1
Kennewick School District Daily Report: Eastgate Elementary Specializing in Projects that Make a Difference® PROJECT TEAM Kennewick School District 1000 4th Ave. Kennewick, WA 99336 (509) 222-7667 www.ksd.org Doug Carl Director of Capital Projects Madsen Mitchell Evenson and Conrad, PLLC 8905 West Gage, Ste 200 Kennewick, WA 99336 (509) 396-7278 www.madmitch.com Doug Mitchell, AIA, LEED AP Project Architect Joe Hampton Project Manager Leone & Kebble Contractor 108 West Boone Spokane, WA 99201 (509) 327-4451 www.leone-keeble.com Tom Mercer Project Manager Carl Clausen Superintendent Strategic Construcon Management, Inc. 3601 North 20th Pasco, WA 99301 (509) 737-0072 www.strategic-cm.com David L. Robison, CCM, LEED AP Owner’s Representave CONSTRUCTION ACTIVITY OBSERVED Report No.: 040114-01 SEPTEMBER 12, 2014 VOL. 1 n ISSUE 78 Kennewick Elementary Improvement Program Prepared By: V. Guzman Weather: 71° Sunny Wind Speed: 7 mph Humidity: 29% Precipitaon: 0.00 in. Electrical floor boxes and conduit runs for future plugs, switches, and data cabling are being installed at all required locaons. Preparaon and compacon of the base rock connues at another secon of the school’s flooring. The concrete mow strip is being installed at the school’s new permanent fence. Compleon of the underground ulies leads to site development and grading around the school. The installaon of the main water line into the school is being pressure tested prior to the connuance of the plumbing requirement.

Kennewick School District...SEPTEMBER 12, 2014 VOL. 1 n ISSUE 78 Kennewick Elementary Improvement Program Prepared By: V. Guzman Weather: 71° Sunny Wind Speed: 7 mph Humidity: 29%

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Kennewick School District...SEPTEMBER 12, 2014 VOL. 1 n ISSUE 78 Kennewick Elementary Improvement Program Prepared By: V. Guzman Weather: 71° Sunny Wind Speed: 7 mph Humidity: 29%

Kennewick School DistrictDaily Report: Eastgate Elementary

Specializing in Projects that Make a Difference®

PROJECT TEAM

Kennewick School District 1000 4th Ave.

Kennewick, WA 99336 (509) 222-7667

www.ksd.org Doug Carl

Director of Capital Projects

Madsen Mitchell Evenson and Conrad, PLLC

8905 West Gage, Ste 200 Kennewick, WA 99336

(509) 396-7278 www.madmitch.com

Doug Mitchell, AIA, LEED AP Project Architect

Joe Hampton Project Manager

Leone & Kebble Contractor

108 West Boone Spokane, WA 99201

(509) 327-4451 www.leone-keeble.com

Tom Mercer Project Manager

Carl Clausen Superintendent

Strategic Construction Management, Inc.

3601 North 20th Pasco, WA 99301 (509) 737-0072

www.strategic-cm.com David L. Robison, CCM, LEED AP

Owner’s Representative

CONSTRUCTION ACTIVITY OBSERVED Report No.: 040114-01

SEPTEMBER 12, 2014 VOL. 1 n ISSUE 78

Kennewick Elementary Improvement ProgramPrepared By: V. Guzman

Weather: 71° SunnyWind Speed: 7 mph

Humidity: 29%Precipitation: 0.00 in.

Electrical floor boxes and conduit runs for future plugs, switches, and data cabling are being installed at all required locations.

Preparation and compaction of the base rock continues at another section of the school’s flooring.

The concrete mow strip is being installed at the school’s new permanent fence.

Completion of the underground utilities leads to site development and grading around the school.

The installation of the main water line into the school is being pressure tested prior to the continuance of the plumbing requirement.