    Strategic Leadership ofPortfolio and ProjectManagement

    Timothy J. Kloppenborg and Laurence J. Laning

  • 7/30/2019 Kloppenborg Chap One

    4/26

    Strategic Leadership of Portfolio and Project Management

    Copyright Business Expert Press, 2012.

    All rights reserved. No part of this publication may be reproduced,

    stored in a retrieval system, or transmitted in any form or by any

    meanselectronic, mechanical, photocopy, recording, or any other

    except for brief quotations, not to exceed 400 words, without the prior

    permission of the publisher.

    First published in 2012 by

    Business Expert Press, LLC

    222 East 46th Street, New York, NY 10017www.businessexpertpress.com

    ISBN-13: 978-1-60649-294-9 (paperback)

    ISBN-13: 978-1-60649-295-6 (e-book)

    DOI 10.4128/ 9781606492956

    Business Expert Press Supply and Operations Management

    collection

    Collection ISSN: 2156-8189 (print)

    Collection ISSN: 2156-8200 (electronic)

    Cover design by Jonathan Pennell

    Interior design by Exeter Premedia Services Private Ltd.,

    Chennai, India

    First edition: 2012

    10 9 8 7 6 5 4 3 2 1

    Printed in the United States of America.

  • 7/30/2019 Kloppenborg Chap One

    5/26

    Abstract

    Tis book is aimed at executive leaders o organizations. Leaders rom

    all organizations will beneft rom this book, but especially organizations

    that may have limited resources and bench strength. Tis book instructs

    executive leadership teams on implementing strategy through identiying,

    selecting, prioritizing, resourcing, and governing an optimal combination

    o projects and other work. Tis book also tells executives who serve as

    a sponsor or who have a project manager direct report what they need

    to do at each project stage. Advice is given to the executive who owns

    the project management competency or the company on utilizing inputrom customers, employees, and processes. Much o the organizations

    work is dependent on inormation technology, and understanding and

    using inormation technology as a strategic weapon helps an organization

    become competitive and eectively implement their business strategies.

    All o these portolio and project decisions need to be made based upon

    both qualitative and quantitative data using reliable analysis methods.

    Keywords

    strategy, execution, portolio management, executive sponsorship,

    executive leadership, project management, inormation technology,

    data-based decision making, organizational assessment

  • 7/30/2019 Kloppenborg Chap One

    6/26

  • 7/30/2019 Kloppenborg Chap One

    7/26

    Contents

    Preface..................................................................................................ix

    Chapter 1 Implementing Strategy Trough

    Portolios and Projects .......................................................1

    Chapter 2 Managing a Portolio to Implement Strategy:

    A Leadership eam Role ..................................................17

    Chapter 3 Sponsoring Successul Projects .........................................43

    Chapter 4 Leading Project Managers:

    Te Project Executive Role...............................................75

    Chapter 5 Listening to Customers, Employees, and Processes:

    A Chie Projects Of cers Role .......................................109

    Chapter 6 Understanding Inormation echnology

    Opportunities and Challenges:

    A Chie Inormation Of cers Role ................................137Chapter 7 Making Sensible Decisions Using Data:

    A Responsibility o All Executives .................................177

    Chapter 8 Conclusions ...................................................................215

    Notes..................................................................................................221

    References ...........................................................................................225

    Index .................................................................................................231

  • 7/30/2019 Kloppenborg Chap One

    8/26

  • 7/30/2019 Kloppenborg Chap One

    9/26

    Preface

    We met over 20 years ago. Laurie was midcareer at Procter & Gamble

    (P&G) having other work experience and his PhD. im was untenured

    at Xavier having a ew years o business and military experience. At the

    time, we were part o a team redesigning the MBA program at Xavier.

    Since then, Laurie has held roles o increasing responsibility during a

    28-year career at P&G including introducing data management, leading

    the implementation o SAP in the supply chain, applying inormationtechnology to P&Gs new product innovation process, and retiring as the

    chie inormation technology enterprise architect. im fnished his U.S.

    Air Force Reserve career with transportation, procurement, and quality

    assurance assignments, worked his way up to distinguished proessor at

    Xavier, wrote nearly 100 publications including several books, consulted

    and trained with many clients, and supervised many student teams who

    helped nonproft organizations.

    With our combined 70 years o corporate, academic, military, con-

    sulting, training, board, and volunteer experience, we have had many dis-

    cussions concerning the common challenges in all o those organizations.

    One central challenge is when dierent parts o the organization either

    do not understand other parts or are even working at cross-purposes. We

    have combined our leadership, quality, project, inormation technol-

    ogy, and decision sciences backgrounds to create a short volume with

    the intent o addressing challenges that are common to many organiza-

    tions. Tis book applies the Pareto Principlethat is, choosing the 20%

    o ideas and techniques that will provide 80% o the value to leaders.

  • 7/30/2019 Kloppenborg Chap One

    10/26

  • 7/30/2019 Kloppenborg Chap One

    11/26

    CHAPTER 1

    Implementing StrategyThrough Portfolios

    and Projects

    Tis book, Strategic Leadership of Portfolio and Project Management,

    provides an approach to leadership by linking strategy to the action neces-

    sary to successully implement it. Many companies ace varying strategic

    implementation challenges as can be seen in able 1.1.

    Te book guides executives through strategic implementation by

    creating a ramework o key concepts and tools rom portolio manage-

    ment, executive sponsorship, project management, quality, inormation

    Table 1.1. Strategic Implementation Challenges Facing Companies

    Company Challenge

    Duke Energy is one of the largest electric

    utility companies in the United States.

    Duke continually faced large uncertainties

    in regulatory and business conditions and

    a huge pipeline of needs.

    TriHealth consists of several large

    hospitals, physician groups, and related

    health-care facilities.

    TriHealth did not have consistency in

    executive leadership roles, especially for

    projects.

    Messer is a full-service commercial

    construction company specializing in health

    care, higher education, and life sciences.

    Messer needed consistently successful

    construction projects.

    The Midland Company delivers specialized

    insurance services for mobile homes,

    classic cars, motorcycles, and snowmobiles.

    Midland has many methodologies and

    needed to decide how they can help

    execute the key initiatives of its business

    strategy.

    YourEncore is a consulting company with

    a network of veteran scientific,

    engineering, and technical experts.

    YourEncore needed to determine whether

    its information technology systems would

    be strong enough to support future growth.

    Givaudan is a global leader in the

    fragrance and flavor industries.

    Givaudan needed to make decisions about

    what development projects to undertake.

  • 7/30/2019 Kloppenborg Chap One

    12/26

    2 STRATEGIC LEADERSHIP OF PORTFOLIO

    technology (I), and decision-making. Each chapter describes how one

    o these companies met its implementation challenge by using conceptsrom that chapter.

    Te scope o this book encompasses both ongoing operational work

    and projects. Tis is a book about holistically leading an organization

    to achieve success as defned by our sets o competing objectives that

    are explained below. Tis chapter starts by describing the our sets o

    competing objectives aced by most organizations. Ten projects are

    defned including how each proceeds through a lie cycle and how

    success is determined. Te need or standards and the roles executives

    perorm in leading an organizations portolio o projects are intro-

    duced. Te chapter concludes with an overview o the other chapters

    in this book.

    Competing Objectives

    In many organizations, executives determine strategy and manag-

    ers implement it. Oten a gap can exist in successully accomplishing

    both objectives. Organizations also requently struggle with successullyaccomplishing three other sets o competing objectives: sustainable

    organizational capability and current business results, project goals and

    operational goals, and competing goals o dierent organizational unc-

    tions. Successul organizations consistently deliver each set o these com-

    peting objectives. Tis book is aimed to help you simultaneously better

    achieve each o these sets o competing objectives by describing concepts

    and tools or implementing strategy through careully identifed, aligned,

    selected, prioritized, resourced, and controlled projects.

    Executives Set Strategy and Managers Implement It

    Executives oten do not get very involved with projects. Tis may be due

    to excessive demands upon their time. Lack o executive involvement

    could also be due to lack o understanding o the technical nature o

    some o the project work or ear that i they are seen as closely tied to

    a project, they may be held responsible or any ailure. Limited execu-

    tive involvement in project implementation can lead to a gap between

  • 7/30/2019 Kloppenborg Chap One

    13/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 3

    the executive level that develops strategy and the management level that

    is charged with implementing it.Among the reasons or the ailure o strategic plan implementations

    are the leaderships imperect:

    understanding o customers true needs and wants,

    estimation o resource competence,

    coordination o work,

    ability to secure commitment rom both senior management

    and employees,

    creation o and adherence to logical plans,

    communication with employees and other stakeholders, and

    ability to identiy and manage risks.1

    Organizational Capability and Business Results

    In this book, we describe how companies strive to simultaneously achieve

    improvements in organizational capability and desired business results as

    stated by organizational objectives. Oten the pressure to achieve impres-sive short-term business results can lead to decisions that do not promote

    long-term organizational capability. Organizational capability can be

    expressed in terms o a companys:

    human resources: its number, quality, skills, and experience;

    physical and material resources: machines, land, buildings;

    fnancial resources: money and credit;

    inormation resources: pool o knowledge, databases; intellectual resources: copyrights, designs, patents, and so

    orth.2

    Project Goals and Operational Goals

    Yet another gap may exist between the project and the operational types

    o work in an organization, as shown in Figure 1.1. Operations (shown

    as processes in Figure 1.1) typically are the mechanism by which knowl-

    edge is turned into revenue. Tus, it is very important to keep this work

  • 7/30/2019 Kloppenborg Chap One

    14/26

    4 STRATEGIC LEADERSHIP OF PORTFOLIO

    moving eectively as the cash generated by these processes is the lieblood

    that sustains an organization. Te frm needs knowledge to successully

    capitalize upon and this is where projects come in handy. Projects o vari-

    ous types create knowledge ranging rom early stage research to specifcally

    applied process improvements. Without the knowledge an organization

    gains rom such work, it would quickly become obsolete.3

    Competing Goals of Different Organizational Functions

    Another set o competing objectives occurs between unctional silos o

    organizations. Each unctional area o an organization has work to accom-

    plish. An overemphasis on one department can shortchange another.

    Coordination between departments needs to be consciously developed

    through eective communication and cultural change.

    In this book, we describe how leaders strive to accomplish all our

    sets o competing objectives. Leaders can coordinate eorts at both the

    executive and the managerial levels. When leaders bridge the execu-

    tivemanager gap, they better deliver both current business results and

    organizational capability improvements. Tey also develop and capital-

    ize upon knowledge with projects and processes, and coordinate vari-

    ous department goals. All these things can be enhanced by eectively

    Knowledge

    building

    projects

    Options

    development

    projects

    Implementation

    projects

    Processes

    Keeping the lights on

    Examples:

    Basic R&D;

    Customer research;

    M&A due diligence

    Examples:

    Competitive strategy;

    Product development;

    Market entry;

    Channel strategy

    Inbound logistics

    Operations

    Incrementalprocessimprovements

    Sales and marketing

    Customer service

    Manufacturing

    Procurement

    Human resources

    Option

    execution

    projects

    Radical

    process

    improvements

    Reliable knowledge

    Knowledge continuum

    Little knowledge

    Knowledge to $

    Projects portfolio Current knowledgeNew

    knowledge

    Figure 1.1. Intertwining of projects and processes to create

    sustainable value.

  • 7/30/2019 Kloppenborg Chap One

    15/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 5

    identiying, aligning, selecting, prioritizing, resourcing, and controlling

    a best portolio o project and operational work to achieve all o theorganizational objectives.

    Projects

    A project is a temporary endeavor undertaken to create a unique prod-

    uct, service, or result.4 Because it is temporary, each project goes through

    a predictable series o stages called a lie cycle. Because it is an endeavor,

    each project requires resources to complete. Because it is unique, each

    project requires planning and control in a variety o areas such as scope

    (the amount o work), risk, budgeting, and so orth. Because projects

    create products, services, or results, stakeholders exist who are counting

    on those deliverables. Tose stakeholders must be identifed, understood,

    prioritized, communicated with, and satisfed.

    Universality of Projects

    In many ways, the world is changing aster than ever due to globalization,I, and knowledge creation. Project management can be a great way to

    plan and manage changes proactively. Project management skills enable

    people to quickly and exibly plan and deliver a wide variety o projects.

    A ew o the most useul skills are:

    initiating the eort with a charter,

    developing communication plans and dealing eectively with

    stakeholders,

    dividing work into manageable portions,

    scheduling complex interrelated work,

    managing risks and change, and

    reporting progress.

    Work in any unctional arena can be modeled and managed as a pro-

    ject. Project Management Institute (PMI) is the leading global proessional

    group that deals with project management. With over 370,000 members,

    PMI has communities o interest in dozens o industries, plus various

  • 7/30/2019 Kloppenborg Chap One

    16/26

    6 STRATEGIC LEADERSHIP OF PORTFOLIO

    unctional groups including fnancial services, human resources, inorma-

    tion systems, leadership, retail, and transportation.5

    Project management techniques can be applied to an endeavor o any

    size, rom a very simple endeavor to a highly involved one. Even or the

    simplest projects, it is important to be able to state what will be accom-

    plished and why it is important to the organization. Te largest and most

    complicated projects share the need o starting with what will be accom-

    plished and why, but the level o detail in planning and managing them

    should be commensurate with the challenge.

    Project Leadership Roles

    A variety o executive leadership responsibilities concerning projects need

    to be ulflled i a company is to optimally implement its strategy. Who

    handles each o these responsibilities and what their titles are varies con-

    siderably rom one company to another. For clarity, we will use consistent

    titles or the roles we describe.

    We need to clariy a ew things about these roles. Some o the respon-

    sibilities can be delegated rom an executive to a manager, whereas oth-ers should be retained. In larger organizations, sometimes several people

    each have a portion o the duties we describe in a given role. In smaller

    organizations, one person may have more than one o these roles and

    other responsibilities also.

    We have two general pieces o advice regarding these executive roles.

    First, since their duties are so dierent, do not use the same person in

    the role o a sponsor and a project manager on the same project. Second,

    ensure you understand each role and the reason or it. Make the conscious

    decision to have someone perorm each duty.

    Identiying these leadership roles in your company is helpul in

    assigning the right person to perorm each duty, thereby ensuring all

    responsibilities are perormed and helping executives understand where

    they can improve. Te executive roles we use in this book are leadership

    team, sponsor, project executive, chie projects o cer (CPO), and chie

    inormation o cer (CIO).

    Aleadership team is responsible or the results o all work in the port-

    olio. Tis team is oten composed o the top person in the organization

  • 7/30/2019 Kloppenborg Chap One

    17/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 7

    and the people who report to them. Te people described in some or all o

    the other roles may be members o the leadership team. Tey collectivelymake portolio decisions o identiying, selecting, prioritizing, resourcing,

    and governing projects.

    A sponsor wants the project results and is jointly responsible or

    achieving them along with the project executive and the project man-

    ager. She is the key decision-maker or the project. Te sponsor provides

    overall project resources, oversees stakeholders, and delivers project results

    according to the business case. Te sponsor has specifc responsibilities

    during each stage o the project lie cycle. I the project manager normally

    reports to the sponsor, she will also serve as the project executive.

    Aproject executive supervises one or more project managers who report

    directly to them and is jointly responsible or delivering project results with

    the sponsor and the project manager. He provides unctional resources, gov-

    erns methods used on the project, helps the project manager develop leader-

    ship competency, and delivers project results according to plan. Te project

    executive has specifc task and coaching responsibilities at each stage in the

    project lie cycle. Te project executive may also be the sponsor.

    ACPO responsible or developing project management competencyand acilitating the leadership team as they make portolio decisions. Te

    CPO has ongoing responsibilities in developing the project management

    system and competence along with specifc acilitating duties at key port-

    olio decision points.

    ACIO is responsible or all the I needs o the company. Te CIO

    works with senior management to defne a strategic I master plan that

    implements business strategy. Te CIO deals extensively with internal

    resources along with I consultants and I vendor companies.

    We describe each o these roles in more detail in the ollowing

    chapters. Te role o the sponsor is the only executive role that is

    clearly defned in proessional standards. We use those standards and

    add to them based upon our research over the last fve years concerning

    specifc duties and the impact each has on various measures o project

    success.

    While this book is written or executives, we will reer to the ol-

    lowing three project management roles. First, the project manager is the

    ocal point and is responsible or project planning, communications, and

  • 7/30/2019 Kloppenborg Chap One

    18/26

    8 STRATEGIC LEADERSHIP OF PORTFOLIO

    implementation. Te second role is the project core team. Tis team is

    comprised o members who are involved in the project or the entireduration and who help the project manager make decisions and carry out

    tasks. Te third role is that o subject matter experts who are extra hands

    brought on the project as needed.

    Project Success

    Project success has been widely studied and many researchers have pro-

    posed overlapping suggestions o how to measure it. At one time, many

    people viewed project success narrowly as delivering to specifcation, on

    time, and within budget. During the 21st century, many people have dra-

    matically expanded their views on project success. One way o incorpo-

    rating the many suggestions o project success into a useul ramework is

    to group the measures into (1) project management success, (2) business

    results achieved, and (3) operational capability improvements.

    Project Success Measurements

    1. Project management success

    Specifcations

    Cost

    Schedule.

    2. Business results achieved

    Proft

    Market share

    Increased sales New product

    Customer satisaction.

    3. Organizational capability improvements

    Improved customer capability

    Sustainable results

    eam member loyalty

    eam member development

    eam member satisaction

  • 7/30/2019 Kloppenborg Chap One

    19/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 9

    Organizational learning

    New technology and methods.6

    Project management success means delivering exactly what you prom-

    ised on time and within budget. Tis is important, but ar rom the total

    understanding o project success. Projects also contribute toward current

    business results with sales, profts, products, and satisfed customers. Pro-

    jects can urther be envisioned as a means o improving the organizational

    capabilities o the customers and the parent organizations technologies

    and people.

    Current research rom various industries and project types consist-

    ently shows satisying customers is the most important success criterion

    and i that is accomplished, many o the other business results and organi-

    zational capability improvement measures will be realized.7 However, sat-

    isying the customer completely and achieving the project management

    success measures o on time, within budget, and to specifcation do not

    always go together without good project planning and execution.

    Project Life Cycle

    Most researchers and practicing managers use a stage-gate or lie cycle

    model (Figure 1.2) to understand how projects vary rom one point in

    time to another. Te concept o a project lie cycle is that during a given

    stage certain requirements must be met or the project is not allowed to

    pass to the next stage. Many industries have their own specifc lie cycle

    models due to the specifc characteristics projects encounter. For exam-

    ple, construction projects have very dierent demands than research and

    development projects.

    Despite the uniqueness o specifc industries, many people use

    a generic project lie cycle model as a starting point. Te most basic model

    oten includes some sort o initiation to make the project o cial ollowed

    by other stages to plan, execute, and close the project. Project responsi-

    bilities start even beore the initiation stage with selection o the project.

    Responsibilities also extend ater project completion to ensure the prom-

    ised benefts are realized. For this book, we use the model in Figure 1.2

  • 7/30/2019 Kloppenborg Chap One

    20/26

    10 STRATEGIC LEADERSHIP OF PORTFOLIO

    to describe how responsibilities change rom one stage to the next. I all o

    the work is not accomplished, the ow o the project work either returns

    to planning or continues to the execution stage. For many projects, it isimpractical to plan the entire project at the outset; it makes more sense to

    plan and accomplish some work to being with and use the results o the

    early work to help plan uture work.

    The Need for Standards

    Troughout this book, you will see the topic o standards dealt with in

    specifc examples. Here, we talk about the topic o standards in general as

    it applies across the board.

    Te simple question is, why should we have standards and what ben-

    efts do they provide? Clearly, there are processes in your organization

    where you want creativity and innovation to prevail. But there are also

    many processes where doing things dierently or not in the same man-

    ner each time provides no benefts and simply costs you money. Having

    a standard way o doing things in these types o processes makes a lot

    o sense.

    Select project

    Initiate project

    Plan project

    No

    Yes

    Execute project

    Close project

    Leverage benefits

    Are all

    requirements

    planned and

    satisfied?

    Figure 1.2. The project life cycle model.

  • 7/30/2019 Kloppenborg Chap One

    21/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 11

    Example processes or which organizations would preer to have

    a standard way o doing things consistently across the entire organiza-tion are:

    preparing and approving expense reports or business travel,

    processing fnancial transactions,

    taking orders rom customers,

    a stage-gate process or new product and service development,

    reserving conerence rooms, and

    having a common methodology or managing projects, and so

    orth.

    Te above list could go on. Note there are both internally and exter-

    nally developed standards. An internally developed standard involves

    adopting your best practice to how a common process is best executed

    and then reapplying that approach as your standard or this process.

    Te expense report example above could be such an internal standard.

    Adopting an externally developed standard, as the name implies, involves

    researching and selecting a standard that has been developed by a proes-

    sional organization or a vendor. A common example is adopting the PMI

    project management methodology or managing projects.

    Te primary benefts o adopting standards are:

    Standards allow you to leverage scale. I you have operations

    in multiple locations, your people only have to learn one way

    to implement the process.

    Standards also provide a common vocabulary and experienceor your people as they relate to the standardized processes.

    For processes where you use automated/computerized tools,

    using standards means you can have a single tool to buy and

    support.

    In the case o adopting externally developed standards, you

    clearly beneft rom the experience o many peoples use o

    this standard in many dierent types o organizations.

  • 7/30/2019 Kloppenborg Chap One

    22/26

    12 STRATEGIC LEADERSHIP OF PORTFOLIO

    One Size May Not Fit All

    While in many situations standardizing to a single approach may be

    beneicial, there are instances where having one standard will not

    meet the needs o the widely varying work processes in varying busi-

    nesses, markets, or cultures. An example one o the authors (Laning)

    is in the 1990s when Procter & Gamble (P&G) chose to implement

    the Systems, Applications, and Products (SAP) sotware in its global

    supply chains. he initial rollout o global SAP solutions oten had a

    single coniguration/version. We ound that having only one stand-

    ard process or supply chain processes was too restrictive and addedunnecessary costs due to the adoption o a single solution that pro-

    vided much more unctionality than needed in small, simple manu-

    acturing plants. Subsequently, many supply chain processes at P&G

    moved to have three types o solutions (e.g., small, medium, and

    large) versus having only one solution. his allowed the establish-

    ment o standards and the realization o cost beneits in addition to

    enabling the option o having solutions that were appropriate or the

    dierent business situations based on the dierences in their com-

    plexity. his allowed the standards to take into consideration actors

    such as size and complexity o a manuacturing plant, whether the

    business was regulated or nonregulated, and how many SAP modules

    were being implemented in that business. hereore, in some situa-

    tions that vary widely in terms o size and complexity, having a ew

    clearly deined standards versus having only one standard may pro-

    vide great beneits.

    Fostering Creativity Through Control

    A standard approach is like rules and boundaries in a game. All teams

    play on the same court and ollow the same rules. Understanding the

    limits these rules and boundaries impose allows a coach to develop di-

    erent strategies based on the skills o his players and the challenges

    posed by a given opponent. Likewise, standards are like rules and

    boundaries that help everyone understand the normal limits and grant

    thoughtul leaders the chance to use innovative approaches within those

    limits.

  • 7/30/2019 Kloppenborg Chap One

    23/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 13

    Chapter Overviews

    Te next six chapters describe conceptual knowledge and demonstrate

    skills executives will fnd useul in simultaneously achieving each o

    the our sets o competing objectives. Each chapter introduction will

    include the purpose o the chapter, a dilemma aced by the company

    chosen to demonstrate the chapter concepts, and the key question the

    chapter answers. Te body o each chapter varies considerably with

    some including more concepts and others including more techniques.

    Each chapter ends with what the chosen company did to solve its

    dilemma, a summary o how the chapter contributes to enhancing theachievement o the dual sets o objectives, and a set o the top 10

    assessment questions executives can use to determine how well their

    company is currently perorming.

    Te assessment questions in each chapter are a unique eature o this

    book. Teir intent is to highlight the key areas the authors believe you

    need to think about and evaluate or your organization. I this book is

    used in an academic setting, the assessment questions can be used to

    assess a students knowledge o an area.

    Figure 1.3 summarizes the book at a glance.

    Chapter 2 describes a work portolio as the entire body o work an

    organization is doing to best accomplish its goals, subject to the limits

    o resources and its tolerance or risk. Ten the components o porto-

    lio management are described and a method or accomplishing them

    Managing a portfolio

    to implement

    strategy (chapter 2)

    Sponsoring

    successful projects

    (chapter 3)

    Making data-based

    decisions (chapter 7)

    Leading project

    managers

    (chapter 4)

    Understanding IT

    opportunities and

    challenges (chapter 6)

    Listening to customers,

    employees, and

    processes (chapter 5)

    Competingobjectives to

    achieve:

    1. Executive vs.

    Manager

    2. Capability vs.

    Results

    3. Projects vs.

    Operations

    4. Function vs.

    Function

    Figure 1.3. Overview of the book.

  • 7/30/2019 Kloppenborg Chap One

    24/26

    14 STRATEGIC LEADERSHIP OF PORTFOLIO

    is detailed. Te components include identiying, selecting, prioritizing,

    resourcing, and governing the organizations work. Te leadership teamoten collectively makes the portolio decisions.

    Chapter 3 defnes the role an executive serving as a sponsor when

    she wants a manager and a team to lead a project that will create some-

    thing she values. Te overarching responsibilities o a sponsor are to

    provide resources, oversee stakeholders, and deliver results. Te chapter

    also details the ew select behaviors busy executive sponsors can per-

    orm at each stage o a project to enhance the probability o project

    success.

    Chapter 4 describes the role o the project executivethat is, directly

    supervising a project manager. Te responsibilities o a project manager are

    described so that an executive can understand the dierent roles a project

    manager plays compared with the roles played by a unctional manager.

    Te remainder o the chapter deals with specifc task and coaching respon-

    sibilities o a project executive at each stage o the project lie cycle.

    Chapter 5 describes how the CPO can use quality approaches when

    implementing strategy through projects. Tese concepts guide an execu-

    tive who is responsible or developing project management competencyand acilitate the leadership team as they make portolio decisions.

    Tis executive needs to incorporate input rom customers, employees,

    and processes.

    Chapter 6 explains the basics o what I is and what it makes pos-

    sible. Te chapter also shows how the CIO works with other executives

    to defne a strategic I master plan that implements the business strategy.

    Te chapter concludes with best practices on when and how to use I

    consultants and I vendor companies.

    Chapter 7 makes the case or the analysis o both quantitative and

    qualitative data in making decisions within your organization. Te chap-

    ter provides guidance to all executives regarding how to defne and col-

    lect clean and useul data. Te chapter then concisely takes you through a

    careul selection o simple yet powerul analysis techniques to use within

    your organization to make better decisions that have more impact.

    Chapter 8 highlights the key learnings we want you to take away

    rom each chapter. We then give you specifc ideas o how to apply what

    you have learned in a call to action or your organization.

  • 7/30/2019 Kloppenborg Chap One

    25/26

    IMPLEMENTING STRATEGY THROUGH PORTFOLIOS 15

    Te appendixes in this book are intended or readers who need to

    master the undamentals o an area and do not have su cient knowledgeor experience in the area. For example, Appendix B is intended or read-

    ers who have little understanding o the basics o I and need to get up

    to speed on topics such as hardware, sotware, telecommunications, and

    databases. Appendixes are included in chapters 5, 6, and 7.