Upload
bradyn-newson
View
224
Download
2
Embed Size (px)
Citation preview
Ken Jacobs
Airport Planning & Environmental Division
March 3, 2010
Federal AviationAdministrationFederal AviationAdministration
33rd Annual Airports Conference
Hershey, PA
Airports Safety Management System
Integrating Planning Integrating Planning Into the ProcessInto the Process
2Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Safety Management System– SMS
• A process for achieving acceptable levels of safety risk*• Elements
– Policy• Commitment• Boundaries
– Safety Risk Management• Analyze Risk• Control Risks (mitigate)• Accept Risks• System Changes
– Assurance• System performance• Hazard identification
– Promotion• Communication, outreach, culture and human resources
* FAA Order 8000.369, Safety Management System Guidance
* FAA Order 8000.369, Safety Management System Guidance
SMS is a quality process that provides
feedback for continuous
improvement
SMS is a quality process that provides
feedback for continuous
improvement
3Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Safety Risk Management– SRM • Describe the System
– Mission– Human– Machine– Management– Media or Environment
• Identify Hazards– What can go wrong– Causes– System State– Effect
• Analyze Risks– Existing controls– Severity– Likelihood
• Assess Risks– Single point failure– Common cause failure– Risk acceptability– high,
medium, or low
• Treat Risks– Mitigation – Avoidance– Transfer– Assumption– Control– Implementation and
monitoring
Infrastructure
4Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Airport Planning
• Existing Conditions Inventory
• Aviation Forecasts
• Facility Requirements
• Alternatives Development and Evaluation
• Airport Layout Plan
• Project Selection and Implementation– Project sequencing and master schedule
– Environmental review
– Financing
– (Safety assessment and acceptance)
Airport Planning SRM A Process For Satisfying Long-term Aeronautical Demand
A Process For Satisfying Long-term Aeronautical Demand
5Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Airport Planning SRM Context
Airport Process (SMS)
FAA ATO SMSFAA ATO SMS
FAA ARP SMS (TBD)
FAA ARP SMS (TBD)
Airport Planning Airport Planning SRMSRM
6Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
System Infrastructure and Operations• Infrastructure and Operations
– Infrastructure can (almost always) be operated in a safe manner
– Therefore, system operations ultimately determine system safety.
• SMS balances operational production and safety– Therefore, airport infrastructure must provide for a safe operation that
meets aeronautical demands
– Airport production can be measured in terms of system capacity, efficiency and utility
• Infrastructure– Provided by the Airport, ATO Tech Ops– Approved and funded by ARP
• Operations– Provided by…– Flight Operations: Air Traffic (ATO), Flight Standards, etc
– Airport Operations: Airport
– Aircraft Operations: Pilot
Airport Planning
7Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Time Line
-Infrastructure
-Operations
Decision
Level
New operations beginNew operations begin
Planning… Construction…
Planning Process Decisions
8Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Planning Process and SRM
Plan
Construct
Design
Operate
Complete SRM
*Planning Safety Assessment)*Planning Safety Assessment)
Start SRM*
9Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Planning Safety Assessment
• Develop Alternatives• Preliminary Hazard Identification & Risk Assessment• Modification of Standards• Identify Potential Limitations
– Aircraft– Taxiways– Runways– Procedures– Capacity
• Establish Efficiency, Capacity and Utility Targets
10Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
SRM in PlanningMaster Planning
Form Advisory Committee
Inventory
Aviation Forecasts
Demand/ Capacity Analysis
Facility Requirements
Alternatives Analysis
SRM Planning Analysis Occurs Here
Environmental Overview
Airport Layout Plans (ALP)
Financial/ Feasibility Analysis
FAA Approval of Forecasts and ALP
11Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
SRM in EnvironmentalEnvironmental Assessment Environmental Impact Statement
Form Advisory Committee Form Advisory Committee and Public Outreach/Participation Program
Scoping Scoping
Purpose and Need Purpose and Need
Proposed Action Proposed Action
Alternatives Development Alternatives Development
Analysis/ Refinement Analysis/ Refinement
SRM Planning Analysis Occurs Here SRM Planning Analysis Occurs Here
Affected Environment Affected Environment
Environmental Consequences Environmental Consequences
Draft EA Draft EIS
Public Hearings Public Hearings
Public Review Period Public Review Period
Final EA Final EIS
FAA APPROVES by Issuing Finding or No Significant Impact (FONSI) FAA APPROVES by Issuing Record of Decision (ROD)
12Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
SRM in Design and ConstructionDesign Construction
Pre-Design Conference Airport Sponsor Prepares Grant Application Based on Construction Cost Estimate
Airport Sponsor Prepares Grant Application for Design FAA Awards Grant
FAA Awards Grant Advertise for Bids from Contractors
Prepare 30% Plans & Specs Award contractor with the lowest most responsive bid
Airport Sponsor/FAA/State Review Pre-Construction Conference with stake holders
Prepare 60% Plans & Specs SRM Analysis occurs at this stage
Airport Sponsor/FAA/State Review Construction Begins
Prepare 90% Plans & Specs Construction Completed
SRM Analysis Occurs at this stage FAA/State/Airport Sponsor Initial Final Inspection/Punch List
Airport Sponsor/FAA/State Review Contractor Completes Work
Prepare 100% Plans & Specs, Safety Phasing Plan(s) and Construction Cost Estimate . i.e. Construction
DocumentsFAA/State/Airport Sponsor Conduct Final Inspection
FAA/State/Airport Sponsor Accepts Work and Approves
Airport Sponsor Updates ALP to Reflect Changes to Airport
13Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Concurrent Planning…
• Begin with the end in mind– operational benefits for the aviation system
• Initial planning must include safety as well as other considerations
• Assemble a complete complement of stakeholders, including operations safety
• Capture and apply critical safety decisions to each subsequent phase of the airport planning and development process
SRM Benchmarks for Airport Planning SRM Benchmarks for Airport Planning
14Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Implementation Studies
• What– Incorporate SRM into the airport planning and development process– Master Planning and ALP
Approval
– Environmental Review
– Modification of Standards
– Construction Safety Phasing
• How– Test various SRM approaches to the planning/development process – ATO SRM
– Airport SRM
– ARP Contractor SRM
– Passive
– Case studies
• FAA Team Effort
• Interview Participants
• Identify Lessons Learned and Best Practices
• Apply to SRM Guidance
• FAA Team Effort
• Interview Participants
• Identify Lessons Learned and Best Practices
• Apply to SRM Guidance
15Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
SRM Approaches• ATO SRM
SRM panel facilitated by ATO. Expand the current ATO role and require more involvement from ARP to address the entire airfield, including proposed development and the associated airspace.
• Airport SRM Airport sponsor hires a safety consultant to perform a safety assessment. Readily funded by the Airport Improvement Program (AIP). Airport sponsor has direct control over airport safety operations during and after construction.
• ARP Contractor SRMSRM panel facilitated by the ARP SMS support contractor. Can effectively leverage the outcomes for ARP guidance.
• PassivePassive participation in the planning process. Observe and propose how a new SRM process could be incorporated into existing planning process steps. Minimal impact on the existing planning process.
• Case studies Review outcomes and interview participants of completed ATO SRM processes
16Federal AviationAdministrationMarch 2010 33rd Annual Airports Conference
Thanks for Your Time…Now…