Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
KU GEOTECHNICAL CONFERENCE
2019 MISSOURI RIVER FLOOD EVENT
JOHN D. HOLMCHIEF, ENGINEERING DIVISIONKANSAS CITY DISTRICT
14 NOVEMBER 2019
AGENDA
Introduction
Missouri River Background Information
March 2019 Flood Event
May-July 2019 Flood Event
Levee Damages Summary
Wrap-Up
Questions
DEFINITIONS
• Federal Levee – USACE Federally constructed, owned and maintained by local sponsors
• Non-Federal Levee – Non-Federally constructed, owned and maintained by local sponsors
• Other Levees – All other levee systems• Public Law (PL) 84-99 – Flood Control and Coastal Emergency
Act - Provides the Corps of Engineers with the authority to prepare for, respond to, and recover from floods and coastal emergencies
• USACE – US Army Corps of Engineers• NWK – Kansas City District – Missouri below Rulu, NE• NWO – Omaha District – Missouri above Rulu, NE• NWD – Northwestern Division
OUR MISSIONREGULATE MISSOURI RIVER MAINSTEM RESERVOIRS
• Priority: Life and Safety• Operational Decisions: Driven by Annual Runoff ConditionsWater captured in System flood control storage zones each year, must leave System each year.• Master Manual: Storage and release decisions designed significantly around
Flood Control, Navigation, & Water Supply purposes
• Authorized Purposes: Funds power plant projects, allows food plots for wildlife, reservoirs stocked with fish, irrigation intakes, boat ramps, water quality testing, etc.
The Corps does not store more water in the System for Threatened and Endangered Species.
Flood Control Navigation Hydropower Water Supply Fish & Wildlife Irrigation Water Quality Control
Recreation
HYDROPOWER
NAVIGATIONFLOOD CONTROL WATER SUPPLY
RECREATIONIRRIGATIONWATER QUALITY
CONTROLFISH & WILDLIFE
Eight Authorized Purposes Flood Control – Requires Empty Space Navigation Hydropower Water Supply Water Quality Control Recreation Irrigation Fish and Wildlife (including T&E*)
Purpose = PriorityRunoff Driven System – The runoff drives system releases, and is
managed on an annual basis. We do not carryover water in the flood control zones
Basically operate for flood control or meeting downstream targets (nav)
* - As Hydrologic Conditions Allow
Requires Access to Water or Releases
MISSOURI RIVER AUTHORIZATION/MISSION
0
10
20
30
40
50
60
70
1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
MIL
LIO
N A
CR
E FE
ET (M
AF)
YEARS
Actual Drought Periods Current Forecast MED
ANNUAL RUNOFF ABOVE SIOUX CITY, IA
2019
Historic Drought Periods
Median
2019 Runoff Forecast … 61.0 MAF*Average Runoff … 25.3 MAF*October 1 forecast (ties record set in 2011)
MISSOURI RIVER MAINSTEM RESERVOIR SYSTEMFORT PECK GARRISON
BIG BEND
GAVINS POINT
OAHE
FORT RANDALL Bank Stabilization and Navigation Project, Sioux City, IA to St. Louis, MO
MAINSTEM PROJECTS - STORAGE
Flood Control Storage of Gavins Point:2/3 Cup Measuring Cup = 0.13 MAF
Combined Flood Control Storage of:Fort Peck, Garrison, Oahe, Big Bend, Ft. Randall5 Gallon Bucket = 16.2 MAF
MAINSTEM PROJECTS – FLOOD CONTROL STORAGE
Kansas City District Dams and Reservoirs
KANSAS CITY DISTRICT RESERVOIR STORAGE
Federal Levees – 58 systemsNon-Federal Levees - 83 systems, 94 segmentsOther – Not Shown
13
LEVEES: FEDERAL VS NON-FEDERAL
MISSOURI RIVER BASIN – RUNOFF ABOVE SIOUX CITY, IA
Plains Snowpack+ Rainfall
March & April
Mountain Snowpack+ Rainfall
May – July
Rainfall
August – February
~ 25% annual runoff ~ 50% annual runoff
Average Annual Runoff ~ 25.3 million acre-feetFeb Forecasted 2019 Runoff ~ 25.6 million acre-feet
MARCH FLOOD EVENT - SNOWPACK• Mountain snowpack was
about average in 2019
• One difference between 2019 and 2011 … mountain snowpack was MUCH ABOVE average in 2011.
• Plains snowpack was present in the entire upper basin, Nebraska and Iowa
• Heavy to very heavy plains snowpack in portions of the central and eastern Dakotas
• Deeply frozen soils resulted in little to no infiltration during March snowmelt/rainfall events
16
File Name
16BOMB CYCLONE
MARCH FLOOD EVENT - FLOWS
- 14 levee systems breached north of Kansas City on Missouri River.
- Estimated that 350 miles of levee systems impacted in some manner by flood waters
- Over 4.8 million acres inundated throughout Missouri River basin, March 8-21
Henry Pohl Levee March 27th 2019Atchison County, KS
Craig, MOMarch 2019
MARCH 2019 - DAMAGES
BREACHES
File Name
19
- Overtoppping and breaching of left bank levee systems resulted in overland flow above the Mill Creek private levee
- Mill Creek private levee overtopped and breached allowing water to flank the main levees
- Ultimately water overtopped and breached the Big Tarkio private levees
MILL CREEK BREACH
File Name
20
Breach DimensionsLength 600 feetScour Depth 80 feet
MILL CREEK BREACH
File Name
21
BIG TARKIO BREACH
File Name
22
Breach DimensionsLength 1,100 feetScour Depth 50 feet
PHASE I: STOP BREACH FLOWS
File Name
23
Temporary Emergency MeasuresHolt County, Missouri• Temporary closure of levee breaches
at two locations on Mill Creek and Big Tarkio River
• Affected communities include Corning, Craig, Big Lake and Fortescue, Missouri
• 23,000 acres affected, with estimated property value of $185 million
• $28M Effort
BIG TARKIO BREACH
File Name
24
BIG TARKIO BREACH
File Name
25
03/23/2019
03/28/2019
• 1st Federal levee to overtop and breach since 1993
• Doniphan County, KS
MRLS 500-R
Buchanan CO, MO/Doniphan CO, KS
MRLS 471-460-R
MARCH 23 2019 – R471-460 LEVEE
MARCH 23 2019 – R471-460 LEVEE
NWK RESERVOIRS – MID APRIL
MAY - JUNE FLOODING
• May rainfall in KS averaged 10.4”; largest monthly rainfall, (exceeded July 1993).
• Precipitation in WY, SD, NE, IA, MO, KS … all much above average and on VERY saturated soils.
PEAK RESERVOIR CONDITIONS
TUTTLE CREEK SURFACE AREA
File Name 34
PERCENT OF FLOOD CONTROL POOL OCCUPIED – 04 JUN 2019
IMPACTS TO RESERVOIRS
Kansas City District
On peak day, 9 MAF of 11 MAF of flood control storage was occupied
Surcharge operations at Harry S Truman, Tuttle Creek, Perry and Long Branch
Record pools at 9 reservoirs: Perry, Clinton, Truman, Pomona, Melvern, Hillsdale, Pomme de Terre, Harlan County and Long Branch
File Name
36
• May precipitation ranged between 10-15 inches across a majority of the NWK AOR.
• Wettest May on record• JAN 2019 – JUN 2019 – record
precipitation levels for time span• NWK reservoirs continue to store runoff
due to high flows on Missouri River.• 9M of 11M acre-feet of flood control
storage utilized.
MAY 2019 FLOOD EVENT
MAY-JUNE FLOODING: LEVEE STATUS
• 50 levee systems Overtopped, or Overtopped and Subsequently Breached, 23 May - 17 June 2019
• All on the Missouri and Grand River located downstream of Kansas City
• NWK estimates approx. 655 additional levee miles from Kansas City – St. Louis damaged in May 2019
Garden of Eden Levee SystemGrand River
OBSERVATIONS
38
y
Slide
Chariton River
Grand River RR Bridge, RR working to move debris downstream
OBSERVATIONS
39
y
Emergency Repair ~ Sta. 95+00 L246
OBSERVATIONS
40
y
L246 Sta. 64+00 Sandbagged Low Spot
41
MRLS-246L• 2nd Federal levee to Overtop
and Breach since 1993 • Protects 25.8K acres• 35.2mil estimated property
value
IMPACTS TO LEVEES
Kansas City District
2 Federal Levees overtopped, 2 breaches
64 Non-Federal Levees overtopped, 43 breaches
LEVEE REHABILITATION AND USACE ASSISTANCE
Levee rehabilitation basic details• Goal is to repair eligible “Active” projects damaged by flooding prior to
the next flood season• Assistance must be requested by levee sponsor and is limited to pre-
disaster condition and level of protection• Repairs must be economically justified and are prioritized based on
consequences and severity of damage• Active federal levee rehabilitation projects are repaired at 100% federal
cost• Active non-federal projects are cost-shared 80% federal, 20% non-
federal• Levee sponsors must provide land access easements, rights-of-way,
relocations and borrow (earthen material to repair levee) at no cost to the federal government
LEVEE REHABILITATION AND USACE ASSISTANCE
Levee rehabilitation status• Mainstem releases from Gavins to continue at 80,000 cfs through
November – plan is to evacuate all flood storage before winter freeze• NWK continues to make releases from the Kanas reservoirs with the
goal to evacuate all flood storage over the next 6 weeks• NWK has completed all but four of the PIRs (Project Investigation
Report)• Challenged due to ongoing high water
• NWD is approving PIR’s • Emergency repairs for Mill Creek and Big Tarkio awarded early August• NWK has advertised four repair contracts• As PIR’s are approved by NWD, NWK staff are developing contract
documents for future advertisements• All advertisements are dependent upon the sponsors providing land
access easements, rights-of-way, relocations and borrow (earthen material to repair levee) at no cost to the federal government
File Name 45
PERCENT OF FLOOD CONTROL POOL OCCUPIED 04 NOV 2019
QUESTIONS
46