KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

Embed Size (px)

Citation preview

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    1/27

    Method of Statement for Khabat PP132kV Switchyard Circuit Breaker 

    Installation Works

    TOTAL 27 PAGES

    (Including Cover)

    PROJECT NAME : Khabat Thermal Power Plant Units 1&2Purpose

    ☐ For Information

    ☐ For Review

    ☐ For Approval

    ☒ For Construction

    ☐ As-Built

    DOCUMENT NO. : KP-00+++-MQ758-V0010

    TITLE : Method of Statement for Khabat PP  132kV Switchyard Circuit Breaker Installation

    Works

    OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government

    0 12.02.2015 For Construction DE EÖ AY YÖ

    A 09.02.2015 First Issue DE EÖ AY YÖ

    Rev.No.

    DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED

    GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

    Owner 

    Ministr y of Electrici ty (MOE)

    of Kurdistan Regional Government

    Contractor 

    POSCO ENGINEERING

    & CONSTRUCTION CO., LTD.

    Main Subcontractor 

    GAMA POWER SYSTEMSENGINEERING & CONTRACTING,INC.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    2/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 1/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    Khabat Thermal Power Plant Units 1&2 Project132kV Air Insulated Switchgear 

    METHOD OF STATEMENT FOR 132kV

    SWITCHYARD CIRCUIT BREAKERINSTALLATION

    DOCUMENT NO: KP-00+++-MQ758-V0010

    SUBCONTRACTOR: SIEMENS

    GAMA REVIEW

    DisciplineSuperintendent

    HSE Manager QA/QC Manager Site Manager  

    Name

    Date

    Sign

    Remarks:Any such review or consent by GAMA, shall not relieve the Subcontractor, in any case or for any reason whatsoever,from any obligation, liability or responsibility arising out of or in connection with the Contract, including without beinglimited thereto, to the responsibility for errors, omissions, discrepancies and non-compliances. Within this context, thisdocument shall not prevail over or amend the Contract, or relieve the Subcontractor from any of its duties, obligations,responsibilities or liabilities under the Contract.Anything presented herein by the Subcontractor shall in no eventi) excuse the Subcontractor’s non-performance under the Contract, or ii) entitle him to a variation under the Contract or an adjustment to the Contract Price.

    SUBCONTRACTOR

    Rev.No.

    Date Description*Prepared

    byHSE

    Manager QA/QC

    Manager Site

    Manager Project

    Manager 

    A 09.02.2015 132kV SwitchyardSteel Erection

    Works

    DenizEREN

    - - - EyyüpÖZBAY

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    3/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 2/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    0 12.02.2015 132kV SwitchyardSteel Erection

    Works

    DenizEREN

    - - - EyyüpÖZBAY

    DOCUMENT HISTORY:

    Rev.

    No.  Date

    Remarks

    (Reason for Revision)

    A 09.02.2015 First Issue

    0 12.02.2015 For Construction

    * Descript ion:

    Document issue purpose

    -   First Issue

    -   For Information

    -   For Review-   For Approval (or Issued for Construct ion)

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    4/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 3/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    CONTENT

    1.0 PURPOSE .................................................................................................................................................................................... 4

    2.0 SCOPE OF WORK ...................................................................................................................................................................... 4

    3.0 RESPONSIBILITIES .................................................................................................................................................................... 4

    4.0 DEFINITIONS / ABBREVIATIONS ............................................................................................................................................. 4

    5.0 PERSONNEL ............................................................................................................................................................................... 4

    6.0 MATERIALS ................................................................................................................................................................................. 5

    7.0 EQUIPMENT ................................................................................................................................................................................ 5

    8.0 SUBCONTRACTORS’ SUB-TIER CONTRACTORS ................................................................................................................ 59.0 EXECUTION ................................................................................................................................................................................. 5

    10.0 TIME LINE OF ACTIVITIES ........................................................................................................................................................ 7

    11.0 PROGRESS MEASUREMENT ................................................................................................................................................... 7

    12.0 QUALITY REQUIREMENTS ....................................................................................................................................................... 7

    13.0 HEALTH, SAFETY and ENVIRONMENTAL REQUIREMENTS ............................................................................................... 8

    14.0 RISK ASSESSMENTS ................................................................................................................................................................ 8

    15.0 REFERENCES ............................................................................................................................................................................. 9

    16.0 TECHNICAL APPENDICES ........................................................................................................................................................ 9

    17.0 ATTACHMENTS .......................................................................................................................................................................... 9

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    5/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 4/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    1.0 PURPOSE

    This procedure outlines the methods to be followed for installation of the Circuit Breakers for 132kV

    Switchyard at Khabat Thermal Power Plant Units 1&2 Project.

    2.0 SCOPE OF WORK

    Installation of steel structure for below 132kV feeders include busbars

    ·  132kV line feeders ( 6 pcs)

    ·  132kV cable feeders ( 2 pcs)·  Transformers feeders (2 pcs)·  Coupling feeders (1 pcs)

    3.0 RESPONSIBILITIES

    This MS is under responsibility of Siemens. When any changes occur, Siemens will revise this document and issue according to communication plan on which Siemens and Gama agreed.

    4.0 DEFINITONS / ABBREVATIONS

    PP: Thermal Power PlantAIS: Air Insulated Switchgear  MS: Method StatementITP: Inspection & Test PlanQA/QC: Quality Assurance / Quality ControlHSE: Health, Safety, EnvironmentJSA: Job Safety AnalysisPPE: Personal Protective EquipmentHV: High Voltage

    MV: Medium VoltageLV: Low VoltageAC: Alternative CurrentDC: Direct CurrentUPS: Uninterruptable Power Supply

    5.0 PERSONNEL

    -  Site Manager 

    -  Site Engineer(s)

    -  QA/QC Engineer 

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    6/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 5/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    -  HSE Supervisor 

    -  Site Supervisor(s)

    -  Survey Team

    -  Site Foreman(s)

    -  Workers (iron, formwork, concrete, steel, electrical etc)

    -  Operator(s) (Construction Machine, crane etc. )

    6.0 MATERIALS

    -  Prefabricated Steel Parts

    -  Bolts, washers, nuts

    7.0 EQUIPMENT

    -  Truck (if necessary)

    -  Crane

    -  Manlift

    -  Survey equipments

    -  Handtools

    -  Powertools

    8.0 SUBCONTRACTORS’ SUB-TIER CONTRACTORS

    9.0 EXECUTION

    The work method to install the above mentioned Circuit Breaker shall be in the followingsequence.

    A. Pre-Installation Checks

    · Verification of Equipment layout from relevant Construction Drawings.

    Mr.Mesut AYDIN Civil Subcontractor Silopi Aypa Ltd.Şti

    Mr.Ufuk MANAV Erection & Commissioning Subcontractor  YNE Enerji Elektrik Mühendislikinşaat San.Tic.ltd.Şti.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    7/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 6/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    · Check drawings are of current revised status.

    · Site released for Equipment installation, all supporting steel installation completed 

    · Conform readiness of the area.· Review Vendor drawings of the equipement and familiarize the installation method 

    recommended by the Vendor.

    · Exposed erection areas shall be cordoned by means of hazard identifying tape.

    · Confirm that all Tools & Tackles required for installation are available. As a minimum thefollowing shall be made available.

    Open End WrenchesStar End WrenchesTorque WrenchSlings

    D-ShacklesCrowbarsDrill MachineGrinding MachineAll necessary special tools

    · Check adequate place for unloading the Circuit Breaker.

    · Personnel involved in the activity are made aware of the risks and the steps to be taken tomitigate any hazard or unsafe situation.

    · Foundation frame shall be made and properly aligned for the installation of the Circuit Breaker.

    B. Material withdrawn from ware-house

    · Material inspection will be carried out to ascertain that no damage has occurred in the package of the equipments. Incase of any damages common inspection and report will be issued.

    · Store material requisition shall be made.

    · The material shall be transported in their Original packing to location.

    · The Hi-Ab shall be positioned in such a way that there is no obstruction to movement of vehiclesor hindrance to works of other companies.

    C. Description of sequence

    The following will be follwed after the preparation works:

    · Check the availability of SF6 gas inside column and the breaking unit

    · Install the corana rings to breaking unit if available

    · Install the current conducting rings to both end of the breaking unit

    · Install the coupling capacitor to the breaking unit if available

    · Connect the column and breaking unit

    · Use suitable wowen sling to lift up the Circuit Breaker 

    · Lift up the Circuit Breaker with Hi-Ab according to the supplier documents and raised over the

    steel support

    · Align the Circuit Breaker over the support base plate and fit the Erection bolts.

    · Check the horizontal and vertical alignment of the Circuit Breaker and adjusted as necessary.

    · Install the control cubicle, be sure that the indicators on control cubicle should be in “OPEN”and “DISCHARGED” positions.

    · Fill up the CB with SF6 gas.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    8/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 7/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    · Tigth the bolts and nuts according to the torque values given in the table below:

    Bolt Type, d Nominal Radius, mm.  Quality Type A325

    Recommended TorqueValue Nm.

    M8 8 16M10 10 32M12 12 59M14 14 94M16 16 146

    M18 18 200M20 20 284M22 22 388M24 24 492M27 27 720M30 30 979M33 33 1331M36 36 1709M39 39 2211

    Bolt tightening is done by torque wrench, according to recommended values. Before assembystarts,10 percent of tightened bolts are controlled with GAMA’s surveillance.

    10.0 TIME LINE OF ACTIVITIES

    According to attached 27 January 2015 dated updated project time schedule.

    11.0 PROGRESS MEASUREMENT

    Monthly progress reports will permanently be submitted to Gama for progress measurement.

    12.0 QUALITY REQUIREMENTS

    Inspection and Test Plan (ITP) for Circuit Breaker Installation Works (Doc. No: KP-00+++-CQ712-B7357)shall be followed during the execution of works.

    Test, inspections and reporting shall be carried out by the Subcontractor in accordance to the ITP and required documents mentioned on the ITP shall be submitted to GAMA for his review.

    All measurement equipments and torque wrenches shall be calibrated. Calibration certificates shall besubmitted to GAMA before site applications according KP-00+++-MQ732-G0005_Rev.0_CalibrationProcedure. Test certificates and mill certification verifying that the materials comply with the relevant

    approved standards and material certificates shall be issued for all structural steel, bolting materials,consumable materials. Approved materials shall be used in project according to approved vendor list and material submittal form.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    9/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 8/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    13.0 HEALTH, SAFETY and ENVIRONMENTAL REQUIREMENTS

    Toolbox talk will be done with the team who is involved in the foundation works. Job Safety Analysis (JSA)will be prepared and distributed to Site Supervisor(s). Using related JSA, Method Statement and Risk Assessment will be discussed during the toolbox talk.

    While excavation works, barricade will be installed to the around the pit and warning signs will be put towarn other people to keep away.

    Mandatory Personal Protective Equipment will be used by the person involved in the operation. There is norequirement for additional PPE.

    Risk Assessment will be taken into consideration and required precautions will be taken.

    Materials

    1. Mandatory Personal Protective Equipment,

    -  Safety Helmet

    -  Safety Shoes

    -  Safety Vest

    -  Safety Gloves

    -  Safety Glasses’/Goggles

    2. Personal Protective Equipment Required Due to Specific Risks,

    -  Safety Harness,

    -  Dust and/or Chemical Masks

    3. Safety Barricading Fence/Netlon Fence

    4. Related Safety/Warning Signs.

    14.0 RISK ASSESSMENTS

    Please see attached Khabat Project Risk assessment as Attachment-2.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    10/27

    METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION

    Page: 9/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015

    Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0

    15.0 REFERENCES

    All erection works will be controlled and checked after installation as per the document indicated below:

    Document Name Document Number  

    ITP for CIRCUIT BREAKER INSTALLATION WORKS

    KP-00+++-CQ712-B7357

    16.0 TECHNICAL APPENDICES

    Please see attached Khabat Project Vendor List as Attachment-3.

    17.0 ATTACHMENTS

    Attachment-1 27.01.2015 Dated Time ScheduleAttachment-2 Risk AssessmentAttachment-3 Vendor List

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    11/27

    Design, Equipment Manufacturing, Test andDelivery Time Schedule

    TOTAL 6 PAGES

    (Including Cover)

    PROJECT NAME : Khabat Thermal Power Plant Units 1&2 Purpose

    ☐ For Information

    ☒ For Review

    ☐ For Approval

    ☐ For Construction

    ☐ As-Built

    DOCUMENT NO. : KP-00++++-MX000-V0001

    TITLE : Updated time schedule / 27.01.2015

    OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government

    S 27.01.2015 27.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ

    R 20.01.2015 20.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ

    P 13.01.2015 13.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ

    0 06.01.2015 06.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ

    N 30.12.2014 30.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    M 23.12.2014 23.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    L 16.12.2014 16.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    K 09.12.2014 09.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    J 02.12.2014 02.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    I 25.11.2014 25.11.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    H 18.11.2014 18.11.2014 dated TS update SIEMENS/OO SIEMENS/EÖ

    Rev.No.

    DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED

    GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

    Owner 

    Ministry of Electrici ty (MOE)of Kurdistan Regional Government

    Contractor 

    POSCO ENGINEERING

    & CONSTRUCTION CO., LTD.

    Main Subcontractor 

    GAMA POWER SYSTEMSENGINEERING & CONTRACTING,INC.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    12/27

    Activity Name Dur. %Complete Start Finish

    alal 03 66.31%25-Apr-14 A 11-Jun-15

    ababat Updated Work Programme- ACT_27.01.2015 03 66.31%25-Apr-14 A 11-Jun-15

    ectect Start (General) 0 3 1 00 % 2 5- Apr -1 4 A 11-Jun-15

    10 Co ntract Signature & Co mm encement Date (O ffshore) 1 1 00 % 25 -Apr-1 4 A 2 5-Apr-1 4 A

    82 Providing of Soil Investigation Report By GAMA 0 100% 15-May-14

    11 Co ntract Signature & Co mm ensment Date (Onsho re) 1 1 00 % 13 -Jun-1 4 A 1 3-Jun-1 4 A

    85 Advance Payment (Onshore and Offshore) 0 100% 20-Jun-14 A

    81 Submission of Inspection and Test Plan 0 100% 01-Jul-14 A

    83 Site Handover 0 100% 30-Aug-14 A

    84 Site Requirements for Mobilization ((Power/Water Supply, Sanitary, Storage Area 0 100% 30-Aug-14 A

    88 M eth od of St ate me nt fo r S ub st at io n Er ec tio n( KHB -S IE -G AM -A IS -0 05 8) 0 1 00 % 0 3- Sep -1 4 A

    87 Method of Statement for Mobilization 0 100% 17-Sep-14 A

    90 Method of Statement for Civil Work at Switchyard Area 0 100% 12-Nov-14

    86 PAC (Ready for Energization - Take Over) 0 0% 11-Jun-15

    gngn & Engineering 72 94.85%01-May -14 A 09-Feb-15

    sicsic Design 1 97 1 00 % 0 1 -M ay -1 4 A 1 2- No v- 14

    -11 Preparation and Submission of General Layout, Site Layout & Section 2 1 1 00 % 0 1 -M ay -1 4 A 2 2- Ma y- 14

    - 11 P rep ar at io n an d S ubm is sio n o f S ec ond ar y B as e Des ign 2 1 1 00 % 0 1- May -1 4 A 2 2- May -1 4

    -1 1 Preparatio n and Submiss io n o f Single Line Diagram 2 1 1 00 % 01 -M ay-1 4 A 2 2-M ay-14

    -11 Preparation and Submission of Control, Protection & Metering System Base Desig 21 100% 01-May-14 A 22-May-14

    -11 Preparat ion and Submission of Substation Building Equipment Layout Plan 21 100%01-May-14 A 22-May-14

    -11 Preparat ion and Submission of General Cable Trenches and Foundation Layout 21 100%01-May-14 A 22-May-14

    -11 Approval of Single Line Diagram 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A

    -11 Approval of General Layout, Site Layout & Section 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A

    -11 Approval of Secondary Base Design 14 100% 23-May-14 A 03-Jul-14 A

    - 11 A pp ro va l o f Co nt ro l, Pr ot ec ti on & Me te rin g S ys te m B as e D es ig n 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A

    - 11 A ppr ova l o f S ub st at io n B uild in g E qu ipm en t La yo ut Pla n 1 4 1 00 % 2 3- May -1 4 A 0 3- Jul- 14 A

    - 11 A pp ro va l o f G en er al C ab le T re nc he s a nd F ou nd at io n L ay ou t 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A

    - 11 S tat ic & Dy nam ic Lo ad Calc ulat io ns fo r 1 32 kV Equ ip me nts 5 1 00 % 0 1- Sep -1 4 A 0 5- Sep -1 4 A

    095 Decision for ECS -1 Option(KHB-GAM-SIE-AIS-0051 dtd 05.09.2014) 0 100% 05-Sep-14 A

    093 Approval of AC/DC Load List for Battery & Battery Charger 0 100% 14-Sep-14 A

    094 Dec is ion f or 48VDC Ba tt ery & Ba tt ery Cha rger(K HB-GAM-SIE-AIS-00073 d td 30. 0 100% 30-Sep-14 A

    096 Decision for Painting Code of LV Panels & Control Protection Panels(KHB-SIE-GA - -0 100% 12-Nov-14

    hn ihnical Documents for Equipment/Systems 114 87.69%01-Aug-14 A 09-Feb-15

    -11 Preparation and Submission of 120 Surge Arresters Technical Documents(KHB-SI- - -5 0 1 00 % 0 1 -A ug -1 4 A 1 4- Au g- 14 A

    -11 Preparation and Submission of 132kV Disconnecting Switch Technical Documents 50 100% 09-Aug-14 A 15-Sep-14 A

    -11 Preparation and Submission of 132kV Earthing Switch Technical Documents 5 0 1 00 % 0 9- Sep -1 4 A 15-Sep-14 A-11 Preparation and Submission of 132kV Capacitive Voltage Transformers Technical 5 0 1 00 % 0 9- Aug -1 4 A 18-Sep-14 A

    -11 Preparation and Submission of 132kV Current Transformers Technical Documents 50 100% 09-Aug-14 A 18-Sep-14 A

    -11 Approval of 132kV Capacitive Voltage Transformers Technical (KHB-GAM-SIE-AIS- 1 4 1 00 % 1 9 -S ep -1 4 A 0 3- Oc t- 14 A

    -11 Approval of 132kV Current Transformers Technical Documents(KHB-GAM-SIE-AI - 1 4 1 00 % 1 9 -S ep -1 4 A 0 3- Oc t- 14 A

    -11 Approval of 132kV Disconnecting Switch Technical Documents(KHB-GAM-SIE-AIS- 1 4 1 00 % 1 6 -S ep -1 4 A 0 3- Oc t- 14 A

    -11 Approval of 132kV Earthing Switch Technical Documents(KHB-GAM-SIE-AIS-000 14 100%16-Sep-14 A 03-Oct-14 A

    -11 Preparation and Submission of Insulators Technical Documents(KHB-SIE-GAM-AI - 5 0 1 00 % 1 2- Sep -1 4 A 07-Oct-14 A

    -11 Preparation and Submission of LV Cable Technical Documents(KHB-SIE-GAM-AIS- 1 0 1 00 % 0 1 -O ct -1 4 A 1 3- Oc t- 14 A

    -11 Preparat ion and Submission of 132kV Curcuit Breaker Technical Documents(KHB- - - -5 0 1 00 % 1 2 -S ep -1 4 A 1 4- Oc t- 14 A

    -11 Approval of LV Cable Technical Documents(KHB-GAM-SIE-00093 dtd 30.10.201 14 100%14-Oct-14 A 30-Oct-14 A

    -11 Approval of Insulators Technical Documents(KHB-GAM-SIE-00092 dtd 30.10.20 14 100%14-Oct-14 A 30-Oct-14 A

    -11 Approval of 132kV Curcuit Breaker Technical Documents(KHB-GAM-SIE-00091 d 14 100%14-Oct-14 A 30-Oct-14 A

    -11 Preparation and Submission of Earthing Conductor Technical Particulars(KP-SIE-G - -1 6 1 00 % 2 3 -S ep -1 4 A 1 4- No v- 14

    -11 Preparat ion and Submission of Aluminium Bus Bar Technical Documents(KHB-SIE- - -5 0 1 00 % 1 2- Sep -1 4 A 19-Nov-14

    -11 Approval of 120kV Surge Arresters Technical Documents(KHB-GAM-SIE-AIS-001 1 4 1 00 % 1 4- Aug -1 4 A 21-Nov-14

    -11 Preparat ion and Submission of Tension and Suspent ion Technical Documents(KH- - - -5 0 1 00 % 1 2 -S ep -1 4 A 2 4- No v- 14

    -11 Approval of Aluminium Bus Bar Technical Documents(KHB-GAM-SIE-AIS-00127 d 14 100% 19-Nov-14 A 03-Dec-14 A

    -11 Approval of Earthing Conductor Technical Particulars(KHB-GAM-SIE-AIS-00128 dt 14 100% 14-Nov-14 A 03-Dec-14 A

    -11 Approval of Tension and Suspention Technical Documents(KHB-GAM-SIE-AIS-00 14 100%24-Nov-14 A 05-Dec-14 A

    -11 Preparation and Submission of Battery Chargers Documents(KHB-SIE-GAM-AIS- 3 5 1 00 % 1 2 -N ov -1 4 A 2 3- De c- 14 A

    -11 Preparation and Submission of Station Batteries Documents(KHB-SIE-GAM-AIS-0 3 5 1 00 % 1 2 -N ov -1 4 A 2 3- De c- 14 A

    -11 Approval of Station Batteries Documents 1 4 0 % 23 -Dec-1 4 A 0 9-Feb-1 5

    -11 Approval of Battery Chargers Documents 14 0% 23-Dec-14 A 09-Feb-15

    tai lailed Design 153 90.85%22-May -14 A 09-Feb-15uipmuipment/Systems 97 85.55%22-May -14 A 09-Feb-15

    1-1 Preparat ion of Typical Feeders Schematic Drawings & Cable Schedules & LVAC-LV - - - -4 9 1 00 % 2 2 -M ay -1 4 A 0 5- Au g- 14 A

    1-1 Submission of Typical Feeders Schematic Drawings & Cable Schedules & & LVAC- 1 1 00 % 0 5 -A ug -1 4 A 0 5- Au g- 14 A

    1-1 Preparation of General Earthing and Outdoor Equipment Earthing and Cable Tray - - - -1 8 1 00 % 0 2- Aug -1 4 A 28-Aug-14 A

    1-1 Preparation and Submission of Substation Grounding Mesh Layout (KHB-SIE-GA - -1 8 1 00 % 1 0- Aug -1 4 A 28-Aug-14 A

    -1 Submission of Earthing Detailed Design 1 100% 28-Aug-14 A 28-Aug-14 A

    1- 1 P re pa ra ti on of Fa ra da y C ag e P ro je ct (K HB -S IE -G AM -A IS -0 06 3) 7 1 00 % 2 9 -A ug -1 4 A 0 7- Se p- 14 A

    -1 Submission of Faraday Cage Project 1 100% 07-Sep-14 A 07-Sep-14 A

    1-1 Approval of Earthing Detailed Design(KHB-GAM-SIE-AIS-0070 dtd 24.09.2014)(S - - -1 4 1 00 % 2 8 -A ug -1 4 A 3 0- Se p- 14 A

    Feb Mar   Apr  May Jun Jul  Aug Sep Oct Nov Dec Jan Feb Mar   Apr  May Jun Jul  Aug Sep

    Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015

    11-Jun-15, Total

    11-Jun-15, K haba t Updat ed Work P -

    11-Jun-15, Project Start (General)

    Providing of Soil Investigation Report By GAMA

    Advance Payment (Onshore and Offshore)

    Submission of Inspection and Test Plan

    Site Handover

    Site Requirements for Mobilization ((Power/Water Supply, Sanitary, Storage Area) by GAMA)

    Method of Statement for Substation Erection(KHB-SIE-GAM-AIS-0058)

    Method of Statement for Mobilization

    Method of Statement for Civil Work at Switchyard Area

    PAC (Ready for Energization - Take

    09-Feb-15, Design & Engineering

    12-Nov-14 A, Basic Design

    Decision for ECS -1 Option(KHB-GAM-SIE-AIS-0051 dtd 05.09.2014)

    Approval of AC/DC Load List for Battery & Battery Charger

    Decision for 48VDC Battery & Battery Charger(KHB-GAM-SIE-AIS-00073 dtd 30.09.201 4))

    Decision for Painting Code of LV Panels & Control Protection Panels(KHB-SIE-GAM-AIS-00113 dtd 05.11.2014 ))

    09-Feb-15, Technical Documents for Equipment/Systems

    09-Feb-15, Detailed Design

    09-Feb-15, Equipment/Systems

    at Updated Work Programme- ACT_27.01.2015 1 of 5

     Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Summary

    132kV Khabat Updated Work Programme

    Data date: 27.01.2015

    Date Revision Chec... Approved

    K habat P RO JE CT O O

    s

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    13/27

    Activity Name Dur. %Complete Start Finish

    -1 Subm is sio n of Lightning Pro tec tio n Detailed Design 1 1 00 % 01 -Oc t-1 4 A 0 1-Oct-1 4 A

    1-1 Switchyard and Control Building Lightning Protection Layout (KHB-SIE-GAM-AIS-0 2 0 1 00 % 0 1 -S ep -1 4 A 0 1- Oc t- 14 A

    1-1 Approval of Lightning Protect ion Detailed Design(KHB-GAM-SIE-AIS-0082 dtd 17. 14 100%01-Oct-14 A 17-Oct-14 A

    1-1 Approval of Typical Feeders Schematic Drawings & Cable Schedules & & LVAC-LV - -1 4 1 00 % 0 5 -A ug -1 4 A 2 2- Oc t- 14 A

    1-1 Preparat ion and Submission of HV Hardware & Connectors Layout Plan & Sect ion - - - -1 6 1 00 % 2 3 -S ep -1 4 A 2 9- Oc t- 14 A

    -1 Preparation of ECS System Detailed Design 5 0 1 00 % 1 3- Sep -1 4 A 09-Nov-14

    -1 Submission of ECS System Detailed Design 1 1 00 % 0 9- Oc t- 14 A 0 9- No v- 14

    1- 1 P rep ar at io n of Te le co mm un ic at io n Sys te m Det aile d Des ig n 5 0 1 00 % 2 4- Sep -1 4 A 1 3- No v- 14

    1-1 Preparat ion and Submission of HV Hardware & Connectors Detailed Outline Draw - - - -1 6 1 00 % 2 3 -S ep -1 4 A 1 4- No v- 14

    1-1 Submission of Indoor & Outdoor Lighting & Low Power Detailed Design(KP-SIE-G - -1 1 00 % 1 4 -N ov -1 4 A 1 4- No v- 14

    1-1 Submission of Telecommunicat ion System Detailed Design(KP-SIE-GMH-T-00076 1 100%14-Nov-14 A 14-Nov-14

    1-1 Preparat ion of Indoor & Outdoor & Emergency Lighting & Low Power Detailed De 30 100%08-Sep-14 A 14-Nov-14

    -1 Approval of HV Hardware & Connectors Detailed Design(KHB-GAM-SIE-AIS-0011 1 4 1 00 % 1 4 -N ov -1 4 A 2 0- No v- 14

    -1 Approval of Faraday Cage Project(KHB-GAM-SIE-AIS-00117 dtd 21.11.2014) 1 4 1 00 % 0 7- Sep -1 4 A 21-Nov-14

    -1 Appro val of Telec om municatio n System Detailed Design 1 4 0 % 14 -No v-1 4 A 0 9-Feb-1 5

    -1 Approval of ECS System Detailed Design 14 0% 09-Nov-14 A 09-Feb-15

    1- 1 A pp ro va l o f In do or & Ou td oo r Li gh ti ng & Lo w Po we r D et ai le d D es ig n 1 4 0 % 1 4 -N ov -1 4 A 0 9- Fe b- 15il Wil Works 1 53 9 7. 39 % 0 3 -J ul -1 4 A 3 0- Ja n- 15eel -eel Structures-Fabrication and Templates 1 34 1 00 % 2 5 -A ug -1 4 A 1 8- Ja n- 15 A

    1-1 132kV Gantry Tower Type P1 Fabrication Drawings (KHB-SIE-GAM-AIS-0053) 2 0 1 00 % 2 5- Aug -1 4 A 02-Sep-14 A

    1-1 132kV Gantry Tower Beam Type K1 Fabrication Drawings(KHB-SIE-GAM-AIS-00 2 0 1 00 % 2 5- Aug -1 4 A 02-Sep-14 A

    1-1 1 32 kV Gantry To wer Type P6 F abrication Draw ings 1 2 1 00 % 06 -Sep-1 4 A 2 0-Sep-1 4 A

    1- 1 1 32 kV Ga ntr y To wer Be am Typ e K6 Fa br ic at io n Dra win gs 1 2 1 00 % 0 6- Sep -1 4 A 2 0- Sep -1 4 A

    1-1 132kV Voltage Transformer Support Structure Fabrication Drawings(KP-SIE-GM - -20 100% 06-Sep-14 A 27-Oct-14 A

    1-1 132kV Current Transformer Support Structure Fabrication Drawings(KP-SIE-GM - -20 100% 06-Sep-14 A 27-Oct-14 A

    1-1 132kV Disconnecting Switch Serial Type Support Structure Fabrication Drawing(K - - - -2 0 1 00 % 0 6 -S ep -1 4 A 2 7- Oc t- 14 A

    1-1 132kV Lightning Tower Fabrication Drawings_P2(KP-SIE-GMH-T-00057) 2 0 1 00 % 0 6- Sep -1 4 A 27-Oct-14 A

    1-1 132kV Surge Arrester Support Structure Fabrication Drawings(KP-SIE-GMH-T-00 2 0 1 00 % 0 6- Sep -1 4 A 29-Oct-14 A

    1-1 132kV Curcuit Breaker Support Structure Fabricat ion Drawings(KP-SIE-GMH-T-0 20 100%06-Sep-14 A 01-Nov-14

    1-1 Subm is sio n o f 1 32 kV Steel Structure Detailed Design 1 1 00 % 17 -No v-1 4 A 1 7-No v-1 4

    1-1 132kV Ear th ing Sw it ch + SA Suppo rt Struc ture Fabrica tion Draw ing 20 100%06-Sep-14 A 17-Nov -14

    1-1 132kV Disconnecting Switch with Earthing Blade Support Structure Fabrication Dr 20 100% 06-Sep-14 A 17-Nov-14

    1-1 132kV Surge Arrester Support Structure Fabrication Drawing - Transformer Side 20 100%06-Sep-14 A 17-Nov-14

    1-1 132kV Cable Sealing End Support Structure Fabrication Drawing (KP-SIE-GMH-T- 5 1 00 % 0 6- Jan -1 5 A 1 8- Jan -1 5 Awitc hwitchyard Civil Design 1 38 9 7. 1% 1 5 -S ep -1 4 A 30-Jan-15ound ,oundation for Equipment, Gantry and Busducts 1 38 9 7. 1% 1 5 -S ep -1 4 A 3 0- Ja n- 15

    1- 132kV Gantry Tower Type P1 & P6 Foundation Drawings(KHB-SIE-GAM-AIS-009 8 100%15-Sep-14 A 01-Oct-14 A

    1- 132kV Surge Arrester Support Structure Foundat ion Drawing(KP-SIE-GMH-T-000 10 100%29-Oct-14 A 10-Nov-14

    1- 132kV Voltage Transformer Support Structure Foundat ion Drawing(KP-SIE-GMH-- 10 100%27-Oct-14 A 10-Nov-14

    1- 132kV Current Transformer Support Structure Foundation Drawing(KP-SIE-GMH-- 10 100% 27-Oct-14 A 10-Nov-14

    1- 132kV Circuit Breaker Support Structure Foundation Drawing(KP-SIE-GMH-T-00 1 0 1 00 % 0 3 -N ov -1 4 A 1 0- No v- 14

    1- 132kV Lightning Tower Foundation Drawings_P2(KP-SIE-GMH-T-00073) 1 0 1 00 % 2 7 -O ct -1 4 A 1 0- No v- 14

    1- S ub mis si on of 13 2k V E qu ip me nt Fo un da ti on De ta il s a nd Se ct io ns 1 1 00 % 1 7 -N ov -1 4 A 1 7- No v- 14

    1- 132kV Disconnecting Switch Serial Type Support Structure Foundation Drawing 10 100%27-Oct-14 A 17-Nov-14

    1- 132kV Disconnecting Switch with Earthing Blade Support Structure Foundat ion Dr 5 100%11-Nov-14 A 17-Nov-14

    1- 132kV Surge Arrester Support Structure Foundation Drawing Transformer Side 5 100%11-Nov-14 A 17-Nov-14

    1- 132kV Earthing Switch + SA Support Structure Foundation Drawing Transformer 5 100% 11-Nov-14 A 17-Nov-14

    1- 132kV Cable Sealing End Support Structure Foundation Drawing 5 2 0% 2 6 -J an -1 5 A 3 0- Jan -1 5vilvil Work Design of Ancillary Service Foundations 8 0 1 00 % 1 5- Sep -1 4 A 17-Nov-14

    1- P repa ra tion and Submiss ion of Cable T rench P lan & Se ct ions & Re in fo rcement Det - - - -1 0 1 00 % 1 5 -S ep -1 4 A 1 5- Oc t- 14 A

    1- A pp ro va l o f Ca bl e T re nc h Pl an & Se ct io ns & Re in fo rc em en t D et ai ls 1 4 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A

    1- Preparation and Submission of Marshalling Box Foundation Application Plan, Form 1 0 1 00 % 1 5 -S ep -1 4 A 1 5- Oc t- 14 A

    1- Approval of Marshalling Box Foundation Application Plan, Formwork & Reinforcem 14 100% 15-Oct-14 A 15-Oct-14 A

    1- P re pa ra ti on a nd S ub mi ss io n of S wit ch ya rd L ig ht in g & Fo un da ti on s 1 0 1 00 % 1 5 -S ep -1 4 A 1 7- No v- 14

    1- Approval of Switchyard Lighting Pole & Foundations 1 4 1 00 % 1 7 -N ov -1 4 A 1 7- No v- 14vilvil Work Design of Site Works 4 9 1 00 % 2 4- Sep -1 4 A 17-Nov-14

    1- Preparat ion of Substat ion Fence & Gate Details(KP-SIE-GMH-T-00051 dtd 15.10 10 100%24-Sep-14 A 15-Oct-14 A

    1- Preparation of Switchyard Service Road Plan Details and Sections(KP-SIE-GMH-T- 1 0 1 00 % 2 4 -S ep -1 4 A 1 5- Oc t- 14 A

    1- Submission of Substation Fence & Gate Details 1 100% 15-Oct-14 A 15-Oct-14 A

    1- Approval of Substation Fence & Gate Details 14 100% 15-Oct-14 A 15-Oct-14 A

    1- S ub mis si on of Sw it ch ya rd Se rv ic e R oa d P la n De ta il s a nd Se ct io ns 1 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A

    1- Approval of Switchyard Service Road Plan Details and Sections 1 4 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A

    1- Preparation and Submission of Drainage System 1 0 1 00 % 2 4- Sep -1 4 A 17-Nov-14

    1- Approval of Switchyard Drainage System 14 100% 17-Nov-14 A 17-Nov-14uildinilding Architectural Design 1 5 1 00 % 0 3- Jul- 14 A 0 4- Sep -1 4 A

    1-1 Subs tatio n Building Architectural Plans and Details 1 4 1 00 % 03 -Jul-1 4 A 1 7-Jul-1 4 A

    1-1 Submission of Architectural Detailed Design for Substation Building(KHB-SIE-GAM- -1 100% 17-Jul-14 A 17-Jul-14 A

    1-1 Approval of Architectural Detailed Design for Substation Building(KHB-SIE-GAM-AI- 14 100% 17-Jul-14 A 04-Sep-14 Auildinilding Structural Design 2 4 1 00 % 0 4- Sep -1 4 A 22-Sep-14 A

    1-1 Substation Building Structural Plans and Details 1 4 1 00 % 0 4- Sep -1 4 A 19-Sep-14 A

    1- 1 S ub mis si on of St ru ct ur al De ta il ed De si gn fo r Su bs ta ti on Bu il di ng 1 1 00 % 1 9 -S ep -1 4 A 1 9- Se p- 14 A

    1- 1 A pp ro va l o f S tr uc tu ra l D et ail ed De si gn fo r S ub st at io n B ui ld in g 1 4 1 00 % 2 2 -S ep -1 4 A 2 2- Se p- 14 Auildinilding Sanitary Design 4 3 1 00 % 1 4 -O ct -1 4 A 1 7- No v- 14

    1-1 Substation Building Sanitary and Sewage System for Ground & First Floor Layout 10 100% 14-Oct-14 A 17-Nov-14

    1-1 Submit of Substation Building Sanitary and Sewage System for Ground & First Flo 1 100% 17-Nov-14 A 17-Nov-14

    leasease for Construction Drawings 4 7 1 00 % 0 3- Jul- 14 A 1 5- Oc t- 14 A

    -11 RFC Drawing for General Layout, Site Layout & Section 7 1 00 % 0 3- Jul- 14 A 0 3- Jul- 14 A

    - 11 RF C Dr aw in g fo r S ubs ta tio n B uild in g E qu ip men t La yo ut Pla n 7 1 00 % 0 3- Jul- 14 A 0 3- Jul- 14 A

    - 11 R FC Dr aw in g f or Ge ne ra l C ab le Tr en ch es an d F ou nd at io n L ay ou t 7 1 00 % 0 3 -J ul -1 4 A 0 3- Ju l- 14 A

    -11 RFC Drawing f or Struc tura l Det ai le d Des ign f or Subst at ion Bui ld ing 7 100%25-Sep-14 A 25-Sep-14 A

    -11 RFC Draw ing f or Arch it ec tura l Det ai le d Des ign f or Subs ta tion Bu ilding 7 100%26-Sep-14 A 26-Sep-14 A-11 RFC Drawing for Substation Fence & Gate Details(KP-SIE-GMH-T-00051 dtd 15. 7 100%15-Oct-14 A 15-Oct-14 A

    -11 RFC Drawing for Switchyard Service Road Plan Details and Sections(KP-SIE-GMH- - 7 1 00 % 1 5- Oc t- 14 A 1 5- Oc t- 14 A

    -11 RFC Drawing for Cable Trench Plan & Sections & Reinforcement Details(KP-SIE-G - -7 1 00 % 1 5- Oc t- 14 A 1 5- Oc t- 14 A

    chachasing & Manufacturing 0 6 7 1. 84 % 1 3 -J un -1 4 A 2 5- Ma r- 15

    r chachase Order 1 02 1 00 % 1 3 -J un -1 4 A 0 2- De c- 14 A

    -11 Purchasing of Steel Structures 10 100% 13-Jun-14 A 13-Jun-14 A

    -11 Purchasing of 120kV Surge Arresters 10 100% 04-Jul-14 A 17-Jul-14 A

    -11 Purchasing of Disconnecting Switch 10 100% 04-Jul-14 A 17-Jul-14 A

    -11 Purchasing of Earthing Switch 1 0 1 00 % 0 4- Jul- 14 A 1 7- Jul- 14 A

    -11 Purchasing of 132kV Capacitive Voltage Transformers 1 0 1 00 % 0 4- Jul- 14 A 1 8- Jul- 14 A

    Feb Mar   Apr  May Jun Jul  Aug Sep Oct Nov Dec Jan Feb Mar   Apr  May Jun Jul  Aug Sep

    Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015

    30-Jan-15, Civil Works

    18-Jan-15 A, Steel Structures-Fabrication and Templates

    30-Jan-15, Switchyard Civil Design

    30-Jan-15, Foundation for Equipment, Gantry and Busducts

    17-Nov-14 A, Civil Work Design of Ancillary Service Foundations

    17-Nov-14 A, Civil Work Design of Site Works

    04-Sep-14 A, Building Architectural Design

    22-Sep-14 A, Building Structural Design

    17-Nov-14 A, Building Sanitary Design

    15-Oct-14 A, Release for Construction Drawings

    25-Mar-15, Purchasing & Manufacturing

    02-Dec-14 A, Purchase Order

    at Updated Work Programme- ACT_27.01.2015 2 of 5

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    14/27

    Activity Name Dur. %Complete Start Finish

    -11 Purchasing of 132kV Current Transformers 10 100% 04-Jul-14 A 18-Jul-14 A

    -11 Purchasing of 132kV Curcuit Breaker 10 100% 18-Jul-14 A 28-Jul-14 A

    -11 Purchasing of Telecommunication System 10 100% 15-Aug-14 A 10-Sep-14 A

    -1 1 Purchasing o f ECS Sys tem(KHB-GAM -SIE-AIS-0 05 1)) 1 0 1 00 % 06 -Sep-1 4 A 1 5-Sep-1 4 A

    -11 P urchasing of Insulators 10 100% 15-Sep-14 A 22-Sep-14 A

    -11 Purchasing of LV Cables 1 0 1 00 % 0 2- Sep -1 4 A 22-Sep-14 A

    -11 Purchasing of Control, Protection & Metering Panels 1 0 1 00 % 1 4 -O ct -1 4 A 1 4- Oc t- 14 A

    -11 Purchasing of LVAC Distribution Panels 10 100% 14-Oct-14 A 21-Oct-14 A

    -11 Purchasing of LVDC Distribution Panels 10 100% 14-Oct-14 A 21-Oct-14 A

    -11 Purchasing of Earthing Materials 10 100% 13-Oct-14 A 23-Oct-14 A

    -11 Purchasing of Station Batteries (KHB-SIE-GAM-AIS-0035),(KHB-SIE-GAM-AIS-00 1 0 1 00 % 3 0 -S ep -1 4 A 3 1- Oc t- 14 A

    -11 Purchasing of Battery Chargers(KHB-SIE-GAM-AIS-0035),(KHB-SIE-GAM-AIS-00 1 0 1 00 % 3 0 -S ep -1 4 A 3 1- Oc t- 14 A

    -11 Purchasing of HV Hardware & Connectors 1 0 1 00 % 0 9 -O ct -1 4 A 0 3- No v- 14

    -11 Purchasing of Aluminium Bus Bar 1 0 1 00 % 0 9 -O ct -1 4 A 0 4- No v- 14

    -11 Purchasing of Tension and Suspention 10 100% 04-Nov-14 A 07-Nov-14

    -11 Purchasing of Lightning Protection Materials 10 100% 1 0-Nov-14 A 11-Nov-14

    -11 P urchasing of Cable Trays 10 100% 07-Nov-14 A 25-Nov-14

    -1 1 Purchasing of Indo or & Lighting Luminares_ Outdo or 1 0 1 00 % 14 -No v-1 4 A 0 2-Dec -1 4 A

    nuf nufacturing 0 6 7 1. 84 % 1 8 -J ul -1 4 A 2 5- Ma r- 15

    -11 Manufacturing of 120kV Surge Arresters 1 72 1 00 % 1 8- Jul- 14 A 2 7- Oc t- 14 A

    -11 Manufacturing of P1 & P6 Templates / Anchor Bolts 5 2 1 00 % 0 6 -O ct -1 4 A 0 8- No v- 14

    -1 1 M anufacturing o f Lightning Pro tec tio n M aterials 3 5 1 00 % 11 -No v-1 4 A 1 8-No v-1 4

    -1 1 M anufacturing o f Other Templates / Anchor Bolts 2 0 1 00 % 01 -No v-1 4 A 2 6-No v-1 4

    - 11 M anu fa ct urin g o f 13 2kV C ap ac it iv e Vo lt ag e Tr ans fo rm er s 1 72 1 00 % 1 8- Jul- 14 A 3 0- No v- 14

    -11 Manufacturing of 132kV Current Transformers 172 100% 1 8-Jul-14 A 30-Nov-14

    -11 Manufacturing of Disconnecting Switch 172 100% 18-Jul-14 A 30-Nov-14

    -11 Manufacturing of Earthing Switches 1 72 1 00 % 1 8- Jul- 14 A 3 0- No v- 14

    -11 Manufacturing of P1 & P6 Steel Structures 5 2 1 00 % 2 0 -O ct -1 4 A 0 3- De c- 14 A

    -11 Manufacturing of Earthing Materials (Lugs, Rods, Cadweld Materials, Equi-potentia 80 100% 23-Oct-14 A 15-Dec-14 A

    -11 Manufacturing of LVAC Distribution Panels 100 100% 21-Oct-14 A 21-Dec-14 A

    -11 Manufacturing of LVDC Distribution Panels 100 100% 21-Oct-14 A 21-Dec-14 A

    -11 M anufacturing of Insulators 140 100% 24-Sep-14 A 22-Dec-14 A

    -11 Manufacturing of Aluminium Bus Bar 70 100% 04-Nov-14 A 28-Dec-14 A

    -11 Manufacturing of Other Switchyard Steel Structures & Templates 6 4 1 00 % 2 0 -O ct -1 4 A 2 9- De c- 14 A

    -11 Manufacturing of Cable Trays 6 0 1 00 % 2 5 -N ov -1 4 A 3 1- De c- 14 A

    -11 Manufacturing of HV Hardware & Connectors 70 100% 03-Nov-14 A 15-Jan-15 A

    -11 M anufacturing of LV Cables 130 100% 22-Sep-14 A 15-Jan-15 A

    -11 Manufacturing of Tension and Suspentions 70 100% 07-Nov-14 A 15-Jan-15 A

    -11 Manufacturing of Control, Protection Panels 100 100% 1 4-Oct-14 A 26-Jan-15 A

    -11 Manufacturing of Telecommunication System 130 100% 1 0-Sep-14 A 27-Jan-15 A

    -11 Manufacturing of Station Batteries 9 0 1 00 % 3 1 -O ct -1 4 A 2 7- Ja n- 15 A

    -11 Manufacturing of Battery Chargers 9 0 1 00 % 3 1 -O ct -1 4 A 2 7- Ja n- 15 A

    -11 Manufacturing of 132kV Curcuit Breakers 199 96.98% 18-Jul-14 A 01-Feb-15

    -11 M anufacturing of ECS 160 87.5% 15-Sep-14 A 15-Feb-15

    -11 Manufacturing of Metering Panels 100 80% 14-Oct-14 A 15-Feb-15

    - 11 M anu fa ct ur ing o f Indo or & O ut do or Lig ht ing L um in are s 1 00 5 6% 0 2 -De c- 14 A 2 5- Mar -1 5

    utinutine Tests 56 62.64%26-Dec-14 A 16-Feb-15

    -12 Submission of 132kV Capacitive Voltage Transformers Routine Test Reports 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A

    -12 Submission of 120kV Surge Arresters Routine Test Reports 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A

    - 12 S ub mis si on o f 1 32 kV C ur re nt Tr an sf or me rs Ro ut in e T es t R ep or ts 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A

    - 12 S ubm is sio n o f Dis co nn ec tin g S wit ch Ro ut in e Te st Rep ort s 1 1 00 % 2 6- De c- 14 A 2 6- Dec -1 4 A

    -1 2 Subm is sio n o f Earthing Switch Ro utine Test Repo rts 1 1 00 % 26 -Dec-1 4 A 2 6-Dec -1 4 A

    -12 Submission of Insulators Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    - 12 S ubm is sio n o f L VAC Dis tr ibu tio n P an els Ro ut in e T es t Rep ort s 1 0 % 2 7- Jan -1 5 2 7- Jan -1 5

    -12 Submission of LVDC Distribution Panels Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    -12 Submission of Aluminium Bus Bar Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    - 12 S ubm is sio n o f H V Ha rd wa re & C on ne ct or s Ro utin e T es t Rep or ts 1 0 % 2 7- Jan -1 5 2 7- Jan -1 5

    - 12 S ub mis si on o f L ig ht ni ng P ro te ct io n M at er ia ls R ou ti ne T es t R ep or ts 1 0 % 2 7 -J an -1 5 2 7- Ja n- 15

    -12 Submission of Station Batteries Routine Test Reports 1 0% 2 7-Jan-15 27-Jan-15

    -12 Submission of Battery Chargers Routine Test Reports 1 0% 2 7-Jan-15 27-Jan-15

    -1 2 Subm is sio n o f Earthing M aterials Ro utine Test Repo rts 1 0 % 27 -Jan-1 5 2 7-Jan-1 5

    -12 Submission of LV Cables Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    -12 Submission of Tension and Suspention Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    -12 Submission of Cable Trays Routine Test Reports 1 0% 27-Jan-15 27-Jan-15

    -1 2 Subm is sio n o f 1 32 kV Curcuit Breaker Ro utine Tes t Repo rts 1 0 % 02 -F eb-15 0 2-Feb-1 5

    -12 Submiss ion o f Cont ro l, Pro te ct ion & Me te ring Pane ls Routine Te st Repo rts 1 0%16-Feb-15 16-Feb-15

    patcpatch 186 41.33%08-Nov -14 A 16-May -15

    13 M aterial Delivery Completed 0 0% 16-May-15

    nspnsportation 186 41.33%08-Nov -14 A 16-May -15

    -13 Transportation of P1&P6 Switchyard Templates / Anchor Bolts from Turkey to B 2 1 00 % 0 8 -N ov -1 4 A 0 9- No v- 14

    -13 Transportat ion of P1&P6 Switchyard Templates / Anchor Bolts from Border to Sit 3 100%09-Nov-14 A 12-Nov-14

    -13 Transportat ion of Other Switchyard Templates / Anchor Bolts from Turkey to Bo 2 100%27-Nov-14 A 28-Nov-14

    -13 Transportat ion of Other Switchyard Templates / Anchor Bolts from Border to Site 3 100%28-Nov-14 A 04-Dec-14 A

    - 13 T ra ns po rt at io n o f P 1& P6 St ee l S tr uc tu re fr om Tu rk ey to Bo rd er 1 0 1 00 % 0 3 -D ec -1 4 A 1 2- De c- 14 A

    - 13 T ra ns po rt at io n o f P 1& P6 St ee l S tr uc tu re f ro m B or de r t o S it e 1 0 1 00 % 1 2 -D ec -1 4 A 1 3- De c- 14 A

    -13 Transportation of Disconnecting Switch from Factory to Border 1 0 1 00 % 1 5 -D ec -1 4 A 2 0- De c- 14 A

    -13 Transportation of Earthing Switch from Factory to Border 1 0 1 00 % 1 5 -D ec -1 4 A 2 0- De c- 14 A

    - 13 T ra ns po rt at io n o f D is co nn ec tin g S wit ch f ro m B or de r t o S it e 1 0 1 00 % 2 0 -D ec -1 4 A 2 4- De c- 14 A

    - 13 T ran sp or tat io n o f Ea rt hin g S wit ch fr om B or der t o S it e 1 0 1 00 % 2 0- De c- 14 A 2 4- Dec -1 4 A

    -13 Transportat ion of 132kV Capacit ive Voltage Transformers Factory to Site 20 100%15-Dec-14 A 30-Dec-14 A

    - 13 T ra ns po rt at io n o f 1 32 kV Cu rr en t T ra ns fo rm er s F ac to ry to Sit e 2 0 1 00 % 1 5 -D ec -1 4 A 3 0- De c- 14 A-13 Transportation of Other Steel Structure & Templates / Anchor Bolts from Turkey 6 100% 06-Jan-15 A 11-Jan-15 A

    -13 Transportation of Other Steel Structure & Templates / Anchor Bolts from Border 3 1 00 % 1 2- Jan -1 5 A 1 5- Jan -1 5 A

    -13 Transportation of Cable trays from Turkey to Border 1 0 1 00 % 0 8 -J an -1 5 A 2 0- Ja n- 15 A

    - 13 T ra ns po rt at io n of 1 20 kV S ur ge Ar re st er s fr om F ac to ry to B or de r 2 0 1 00 % 0 4 -D ec -1 4 A 2 0- Ja n- 15 A

    -1 3 Transportatio n o f Insulators fro m Facto ry to Bo rder 1 4 1 00 % 29 -Dec-1 4 A 2 0-Jan-1 5 A

    -13 Transportation of Cable trays from Border to Site 5 100% 2 2-Jan-15 A 22-Jan-15 A

    - 13 T ra ns po rt at io n o f 1 20 kV S ur ge A rr es te rs f ro m B or de r t o S it e 5 1 00 % 2 2 -J an -1 5 A 2 2- Ja n- 15 A

    -13 Transportation of Insulators from Border to Site 5 100% 2 2-Jan-15 A 22-Jan-15 A

    -13 Transportation of Aluminium Bus Bar from Turkey to Border 1 0 7 0% 2 3 -J an -1 5 A 3 0- Jan -1 5

    -13 Transportation of Aluminium Bus Bar from Border to Site 5 0% 30-Jan-15 04-Feb-15

    Feb Mar   Apr  May Jun Jul  Aug Sep Oct Nov Dec Jan Feb Mar   Apr  May Jun Jul  Aug Sep

    Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015

    25-Mar-15, Manufacturing

    16-Feb-15, Routine Tests

    16-May-15, Dispatch

    Material Delivery Completed

    16-May-15, Transportation

    at Updated Work Programme- ACT_27.01.2015 3 of 5

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    15/27

    Activity Name Dur. %Complete Start Finish

    -13 Transpo rt at ion o f L ight ning P ro te ct ion Mat er ia ls f rom Turkey t o Bo rder 10 0%27- Jan-15 06-Feb-15

    -1 3 Transportatio n o f HV Co nnectors fro m F actory to Turkey 1 0 0 % 28 -Jan-1 5* 0 6-Feb-1 5

    - 13 T ra ns po rt at io n o f T en si on an d S us pe nt io n f ro m F ac to ry t o B or de r 1 0 0 % 2 8 -J an -1 5* 0 6- Fe b- 15

    - 13 T ran sp or tat io n of 13 2k V C urc uit Br ea ke r f ro m Fa ct or y t o Tu rk ey 5 0 % 0 2- Feb -1 5 0 6- Fe b- 15

    - 13 T ran sp or tat io n o f Ea rt hin g M at eria ls f ro m Tu rke y t o B ord er 4 0 % 0 4- Feb -1 5* 0 7- Fe b- 15

    -13 Transportation of HV Connectors from Turkey to Border 4 0% 0 7-Feb-15 10-Feb-15

    -13 Transportation of Tension and Suspention from Border to Site 4 0% 0 7-Feb-15 10-Feb-15

    -13 Transportation of LV Cables from Turkey to Border 15 0% 2 8-Jan-15* 11-Feb-15

    - 13 T ra ns po rt at io n o f H V H ar dw ar e & C on ne ct or s f ro m B or de r t o S it e 1 0 % 1 1 -F eb -1 5 1 1- Fe b- 15

    -1 3 Transportatio n o f Earthing M aterials from Bo rder to Site 5 0 % 08 -F eb-15 1 2-Feb-1 5

    - 13 T ra ns po rt at io n o f Te le co mm un ic at io n Sy st em f ro m Tu rk ey t o B or de r 1 0 0 % 0 6 -F eb -1 5* 1 6- Fe b- 15

    -13 Transportation of LV Cables from Border to Site 5 0% 12-Feb-15 16-Feb-15

    -13 Transportation of 132kV Curcuit Breaker from Turkey to Border 10 0% 0 7-Feb-15 16-Feb-15

    -13 Transportation of Lightning Protection Materials from Border to Site 10 0% 0 8-Feb-15 17-Feb-15

    -1 3 Transportatio n o f LVAC Panel fro m Turkey to Bo rder 1 5 0 % 03 -F eb-15 * 1 8-Feb-1 5

    -1 3 Transportatio n o f LVDC Panels from Turkey to Border 1 5 0 % 03 -F eb-15 * 1 8-Feb-1 5

    - 13 T ra ns po rt at io n o f T el ec om mu ni ca ti on S ys te m f ro m B or de r t o S it e 5 0 % 1 6 -F eb -1 5 2 1- Fe b- 15

    - 13 T ran sp or tat io n o f 1 32 kV C urc uit B rea ke r f ro m B or der t o S it e 5 0 % 1 7- Feb -1 5 2 1- Fe b- 15

    - 13 T ran sp or tat io n o f St atio n B at ter ie s f ro m F ac to ry to Bo rd er 1 5 0 % 1 0- Feb -1 5* 2 4- Fe b- 15

    -13 Transportation of Battery Chargers from Factory to Border 1 5 0 % 10 -F eb-15 * 2 4-Feb-1 5

    -13 Transportation of ECS System from Turkey to Border 10 0% 1 6-Feb-15 25-Feb-15

    -13 Transportat ion of Control, Protect ion & Metering Panels from Turkey to Border 10 0%16-Feb-15* 26-Feb-15

    -1 3 Transportatio n o f Battery Chargers fro m Border to Site 5 0 % 25 -F eb-15 0 1-M ar-1 5

    -1 3 Transportatio n o f Statio n Batteries from Bo rder to Site 5 0 % 25 -F eb-15 0 1-M ar-1 5

    -13 Transportation of LVAC Panel from Border to Site 15 0% 1 8-Feb-15 05-Mar-15

    -13 Transportation of LVDC Panels from Border to Site 15 0% 1 8-Feb-15 05-Mar-15

    -13 Transportation of ECS System from Border to Site 10 0% 2 6-Feb-15 07-Mar-15

    -13 Transportation of Control, Protection & Metering Panels from Border to Site 10 0% 2 6-Feb-15 08-Mar-15

    - 13 T ran sp or tat io n o f Ligh tin g Lu min ar es fr om Tu rke y to Bo rd er 1 0 0 % 2 6- Mar -1 5 0 4- Apr -1 5

    -1 3 Transportatio n o f Lighting Luminares fro m Border to Site 1 0 0 % 05 -Apr-1 5 1 4-Apr-1 5

    -13 T ransportation of Remaining Parts 30 0% 17-Apr-15 16-May-15

    WWorks 68 55.14%30-Aug-14 A 27-May -15

    bilizbilization 2 0 1 00 % 3 0 -A ug -1 4 A 2 0- Se p- 14 A

    _00 Mobilization 20 100% 30-Aug-14 A 20-Sep-14 A

    nn Building Works 167 63.06%22-Sep-14 A 29-Mar-15BSTBSTATIONCONTROL BUILDING 167 63.06%22-Sep-14 A 29-Mar-15

    _4 Excavation of Control Bldg. 10 100% 22-Sep-14 A 30-Sep-14 A

    _4 Foundation Construction of Control Bldg. 10 100% 15-Oct-14 A 22-Nov-14

    _4 R/C Walls Construction of Control Bldg. 5 100% 25-Nov-14 A 17-Dec-14 A

    _4 Column and Roof Slab of Control Bldg. 15 70% 18-Dec-14 A 31-Jan-15

    1_4 Completion of ground level concrete works 10 0% 1 0-Feb-15 20-Feb-15

    _4 Completion of the walls and roof (incl. plastering) 10 0% 1 0-Feb-15 20-Feb-15

    _4 Completion of the plumbing works 7 0% 20-Feb-15 27-Feb-15

    1_4 Completion of the electrical works installation (Indoor lighting / small power distri 10 0% 2 0-Feb-15 02-Mar-15

    _4 Completion of the surface finishing 10 0% 27-Feb-15 09-Mar-15

    _4 Completion of the remaining works 10 0% 09-Mar-15 19-Mar-15

    _4 Control Building Ready for Installation 0 0% 19-Mar-15

    1_4 Completion of the windows and doors 3 0% 1 9-Mar-15 22-Mar-15

    _4 Leakproof Cesspool and seepage pit for Substation Building 12 0% 1 7-Mar-15 29-Mar-15a kp rakproof Cesspool and seepage pit for Substation Building 7 0% 1 9-Mar-15 26-Mar-15

    _4 Completion of the sanitary works for Control Building 7 0% 1 9-Mar-15 26-Mar-15

    2 k2kV Foundation Group 113 74.34%25-Oct-14 A 24-Feb-15

    _44 132kV Gantry Tower Type 1 foundations (P1) 25 100% 2 5-Oct-14 A 06-Jan-15 A

    _44 1 32kV Busbar support foundations (P6) 25 100% 09-Nov-14 A 06-Jan-15 A

    _44 132kV Lightning Tower Gantry foundations (P2) 2 5 1 00 % 0 5 -D ec -1 4 A 1 3- Ja n- 15 A

    _45 132kV Precast -Current transformer foundations 25 80% 0 4-Dec-14 A 31-Jan-15

    _ 46 1 32 kV P rec as t -C ap ac itiv e vo lt ag e tra ns fo rm er f ou nd at io ns 2 5 8 0% 0 4 -De c- 14 A 3 1- Jan -1 5

    _ 46 1 32 kV Precas t -Surge Arrester foundatio ns (1 phase) 2 5 8 0% 0 4-Dec-1 4 A 3 1-Jan-1 5

    _44 1 32kV Precast -DS Serial foundations 25 60% 04-Dec-14 A 05-Feb-15

    _45 132kV Precast -DS foundations 25 60% 04-Dec-14 A 05-Feb-15

    _45 132kV Circuit breaker foundations 15 20% 12-Jan-15 A 07-Feb-15

    _46 132kV CSE-SA foundations (1 phase) 25 0% 3 1-Jan-15 24-Feb-15

    ble tble trenches and pipes 35 24.57%02-Jan-15 A 22-Feb-15

    _62 Marshalling Kiosk Foundations 15 20% 12-Jan-15 A 07-Feb-15

    _62 L ighting Poles Foundations the switchyards 20 0% 27-Jan-15 11-Feb-15

    _46 Cable Trenches 32 30% 02-Jan-15 A 22-Feb-15

    e De Drainage 25 0% 3 1-Jan-15 24-Feb-15

    _41 Drainage works 25 0% 31-Jan-15 24-Feb-15

    t hithing System 30 0% 2 2-Feb-15 24-Mar-15

    _41 Earthing System Trench 30 0% 2 2-Feb-15 24-Mar-15

    adsads 30 0% 2 3-Apr-15 23-May-15

    _ 41 Internal Co ncrete ro ads and site co ncrete co vering wo rks 3 0 0 % 23 -Apr-1 5 2 3-M ay-15

    talltallation of Fire Detection System 20 0% 1 9-Mar-15 08-Apr-15

    _52 Fire detection system 20 0% 19-Mar-15 08-Apr-15

    talltallation of Air - Conditioning system 20 0% 1 9-Mar-15 08-Apr-15

    _52 Air conditioning system 20 0% 1 9-Mar-15 08-Apr-15

    rkrk of gravel layer and BRC fence 64 0% 2 4-Mar-15 27-May-15

    _45 15 cm layer crushed stone 30 0% 24-Mar-15 23-Apr-15

    _45 C oncrete Posts surrounding the Switchyards 20 0% 23-Apr-15 13-May-15

    _ 45 S witc hyar d M ain Gat e fo r v eh ic le s a nd ped es tra in (1 +5 met er ) 6 0 % 1 7- May -1 5 2 3- May -1 5

    _45 Switchyard Gate for pedestrain (1 meter) 6 0% 17-May-15 23-May-15_45 Galvanised fencing surrounding the Switchyards 14 0% 1 3-May-15 27-May-15

    _45 Production and construction of galvanized barbed wire surrounding the switchyar 14 0% 1 3-May-15 27-May-15

    allallation 1 30 1 0. 8% 0 8 -J an -1 5 A 2 2- Ma y- 15

    elel Structures 6 8 2 0. 47 % 0 8 -J an -1 5 A 2 2- Ma r- 15el Seel Structures for 132kV System 37 38.81%08-Jan-15 A 18-Feb-15

    010 145kV Busbar System & Pylons Steel Structures 14 38.1% 0 8-Jan-15 A 04-Feb-15

    060 145kV Equipment Steel Structures 18 2% 25-Jan-15 A 18-Feb-15

    nsionsion and Suspention_Al Basbar 15 0% 1 8-Feb-15 05-Mar-15

    1611Ins ta llat ion o f A luminium Bus Bar inc lude s Pos t Insulat o rs f or Bus Bar 15 0%18-Feb-15 05-Mar-15

    1612 Installation of Tension and Suspention 15 0% 1 8-Feb-15 05-Mar-15

    Feb Mar   Apr  May Jun Jul  Aug Sep Oct Nov Dec Jan Feb Mar   Apr  May Jun Jul  Aug Sep

    Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015

    27-May-15, Civil Works

    20-Sep-14 A, Mobilization

    29-Mar-15, Main Building Works

    29-Mar-15, SUBSTATION CONTROL BUILDING

    Control Building Ready for Installation

    26-Mar-15, Leakproof Cesspool and seepage pit for Substation

    24-Feb-15, 132kV Foundation Group

    22-Feb-15, Cable trenches and pipes

    24-Feb-15, Site Drainage

    24-Mar-15, Earthing System

    23-May-15, Roads

    08-Apr-15, Installation of Fire Detection System

    08-Apr-15, Installation of Air - Conditioning system

    27-May-15, Work of gravel layer and BR

    22-May-15, Installation

    22-Mar-15, Steel Structures

    18-Feb-15, Steel Structures for 132kV System

    05-Mar-15, Tension and Suspention_Al Basbar

    at Updated Work Programme- ACT_27.01.2015 4 of 5

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    16/27

    Activity Name Dur. %Complete Start Finish

    ble Tble Tray,Racks and Ladders 28 0% 2 2-Feb-15 22-Mar-15

    320 Installation of Cable Tray, Ladders and Racks 28 0% 22-Feb-15 22-Mar-15

    t hithing System 28 0% 1 3-Mar-15 10-Apr-15

    251 Earthing Work 28 0% 13-Mar-15 10-Apr-15

    2 k2 kV Equipments 44 0% 0 5-Mar-15 18-Apr-152 kV2 kV Primary Equipments 38 0% 0 5-Mar-15 14-Apr-15

    1180 145kV Disconnecting & Earthing Switchs 38 0% 0 5-Mar-15 12-Apr-15

    200 145kV Measuring Transformers 38 0% 05-Mar-15 12-Apr-15

    220 145kV Surge Arresters 38 0% 05-Mar-15 12-Apr-15

    613 145kV Post Insulators 38 0% 05-Mar-15 12-Apr-15

    160 145kV Circuit Breakers 38 0% 05-Mar-15 14-Apr-152 kV2 kV Secondary Equipments 30 0% 1 9-Mar-15 18-Apr-15

    390 Installation of Control & Protection Panels 30 0% 19-Mar-15 18-Apr-15

    SySystem 35 0% 2 9-Mar-15 03-May-15

    440 B atteries, Battery Chargers, AC & DC Panel 35 0% 29-Mar-15 03-May-15

    t dotdoor Ligthing 35 0% 1 5-Apr-15 19-May-15

    510 145kV Lighting 35 0% 15-Apr-15 19-May-15

    blesbles 40 0% 1 2-Apr-15 22-May-15

    340 Laying & Termination of Cables 40 0% 12-Apr-15 22-May-15

    ec oecom and Scada System 55 0% 1 9-Mar-15 13-May-15

    600 Telecom Equipments 50 0% 1 9-Mar-15 08-May-15

    610 SCADA System 45 0% 29-Mar-15 13-May-15

    t &t & Commissioning 20 0% 2 2-May-15 11-Jun-15

    _60 T est and Commissioning 20 0% 22-May-15 11-Jun-15

    epteptance 0 0% 11-Jun-15 11-Jun-15

    _70 Energization 0 0% 11-Jun-15*

    tortory Acceptance Tests 92 80.97%28-Oct-14 A 15-Feb-15

    5 k5kV Circuit Breakers 1 1 00 % 1 5- Jan -1 5 A 1 5- Jan -1 5 A

    -1 2 F ac to ry Acceptance Test o f 1 45 kV Circuit Breakers 1 1 00 % 15 -Jan-1 5 A 1 5-Jan-1 5 A

    5 k5kV Disconnecting Swich 1 1 00 % 0 1 -D ec -1 4 A 0 1- De c- 14 A

    - 12 F ac to ry A cc ep ta nc e Te st s o f 1 45 kV Dis co nne ct ing S wic h 1 1 00 % 0 1- De c- 14 A 0 1- Dec -1 4 A

    5 k5kV Surge Arresters 1 1 00 % 2 8- Oc t- 14 A 2 8- Oc t- 14 A

    -1 2 F ac tory Acceptanc e Tests of 1 45 kV Surge Arres ters 1 1 00 % 28 -Oc t-1 4 A 2 8-Oct-1 4 A

    5 k5kV CT & VT 1 1 00 % 2 4 -N ov -1 4 A 2 4- No v- 14

    -12 Factory Acceptance Tests of 145kV Current Transformer & Voltage Transformer 1 1 00 % 2 4 -N ov -1 4 A 2 4- No v- 14

    ntrontrol Protection Panels 18 94.44%26-Jan-15 A 15-Feb-15

    -1 2 F ac to ry Acceptance Test of Co ntro l Pro tectio n Panels 1 1 00 % 26 -Jan-1 5 A 2 6-Jan-1 5 A

    -12 Factory Acceptance Test of Metering Panels 1 0% 15-Feb-15 15-Feb-15

    herher FATs 50 64.71%29-Dec-14 A 15-Feb-15

    -12 Factory Acceptance Tests of Steel Structures 1 100% 29-Dec-14 A 29-Dec-14 A

    -12 Factory Acceptance Tests of Telecommunication 1 0% 2 9-Jan-15* 30-Jan-15

    -12 Factory Acceptance Tests of ECS System 1 0% 1 5-Feb-15 15-Feb-15

    Feb Mar   Apr  May Jun Jul  Aug Sep Oct Nov Dec Jan Feb Mar   Apr  May Jun Jul  Aug Sep

    Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015

    22-Mar-15, Cable Tray,Racks and Ladders

    10-Apr-15, Earthing System

    18-Apr-15, 132 kV Equipments

    14-Apr-15, 132 kV Primary Equipments

    18-Apr-15, 132 kV Secondary Equipments

    03-May-15, DC System

    19-May-15, Outdoor Ligthing

    22-May-15, Cables

    13-May-15, Telecom and Scada System

    11-Jun-15, Test & Commissioning

    11-Jun-15, Acceptance

    Energization

    15-Feb-15, Factory Acceptance Tests

    15-Jan-15 A, 145kV Circuit Breakers

    01-Dec-14 A, 145kV Disconnecting Swich

    28-Oct-14 A, 145kV Surge Arresters

    24-Nov-14 A, 145kV CT & VT

    15-Feb-15, Control Protection Panels

    15-Feb-15, Other FATs

    at Updated Work Programme- ACT_27.01.2015 5 of 5

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    17/27

    Risk Assessment for Khabat PP132kV Switchyard Electrical Works

    TOTAL 9 PAGES

    (Including Cover)

    PROJECT NAME : Khabat Thermal Power Plant Units 1&2 Purpose

    ☐ For Information☒ For Review

    ☐ For Approval

    ☐ For Construction

    ☐ As-Built

    DOCUMENT NO. : KP-00+++-MQ734-V0100

    TITLE : Risk Assessment for Khabat PP  132kV Switchyard

    OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government

    A 02.01.2015 First Issue DE EÖ AY YÖ

    Rev.No.

    DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED

    GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

    Owner 

    Ministr y of Electrici ty (MOE)of Kurdistan Regional Government

    Contractor 

    POSCO ENGINEERING

    & CONSTRUCTION CO., LTD.

    Main Subcontractor 

    GAMA POWER SYSTEMS

    ENGINEERING & CONTRACTING,INC.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    18/27

    Description

       T  a  r  g  e   t   P .   E .   A .   R .

    Impacts

    (Consequences)

       H  a  z  a  r   d   S  e  v  e  r   i   t  y

       L   i   k  e   l   i   h  o  o   d  o   f   O  c  c  u  r  r  e  n  c  e .

       R   i  s   k   R  a   t   i  n  g .

       H  a  z  a  r   d   S  e  v  e  r   i   t  y

       L   i   k  e   l   i   h  o  o   d  o   f   O  c  c  u  r  r  e  n  c  e .

       R  e  s   i   d  u

      a   l   R   i  s   k   E  v  a   l  u  a   t   i  o  n

       H   /   M   /   L .

    1 Before start to work 

    Inexperienced

     personnel

    involved in the

    operation

    Injury to personnel

    damage to equipment

    due to incompetency 

    4 2 8 3 1 3

    2  Before start to work 

    Inadequate

    working

    environment 

    Injury to personnel

    damage to unsafe

    working environment 

    4 2 8 3 1 3

    3 Excavation

    Contact with

    existing 

    buried services

    Injury to personnel,material damage due

    to electrocution and

    explosion due to

    contact with existing

    buried services.

    5 1 5 5 1 5  

    4 Excavation

    Open

    Excavations,

    Trenches

    4C 

    Injury to personnel

    due to falling into

    open excavations

    5 3 15 4 1 4

    5  Excavation

    Open

    Excavations,Trenches

    4C 

    Injury to personnel

    due to Collapse of the

    excavations andentombment of

     personnel.

    5 2 10 5 1 5  

    6 Pylon / Equipment

    Pylon Foundations

    Manual Handling

    Physical Force2C 

    Injury to personnel

    due to

    Handling/loading

    materials by body

    force Improper

    equipment.

    3 3 9 2 1 2  

    Civil Operations

     /Handtools /

    Electrical

    Equipments

    Mechanical /

    Physical Risk 4C 

    Multiple injuries (eye,

    arm,face irritation ),

    Burns, Disability /

    Fatality due to unsafe

    working conditions,

    Electrical shock,

    uncontrolled/not

    tested electrical

    equipments, and

    uncalibrated

    equipments

    5 3 15 4 1 4

    8   All activitiesLack of

    supervision4B

    Injury, fatality,

     property damage due

    to insufficient

    management 

    5 2 10 4 1 4

    HSE department will check the area and

    ensure that all precautions are taken prior to

    start to work.

    Obtain a valid PTW for “Excavations” before

    starting any digging activity.

    Ensure that all buried services are properly

    identified. Follow the instructions

    contained in the PTW. Execute only manual

    digging close to energized buried cable lines

    and pressurized buried pipelines.

     Any excavation deeper than 1.2 m or any

    different elevations more than 1,2 m shall be

    barricaded with scaffolding or any other strong

    materials.

    Temporary barricades shall be netlon fence,

    which provides solid visual 

    barricade. The height of the barricades s hall

    Dedicated team leader will be in place during

    all work activities. A toolbox talk will be done prior to the

    operation. Method Statement and Risk

    assessment will be communicated to all

     personnel involved to the operation.

    Workplace Risk Assessment - WorksheetSITE / UNIT: Iraq- Khabat Project ASSESSMENT TEAM LEADER:Ali Ugur Benli ASSESSMENT Ref No:

    DATE OF ASSESSMENT: 09/14

    TIMEOF ASSESSMENT:14.00 

     ACTIVITY DESCRIPTION: Pylon Foundation, Steel Erection,

    Electrical Works. ASSESSMENT TEAM MEMBERS:Ali Ugur Benli, Eyup Ozbay 

    HAZARD INITIAL RISK  

    Job StagesNo

    CONTROLS

    Control & Recovery Measures Required 

    RESIDUAL RISK 

    For excavations deeper than 170 cm, sheet 

     piles will be used. When necessary an efficient

    dewatering system must be installed. In cases

    of deep excavations with reduced width and

    difficult access, a valid PTW for “Confined

    Spaces” must be obtained before starting any

    activity inside and all prescribed precautions

    strictly followed.

     All working instructions & checklist related to

    civil operations are all in place provided by

    Siemens.

    Safe Manual Handling practices should be

    applied during installation.

    Manual Handling Training (incl.basic

    ergonomy) shall be given where required.

     All safety devices should be checked beforefor their proper fitting and function

    No person to be inside a dangerous area while

    functional checks or run up procedures are

    being carried out.

     All actions to be carried out bu competent

     persons. All electrical hand tools will be

    checked by site EHS officer and inspection

    label will be put on tools as green; safe to use,

    red; not safe dont use. Workplace to be

    restricted, not allow to get anyone inside

    Other all safety measures to be taken into

    account mentioned in working instructions.

    Handtools run with 24V if possibel especially

    in Confined Spaces.

    Only trained and experienced personnel to be

    involved in the activity.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    19/27

    9  All activities Visibility 3B

    injury due to poor

    vision, not enough

    illumination

    4 2 8 3 1 3

    10   All activitiesVehicle

    Movement 4C 

    Injury, fatality,

     property damage due

    to Vehicle collisions.

    5 3 15 4 1 4

    11  All activitiesVehicle

    Movement 4B

    Injury, fatality,

     property damage due

    to Crushing of

     personnel by 

    vehicles in movement.

    5 2 10 5 1 5  

    12  Backfilling Machinery 3C  

    injury or material

    damage due to poor

    maintenance of

    vehicle / equipment 

    4 3 12 3 1 3

    13Simultaneous

    Operations

    Working in

    conjunction with

    the truck or

    equipments

    3C 

    Injury to personnel or

    material damage due

    to hit by truck or

    equipment 

    4 3 12 3 1 3

    14

    Transportation of

    the backfilling

    material from

    storage area to

    backfilling area

    Loading,

    transportation

    and unloading

    the backfilling

    material 

    3C 

    Injury or material

    damage due to hit by

    truck / equipment 

    4 3 12 4 1 4

    15  Completion of Work 

    Incorrect wastemanagement

     procedures in

     place

    2C 

    Pollution,

    Environmental

    Damage

    3 3 9 3 1 3

    16  Housekeeping 

    Mechanic risks

    Chemical risks

    Physical Effects

    Non-quality work

    Chemicals

    Wastes

    Not accessible

    fire fighting

    systems

    4C 

    Multiple injuries (eye,

    arm,face,etc.),

    Electrical shock, Fire,

    Environmental impact

    due to Materials (civil,

    electrical, mechanic )

    that are not stored in a

     proper place and safe,

    Cable bobbins left

    random along the

    ways without scotchs

    around, Equipment

    usage in an unsafe

    way, Electrical,

    lighting cables left

    random on the floors,

    Probable night works,

    Chemical, oil leakage

    around the workplace,

    Wastes stored

    random within site

    witout segragation

    5 3 15 4 1 4

    Materials to be stored in proper, well defined

    area

    Permanent walkways and stairs installed 

    Road access shall not be obstructed by parked

    vehicles, trucks, cranes and machinery.

    Wastes segragated and stored in a proper

     place

    Leakages to be removed within site

     All trailing leads and cables shall be safely

    suspended or fully protected.

    Obstruct materials should be removed from

    workplace.

    Vehicles and equipment will be visually

    checked by drivers / operators prior to start to

    operation.Banksman (watchman) will be also

    on site, communicating with vehicle operator.

    Vehicle / equipment movements around the

    wall will be controlled by a watchman.

    Trucks and equipments will be operated by

    experienced and authorized personnel.

    Smoking, eating and talking by mobile phone

    strictly forbidden. Trucks will obey the speed

    limit at all times. (20 km/h) The vehicle

    movements around the wall will be controlled

    by a watchman

     All waste will be collected and segrageted

    according to their type and stored properly.

    Hazardous wastes will be disposed align with

    standarts. The wastes could be recycled if

    applicable

    Operation (including preparations) will be done

    in day time only.

    Follow the site roads only and respect the

    speed limits. Flashing lights always on and

    use of a trained banks man, when and where

    necessary. It is forbidden to use the mobile

     phone, smoking and eating while driving. Sit

    belts must be used at all times by the driver

    and any passenger.

    Wearing high visibility vests is mandatory all

    over the site area. Follow the

     pedestrian walkways. All vehicles must be

     provided with audible reversing 

    warning devices or accompanied by a qualified

    banks man. Keep the safety distance from all

    vehicles in operation.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    20/27

    17 

    Preperations for

    work

    Inexperienced

     personnel

    involved in the

    operation /

    Inadequate

    working

    environment 

    Injury to personnel

    damage to equipment

    due to incompetency /

    unsafe working

    environment 

    5 2 10 4 1 4

    18  Smoking Fire and Health

    Hazard 

    P E 

     A

    Burn Injuries, Fire andExplosion, Multiple

    Fatalities

    5 3 15 4 2 8  

    19

    Civil Work Stage

     Assembly Operation

    (Ground level)

    Mechanical /

    Physical Risk 

    (Hand tools

    Power tools )

    P Electrical shock,

    single fatality or

     permanent disability 

    4 3 12 2 2 4

    20 

    Civil Work Stage

    Steel base erection

     Access/ Exit to

    Plylon Socket P 

    Injury to personnel

    due to falling into

    socket, major injury 

    3 4 12 1 3 3

    21

    Civil Work Stage

     Assembly Operation

    (Foundation Level)

    Mechanical /

    Physical Risk 

    (Hand tools

    Power tools )

     A

    Injury to personnel

    due to

    Handling/loading

    materials by body

    force

    Improper equipment;

    (deformed electrical

    cables,no guarding on

    machine, etc.)

    electrical shock,single

    fatality 

    4 4 16 2 2 4

    22 

    Civil Work Stage

     Assembly operation

    ; Butt splice / beam

    assembly 

    Mechanical /

    Physical Risk 

    Environmental

    Risks

    (Crane usage)

     A

    Multiple Fatalities, ,

    Leakege from hoisting

    equipments, Property

    damages.

    5 3 15 3 1 3

    23

    Civil Work Stage

     Assembly operation

    ; Butt splice / beam

    assembly 

    Mechanical /

    Physical Risk 

    (Hand tools )

    Major injury to

     personnel due to

    Handling/loading

    materials by body

    force

    Improper equipment;

    3 4 12 1 3 3

    24 Cable layingManual Handling

    Physical Force

    Minor injury to

     personnel due to

    Handling/loading

    materials by body

    force Improper

    equipment.

    3 3 9 1 2 2  

    25 Lifting

    Lifting equipment

    failure, fall from

    height and run

    over 

    P

    E

     A

    Fatality, Major Injuries,

    Leakege from hoisting

    equipments, Property

    damages.

    4 4 16 3 3 9

    26

    Working at height

    Working at the

    height above 1.8mtr 

    Fall hazards and

    objects falling

    from heights

    P

    E

     A

    R

    Fatality

    Fracture, major

    injuries4 3 12 3 2 6

    Color code and inspection at all lifting gears

    Insurance documents shall be provided 

    Outriggers shall be utilized during all

    operations

    Proper crane setup, especially near

    excavations

    Pads shall ve utilized for outriggers at all times

    Hoisting crane examination before work start.

    Check the documents for hoisting mechanism

    and devices.

     

    PPE supply.

    First Aid Kit availability on site.

    Wear proper PPE.

    Only qualified and trained (inc. risk

    assesments & procedures) personnel access

    to construction site.

    Proper equipment with specifications and

    maintenance records.

    PTW system shall be followed,

    Underground facilities shall be identified and

    drawing shall be provided before commencing

    activity.

     Smoking is prohibited at site area.

    Fire extinguisher.

    It is allowed at designated area only.

    Ensure that all personnel shall undergo for the

    induction training to know they dos and don’ts

    at site.

    In addition to mandatory PPEs;mechanical

    resistant gloves and high visible jacket to be

    worn

    Safety barriers to be put in place to restrict

    working area especially if workplace jsut near

    road (vehicle movement area)

    Screening of working area

    First aid kits

    Use right tool fit for the purpose

     

    Obtain a valid PTW for “Access/Exit to

    sockets'' 

    Ensure that ladders are in line with Siemens

    Standards; aluminum, fixed at the bottom and

    the upper part, and exceed the final level to be

    reached of at least 1m.

    In addition to mandatory PPEs;mechanical

    resistant gloves and high visible jacket to be

    worn

    Safety barriers to be put in place to restrict

    working area especially if workplace jsut near

    road (vehicle movement area)

    Screening of working area

    First aid kits

    Use right tool fit for the purpose

    Ensure all power tools are in good condition

    with insulation

    Ensure the use of 220 V power tools

    Trained and authorized person only shall

    operate the power tools

    Ensure for appropriate PPE 

    Check validity before use of tools by

    employees

     Attests of manufacturer, regular check of

    condition

    Color code and inspection at all electrical

    equipments

    Inspection, maintainance and repair of

     All safety devices should be checked before

    for their proper fitting and function

    No person to be inside a dangerous area while

    functional checks or run up procedures are

    being carried out.

     All actions to be carried out bu competent

     persons. Workplace to be restricted, not allow

    to get anyone inside

    Other all safety measures to be taken into

    account mentioned in working instructions.

    In addition to mandatory PPEs;mechanical

    resistant gloves and high visible jacket to be

     All working instructions & checklist related to

    civil operations are all in place provided by

    Siemens.

    Safe Manual Handling practices should be

    applied during installation.

    Manual Handling Training (incl.basic

    ergonomy) shall be given where required.

    Color code and inspection at all lifting gears

    Insurance documents shall be provided

     All outriggers shall be utilized during all

    operations

    Proper crane setup, especially near

    excavations

    Pads shall ve utilized for outriggers at all times

    Hoisting crane examination before work start.

    Check the documents for hoisting mechanism

    and devices and certificates shall be kept for

    Ladders shall not be used as platformFall protection device full body harness shall

    be used and it should be 100% tie off with

    double lanyard

    Don’t carry materials while climbing on ladder.

    Ensuring the personnel get the education for

    working at height.

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    21/27

    27 Working with manlift

    Fall hazards and

    objects falling

    from heights

    P

     A

    R

    Fatality, Major Injuries,

    Leakege from hoisting

    equipments

    3 4 12 2 3 6 

    28

    Use of ladders

    Climbing up and

    down throughladders and

    improper or insecure

    positioning

    Slip, trip, injuries

    due to brokenand metal

    ladders and fall

    from ladder 

    P Dea th , f al l f rom he igh t

    and sprain injuries5 3 15 3 3 9

    29

    Mechanical

     Assembly

     /Handtools /

    ElectricalEquipments

    Mechanical /

    Physical Risk 

    (Handtools /Power Tools)

     A

    Multiple injuries (eye,

    arm,face irritation ),

    Burns, Disability /

    Single Fatality due to

    unsafe working

    conditions, Electrical

    shock,

    uncontrolled/not

    tested electrical

    equipments, and

    uncalibrated

    equipments

    4 3 12 3 2 6  

    30 Working with Dilo

    compression set

    Compressed

    SF6 gas

    cylinders

     A

    Permanent disability,

    multiple fatalities,

    major damage, major

    national impact

    5 4 20 4 2 8  

    31  All activitiesLack of

    supervisionP 

    Permanent disability,

    single fatality,

     property damage due

    to insufficient

    management 

    4 3 12 3 2 6  

    32   All activities Visibility P 

    Major injury due to

     poor vision, not

    enough illumination

    3 3 9 2 2 4

    33  All activitiesVehicle

    Movement 

     A

    Fatality/Permanent

    disability due to traffic

    accident 

    Press. Jamming. Load

    or Equipment

    Changeover.

    Fuel and Lubricants

    Spillage/ 

    5 3 15 3 2 6  

    Color code and inspection for manlift

    Manlift shall be equipped with railings for each

    open part and each end: a rigid top rail, 1

    meter high, an average rail, 0.45 meter high

    and a baseboard (0.15 m. high).

    Insurance documents shall be provided

    Proper manlift setup, especially near

    excavations

     Ensure appropriate ladders in use

    Three point contact is must

    Check the ladders before use

    Position it properly and tie where necessary

    Check the ladder before each use

    While using more than 3mtr ladder, a person

    has to hold it

    Before use, ladder has to be visually checked.

    Ladders have to be placed that horizontal and

    vertical ratio is 1:4. Approximately angel of 75°.

    Ladder shell not is used as working platform.

    Regular checking of safety devices and proper

    positioning of the ladder.

    Periodical inspection for ladder by competent

    Use right tool fit for the purpose

    Ensure all power tools are in good condition

    with insulation

    Ensure the use of 220 V power tools

    Trained and authorized person only shall

    operate the power tools

    Ensure for appropriate PPE 

    Check validity before use of tools by

    employees Attests of manufacturer, regular check of

    condition

    Periodical inspection with color coding system

    Certified electricians shall repair power tools

    Color code system will be applied to all

    electrical equipments

    Gas cylinders will be kept at proper storage

    area

    Storage area will be protected from climate

    effects (rain, direct sun light, overtemp,

    extreme cold etc.)

    Storage area shall be locked and key shall be

    hand in responsible person

    Storage area will be marked as indicating risks

    and stored material 

     

    Dedicated team leader will be in place during

    all work activities.

     A toolbox talk will be done prior to the

    operation. Method Statement and Risk

    assessment will be communicated to all

     personnel involved to the operation.

    STARRT code system shall be applied.

    Supervision of work team shall be provided by

    a competent supervisors during all activities.

    Operation (including preparations) will be done

    in day time only.

    In poor visibility (heavy rain, dust storm, sand

    storm etc.) activities shall be suspended.

    Driver should follow Safety Rules while Driving

    Transport Vehicles.

    Seat belt shall be worn at all times by all

     passengers and driver.

    Daily checlist shall be done before start

    driving.

    The Drivers should:

    Seat belt shall be worn all times

    Have valid certificate and driver license

    Do daily checlist before driving 

    Follow Speed Restriction Signs in accordance

    with Road Requirements; Always be on the

    alert to potential hazards; Look at mirrors and

    use signals before maneuvering; Keep safety

    distance behind other transport-vehicles; Use

    Dipped Headlight and Slow Speed in condition

    of poor visibility; Do not use cell phones or

    other means of communication in Driving; Do

  • 8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf

    22/27

    34Simultaneous

    Operations

    Working in

    conjunction with

    the truck or

    equipments

     A

    Permanent disability

    to personnel, single

    fatality or material

    damage due to hit by

    truck or equipment 

    4 2 8 3 2 6  

    35  Completion of Work 

    Incorrect waste

    management

     procedures in

     place

    Pollution,

    Environmental

    Damage

    Soil contamination

    3 3 9 1 3 3

    36 

    Territory

    housekeeping by

    work completion

    Waste. Sharp

    materials, fall,

    trip, slip

    P

    E

    Slight injuries. Trip,

    fall.

    Wrong wastes

    disposal.

    Fuel and Lubricants

    spillage.

    2 4 8 1 3 3

    37 Working under 380

    kV High Voltage

    Unsafe working

    without taking

    necessary

    safetymeasures.

     A

    Getting closer than

    limit approach value

    Working with

    4 2 8 3 2 6  

    38 Working under

    380Kv High Voltage

    Unsafe working

    without taking

    necessary

    safety

    measures.

     A

    Working in bad

    weather conditions3 4 12 1 3 3

    39Working under

    380Kv High Voltage

    Unsafe working

    without taking

    necessary

    safety

    measures.

     A

    Working with no Ekat

    certificate personal 3 3 9 2 2 4

    40 Working under

    380Kv High Voltage

    Unsafe workingwithout taking

    necessary

    safety

    measures.

     A

    Throwing materials 3 4 12 2 3 6  

    41Preperations for

    work 

    Inexperienced

     personnel

    involved in the

    operation /

    Inadequate

    working

    environment 

    Injury to personnel

    damage to equipment

    due to incompetency /

    unsafe working

    environment 

    2 5 10 1 4 4

    42  Smoking Fire and Health

    Hazard 

     A

    Burn Injuries, Fire and

    Explosion, Multiple

    Fatalities

    4 4 16 3 3 3

    43

    Civil Work Stage

     Assembly Operation

    (Ground level)

    Mechanical /

    Physical Risk 

    (Hand tools

    Power tools )

    P Electrical shock,

    single fatality or

     permanent disability 

    4 4 16 2 3 6 

    44

    Civil Work Stage

    Steel base erection

     Access/ Exit to

    Plylon Socket P 

    Injury to personnel

    due to falling into

    socket, major injury 

    3 4 12 1 4 4

    Vehicle / equipment movements around the

    wall will be controlled by a watchman.

    Banksman will manage vehicle activities

    Vehicle road and pedestrian route shall be

    identified.

     All waste will be collected and segrageted

    according to their type and stored properly.

    Hazardous wastes will be disposed align with

    standarts. The wastes could be recycled if

    applicable.

     Any contamination shall be removed

    immediately and shall be sent to the waste

     All trailing leads and cables shall be safely

    suspended or fully protected.

    Obstruct materials should be removed from

    workplace.

    Control by Foremen, Supervisors, Safety

    Engineers.

    Regular, routine housekeeping and working

    place compulsory cleaning at the end of

    working shift.

    Min. 10 meter approach limit must be kept.

    Never conductive objects such as shovel,

    digger etc.

     Also it must be forbidden to use construction

    wire inside the switchyard zone.

    Hand tools must be suplied from outside

    grounded