Upload
cianurel2184
View
226
Download
3
Embed Size (px)
DESCRIPTION
model plan control
Citation preview
Tip document:
PLAN DE CONTROL SI EXAMINARE FABRICA/ WORKSHOP CONTROL AND EXAMINATION PLAN
Rev. 0 Data / Date:
Client / Customer:
Elemente examinate / Examined elements: Structura metalica
Comanda / Order:
Locatie / Location: Str.Moliere 12-14, sector 1- Bucuresti
Intocmit,
Pag. 1 / 2
F-54-09
Validare / Validation
Nr. crt.
Tip control / Type of
control
Cerinte /
Requirements
Documente referinta / Reference documents
Competenta / Competence
Frecventa / Frequency
Documentatie / Documentation
Coifer
CUSTOMER
Inregistrari /
Records
1 Identificare si examinare: - Desene executie; - TS
Solutii constructive Dimensiuni Imbinari in uzina Solutii asamblare Control nedistructiv
Standarde si norme aplicabile TS
QPR WR
100% Intrebari si propuneri adresate proiectantului (daca este cazul)
QPR QC Tehnologie asamblare Intrebari tehnice
2 Evaluare resurse necesare: - Coordonare sudare; - Proceduri sudare
omologate; - Sudori calificati - Surse sudare,
preincalzire, craituire - Echipamente uscare
electrozi si flux - EMM necesare
WR QC TS
SR EN ISO 14614:2007 SR EN 287:2004
QPR WR
WPS WPQR Lista utilaje Documentatii echipamente
QPR QC WPS WPQR Lista sudori Lista EMM
3 Plan examinare nedistructiva si distructiva pentru imbinarile sudate
TS SR EN 1090-2:2008 C150-99
TS
WR Conform TS Desene executie TS
QPR QC Plan examinare
4 Evaluare tipuri sanfrene necesare
TS SR EN 1090-2:2008
Desene executie SR EN ISO 9692-1:2004
WR 100% Shop drawing Desene executie
QPR QC
Material: - S355J2+N
Certificate tip 3.1
Desene si liste de materiale SR EN 10025:2005 SR EN 10204:2005
SC 100% Liste materiale Cerinte
QI Certificate calitate materiale
5 Controlul documentelor si listelor / comenzilor de aprovizionare
Materiale de adaos si consumabile sudare
SR EN 10204:2005 SR EN ISO 2560:2006 SR EN 756:2004
QI/WR 100% QPR Certificate calitate materiale adaos
6 Controlul documentelor privind materialele aprovizionate – cantitate, dimensiuni, marcare, certificate calitate, cf. comanda
SR EN 1090-2:2008 TS
SR EN 10025-2:2005 SR EN 10029:1995 SR EN 10056:2002
QI 100% Cerinte aprovizionare
QPR Certificate calitate materiale
7 Controlul trasabilitatii materialelor
SR EN 1090-2:2008 PO-12-09 IL-12-09
QI 100% - QPR Fise CNC Harta sarjelor
8 Controlul geometric al reperelor Tolerante specificate in desene / TS
SR EN 1090-2:2008 EN ISO 13920:1998 STAS 767/0-88
SC - QI MR F-39-09
Tip document:
PLAN DE CONTROL SI EXAMINARE FABRICA/ WORKSHOP CONTROL AND EXAMINATION PLAN
Rev. 0 Data / Date:
Client / Customer:
Elemente examinate / Examined elements: Structura metalica
Comanda / Order:
Locatie / Location: Str.Moliere 12-14, sector 1- Bucuresti
Intocmit,
Pag. 2 / 2
F-54-09
9 Controlul executarii prelucrarii muchiilor si sanfrenelor inainte de sudare
WPS, Desene, TS SR EN 1090-2:2008
WPS, Desene, TS SC
100% -
QI
WPS, F-60-09
10 Controlul dosarului pentru sudare
- WPS - WPQR - Lista sudori - Autorizatii sudori
SR EN 1090-2:2008 PO-18-09
SR EN ISO 15614:2007 SR EN 287:2004
QPR
HP WPS WPQR Lista sudori Autorizatii sudori
11 Sudarea TS SR EN 1090-2:2008 SR EN ISO 15614:2007
WR QPR Lista sudori
VT SR EN 1090-2:2008 TS
SR EN 970:1999 SR EN 5817:2008 nivel “B”
QI/WR 100% Plan examinare
QI HP Buletin NDT F-60-09 F-61-09
UT SR EN 1090-2:2008
SR EN 1714:2000 SR EN 5817:2008 nivel “B”
Subcontractor 25% suduri cap la cap cf. proiect #>8
mm 100% suduri cap la cap suplimentare
#>8 mm 25% suduri
longitudinale cu patrundere
Plan examinare QPR/WR HP Buletin NDT F-61-09
12 Examinare nedistructiva a sudurilor.
MT SR EN 1090-2:2008
SR EN 1290:2000 SR EN 5817:2008 nivel “B”
Subcontractor 10% (suduri de colt)
Plan examinare
QPR/WR HP Buletine NDT
13 Controlul dimensional si al geometriei pieselor sudate
SR EN 1090-2:2008 TS
SR EN 1090-2:2008 STAS 767/0-88
QI 100% MR QI HP Fisa de masuratori F-39-09
14 Curatarea suprafetelor Sa 2 ½ Rz = 30÷50
SR EN 8501-1:2007 SR EN 8503:2006
SC 100% TS QI HP Proces verbal protectie anticoroziva
15 Protectie anticoroziva Conform TS SR EN 12944:2002 QI 100% - QI PV protectie anticoroziva 16 Controlul calitatii protectiei
anticorozive si al grosimii peliculei
TS* SR EN 12944:2002 SR EN ISO 2409:2007 SR EN ISO 2808:2007
QI
TS
QI
HP
Proces verbal protectie anticoroziva F-46-09
17 Control final in fabrica Conform procedura QMS
Conform cerinte TS FIC 100% MR; SPR FIC Certificat calitate Declaratie de conf.
18 Receptia in fabrica TS
SR EN 1090-2:2008 TS
QPR; CRC 100% Documentatie executie
QPR CRC Inregistrari si documente receptie
Legenda: QPR – Quality Production Responsible / Reponsabil calitate productie; QI – Quality inspector / Inspector calitate; WR – Welding Responsible / Coordonator sudura; SC – Self control / Autocontrol; MR – Measurement report / Fisa de masuratori; FIC – Final Inspection Commission / Comisie receptie finala; SPR – Special Processes Report / Raport process special; TS – Technical Specifications / Caiet de sarcini; HP – Hold Point / Punct stationare; QMS – Quality management System / Sistem de management al calitatii; CRC - Customer Reception Commission / Comisie receptie client; PO-18-09 – Welding operational procedure / Procedura operationala sudare; VT – Visual test / Test vizual; NDT – Non Destructive Test / Test nedistructiv; EMM – Monitoring and Measuring Equipment / Echipamente monitorizare, masurare.
NOTA: Acolo unde sunt aplicabile mai multe reglementari vizand aceeasi problema, se va alege varianta cea mai restrictiva.