81.3 1
Sunflower 0.8 130.1 1.04
The result of effective rainfall estimation for various crops, as extrapolated from the Practice
Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005) is
given in Table 2.21.
11
Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
12 Feasibility Study and Preliminary Design -Lake Challa Water Resources Integrated Development
Project- August 2011
13 Irrigation and Drainage Paper No 56 - Food and Agricultural Organisation (FAO) 1998
14 Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Worked Example 2
Estimation of Effective Rainfall (REFF)
Average available water in soil profile = 162.6 mm/m (See Section 2.11.2.3 of this Report)
For Maize, Average Root Zone = 1 m, (Table 2.20)
Therefore;
Effective Storage =162.6 mm/m x 1 m =162.6 mm (An adjustment factor of 1.06 is
applicable as per Table 2.20)
For ETcrop = 83.097 mm (equation (3)) and mean monthly rainfall of 95 mm (Figure 2.1) and
through extrapolation from Table 7 of the Practice Manual for Water Services in Kenya–
Ministry of Water and Irrigation (October 2005) and applying a Storage Factor of 1.06 then
Estimated Effective Rainfall (REFF) = 58 x 1.06 = 61.480 mm ………………….…… (5)
Table 2.21 - Estimated Effective Rainfall (REFF) (mm)
Season Crop Mar Apr May June July Aug Total
Season
One
Maize 61.5 95.4 48.8 15.9 4.2 225.8
Beans 59.2 91.8 45.9 6.1 - - 203.0
Green Grams 59.2 91.8 45.9 6.1 - - 203.0
Cowpeas 59.2 91.8 45.9 6.1 - - 203.0
Tomatoes 57.7 92.7 46.4 6.2 - - 202.9
Kales 52.1 85.6 42.8 - - - 180.4
Water
Melons 64.5 87.4 44.7 14.6 8.3 - 219.4
Onions 57.7 83.7 44.6 7.4 - - 193.4
Chilies 62.0 90.0 46.0 8.0 - - 206.0
Bananas 66.0 90.0 43.0 13.0 7.0 8.0 233.0
Pawpaw 66.0 90.0 43.0 13.0 7.0 8.0 227.0
Sunflower 58.2 95.7 48.9 15.6 8.3 - 226.7
Season
Two
Crop Sept Oct Nov Dec Jan Feb Total
Maize 8.5 15.9 91.2 60.4 21.2 - 197.2
Beans 8.2 15.3 81.6 20.4 - - 125.5
Green Grams 8.2 15.3 81.6 20.4 - - 125.5
Cowpeas 8.2 15.3 81.6 20.4 - - 125.5
Tomato 7.2 15.5 82.4 20.6 - - 125.7
Kales 6.5 13.0 70.7 - - - 90.2
Water
Melons 9.4 13.5 90.5 56.2 20.8 - 190.3
Onions 8.4 14.9 76.3 25.1 - - 124.6
Chilies 9.0 13.0 85.0 25.0 - - 132.0
Coast Development Authority
Season Crop Mar Apr May June July Aug Total
Bananas 9.0 15.0 85.0 53.0 36.0 26.0 224.0
Pawpaw 9.0 15.0 85.0 53.0 36.0 26.0 224.0
Sunflower 8.3 16.6 91.5 58.2 20.8 - 195.5
2.11.2.4 ESTIMATED NET IRRIGATION WATER REQUIREMENTS (NIR)
Based on equation 3, the estimated monthly and yearly net irrigation water requirement (NIR)
for the proposed project cropping scheme is given in Table 2.22.
Table 2.22 -Estimated Net Irrigation Water Requirements (NIR)(mm)
Season Crop Mar Apr May June July Aug Total
Season
One
Maize 21.7 0.6 80.0 94.8 29.2 - 225.7
Beans 16.9 22.2 58.5 10.1 - - 107.7
Green Grams 16.9 22.2 58.5 10.1 - - 107.7
Cowpeas 16.9 22.2 58.5 10.1 - - 107.7
Tomato 25.6 21.3 68.9 26.2 - - 142.1
Kales 31.2 40.4 60.9 0 - - 132.6
Water Melons 18.8 2.64 67.3 77.2 30.7 - 194.1
Onions 32.7 30.3 67.7 35.8 - - 166.5
Chilies 10.7 18.0 71.8 37.9 - - 138.4
Bananas 53.0 12.0 80.2 105.8 57.8 61.6 370.4
Pawpaw 53.0 12.0 80.2 105.8 57.8 61.6 370.4
Sunflower 17.9 18.3 79.9 65.4 14.0 - 195.5
Season
Two
Crop Sept Oct Nov Dec Jan Feb Total
Maize 70.7 102.5 69.8 83.6 22.2 - 348.9
Beans 64.4 124.3 47.9 - - - 236.7
Green Grams 64.4 124.3 47.9 - - - 236.7
Cowpeas 64.4 124.3 47.9 - - - 236.7
Tomato 72.0 124.2 61.1 22.8 - - 280.0
Kales 72.7 142.4 58.8 - - - 273. 9
Water Melons 69.8 97.5 49.5 62.8 - - 309.5
Onions 77.4 125.0 63.7 32.7 - - 298.9
Chilies 60.3 119.2 62.0 36.4 - - 278.0
Bananas 103.2 110.8 69.0 101.0 48.0 61.0 493.0
Pawpaw 103.2 110.8 69.0 101.0 48.0 61.0 493.0
Sunflower 64.3 123.0 69.5 46.8 8.1 - 311.6
Worked Example 3
Estimation of Net Irrigation Water Requirements (NIR)
Through extrapolation from Table 7 of the Practice Manual for Water Services in From
Equation 4 and applying the figures in equations (3) and (5)
NIR = ETCROP - REFF =83.097 – 61.480 = 21.617m
For the existing Challa Irrigation it is proposed that water for an additional 20 ha will
Coast Development Authority
Be provided
Hence, the volumetric Net Irrigation Water Requirements (NIR) for the month of March is
estimated to be
NIR = 21.617 mm x 20 ha x 104 m2/ha x 10
-3 m/mm
=4,323.4 m3……………………………………………………………(6)
Based on the above and the areas to be irrigated as proposed in Chapter 2.6 of this report, the
estimated Net Irrigation Water Requirements, by crops and specific sites, are shown in Tables
2.23 and 2.24, respectively.
Coast Development Authority
Table 2.23 -Net Monthly Irrigation Water Requirements (by Crops)
Crop/
Site
Area
(ha)
Net Irrigation Water Requirements (NIR)(m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
MAIZE
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 20 4,431.0 0 4,323.4 120.0 16,008.0 18,960.0 5,841.0 0 14,144.0 20,500.0 13,968.0 16,728.9 115,024.3
Nakuruto 10 2,215.5 0 2,161.7 60.0 8,004.0 9,480.0 2,920.5 0 7,072.0 10,250.0 6,984.0 8,364.5 57,512.1
Timbilla 20 4,431.0 0 4,323.4 120.0 16,008.0 18,960.0 5,841.0 0 14,144.0 20,500.0 13,968.0 16,728.9 115,024.3
Jipe 100 22,154.8 0 21,617.0 600.0 80,040.0 94.800.0 29,205.0 0 70,720.0 102,500.0 69,840.0 83,644.5 575,121.3
Mwaktau 40 8,861.9 0 8,646.7 240.0 32,016.0 37,920.0 11,682.0 0 28,288.0 41,000.0 27,936.0 33,457.8 230,048.5
Total 190 42,094.2 0 41,072.0 1,140.0 152,076.0 180,120.0 55,490.0 0 134,368.0 194,750.0 132,696.0 158,925.0 1,092,730.0
BEANS
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 45 0 0 7,621.5 9,990.0 26,330.8 4,536.0 0 0 28,998.0 55,955.3 21,555.0 574.8 155,561.5
Mwaktau 15 0 0 2,540.5 3,330.0 8,776.9 1,512.0 0 0 9,666.0 18,651.8 7,185.0 191.6 51,853.8
Total 60 0 0 10,162.0 13,320.0 35,107.7 6,048.0 0 0 38,664.0 74,607.1 28,740.0 766.42 207,415.4
GREEN GRAMS
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 30 0 0 5,081.0 6,660.0 17,553.9 3,024.0 0 0 19,332.0 37,303.5 14,370.0 383.2 103,707.7
Mwaktau 15 0 0 2,540.5 3,330.0 8,776.9 1,512.0 0 0 9,666.0 18,651.8 7,185.0 191.6 51,853.8
Total 45 0 0 7,621.5 9,990.0 26,330.8 4,536.0 0 0 28,998.0 55,955.3 21,555.0 574.8 155,561.5
COWPEAS
Coast Development Authority
Crop/
Site
Area
(ha)
Net Irrigation Water Requirements (NIR)(m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 10 0 0 1,693.7 2,220.0 5,851.3 1,008.0 0 0 6,444.0 12,434.5 4,790.0 127.7 34,569.2
Nakuruto 5 0 0 846.8 1,110.0 2,925.6 504.0 0 0 3.222.0 6,217.3 2,395.0 63.9 17,284.6
Timbilla 10 0 0 1,693.7 2,220.0 5,851.3 1,008.0 0 0 6,444.0 12,434.5 4,790.0 127.7 34,569.2
Jipe 20 0 0 3,387.4 4,440.0 11,702.6 2,016.0 0 0 12,888.0 24,869.0 9,580.0 255.5 69,138.5
Mwaktau 15 0 0 2,540.5 3,330.0 8,776.9 1,512.0 0 0 9,666.0 18,651.8 7,185.0 191.6 51,853.8
Total 60 0 0 10,162.1 13,320.0 35,107.7 6,048.0 0 0 38,664.0 74,607.1 28,740.0 766.4 207,415.4
TOMATOES
Kilanga 20 0 0 5,128.5 4,260.0 13,780.3 5,244.0 0 0 14,398.0 24,839.0 12,220.0 4,551.0 84,420.8
Challa 10 0 0 2,564.3 2,130.0 6,890.2 2,622.0 0 0 7,199.0 12,419.5 6,110.0 2,275.5 42,210.4
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 10 0 0 2,564.3 2,130.0 6,890.2 2,622.0 0 0 7,199.0 12,419.5 6,110.0 2,275.5 42,210.4
Jipe 0 0 0 0 0 0 0 0 0 0 0 0
Mwaktau 0 0 0 0 0 0 0 0 0 0 0 0
Total 40 10,257.1 8,520.0 27,560.7 10,488.0 0 0 28,796.0 49,678.1 24,440.0 9102.0 168,841.7
KALES
Kilanga 10 0 0 3,124.3 4,044.0 6,091.0
0 0 0 7,269.0 14,238.0 5,882.0 0 40,648.3
Challa 10 0 0 3,124.3 4,044.0 6,091.0
0 0 0 7,269.0 14,238.0- 5,882.0 0 40,648.3
Nakuruto 5 1,562.1 2,022.0 3,045.5
3,634.5 7,119.0 2,941.0 0 20,324.2
Timbilla 10 0 0 3,124.3 4,044.0 6,091.0
0 0 0 7,269.0 1,4238.0 5,882.0 0 40,648.3
Jipe 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Mwaktau 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Total 35 0 0 10,935.0 14,154.0 21,318.6
0 0 0 25,441.5 49,833.0 20,587.0 0 142,269.0
SUNFLOWER
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Coast Development Authority
Crop/
Site
Area
(ha)
Net Irrigation Water Requirements (NIR)(m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 25 2,025.8 0 4,464.2 4,580.0 19,980.0 16,350.0 3,494.2 0 16,070.0 30,751.3 17,370.0 11,690.0 126,775.5
Mwaktau 15 1,215.5 0 2,678.5 2,748.0 11,988.0 9,810.0 2,096.5 0 9,642.0 18,450.8 10,422.0 7,014.0 76,065.3
Total 40 3,241.3 0 7,142.7 7,328.0 31,968.0 26,160.0 5,590.7 0 25,712.0 49,202.1 27,792.0 18,704.0 202,840.8
BANANAS
Kilanga 20 9,600.0 12,200.0 10,600.0 2,400.0 16,040.0 21,160.0 11,560.0 12,320.0 20,640.0 22,160.0 13,800.0 20,200.0 172,680.0
Challa 10 4,800.0 6,100.0 5,300.0 1,200.0 8,020.0 10,580.0 5,780.0 6,160.0 10,320.0 11,080.0 6,900.0 10,100.0 86,340.0
Nakuruto 5 2,400.0 3,050.0 2,650.0 600.0 4,010.0 5,290.0 2,890.0 3,080.0 5,160.0 5,540.0 3,450.0 5,050.0 43,170.0
Timbilla 10 4,800.0 6,100.0 5,300.0 1,200.0 8,020.0 10,580.0 5,780.0 6,160.0 10,320.0 11,080.0 6,900.0 10,100.0 86,340.0
Jipe 100 48,000.0 61,000.0 53,000.0 12,000.0 80,200.0 105,800.0 57,800.0 61,600.0 103,200.0 110,800.0 69,000.0 101,000.0 863,400.0
Mwaktau 40 19,200 24,400.0 21,200.0 4,800.0 32,080.0 42,320.0 23,120.0 24,640.0 41,280.0 44,320.0 27,600.0 40,400.0 345,360.0
Total 185 88,800.0 112,850.0 98,050.0 22,200.0 148,370.0 195,730.0 106,930.0 113,960.0 190,920.0 204,980.0 127,650.0 186,850.0 1,597,290.0
WATER MELONS
Kilanga 10 2,978.1 0 1,884.3 264.0 6,728.0 7,724.0 3,069.9 0 6,984.0 9,748.0 4,952.0 6,284.0 50,616.3
Challa 10 2,978.1 0 1,884.3 264.0 6,728.0 7,724.0 3,069.9 0 6,984.0 9,748.0 4,952.0 6,284.0 50,616.3
Nakuruto 5 1,489.0 0 942.1 132.0 3,364.0 3,862.0 1,535.0 0 3,492.0 4,874.0 2,476.0 3,142 25,308.1
Timbilla 10 2,978.1 0 1,884.3 264.0 6,728.0 7,724.0 3,069.9 0 6,984.0 9,748.0 4,952.0 6,284.0 50,616.3
Jipe 10 2,978.1 0 1,884.3 264.0 6,728.0 7,724.0 3,069.9 0 6,984.0 9,748.0 4,952.0 6,284.0 50,616.3
Mwaktau 5 1,489.0 0 942.1 132.0 3,364.0 3,862.0 1,535.0 0 3,492.0 4,874.0 2,476.0 3,142 25,308.1
Total 50 14,890.3 0 9,421.3 1,320.0 33,640.0 38,620.0 15,350.0 0 34,920.0 48,740.0 24,760.0 31,420.0 253,081.3
PAWPAWS
Kilanga 20 9,600.0 12,200.0 10,600.0 2,400.0 16,040.0 21,160.0 11,560.0 12,320.0 20,640.0 22,160.0 13,800.0 20,200.0 172,680.0
Challa 10 4,800.0 6,100.0 5,300.0 1,200.0 8,020.0 10,580.0 5,780.0 6,160.0 10,320.0 11,080.0 6,900.0 10,100.0 86,340.0
Nakuruto 5 2,400.0 3,050.0 2,650.0 600.0 4,010.0 5,290.0 2,890.0 3,080.0 5,160.0 5,540.0 3,450.0 5,050.0 43,170.0
Timbilla 10 4,800.0 6,100.0 5,300.0 1,200.0 8,020.0 10,580.0 5,780.0 6,160.0 10,320.0 11,080.0 6,900.0 10,100.0 86,340.0
Jipe 75 36,000.0 45,750.0 39,750.0 9,000.0 60,150.0 79,350.0 43,350.0 46,200.0 77,400.0 83,100.0 51,750.0 75,750.0 647,550.0
Mwaktau 25 12,000.0 15,250.0 13,250.0 3,000.0 20,050.0 26,450.0 14,450.0 15,400.0 25,800.0 27,700.0 17,250.0 25,250.0 215,850.0
Coast Development Authority
Crop/
Site
Area
(ha)
Net Irrigation Water Requirements (NIR)(m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Total 145 69,600.0 88,450.0 76,850.0 17,400.0 116,290.0 153,410.0 83,810 89,320.0 149,640.0 160,660.0 100,050.0 146,450.0 1,251,930.0
ONIONS
Kilanga 10 0 0 3,266.3 3,030.0 6,772.1 3,576.0 0 0 7,743.0 12,500.4 6,374.0 3,269.7 46,531.4
Challa 10 0 0 3,266.3 3,030.0 6,772.1 3,576.0 0 0 7,743.0 12,500.4 6,374.0 3,269.7 46,531.4
Nakuruto 5 0 0 1,633.1 1,515.0 3,386.1 1,788.0 0 0 3,871.5 6,250.2 3,187.0 1,634.8 23,265.7
Timbilla 10 0 0 3,266.3 3,030.0 6,772.1 3,576.0 0 0 7,743.0 12,500.4 6,374.0 3,269.7 46,531.4
Jipe 50 0 0 16,331.0 15,150.0 33,860.7 17,880.0 0 0 38,715.0 62,501.9 31,870.0 16,348.2 232,657.1
Mwaktau 25 0 0 8,165.6 7,575.0 16,930.3 8,940.0 0 0 19,357.5 31,251.0 15,935.0 8,174.1 116.328.5
Total
110 0 0 35,929.0 33330 74493.42 39,336.0 0 0 85,173.0 137,504.0 70,114.0 35,966.1 511,845.6
CHILLIES
Kilanga 10 0 0 1,071.0 1,800.0 7,178.1 3,790.0 0 0 6,030.0 11,924.5 6,200.0 3,641.9 41,635.5
Challa 10 0 0 1,071.0 1,800.0 7,178.1 3,790.0 0 0 6,030.0 11,924.5 6,200.0 3,641.9 41,635.5
Nakuruto 5 0 0 535.5 900.0 3,589.0 1,895.0 0 0 3,015.0 5,962.3 3,100.0 1,821.0 20,817.7
Timbilla 10 0 0 1,071.0 1,800.0 7,178.1 3,790.0 0 0 6,030.0 11,924.5 6,200.0 3,641.9 41,635.5
Jipe 10 0 0 1,071.0 1,800.0 7,178.1 3,790.0 0 0 6,030.0 11,924.5 6,200.0 3,641.9 41,635.5
Mwaktau 5 0 0 535.5 900.0 3,589.0 1,895.0 0 0 3,015.0 5,962.3 3,100.0 1,821.0 20,817.7
Total 50 0 0 5,354.8 9,000.0 35,890.3 18,950.0 0 0 30,150.0 59,622.6 31,000.0 18,209.7 208,177.4
GRAND
TOTAL 1,020 361,342.3 334,399.0 534,606.0 251,361.0 1,220,902.0 1,121,436.0 441531 337,688.5 1,343,322.0 1,921,792.0 1,055,165.0 1,002,444.0 9,925,989.0
Coast Development Authority
Table 2.24 -Net Monthly Irrigation Water Requirements per Site
Site
Area
(ha) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Kilanga 100 29,321.4 32,006.2 47,220.0 24,414.0 96,937.1 83,295.7 34,591.0 32,321.0 111,407.0 157,143.0 84,375.3 77,276.7 810,307.3
Challa 100 29,075.3 20,854.7 48,764.0 27,364.0 122,322.5 100,581.0 34,993.0 21,059.8 130,689.0 198,162.0 106,113.0 89,791.0 929,769.8
Nakuruto 45 14,537.6 10,427.4 22,190.0 11,862.0 55,272.2 48,049.6 17,497.0 10,529.9 59,191.5 88,466.2 47,834.2 42,950.6 428,807.6
Timbilla 100 29,075.3 20,854.7 48,764.0 27,364.0 122,322.5 100,581.0 34,993.0 21,059.8 130,689.0 198,162.0 106,113.0 89,791.0 929,769.8
Jipe 465 190,014.9 182,479.0 263,602.0 110,229.0 587,562.3 573,111.0 234050 184,273.5 650,149.0 905,049.0 506,815.0 512,089.0 4,899,424.0
Mwaktau 200 73,105.1 67,777.8 107,761.0 50,231.0 250,167.8 232,022.0 90,399.0 68,444.4 273,286.0 392,330.0 215,853.0 204,844.0 2,026,222.0
Total 1,010 361,342.3 334,399.0 534,606.0 251,361.0 1,220,902.0 1,121,436.0 441,531.0 337,688.5 1,343,322.0 1,921,792.0 1,055,165.0 1,002,444.0 9,925,989.0
Coast Development Authority
2.11.3 GROSS IRRIGATION WATER REQUIREMENTS (GWR)
The annual Gross irrigation water requirement (GWR) is summation of annual net irrigation
water requirement (NIR) and extra amount needed to compensate for possible water losses and is
given by;
GWR = NIR/ƞ and ƞ = ƞa x ƞc ……………………………..………………….(7)
Where ƞ is the efficiency of Field Application and Conveyance
ƞa = Field Application Efficiency (Ratio of Water Available to Crop versus Water at Field Inlet)
ƞc = Conveyance Efficiency (Ratio of Water at Field Inlet versus water at source including an
allowance due to water evaporation from the open reservoirs)
The irrigation efficiencies for different irrigation methods considered in the project are tabulated
in Table 2.25.
Table 2.25- Irrigation Systems Efficiencies
Irrigation
System
Field Application
Efficiency (ƞa) 15
(%)
Conveyance
Efficiency (ƞc) *
(%)
Overall Efficiency (ƞ)
(%)
Drip 90 90 81
Sprinkler 80 90 72
Surface 65 90 58.5 * Assumed
The project estimated crop-wise, monthly and yearly gross requirement in accordance with the
mode of irrigation recommended earlier and equation (7) is given in Tables 2.26 -2.29.
Worked Example 4
Estimation of Gross Irrigation Water Requirements (GWR)
From equation (7)
GWR = NIR/ƞ
For 20 ha of maize in the Challa project as per equation (6)
NIR = 4,323.4 m3
ƞ = 58.5 % (Table 2.25)
15
Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Therefore;
GWR = 4,323.4 m3 /58.5/100 = 7,390.4 m
3………………………..………….(8)
The Gross Irrigation Requirement is approximately 9,925,989.0 m3 for the proposed irrigation
area of 2,020 ha on annual basis as shown in Table 2.26.
Coast Development Authority
Table 2.26 - Gross Irrigation Water Requirements (m3)
Crop/
Site
Area
(ha)
Gross Irrigation Water Requirements (m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
MAIZE
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 20 7,574.3 0 7,390.4 205.1 27,364.1 32,410.3 9,984.7 0 24,177.8 35,042.7 23,876.9 28,596.4 196,622.7
Nakuruto 10 3,787.2 0 3,695.2 102.6 13,682.1 16,205.1 4,992.3 0 12,088.9 17,521.4 11,938.5 14,298.2 98,311.3
Timbilla 20 7,574.3 0 7,390.4 205.1 27,364.1 32,410.3 9,984.7 0 24,177.8 35,042.7 23,876.9 28,596.4 196,622.7
Jipe 100 37,871.5 0 36,952.0 1,025.6 136,820.5 162,051.0 49,923.0 0 120,889.0 175,214.0 119,385.0 142,982.0 983,113.3
Mwaktau 40 15,148.6 0 14,781.0 410.3 54,728.2 64,820.5 19,969.0 0 48,355.6 70,085.5 47,753.8 57,192.8 393,245.3
Total 190 68,168.7 0 66,513.0 1,846.2 246,276.9 291,692.0 89,862.0 0 217,600.0 315,385.0 214,892.0 257,368.0 1,769.604.0
BEANS
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 45 0 0 13,028.0 17,077.0 45,009.9 7,753.9 0 0 49,569.2 95,650.1 36,846.2 982.6 265,917.1
Mwaktau 15 0 0 4,342.8 5,692.3 15,003.3 2,584.6 0 0 16,523.1 31,883.4 12,282.1 327.5 88,639.0
Total 60 0 0 17,371.0 22,769.0 60,013. 10338.5 0 0 66,092.3 127,533.0 49,128.2 1,310.2 354,556.2
GREEN GRAM
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 30 0 0 8,685.5 11,385.0 30,006.6 5,169.2 0 0 33,046.2 63,766.7 24,564.1 655.1 177,278.1
Mwaktau 15 0 0 4,342.8 5,692.3 15,003.3 2,584.6 0 0 16,523.1 31,883.4 12,282.1 327.5 886,39.0
Total 45 0 0 13,028.0 17,077.0 45,009.9 7,753.8 0 0 49,569.2 95,650.1 36,846.2 982.6 265,917.1
COWPEA
Coast Development Authority
Crop/
Site
Area
(ha)
Gross Irrigation Water Requirements (m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 10 0 0 2,895.2 3,794.9 10,002.2 1723.1 0 0 11015.4 21,255.6 8,188.0 218.4 59,092.7
Nakuruto 5 0 0 1,447.6 1,897.4 5,001.1 861.5 0 0 5507.7 10627.8 4094.02 109.2 29,546.3
Timbilla 10 0 0 2,895.2 3,794.9 10,002.2 1723.1 0 0 11015.4 21,255.6 8,188.0 218.4 59,092.7
Jipe 20 0 0 5,790.4 7,589.7 20,004.4 3446.15 0 0 22,030.8 42,511.2 16,376.1 436.7 118,185.4
Mwaktau 15 0 0 4,342.8 5,692.3 15,003.3 2,584.6 0 0 16,523.1 31,883.4 12,282.1 327.5 88,639.0
Total 60 0 0 17,371.0 22,769.0 60,013.2 10,338.5 0 0 66,092.3 127,533.0 49,128.2 1,310.2 354,556.2
TOMATO
Kilanga 20 0 0 6,703.9 5,568.6 18,013.5 6,854.9 0 0 18,820.9 32,469.3 15,973.9 5,949.0 110,354.0
Challa 10 0 0 4,383.3 3,641.0 11,778.1 4,482.1 0 0 12,306.0 21,229.9 10,444.4 3,889.7 72,154.6
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 10 0 0 4,383.3 3,641.0 11,778.1 4,482.1 0 0 12,306.0 21,229.9 10,444.4 3,889.7 72,154.6
Jipe 0 0 0 0 0 0 0 0 0 0 0 0
Mwaktau 0 0 0 0 0 0 0 0 0 0 0 0
Total 40 15,471.0 12,851.0 41569.6 15819 0 0 43,432.9 74,929.2 36,862.7 13,728.4 254,663.2
KALE
Kilanga 10 0 0 4,339.2 5,616.7 8,459.8 0 0 0 10,095.8 19,775.0 8,169.4 0 56,456.0
Challa 10 0 0 5,340.6 6,912.8 10,412.0 0 0 0 12,425.6 24,338.5 10,054.7 0 69,484.3
Nakuruto 5 2,670.3 3,456.4 5,206.0 0 0 0 6,212.8 12,169.2 5,027.4 0 34,742.1
Timbilla 10 0 0 5,340.6 6,912.8 10,412.0 0 0 0 12,425.6 24,338.5 10,054.7 0 69,484.3
Jipe 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mwaktau 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 35 0 0 17,691.0 22,899.0 34,489.8 0 0 0 41,160.0 80,621.2 33,306.2 0 230,166.6
SUNFLOWER
Kilanga 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Challa 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Coast Development Authority
Crop/
Site
Area
(ha)
Gross Irrigation Water Requirements (m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Nakuruto 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Timbilla 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Jipe 25 3,462.9 0 7,631.1 7,829.1 34,153.8 27,948.7 5,973.0 0 27,470.1 52,566.3 29,692.3 19,982.9 216,710.2
Mwaktau 15 2,077.8 0 4,578.7 4,697.4 20,492.3 16,769.2 3,583.8 0 16,482.1 31,539.8 17,815.4 11,989.7 130,026.1
Total 40 5,540.7 0 12,210.0 12,526.0 54,646.1 44,717.9 9,556.8 0 43,952.1 84,106.1 47,507.7 31,972.6 346,736.4
BANANA
Kilanga 20 11,851.9 15,061.7 13,086.0 2,963.0 19,802.5 26,123.5 14,272.0 15,209.9 25,481.5 27,358.0 17,037.0 24,938.3 213,185.2
Challa 10 8,205.1 10,427.4 9,059.8 2,051.3 13,709.4 18,085.5 9,880.3 10,529.9 17,641.0 18,940.2 11,794.9 17,265.0 147,589.7
Nakuruto 5 4,102.6 5,213.7 4,529.9 1,025.6 6,854.7 9,042.7 4,940.2 5265.0 8,820.5 9,470.1 5,897.4 8,632.5 73,794.9
Timbilla 10 8,205.1 10,427.4 9,059.8 2,051.3 13,709.4 18,085.5 9,880.3 10,529.9 17,641.0 18,940.2 11,794.9 17,265.0 147,589.7
Jipe 100 82,051.3 104,274.0 90,598.0 20,513.0 137,094.0 180,855.0 98,803.0 105,299.1 176,410.0 189,402.0 117,949.0 172,650.0 1,475.897.0
Mwaktau 40 32,820.5 41,709.4 36,239.0 8,205.1 54,837.6 72,341.9 39,521.0 42,119.7 70,564.1 75,760.7 47,179.5 69,059.8 590,359.0
Total 185 147,236.5 187,113.0 162,574.0 36,809.0 246,007.6 324,534.0 177,297.0 188,953.5 316,558.0 339,871.0 211,652.0 309,810.0 2,648,416.0
WATER MELON
Kilanga 10 4,136.2 0 2,617.0 366.7 9,344.4 10,727.8 4,263.8 0 9,700.0 13,538.9 6,877.8 8,727.8 70,300.4
Challa 10 5,090.7 0 3,221.0 451.3 11,500.9 13,203.4 5,247.8 0 11,938.5 16,663.2 8,465.0 10,741.9 86,523.5
Nakuruto 5 2,545.3 0 1,610.5 225.6 5,750.4 6,601.7 2,623.9 0 5,969.2 8,331.6 4,232.5 5,370.9 43,261.8
Timbilla 10 5,090.7 0 3,221.0 451.3 11,500.9 13,203.4 5,247.8 0 11,938.5 16,663.2 8,465.0 10,741.9 86,523.5
Jipe 10 5,090.7 0 3,221.0 451.3 11,500.9 13,203.4 5,247.8 0 11,938.5 16,663.2 8,465.0 10,741.9 86,523.5
Mwaktau 5 2,545.3 0 1,610.5 225.6 5,750.4 6,601.7 2,623.9 0 5,969.2 8,331.6 4,232.5 5,370.9 43,261.8
Total 50 24,499.0 0 15,501.0 2,171.8 55,347.9 63,541.5 25,255.0 0 57,453.8 80,191.9 40,737.6 51,695.3 416,394.4
PAWPAW
Kilanga 20 13,333.3 16,944.4 14,722.0 3,333.3 22,277.8 29,388.9 16.056.0 17,111.1 28,666.7 30,777.8 19,166.7 28,055.6 239,833.3
Challa 10 8,205.1 10,427.4 9,059.8 2,051.3 13,709.4 18,085.5 9,880.3 10,529.9 17,641.0 18,940.2 11,794.9 17,265.0 147,589.7
Nakuruto 5 4,102.6 5,213.7 4,529.9 1,025.6 6,854.7 9,042.7 4,940.2 5265.0 8,820.5 9,470.1 5,897.4 8,632.5 73,794.9
Timbilla 10 8,205.1 10,427.4 9,059.8 2,051.3 13,709.4 18,085.5 9,880.3 10,529.9 17,641.0 18,940.2 11,794.9 17,265.0 147,589.7
Jipe 75 61,538.5 78,205.1 67,949.0 15,385.0 102,820.5 135,641.0 74,103.0 78,974.4 132,308.0 142,051.0 88,461.5 129,487.0 1,106,923.0
Coast Development Authority
Crop/
Site
Area
(ha)
Gross Irrigation Water Requirements (m3)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Mwaktau 25 20,512.8 26,068.4 22,650.0 5,128.2 34,273.5 45,213.7 24,701.0 26,324.8 44,102.6 47,350.4 29,487.2 43,162.4 368,974.4
Total 145 115,897.4 147,286.0 127,970.0 28,974.0 193,645.3 255,457.0 139,560.0 148,735.0 249,179.0 267,530.0 166,603.0 243,868.0 2,084,705.0
ONION
Kilanga 10 0 0 4,536.5 4,208.3 9,405.7 4,966.7 0 0 10,754.2 17,361.6 8,852.8 4,541.2 64,627.0
Challa 10 0 0 5,583.3 5,179.5 11,576.3 6,112.8 0 0 13,235.9 21,368.2 10,895.7 5,589.1 79,540.9
Nakuruto 5 0 0 2,791.7 2,589.7 5,788.1 3,056.4 0 0 6,618.0 10,684.1 5,447.9 2,794.6 39,770.4
Timbilla 10 0 0 5,583.3 5,179.5 11,576.3 6,112.8 0 0 13,235.9 21,368.2 10,895.7 5,589.1 79,540.9
Jipe 50 0 0 27,917.0 25,897.0 57,881.4 30,564.1 0 0 66,179.5 106,841.0 54,478.6 27,945.7 397,704.4
Mwaktau 25 0 0 13,958.0 12,949.0 28,940.72 15,282.1 0 0 33,089.7 53,420.5 27.0239.3 13,972.8 198,852.2
Total
110 0 0 60,370.0 56,003.0 125,168.6 66,094.9 0 0 143,113.0 231,043.0 117,810.0 60,432.5 860,035.8
CHILLIES
Kilanga 10 0 0 1,586.6 2,666.7 10,634.2 5,614.8 0 0 8,933.3 17,665.9 9,185.2 5,395.5 61,682.2
Challa 10 0 0 1,830.7 3,076.9 12,270.2 6,478.6 0 0 10,307.7 20,383.8 10,598.3 6,225.5 71,171.8
Nakuruto 5 0 0 915.4 1,538.5 6,135.1 3,239.3 0 0 5,153.9 10,191.9 5,299.2 3,112.77 35,585.9
Timbilla 10 0 0 1,830.7 3,076.9 12,270.2 6,478.6 0 0 10,307.7 20,383.8 10,598.3 6,225.5 71,171.8
Jipe 10 0 0 1,830.7 3,076.9 12,270.2 6,478.6 0 0 10,307.7 20,383.8 10,598.3 6,225.5 71,171.8
Mwaktau 5 0 0 915.4 1,538.5 6,135.1 3,239.3 0 0 5,153.9 10,191.9 5,299.2 3,112.77 35,585.9
Total 50 0 0 8,909.5 14,974.0 59,715.0 31,529.3 0 0 50,164.1 99,201.1 51,578.3 30,297.6 346,369.3
GRAND
TOTAL 1,020 351,637.8 334,399.3 521,880.0 246,828.8 1,174,589.7 1,077,971.7 428,737.8 337,688.5 1,299,952.0 1,852,981.0 1,015,361.0 965,559.0 9,607,587.0
Coast Development Authority
Table 2.27- Summary of Gross Irrigation Water Requirements
Area
Gross Irrigation Water Requirements (m3)
Jan Feb Mar Apr May June Jul Aug Sep Oct Nov Dec Annual
Kilanga 29,321.4 32,006.2 47,220.0 24,414.0 96,937.1 83,295.7 34,591.0 32,321.0 111,407.0 157,143.0 84,375.3 77,276.7 810,307.3
Challa 27,655.1 20,854.7 46,836.0 26,614.1 115,316.3 94,181.2 33,121.0 21,059.8 124,090.0 83,188.2 44,828.1 40,249.2 404,834.3
Nakuruto 13,827.5 10,427.4 21,226.0 11,486.5 51,769.1 44,849.6 16,560.5 10,529.9 55,892.1 88,466.2 47,834.2 42,950.6 428,807.6
Timbilla 27,655.1 20,854.7 46,836.0 26,614.1 115,316.3 94,181.2 33,121.0 21,059.8 124,090.0 187,606.0 100,101.0 84,388.2 881,823.2
Jipe 182,914.0 182,478.6 255,588.0 108,613.7 558,157.7 542,080.3 224,689.4 184,273.5 623,351.0 864,226.0 481,360.0 485,198.0 4,692,931.0
Mwaktau 70,264.7 67,777.8 104,175.0 49,086.5 237,093.1 219,383.8 86,655.0 68,444.4 261,122.0 373,211.0 204,596.0 194,059.0 1,935,868.0
Total 351,637.8 334,399.3 521,880.0 246,828.8 1,174,589.7 1,077,971.7 428,737.8 337,688.5 1,299,952.0 1,852,981.0 1,015,361.0 965,559.0 9,607,587.0
Total Season One 3,787,697.0
Total Season Two 5,819,890.0
GRAND TOTAL 9,607,587.0
Coast Development Authority
2.12 PROPOSED IRRIGATION SYSTEMS COMPONENTS
2.12.1 Introduction
One of the major objectives of the Lake Challa Water Resources Integrated Development Project
is to develop an Irrigation System that will cover 1,120 ha of various crops as detailed in
Sections 2.6 and 2.8 of this report, and as summarized below;
Table 2.28 - Proposed Annual Irrigable Areas
Site Status Remarks Mode of irrigation Area (ha)
Kilanga Pilot
Project
Proposed New
Development
Drip (80 ha) 200
Sprinkler (120 ha)
Challa (Existing
Scheme)
Existing Extension Surface Irrigation 200
Nakuruto Proposed New
Development
Surface Irrigation 90
Timbilla(Existing
Scheme)
Existing Extension Surface Irrigation 200
Jipe Settlement
Scheme
Proposed New
Development
Surface Irrigation 930
Mwaktau Proposed New
Development
Surface Irrigation 400
Total 2,020
2.12.2 Design Criteria and Data
12.2.2.1 DRIP IRRIGATION SYSTEM
Area of Coverage
This will be designed for the 40 ha (per season) in the Kilanga Pilot Irrigation Project. This will
consist of 20 ha each of tomatoes and bananas.
Various parameters used for the design are described below in Table 2.29.
Coast Development Authority
Table 2.29 - Design Parameters for Drip Irrigation System16
Parameter Abbrev. Unit Quantity
Agro-Technical Parameters
Available Water (Amount of Water released
between Field Capacity and Wilting Point)
AWC mm/m 117
Management Allowable Deficit MAD % 50
Design (effective) Root Zone –Tomatoes (Table
2.20)
DRZ m 0.7
Design (effective) Root Zone –Bananas (Table 2.20) DRZ m 0.5
Maximum Soil Infiltration Rate IM mm/h 72.6
Gross Water Requirements (the peak is experienced
in October)- for Tomatoes(Table 2.27)
GWRT m3/month 32,469.3
Gross Water Requirements (the peak is experienced
in October)- for Bananas (Table 2.27)
GWRB m3/month 27,358.0
Total Design Gross Water Requirements GWR m3/month 59,827.3
Average CROP WATER REQUIREMENTS (TABLE 2.18)*
ETCROP mm/day 4.4
Technical Parameters
Total Area to be under Irrigation (per season) AT ha 40
Irrigation Period per week Ip day 6
Operational hours per day Td h/day 15
Spacing between drip line laterals (Tomatoes) S1 m 1.2
Spacing between drip line laterals (Bananas) S1 m 5.0 *Worked on the average value of tomatoes and bananas
12.2.2.1.1 IRRIGATION SUPPLY REQUIREMENTS
Total Design Gross Water Requirements (GWR) per month = 59,827.3 m3/month
Therefore;
GWR per day = 59,827.3 m3/month/31 days per month
=1,929.91 m3 /day…………………………………………………………(9)
The net Required Discharge is given by;
Q = GWR per day x 7 / (Id x Ip)
Where;
Q = Required Discharge in m3/h
16
Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
GWR = Gross Irrigation Requirement (mm/day) = 1,929.91 m3 /day
Id = Operational hours per day = 15 h
Ip = working days per week = 6 days
Therefore;
Q = 1,929.91 x 7 / (15 x 6) = 150.1 m3/h ……………..................…(10)
12.2.2.1.1 IRRIGATION INTERVAL
The time interval (frequency) between successive irrigations, I, is given by;
I = MAD x AWC x DRZ days = 0.5 x 117 x 0.6/4.4 = 7.98 say 8 days…...(11)
ETCROP
12.2.2.2 OVERHEAD SPRINKLER IRRIGATION SYSTEM
Area of Coverage
This will be designed for the 60 ha (per season) in the Kilanga Pilot Irrigation Project. The crops
composition is shown in Table 2.12.
The various parameters used for the design are described below in Table 2.30.
Table 2.30 - Design Parameters for Overhead Sprinkler Irrigation System17
Parameter Abbrev. Unit Quantity
Agro-Technical Parameters
Available Water (Amount of Water released between
Field Capacity and Wilting Point)
AWC mm/m 117
Management Allowable Deficit MAD % 50
Design (effective) Root Zone (Average) DRZ m 0.5
Maximum Soil Infiltration Rate IM mm/h 72.6
Gross Water Requirements (the peak is experienced in
October (Table 2.27)
GWRT m3/month 98,315.7
Average CROP WATER REQUIREMENTS (TABLE 2.18)* Average CROP WATER REQUIREMENTS
ETCROP mm/day 4.3
Technical Parameters
Total Area to be under Irrigation (per season) AT ha 60
Irrigation Period per week Ip day 6
17
Practice Manual for Water Services in Kenya– Ministry of Water and Irrigation (October 2005)
Coast Development Authority
Parameter Abbrev. Unit Quantity
Agro-Technical Parameters
Operational hours per day Td h/day 15
Spacing between overhead sprinklers on lateral S1 m 12
Spacing between overhead sprinkler Laterals S2 m 18
Discharge per overhead sprinkler Qs m3/h 1.9
Overhead sprinklers designed operating head P m 30
12.2.2.2.1 IRRIGATION SUPPLY REQUIREMENTS
Total Design Gross Water Requirements (GWR) per month = 98,315.7 m3/month
Therefore;
GWR per day = 98,315.7 3 m3/month/31 days per month
= 3,174.47 m3 /day………………………………………………………(12)
The net Required Discharge is given by;
Q = GWR per day x 7 / (Id x Ip)
Where;
Q = Required Discharge in m3/h
GWR = Gross Irrigation Requirement (mm/day) = 3,174.47 m3 /day
Id = Operational hours per day = 15 h
Ip = working days per week = 6 days
Therefore;
Q = 1,929.91 x 7 / (15 x 6) = 246.67 m3/h ……………................…(13)
12.2.2.2.2 IRRIGATION INTERVAL
The time interval (frequency) between successive irrigations, I, is given by;
I = MAD x AWC x DRZ days = 0.5 x 117 x 0.5/4.3 = 6.80 say 7 days…………(14)
ETCROP
2.12.3 Project Components
2.12.3.1 SOURCE OF ENERGY
Electrical power will be acquired from the national power grid line running south-east along the
Taveta – Challa Road through the Kenya Power and Lighting Company.
Coast Development Authority
2.12.3.2 PUMP STATION
There will be a booster Pumping Station next to the reservoir site to pump water to the overhead
sprinkler irrigation system. The pump house will house pump motors, control valves, pressure
gauges and gantry crane, and delivery manifold connected to the main piping.
2.12.3.3 DRIP IRRIGATION SYSTEM
The drip irrigation system will consist of;
1 All suitable connections to the sub-main piping.
2 Secondary piping and fittings.
3 Suitable Control heads.
Each control head shall comprise of a filtration unit with gravel (for removal of algae and
any other organic materials) and 120 mesh screen filters (for the removal of fine sand),
air-release valve, control valves, and other ancillary fittings. The unit will be fitted with
an automatic back flushing unit powered by a rechargeable battery and will be installed
on a paved, easily drainable and lockable enclosure. Manual gate valves shall be used to
control the flow of water through the laterals.
The gravel/sand media filters, providing filtration up to 200 mesh, will be self cleaning
through a “back-flush” mechanism. This mechanism will detect the drop in pressure due
to the accumulation of filtered particles and then flushes water back through the media to
dispose of clay, silt, and organic particles.
The screen filters shall be located in a manner that allows both easy access to and
removal of the filter elements from the housing and shall be cleaned manually by
removing the screen and washing it with clean water.
Each control head will be fitted with suitable fertiliser injectors and tanks.
4 Tertiary piping and fittings.
5 Driplines.
Driplines with pressure compensating and self- cleaning integral emitters (at 1.0 m
spacing) with associated fittings shall be installed. Pressure Compensation ensures that
all of the emitters inside the drip-line emit the same amount of water. Each row shall be
served by a drip-line with a spacing of 5 m between the rows for bananas, and 1.2 m for
tomatoes.
Each control head shall comprise of a filtration unit with gravel (for removal of algae and
any other organic materials) and 120 mesh screen filters (for the removal of fine sand),
air-release valve, control valves, and other ancillary fittings. The unit will be fitted with
an automatic back flushing unit powered by a rechargeable battery and will be installed
on a paved, easily drainable and lockable enclosure. Manual gate valves shall be used to
control the flow of water through the laterals.
Coast Development Authority
The gravel/sand media filters, providing filtration up to 200 mesh, will be self cleaning
through a “back-flush” mechanism. This mechanism will detect the drop in pressure due
to the accumulation of filtered particles and then flushes water back through the media to
dispose of clay, silt, and organic particles.
The screen filters shall be located in a manner that allows both easy access to and
removal of the filter elements from the housing and shall be cleaned manually by
removing the screen and washing it with clean water.
2.12.3.4 OVERHEAD SPRINKLER IRRIGATION SYSTEM
This will consist of a fixed 315 mm Ø UPVC main piping, and 160 mm Ø UPVC sub-main
piping. The sub-main piping shall be fitted with hydrants at 54 m spacing. The spacing of 18 m
between the hydrants has been adopted in order to minimize the number of hydrants to be
installed.
There shall be portable aluminium pipes fitted with full circle twin nozzle sprinklers with a
capacity of about 1.9 m3/h at 30 m head to be spaced at 12 m in a lateral and 18 m between the
laterals. This is designed to give an equivalent “rainfall precipitation” of about 8.8 mm/h.
2.12.3.5 SURFACE IRRIGATION SYSTEMS
Area of Coverage
This will be mainly designed to cover the 465 ha and 200 ha, per annum, in the Jipe Settlement
and Mwaktau Schemes, respectively. Water for irrigation will be sold in bulk to the farmers in
Challa, Nakuruto and Timbilla Schemes in order to boost their current efforts.
Design Criteria and Data
Various parameters used for the design of furrow irrigation are described below in Table 2.31,
below.
Table 2.31 - Design Parameters of Straight Furrow Irrigation
Soil
Texture
Furrow
Slope,
(%)
Furrow
Width
(m)
Furrow
Length
( m)
Flow rate
(l.p.s)
Cut off
length
(%)
Depth applied
(mm )
Coarse 0.05 –0.1 0.6 – 0.75 60 – 90 3-4.5 100 75-100
0.1 – 0.2 0.6 – 0.75 60 – 90 3 – 4.5 95 75-100
02 – 0.3 0.6 – 0.75 60 – 75 1.5 – 3 90 50-75
Medium 0.05 – .1 0.75 – 0.90 100-150 3-4 100 75-90
0.1 – 0.2 0.75 – 0.90 60-100 1.5-3 95 60-75
0.2 – 0.3 0.75 – 0.90 50-75 1.5 –2.5 90 50-75
Fine 0.05 –0.1 0.9 – 1.0 100-200 2.5 – 3.5 95 75-100
0.1 – 0.2 0.9 – 1.0 50 – 100 1.5 – 2.5 90 60-75
Coast Development Authority
Conveyance Systems
From the ground reservoir, water will be conveyed to the field through a closed pipe system for
the main distribution and secondary network leading to unlined tertiary canals. Hazen’s Williams
and Manning’s Equation are used in determining the most economical sections.
Some of the advantages of pipe line conveyance are listed below;
a) It can follow the most direct route from source to outlet points rather than following
land contours
b) Loss of land can be eliminated
c) Seepage/ evaporation losses are eliminated
Jipe Scheme
The conveyance system shall consist of UPVC 400 A (2,200 m long) main piping and UPVC 315
A (10,800 m long) secondary piping.
All the necessary tees, crosses, valves and other fittings shall be provided Farmers will be assisted
to lay strategies for the installation of the tertiary canals.
As noted in Section 2.4.2.5 of this report, the soils in the scheme are susceptible to gully erosion.
Therefore, two check dams will be constructed on each of the major gullies in the area.
Mwaktau Scheme
Like in the case of the Jipe Scheme, the conveyance system shall consist of UPVC 315 A (2,600
m long) main piping and UPVC 160 A (6,000 m long) secondary piping.
All the necessary fittings e.g. tees, crosses, valves shall be provided. Farmers will also be
expected to lay strategies for the installation of the tertiary canals.
Coast Development Authority
CHAPTER 3: DESIGN OF WATER SUPPLY SYSTEMS
Coast Development Authority
Table of Contents
CHAPTER 3: DESIGN OF WATER SUPPLY SYSTEMS ......................... 3-79
Table of Contents ............................................................... 3-17
List of Tables .................................................................. 3-81
3.1 GENERAL ........................................................................................................................ 3-82
3.2 SOURCES OF WATER ................................................................................................... 3-82
3.3 RAW WATER PIPELINE ................................................................................................ 3-83
3.4 LAKE CHALLA TANK ................................................................................................... 3-83
3.5 RESERVOIRS .................................................................................................................. 3-84
3.5.1 Reservoir Characteristics ........................................................................................... 3-84
3.5.2 Timbila Tank .............................................................................................................. 3-85
3.6 TRANSMISSION PIPELINES ......................................................................................... 3-86
3.7 DOMESTIC WATER SUPPLY ....................................................................................... 3-87
3.8 ANCILLARY WORKS .................................................................................................... 3-87
3.8.1 Administration Building and Laboratory ................................................................... 3-88
3.8.2 Staff Houses ............................................................................................................... 3-88
3.8.3 Site Drainage .............................................................................................................. 3-88
3.8.4 Workshop ................................................................................................................... 3-88
3.8.5 Pump House ............................................................................................................... 3-88
3.8.6 Access Roads ............................................................................................................. 3-88
3.8.7 Power Supply ............................................................................................................. 3-88
3.9 MATERIALS SPECIFICATIONS ................................................................................... 3-89
3.9.1 Transmission and Distribution Pipelines ................................................................... 3-89
Coast Development Authority
3.9.2 Flow Regulating Valves ............................................................................................. 3-89
List of Tables
Table 3.1 - Recommended Abstraction Rates
Table 3.2 – Capacities of Water Reservoirs
Table 3.3- Reservoirs Technical Details
Table 3.4 – Transmission Pipelines Technical Details
Table 3.5 – Water Demands
Coast Development Authority
CHAPTER 3 - DESIGN OF WATER SUPPLY SYSTEMS
3.1 GENERAL
Water will be sourced from Lake Challa and three boreholes to be sited in the Kilanga area.
Abstracted water will then be used for irrigation, domestic, livestock, environmental
conservation and wildlife within the Taveta – Mwaktau corridor.
Conveyance of this water will be by both steel and uPVC pipelines of various pressure ratings
based on the pressure requirements. There are three major areas of water supply i.e. Kilanga, Jipe
and Mwaktau, which are also the main focus for irrigation.
Irrigation system has been designed to operate by gravity save for Kilanga area where it is
pressurized.
It must also be noted that domestic water has only been supplied to areas which suffer acute
water shortages and which have otherwise not benefited from the existing TAVEVO Water and
Sanitation Company schemes. These areas include Kasokoni in Chala, Kasaani at Jipe, Kidong’u
and Mwaktau.
Between Jipe and Mwaktau the water supply system cuts through the Tsavo West National Park
managed by Kenya Wildlife Service. Between Taveta and Mwaktau a shallow water pan has
been provided for to supply wildlife with water, a phenomenon that will improve tourism in the
area as the pan will be strategically located along the Voi – Taveta Road.
3.2 SOURCES OF WATER
A combination of Lake Challa and boreholes has been identified as the sources of water for the
project.
Although Lake Challa has the capacity of supply the required demand for the entire project, to
include both irrigation and domestic water supply, trans-boundary issues had to be considered
due to the fact that Kenya shares the Lake water with Tanzania equally.
The following table shows amounts of abstractions considered from the two sources;
Table 3.1 - Recommended Abstraction Rates
Source
Volume (m3)
Annual per day per hour
1 Lake Challa 2,640,000 8,000 400
2 Boreholes 7,920,000 24,000 1,200
Total 10,560,000 32,000 1,600
The intake works will consists of two submersible pumps; one duty and the other standby; in a
pump house built on girders on a floating pontoon.
Coast Development Authority
The structural components for the intake works include the reinforced concrete retaining walls,
structural steel buttress supports, reinforced concrete shaft, floating girder platforms and floating
pontoons
Retaining walls have been designed to provide a route for the transmission line and provide
access to the intake works. Due to the steep topography, the walls have been designed with a
maximum height of 5.8 m. For stability and strength considerations both the toe and heel have
been provided to safeguard against sliding and overturning.
To further support the high walls, a steel buttress structure has been designed supporting the
walls at various intervals along the height. This in effect reduced the cantilever effect of the wall
due to the active earth pressure acting behind it. Consequently, the walls have been designed as
simply supported slabs spanning between the supporting steel structures with the maximum earth
pressure at the bottom being considered for design.
The member sizing for the buttress is such as to effectively resist the horizontal forces without
overturning, excessive deflection or failure. The foundations have similarly been designed for the
resultant forces and moments.
The girder platform has been designed to accommodate the pumps and to float on the lake. This
has been achieved by designing pontoons such that the total weight of water displaced by the
pontoons is greater than the total weight of the structure. Additionally the possibilities of
fluctuations in water levels have been addressed by providing hinges on the girder thus allowing
vertical movement.
The entire steel girder is firmly secured by anchor bolts and high tensile galvanized gay cables
fixed on the buttress structure.
The pump house is a steel framed structure with sheet cladding on the external walls and the
roof. The interior is finished using a galvanized plate welded on the steel frame to form a
watertight surface. Additional surface treatment may be specified to enhance water tightness.
3.3 RAW WATER PIPELINE
There will be two main raw water pipelines for the project. One will convey water from Lake
Challa through pumping designed to deliver 8,000 m3/day via DN 300mm steel pipeline and the
other from two boreholes to deliver 16,000m3/day via a DN 400mm pipelines.
Pipelines have been designed with a Hazen-Williams ‘C’ value of 140 for new pipes.
The three raw water pipelines merge and deliver water to a 1,000 m3 reinforced concrete tank to
be located at the top rim of Lake Challa.
3.4 LAKE CHALLA TANK
The Capacity of Lake Challa reinforced concrete as mentioned above is 1000m3. The tank is
strategically located to command flow of water via gravity to the entire project save for Mwaktau
which is at higher ground level than the tank location.
Coast Development Authority
3.5 RESERVOIRS
The project is designed to hold three major water storage earth-fill reservoirs as indicated in the
following table.
Table 3.2 – Capacities of Water Reservoirs
Site Capacity (m3)
Kilanga 75,000
Jipe 75,000
Mwaktau 65,000
The sizing of the required earth-fill reservoirs depends on the volume of water stored based on
the amount of water required to irrigate the projected areas. They will be rectangular in shape. It
is assumed that the earth removed from the reservoir bases during excavations will be
utilised in building the reservoir walls.
3.5.1 RESERVOIR CHARACTERISTICS
The reservoirs will be designed with the following characteristics;
Walls will be sloping with a ratio of 1:2 on the external side and 1:4 on the internal side.
A free board of 0.7m above the maximum water level.
The reservoirs will be lined with HDPE plastic linings in order to prevent seepage.
Width of the reservoir wall’s crown will be at least 5m wide to allow vehicles to drive
round the reservoir for maintenance and fishing purposes.
The reservoirs will be surrounded by an electrified perimeter fence in order to prevent
wild animal access.
Based on the water quality analysis, it is envisaged that there be will minimal deposits at the
bottom of the reservoirs in form of sedimentation. However, sludge/silt accumulated in the
reservoir over time will be carefully scrapped manually to ensure that the HDPE lining is not
damaged.
The following table gives the technical details of each reservoir in the proposed project areas.
Coast Development Authority
Table 3.3- Reservoirs Technical Details
Description Unit Kilanga
Reservoir
Jipe
Reservoir
Mwaktau
Reservoir
Reservoir Volume m3 75,000 75,000 65,000
Total Area m2 36,000 36,000 20,250
Length m 225 225 150
Width m 160 160 135
Water Surface Area m2 18,780 18,780 16,505
Reservoir Area Base m2 9,750 9,750 8,125
Water Depth m 5.3 5.3 5.3
Free Board m 0.7 0.7 0.7
Total Embankment Height m 6.0 6.0 6.0
Embankment slopes
(internal/external) 1:4 & 1:2 1:4 & 1:2 1:4 & 1:2
Plastic Lining Area
Total Embankment Area m
2
20,915
20,915
18,475
Total Embankment Length m 622 622 592
3.5.2 TIMBILA TANK
The reinforced concrete tank is designed to have a capacity of 1000 m3
to be supplied through a
DN 220mm PVC pipe. The water is intended for irrigation in the Timbila area.
However, during the design stage, no land for irrigation was identified due to settlements and
many permanent houses developed in the area. However, a provision has been made at the outlet
end of the tank.
Coast Development Authority
3.6 TRANSMISSION PIPELINES
The details of the transmission pipelines are as shown in the table below.
Table 3.4 – Transmission Pipelines Technical Details
Pipeline Description
PIPELINE
Diameter
(mm)
Length (m) and Pressure Ratings uPVC
Class D PN25 PN16 PN10
Lake Challa- Challa Tank
Rising main 300
232
Challa - Jipe Pipeline 500 14000
Jipe - Mwaktau – Kwa
Mnengwa Pipeline
450 2400 7200 7200
400
22300
300
3,440
100
1,560
75
1,560
50
1,556
Kilanga - Challa Pipeline
450 2,000
400
3,500
Kidongu Pipeline 75 1,444
Jipe Reservoir Pipeline 500 225
Mwaktau Reservoir
Pipeline 300 301 301
Timbila Tank Pipeline 200
615
KWS pipeline to water pan 75
1,000
Kilanga – Existing Challa
Irrigation scheme 300
3,000
Mwaktau Tank Inlet pipe 150
250
Nakuruto Tank Inlet pipe 150
1,000
Jipe Tank Inlet pipe 50
675
Water is conveyed in all the above pipelines by gravity except for Jipe – Mwaktau – Kwa
Mnengwa pipeline which is a pumping mains from Jipe at an altitude of 865 masl to Mwaktau at
1120 masl i.e. an elevation difference of 255m. The rest of the pipelines are served by Lake
Challa which stands at a height of 914 masl.
To minimise costs, the pipeline has been designed for various pressure ratings ranging from PN
30 to PN 25 according to the pressure requirements at those specific areas.
Coast Development Authority
3.7 DOMESTIC WATER SUPPLY
Domestic water supply has also been incorporated in the project for only areas that experience
acute water shortages. Areas of concern that have been considered include Kasokoni, Kasaani in
Jipe, Kidongu, Mwaktau Trading Center and Kwa Mnengwa.
In all these identified locations, a water tank has been provided, strategically located and
designed to allow the supply in the respective area by gravity.
It is important to note that an elevated steel water tank with a capacity of 200m3 has been
provided for in Kasokoni, Mwaktau and Kasaani area and a 250m3 concrete tank provided for at
Kwa Mnengwa and Kidong’u, located at the trading center and Kidong’u Hill respectively.
Water demand projections for the ultimate year of 2035 were calculated focussing on the areas of
concern. This was derived from population projection using a population growth of 1.8%.
During computation of the demand requirements; irrigation demand and domestic water were
both considered simultaneously based on the total available water from the two sources.
Table 3.5 shows the water irrigation and domestic demands for the various sites.
Table 3.5 – Water Demands
Area
Water Demands (m3/year)
Irrigation Domestic Others Total
1 Kilanga Pilot Project 810,307 - - 810,307
2 Challa Irrigation Project 881,823 - - 881,823
3 Nakuruto/Kasokoni 404,834 58,552 - 463,386
4 Timbilla/Kidong’u 881,823 44,297 - 926,120
5 Jipe 4,692,931 53,351 - 4,746,282
6 Mwaktau 1,935,868 120,400 - 2,056,268
7 Msorongo - 125,369 - 125,369
8 Environment Conservation 45,000 45,000
9 Wildlife (Tsavo National Park) 91,250 91,250
10 Fisheries 20,000 20,000
Total 9,607,587 401,969 136,250 10,145,806
3.8 ANCILLARY WORKS
The typical civil and ancillary works proposed include the following:-
Coast Development Authority
3.8.1 ADMINISTRATION BUILDING AND LABORATORY
The administration building is designed to house an office, laboratory and a toilet with separate a
shower compartment. This has been provided for in Kilanga, Jipe and Mwaktau.
3.8.2 STAFF HOUSES
2 No. twin housing will be provided for the staff operating the works at Kilanga, Jipe and
Mwaktau.
3.8.3 SITE DRAINAGE
Foul water from the administration building and staff houses will be channelled into a separate
system discharging into a septic tank and soak away pit.
3.8.4 WORKSHOP
A workshop has also been provided for to help in operation and maintenance purposes of various
items within the facility in Kilanga, Jipe and Mwaktau.
3.8.5 PUMP HOUSE
A pump house has been provided for the in the Jipe site. In addition, a 1,000 m3 concrete tank to
facilitate pumping water to Mwaktau has also been included.
3.8.6 ACCESS ROADS
New site access from the road adjacent to the site will be constructed. Service roads within the
treatment works will be constructed to single seal bitumen standards.
Access to Kilanga will however involve rehabilitation of an existing 3 km long gravel road to
motorable status.
3.8.7 POWER SUPPLY
An 11KV/415V electrical power line exists in the vicinity of Kilanga, Jipe and Mwaktau sites
and this will be utilized for power supplies to the works. Arrangements will be made with Kenya
Power Company for power supply to the respective sites.
Coast Development Authority
3.9 MATERIALS SPECIFICATIONS
3.9.1 TRANSMISSION AND DISTRIBUTION PIPELINES
The pipelines shall be Steel Pipes suitable for working pressures ranging from 10 to 25 bar with
their respective flanges and other fittings of equivalent pressure ratings.
Pipes shall be manufactured to BS EN 1561 250 cast iron, suitable for on or off seat installations
as shown on the drawings.
3.9.2 FLOW REGULATING VALVES
Flow Regulating Valves will be mechanically operated incorporating a cylindrical sleeve or
needle valve. They will be suitable for operating at any flow for long periods of time without
vibration or cavitation. They shall be designed for minimal maintenance, safe energy dissipation
and low operating effort. Operation shall be manual via a removable hand wheel. Valve bodies
shall be cast iron or ductile iron with stainless steel operating trim.
Coast Development Authority
CHAPTER 4: COST ESTIMATES AND PROJECT PHASING
Coast Development Authority
Table of Contents
CHAPTER 4 – COST ESTIMATES AND PROJECT PHASING
4.1 GENERAL ....................................................................................................................................... 4-92
4.2 BASIS FOR ESTIMATION OF COSTS ......................................................................................... 4-92
4.3 SUMMARY OF ESTIMATED COSTS .......................................................................................... 4-92
4.3.1 Intake Works .................................................................................... 4-93
4.3.2 Developing and equipping Boreholes ............................................................... 4-93
4.3.3 Transmission Pipelines ......................................................................................... 4-93
4.3.4 Civil Works ............................................................................................................... 4-93
4.3.5 Irrigation Works ..................................................................................................... 4-93
4.3.6 Trans-boundary Issues and Environment and Resettlement ...................... 4-93
4.3.7 Forestry and Fisheries .......................................................................................... 4-94
4.4 ITEMISED WORKS COST ESTIMATES ...................................................................................... 4-94
4.5 PROJECT PHASING....................................................................................................................... 4-98
4.5.1 INTRODUCTION ....................................................................................................... 4-98
4.5.2 COST BY PHASES ..................................................................................................... 4-98
Coast Development Authority
CHAPTER 4 – COST ESTIMATES AND PROJECT PHASING
4.1 GENERAL
The project development will consist of irrigation works in Kilanga, Jipe and Mwaktau with a
pressurised system in Kilanga while the other two will be operated through gravity. Improvement
of the existing Challa Irrigation scheme has also been included as part of this project.
There will be three sites in total constructed for the operation and coordination of the project at
Kilanga, Jipe and Mwaktau, respectively. These sites will be fully equipped with administration
and laboratory buildings, staff houses, workshops and stores.
Domestic water supply has also been provided for areas which currently experience acute water
shortages within the project area such as Kasaani near Jipe, Kidong’u and Mwaktau areas.
Water for wild animals at Tsavo West National Park has also been provided for through a shallow
water pan to be located near Murka area along the Taveta – Voi Road.
The project also encompasses forestry and fishing activities in Taveta and Mwaktau areas.
4.2 BASIS FOR ESTIMATION OF COSTS
For the preparation of Cost Estimate, quantities for the various items in Bills Nos. 2 - 13 have been
calculated from drawings while for Bill No.1 the quantities have been estimated using the
Consultant’s experience on similar work in the past. The rates used in estimation have been derived
from unit rates and works of similar kind carried out by the Consultant in the recent past.
The rates for various items of works have been adopted after taking into account the current rates
of materials, labour and equipment prevalent in the project. A lump sum provision for some items
which cannot be quantified at this stage of project preparation are based on the experience of
consultants and also takes into consideration the current rates.
4.3 SUMMARY OF ESTIMATED COSTS
Intake Works at Lake Challa - Ksh 73.80 million
Development and equipping three Boreholes - Ksh 73.74 million
Transmission Pipelines - Ksh 1,076.05 million
Civil Works including reservoirs - Ksh 976.24 million
All the above costs are without any escalations.
Coast Development Authority
4.3.1 INTAKE WORKS
Lake Challa Intake Works include submersible pumps in a pump house fully equipped with a
control panel at the surface of Lake Challa designed on a floating pontoon and a series of
reinforced concrete retaining walls cascading from the top of the rim to the to the lakeshores
reinforced by steel buttresses and girders. This adds up the cost by a further Kshs. 87.86 million
which includes for the required electromechanical installation.
4.3.2 DEVELOPING AND EQUIPPING BOREHOLES
Three boreholes will be developed in the Kilanga and Challa areas. They will be equipped with
all necessary pumping units, piping, associated accessories and other ancillary equipment all at
an estimated cost of Ksh 73.74 million.
4.3.3 TRANSMISSION PIPELINES
Transmission pipelines will be composed of steel pipes of various pressure ratings that is PN 30,
PN 25, PN 10 and uPVC Class D pipelines. The total cost of pipelines is therefore Ksh. 1,076.05
million.
4.3.4 CIVIL WORKS
Under civil works, the costs encompass the cost of reservoirs at Kilanga and Jipe, both of 75,000
m3
capacity and at Mwaktau with a capacity of 65,000 m3. It also includes for roadworks, onsite
water supply, foul water drainage, septic tanks and fencing (where fencing is mostly electric
fencing especially to areas prone to wild animals attack) at Jipe and Mwaktau areas. The total cost
of this work is estimated to be Kshs 976.24 million.
4.3.5 IRRIGATION WORKS
Irrigation works will involve the cost of infrastructure for irrigation. It also includes three
boreholes, one to supply the irrigation waters into Kilanga reservoir, and the other for Jipe and
Mwaktau. A pumping system for irrigation at Kilanga and an extension pipeline 3 km long for
expansion of the existing Challa Irrigation scheme.
Main pipelines and laterals including the necessary valves and fitting for both Jipe and Mwaktau
irrigation schemes have also been included. The total cost of Irrigation is therefore Ksh 205.59
million.
4.3.6 TRANS-BOUNDARY ISSUES AND ENVIRONMENT AND
RESETTLEMENT
A provision has been allowed as detailed in the Environmental Impact Assessment report on
Implementation of Trans boundary Action Plan due to the shared water of Lake Challa with
Tanzania and also in the implementation of the Environmental Mitigation Measures, all valued at
Ksh. 22.6 Million. A further Ksh. 10 Million has been allowed for the construction of a check dam
of a check dam on River Karimeri to be located about 200 m upstream of the bridge on the Challa
Taveta Road. The dam will mitigate the flooding effects and also serve as a water reservoir.
Coast Development Authority
A provisional sum of Kshs 410 Million has been added for the resettlement of the affected
population.
4.3.7 FORESTRY AND FISHERIES
Cost of re-afforestation in identified areas and the setting up of a fisheries industry in the area has
also been factored in the works costs estimates. A provision of Kshs. 75 Million has been factored
in the project costs for this purpose.
4.4 ITEMISED WORKS COST ESTIMATES
Intake Works
Sl No Item of Works Amount (Ksh)
1 Retaining walls, steel buttress and box girder, pump
house, pumps and raw water mains.
73,808,498.00
2 Electromechanical Installations 14,057,500.00
Total 87,865,998.00
Boreholes
Sl No Item of Works Amount (Ksh)
1 Development of three boreholes @ Kshs 6,262,000 18,786,000.00
2 Equipping three boreholes @ Kshs 18,319,680 54,959,040.00
Total 73,745,040.00
Irrigation Works
Sl No Item of Works Amount (Ksh)
1 Kilanga Irrigation Scheme 59,111,100.00
2 Expansion of Existing Challa Irrigation Scheme 10,890,000.00
3 Jipe Irrigation Scheme 118,580,000.00
4 Mwaktau Irrigation Scheme 17,013,000.00
Total 205,594,100.00
Coast Development Authority
Transmission Pipelines
Sl No Item of Works Amount (Ksh)
1 Kilanga - Challa Pipeline 67,611,336.00
2 Challa - Jipe Pipeline 329,337,106.00
3 Kidong'u Tank Pipeline 11,753,939.00
4 Timbila Reservoir Pipeline 13,303,642.00
5 Jipe Reservoir Pipeline 6,087,396.00
6 Jipe - Mwaktau - Kwa Mnengwa Pipeline 627,310,466.00
7 Mwaktau Reservoir Pipeline 4,831,104.00
Total 1,076,051,327.00
Kilanga Works
Sl No Item of Works Amount (Ksh)
1 Kilanga Reservoir – 75,000m3 271,796,760.00
2 Administration and Laboratory Building 2,761,060.00
3 Workshop and Store 4,524,290.00
4 Gate House 1,978,430.00
5 Civil Works 31,388,351.00
6 Electromechanical Installations 22,261,700.00
Total 312,448,891.00
Jipe Works
Sl No Item of Works Amount (Ksh)
1 Jipe Reservoir – 75,000m3 338,300,620.00
2 Administration and Laboratory Building 2,761,060.00
3 Workshop and Store 4,499,050.00
4 Gate House 1,978,430.00
5 Civil Works 9,893,351.00
6 1,000m3 Reinforced Concrete Tank 15,086,240.00
7 Pump House 7,898,875.00
8 Pumps 29,299,600
9 Electromechanical Installations 26,358,400.00
Total 409,649,336.00
Coast Development Authority
Mwaktau Works
Sl No Item of Works Amount (Ksh)
1 Mwaktau Reservoir – 65,000m3 315,195,170.00
2 Administration and Laboratory Building 2,773,060.00
3 WorKshop and Store 4,183,090.00
4 Gate House 1,978,430.00
5 Civil Works 9,668,351.00
6 Electromechanical Installations 26,358,400.00
Total 333,798,101.00
Reinforced Concrete Tanks
Sl No Item of Works Amount (Ksh)
1 Challa Tank - 1000m3 23,272,115.50
2 Nakuruto Tank - 1000m3 15,285,739.50
3 Timbilla Tank - 1000m3 15,527,740.00
4 Kidong’u Tank – 250m3 6,003,992.00
5 Kwa Mnegwa – 250m3 5,709,114.00
Total 74,344,286.00
Elevated Steel Tanks
Sl No Item of Works Amount (Ksh)
1 Kasaani – 250m3 3,780,055.00
2 Mwaktau – 250m3 3,472,512.00
Total 7,252,567.00
Coast Development Authority
LAKE CHALLA WATER RESOURCES INTEGRATED DEVELOPMENT PROJECT COST
Sl No Item of Works Amount (Ksh)
1 Bill No. 1 - Preliminary and
General Items
347,066,450.00
2 Bill No. 2 - Intake Works 73,808,498.00
3 Bill No. 2B - Electromechanical
Works - Intake Works
14,057,500.00
4 Bill No. 3 - Challa Tank 23,272,115.50
5 Bill No. 4 - Transmission Pipelines 1,076,051,327.00
6 Bill No. 5 - Kilanga Works 312,448,891.00
7 Bill No. 5B - Electromechanical
Works - Kilanga Works
22,261,700.00
8 Bill No. 6 - Timbila Tank 15,285,739.50
9 Bill No. 7 - Kasaani Tank 3,780,055.00
10 Bill No. 8 - Kidong'u Tank 6,003,992.00
11 Bill No. 9 - Jipe Works 409,649,336.00
12 Bill No. 9B -Electromechanical
Works -
Jipe Works
26,358,400.00
13 Bill No. 10 - Mwaktau Tank 3,472,512.00
14 Bill No. 11 - Mwaktau Works 333,798,101.00
15 Bill No. 11B - Electromechanical
Works -
Mwaktau Works
18,812,300.00
16 Bill No. 12 - Kwa Mnengwa Tank 5,709,114.00
17 Bill No. 13 – Irrigation and
boreholes
279,339,140.00
18 Bill No. 14 - Kasokoni Tank 3,780,055.00
19 Bill No. 15 - Nakuruto Tank 15,285,739.50
Sub-Total 1 2,960,540,966.00
Add 10% Contingency 296,054,096.60
Total Cost Estimate of The
Project
3,289,265,062.60
Coast Development Authority
4.5 PROJECT PHASING
4.5.1 INTRODUCTION
The major objective of the Lake Challa Water Resources Integrated Development Project is to
develop an Irrigation System that will cover 1,010 ha of various crops as detailed in the irrigation
component sections of this report,
For speedy implementation of the Project, it is proposed that the project be implemented in three
phases as described below;
4. Phase One – to cover Kilanga Pilot Irrigation Project and the existing Challa Irrigation
Scheme
5. Phase Two – to cover Timbila and Jipe Irrigation Schemes (including provision of
irrigation and domestic water within the areas covered by the pipelines)
6. Phase Three – to cover Mwaktau Irrigation Schemes (including provision of domestic
water within the areas covered by the pipelines)
4.5.2 COST BY PHASES
The project components and respective costs as itemized by phases are tabulated below.
Sl
No Item of Works
Phase I Phase II Phase III
Kilanga and
Challa
Jipe &Timbila
Mwaktau
1 Bill No. 1 -
Preliminary and
General Items
115,688,816.83 115,688,816.83 115,688,816.83
2 Bill No. 2 - Intake
Works
73,808,498.00
3 Bill No. 2B -
Electromechanical
Works - Intake
Works
14,057,500.00
4 Bill No. 3 - Challa
Tank
23,272,115.50
5 Bill No. 4 -
Transmission
Pipelines
67,611,336.00
376,298,421.00
632,141,570.00
6 Bill No. 5 - Kilanga
Works
312,448,891.00
7 Bill No. 5B -
Electromechanical
Works - Kilanga
22,261,700.00
Coast Development Authority
Sl
No Item of Works
Phase I Phase II Phase III
Kilanga and
Challa
Jipe &Timbila
Mwaktau
Works
8 Bill No. 6 - Timbila
Tank
15,285,739.50
9 Bill No. 7 - Kasaani
Tank
3,780,055.00
10 Bill No. 8 -
Kidong'u Tank
6,003,992.00
11 Bill No. 9 - Jipe
Works
409,649,336.00
12 Bill No. 9B -
Electromechanical
Works - Jipe Works
26,358,400.00
13 Bill No. 10 -
Mwaktau Tank
3,472,512.00
14 Bill No. 11 -
Mwaktau Works
333,798,101.00
15 Bill No. 11B -
Electromechanical
Works - Mwaktau
Works
18,812,300.00
16 Bill No. 12 - Kwa
Mnengwa Tank
5,709,114.00
17 Bill No. 13 –
Irrigation and
Boreholes
94,582,780.00 167,743,360.00 17,013,000.00
18 Bill No. 14 -
Kasokoni Tank 3,780,055.00
19 Bill No. 15 -
Nakuruto Tank 15,285,739.50
Sub-Total 1 612,593,524.00 1,251,012,028.00 1,126,635,413.83
Add 10%
Contingency
61,259,352.00 125,101,202.00 112,663,541.38
Total Cost 673,852,876.00 1,376,113,231.00 1,239,298,955.22
Coast Development Authority
Components of Phases
Phasing Main Components Cost Kshs.
Phase 1
Kilanga Irrigation Scheme
673,852,876.00
Improvement of existing Challa Irrigation
Scheme
Fishing and Forestry
Phase 2
Jipe Irrigation Scheme
1,376,113,231.00
Timbila Irrigation Scheme
Nakuruto Irrigation and Domestic Water
Kidong'u Domestic Water
Jipe Domestic Water
Fishing and Forestry
Phase 3
Mwaktau Irrigation Scheme
1,239,298,955.22
Mwaktau Domestic Water
Kwa Mnengwa Domestic Water
KWS Drinking Water for Animals
Fishing and Forestry
Total 3,289,265,062.00