Upload
utku-can-kilic
View
236
Download
0
Embed Size (px)
Citation preview
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
1/27
Method of Statement for Khabat PP132kV Switchyard Circuit Breaker
Installation Works
TOTAL 27 PAGES
(Including Cover)
PROJECT NAME : Khabat Thermal Power Plant Units 1&2Purpose
☐ For Information
☐ For Review
☐ For Approval
☒ For Construction
☐ As-Built
DOCUMENT NO. : KP-00+++-MQ758-V0010
TITLE : Method of Statement for Khabat PP 132kV Switchyard Circuit Breaker Installation
Works
OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government
0 12.02.2015 For Construction DE EÖ AY YÖ
A 09.02.2015 First Issue DE EÖ AY YÖ
Rev.No.
DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.
Owner
Ministr y of Electrici ty (MOE)
of Kurdistan Regional Government
Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
GAMA POWER SYSTEMSENGINEERING & CONTRACTING,INC.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
2/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 1/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
Khabat Thermal Power Plant Units 1&2 Project132kV Air Insulated Switchgear
METHOD OF STATEMENT FOR 132kV
SWITCHYARD CIRCUIT BREAKERINSTALLATION
DOCUMENT NO: KP-00+++-MQ758-V0010
SUBCONTRACTOR: SIEMENS
GAMA REVIEW
DisciplineSuperintendent
HSE Manager QA/QC Manager Site Manager
Name
Date
Sign
Remarks:Any such review or consent by GAMA, shall not relieve the Subcontractor, in any case or for any reason whatsoever,from any obligation, liability or responsibility arising out of or in connection with the Contract, including without beinglimited thereto, to the responsibility for errors, omissions, discrepancies and non-compliances. Within this context, thisdocument shall not prevail over or amend the Contract, or relieve the Subcontractor from any of its duties, obligations,responsibilities or liabilities under the Contract.Anything presented herein by the Subcontractor shall in no eventi) excuse the Subcontractor’s non-performance under the Contract, or ii) entitle him to a variation under the Contract or an adjustment to the Contract Price.
SUBCONTRACTOR
Rev.No.
Date Description*Prepared
byHSE
Manager QA/QC
Manager Site
Manager Project
Manager
A 09.02.2015 132kV SwitchyardSteel Erection
Works
DenizEREN
- - - EyyüpÖZBAY
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
3/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 2/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
0 12.02.2015 132kV SwitchyardSteel Erection
Works
DenizEREN
- - - EyyüpÖZBAY
DOCUMENT HISTORY:
Rev.
No. Date
Remarks
(Reason for Revision)
A 09.02.2015 First Issue
0 12.02.2015 For Construction
* Descript ion:
Document issue purpose
- First Issue
- For Information
- For Review- For Approval (or Issued for Construct ion)
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
4/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 3/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
CONTENT
1.0 PURPOSE .................................................................................................................................................................................... 4
2.0 SCOPE OF WORK ...................................................................................................................................................................... 4
3.0 RESPONSIBILITIES .................................................................................................................................................................... 4
4.0 DEFINITIONS / ABBREVIATIONS ............................................................................................................................................. 4
5.0 PERSONNEL ............................................................................................................................................................................... 4
6.0 MATERIALS ................................................................................................................................................................................. 5
7.0 EQUIPMENT ................................................................................................................................................................................ 5
8.0 SUBCONTRACTORS’ SUB-TIER CONTRACTORS ................................................................................................................ 59.0 EXECUTION ................................................................................................................................................................................. 5
10.0 TIME LINE OF ACTIVITIES ........................................................................................................................................................ 7
11.0 PROGRESS MEASUREMENT ................................................................................................................................................... 7
12.0 QUALITY REQUIREMENTS ....................................................................................................................................................... 7
13.0 HEALTH, SAFETY and ENVIRONMENTAL REQUIREMENTS ............................................................................................... 8
14.0 RISK ASSESSMENTS ................................................................................................................................................................ 8
15.0 REFERENCES ............................................................................................................................................................................. 9
16.0 TECHNICAL APPENDICES ........................................................................................................................................................ 9
17.0 ATTACHMENTS .......................................................................................................................................................................... 9
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
5/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 4/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
1.0 PURPOSE
This procedure outlines the methods to be followed for installation of the Circuit Breakers for 132kV
Switchyard at Khabat Thermal Power Plant Units 1&2 Project.
2.0 SCOPE OF WORK
Installation of steel structure for below 132kV feeders include busbars
· 132kV line feeders ( 6 pcs)
· 132kV cable feeders ( 2 pcs)· Transformers feeders (2 pcs)· Coupling feeders (1 pcs)
3.0 RESPONSIBILITIES
This MS is under responsibility of Siemens. When any changes occur, Siemens will revise this document and issue according to communication plan on which Siemens and Gama agreed.
4.0 DEFINITONS / ABBREVATIONS
PP: Thermal Power PlantAIS: Air Insulated Switchgear MS: Method StatementITP: Inspection & Test PlanQA/QC: Quality Assurance / Quality ControlHSE: Health, Safety, EnvironmentJSA: Job Safety AnalysisPPE: Personal Protective EquipmentHV: High Voltage
MV: Medium VoltageLV: Low VoltageAC: Alternative CurrentDC: Direct CurrentUPS: Uninterruptable Power Supply
5.0 PERSONNEL
- Site Manager
- Site Engineer(s)
- QA/QC Engineer
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
6/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 5/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
- HSE Supervisor
- Site Supervisor(s)
- Survey Team
- Site Foreman(s)
- Workers (iron, formwork, concrete, steel, electrical etc)
- Operator(s) (Construction Machine, crane etc. )
6.0 MATERIALS
- Prefabricated Steel Parts
- Bolts, washers, nuts
7.0 EQUIPMENT
- Truck (if necessary)
- Crane
- Manlift
- Survey equipments
- Handtools
- Powertools
8.0 SUBCONTRACTORS’ SUB-TIER CONTRACTORS
9.0 EXECUTION
The work method to install the above mentioned Circuit Breaker shall be in the followingsequence.
A. Pre-Installation Checks
· Verification of Equipment layout from relevant Construction Drawings.
Mr.Mesut AYDIN Civil Subcontractor Silopi Aypa Ltd.Şti
Mr.Ufuk MANAV Erection & Commissioning Subcontractor YNE Enerji Elektrik Mühendislikinşaat San.Tic.ltd.Şti.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
7/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 6/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
· Check drawings are of current revised status.
· Site released for Equipment installation, all supporting steel installation completed
· Conform readiness of the area.· Review Vendor drawings of the equipement and familiarize the installation method
recommended by the Vendor.
· Exposed erection areas shall be cordoned by means of hazard identifying tape.
· Confirm that all Tools & Tackles required for installation are available. As a minimum thefollowing shall be made available.
Open End WrenchesStar End WrenchesTorque WrenchSlings
D-ShacklesCrowbarsDrill MachineGrinding MachineAll necessary special tools
· Check adequate place for unloading the Circuit Breaker.
· Personnel involved in the activity are made aware of the risks and the steps to be taken tomitigate any hazard or unsafe situation.
· Foundation frame shall be made and properly aligned for the installation of the Circuit Breaker.
B. Material withdrawn from ware-house
· Material inspection will be carried out to ascertain that no damage has occurred in the package of the equipments. Incase of any damages common inspection and report will be issued.
· Store material requisition shall be made.
· The material shall be transported in their Original packing to location.
· The Hi-Ab shall be positioned in such a way that there is no obstruction to movement of vehiclesor hindrance to works of other companies.
C. Description of sequence
The following will be follwed after the preparation works:
· Check the availability of SF6 gas inside column and the breaking unit
· Install the corana rings to breaking unit if available
· Install the current conducting rings to both end of the breaking unit
· Install the coupling capacitor to the breaking unit if available
· Connect the column and breaking unit
· Use suitable wowen sling to lift up the Circuit Breaker
· Lift up the Circuit Breaker with Hi-Ab according to the supplier documents and raised over the
steel support
· Align the Circuit Breaker over the support base plate and fit the Erection bolts.
· Check the horizontal and vertical alignment of the Circuit Breaker and adjusted as necessary.
· Install the control cubicle, be sure that the indicators on control cubicle should be in “OPEN”and “DISCHARGED” positions.
· Fill up the CB with SF6 gas.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
8/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 7/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
· Tigth the bolts and nuts according to the torque values given in the table below:
Bolt Type, d Nominal Radius, mm. Quality Type A325
Recommended TorqueValue Nm.
M8 8 16M10 10 32M12 12 59M14 14 94M16 16 146
M18 18 200M20 20 284M22 22 388M24 24 492M27 27 720M30 30 979M33 33 1331M36 36 1709M39 39 2211
Bolt tightening is done by torque wrench, according to recommended values. Before assembystarts,10 percent of tightened bolts are controlled with GAMA’s surveillance.
10.0 TIME LINE OF ACTIVITIES
According to attached 27 January 2015 dated updated project time schedule.
11.0 PROGRESS MEASUREMENT
Monthly progress reports will permanently be submitted to Gama for progress measurement.
12.0 QUALITY REQUIREMENTS
Inspection and Test Plan (ITP) for Circuit Breaker Installation Works (Doc. No: KP-00+++-CQ712-B7357)shall be followed during the execution of works.
Test, inspections and reporting shall be carried out by the Subcontractor in accordance to the ITP and required documents mentioned on the ITP shall be submitted to GAMA for his review.
All measurement equipments and torque wrenches shall be calibrated. Calibration certificates shall besubmitted to GAMA before site applications according KP-00+++-MQ732-G0005_Rev.0_CalibrationProcedure. Test certificates and mill certification verifying that the materials comply with the relevant
approved standards and material certificates shall be issued for all structural steel, bolting materials,consumable materials. Approved materials shall be used in project according to approved vendor list and material submittal form.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
9/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 8/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
13.0 HEALTH, SAFETY and ENVIRONMENTAL REQUIREMENTS
Toolbox talk will be done with the team who is involved in the foundation works. Job Safety Analysis (JSA)will be prepared and distributed to Site Supervisor(s). Using related JSA, Method Statement and Risk Assessment will be discussed during the toolbox talk.
While excavation works, barricade will be installed to the around the pit and warning signs will be put towarn other people to keep away.
Mandatory Personal Protective Equipment will be used by the person involved in the operation. There is norequirement for additional PPE.
Risk Assessment will be taken into consideration and required precautions will be taken.
Materials
1. Mandatory Personal Protective Equipment,
- Safety Helmet
- Safety Shoes
- Safety Vest
- Safety Gloves
- Safety Glasses’/Goggles
2. Personal Protective Equipment Required Due to Specific Risks,
- Safety Harness,
- Dust and/or Chemical Masks
3. Safety Barricading Fence/Netlon Fence
4. Related Safety/Warning Signs.
14.0 RISK ASSESSMENTS
Please see attached Khabat Project Risk assessment as Attachment-2.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
10/27
METHOD OF STATEMENT FOR 132kV SWITCHYARDCIRCUIT BREAKER INSTALLATION
Page: 9/9 Doc. No: KP-00+++-MQ758-V0010 Date:12 02.2015
Dok. No: KP-00+++-MQ758-V0010, Rev. No: 0
15.0 REFERENCES
All erection works will be controlled and checked after installation as per the document indicated below:
Document Name Document Number
ITP for CIRCUIT BREAKER INSTALLATION WORKS
KP-00+++-CQ712-B7357
16.0 TECHNICAL APPENDICES
Please see attached Khabat Project Vendor List as Attachment-3.
17.0 ATTACHMENTS
Attachment-1 27.01.2015 Dated Time ScheduleAttachment-2 Risk AssessmentAttachment-3 Vendor List
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
11/27
Design, Equipment Manufacturing, Test andDelivery Time Schedule
TOTAL 6 PAGES
(Including Cover)
PROJECT NAME : Khabat Thermal Power Plant Units 1&2 Purpose
☐ For Information
☒ For Review
☐ For Approval
☐ For Construction
☐ As-Built
DOCUMENT NO. : KP-00++++-MX000-V0001
TITLE : Updated time schedule / 27.01.2015
OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government
S 27.01.2015 27.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ
R 20.01.2015 20.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ
P 13.01.2015 13.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ
0 06.01.2015 06.01.2015 dated TS update SIEMENS/OO SIEMENS/EÖ
N 30.12.2014 30.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
M 23.12.2014 23.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
L 16.12.2014 16.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
K 09.12.2014 09.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
J 02.12.2014 02.12.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
I 25.11.2014 25.11.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
H 18.11.2014 18.11.2014 dated TS update SIEMENS/OO SIEMENS/EÖ
Rev.No.
DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.
Owner
Ministry of Electrici ty (MOE)of Kurdistan Regional Government
Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
GAMA POWER SYSTEMSENGINEERING & CONTRACTING,INC.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
12/27
Activity Name Dur. %Complete Start Finish
alal 03 66.31%25-Apr-14 A 11-Jun-15
ababat Updated Work Programme- ACT_27.01.2015 03 66.31%25-Apr-14 A 11-Jun-15
ectect Start (General) 0 3 1 00 % 2 5- Apr -1 4 A 11-Jun-15
10 Co ntract Signature & Co mm encement Date (O ffshore) 1 1 00 % 25 -Apr-1 4 A 2 5-Apr-1 4 A
82 Providing of Soil Investigation Report By GAMA 0 100% 15-May-14
11 Co ntract Signature & Co mm ensment Date (Onsho re) 1 1 00 % 13 -Jun-1 4 A 1 3-Jun-1 4 A
85 Advance Payment (Onshore and Offshore) 0 100% 20-Jun-14 A
81 Submission of Inspection and Test Plan 0 100% 01-Jul-14 A
83 Site Handover 0 100% 30-Aug-14 A
84 Site Requirements for Mobilization ((Power/Water Supply, Sanitary, Storage Area 0 100% 30-Aug-14 A
88 M eth od of St ate me nt fo r S ub st at io n Er ec tio n( KHB -S IE -G AM -A IS -0 05 8) 0 1 00 % 0 3- Sep -1 4 A
87 Method of Statement for Mobilization 0 100% 17-Sep-14 A
90 Method of Statement for Civil Work at Switchyard Area 0 100% 12-Nov-14
86 PAC (Ready for Energization - Take Over) 0 0% 11-Jun-15
gngn & Engineering 72 94.85%01-May -14 A 09-Feb-15
sicsic Design 1 97 1 00 % 0 1 -M ay -1 4 A 1 2- No v- 14
-11 Preparation and Submission of General Layout, Site Layout & Section 2 1 1 00 % 0 1 -M ay -1 4 A 2 2- Ma y- 14
- 11 P rep ar at io n an d S ubm is sio n o f S ec ond ar y B as e Des ign 2 1 1 00 % 0 1- May -1 4 A 2 2- May -1 4
-1 1 Preparatio n and Submiss io n o f Single Line Diagram 2 1 1 00 % 01 -M ay-1 4 A 2 2-M ay-14
-11 Preparation and Submission of Control, Protection & Metering System Base Desig 21 100% 01-May-14 A 22-May-14
-11 Preparat ion and Submission of Substation Building Equipment Layout Plan 21 100%01-May-14 A 22-May-14
-11 Preparat ion and Submission of General Cable Trenches and Foundation Layout 21 100%01-May-14 A 22-May-14
-11 Approval of Single Line Diagram 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A
-11 Approval of General Layout, Site Layout & Section 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A
-11 Approval of Secondary Base Design 14 100% 23-May-14 A 03-Jul-14 A
- 11 A pp ro va l o f Co nt ro l, Pr ot ec ti on & Me te rin g S ys te m B as e D es ig n 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A
- 11 A ppr ova l o f S ub st at io n B uild in g E qu ipm en t La yo ut Pla n 1 4 1 00 % 2 3- May -1 4 A 0 3- Jul- 14 A
- 11 A pp ro va l o f G en er al C ab le T re nc he s a nd F ou nd at io n L ay ou t 1 4 1 00 % 2 3 -M ay -1 4 A 0 3- Ju l- 14 A
- 11 S tat ic & Dy nam ic Lo ad Calc ulat io ns fo r 1 32 kV Equ ip me nts 5 1 00 % 0 1- Sep -1 4 A 0 5- Sep -1 4 A
095 Decision for ECS -1 Option(KHB-GAM-SIE-AIS-0051 dtd 05.09.2014) 0 100% 05-Sep-14 A
093 Approval of AC/DC Load List for Battery & Battery Charger 0 100% 14-Sep-14 A
094 Dec is ion f or 48VDC Ba tt ery & Ba tt ery Cha rger(K HB-GAM-SIE-AIS-00073 d td 30. 0 100% 30-Sep-14 A
096 Decision for Painting Code of LV Panels & Control Protection Panels(KHB-SIE-GA - -0 100% 12-Nov-14
hn ihnical Documents for Equipment/Systems 114 87.69%01-Aug-14 A 09-Feb-15
-11 Preparation and Submission of 120 Surge Arresters Technical Documents(KHB-SI- - -5 0 1 00 % 0 1 -A ug -1 4 A 1 4- Au g- 14 A
-11 Preparation and Submission of 132kV Disconnecting Switch Technical Documents 50 100% 09-Aug-14 A 15-Sep-14 A
-11 Preparation and Submission of 132kV Earthing Switch Technical Documents 5 0 1 00 % 0 9- Sep -1 4 A 15-Sep-14 A-11 Preparation and Submission of 132kV Capacitive Voltage Transformers Technical 5 0 1 00 % 0 9- Aug -1 4 A 18-Sep-14 A
-11 Preparation and Submission of 132kV Current Transformers Technical Documents 50 100% 09-Aug-14 A 18-Sep-14 A
-11 Approval of 132kV Capacitive Voltage Transformers Technical (KHB-GAM-SIE-AIS- 1 4 1 00 % 1 9 -S ep -1 4 A 0 3- Oc t- 14 A
-11 Approval of 132kV Current Transformers Technical Documents(KHB-GAM-SIE-AI - 1 4 1 00 % 1 9 -S ep -1 4 A 0 3- Oc t- 14 A
-11 Approval of 132kV Disconnecting Switch Technical Documents(KHB-GAM-SIE-AIS- 1 4 1 00 % 1 6 -S ep -1 4 A 0 3- Oc t- 14 A
-11 Approval of 132kV Earthing Switch Technical Documents(KHB-GAM-SIE-AIS-000 14 100%16-Sep-14 A 03-Oct-14 A
-11 Preparation and Submission of Insulators Technical Documents(KHB-SIE-GAM-AI - 5 0 1 00 % 1 2- Sep -1 4 A 07-Oct-14 A
-11 Preparation and Submission of LV Cable Technical Documents(KHB-SIE-GAM-AIS- 1 0 1 00 % 0 1 -O ct -1 4 A 1 3- Oc t- 14 A
-11 Preparat ion and Submission of 132kV Curcuit Breaker Technical Documents(KHB- - - -5 0 1 00 % 1 2 -S ep -1 4 A 1 4- Oc t- 14 A
-11 Approval of LV Cable Technical Documents(KHB-GAM-SIE-00093 dtd 30.10.201 14 100%14-Oct-14 A 30-Oct-14 A
-11 Approval of Insulators Technical Documents(KHB-GAM-SIE-00092 dtd 30.10.20 14 100%14-Oct-14 A 30-Oct-14 A
-11 Approval of 132kV Curcuit Breaker Technical Documents(KHB-GAM-SIE-00091 d 14 100%14-Oct-14 A 30-Oct-14 A
-11 Preparation and Submission of Earthing Conductor Technical Particulars(KP-SIE-G - -1 6 1 00 % 2 3 -S ep -1 4 A 1 4- No v- 14
-11 Preparat ion and Submission of Aluminium Bus Bar Technical Documents(KHB-SIE- - -5 0 1 00 % 1 2- Sep -1 4 A 19-Nov-14
-11 Approval of 120kV Surge Arresters Technical Documents(KHB-GAM-SIE-AIS-001 1 4 1 00 % 1 4- Aug -1 4 A 21-Nov-14
-11 Preparat ion and Submission of Tension and Suspent ion Technical Documents(KH- - - -5 0 1 00 % 1 2 -S ep -1 4 A 2 4- No v- 14
-11 Approval of Aluminium Bus Bar Technical Documents(KHB-GAM-SIE-AIS-00127 d 14 100% 19-Nov-14 A 03-Dec-14 A
-11 Approval of Earthing Conductor Technical Particulars(KHB-GAM-SIE-AIS-00128 dt 14 100% 14-Nov-14 A 03-Dec-14 A
-11 Approval of Tension and Suspention Technical Documents(KHB-GAM-SIE-AIS-00 14 100%24-Nov-14 A 05-Dec-14 A
-11 Preparation and Submission of Battery Chargers Documents(KHB-SIE-GAM-AIS- 3 5 1 00 % 1 2 -N ov -1 4 A 2 3- De c- 14 A
-11 Preparation and Submission of Station Batteries Documents(KHB-SIE-GAM-AIS-0 3 5 1 00 % 1 2 -N ov -1 4 A 2 3- De c- 14 A
-11 Approval of Station Batteries Documents 1 4 0 % 23 -Dec-1 4 A 0 9-Feb-1 5
-11 Approval of Battery Chargers Documents 14 0% 23-Dec-14 A 09-Feb-15
tai lailed Design 153 90.85%22-May -14 A 09-Feb-15uipmuipment/Systems 97 85.55%22-May -14 A 09-Feb-15
1-1 Preparat ion of Typical Feeders Schematic Drawings & Cable Schedules & LVAC-LV - - - -4 9 1 00 % 2 2 -M ay -1 4 A 0 5- Au g- 14 A
1-1 Submission of Typical Feeders Schematic Drawings & Cable Schedules & & LVAC- 1 1 00 % 0 5 -A ug -1 4 A 0 5- Au g- 14 A
1-1 Preparation of General Earthing and Outdoor Equipment Earthing and Cable Tray - - - -1 8 1 00 % 0 2- Aug -1 4 A 28-Aug-14 A
1-1 Preparation and Submission of Substation Grounding Mesh Layout (KHB-SIE-GA - -1 8 1 00 % 1 0- Aug -1 4 A 28-Aug-14 A
-1 Submission of Earthing Detailed Design 1 100% 28-Aug-14 A 28-Aug-14 A
1- 1 P re pa ra ti on of Fa ra da y C ag e P ro je ct (K HB -S IE -G AM -A IS -0 06 3) 7 1 00 % 2 9 -A ug -1 4 A 0 7- Se p- 14 A
-1 Submission of Faraday Cage Project 1 100% 07-Sep-14 A 07-Sep-14 A
1-1 Approval of Earthing Detailed Design(KHB-GAM-SIE-AIS-0070 dtd 24.09.2014)(S - - -1 4 1 00 % 2 8 -A ug -1 4 A 3 0- Se p- 14 A
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
11-Jun-15, Total
11-Jun-15, K haba t Updat ed Work P -
11-Jun-15, Project Start (General)
Providing of Soil Investigation Report By GAMA
Advance Payment (Onshore and Offshore)
Submission of Inspection and Test Plan
Site Handover
Site Requirements for Mobilization ((Power/Water Supply, Sanitary, Storage Area) by GAMA)
Method of Statement for Substation Erection(KHB-SIE-GAM-AIS-0058)
Method of Statement for Mobilization
Method of Statement for Civil Work at Switchyard Area
PAC (Ready for Energization - Take
09-Feb-15, Design & Engineering
12-Nov-14 A, Basic Design
Decision for ECS -1 Option(KHB-GAM-SIE-AIS-0051 dtd 05.09.2014)
Approval of AC/DC Load List for Battery & Battery Charger
Decision for 48VDC Battery & Battery Charger(KHB-GAM-SIE-AIS-00073 dtd 30.09.201 4))
Decision for Painting Code of LV Panels & Control Protection Panels(KHB-SIE-GAM-AIS-00113 dtd 05.11.2014 ))
09-Feb-15, Technical Documents for Equipment/Systems
09-Feb-15, Detailed Design
09-Feb-15, Equipment/Systems
at Updated Work Programme- ACT_27.01.2015 1 of 5
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
132kV Khabat Updated Work Programme
Data date: 27.01.2015
Date Revision Chec... Approved
K habat P RO JE CT O O
s
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
13/27
Activity Name Dur. %Complete Start Finish
-1 Subm is sio n of Lightning Pro tec tio n Detailed Design 1 1 00 % 01 -Oc t-1 4 A 0 1-Oct-1 4 A
1-1 Switchyard and Control Building Lightning Protection Layout (KHB-SIE-GAM-AIS-0 2 0 1 00 % 0 1 -S ep -1 4 A 0 1- Oc t- 14 A
1-1 Approval of Lightning Protect ion Detailed Design(KHB-GAM-SIE-AIS-0082 dtd 17. 14 100%01-Oct-14 A 17-Oct-14 A
1-1 Approval of Typical Feeders Schematic Drawings & Cable Schedules & & LVAC-LV - -1 4 1 00 % 0 5 -A ug -1 4 A 2 2- Oc t- 14 A
1-1 Preparat ion and Submission of HV Hardware & Connectors Layout Plan & Sect ion - - - -1 6 1 00 % 2 3 -S ep -1 4 A 2 9- Oc t- 14 A
-1 Preparation of ECS System Detailed Design 5 0 1 00 % 1 3- Sep -1 4 A 09-Nov-14
-1 Submission of ECS System Detailed Design 1 1 00 % 0 9- Oc t- 14 A 0 9- No v- 14
1- 1 P rep ar at io n of Te le co mm un ic at io n Sys te m Det aile d Des ig n 5 0 1 00 % 2 4- Sep -1 4 A 1 3- No v- 14
1-1 Preparat ion and Submission of HV Hardware & Connectors Detailed Outline Draw - - - -1 6 1 00 % 2 3 -S ep -1 4 A 1 4- No v- 14
1-1 Submission of Indoor & Outdoor Lighting & Low Power Detailed Design(KP-SIE-G - -1 1 00 % 1 4 -N ov -1 4 A 1 4- No v- 14
1-1 Submission of Telecommunicat ion System Detailed Design(KP-SIE-GMH-T-00076 1 100%14-Nov-14 A 14-Nov-14
1-1 Preparat ion of Indoor & Outdoor & Emergency Lighting & Low Power Detailed De 30 100%08-Sep-14 A 14-Nov-14
-1 Approval of HV Hardware & Connectors Detailed Design(KHB-GAM-SIE-AIS-0011 1 4 1 00 % 1 4 -N ov -1 4 A 2 0- No v- 14
-1 Approval of Faraday Cage Project(KHB-GAM-SIE-AIS-00117 dtd 21.11.2014) 1 4 1 00 % 0 7- Sep -1 4 A 21-Nov-14
-1 Appro val of Telec om municatio n System Detailed Design 1 4 0 % 14 -No v-1 4 A 0 9-Feb-1 5
-1 Approval of ECS System Detailed Design 14 0% 09-Nov-14 A 09-Feb-15
1- 1 A pp ro va l o f In do or & Ou td oo r Li gh ti ng & Lo w Po we r D et ai le d D es ig n 1 4 0 % 1 4 -N ov -1 4 A 0 9- Fe b- 15il Wil Works 1 53 9 7. 39 % 0 3 -J ul -1 4 A 3 0- Ja n- 15eel -eel Structures-Fabrication and Templates 1 34 1 00 % 2 5 -A ug -1 4 A 1 8- Ja n- 15 A
1-1 132kV Gantry Tower Type P1 Fabrication Drawings (KHB-SIE-GAM-AIS-0053) 2 0 1 00 % 2 5- Aug -1 4 A 02-Sep-14 A
1-1 132kV Gantry Tower Beam Type K1 Fabrication Drawings(KHB-SIE-GAM-AIS-00 2 0 1 00 % 2 5- Aug -1 4 A 02-Sep-14 A
1-1 1 32 kV Gantry To wer Type P6 F abrication Draw ings 1 2 1 00 % 06 -Sep-1 4 A 2 0-Sep-1 4 A
1- 1 1 32 kV Ga ntr y To wer Be am Typ e K6 Fa br ic at io n Dra win gs 1 2 1 00 % 0 6- Sep -1 4 A 2 0- Sep -1 4 A
1-1 132kV Voltage Transformer Support Structure Fabrication Drawings(KP-SIE-GM - -20 100% 06-Sep-14 A 27-Oct-14 A
1-1 132kV Current Transformer Support Structure Fabrication Drawings(KP-SIE-GM - -20 100% 06-Sep-14 A 27-Oct-14 A
1-1 132kV Disconnecting Switch Serial Type Support Structure Fabrication Drawing(K - - - -2 0 1 00 % 0 6 -S ep -1 4 A 2 7- Oc t- 14 A
1-1 132kV Lightning Tower Fabrication Drawings_P2(KP-SIE-GMH-T-00057) 2 0 1 00 % 0 6- Sep -1 4 A 27-Oct-14 A
1-1 132kV Surge Arrester Support Structure Fabrication Drawings(KP-SIE-GMH-T-00 2 0 1 00 % 0 6- Sep -1 4 A 29-Oct-14 A
1-1 132kV Curcuit Breaker Support Structure Fabricat ion Drawings(KP-SIE-GMH-T-0 20 100%06-Sep-14 A 01-Nov-14
1-1 Subm is sio n o f 1 32 kV Steel Structure Detailed Design 1 1 00 % 17 -No v-1 4 A 1 7-No v-1 4
1-1 132kV Ear th ing Sw it ch + SA Suppo rt Struc ture Fabrica tion Draw ing 20 100%06-Sep-14 A 17-Nov -14
1-1 132kV Disconnecting Switch with Earthing Blade Support Structure Fabrication Dr 20 100% 06-Sep-14 A 17-Nov-14
1-1 132kV Surge Arrester Support Structure Fabrication Drawing - Transformer Side 20 100%06-Sep-14 A 17-Nov-14
1-1 132kV Cable Sealing End Support Structure Fabrication Drawing (KP-SIE-GMH-T- 5 1 00 % 0 6- Jan -1 5 A 1 8- Jan -1 5 Awitc hwitchyard Civil Design 1 38 9 7. 1% 1 5 -S ep -1 4 A 30-Jan-15ound ,oundation for Equipment, Gantry and Busducts 1 38 9 7. 1% 1 5 -S ep -1 4 A 3 0- Ja n- 15
1- 132kV Gantry Tower Type P1 & P6 Foundation Drawings(KHB-SIE-GAM-AIS-009 8 100%15-Sep-14 A 01-Oct-14 A
1- 132kV Surge Arrester Support Structure Foundat ion Drawing(KP-SIE-GMH-T-000 10 100%29-Oct-14 A 10-Nov-14
1- 132kV Voltage Transformer Support Structure Foundat ion Drawing(KP-SIE-GMH-- 10 100%27-Oct-14 A 10-Nov-14
1- 132kV Current Transformer Support Structure Foundation Drawing(KP-SIE-GMH-- 10 100% 27-Oct-14 A 10-Nov-14
1- 132kV Circuit Breaker Support Structure Foundation Drawing(KP-SIE-GMH-T-00 1 0 1 00 % 0 3 -N ov -1 4 A 1 0- No v- 14
1- 132kV Lightning Tower Foundation Drawings_P2(KP-SIE-GMH-T-00073) 1 0 1 00 % 2 7 -O ct -1 4 A 1 0- No v- 14
1- S ub mis si on of 13 2k V E qu ip me nt Fo un da ti on De ta il s a nd Se ct io ns 1 1 00 % 1 7 -N ov -1 4 A 1 7- No v- 14
1- 132kV Disconnecting Switch Serial Type Support Structure Foundation Drawing 10 100%27-Oct-14 A 17-Nov-14
1- 132kV Disconnecting Switch with Earthing Blade Support Structure Foundat ion Dr 5 100%11-Nov-14 A 17-Nov-14
1- 132kV Surge Arrester Support Structure Foundation Drawing Transformer Side 5 100%11-Nov-14 A 17-Nov-14
1- 132kV Earthing Switch + SA Support Structure Foundation Drawing Transformer 5 100% 11-Nov-14 A 17-Nov-14
1- 132kV Cable Sealing End Support Structure Foundation Drawing 5 2 0% 2 6 -J an -1 5 A 3 0- Jan -1 5vilvil Work Design of Ancillary Service Foundations 8 0 1 00 % 1 5- Sep -1 4 A 17-Nov-14
1- P repa ra tion and Submiss ion of Cable T rench P lan & Se ct ions & Re in fo rcement Det - - - -1 0 1 00 % 1 5 -S ep -1 4 A 1 5- Oc t- 14 A
1- A pp ro va l o f Ca bl e T re nc h Pl an & Se ct io ns & Re in fo rc em en t D et ai ls 1 4 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A
1- Preparation and Submission of Marshalling Box Foundation Application Plan, Form 1 0 1 00 % 1 5 -S ep -1 4 A 1 5- Oc t- 14 A
1- Approval of Marshalling Box Foundation Application Plan, Formwork & Reinforcem 14 100% 15-Oct-14 A 15-Oct-14 A
1- P re pa ra ti on a nd S ub mi ss io n of S wit ch ya rd L ig ht in g & Fo un da ti on s 1 0 1 00 % 1 5 -S ep -1 4 A 1 7- No v- 14
1- Approval of Switchyard Lighting Pole & Foundations 1 4 1 00 % 1 7 -N ov -1 4 A 1 7- No v- 14vilvil Work Design of Site Works 4 9 1 00 % 2 4- Sep -1 4 A 17-Nov-14
1- Preparat ion of Substat ion Fence & Gate Details(KP-SIE-GMH-T-00051 dtd 15.10 10 100%24-Sep-14 A 15-Oct-14 A
1- Preparation of Switchyard Service Road Plan Details and Sections(KP-SIE-GMH-T- 1 0 1 00 % 2 4 -S ep -1 4 A 1 5- Oc t- 14 A
1- Submission of Substation Fence & Gate Details 1 100% 15-Oct-14 A 15-Oct-14 A
1- Approval of Substation Fence & Gate Details 14 100% 15-Oct-14 A 15-Oct-14 A
1- S ub mis si on of Sw it ch ya rd Se rv ic e R oa d P la n De ta il s a nd Se ct io ns 1 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A
1- Approval of Switchyard Service Road Plan Details and Sections 1 4 1 00 % 1 5 -O ct -1 4 A 1 5- Oc t- 14 A
1- Preparation and Submission of Drainage System 1 0 1 00 % 2 4- Sep -1 4 A 17-Nov-14
1- Approval of Switchyard Drainage System 14 100% 17-Nov-14 A 17-Nov-14uildinilding Architectural Design 1 5 1 00 % 0 3- Jul- 14 A 0 4- Sep -1 4 A
1-1 Subs tatio n Building Architectural Plans and Details 1 4 1 00 % 03 -Jul-1 4 A 1 7-Jul-1 4 A
1-1 Submission of Architectural Detailed Design for Substation Building(KHB-SIE-GAM- -1 100% 17-Jul-14 A 17-Jul-14 A
1-1 Approval of Architectural Detailed Design for Substation Building(KHB-SIE-GAM-AI- 14 100% 17-Jul-14 A 04-Sep-14 Auildinilding Structural Design 2 4 1 00 % 0 4- Sep -1 4 A 22-Sep-14 A
1-1 Substation Building Structural Plans and Details 1 4 1 00 % 0 4- Sep -1 4 A 19-Sep-14 A
1- 1 S ub mis si on of St ru ct ur al De ta il ed De si gn fo r Su bs ta ti on Bu il di ng 1 1 00 % 1 9 -S ep -1 4 A 1 9- Se p- 14 A
1- 1 A pp ro va l o f S tr uc tu ra l D et ail ed De si gn fo r S ub st at io n B ui ld in g 1 4 1 00 % 2 2 -S ep -1 4 A 2 2- Se p- 14 Auildinilding Sanitary Design 4 3 1 00 % 1 4 -O ct -1 4 A 1 7- No v- 14
1-1 Substation Building Sanitary and Sewage System for Ground & First Floor Layout 10 100% 14-Oct-14 A 17-Nov-14
1-1 Submit of Substation Building Sanitary and Sewage System for Ground & First Flo 1 100% 17-Nov-14 A 17-Nov-14
leasease for Construction Drawings 4 7 1 00 % 0 3- Jul- 14 A 1 5- Oc t- 14 A
-11 RFC Drawing for General Layout, Site Layout & Section 7 1 00 % 0 3- Jul- 14 A 0 3- Jul- 14 A
- 11 RF C Dr aw in g fo r S ubs ta tio n B uild in g E qu ip men t La yo ut Pla n 7 1 00 % 0 3- Jul- 14 A 0 3- Jul- 14 A
- 11 R FC Dr aw in g f or Ge ne ra l C ab le Tr en ch es an d F ou nd at io n L ay ou t 7 1 00 % 0 3 -J ul -1 4 A 0 3- Ju l- 14 A
-11 RFC Drawing f or Struc tura l Det ai le d Des ign f or Subst at ion Bui ld ing 7 100%25-Sep-14 A 25-Sep-14 A
-11 RFC Draw ing f or Arch it ec tura l Det ai le d Des ign f or Subs ta tion Bu ilding 7 100%26-Sep-14 A 26-Sep-14 A-11 RFC Drawing for Substation Fence & Gate Details(KP-SIE-GMH-T-00051 dtd 15. 7 100%15-Oct-14 A 15-Oct-14 A
-11 RFC Drawing for Switchyard Service Road Plan Details and Sections(KP-SIE-GMH- - 7 1 00 % 1 5- Oc t- 14 A 1 5- Oc t- 14 A
-11 RFC Drawing for Cable Trench Plan & Sections & Reinforcement Details(KP-SIE-G - -7 1 00 % 1 5- Oc t- 14 A 1 5- Oc t- 14 A
chachasing & Manufacturing 0 6 7 1. 84 % 1 3 -J un -1 4 A 2 5- Ma r- 15
r chachase Order 1 02 1 00 % 1 3 -J un -1 4 A 0 2- De c- 14 A
-11 Purchasing of Steel Structures 10 100% 13-Jun-14 A 13-Jun-14 A
-11 Purchasing of 120kV Surge Arresters 10 100% 04-Jul-14 A 17-Jul-14 A
-11 Purchasing of Disconnecting Switch 10 100% 04-Jul-14 A 17-Jul-14 A
-11 Purchasing of Earthing Switch 1 0 1 00 % 0 4- Jul- 14 A 1 7- Jul- 14 A
-11 Purchasing of 132kV Capacitive Voltage Transformers 1 0 1 00 % 0 4- Jul- 14 A 1 8- Jul- 14 A
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
30-Jan-15, Civil Works
18-Jan-15 A, Steel Structures-Fabrication and Templates
30-Jan-15, Switchyard Civil Design
30-Jan-15, Foundation for Equipment, Gantry and Busducts
17-Nov-14 A, Civil Work Design of Ancillary Service Foundations
17-Nov-14 A, Civil Work Design of Site Works
04-Sep-14 A, Building Architectural Design
22-Sep-14 A, Building Structural Design
17-Nov-14 A, Building Sanitary Design
15-Oct-14 A, Release for Construction Drawings
25-Mar-15, Purchasing & Manufacturing
02-Dec-14 A, Purchase Order
at Updated Work Programme- ACT_27.01.2015 2 of 5
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
14/27
Activity Name Dur. %Complete Start Finish
-11 Purchasing of 132kV Current Transformers 10 100% 04-Jul-14 A 18-Jul-14 A
-11 Purchasing of 132kV Curcuit Breaker 10 100% 18-Jul-14 A 28-Jul-14 A
-11 Purchasing of Telecommunication System 10 100% 15-Aug-14 A 10-Sep-14 A
-1 1 Purchasing o f ECS Sys tem(KHB-GAM -SIE-AIS-0 05 1)) 1 0 1 00 % 06 -Sep-1 4 A 1 5-Sep-1 4 A
-11 P urchasing of Insulators 10 100% 15-Sep-14 A 22-Sep-14 A
-11 Purchasing of LV Cables 1 0 1 00 % 0 2- Sep -1 4 A 22-Sep-14 A
-11 Purchasing of Control, Protection & Metering Panels 1 0 1 00 % 1 4 -O ct -1 4 A 1 4- Oc t- 14 A
-11 Purchasing of LVAC Distribution Panels 10 100% 14-Oct-14 A 21-Oct-14 A
-11 Purchasing of LVDC Distribution Panels 10 100% 14-Oct-14 A 21-Oct-14 A
-11 Purchasing of Earthing Materials 10 100% 13-Oct-14 A 23-Oct-14 A
-11 Purchasing of Station Batteries (KHB-SIE-GAM-AIS-0035),(KHB-SIE-GAM-AIS-00 1 0 1 00 % 3 0 -S ep -1 4 A 3 1- Oc t- 14 A
-11 Purchasing of Battery Chargers(KHB-SIE-GAM-AIS-0035),(KHB-SIE-GAM-AIS-00 1 0 1 00 % 3 0 -S ep -1 4 A 3 1- Oc t- 14 A
-11 Purchasing of HV Hardware & Connectors 1 0 1 00 % 0 9 -O ct -1 4 A 0 3- No v- 14
-11 Purchasing of Aluminium Bus Bar 1 0 1 00 % 0 9 -O ct -1 4 A 0 4- No v- 14
-11 Purchasing of Tension and Suspention 10 100% 04-Nov-14 A 07-Nov-14
-11 Purchasing of Lightning Protection Materials 10 100% 1 0-Nov-14 A 11-Nov-14
-11 P urchasing of Cable Trays 10 100% 07-Nov-14 A 25-Nov-14
-1 1 Purchasing of Indo or & Lighting Luminares_ Outdo or 1 0 1 00 % 14 -No v-1 4 A 0 2-Dec -1 4 A
nuf nufacturing 0 6 7 1. 84 % 1 8 -J ul -1 4 A 2 5- Ma r- 15
-11 Manufacturing of 120kV Surge Arresters 1 72 1 00 % 1 8- Jul- 14 A 2 7- Oc t- 14 A
-11 Manufacturing of P1 & P6 Templates / Anchor Bolts 5 2 1 00 % 0 6 -O ct -1 4 A 0 8- No v- 14
-1 1 M anufacturing o f Lightning Pro tec tio n M aterials 3 5 1 00 % 11 -No v-1 4 A 1 8-No v-1 4
-1 1 M anufacturing o f Other Templates / Anchor Bolts 2 0 1 00 % 01 -No v-1 4 A 2 6-No v-1 4
- 11 M anu fa ct urin g o f 13 2kV C ap ac it iv e Vo lt ag e Tr ans fo rm er s 1 72 1 00 % 1 8- Jul- 14 A 3 0- No v- 14
-11 Manufacturing of 132kV Current Transformers 172 100% 1 8-Jul-14 A 30-Nov-14
-11 Manufacturing of Disconnecting Switch 172 100% 18-Jul-14 A 30-Nov-14
-11 Manufacturing of Earthing Switches 1 72 1 00 % 1 8- Jul- 14 A 3 0- No v- 14
-11 Manufacturing of P1 & P6 Steel Structures 5 2 1 00 % 2 0 -O ct -1 4 A 0 3- De c- 14 A
-11 Manufacturing of Earthing Materials (Lugs, Rods, Cadweld Materials, Equi-potentia 80 100% 23-Oct-14 A 15-Dec-14 A
-11 Manufacturing of LVAC Distribution Panels 100 100% 21-Oct-14 A 21-Dec-14 A
-11 Manufacturing of LVDC Distribution Panels 100 100% 21-Oct-14 A 21-Dec-14 A
-11 M anufacturing of Insulators 140 100% 24-Sep-14 A 22-Dec-14 A
-11 Manufacturing of Aluminium Bus Bar 70 100% 04-Nov-14 A 28-Dec-14 A
-11 Manufacturing of Other Switchyard Steel Structures & Templates 6 4 1 00 % 2 0 -O ct -1 4 A 2 9- De c- 14 A
-11 Manufacturing of Cable Trays 6 0 1 00 % 2 5 -N ov -1 4 A 3 1- De c- 14 A
-11 Manufacturing of HV Hardware & Connectors 70 100% 03-Nov-14 A 15-Jan-15 A
-11 M anufacturing of LV Cables 130 100% 22-Sep-14 A 15-Jan-15 A
-11 Manufacturing of Tension and Suspentions 70 100% 07-Nov-14 A 15-Jan-15 A
-11 Manufacturing of Control, Protection Panels 100 100% 1 4-Oct-14 A 26-Jan-15 A
-11 Manufacturing of Telecommunication System 130 100% 1 0-Sep-14 A 27-Jan-15 A
-11 Manufacturing of Station Batteries 9 0 1 00 % 3 1 -O ct -1 4 A 2 7- Ja n- 15 A
-11 Manufacturing of Battery Chargers 9 0 1 00 % 3 1 -O ct -1 4 A 2 7- Ja n- 15 A
-11 Manufacturing of 132kV Curcuit Breakers 199 96.98% 18-Jul-14 A 01-Feb-15
-11 M anufacturing of ECS 160 87.5% 15-Sep-14 A 15-Feb-15
-11 Manufacturing of Metering Panels 100 80% 14-Oct-14 A 15-Feb-15
- 11 M anu fa ct ur ing o f Indo or & O ut do or Lig ht ing L um in are s 1 00 5 6% 0 2 -De c- 14 A 2 5- Mar -1 5
utinutine Tests 56 62.64%26-Dec-14 A 16-Feb-15
-12 Submission of 132kV Capacitive Voltage Transformers Routine Test Reports 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A
-12 Submission of 120kV Surge Arresters Routine Test Reports 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A
- 12 S ub mis si on o f 1 32 kV C ur re nt Tr an sf or me rs Ro ut in e T es t R ep or ts 1 1 00 % 2 6 -D ec -1 4 A 2 6- De c- 14 A
- 12 S ubm is sio n o f Dis co nn ec tin g S wit ch Ro ut in e Te st Rep ort s 1 1 00 % 2 6- De c- 14 A 2 6- Dec -1 4 A
-1 2 Subm is sio n o f Earthing Switch Ro utine Test Repo rts 1 1 00 % 26 -Dec-1 4 A 2 6-Dec -1 4 A
-12 Submission of Insulators Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
- 12 S ubm is sio n o f L VAC Dis tr ibu tio n P an els Ro ut in e T es t Rep ort s 1 0 % 2 7- Jan -1 5 2 7- Jan -1 5
-12 Submission of LVDC Distribution Panels Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
-12 Submission of Aluminium Bus Bar Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
- 12 S ubm is sio n o f H V Ha rd wa re & C on ne ct or s Ro utin e T es t Rep or ts 1 0 % 2 7- Jan -1 5 2 7- Jan -1 5
- 12 S ub mis si on o f L ig ht ni ng P ro te ct io n M at er ia ls R ou ti ne T es t R ep or ts 1 0 % 2 7 -J an -1 5 2 7- Ja n- 15
-12 Submission of Station Batteries Routine Test Reports 1 0% 2 7-Jan-15 27-Jan-15
-12 Submission of Battery Chargers Routine Test Reports 1 0% 2 7-Jan-15 27-Jan-15
-1 2 Subm is sio n o f Earthing M aterials Ro utine Test Repo rts 1 0 % 27 -Jan-1 5 2 7-Jan-1 5
-12 Submission of LV Cables Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
-12 Submission of Tension and Suspention Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
-12 Submission of Cable Trays Routine Test Reports 1 0% 27-Jan-15 27-Jan-15
-1 2 Subm is sio n o f 1 32 kV Curcuit Breaker Ro utine Tes t Repo rts 1 0 % 02 -F eb-15 0 2-Feb-1 5
-12 Submiss ion o f Cont ro l, Pro te ct ion & Me te ring Pane ls Routine Te st Repo rts 1 0%16-Feb-15 16-Feb-15
patcpatch 186 41.33%08-Nov -14 A 16-May -15
13 M aterial Delivery Completed 0 0% 16-May-15
nspnsportation 186 41.33%08-Nov -14 A 16-May -15
-13 Transportation of P1&P6 Switchyard Templates / Anchor Bolts from Turkey to B 2 1 00 % 0 8 -N ov -1 4 A 0 9- No v- 14
-13 Transportat ion of P1&P6 Switchyard Templates / Anchor Bolts from Border to Sit 3 100%09-Nov-14 A 12-Nov-14
-13 Transportat ion of Other Switchyard Templates / Anchor Bolts from Turkey to Bo 2 100%27-Nov-14 A 28-Nov-14
-13 Transportat ion of Other Switchyard Templates / Anchor Bolts from Border to Site 3 100%28-Nov-14 A 04-Dec-14 A
- 13 T ra ns po rt at io n o f P 1& P6 St ee l S tr uc tu re fr om Tu rk ey to Bo rd er 1 0 1 00 % 0 3 -D ec -1 4 A 1 2- De c- 14 A
- 13 T ra ns po rt at io n o f P 1& P6 St ee l S tr uc tu re f ro m B or de r t o S it e 1 0 1 00 % 1 2 -D ec -1 4 A 1 3- De c- 14 A
-13 Transportation of Disconnecting Switch from Factory to Border 1 0 1 00 % 1 5 -D ec -1 4 A 2 0- De c- 14 A
-13 Transportation of Earthing Switch from Factory to Border 1 0 1 00 % 1 5 -D ec -1 4 A 2 0- De c- 14 A
- 13 T ra ns po rt at io n o f D is co nn ec tin g S wit ch f ro m B or de r t o S it e 1 0 1 00 % 2 0 -D ec -1 4 A 2 4- De c- 14 A
- 13 T ran sp or tat io n o f Ea rt hin g S wit ch fr om B or der t o S it e 1 0 1 00 % 2 0- De c- 14 A 2 4- Dec -1 4 A
-13 Transportat ion of 132kV Capacit ive Voltage Transformers Factory to Site 20 100%15-Dec-14 A 30-Dec-14 A
- 13 T ra ns po rt at io n o f 1 32 kV Cu rr en t T ra ns fo rm er s F ac to ry to Sit e 2 0 1 00 % 1 5 -D ec -1 4 A 3 0- De c- 14 A-13 Transportation of Other Steel Structure & Templates / Anchor Bolts from Turkey 6 100% 06-Jan-15 A 11-Jan-15 A
-13 Transportation of Other Steel Structure & Templates / Anchor Bolts from Border 3 1 00 % 1 2- Jan -1 5 A 1 5- Jan -1 5 A
-13 Transportation of Cable trays from Turkey to Border 1 0 1 00 % 0 8 -J an -1 5 A 2 0- Ja n- 15 A
- 13 T ra ns po rt at io n of 1 20 kV S ur ge Ar re st er s fr om F ac to ry to B or de r 2 0 1 00 % 0 4 -D ec -1 4 A 2 0- Ja n- 15 A
-1 3 Transportatio n o f Insulators fro m Facto ry to Bo rder 1 4 1 00 % 29 -Dec-1 4 A 2 0-Jan-1 5 A
-13 Transportation of Cable trays from Border to Site 5 100% 2 2-Jan-15 A 22-Jan-15 A
- 13 T ra ns po rt at io n o f 1 20 kV S ur ge A rr es te rs f ro m B or de r t o S it e 5 1 00 % 2 2 -J an -1 5 A 2 2- Ja n- 15 A
-13 Transportation of Insulators from Border to Site 5 100% 2 2-Jan-15 A 22-Jan-15 A
-13 Transportation of Aluminium Bus Bar from Turkey to Border 1 0 7 0% 2 3 -J an -1 5 A 3 0- Jan -1 5
-13 Transportation of Aluminium Bus Bar from Border to Site 5 0% 30-Jan-15 04-Feb-15
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
25-Mar-15, Manufacturing
16-Feb-15, Routine Tests
16-May-15, Dispatch
Material Delivery Completed
16-May-15, Transportation
at Updated Work Programme- ACT_27.01.2015 3 of 5
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
15/27
Activity Name Dur. %Complete Start Finish
-13 Transpo rt at ion o f L ight ning P ro te ct ion Mat er ia ls f rom Turkey t o Bo rder 10 0%27- Jan-15 06-Feb-15
-1 3 Transportatio n o f HV Co nnectors fro m F actory to Turkey 1 0 0 % 28 -Jan-1 5* 0 6-Feb-1 5
- 13 T ra ns po rt at io n o f T en si on an d S us pe nt io n f ro m F ac to ry t o B or de r 1 0 0 % 2 8 -J an -1 5* 0 6- Fe b- 15
- 13 T ran sp or tat io n of 13 2k V C urc uit Br ea ke r f ro m Fa ct or y t o Tu rk ey 5 0 % 0 2- Feb -1 5 0 6- Fe b- 15
- 13 T ran sp or tat io n o f Ea rt hin g M at eria ls f ro m Tu rke y t o B ord er 4 0 % 0 4- Feb -1 5* 0 7- Fe b- 15
-13 Transportation of HV Connectors from Turkey to Border 4 0% 0 7-Feb-15 10-Feb-15
-13 Transportation of Tension and Suspention from Border to Site 4 0% 0 7-Feb-15 10-Feb-15
-13 Transportation of LV Cables from Turkey to Border 15 0% 2 8-Jan-15* 11-Feb-15
- 13 T ra ns po rt at io n o f H V H ar dw ar e & C on ne ct or s f ro m B or de r t o S it e 1 0 % 1 1 -F eb -1 5 1 1- Fe b- 15
-1 3 Transportatio n o f Earthing M aterials from Bo rder to Site 5 0 % 08 -F eb-15 1 2-Feb-1 5
- 13 T ra ns po rt at io n o f Te le co mm un ic at io n Sy st em f ro m Tu rk ey t o B or de r 1 0 0 % 0 6 -F eb -1 5* 1 6- Fe b- 15
-13 Transportation of LV Cables from Border to Site 5 0% 12-Feb-15 16-Feb-15
-13 Transportation of 132kV Curcuit Breaker from Turkey to Border 10 0% 0 7-Feb-15 16-Feb-15
-13 Transportation of Lightning Protection Materials from Border to Site 10 0% 0 8-Feb-15 17-Feb-15
-1 3 Transportatio n o f LVAC Panel fro m Turkey to Bo rder 1 5 0 % 03 -F eb-15 * 1 8-Feb-1 5
-1 3 Transportatio n o f LVDC Panels from Turkey to Border 1 5 0 % 03 -F eb-15 * 1 8-Feb-1 5
- 13 T ra ns po rt at io n o f T el ec om mu ni ca ti on S ys te m f ro m B or de r t o S it e 5 0 % 1 6 -F eb -1 5 2 1- Fe b- 15
- 13 T ran sp or tat io n o f 1 32 kV C urc uit B rea ke r f ro m B or der t o S it e 5 0 % 1 7- Feb -1 5 2 1- Fe b- 15
- 13 T ran sp or tat io n o f St atio n B at ter ie s f ro m F ac to ry to Bo rd er 1 5 0 % 1 0- Feb -1 5* 2 4- Fe b- 15
-13 Transportation of Battery Chargers from Factory to Border 1 5 0 % 10 -F eb-15 * 2 4-Feb-1 5
-13 Transportation of ECS System from Turkey to Border 10 0% 1 6-Feb-15 25-Feb-15
-13 Transportat ion of Control, Protect ion & Metering Panels from Turkey to Border 10 0%16-Feb-15* 26-Feb-15
-1 3 Transportatio n o f Battery Chargers fro m Border to Site 5 0 % 25 -F eb-15 0 1-M ar-1 5
-1 3 Transportatio n o f Statio n Batteries from Bo rder to Site 5 0 % 25 -F eb-15 0 1-M ar-1 5
-13 Transportation of LVAC Panel from Border to Site 15 0% 1 8-Feb-15 05-Mar-15
-13 Transportation of LVDC Panels from Border to Site 15 0% 1 8-Feb-15 05-Mar-15
-13 Transportation of ECS System from Border to Site 10 0% 2 6-Feb-15 07-Mar-15
-13 Transportation of Control, Protection & Metering Panels from Border to Site 10 0% 2 6-Feb-15 08-Mar-15
- 13 T ran sp or tat io n o f Ligh tin g Lu min ar es fr om Tu rke y to Bo rd er 1 0 0 % 2 6- Mar -1 5 0 4- Apr -1 5
-1 3 Transportatio n o f Lighting Luminares fro m Border to Site 1 0 0 % 05 -Apr-1 5 1 4-Apr-1 5
-13 T ransportation of Remaining Parts 30 0% 17-Apr-15 16-May-15
WWorks 68 55.14%30-Aug-14 A 27-May -15
bilizbilization 2 0 1 00 % 3 0 -A ug -1 4 A 2 0- Se p- 14 A
_00 Mobilization 20 100% 30-Aug-14 A 20-Sep-14 A
nn Building Works 167 63.06%22-Sep-14 A 29-Mar-15BSTBSTATIONCONTROL BUILDING 167 63.06%22-Sep-14 A 29-Mar-15
_4 Excavation of Control Bldg. 10 100% 22-Sep-14 A 30-Sep-14 A
_4 Foundation Construction of Control Bldg. 10 100% 15-Oct-14 A 22-Nov-14
_4 R/C Walls Construction of Control Bldg. 5 100% 25-Nov-14 A 17-Dec-14 A
_4 Column and Roof Slab of Control Bldg. 15 70% 18-Dec-14 A 31-Jan-15
1_4 Completion of ground level concrete works 10 0% 1 0-Feb-15 20-Feb-15
_4 Completion of the walls and roof (incl. plastering) 10 0% 1 0-Feb-15 20-Feb-15
_4 Completion of the plumbing works 7 0% 20-Feb-15 27-Feb-15
1_4 Completion of the electrical works installation (Indoor lighting / small power distri 10 0% 2 0-Feb-15 02-Mar-15
_4 Completion of the surface finishing 10 0% 27-Feb-15 09-Mar-15
_4 Completion of the remaining works 10 0% 09-Mar-15 19-Mar-15
_4 Control Building Ready for Installation 0 0% 19-Mar-15
1_4 Completion of the windows and doors 3 0% 1 9-Mar-15 22-Mar-15
_4 Leakproof Cesspool and seepage pit for Substation Building 12 0% 1 7-Mar-15 29-Mar-15a kp rakproof Cesspool and seepage pit for Substation Building 7 0% 1 9-Mar-15 26-Mar-15
_4 Completion of the sanitary works for Control Building 7 0% 1 9-Mar-15 26-Mar-15
2 k2kV Foundation Group 113 74.34%25-Oct-14 A 24-Feb-15
_44 132kV Gantry Tower Type 1 foundations (P1) 25 100% 2 5-Oct-14 A 06-Jan-15 A
_44 1 32kV Busbar support foundations (P6) 25 100% 09-Nov-14 A 06-Jan-15 A
_44 132kV Lightning Tower Gantry foundations (P2) 2 5 1 00 % 0 5 -D ec -1 4 A 1 3- Ja n- 15 A
_45 132kV Precast -Current transformer foundations 25 80% 0 4-Dec-14 A 31-Jan-15
_ 46 1 32 kV P rec as t -C ap ac itiv e vo lt ag e tra ns fo rm er f ou nd at io ns 2 5 8 0% 0 4 -De c- 14 A 3 1- Jan -1 5
_ 46 1 32 kV Precas t -Surge Arrester foundatio ns (1 phase) 2 5 8 0% 0 4-Dec-1 4 A 3 1-Jan-1 5
_44 1 32kV Precast -DS Serial foundations 25 60% 04-Dec-14 A 05-Feb-15
_45 132kV Precast -DS foundations 25 60% 04-Dec-14 A 05-Feb-15
_45 132kV Circuit breaker foundations 15 20% 12-Jan-15 A 07-Feb-15
_46 132kV CSE-SA foundations (1 phase) 25 0% 3 1-Jan-15 24-Feb-15
ble tble trenches and pipes 35 24.57%02-Jan-15 A 22-Feb-15
_62 Marshalling Kiosk Foundations 15 20% 12-Jan-15 A 07-Feb-15
_62 L ighting Poles Foundations the switchyards 20 0% 27-Jan-15 11-Feb-15
_46 Cable Trenches 32 30% 02-Jan-15 A 22-Feb-15
e De Drainage 25 0% 3 1-Jan-15 24-Feb-15
_41 Drainage works 25 0% 31-Jan-15 24-Feb-15
t hithing System 30 0% 2 2-Feb-15 24-Mar-15
_41 Earthing System Trench 30 0% 2 2-Feb-15 24-Mar-15
adsads 30 0% 2 3-Apr-15 23-May-15
_ 41 Internal Co ncrete ro ads and site co ncrete co vering wo rks 3 0 0 % 23 -Apr-1 5 2 3-M ay-15
talltallation of Fire Detection System 20 0% 1 9-Mar-15 08-Apr-15
_52 Fire detection system 20 0% 19-Mar-15 08-Apr-15
talltallation of Air - Conditioning system 20 0% 1 9-Mar-15 08-Apr-15
_52 Air conditioning system 20 0% 1 9-Mar-15 08-Apr-15
rkrk of gravel layer and BRC fence 64 0% 2 4-Mar-15 27-May-15
_45 15 cm layer crushed stone 30 0% 24-Mar-15 23-Apr-15
_45 C oncrete Posts surrounding the Switchyards 20 0% 23-Apr-15 13-May-15
_ 45 S witc hyar d M ain Gat e fo r v eh ic le s a nd ped es tra in (1 +5 met er ) 6 0 % 1 7- May -1 5 2 3- May -1 5
_45 Switchyard Gate for pedestrain (1 meter) 6 0% 17-May-15 23-May-15_45 Galvanised fencing surrounding the Switchyards 14 0% 1 3-May-15 27-May-15
_45 Production and construction of galvanized barbed wire surrounding the switchyar 14 0% 1 3-May-15 27-May-15
allallation 1 30 1 0. 8% 0 8 -J an -1 5 A 2 2- Ma y- 15
elel Structures 6 8 2 0. 47 % 0 8 -J an -1 5 A 2 2- Ma r- 15el Seel Structures for 132kV System 37 38.81%08-Jan-15 A 18-Feb-15
010 145kV Busbar System & Pylons Steel Structures 14 38.1% 0 8-Jan-15 A 04-Feb-15
060 145kV Equipment Steel Structures 18 2% 25-Jan-15 A 18-Feb-15
nsionsion and Suspention_Al Basbar 15 0% 1 8-Feb-15 05-Mar-15
1611Ins ta llat ion o f A luminium Bus Bar inc lude s Pos t Insulat o rs f or Bus Bar 15 0%18-Feb-15 05-Mar-15
1612 Installation of Tension and Suspention 15 0% 1 8-Feb-15 05-Mar-15
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
27-May-15, Civil Works
20-Sep-14 A, Mobilization
29-Mar-15, Main Building Works
29-Mar-15, SUBSTATION CONTROL BUILDING
Control Building Ready for Installation
26-Mar-15, Leakproof Cesspool and seepage pit for Substation
24-Feb-15, 132kV Foundation Group
22-Feb-15, Cable trenches and pipes
24-Feb-15, Site Drainage
24-Mar-15, Earthing System
23-May-15, Roads
08-Apr-15, Installation of Fire Detection System
08-Apr-15, Installation of Air - Conditioning system
27-May-15, Work of gravel layer and BR
22-May-15, Installation
22-Mar-15, Steel Structures
18-Feb-15, Steel Structures for 132kV System
05-Mar-15, Tension and Suspention_Al Basbar
at Updated Work Programme- ACT_27.01.2015 4 of 5
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
16/27
Activity Name Dur. %Complete Start Finish
ble Tble Tray,Racks and Ladders 28 0% 2 2-Feb-15 22-Mar-15
320 Installation of Cable Tray, Ladders and Racks 28 0% 22-Feb-15 22-Mar-15
t hithing System 28 0% 1 3-Mar-15 10-Apr-15
251 Earthing Work 28 0% 13-Mar-15 10-Apr-15
2 k2 kV Equipments 44 0% 0 5-Mar-15 18-Apr-152 kV2 kV Primary Equipments 38 0% 0 5-Mar-15 14-Apr-15
1180 145kV Disconnecting & Earthing Switchs 38 0% 0 5-Mar-15 12-Apr-15
200 145kV Measuring Transformers 38 0% 05-Mar-15 12-Apr-15
220 145kV Surge Arresters 38 0% 05-Mar-15 12-Apr-15
613 145kV Post Insulators 38 0% 05-Mar-15 12-Apr-15
160 145kV Circuit Breakers 38 0% 05-Mar-15 14-Apr-152 kV2 kV Secondary Equipments 30 0% 1 9-Mar-15 18-Apr-15
390 Installation of Control & Protection Panels 30 0% 19-Mar-15 18-Apr-15
SySystem 35 0% 2 9-Mar-15 03-May-15
440 B atteries, Battery Chargers, AC & DC Panel 35 0% 29-Mar-15 03-May-15
t dotdoor Ligthing 35 0% 1 5-Apr-15 19-May-15
510 145kV Lighting 35 0% 15-Apr-15 19-May-15
blesbles 40 0% 1 2-Apr-15 22-May-15
340 Laying & Termination of Cables 40 0% 12-Apr-15 22-May-15
ec oecom and Scada System 55 0% 1 9-Mar-15 13-May-15
600 Telecom Equipments 50 0% 1 9-Mar-15 08-May-15
610 SCADA System 45 0% 29-Mar-15 13-May-15
t &t & Commissioning 20 0% 2 2-May-15 11-Jun-15
_60 T est and Commissioning 20 0% 22-May-15 11-Jun-15
epteptance 0 0% 11-Jun-15 11-Jun-15
_70 Energization 0 0% 11-Jun-15*
tortory Acceptance Tests 92 80.97%28-Oct-14 A 15-Feb-15
5 k5kV Circuit Breakers 1 1 00 % 1 5- Jan -1 5 A 1 5- Jan -1 5 A
-1 2 F ac to ry Acceptance Test o f 1 45 kV Circuit Breakers 1 1 00 % 15 -Jan-1 5 A 1 5-Jan-1 5 A
5 k5kV Disconnecting Swich 1 1 00 % 0 1 -D ec -1 4 A 0 1- De c- 14 A
- 12 F ac to ry A cc ep ta nc e Te st s o f 1 45 kV Dis co nne ct ing S wic h 1 1 00 % 0 1- De c- 14 A 0 1- Dec -1 4 A
5 k5kV Surge Arresters 1 1 00 % 2 8- Oc t- 14 A 2 8- Oc t- 14 A
-1 2 F ac tory Acceptanc e Tests of 1 45 kV Surge Arres ters 1 1 00 % 28 -Oc t-1 4 A 2 8-Oct-1 4 A
5 k5kV CT & VT 1 1 00 % 2 4 -N ov -1 4 A 2 4- No v- 14
-12 Factory Acceptance Tests of 145kV Current Transformer & Voltage Transformer 1 1 00 % 2 4 -N ov -1 4 A 2 4- No v- 14
ntrontrol Protection Panels 18 94.44%26-Jan-15 A 15-Feb-15
-1 2 F ac to ry Acceptance Test of Co ntro l Pro tectio n Panels 1 1 00 % 26 -Jan-1 5 A 2 6-Jan-1 5 A
-12 Factory Acceptance Test of Metering Panels 1 0% 15-Feb-15 15-Feb-15
herher FATs 50 64.71%29-Dec-14 A 15-Feb-15
-12 Factory Acceptance Tests of Steel Structures 1 100% 29-Dec-14 A 29-Dec-14 A
-12 Factory Acceptance Tests of Telecommunication 1 0% 2 9-Jan-15* 30-Jan-15
-12 Factory Acceptance Tests of ECS System 1 0% 1 5-Feb-15 15-Feb-15
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
22-Mar-15, Cable Tray,Racks and Ladders
10-Apr-15, Earthing System
18-Apr-15, 132 kV Equipments
14-Apr-15, 132 kV Primary Equipments
18-Apr-15, 132 kV Secondary Equipments
03-May-15, DC System
19-May-15, Outdoor Ligthing
22-May-15, Cables
13-May-15, Telecom and Scada System
11-Jun-15, Test & Commissioning
11-Jun-15, Acceptance
Energization
15-Feb-15, Factory Acceptance Tests
15-Jan-15 A, 145kV Circuit Breakers
01-Dec-14 A, 145kV Disconnecting Swich
28-Oct-14 A, 145kV Surge Arresters
24-Nov-14 A, 145kV CT & VT
15-Feb-15, Control Protection Panels
15-Feb-15, Other FATs
at Updated Work Programme- ACT_27.01.2015 5 of 5
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
17/27
Risk Assessment for Khabat PP132kV Switchyard Electrical Works
TOTAL 9 PAGES
(Including Cover)
PROJECT NAME : Khabat Thermal Power Plant Units 1&2 Purpose
☐ For Information☒ For Review
☐ For Approval
☐ For Construction
☐ As-Built
DOCUMENT NO. : KP-00+++-MQ734-V0100
TITLE : Risk Assessment for Khabat PP 132kV Switchyard
OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government
A 02.01.2015 First Issue DE EÖ AY YÖ
Rev.No.
DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED
GAMA POWER SYSTEMS ENG &CONTRACTING,INC.
Owner
Ministr y of Electrici ty (MOE)of Kurdistan Regional Government
Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
GAMA POWER SYSTEMS
ENGINEERING & CONTRACTING,INC.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
18/27
Description
T a r g e t P . E . A . R .
Impacts
(Consequences)
H a z a r d S e v e r i t y
L i k e l i h o o d o f O c c u r r e n c e .
R i s k R a t i n g .
H a z a r d S e v e r i t y
L i k e l i h o o d o f O c c u r r e n c e .
R e s i d u
a l R i s k E v a l u a t i o n
H / M / L .
1 Before start to work
Inexperienced
personnel
involved in the
operation
Injury to personnel
damage to equipment
due to incompetency
4 2 8 3 1 3
2 Before start to work
Inadequate
working
environment
Injury to personnel
damage to unsafe
working environment
4 2 8 3 1 3
3 Excavation
Contact with
existing
buried services
Injury to personnel,material damage due
to electrocution and
explosion due to
contact with existing
buried services.
5 1 5 5 1 5
4 Excavation
Open
Excavations,
Trenches
4C
Injury to personnel
due to falling into
open excavations
5 3 15 4 1 4
5 Excavation
Open
Excavations,Trenches
4C
Injury to personnel
due to Collapse of the
excavations andentombment of
personnel.
5 2 10 5 1 5
6 Pylon / Equipment
Pylon Foundations
Manual Handling
Physical Force2C
Injury to personnel
due to
Handling/loading
materials by body
force Improper
equipment.
3 3 9 2 1 2
7
Civil Operations
/Handtools /
Electrical
Equipments
Mechanical /
Physical Risk 4C
Multiple injuries (eye,
arm,face irritation ),
Burns, Disability /
Fatality due to unsafe
working conditions,
Electrical shock,
uncontrolled/not
tested electrical
equipments, and
uncalibrated
equipments
5 3 15 4 1 4
8 All activitiesLack of
supervision4B
Injury, fatality,
property damage due
to insufficient
management
5 2 10 4 1 4
HSE department will check the area and
ensure that all precautions are taken prior to
start to work.
Obtain a valid PTW for “Excavations” before
starting any digging activity.
Ensure that all buried services are properly
identified. Follow the instructions
contained in the PTW. Execute only manual
digging close to energized buried cable lines
and pressurized buried pipelines.
Any excavation deeper than 1.2 m or any
different elevations more than 1,2 m shall be
barricaded with scaffolding or any other strong
materials.
Temporary barricades shall be netlon fence,
which provides solid visual
barricade. The height of the barricades s hall
Dedicated team leader will be in place during
all work activities. A toolbox talk will be done prior to the
operation. Method Statement and Risk
assessment will be communicated to all
personnel involved to the operation.
Workplace Risk Assessment - WorksheetSITE / UNIT: Iraq- Khabat Project ASSESSMENT TEAM LEADER:Ali Ugur Benli ASSESSMENT Ref No:
DATE OF ASSESSMENT: 09/14
TIMEOF ASSESSMENT:14.00
ACTIVITY DESCRIPTION: Pylon Foundation, Steel Erection,
Electrical Works. ASSESSMENT TEAM MEMBERS:Ali Ugur Benli, Eyup Ozbay
HAZARD INITIAL RISK
Job StagesNo
CONTROLS
Control & Recovery Measures Required
RESIDUAL RISK
For excavations deeper than 170 cm, sheet
piles will be used. When necessary an efficient
dewatering system must be installed. In cases
of deep excavations with reduced width and
difficult access, a valid PTW for “Confined
Spaces” must be obtained before starting any
activity inside and all prescribed precautions
strictly followed.
All working instructions & checklist related to
civil operations are all in place provided by
Siemens.
Safe Manual Handling practices should be
applied during installation.
Manual Handling Training (incl.basic
ergonomy) shall be given where required.
All safety devices should be checked beforefor their proper fitting and function
No person to be inside a dangerous area while
functional checks or run up procedures are
being carried out.
All actions to be carried out bu competent
persons. All electrical hand tools will be
checked by site EHS officer and inspection
label will be put on tools as green; safe to use,
red; not safe dont use. Workplace to be
restricted, not allow to get anyone inside
Other all safety measures to be taken into
account mentioned in working instructions.
Handtools run with 24V if possibel especially
in Confined Spaces.
Only trained and experienced personnel to be
involved in the activity.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
19/27
9 All activities Visibility 3B
injury due to poor
vision, not enough
illumination
4 2 8 3 1 3
10 All activitiesVehicle
Movement 4C
Injury, fatality,
property damage due
to Vehicle collisions.
5 3 15 4 1 4
11 All activitiesVehicle
Movement 4B
Injury, fatality,
property damage due
to Crushing of
personnel by
vehicles in movement.
5 2 10 5 1 5
12 Backfilling Machinery 3C
injury or material
damage due to poor
maintenance of
vehicle / equipment
4 3 12 3 1 3
13Simultaneous
Operations
Working in
conjunction with
the truck or
equipments
3C
Injury to personnel or
material damage due
to hit by truck or
equipment
4 3 12 3 1 3
14
Transportation of
the backfilling
material from
storage area to
backfilling area
Loading,
transportation
and unloading
the backfilling
material
3C
Injury or material
damage due to hit by
truck / equipment
4 3 12 4 1 4
15 Completion of Work
Incorrect wastemanagement
procedures in
place
2C
Pollution,
Environmental
Damage
3 3 9 3 1 3
16 Housekeeping
Mechanic risks
Chemical risks
Physical Effects
Non-quality work
Chemicals
Wastes
Not accessible
fire fighting
systems
4C
Multiple injuries (eye,
arm,face,etc.),
Electrical shock, Fire,
Environmental impact
due to Materials (civil,
electrical, mechanic )
that are not stored in a
proper place and safe,
Cable bobbins left
random along the
ways without scotchs
around, Equipment
usage in an unsafe
way, Electrical,
lighting cables left
random on the floors,
Probable night works,
Chemical, oil leakage
around the workplace,
Wastes stored
random within site
witout segragation
5 3 15 4 1 4
Materials to be stored in proper, well defined
area
Permanent walkways and stairs installed
Road access shall not be obstructed by parked
vehicles, trucks, cranes and machinery.
Wastes segragated and stored in a proper
place
Leakages to be removed within site
All trailing leads and cables shall be safely
suspended or fully protected.
Obstruct materials should be removed from
workplace.
Vehicles and equipment will be visually
checked by drivers / operators prior to start to
operation.Banksman (watchman) will be also
on site, communicating with vehicle operator.
Vehicle / equipment movements around the
wall will be controlled by a watchman.
Trucks and equipments will be operated by
experienced and authorized personnel.
Smoking, eating and talking by mobile phone
strictly forbidden. Trucks will obey the speed
limit at all times. (20 km/h) The vehicle
movements around the wall will be controlled
by a watchman
All waste will be collected and segrageted
according to their type and stored properly.
Hazardous wastes will be disposed align with
standarts. The wastes could be recycled if
applicable
Operation (including preparations) will be done
in day time only.
Follow the site roads only and respect the
speed limits. Flashing lights always on and
use of a trained banks man, when and where
necessary. It is forbidden to use the mobile
phone, smoking and eating while driving. Sit
belts must be used at all times by the driver
and any passenger.
Wearing high visibility vests is mandatory all
over the site area. Follow the
pedestrian walkways. All vehicles must be
provided with audible reversing
warning devices or accompanied by a qualified
banks man. Keep the safety distance from all
vehicles in operation.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
20/27
17
Preperations for
work
Inexperienced
personnel
involved in the
operation /
Inadequate
working
environment
P
R
Injury to personnel
damage to equipment
due to incompetency /
unsafe working
environment
5 2 10 4 1 4
18 Smoking Fire and Health
Hazard
P E
A
R
Burn Injuries, Fire andExplosion, Multiple
Fatalities
5 3 15 4 2 8
19
Civil Work Stage
Assembly Operation
(Ground level)
Mechanical /
Physical Risk
(Hand tools
Power tools )
P Electrical shock,
single fatality or
permanent disability
4 3 12 2 2 4
20
Civil Work Stage
Steel base erection
Access/ Exit to
Plylon Socket P
Injury to personnel
due to falling into
socket, major injury
3 4 12 1 3 3
21
Civil Work Stage
Assembly Operation
(Foundation Level)
Mechanical /
Physical Risk
(Hand tools
Power tools )
P
A
R
Injury to personnel
due to
Handling/loading
materials by body
force
Improper equipment;
(deformed electrical
cables,no guarding on
machine, etc.)
electrical shock,single
fatality
4 4 16 2 2 4
22
Civil Work Stage
Assembly operation
; Butt splice / beam
assembly
Mechanical /
Physical Risk
Environmental
Risks
(Crane usage)
P
E
A
Multiple Fatalities, ,
Leakege from hoisting
equipments, Property
damages.
5 3 15 3 1 3
23
Civil Work Stage
Assembly operation
; Butt splice / beam
assembly
Mechanical /
Physical Risk
(Hand tools )
P
Major injury to
personnel due to
Handling/loading
materials by body
force
Improper equipment;
3 4 12 1 3 3
24 Cable layingManual Handling
Physical Force
P
Minor injury to
personnel due to
Handling/loading
materials by body
force Improper
equipment.
3 3 9 1 2 2
25 Lifting
Lifting equipment
failure, fall from
height and run
over
P
E
A
Fatality, Major Injuries,
Leakege from hoisting
equipments, Property
damages.
4 4 16 3 3 9
26
Working at height
Working at the
height above 1.8mtr
Fall hazards and
objects falling
from heights
P
E
A
R
Fatality
Fracture, major
injuries4 3 12 3 2 6
Color code and inspection at all lifting gears
Insurance documents shall be provided
Outriggers shall be utilized during all
operations
Proper crane setup, especially near
excavations
Pads shall ve utilized for outriggers at all times
Hoisting crane examination before work start.
Check the documents for hoisting mechanism
and devices.
PPE supply.
First Aid Kit availability on site.
Wear proper PPE.
Only qualified and trained (inc. risk
assesments & procedures) personnel access
to construction site.
Proper equipment with specifications and
maintenance records.
PTW system shall be followed,
Underground facilities shall be identified and
drawing shall be provided before commencing
activity.
Smoking is prohibited at site area.
Fire extinguisher.
It is allowed at designated area only.
Ensure that all personnel shall undergo for the
induction training to know they dos and don’ts
at site.
In addition to mandatory PPEs;mechanical
resistant gloves and high visible jacket to be
worn
Safety barriers to be put in place to restrict
working area especially if workplace jsut near
road (vehicle movement area)
Screening of working area
First aid kits
Use right tool fit for the purpose
Obtain a valid PTW for “Access/Exit to
sockets''
Ensure that ladders are in line with Siemens
Standards; aluminum, fixed at the bottom and
the upper part, and exceed the final level to be
reached of at least 1m.
In addition to mandatory PPEs;mechanical
resistant gloves and high visible jacket to be
worn
Safety barriers to be put in place to restrict
working area especially if workplace jsut near
road (vehicle movement area)
Screening of working area
First aid kits
Use right tool fit for the purpose
Ensure all power tools are in good condition
with insulation
Ensure the use of 220 V power tools
Trained and authorized person only shall
operate the power tools
Ensure for appropriate PPE
Check validity before use of tools by
employees
Attests of manufacturer, regular check of
condition
Color code and inspection at all electrical
equipments
Inspection, maintainance and repair of
All safety devices should be checked before
for their proper fitting and function
No person to be inside a dangerous area while
functional checks or run up procedures are
being carried out.
All actions to be carried out bu competent
persons. Workplace to be restricted, not allow
to get anyone inside
Other all safety measures to be taken into
account mentioned in working instructions.
In addition to mandatory PPEs;mechanical
resistant gloves and high visible jacket to be
All working instructions & checklist related to
civil operations are all in place provided by
Siemens.
Safe Manual Handling practices should be
applied during installation.
Manual Handling Training (incl.basic
ergonomy) shall be given where required.
Color code and inspection at all lifting gears
Insurance documents shall be provided
All outriggers shall be utilized during all
operations
Proper crane setup, especially near
excavations
Pads shall ve utilized for outriggers at all times
Hoisting crane examination before work start.
Check the documents for hoisting mechanism
and devices and certificates shall be kept for
Ladders shall not be used as platformFall protection device full body harness shall
be used and it should be 100% tie off with
double lanyard
Don’t carry materials while climbing on ladder.
Ensuring the personnel get the education for
working at height.
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
21/27
27 Working with manlift
Fall hazards and
objects falling
from heights
P
A
R
Fatality, Major Injuries,
Leakege from hoisting
equipments
3 4 12 2 3 6
28
Use of ladders
Climbing up and
down throughladders and
improper or insecure
positioning
Slip, trip, injuries
due to brokenand metal
ladders and fall
from ladder
P Dea th , f al l f rom he igh t
and sprain injuries5 3 15 3 3 9
29
Mechanical
Assembly
/Handtools /
ElectricalEquipments
Mechanical /
Physical Risk
(Handtools /Power Tools)
P
A
R
Multiple injuries (eye,
arm,face irritation ),
Burns, Disability /
Single Fatality due to
unsafe working
conditions, Electrical
shock,
uncontrolled/not
tested electrical
equipments, and
uncalibrated
equipments
4 3 12 3 2 6
30 Working with Dilo
compression set
Compressed
SF6 gas
cylinders
P
A
R
Permanent disability,
multiple fatalities,
major damage, major
national impact
5 4 20 4 2 8
31 All activitiesLack of
supervisionP
Permanent disability,
single fatality,
property damage due
to insufficient
management
4 3 12 3 2 6
32 All activities Visibility P
Major injury due to
poor vision, not
enough illumination
3 3 9 2 2 4
33 All activitiesVehicle
Movement
P
E
A
R
Fatality/Permanent
disability due to traffic
accident
Press. Jamming. Load
or Equipment
Changeover.
Fuel and Lubricants
Spillage/
5 3 15 3 2 6
Color code and inspection for manlift
Manlift shall be equipped with railings for each
open part and each end: a rigid top rail, 1
meter high, an average rail, 0.45 meter high
and a baseboard (0.15 m. high).
Insurance documents shall be provided
Proper manlift setup, especially near
excavations
Ensure appropriate ladders in use
Three point contact is must
Check the ladders before use
Position it properly and tie where necessary
Check the ladder before each use
While using more than 3mtr ladder, a person
has to hold it
Before use, ladder has to be visually checked.
Ladders have to be placed that horizontal and
vertical ratio is 1:4. Approximately angel of 75°.
Ladder shell not is used as working platform.
Regular checking of safety devices and proper
positioning of the ladder.
Periodical inspection for ladder by competent
Use right tool fit for the purpose
Ensure all power tools are in good condition
with insulation
Ensure the use of 220 V power tools
Trained and authorized person only shall
operate the power tools
Ensure for appropriate PPE
Check validity before use of tools by
employees Attests of manufacturer, regular check of
condition
Periodical inspection with color coding system
Certified electricians shall repair power tools
Color code system will be applied to all
electrical equipments
Gas cylinders will be kept at proper storage
area
Storage area will be protected from climate
effects (rain, direct sun light, overtemp,
extreme cold etc.)
Storage area shall be locked and key shall be
hand in responsible person
Storage area will be marked as indicating risks
and stored material
Dedicated team leader will be in place during
all work activities.
A toolbox talk will be done prior to the
operation. Method Statement and Risk
assessment will be communicated to all
personnel involved to the operation.
STARRT code system shall be applied.
Supervision of work team shall be provided by
a competent supervisors during all activities.
Operation (including preparations) will be done
in day time only.
In poor visibility (heavy rain, dust storm, sand
storm etc.) activities shall be suspended.
Driver should follow Safety Rules while Driving
Transport Vehicles.
Seat belt shall be worn at all times by all
passengers and driver.
Daily checlist shall be done before start
driving.
The Drivers should:
Seat belt shall be worn all times
Have valid certificate and driver license
Do daily checlist before driving
Follow Speed Restriction Signs in accordance
with Road Requirements; Always be on the
alert to potential hazards; Look at mirrors and
use signals before maneuvering; Keep safety
distance behind other transport-vehicles; Use
Dipped Headlight and Slow Speed in condition
of poor visibility; Do not use cell phones or
other means of communication in Driving; Do
8/17/2019 KP-00+++-MQ758-V0010-Rev 0-MS for CB Installation Works.pdf
22/27
34Simultaneous
Operations
Working in
conjunction with
the truck or
equipments
P
A
Permanent disability
to personnel, single
fatality or material
damage due to hit by
truck or equipment
4 2 8 3 2 6
35 Completion of Work
Incorrect waste
management
procedures in
place
E
Pollution,
Environmental
Damage
Soil contamination
3 3 9 1 3 3
36
Territory
housekeeping by
work completion
Waste. Sharp
materials, fall,
trip, slip
P
E
Slight injuries. Trip,
fall.
Wrong wastes
disposal.
Fuel and Lubricants
spillage.
2 4 8 1 3 3
37 Working under 380
kV High Voltage
Unsafe working
without taking
necessary
safetymeasures.
P
A
R
Getting closer than
limit approach value
Working with
4 2 8 3 2 6
38 Working under
380Kv High Voltage
Unsafe working
without taking
necessary
safety
measures.
P
A
R
Working in bad
weather conditions3 4 12 1 3 3
39Working under
380Kv High Voltage
Unsafe working
without taking
necessary
safety
measures.
P
A
R
Working with no Ekat
certificate personal 3 3 9 2 2 4
40 Working under
380Kv High Voltage
Unsafe workingwithout taking
necessary
safety
measures.
P
A
R
Throwing materials 3 4 12 2 3 6
41Preperations for
work
Inexperienced
personnel
involved in the
operation /
Inadequate
working
environment
P
R
Injury to personnel
damage to equipment
due to incompetency /
unsafe working
environment
2 5 10 1 4 4
42 Smoking Fire and Health
Hazard
P
E
A
R
Burn Injuries, Fire and
Explosion, Multiple
Fatalities
4 4 16 3 3 3
43
Civil Work Stage
Assembly Operation
(Ground level)
Mechanical /
Physical Risk
(Hand tools
Power tools )
P Electrical shock,
single fatality or
permanent disability
4 4 16 2 3 6
44
Civil Work Stage
Steel base erection
Access/ Exit to
Plylon Socket P
Injury to personnel
due to falling into
socket, major injury
3 4 12 1 4 4
Vehicle / equipment movements around the
wall will be controlled by a watchman.
Banksman will manage vehicle activities
Vehicle road and pedestrian route shall be
identified.
All waste will be collected and segrageted
according to their type and stored properly.
Hazardous wastes will be disposed align with
standarts. The wastes could be recycled if
applicable.
Any contamination shall be removed
immediately and shall be sent to the waste
All trailing leads and cables shall be safely
suspended or fully protected.
Obstruct materials should be removed from
workplace.
Control by Foremen, Supervisors, Safety
Engineers.
Regular, routine housekeeping and working
place compulsory cleaning at the end of
working shift.
Min. 10 meter approach limit must be kept.
Never conductive objects such as shovel,
digger etc.
Also it must be forbidden to use construction
wire inside the switchyard zone.
Hand tools must be suplied from outside
grounded