49
GENG3830 Engineering Project Management Project Management Lecture 4 Procurement, Tendering and Contracts

L4 - Tendering Contracts and Procurement (Rev 3)

  • Upload
    de

  • View
    273

  • Download
    3

Embed Size (px)

DESCRIPTION

L4 - Tendering Contracts and Procurement (Rev 3)

Citation preview

  • GENG3830

    Engineering Project Management

    Project Management Lecture 4

    Procurement, Tendering and Contracts

  • 2

    Learning Objectives

    This lecture provides an overview of procurement, tendering and

    contracts.

    By the end of this session you should be able to:

    List and describe the different methods of procurement

    Describe the different types of contracts and factors in selecting the preferred contract type for a particular project

    Demonstrated an understanding of contracts, tendering, tender assessment and contract award.

  • 3

    Contents

    Procurement

    Contracts

    Tender / bid processes

    Bid / tender evaluation and assessment

    Contract negotiations

    Selection and contract award

  • 4

    Why Do We Care? Example 1

    Procurement, and in particular contracts, can have a huge effect on

    a project and on a company.

    2007 Clough engineering settled a contract dispute of $250M against it relating to the

    BassGas development off SE Victoria.

    It was reported that the settlement cost

    Clough $70M to the joint venture (client).

    Also worth noting that project commissioning was delayed for 2 years

    and the project costs escalated from $400M to $750M following the

    dispute which led to Clough being sacked as construction contractor

    so, as with most cases, the dispute cost both parties significantly.

    http://www.theaustralian.com.au/business/mining-energy/clough-settles-its-bassgas-dispute/story-

    e6frg9df-1111114314362

  • 5

    Why Do We Care? Example 2

    Oracle Corporation (US) was accused of failing to give promised

    discounts under a supply agreement to the US federal government

    resulting in the government paying more for products that it

    should have.

    In 2011 Oracle agreed to pay around $200M to the US Government

    to settle the contract dispute.

    http://losangeles-businessattorney.com/california-contract-litigation-oracle-loses-big-in-

    contract-dispute-with-the-feds/

  • 6

    Why Do We Care? Example 3

    In 2011 Qantas grounded its entire fleet for almost 2 days after a

    contract dispute with its employees.

    The grounding was estimated to have cost Qantas $20M per day,

    with the total contract dispute estimated have cost nearly $200M in

    just FY2011/12.

    The grounding was also estimated to have cost $250M per day to

    the Australian economy.

    http://www.news.com.au/business/industrial-disputes-costly-for-qantas/story-e6frfm1i-

    1226207880100

    http://www.theaustralian.com.au/business/aviation/cost-of-qantas-crisis-hits-250m-a-day-and-

    rising/story-e6frg95x-1226180980349

  • 7

    Procurement

    Procurement may be defined as:

    the act or process of obtaining goods and/or services

    Engineers may find themselves as either the client, supplier, or

    both. Therefore, an understanding of both parties (the client and

    supplier) in the procurement process is important.

  • 8

    Procurement

    Procurement requires the client to make specific choices

    concerning their strategy for:

    What works, if any, they want to outsource

    How they want the works undertaken

    How they want to pay for the works

    How they want to allocate the works

    How they want to enforce the agreement

    Often the first decision associated with procurement on a project is

    whether to use internal (in-house) resources or procure external

    resources.

  • 9

    Procurement Decisions

    Procurement decisions are typically made taking into account

    organisational culture/practice, availability of resources and techno-

    economic feasibility issues.

    Engineering economic techniques such as Net Present Value,

    Interest Rate of Return, Cost Benefit Analysis and Sensitivity

    Analysis are relevant here.

  • 10

    Techno Economic Feasibility Analysis

    Large project investment decisions represent major commitments

    of resources and have serious consequences on the profitability

    and financial stability of a company. In the public sector, such

    decisions also affect the viability of project investment programs

    and the credibility of the agency in charge of the programs.

    It is therefore important to evaluate potential projects rationally

    with regard to both:

    the economic feasibility of individual projects, and

    the relative net benefits of alternative and mutually exclusive projects.

    A techno economic feasibility analysis (study) examines technical,

    commercial and financial aspects of different project options.

    It is generally the primary report for the formulation of the

    investment proposal and a key step in defining the project and/or

    procurement strategy.

  • 11

    Techno Economic Feasibility Analysis -

    Example

    Deciding whether to purchase, hire/lease or refurbish a piece of

    manufacturing equipment.

  • 12

    Procurement Issues and Considerations

    If external resources are to be used the following should be considered

    and addressed:

    Defining the scope

    Identifying procurement options

    Economic analysis of available options

    Apportioning risk (between the client and supplier / contractor)

    Detailing any procurement conditions (e.g. Conditions of Contract)

    Detailing any applicable accreditation / prequalification requirements and/or standards.

    Determining tendering or bidding and assessment procedures (if any)

    Ensuring probity and confidentiality of the procurement process

  • 13

    Contracts

    Procurement of external resources will generally involve some form

    of contract between the client and supplier.

    There are many definitions of a contract including:

    A legally binding agreement made between two or more parties, by

    which rights are acquired by one or more parties to act on the part of

    the other(s)

    An agreement giving rise to legally enforceable obligations binding

    the parties to it

    All organised activities concerned with demolition, building,

    landscaping, civil engineering, process engineering, mining and

    heavy engineering

  • 14

    Contract Basics

    Contracts:

    Define what will be delivered (Scope) and when (Time)

    Define the standards to be complied with (Quality)

    Define how much will be paid and when (Cost)

    Assign risks to the contract parties (Risk)

    Define procedures, roles and responsibilities for management of the contract

  • 15

    Contracts

    For a contract to be legally binding the following elements must

    exist:

    Offer and acceptance acceptance must be unconditional otherwise it is a counter offer

    Intent to create a legal relationship

    Consideration something of value must be given in return for something of value that is offered

    Legal capacity the parties must be legally competent entities (individuals over 18 years old, companies, government agencies)

    Legality of objects the object of the contract must be legal (i.e. you cant have a contract to do something illegal)

  • 16

    Different Contract Types

    Supply only (sales) contracts (e.g. supply of 100 timber power poles)

    Plant hire agreements and contracts (e.g. hire of a dump truck)

    Consultant and Profession services contracts (e.g. environmental assessments, design)

    Construction contracts

    - construct only (i.e. Shortland to Sandgate road project)

    - design and construct (D&C) or EPC - engineer, procurement and

    construction (i.e. Kempsey Bypass Bridges, Triple J Studio

    Refurbishment)

    - design construct and maintain (DCM) (e.g. Karuah Bypass,

    Kurnell Desalinisation Plant)

    - build own operate transfer (BOOT) (e.g. M7)

    Alliance contracts (part of Hunter Expressway, Hunter8Alliance rail project, Air Warfare Destroyer Alliance )

  • 17

    Different Contract Types

    Internal

    Resources

    Construct Only

    Contract

    Design and

    Construct

    DCM and

    BOOT

    ALLIANCE

  • 18

    Alliance Contracts as an Example

    Alliance contracting is gaining increasing prominence in Australia with

    many large Alliances currently underway or recently completed.

    Alliances are normally reserved for higher risk projects, especially

    where residual risk during the construction or implementation phases

    cannot be quantified or allocated to industry.

    The principles of Alliance contracting are:

    A focus on project outcomes

    Innovative contractual arrangements

    Success of projects measured against key performance indices

    An emphasis on openness and communication between participants

    An equitable risk/reward balance that aligns the commercial interests of the parties.

    Access to and contribution by the best resources of each participant with an emphasis on working together efficiently

  • 19

    Hunter8 Alliance (Rail)

    ARTC (client) has formed the Hunter 8 Alliance with John Holland Pty

    Ltd (construction) and GHD Pty Ltd (designer) to design and build the

    10.8 km, Maitland to Whittingham Third Track project.

    http://www.hunter8alliance.com.au/

  • 20

    Selection of Contract Type

    Selecting a particular form of contract depends on many factors

    which may include:

    The client, their organisational structure, resources and expertise

    The risk profile of the works

    The value of the works

    The availability of suitable contractors

    The level of expertise / specialisation required

  • 21

    Contract Documentation

    The contract documents usually include:

    Formal Instrument of Agreement (setting out all of the documents which comprise the Contract Documents, and the execution

    clauses)

    Conditions of Contract (setting out the detailed contractual terms)

    Specifications

    Reference documents (such as Standards, Guides, etc)

    Drawings

    Post-tender Correspondence

    However, the specific terms of the Contract and documentation

    used will likely vary from project to project, and particularly

    industry to industry.

  • 22

    Standard Contracts

    In the majority of engineering (and many non-engineering)

    industries in Australia, standard contracts are available and widely

    used. Generally, these standard contracts have been developed to

    reduce the costs associated with contract preparation and contract

    administration plus minimise contractual disputes.

    Typically these standard contracts consist of:

    a set of standard clauses which generally do not get changed from project to project

    a deed which both parties sign

    one or more annexure which contain the project specific information.

    Some examples of the above have been loaded onto Blackboard.

  • 23

    Standard Contracts

    In Australia, standard contracts are primarily developed by:

    Standards Australia

    Government authorities

    Professional organisations (such as MBA, NSW Dept of Fair Trading)

    Individual companies

  • 24

    Conditions of Contract - Standards Australia

    Many, many standard contracts are available. For example, the

    following is a list of some relevant Australian Standards:

    General Construction (AS2124, AS4000)

    Design and Construct (AS4300 series)

    Supply and Equipment (AS4910, AS/NZS4911, AS4912)

    Management and Construction (AS4915, AS4916)

    Trade Contracts (AS4917, AS4918)

    Management of Assets (AS4919, AS4920, AS4921)

    Consultant Contracts (AS4121, AS4122)

    Miscellaneous (AS4120, AS4608)

    Many of the above also have associated sub-contract conditions

    (i.e. AS4901 relates to AS4000) to ensure that the provisions of the

    main contract are transferred to any sub-contracts.

  • 25

    Standards Australia - Examples

    AS4000 General Conditions of Contract.

    AS4910 General Conditions of Contract for the Supply of

    Equipment with installation.

    AS4917 Construction Management Trade Contract - General

    Conditions

    AS4919 General Conditions of Contract for the provision of asset

    maintenance and services (Superintendents version).

    AS4122 General Conditions for the Engagement of Consultants.

  • 26

    Accreditation / Pre-Qualification

    Many companies, in particular government agencies, have

    introduced accreditation or pre-qualification requirements. These

    have been introduced to assist in establishing minimum quality

    standards for contractors, consultants and suppliers. They also have

    the effect of reducing the number of companies able to bid /

    tender for projects and therefore reduce costs for both the client

    and potential tenderers.

    Examples include:

    Australian Defence Force, Telstra, ANSTO, Roads and Maritime Services NSW, VicRoads, Queensland Main Roads, ACT Urban

    Services, Hunter Water, Energy Australia, NSW Department of

    Services, Technology and Administration

  • 27

    Accreditation / Pre-Qualification

    In order to achieve accreditation through a particular agency a

    contractor, consultant or supplier is typically required to obtain 3rd

    party certification or client-specific pre-qualification. This process

    normally involves providing evidence that they have a quality

    system of the required standard and have experience and capability

    in the particular area. Certification audits may also be required.

    Typical accreditations include:

    ISO 9000 (quality system)

    RMS R40 (Roadworks projects to $40M) and others

    NATA registration for testing laboratories

    Building and Construction OHS Accreditation Scheme (Federal)

    Workcover licenses for builders, plumbers, electricians, plant operators, HV electrical workers, etc

  • 28

    The payment method used under particular contract typically is one

    of the following

    Lump sum (fixed price)

    Schedule of rates

    Cost plus

    Incentive based

    Alliance (cost recovery plus profit/loss sharing)

    Combination of the above

    Methods of Payment

  • 29

    Standard Contract Conditions (Clauses)

    Roles and responsibilities

    Nature of the contract

    Contract documents

    Intellectual property

    Insurance

    Site

    Time management

    Working hours

    Quality

    Variations

    Payment

    Dispute resolution

  • 30

    Standard Contract Conditions / Clauses

    The Table of Contents from two typical major standard contracts

    are included on Blackboard:

    AS4000 General Conditions of Contract (used in private industry)

    GC21 General Conditions of Contract (used by many government agencies)

    Administration of contracts and some specific contract clauses to

    be aware of will be discussed in detail next week.

  • 31

    Contract Clauses Example 1

  • 32

    Contract Clauses Example 2

  • 33

    Contract Clauses Example 3

  • 34

    Contract Clauses Example 4

  • 35

    Contract Annexure Example

  • 36

    Typical Tendering / Contracting Process

    On very complex and/or high risk projects a two stage process may

    be used to vet tenderers. In these cases stage 1 may involve

    requesting and assessing Expressions of Interest (EOI) prior to the

    undertaking tender process above. In this case only short-listed

    companies would be invited to participate in the 2nd stage (i.e.

    formal request for tender, submission of tender, etc).

  • 37

    Care should be taken so that the work to be undertaken under a

    contract is clearly and logically defined with regard to:

    Request for Tender / Invitation to Bid

    Each item of work to be carried out

    Methods of measurement and payment to be use

    Standards of quality to be achieve

    The general obligations to be met by the parties

  • 38

    Tender assessment is, in many ways, a risk management exercise

    whereby the client aims to select the tender which represents the

    best value for money. This is not always the lowest tender!

    The use of non-price tender assessment criteria is one way of

    mitigating procurement risks.

    Tender Assessment

  • 39

    Tender Assessment Methods

    Tender assessment methods:

    Lowest tender price

    Price and non-price (1 stage using weighted criteria)

    Price and non-price (2 stage EOI plus above)

    Project specific

    Evaluation commonly involves selecting the tender with the highest

    tender evaluation score or ranking, taking into account all relevant

    criteria. The scoring method must ensure the extra value indicated

    by a higher score is worth any extra cost by using appropriate

    weightings that strike an appropriate balance between non-price

    value and price.

  • 40

  • 41

    Tender Assessment

    Tender evaluation criteria may include:

    Whole of life cost

    Delivery time(s) offered

    Quality offered

    Previous performance of tenderer

    Experience of tenderer and personnel proposed

    Capability of tenderer, including technical, management, human resources, organisational and financial capacity

    Conformity with tender requirements

    OHS, environmental, etc practices and performance

    The evaluation criteria should be consistent with the proposed

    contract requirements and aim to identify the tender / bid offering

    the best value for money.

  • 42

    Tender Assessment Weightings Example

    Scoring Guide Criteria: Personnel

    Site/Project Manager Works Supervisor Site Engineer

    4: > 10 yrs relevant exp. 3: Extensive experience 2: Previous experience

    3: > 5 yrs relevant exp. 2: Some relevant exp. 1: Little or no exp.

    2: Some relevant exp. 1: Little relevant experience

    1: Little relevant experience

    Criteria Weighting Contractor A Contractor B Contractor C

    Tender Program 5 3 4 3

    Performance 7 3 5 6

    Quality System 4 1 3 3

    OHS&R 6 3 4 5

    Environmental 4 1 3 3

    Personnel 9 4 6 8

    Claims History 5 2 4 4

    Non-Price Total 40 17 29 32

    Price $500,000 $525,000 $530,000

  • 43

    Probity and Transparency in Tendering

    A key issue associated with the tendering of any contract,

    particularly those where public money is involved, is probity to

    ensure fair and open competition, and minimise the potential for

    fraud and collusion.

    The application of probity principles, generally require that:

    All tenderers are treated fairly and equitably, consistent with the rules of natural justice and procedural fairness;

    A transparent and appropriately planned and documented tender process is established, including a robust evaluation

    methodology;

    All confidential information is protected;

    Strategies are in place to maintain the integrity of the tendering process when in-house bids may be involved;

    Potential and/or actual conflicts of interest are identified and dealt with.

  • 44

    Why Do We Care? Probity Example

    A former manager at UNE was recently part of a NSW Independent

    Commission Against Corruption (ICAC) inquiry relating to

    acceptance of gifts in return for favorable treatment.

    It is alleged that he sought and received benefits for himself in

    return for improperly favouring a number of companies the

    awarding of contract and for approving false invoices.

    The former manager told the inquiry, "I still believe we were doing

    good deals for the university. That was my rationale."

    http://news.smh.com.au/breaking-news-national/uni-boss-admits-organising-bogus-invoices-

    20120123-1qdlb.html

    http://www.icac.nsw.gov.au/investigations/current-investigations/investigationdetail/187

  • 45

    Depending on the industry, company and project, negotiations with

    tenderers may occur after submission of the tender / bid.

    These negotiations may be undertaken to:

    Clarify aspects of the submission

    Seek additional information

    Seek to reduce the tender price (though this is generally not permitted for government contracts).

    Change aspects of the work to be undertaken (i.e. change parts of the scope, drawings, documentation, etc)

    A key aspect of post-tender negotiations is that any agreed

    changes, and any associated correspondence, must form part of

    the contract which is subsequently signed by the parties.

    It is therefore important that all post-tender discussions are

    accurately documented.

    Contract Negotiations

  • 46

    Contract award typically involves:

    Notification of successful and unsuccessful tenderers

    Arrangements for execution of contract documents

    Obtaining copies of the Contractors' insurances

    Obtaining of security deposits (if required)

    Approvals and clearances by statutory authorities (if required)

    Contract Award

  • 47

    Request for Tenders RTA NSW

    GC21 RTA General Conditions of Contract Table of Contents

    GC21 RTA General Conditions of Contract Deed

    GC21 RTA General Conditions of Contract Annexure

    AS4000 General Conditions of Contract Table of Contents

    Additional References on Blackboard

  • 48

    Bid / Tender: An unconditional offer to enter into a particular

    contract to provide goods or services at a certain price

    BOOT: Build Own Operate Transfer

    Contract: An agreement giving rise to legally enforceable

    obligations binding the parties to it

    Conditions of Contract: A document which sets out the detailed

    contractual terms of a contract

    D&C: Design and Construction

    DCM: Design, Construction and Maintenance

    EPC: Engineer, Procurement and Construction

    Probity: Uprightness, honest and integrity

    Procurement: The act or process of obtaining goods and/or

    services

    Some Terminology

  • 49

    This review activity may assist in linking the different aspects

    covered in this lecture.

    List one example (activity) for each of the five (5) main types of contract

    For each contract write a very brief scope statement (3-4 lines)

    For each pair (of contract and example activity):

    - Explain why they are appropriately matched

    - Which, if any, standard conditions of contract could be

    used?

    - Which method of payment would be most suitable?

    - Which party, if either, bears the most risk?

    Note that there is no single correct answer for this activity and

    there may be many multiple correct selections for each dot point.

    Review Questions / Tutorial