Kennewick School DistrictDaily Report: Eastgate Elementary
Specializing in Projects that Make a Difference®
PROJECT TEAM
Kennewick School District 1000 4th Ave.
Kennewick, WA 99336 (509) 222-7667
www.ksd.org Doug Carl
Director of Capital Projects
Madsen Mitchell Evenson and Conrad, PLLC
8905 West Gage, Ste 200 Kennewick, WA 99336
(509) 396-7278 www.madmitch.com
Doug Mitchell, AIA, LEED AP Project Architect
Joe Hampton Project Manager
Leone & Kebble Contractor
108 West Boone Spokane, WA 99201
(509) 327-4451 www.leone-keeble.com
Tom Mercer Project Manager
Carl Clausen Superintendent
Strategic Construction Management, Inc.
3601 North 20th Pasco, WA 99301 (509) 737-0072
www.strategic-cm.com David L. Robison, CCM, LEED AP
Owner’s Representative
CONSTRUCTION ACTIVITY OBSERVED Report No.: 040114-01
SEPTEMBER 12, 2014 VOL. 1 n ISSUE 78
Kennewick Elementary Improvement ProgramPrepared By: V. Guzman
Weather: 71° SunnyWind Speed: 7 mph
Humidity: 29%Precipitation: 0.00 in.
Electrical floor boxes and conduit runs for future plugs, switches, and data cabling are being installed at all required locations.
Preparation and compaction of the base rock continues at another section of the school’s flooring.
The concrete mow strip is being installed at the school’s new permanent fence.
Completion of the underground utilities leads to site development and grading around the school.
The installation of the main water line into the school is being pressure tested prior to the continuance of the plumbing requirement.