Knowledge Area By Project Phase Creating Links Between Projects

Embed Size (px)

DESCRIPTION

Creating Links Between Projects in Microsoft Project

Citation preview

Page 1: Knowledge Area By Project Phase   Creating Links Between Projects

https://share.ps.net/fndr/EQS/Project%20Management%20Instant%20Oatmeal/default.aspx?CalendarDate=11%2F5%2F2010

“Instant Oatmeal”January 23, 2012

Page 2: Knowledge Area By Project Phase   Creating Links Between Projects

2 Services

Page 3: Knowledge Area By Project Phase   Creating Links Between Projects

3 Services

Develop Schedule Dependencies Projects are

not islands they

interact

Page 4: Knowledge Area By Project Phase   Creating Links Between Projects

Links Between Projects

Forrest Kovach, MBA, PMP, MCTS - Project

Page 5: Knowledge Area By Project Phase   Creating Links Between Projects

5 Services

Build Projects by Team or Work Stream

Page 6: Knowledge Area By Project Phase   Creating Links Between Projects

6 Services

Connect Projects in a Collector Project

Page 7: Knowledge Area By Project Phase   Creating Links Between Projects

7 Services

Insert Projects as Subprojects in the Collector

Page 8: Knowledge Area By Project Phase   Creating Links Between Projects

8 Services

Insert Projects as Subprojects in the Collector

Page 9: Knowledge Area By Project Phase   Creating Links Between Projects

9 Services

External Relationships Feature

Page 10: Knowledge Area By Project Phase   Creating Links Between Projects

10 Services

Creating Links

Private Cloud needs Network Infrastructure Compete

Page 11: Knowledge Area By Project Phase   Creating Links Between Projects

11 Services

Creating Links

Select Tasks From Separate Sub-ProjectsClick First Task ID, hold Crtl KeyClick one or more Successors

Page 12: Knowledge Area By Project Phase   Creating Links Between Projects

12 Services

Creating Links

Click the Link Tasks Tool

MS Project Creates the linkBetween Subproject with the PathAnd file names.

Page 13: Knowledge Area By Project Phase   Creating Links Between Projects

13 Services

Creating Links

Use this technique to track key deliverablesfrom many sub-projects to aIntegrated Master Schedule

Page 14: Knowledge Area By Project Phase   Creating Links Between Projects

14 Services

• Links can be added manually in the Predecessor, Successor, Unique ID Predecessor or Unique ID Successor fields.

• For Example, the following entry in a Successor Cell:– 292,C:\Users\Forrest_Kovach\Documents\WK Transition\

TR_WK_Integrated Master Schedule\DELL WK PPM.mpp\593

– Says link to 292 within the project and link to line 593 in the DELL WK PPM project.

– The use of Unique IDs may be more expedient for creating manual external links as these numbers are fixed.

– Use the same technique in Unique ID fields with the Unique ID line numbers.

Maintaining Links

Page 15: Knowledge Area By Project Phase   Creating Links Between Projects

15 Services

Progressing in the Collector

• No different than progressing in a single file.

• Performance may be slow if the number of tasks exceeds 2000.

• Project Status Date Must be Set in Individual Files

• Use the Project Field to Identify what file is being progressed.

Page 16: Knowledge Area By Project Phase   Creating Links Between Projects

16 Services

Progressing in the Collector

Page 17: Knowledge Area By Project Phase   Creating Links Between Projects

17 Services

Progressing in the Sub-Project

• Faster response time

• Can still see impact of external connection in Total Slack

Page 18: Knowledge Area By Project Phase   Creating Links Between Projects

18 Services

Issues with Link Paths

• If files are relocated to a new path MS Project attempts to find the missing links and creates new external links.

• The new added links may become redundant with existing links.

Page 19: Knowledge Area By Project Phase   Creating Links Between Projects

19 Services

• The resources from all projects can be viewed the Resource Sheet.

• Time Phased data can be viewed in aggregate in Resource Usage or Task Usage

Viewing the Aggregate Resource Sheet

Page 20: Knowledge Area By Project Phase   Creating Links Between Projects

20 Services

Aggregate Resource Time-phased Data

• To use the same resource across multiple subprojects requires a resource pool

• Establish shared resourcesin the Collector Project

• You can then allocate a resource across multiple sub-projects to see allocations.

• Resource pools are not required in Project Sever