October 4, 2019TSX: CGwww.centerragold.com
Öksüt Gold ProjectPhotographic Construction Update 11
Öksüt: Funded High Margin Gold Production
Mine Type Open Pit, Heap Leach
Avg. LOM Annual Production 110koz Au
Avg. LOM AISC(1) (US$/oz) $490
Reserve Mine Life 8 years
Development Capex (US$MM) $200
LOM Sustaining Capital(1) (US$MM) $10
P&P Reserves(2)(Moz) 1.3
Au grade (g/t)(2) 1.4
Life of Mine Strip Ratio (w:o) 2:1
First Gold Pour (3) January-2020
Project Highlights
EIA approval received in November 2015
Forestry Permit & GSM License received July 2016
Pastureland Permit received January 2018
Investment Incentive Certificate received February 2018
Start construction March 2018 on track first gold Q1 2020
Bought back Stratex and Teck royalties in 2015 & 2016
US$150MM low-cost financing in-place
Öksüt Heap Leach PadCatalyst Schedule
Öksüt Gold Project
(1) Non-GAAP measure see “Non-GAAP Measures” in Centerra’s MD&A and news release of July 30, 2019.(2) Refer to February 22, 2019 news release and Technical Report on Öksüt Gold Project dated September 3, 2015.(3) Forward-looking information refer to news release of July 30, 2019.October 2019 2
General Mine Site Layout
October 2019 3
Admin Offices and Crushing Area Overview
October 2019 4
Chemical Storage Shed Construction
October 2019 5
Haul Roads and Keltepe Open Pit Location
October 2019 6
Keltepe Open Pit
OMAS Weather Station
Topsoil Stockpile
Haul Road
Keltepe Open Pit Mining
October 2019 7
Mining Keltepe Open Pit
October 2019 8
Mining Keltepe Open Pit
October 2019 9
North Waste Rock Dump
October 2019 10
Primary & Secondary Crushers
October 2019 11
Heap Leach Pads 1A and 1B
October 2019 12
Heap Leach Piping Installation
October 2019 13
Heap Leach Over Liner Material
October 2019 14
ADR Plant, CIC Tanks and PLS Pond
October 2019 15
Barron Solution Tank and Pumps
October 2019 16
WRD Pond and Silt Trap Construction
October 2019 17
TSX: CGwww.centerragold.com