Creating Links Between Projects in Microsoft Project
Citation preview
https://share.ps.net/fndr/EQS/Project%20Management%20Instant%20Oatmeal/default.aspx?CalendarDate=11%2F5%2F2010
“Instant Oatmeal”January 23, 2012
2 Services
3 Services
Develop Schedule Dependencies Projects are
not islands they
interact
Links Between Projects
Forrest Kovach, MBA, PMP, MCTS - Project
5 Services
Build Projects by Team or Work Stream
6 Services
Connect Projects in a Collector Project
7 Services
Insert Projects as Subprojects in the Collector
8 Services
Insert Projects as Subprojects in the Collector
9 Services
External Relationships Feature
10 Services
Creating Links
Private Cloud needs Network Infrastructure Compete
11 Services
Creating Links
Select Tasks From Separate Sub-ProjectsClick First Task ID, hold Crtl KeyClick one or more Successors
12 Services
Creating Links
Click the Link Tasks Tool
MS Project Creates the linkBetween Subproject with the PathAnd file names.
13 Services
Creating Links
Use this technique to track key deliverablesfrom many sub-projects to aIntegrated Master Schedule
14 Services
• Links can be added manually in the Predecessor, Successor, Unique ID Predecessor or Unique ID Successor fields.
• For Example, the following entry in a Successor Cell:– 292,C:\Users\Forrest_Kovach\Documents\WK Transition\
TR_WK_Integrated Master Schedule\DELL WK PPM.mpp\593
– Says link to 292 within the project and link to line 593 in the DELL WK PPM project.
– The use of Unique IDs may be more expedient for creating manual external links as these numbers are fixed.
– Use the same technique in Unique ID fields with the Unique ID line numbers.
Maintaining Links
15 Services
Progressing in the Collector
• No different than progressing in a single file.
• Performance may be slow if the number of tasks exceeds 2000.
• Project Status Date Must be Set in Individual Files
• Use the Project Field to Identify what file is being progressed.
16 Services
Progressing in the Collector
17 Services
Progressing in the Sub-Project
• Faster response time
• Can still see impact of external connection in Total Slack
18 Services
Issues with Link Paths
• If files are relocated to a new path MS Project attempts to find the missing links and creates new external links.
• The new added links may become redundant with existing links.
19 Services
• The resources from all projects can be viewed the Resource Sheet.
• Time Phased data can be viewed in aggregate in Resource Usage or Task Usage
Viewing the Aggregate Resource Sheet
20 Services
Aggregate Resource Time-phased Data
• To use the same resource across multiple subprojects requires a resource pool
• Establish shared resourcesin the Collector Project
• You can then allocate a resource across multiple sub-projects to see allocations.
• Resource pools are not required in Project Sever