    KERALA STATE ELECTRICITY BOARD

    Board SecretariatVydyuthi BhavanamThiruvananthapuram

    No. CP/R&P/Plg.1/AP/2011-12/ Date: 11.10.2010

    CIRCULAR

    Sub: Preparation of Annual Plan for the year 2011-12 Guidelines issued

    Ref: B.O. (FM) No. 2639/2010 (CP/R&P/Plg.1/AP/2011-12) dated 11.10.2010

    Planning process for the year 20011-12 had been kicked off with a series of meetings

    convened by the Chairman, KSEB with the senior officers of Distribution and

    Transmission wings and with the planning core committee. These meetings served thepurpose of critically analyzing the decentralized plan process and identifying the thrust

    areas for the coming year. Various suggestions were evolved based on the discussions in

    these meetings to improve the plan process. The Board vide order read above has

    approved these proposals and directed to issue the following guidelines for the

    preparation of Annual Plan for the year 2011-12.

    1. Decentralized planning method in practice during the last 3 years shall be followed

    for the year 2011-12 also. This decision is justified by the better results we could

    achieve compared to the earlier period.

    2. However some areas require more attention while implementing the plan in the

    coming year. These are Cost/benefit analysis, Project scheduling, Maintenance plan,

    Technical analysis of the projects and Performance evaluation.

    3. Importance of cost/benefit analysis was discussed and it was decided to carry out

    the cost/benefit analysis in the Distribution wing by clubbing together all the works

    undertaken in an Electrical Section as one project. In the Transmission wing, the

    cost/benefit analysis it is to be done for all newly proposed works. It is to be

    ensured that the IRR is positive for implementing the project.

    4. Proper scheduling of the projects shall be made compulsory and should be forwardedalong with the plan proposals.

    5. Maintenance plan should be based on the schedule as provided in the approved

    maintenance manual in both Transmission and Distribution. Major considerations in

    deciding the maintenance plan are listed below:

    Distribution

    a) Sufficient quantity of Safety equipments shall be made available in all Electrical

    Sections.

    b) Maintenance of all Distribution installations and equipments as mentioned in the

    maintenance manual shall be incorporated in the maintenance plan. Priority shall

    be given for undertaking required maintenance of Distribution transformers.

  • 8/7/2019 KSEB_annual_plan_2011-12_-_circular_11.10.10[1]

    2/6

    c) All Electrical Sections of KSEB shall be made faulty meter free by end of 2011-12.

    d) Indexing of 100% consumers and electric poles pole directory shall be prepared

    by the end of 2011-12 in all Electrical Sections.

    e) All Distribution Transformer stations shall be standardized in 24 months, 11 kV

    lines in 24 months and LT lines in 30 months.

    f) All damaged poles shall be replaced in a phased manner.

    g) All electro-mechanical meters shall be converted to static meter in a phased

    manner.

    h) Wherever the number of service connections given from a pole is more, providing

    pole-top Distribution box for service connections can be considered.

    Transmission:

    In addition to the routine maintenance works, the following areas may be given due

    consideration.

    a) Provision shall be made in the plan for improving the earthing of substation

    equipments, wherever necessary.

    b) Proper plan for implementing the recommendations of PET reports received up to

    31st October 2010 shall be incorporated in the Maintenance plan for next year.

    c) Deteriorated tower stubs & foundations shall be identified and rectified.

    d) Strengthening of DC system and protection system.

    e) Ensuring correctness of the metering system.

    f) Re-conductoring of worn-out conductors.

    g) Replacement of worn-out earth wires.

    h) Replacement of deteriorated disc insulators.

    i) Replacement of all 11 kV Bulk Oil Circuit Breakers which are presently in use.

    6. Technical analysis is to be given the due consideration while identifying the works as

    well as to prove the worthiness of the works executed. The idea is to increase the

    engineering content of the projects. The possible activities in Distribution and

    Transmission wing are listed below:

    Distribution

    Various technical parameters to be considered for selection of projects are:

    Minimum fag end voltage of LT feeders

    HT:LT ratio of the Section

    Maximum length of LT feeders

    Maximum load on transformers

    The activities under technical analysis should include among others:

    Load balancing of transformers and feeders

    Load sharing between transformers

    Interlinking of HT & LT feeders Transformer neutral current measurement

  • 8/7/2019 KSEB_annual_plan_2011-12_-_circular_11.10.10[1]

    3/6

    Transmission

    The following areas may be given due consideration:

    Measurement of the earth resistance of the station through different seasons

    Periodic analysis of the oil in transformers

    Load sharing of transformers

    Under / over loading of feeders

    Scheduling the maintenance of breakers based on their number of operations

    Trend in the load growth of station and feeders

    7. Loss reduction targets shall be brought down to the Electrical Section level for which

    at least one Section in each Electrical Division, which is not covered by the R-APDRP

    scheme, shall be provided with DTR meters and border meters.

    8. Activities aimed at improving the safety level should be given utmost importance in

    plan formulation. Some suggestions on this aspect are listed below:

    Distribution

    Necessary safety equipments shall be provided in all Electrical Sections. This shall

    be arranged by the Assistant Engineer / Assistant Executive Engineer.

    Safety classes shall be conducted in all Electrical Sections on a monthly basis,

    once in three months in all Electrical Subdivisions and once in six months in all

    Electrical Divisions. All concerned officers and employees shall compulsorily

    attend these meetings.

    Functioning of the existing Electrical Division level safety squads shall be

    strengthened by carrying out surprise inspections at work sites and reportingnon-conformance of safety standards to the concerned authorities. In case the

    safety squads are not functioning in any Electrical Divisions, immediate action

    may be taken to form such safety squads with Assistant Executive Engineer as

    head of the squad. One Assistant Engineer, two Sub Engineers and a

    representative of recognized trade unions shall be members of the squad. The

    squad shall conduct safety audit at Electrical Section office of another Electrical

    Sub Division. Surprise inspections shall be conducted regularly at the work site

    of contract workers and employees. The squad should submit regular report to

    Executive Engineer and action may be taken based on the report.

    Ensure necessary tools and plant in all Electrical Sections. This shall be arranged

    by the Assistant Engineer / Assistant Executive Engineer. The list of tools and

    plant which shall be available in the Section is listed below:

    o Toolkit - 2 Set

    o Adjustable fiber ladder - 2 Nos.

    o Earthing Rod - 3 Nos.

    o Safety belt - 6 Nos.

    o Helmet - 12 Nos.

    o 11 kV gloves pairs - 8 Nos.

    o Torch - 2 Nos.

    o Lock & Key - As per requirement

  • 8/7/2019 KSEB_annual_plan_2011-12_-_circular_11.10.10[1]

    4/6

    Transmission

    It should be aimed at achieving 100% safety in all installations and work sites.

    All stations should have adequate number of safety equipment in proper

    condition. Necessary tools & plants and safety equipment required in

    Transmission wing shall be procured by the concerned officers based on the priceof items, frequency of usage etc.

    It is to be ensured that all operators including contract staff attend safety

    sessions at least once in every 3 months.

    Safety auditing must be given due weightage during the inspection of stations by

    senior officers.

    9. Priority areas in the capital works of Distribution wing are discussed in below:

    a) It is found that many substations are under loaded due to lack of proper power

    evacuation system. 11 kV network shall be extended to ensure power evacuationfrom these substations. Action plan for improving the loading of substations by

    rearrangement of feeders and load balancing shall also be considered.

    b) All AAC conductors should be replaced with ACSR conductor

    A minimum quantity of 1 km per month per Electrical Section shall be

    ensured in the Annual Plan works (minimum 12 km per annum)

    c) In the case of HT, all copper and non-ACSR conductors shall be replaced with

    ACSR conductors

    d) 11 kV feeders in municipal and corporation areas shall be interconnected to get a

    ring main facility. This will provide back feeding facility during supply

    interruptions, thereby reducing duration of interruption as well as overloading of

    feeders.

    e) Nearby Distribution transformers in municipal and corporation areas shall be

    interconnected with 3-phase lines. This will provide back feeding facility during

    transformer failure thereby reducing duration of supply interruption as well as

    overloading of Distribution transformers.

    f) Eliminate low voltage areas (ensure at least 200 V per phase at the fag end).

    Works necessary to rectify the low voltage shall be included in the annual planand completed by the end of the 2011-12.

    Single Phase to Three Phase conversion a minimum quantity of 1 km per

    month per Electrical Section shall be ensured in the Annual Plan works

    (minimum 12 km per annum)

    g) The priority of works shall be decided based on the following criteria:

    Urban - Area where length of LT Line (Transformer to Fag end) is more

    than 0.5 km

    Semi Urban - Area where length of LT Line (Transformer to Fag end) is

    more than 1 km

    Rural - Area where length of LT Line (Transformer to Fag end) is more

    than 1.5 km

  • 8/7/2019 KSEB_annual_plan_2011-12_-_circular_11.10.10[1]

    5/6

    10. For fulfilling the objectives of model sections, modifications including civil works are

    required in most of the selected section offices (such as enquiry counter, cash

    counter, material stacking area, facilities for customers etc.). The requirement for

    these works in model sections shall be captured in the Annual Plan.

    11. The Board is considering implementation of some projects on selected areas in both

    Distribution and Transmission wings based on a study conducted by six-sigma core

    group. Provisions for incorporating the additional requirement of resources for

    implementing these projects shall also be made in the Annual Plan.

    12. Some pilot projects evolved based on the training of senior officers at IIM, Bangalore

    will also be implemented by the Board. Provision for these projects shall also be

    made in the Annual Plan for the next year.

    13. Provision for the works related to 100% electrification of Assembly constituencies

    and Kuttanad package shall be included in the Annual Plan for the next year.

    14. Executive Engineers of Electrical Divisions shall arrange training / interactive sessionsat Divisions by involving the Assistant Executive Engineer, Divisional Accountant and

    Assistant Engineers in estimate preparation, tendering, bill preparation and

    processing etc.

    15. Finalisation of the plans at district level will be made at the two-day workshops with

    the participation of Transmission and Distribution officers.

    16. Deputy Chief Engineers of Electrical Circles are authorized to finalise the Annual Plan

    under their jurisdiction. The plans, both capital and maintenance, approved by the

    Deputy Chief Engineers shall be forwarded through the Chief Engineers to the Board

    for sanction. The Circle level plans of Transmission wings shall be forwarded to theBoard for finalization and approval

    17. The Executive Engineers shall carry out month wise scheduling of each work. They

    shall also do re-scheduling, if any, based on achievement monitored every month.

    The material allocation to Electrical & Transmission Divisions shall be based only on

    the scheduling of Annual Plan works.

    18. The Executive Engineer of Circle office shall be the nodal officer for Annual Plan

    works. They shall ensure the following

    a. Coordinate with field officers in the preparation of Annual Plan works

    b. Scrutinize the plans prepared by Divisions before forwarding to higher offices

    c. Ensure that scheduling of works for the entire year is carried out by the

    Divisions at the beginning of the year and rescheduling, if any, based on

    achievement is carried out every month.

    d. Monitor the implementation of Plan works and report the progress of works

    regularly to higher offices. The progress reports prepared by the Divisions

    shall be properly scrutinized before forwarding it to higher offices.

    The Assistant Executive Engineer of Electrical Divisions shall carry out the

    above functions at their respective Divisions.

  • 8/7/2019 KSEB_annual_plan_2011-12_-_circular_11.10.10[1]

    6/6

    19. The generation plan for the current year include projects that are scheduled to be

    completed during this year and those which will be commissioned during the coming

    years. The generation plan for 2011-12 shall contain provision for all ongoing

    projects as well as new projects which will be taken up during the next year,

    including investigation works. While formulating project proposals, detailed

    investment proposals including cost benefit analysis shall be carried out. Detailedimplementation schedule of all ongoing and newly proposed projects shall be

    prepared with major milestone charts.

    20. The Tentative Schedule for the finalisation of Annual Plan 2011-12 is given below:

    Senior Officers conference (Plan initiation)3rd and 4th week ofSeptember

    Development of boundary conditions (budget, materials) 1st week of October

    Preparing handbook/Developing templates 1st week of October

    Selection and orientation of facilitators 1st week of OctoberRefresher training at Circle level 2nd week of October

    Circle level planning workshop 1st week of November

    Plan finalisation at Circle office 15-11-2010

    Develop state level plan through a joint effort ofCorporate Planning and TC&M wings

    1st week of December

    Finalisation at board level 15-12-2010

    Final unit plans 31-12-2010

    All field officers are directed to follow the above guidelines in the preparation andimplementation of Annual Plan for the year 2011-12.

    Sd/-

    (B.Mohanan)

    Secretary

    To:Chief Engineer Distribution (South/Central/North) / Chief Engineer Transmission(South/North) / Chief Engineer (Generation) / Chief Engineer (CC-South /North) /Chief Engineer (Civil-I&P) / Chief Engineer (Civil-DS) / Chief Engineer (TC&M)

    All Deputy Chief Engineers, Electrical Circles & Transmission CirclesAll Executive Engineers, Electrical Divisions & Transmission DivisionsCopy to:

    Director (IT) / TA to Chairman / TA to Member (Distn.) / TA to Member (Trans.) /TA to Member (Gen.) / PA to Member (Fin.) / Public Relations Officer / Senior CAto Secretary / Fair Copy Superintendent / Stock file

    Forwarded/By order

    Assistant Engineer