35
Kinnickinnic River Flood Management and Watercourse Rehabilitation Achieving Multiple Design Objectives Thomas R. Sear, PE, CFM Short Elliott Hendrickson Patrick C. Elliott, MMSD

Kinnickinnic River Flood Management and Watercourse Rehabilitation

  • Upload
    wafscm

  • View
    1.167

  • Download
    0

Embed Size (px)

DESCRIPTION

Kinnickinnic River Flood Management and Watercourse Rehabilitation - Tom Sear, SEHNov 2010

Citation preview

Page 1: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Kinnickinnic River Flood Management and

Watercourse RehabilitationAchieving Multiple Design Objectives

Thomas R. Sear, PE, CFMShort Elliott Hendrickson

Patrick C. Elliott, MMSD

Page 2: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Kinnickinnic River (KKR) Watershed

KKR S. 6th St. to I-94 Bridge

Project Location

Page 3: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Updated Floodplain(SEWRPC, 2008)

6th St Bridge

Page 4: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR FM S. 6th St. to I-94 BridgeProject Area Characteristics

• South 6th Street Bridge • Upstream Watercourse Segment

– 500 feet of concrete lined channel– Confined cross-Sections– Steep northern embankment– MMSD CSO Facility on south

• Downstream Watercourse Segment– 500 feet of earthen / rock lined channel– Eroded north embankment, south of 5th Street– Heavily vegetated north embankment– South embankment instability

Page 5: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR FM Project Limits

Downstream WC Segment

Sout

h 6t

hSt

reet

Kinnickinnic River

Sout

h 5t

h St

reet

Brid

ge

Page 6: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR FM Project Limits

Downstream WC Segment

Sout

h 6t

hSt

reet

Kinnickinnic River

Sout

h 5t

h St

reet

Brid

ge

Page 7: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR 6th St. Bridge – Upstream (West Side)

Page 8: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR 6th St. Bridge – Downstream (East Side)

Page 9: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Upstream Watercourse Segment

• Concrete Lined Channel– Constructed in 1983– 500 ft. length, 2:1 side slopes– 60 ft top width, 24 ft bottom width

• Northern Embankment– Buried (300 ft. long) WPA Wall– Railroad trestle remnants– Steep and unstable side slopes

• Southern Embankment– Maintenance Ramp– MMSD CSO facility and outfall

Page 10: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Upstream Watercourse Segment

MMSD KK1 FacilityCombined

Sewer Outfall

Maintenance Ramp

South 6th Street

Unstable Embankment with Sand and

Gravel Fill Material

End of Concrete

Lined Channel

Page 11: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Upstream Watercourse Segment

MMSD CSO Control Facility

Combined Sewer OutfallMaintenance

Ramp

Unstable Embankment with Sand and

Gravel Fill Material

Page 12: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Upstream Watercourse Segment

Page 13: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Upstream Watercourse Segment

Page 14: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream of South 6th Street BridgeJune 7, 1961

Page 15: Kinnickinnic River Flood Management and Watercourse Rehabilitation

WPA Revetment Wall Buried in 1983

Page 16: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Existing KKR Concrete Lined ChannelConstructed 1983

Buried WPA Revetment

Wall

WPA Wall Weep Hole

Combined Sewer Outfall

84” Diameter RCP Storm

Sewer Outfall

Page 17: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Existing KKR Concrete Lined Channel and Buried WPA Revetment Wall, 1983

Buried WPA Revetment

Wall

Approx. 15 ft

WPA Wall Weep Hole

24 feet18 feet 18 feet

Page 18: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Watercourse Segment• Earthen / Rock Lined Channel

– 500 ft. length– Channel scour and deposition – Embankment erosion– Storm sewer outfalls

• Northern Embankment– Failing Gabion Structure– Embankment erosion south of 5th Street– Vegetated riparian areas

• Southern Embankment– Steep / unstable side slopes– Collapsing stone revetment walls– Exposed watercourse flushing pipeline

Page 19: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Watercourse Segment

KKR Earthen / Rock Lined Channel

Steep and Unstable Side

Slopes

Eroded Side Slope due to 5th Street Runoff

Failing Revetment Wall

End of Concrete Lined Channel

Storm Sewer Outfalls

Storm Sewer Outfall

Exposed Abandoned Flushing Pipeline

Page 20: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Watercourse Segment

Steep and Unstable Side

Slopes

Eroded Side Slope due to 5th Street Runoff

Failing Revetment Wall

Storm Sewer Outfalls

Storm Sewer Outfall

Exposed Abandoned Flushing Pipeline

KKR Earthen / Rock Lined Channel

Page 21: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Watercourse Segment

Page 22: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Watercourse Segment

Page 23: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Stakeholder Involvement

• KK River Neighborhood Plan– Plan for overall KK River Flood Management

Project– Coordination with local government agencies

and community groups– Successfully accommodated various design

requests from stakeholders • Public Meetings

Page 24: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Proposed Improvements KKR S. 6th Street Bridge

• Design Objectives– Significantly reduce upstream WSE’s– Maintenance / bike path beneath bridge

• Proposed Design Features– Clear span concrete girder bridge– Functional, durable and attractive bridge

• Final Design Complete– Currently Under Construction– Scheduled for Completion in Dec. 2010

Page 25: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Proposed Bridge

Page 26: Kinnickinnic River Flood Management and Watercourse Rehabilitation

11-02-10 Bridge Construction

Page 27: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Proposed Improvements KKR Upstream Watercourse Segment

• Design Objectives– Rehabilitated Main Channel– Maintain stable side slopes / hydraulic capacity– Maintenance / bike path alignment

• Design Features– Realigned channel centerline– Stone lined channel with riffles and pools– Tiered retaining walls, both sides– Recycle WPA wall limestone blocks– 15 ft. wide maintenance / bike path

Page 28: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Upstream KKR Improvements

Minimum 2:1 Side Slopes

Future KKR Bike Trail

Retaining Walls

Page 29: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Upstream KKR Cross-Sections

Page 30: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Proposed Improvements KKR Downstream Watercourse Segment• Design Goals

– Rehabilitated main channel and floodplain– Stable embankment slopes– Native vegetation plantings– Promote watercourse sediment continuity

• Design Features– Stone lined channel with riffles and pools– 2:1 to 4:1 native vegetated side slopes– Reuse of limestone blocks / streambed stone– 15 ft. wide maintenance / bike path

Page 31: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Downstream KKR Improvements

Future KKR Bike Path

3:1 Side Slope, where space

allows

Five Pools within Main Channel

Repair erosion from 5th St.

runoff

Page 32: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Downstream Cross-Section

Typical Riffle Section

Page 33: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Main Channel Cross-Sections

Typical Pool Section

Page 34: Kinnickinnic River Flood Management and Watercourse Rehabilitation

KKR Watercourse Rehabilitation Improvements Schedule

• Advertisement – May 2010• Construction Start – Oct. 2010• Construction Completion – Dec. 2011• Upstream Improvements

– Finishing Preliminary Engineering– Starting Home Acquisition/Deconstruction

Page 35: Kinnickinnic River Flood Management and Watercourse Rehabilitation

Kinnickinnic River Project Team Acknowledgements

• Dale Miller, Mainstream Restoration

• Rose Chmielewski, Ecological Services of Milwaukee

• Doug Bath, Gestra Engineering