LACE DA working days28-30 September 2010, Ljubljana
Local data assimilation system in Slovenia
LACE DA working days28-30 September 2010, Ljubljana
Facts
• 4.4 km, 43 levels
• 439*421 points / 1931.6 * 1852.4 km
• Aladin cy35t1
• ALARO 3MT
• Timestep: 180s
• 3h ARPEGE LBC
LACE DA working days28-30 September 2010, Ljubljana
Observations
• All OPLACE observations, except METOP and NOAA-19
• local NON-GTS SYNOP data
• No assimilation of SYNOP T2m and RH2m in 3DVAR
LACE DA working days28-30 September 2010, Ljubljana
SMS assimilation suite
LACE DA working days28-30 September 2010, Ljubljana
ODB / bator
• Merge of locally prepared obsoul and OPLACE for conv
• Created by subbases: conv amdr geow wpro sats sevb
• Fix in BATOR to avoid crash in case of no observations selected by lamflag
• Blacklisting not modified (from Hungary)
LACE DA working days28-30 September 2010, Ljubljana
Screening & minimization
• Constant bias correction: VARBC tested, but not yet sufficiently validated
• NITER=70, NSIMU=80
• B matrix computed for July 2007 (~ 450 forecast differences), (downscaled) ensemble method
• REDNMC=1.3 (not tuned yet)
LACE DA working days28-30 September 2010, Ljubljana
Verification
2m RH and T assimilation?
FF 700
Z 700
T 850
LACE DA working days28-30 September 2010, Ljubljana
Problems
• “Packing bug”
– Negative Ts at some grid point
– Disappears if fields not packed (NVGRIB=0)
– Reproducible on some clusters, on others not
– Final solution: not pack surface fields (~10 % increase in file size)
LACE DA working days28-30 September 2010, Ljubljana
Developments I• LSAF Albedo
LACE DA working days28-30 September 2010, Ljubljana
Developments II• Snow assimilation (CANARI + LSAF)
LACE DA working days28-30 September 2010, Ljubljana
Near future tasks
• Production suite + visualization and verification in operations
• Validate VARBC
• Improve observational usage
• Estimate/tune observational and background errors
• Add CANARI snow analysis
• Test and validate 3 hour RUC
LACE DA working days28-30 September 2010, Ljubljana
Longer term
• Assimilate aircraft data, collected by a radar in Ljubljana airport (not really AMDAR)
• Test IASI and probably use it (will have 1py in 2011 - 2012)