66
1 KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION LIMITED PÀ£ÁðlPÀ ¸ËgÀ «zÀÄåvïC©üªÀÈ¢Þ ¤UÀ ªÀÄ ¤AiÀÄ«ÄvÀ Replies against Queries sought by prospective bidders in respect of bid enquiry no. KSPDCL/SP/F-29/2015-16/02 dated 09-12-2015 for establishing 8 nos. of 220/66kV stations along with connected transmission lines for evacuating power from 2000MW Pavagada Solar Park. Query sought KSPDCL Reply Many of the Bidders requested clarity on Vol 1- Commercial requirements vis-a-vis VolI and Vol III Modified Vol 1- Commercial requirements along with Vol II and Vol III including all amendment/corrigenda are being uploaded along with these queries to have more clarity. Bidders are requested to upload Vol III Techno-commercial sheets and price sheets which are hosted along with these queries duly ignoring the price sheets and techno-commercial sheets previously hosted. Please inform whether Employer issues concessional Form C for the materials being bought outside from Karnataka Clause PC14.3, Section VIII, particular conditions page 3-97 states that “Employer will give only necessary certificates in terms of such notifications as per information given by the bidder in declaration form”. Modified Vol 1- Commercial

KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

1

KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION LIMITED PÀ£ÁðlPÀ ¸ËgÀ «zÀÄåvïC©üªÀÈ¢Þ ¤UÀªÀÄ ¤AiÀÄ«ÄvÀ

Replies against Queries sought by prospective bidders in respect of bid enquiry no. KSPDCL/SP/F-29/2015-16/02 dated

09-12-2015 for establishing 8 nos. of 220/66kV stations along with connected transmission lines for evacuating power

from 2000MW Pavagada Solar Park.

Query sought KSPDCL Reply

Many of the Bidders requested clarity on Vol 1-

Commercial requirements vis-a-vis VolI and Vol III

Modified Vol 1- Commercial

requirements along with Vol II

and Vol III including all

amendment/corrigenda are

being uploaded along with these

queries to have more clarity.

Bidders are requested to upload

Vol III Techno-commercial sheets

and price sheets which are

hosted along with these queries

duly ignoring the price sheets and

techno-commercial sheets

previously hosted.

Please inform whether Employer issues concessional

Form C for the materials being bought outside from

Karnataka

Clause PC14.3, Section VIII,

particular conditions page 3-97

states that “Employer will give

only necessary certificates in

terms of such notifications as per

information given by the bidder in

declaration form”.

Modified Vol 1- Commercial

Page 2: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

2

requirements has been

uploaded.

A3 Isolators in BOQ Sheet in Price Sheets

66kV Isolator Quantity is missing

We presume that 66kV Isolator description ( II) is missing

and are listed under 110kV Isolators (I). We presume

that first four S.No. (1 to 4) under Item No.(I) is for 220kV

Isolators and next four S.No. (1 to 4) under Item No.(I) is

for 66kV Isolators. Also kindly provide us the mounting

height of under hung isolator ( 12 Nos, last item in

Isolator BOQ).Kindly confirm

Corrigendum has been issued to

that effect on 21-01-2016.

Corrigendum has been issued to

that effect on 21-01-2016.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III

TL BOQ Sheets

In Price Sheets In the absence of route survey, per km

rates are given by you for Transmission Line

We would like to inform you that there is no provision to

enter our value against your requirement. Hence we

request you to revise the sheet to quote our rates and

also request you to kindly inform about the way of

Billing the same to you during execution

BOQ Sheets for techno

commercial opening for Lot 1 has

been uploaded in corrigendum

on 21-01-2016 as Annexure 13.

BOQ Sheets for cost opening for

Lot 1 has been uploaded in

corrigendum on 21-01-2016 as

Annexure 14.

BOQ Sheets for techno

commercial opening for Lot 2 has

been uploaded in corrigendum

on 21-01-2016 as Annexure 15.

BOQ Sheets for cost opening for

Lot 2 has been uploaded in

corrigendum on 21-01-2016 as

Annexure 16.

Modified price sheets and techno

Page 3: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

3

commercial sheets uploaded

vide Vol III.

BOQ Sheets in Price Sheets

In Column 3a of all BOQ schedules, the quantities are

mentioned for one Substation.

We request your confirmation that we should quote for

each Lot (Column 4a) by multiplying for the quantity in

3a by number of stations.

Suitable modification has been

effected through corrigendum on

21-01-2016.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Schedule 21 Materials sourced from Karnataka

Please inform the necessity for this information. Also,

what will be the impact, incase, we now identifies the

items source outside Karnataka and during execution

sourced at Karnataka.

In case of any statutory variation

in taxes/duties/levies or if any

tax/duty/levy is newly introduced

by the Government applicable

for this Contract with effect from

the next day of the date of

submission of the bid these

variations/additional

taxes/duties/levies will be to the

account of the owner. In case

the Bidders indicate lesser rates of

taxes and duties with reference

to the prevailing rates of taxes

and duties at the time of bidding

any variations in the taxes and

duties would be paid/recovered

keeping the rates of taxes and

duties applicable as on the date

of bid opening as the base and

not the quoted rates of taxes and

duties for payment/recovery of

difference in the taxes and

Page 4: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

4

duties. If the Contractor is

required to pay additional tax or

duty, then the owner shall

reimburse the Contractor the

additional tax or duty so paid by

the contractor against submission

of documentary evidence to the

satisfaction of the owner by the

contractor. This provision will not

be applicable to transaction

between the contractor and his

sub-suppliers, sub-contractors for

raw materials, for „bought out‟

items etc., and will be applicable

only for the „own/direct

transactions‟ between the

contractor and the owner for the

materials supplied from his own

manufacturing units and erection

and civil works.

Modified Vol 1- Commercial

requirements has been

uploaded.

Schedule 13 Optional Spares

Please inform whether this optional spares price shall be

taken for evaluation.

Modified Vol 1- Commercial

requirements has been

uploaded.

Schedule 12 Type test charges: In case of availability of valid type

test reports with OEMs, then we don't have to quote

Type tests conducted in the past

5 years are considered for supply

Page 5: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

5

type test charges. Please confirm. in accordance with clause 13.3

and 13.4 of Vol IIA (2 of 3).

Schedule 4 Mandatory Spares: KSPDCL indicated the items / qty to

be supplied in this price schedule. Hope, we need to

consider the same qty for Lot I and Lot II.

Same has been clarified in the

corrigendum, wherein it is stated

that one set will be considered

while placing order for all the 8

stations under Lot 1 & Lot 2.

However, for evaluation purpose

the rates quoted by the

prospective bidders shall be

considered for all the 8 stations.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Schedule -2 (1 of 2) As per Km rate is given by KSPDCL for Transmission line,

please guide to fill in this schedule.

BOQ Sheets for techno

commercial opening for Lot 1 has

been uploaded in corrigendum

as Annexure 13.

BOQ Sheets for cost opening for

Lot 1 has been uploaded in

corrigendum as Annexure 14.

BOQ Sheets for techno

commercial opening for Lot 2 has

been uploaded in corrigendum

as Annexure 15.

BOQ Sheets for cost opening for

Lot 2 has been uploaded in

corrigendum as Annexure 16.

Page 6: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

6

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Schedule 3A(i), 3B(i), 3B(iii), Supply, Erection, Civil for Transmission line: In the

absence of detailed survey, the approx cost for 220KV

SC TL works out to Rs. 55 L / km and 1 Cr / Km for MC

Line.

Please confirm whether this rate includes Supply, Civil

and erection works. Please inform the type of soil, No.

of towers considered. In case, if our estimation varies

from this rate, please inform the ways to indicate the

difference. Also, please inform the method of

evaluation.

BOQ Sheets for techno

commercial opening for Lot 1 has

been uploaded in corrigendum

as Annexure 13.

BOQ Sheets for cost opening for

Lot 1 has been uploaded in

corrigendum as Annexure 14.

BOQ Sheets for techno

commercial opening for Lot 2 has

been uploaded in corrigendum

as Annexure 15.

BOQ Sheets for cost opening for

Lot 2 has been uploaded in

corrigendum as Annexure 16.

Provisional tower schedule for

transmission line is provided. Work

is to be executed after availing

approved tower schedule.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Schedule 3B(II) Civil: KSPDCL indicates "Zero" qty per station for few

items like Site levelling, Filling, Cable trench, Retaining

Details have been provided in

the corrigendum uploaded,

Page 7: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

7

wall etc.,

If so, please inform whether these items / scope are not

required to be executed at 8 Substation locations. In

case of requirement or to be executed, request you to

provide contour drawing for 8 locations.

wherein provision for 4 stations in

each lot has been made.

Provisional design of switchyard

layout is provided. Work is to be

executed after availing

approved drawings.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Price Schedule - Supply, Mandatory Spares: Format

gives provision to give breakup for Ex-works, duties and

taxes.

Please inform whether for bought out items, duties &

taxes to be included in Exworks price.

In case of any statutory variation

in taxes/duties/levies or if any

tax/duty/levy is newly introduced

by the Government applicable

for this Contract with effect from

the next day of the date of

submission of the bid these

variations/additional

taxes/duties/levies will be to the

account of the owner. In case

the Bidders indicate lesser rates of

taxes and duties with reference

to the prevailing rates of taxes

and duties at the time of bidding

any variations in the taxes and

duties would be paid/recovered

keeping the rates of taxes and

duties applicable as on the date

of bid opening as the base and

not the quoted rates of taxes and

duties for payment/recovery of

difference in the taxes and

duties. If the Contractor is

Page 8: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

8

required to pay additional tax or

duty, then the owner shall

reimburse the Contractor the

additional tax or duty so paid by

the contractor against submission

of documentary evidence to the

satisfaction of the owner by the

contractor. This provision will not

be applicable to transaction

between the contractor and his

sub-suppliers, sub-contractors for

raw materials, for „bought out‟

items etc., and will be applicable

only for the „own/direct

transactions‟ between the

contractor and the owner for the

materials supplied from his own

manufacturing units and erection

and civil works.

Modified Vol 1- Commercial

requirements has been

uploaded.

Price Schedule - Supply &Civil, Spares: KSPDCL furnished

the items to be operated in this price schedule with

quantity per station.

We understand that the contract is on "Item rate basis".

Please confirm.

Quantity / station need to be

multiplied by 4 while indicating

quantity for either of lots.

The contract is on Lot wise basis

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Page 9: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

9

Vol IIA 1 of 3, page 12 of 14 Altitude up to 1500Mtr

Please inform individual Substation wise altitude so that

we consider the equipment accordingly, as the

equipment price varies with Altitude above 1000 m

from Mean Sea Level

For all the proposed 8 stations,

the details provided in Vol IIA 1 of

3, page 12 of 14 are same.

Vol IIA 1 of 3, page 10 of 14 The contractor shall make his own arrangements for

electrical power required for construction purposes as

well as for its staff labour colony.

We request KSPDCL to provide construction power at

one point at each of the substation and the actual

consumption charges shall be deducted in our bills.

Yes.

Arranging construction power for

each of the substation shall be

the responsibility of the

Contractor. KSPDCL shall not be

responsible for arranging

construction power.

Vol IIA 1 of 3, page 9 of 14 Soil Investigation Report if available may be obtained

from the Chief Executive Officer, KSPDCL.

Please provide us the Soil investigation report for the 8

Substation locations

Preliminary Geo Technical study

in respect of location of each of

the station is uploaded. However,

the successful bidder needs to

conduct geo-technical

investigation before taking up of

design of various structures.

GC, 42.1.1, page 69 The Employer may at any time terminate the Contract

for any reason by giving the Contractor a notice of

termination.

We request you to include the cluase as below:-

The Employer after having mutual consent with

contractor may at any time terminate the Contract for

any reason by giving the Contractor a notice of

As the termination of the contract

is effected for non performance

of the obligations by the bidder,

the request of the bidder for

mutual consent cannot be

considered.

Modified Vol 1- Commercial

Page 10: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

10

termination. requirements has been

uploaded.

GC, 40, page 66 We request you to include the following clause:-

In case the Contractor's performance is delayed due

to any default on the part of the owner/employer or

their authorized agents, then Contractor shall be given

due extension of time for the completion of the Works,

to the extent such omission on the part of the

owner/employer has caused delay in the Contractor's

performance of the contract. Contractor shall be

granted appropriate cost compensation along with

time extension.

Since the contract is on total turn

keybasis , it is the responsibility of

the contractor for execution of

the work in toto within the

prescribed time frame. As such,

no such eventualities as

envisaged by bidder shall

encounter while execution of the

work.

Modified Vol 1- Commercial

requirements has been

uploaded.

Appendix-6 Scope of Works and Supply by the Employer

All Equipment/Materials and personnel as described

herein will be provided by the Purchaser in good time

so as not to delay the performance of the Contractor,

in accordance with the approved Time Schedule.

Please provide us the schedule of handing over of site

for the execution and also the status of ROW.

Further, we request in case there is delay in handing

over of site to the contractor then the contractor

should be entitled to cost as well as Extension of time.

As the premises of station

locations are within the solar

park, the question of ROW does

not arise.

Tentative schedule of handing

over of site: April 2016.

It is proposed to hand over the

site to bidder by April 2016. As

such, no time overrun and cost

overrun are envisaged.

Modified Vol 1- Commercial

Page 11: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

11

requirements has been

uploaded.

Appendix-1 Terms and Procedures of Payment

We hope the advance payment is interest free.

Ten percent (10%) of the amount

as an advance payment shall be

made by the employer against

receipt of invoice, and an

irrevocable advance payment

security for the equivalent

amount made out in favor of the

Employer.

The advance payment shall be

interest free.

ITB, Clause 7.2, page 1 Officer contact details

We plan to visit the site and carry out walk out survey

for the proposed lines. Please provide us the officer

details to be contacted at site and TL preliminary

survey reports. Please inform whether all 4 locations,

land acquisition is completed.

Sri. Nagaraju, AGM(Field),

07899915814

KSPDCL, Bengaluru.

Lease Agreements with the land

owners are proposed to be

completed by the time LOA is

issued to the successful bidder.

4.ITB & BDS: We request you to allow price variation since the

project duration is 360 days for Lot I and 540 days for

Lot II from the Effective Date.

The commissioning period for

both the Lots is 12 months from

the date of Letter of Award/ Letter

of Intent (as applicable) including

Monsoon period.

Contract Price Adjustment:

The Prices, only for the following

items, quoted by the Bidder shall

Page 12: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

12

be VARIABLE in accordance with

the relevant IEEMA/CACMAI

Price Variation Formula and

Indices without ceiling during the

contractual delivery period. Price

Variation is not admissible for

other Items. The base date

applicable for Price Variation is

the date of Tendering i.e., date

of Techno-Commercial Bid

Submission date as notified

(either original or extended) as

per IEEMA/ CACMAI Circulars:

I Equipments / Materials :

1) Power Transformers

2) Circuit Breakers /

Switchgears.

3) Conductors & Ground

Wires.

4) Lightning Arresters.

5) Transformer Oil.

6) Tower Parts, equipment

mounting/Station

Structures.

7) Control Cables.

8) HT UG Cables

9) Conductor Hardware.

10) Battery & Battery Chargers.

11) Instrument Transformers.

12) Insulators

Page 13: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

13

II. In respect of above Electrical

goods covered under works

contract / procurement shall be

in accordance with the relevant

IEEMA / CACMAI Price Variation

formulae and indices.

III. In respect of Turnkey Projects

involving Civil Works and Erection

Portion shall be as per relevant

Formulae as evolved by IEEMA.

However, as far as admissibility of

price variation towards erection

and civil works is concerned, the

same would be restricted to

below appended activities only.

a) Concreting (With or without

steel reinforcement)

b) Steel reinforcement and

structural steel.

c) Any other civil works where

rates are individually/

independently indicated for

concreting (with or without

reinforcement) and Steel

reinforcement and structural

steel.

The quoted Prices for all the

remaining items shall remain fixed

Page 14: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

14

during the Performance of the

Contract and shall not be subject

to variation on any account save

for change in Quantity.

Modified Vol 1- Commercial

requirements has been

uploaded.

ITB, Clause 2, page 5 Being a world bank funded project, please inform us

the benefits available / to be considered for this bid.

Also, please inform us the list of documents provided by

Customer towards the same.

No benefits shall be accounted

by the bidder while quoting the

bid.

It is requested to extend the Bid submission time for

atleast 20 days from the present schedule date as

there are continuous sankranti holidays. Suppliers

expressed that they could not provide the offers on

time for major materials. Hence, request for extension.

The bid submission date has

already been extended to 10th

Feb 2016. No more extension.

In the File named' vol_i_ ncb_ supply_ and_ installation_

pavagada' of the bidding documents of the subjected

tender, 'Section-ii Bid Data Sheet-Preparation of Bids'

under sub clause 'ITB 17.7.The prices quoted by the

Bidder shall be:Fixed' to be modified and Price

adjustment provision shall be provided as per latest

IEEMA indices

Contract Price Adjustment:

The Prices, only for the following

items, quoted by the Bidder shall

be VARIABLE in accordance with

the relevant IEEMA/CACMAI

Price Variation Formula and

Indices without ceiling during the

contractual delivery period. Price

Variation is not admissible for

other Items. The base date

applicable for Price Variation is

the date of Tendering i.e., date

Page 15: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

15

of Techno-Commercial Bid

Submission date as notified

(either original or extended) as

per IEEMA/ CACMAI Circulars:

I Equipments / Materials :

1) Power Transformers

2) Circuit Breakers /

Switchgears.

3) Conductors & Ground

Wires.

4) Lightning Arresters.

5) Transformer Oil.

6) Tower Parts, equipment

mounting/Station

Structures.

7) Control Cables.

8) HT UG Cables

9) Conductor Hardware.

10) Battery & Battery Chargers.

11) Instrument Transformers.

12) Insulators

II. In respect of above Electrical

goods covered under works

contract / procurement shall be

in accordance with the relevant

IEEMA / CACMAI Price Variation

formulae and indices.

III. In respect of Turnkey Projects

involving Civil Works and Erection

Page 16: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

16

Portion shall be as per relevant

Formulae as evolved by IEEMA.

However, as far as admissibility of

price variation towards erection

and civil works is concerned, the

same would be restricted to

below appended activities only.

a) Concreting (With or without

steel reinforcement)

b) Steel reinforcement and

structural steel.

c) Any other civil works where

rates are individually/

independently indicated for

concreting (with or without

reinforcement) and Steel

reinforcement and structural

steel.

The quoted Prices for all the

remaining items shall remain fixed

during the Performance of the

Contract and shall not be subject

to variation on any account save

for change in Quantity.

Modified Vol 1- Commercial

requirements has been

uploaded.

Page 17: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

17

In the File named 'NIT' of the bidding documents of the

subjected tender, 'Clause No 6. Qualifying

requirements of Bidder', under 'sub clause 3.0 Qualifying

Requirements (Technical)

3.2.TRANSMISSION LINE :For one lot

Should have constructed 220/66kV Transmission Line or

above category on Total Turnkey basis or Partial

Turnkey basis to an extent equivalent to the length of

the line proposed in the tender or to an extent of 25

kmswhich ever is less in the last Seven years preceding

the date of Bid submission, out of which 50% of the

above quantity or 15 Km whichever is less shall be in

satisfactory service for a period of One year prior to the

date of submission of the Bid.' shall be modifies as

'3.2.TRANSMISSION LINE :For one lot

Should have constructed 220/66kV Transmission Line or

above category on Total Turnkey basis or Partial

Turnkey basis to an extent equivalent to the length of

the line proposed in the tender or to an extent of 25

kmswhich ever is less in the last Seven years preceding

the date of Bid submission, out of which 50% of the

above quantity or 15 Km whichever is less shall be in

satisfactory service for a period of One year prior to the

date of submission of the Bid.

Shall be a Labour Contractor or Sub-Contractor of a

Turnkey Contractor and who has executed the work of

construction of 220kV Transmission Line or above

category equivalent to two times the length of the line

proposed in the tender or to an extent of 50Kms

whichever is less in the last seven years preceding the

date of Bid submission, out of which 50% of the above

quantity or 25Kms whichever is less shall be in

satisfactory service for a period of two years prior to the

date of submission of the Bid.'

Since the work is awarded to the

main contractor the experience

of the sub contractor /labour

contractor cannot be considered

as a qualifying requirement for

awarding the work to main

contractor.

“220/66kV” shall be read as

“220kV” only in the Qualifying

Requirement of TRANSMISSION

LINE as 66kV Transmission Line are

not envisaged in this package.

Modified Vol 1- Commercial

requirements has been

uploaded.

Page 18: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

18

Labour Contractor or Sub-Contractor experience also

shall be considered for Technical QR related to line

4.1 (a) 4.1 (b) In the File named 'NIT' of the bidding documents of the

subjected tender, 'Clause No 6. Qualifying

requirements of Bidder', under 'sub clause 4.0

QUALIFYING REQUIREMENTS (FINANCIAL) 4.2.4. The

Bidder shall stand disqualified if the total value of Works

on hand including contract against subject tender if

awarded, exceeds 2 times the MAAT (minimum

average annual turnover)' shall be modified as 'While

computing the balance works on hand, those works

should not be considered which are awarded 3 months

prior to the original date of bid submission. Rest of the

Total value of works on hand shall not exceed 4 times

of the MAAT.'

In general the works on hand for any reputed EPC

Contractor will be on higher side, hence this clause to

be modified accordingly.

The provisions of bid document

shall prevail.

Modified Vol 1- Commercial

requirements has been

uploaded.

4.1 (a) 4.1 (b) In the File named 'NIT' of the bidding documents of the

subjected tender, 'Clause No 6. Qualifying

requirements of Bidder', under 'sub clause 4.0

QUALIFYING REQUIREMENTS (FINANCIAL)

For the purpose of Lot I this particular Bid, Bidders shall

meet the following minimum criteria Minimum Average

Annual Turnover (MAAT) of the bidder for best three

years out of last preceding five financial years ending

on March or December as the case may be, shall not

be less than Rs. 28000.Lakhs.

For the purpose of Lot II this particular Bid, Bidders shall

The provisions of bid document

shall prevail.

Modified Vol 1- Commercial

requirements has been

uploaded.

Page 19: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

19

meet the following minimum criteria Minimum Average

Annual Turnover (MAAT) of the bidder for best three

years out of last preceding five financial years ending

on March or December as the case may be, shall not

be less than Rs. 26000.Lakhs shall be modified as 'MAAT

Requirement for both the Lots will be equal to ECV i.e.,

MAAT for LOT I shall not be less than Rs. 14000.Lakhs.

MAAT for LOT II shall not be less than Rs. 13000.Lakhs.'

In the File named 'NIT' of the bidding documents of the

subjected tender, 'Clause No 6. Qualifying

requirements of Bidder', under 'sub clause 2.0(a)The

Bidder or his JV partner should possess valid Super

Grade Electrical Contractors License issued by the

Government of Karnataka as on the date of opening

of techno-commercial bid' shall be modified as 'The

contractor should apply for supergrade licence and

Acknowledgement copy of the same should be

provided and uploaded with the bid, the valid

supergrade licence should be provided in case of

successful bidder by the time of award of the contract'

or within 45 days from the date of bid opening.

The provisions of bid document

shall prevail.

Modified Vol 1- Commercial

requirements has been

uploaded.

ITB 19.2 & ITB 20 The validity of EMD bank guarantee is mentioned as 28

days and 45 days in ITB 19.2 & ITB 20 respectively from

the bid submission date.

Modified Vol 1- Commercial

requirements has been

uploaded.

GCC 13 The modalities of contract securities is discussed. Kindly

confirm the validity of the performance securities and

the advance bank guarantee to be submitted.

The validity of the contract

securities shall be for a entire

period/extended period of

contract.

Modified Vol 1- Commercial

requirements has been

uploaded.

Page 20: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

20

Page 1-69 of section IV bidding forms

&

The price adjustment formula is provided. Contract Price Adjustment:

The Prices, only for the following

items, quoted by the Bidder shall

be VARIABLE in accordance with

the relevant IEEMA/CACMAI

Price Variation Formula and

Indices without ceiling during the

contractual delivery period. Price

Variation is not admissible for

other Items. The base date

applicable for Price Variation is

the date of Tendering i.e., date

of Techno-Commercial Bid

Submission date as notified

(either original or extended) as

per IEEMA/ CACMAI Circulars:

I Equipments / Materials :

1) Power Transformers

2) Circuit Breakers /

Switchgears.

3) Conductors & Ground

Wires.

4) Lightning Arresters.

5) Transformer Oil.

6) Tower Parts, equipment

mounting/Station

Structures.

7) Control Cables.

8) HT UG Cables

Appendix-2 (Page 115) of Sec IX Contract forms indicates that the same is “Not

Applicable”. Kindly confirm whether the contract is on

“Firm” basis or “Price adjustment” is applicable.

Page 21: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

21

9) Conductor Hardware.

10) Battery & Battery Chargers.

11) Instrument Transformers.

12) Insulators

II. In respect of above Electrical

goods covered under works

contract / procurement shall be

in accordance with the relevant

IEEMA / CACMAI Price Variation

formulae and indices.

III. In respect of Turnkey Projects

involving Civil Works and Erection

Portion shall be as per relevant

Formulae as evolved by IEEMA.

However, as far as admissibility of

price variation towards erection

and civil works is concerned, the

same would be restricted to

below appended activities only.

a) Concreting (With or without

steel reinforcement)

b) Steel reinforcement and

structural steel.

c) Any other civil works where

rates are individually/

independently indicated for

concreting (with or without

reinforcement) and Steel

Page 22: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

22

reinforcement and structural

steel.

The quoted Prices for all the

remaining items shall remain fixed

during the Performance of the

Contract and shall not be subject

to variation on any account save

for change in Quantity.

Modified Vol 1- Commercial

requirements has been

uploaded.

Contract will be awarded in two separate parts i.e. First

Contract (Supply) and second contract (installation) or

as a single contract.

Contract will be awarded on

total turnkey basis including

supply of all Materials, Erection

(including Civil Works), Testing

and Commissioning.

Modified Vol 1- Commercial

requirements has been

uploaded.

The modalities including the detailed scope for the

treatment of ROW (Right of Way), Way leave

clearances, Power line/Highway crossings and Forest

clearance if any.

As the premises of station

establishment is within the solar

park, the question of ROW does

not arise.

Any variation in taxes & duties during the period of the

contract will be reimbursed at actual by the Employer.

In case of any statutory variation

in taxes/duties/levies or if any

tax/duty/levy is newly introduced

by the Government applicable

for this Contract with effect from

the next day of the date of

Page 23: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

23

submission of the bid these

variations/additional

taxes/duties/levies will be to the

account of the owner. In case

the Bidders indicate lesser rates of

taxes and duties with reference

to the prevailing rates of taxes

and duties at the time of bidding

any variations in the taxes and

duties would be paid/recovered

keeping the rates of taxes and

duties applicable as on the date

of bid opening as the base and

not the quoted rates of taxes and

duties for payment/recovery of

difference in the taxes and

duties. If the Contractor is

required to pay additional tax or

duty, then the owner shall

reimburse the Contractor the

additional tax or duty so paid by

the contractor against submission

of documentary evidence to the

satisfaction of the owner by the

contractor. This provision will not

be applicable to transaction

between the contractor and his

sub-suppliers, sub-contractors for

raw materials, for „bought out‟

items etc., and will be applicable

only for the „own/direct

transactions‟ between the

contractor and the owner for the

materials supplied from his own

Page 24: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

24

manufacturing units and erection

and civil works.

Modified Vol 1- Commercial

requirements has been

uploaded.

The Start date of the project, whether it will be from the

date of issue of NOA (Notification of Award) or whether

it will be from the finalization of project schedule (L2

network) or release of advance whichever is later.

Start date of the project shall be

from the date of Letter of

Award/Letter of Intent.

The advance to be released as part of the contract is

interest free in nature. Kindly confirm.

Ten percent (10%) of the amount

as an advance payment shall be

made by the employer against

receipt of invoice, and an

irrevocable advance payment

security for the equivalent

amount made out in favour of

the Employer.

No interest shall be levied on the

advance payment.

The index sheet of Vol II (1of3), wherein it is indicated

that the bidding documents consists of Sec-IV (Erection

conditions of contract) under Vol-1(commercial

conditions). However, the same is not available in Vol-I

(Commercial conditions).

Modified Vol 1- Commercial

requirements containing ECC has

been uploaded.

The site survey wherein it has been observed that the

roads passing through the village to the location are

very narrow and transportation of 150MVA transformers

etc through this stretch will be practically very difficult.

Kindly confirm whether suitable approach roads for

transportation shall be made by KSPDCL.

Suitable approach roads will be

provided by KSPDCL

Kindly confirm whether construction power and water

shall be free issued by KSPDCL or whether the same

Arranging construction power for

each of the substation shall be

Page 25: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

25

shall be issued on chargeable basis. the responsibility of the

Contractor. KSPDCL shall not be

responsible for arranging

construction power.

Arranging water during

construction period shall also be

the responsibility of the Bidder.

KSPDCL shall not be responsible

for arranging Water.

Kindly confirm that the statutory clearances from all the

relevant authorities shall be arranged by KSPDCL.

All clearance and approvals

required by Bidder‟s except

the following shall be

obtained by KSPDCL:

1. Drawing & safety Approval

by Chief Electrical Inspector,

GoK.

2. RT and R&D Pre

Commissioning approval –

RT Department, KPTCL.

3. Station Commissioning and

pre commissioning by –

KPTCL and ESCOM.

4. Material inspection by

TA&QC wing, KPTCL.

We refer to the Qualification, criteria, wherein having a

Super Grade Electrical Contractor license is mentioned

as a Essential Minimum qualifying criteria and the copy

of the same to be submitted along with the bid. We

request you kindly amend the same as “The bidder to

give an undertaking that the Super Grade Electrical

Contractor license shall be submitted within 1 month of

award of order”.

The provisions of modified

uploaded Bid Document shall

prevail.

As stated, our parent company(TBEA Shenyang The experience of the parent

Page 26: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

26

Transformer Group Co Ltd) has executed various

400/765 kV substation projectsin INDIA. Hence, we

request you to consider the credentials of our parent

company and also consider the Parent company

andthe subsidiary (TBEA Energy India Ltd) as single

entity for Technical & Financial Evaluation.

company cannot be considered

for subsidiary company for

Technical & Financial Evaluation.

VOLUME-IIA (Part2 of 3) Clause

No.14.2

Page No. 123

TECHNICAL Specification for Transformers:

"The purchaser however reserves the right to waive the

minimum experience condition stipulated in clause

13.04.00 (i) in case of firm having collaboration with well

experience firms. The experience of the collaborating

firms in the manufacture of similar type power

transformer shall be not less than ten years. The waiving

of minimum experience condition will be considered by

the purchaser only on furnishing the performance

guarantee for the power transformer manufactured by

the collaborating firms."

As stated above:

1. In case of collabaration (or) subsidiaries established

production facility in INDIA recently, Performance

Guarantee(PG) to be furnished at the time supply or

at Tendering stage. Kindly confirm.

2. Kindly confirm the List of Documents to be

submitted at the tendering stage by the

collaborating firms.

(1) Performance Guarantee (PG)

has to be furnished at the time

of entering into contract.

(2) The list of documents notified

in the tender need to be

submitted/uploaded.

Modified Vol 1- Commercial

requirements has been

uploaded.

VOLUME-IIA (Part2 of 3)

Clause No.12.2.3.7

Page No. 118

TECHNICAL Specification for Transformers

"The purchaser at his discretion may or may not opt for

conducting “short circuit test”. So, the charges quoted

for the above test may or may not be taken into

consideration during evaluation. The decision of the

purchaser in this regard is final and binding on the

Page 27: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

27

bidder".

Kindly Confirm:

1. Is conducting SC test as per the KPTCL Specification

is Mandatory or submission of SC calculation will do

the needful?

2. In case of SC waiver, on what basis waiver from

conducting SC Test shall be given? In case a bidder

who posses Similar/Higher rating SC report, within

the last 5 Years, needs to conduct SC again?

KINDLY CONFIRM THE ABOVE AS IT INVOLVES HUGE

COST IMPLICATION.

(1) Conducting dynamic short

circuit withstand test can be

considered for waiver subject

to condition that the design

provided by the bidder shall

be got approved by

competent agency.

(2) Bidder who posses

Similar/Higher rating SC report,

within the last 5 Years, need

not conduct SC again.

However, the design provided

by the bidder shall be got

approved by competent

agency.

NIT clause no 5 & ITB clause no 20.3 As per ITB the EMD BG shall be valid for 45 days beyond

bid validity period and as per NIT EMD BG shall be valid

for 30 days beyond the bid validity period.

We understand that EMD BG validity shall be 30 days

beyond bid validity period as per ITB.Kindly confirm

Modified Vol 1- Commercial

requirements has been

uploaded.

GC,clause no 10.2 We understand that the space required for site office,

stores and labour colonies shall be provided by KSPDCL

free of cost.

KSPDCL will provide temporary

space required for site office,

stores and labour colonies.

GC clause no.14 We understand Form C wil be issued by KSPDCL for all

Bought out as well as direct transactions. Please

confirm.

Clause PC14.3, Section VIII,

particular conditions page 3-97

states that “Employer will give

only necessary certificates in

terms of such notifications as per

information given by the bidder in

declaration form”.

Form C will be issued by KSPDCL

only for „own/direct transactions‟

Page 28: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

28

Modified Vol 1- Commercial

requirements has been

uploaded.

GC clause no.14 Please confirm whether any special VAT rate is

applicable for the package.

No.

General Kindly clarify regarding the divisibilty of the Contract.

We request KSPDCL to kindly issue three separate

contracts viz; Supply Contract, Erection Contract, Civil

works Contract.

Contract will be awarded on

total turnkey basis including

supply of all Materials, Erection

(including Civil Works), Testing

and Commissioning.

Modified Vol 1- Commercial

requirements has been

uploaded.

Volume II section 3 clause no. 12.2.2 As per the referred clause 220/66/11kV,150 MVA

transformer first unit needs to undergo dynamic short

circuit withstand test.

It is to be noted that it will be difficult to conduct short

circuit withstand test on 220/66/11kV,150 MVA

transformer in India with the existing facilities. If at all it is

arranged in CPRI, it will take almost 8-9 months to

complete the test. And if is not possible in CPRI then for

conducting the SC test, the manufactured unit has to

go to KEEMA, which takes a minimum period of 12-18

months and sometimes KEMA does not provide any

confirmation on dates due to their loading on test

facility. Project duration being 12 months (lot 1) & 18

months (lot 2),it is impossible to conduct the dynamic

short circuit withstand test.

Keeping the above point in view, request you to kindly

delete the clause pertaining to dynamic short circuit

test that needs to be conducted on the first unit of

transformer.

Conducting dynamic short circuit

withstand test can be considered

for waiver subject to condition

that the design provided by the

bidder shall be got approved by

competent agency.

Bidder who posses Similar/Higher

rating SC report, within the last 5

Years, need not conduct SC

again. However, the design

provided by the bidder shall be

got approved by competent

agency.

Volume II section 3 clause no. 19.03 &

clause no 10.03 for section V (320 of

As per clause no 19.03 of section 3, guaranteed period

for the equipments is 60 months from the date of

The equipments offered shall be

guaranteed for satisfactory

Page 29: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

29

403) satisfactory commissioning of the equipment.As per

clause no 10.02 ,of section V guaranteed period for

power transformer, delay panels, isolators,control

cables,battery set,circuit breaker and substation

automation system is 42 months from the date of

satisfactory commissioning of the equipments and 12

months for rest of the project from the date of

satisfactory commissioning of equipment.But as per

particular conditions the guaranteed period is 18

months.In this regard,request you to kindly clarify the

DLP period that is to be considered.

performance for a period of 60

months from the date of

satisfactory commissioning of

equipment. The equipment

found defective/failed with in the

above guarantee period shall be

replaced or repaired by the

supplier free of cost with in one

month from receipt of intimation.

If the defective/failed

equipments are not

replaced/repaired as per the

above guarantee clause, the

KPSDCL shall recover an

equivalent amount plus 15%

supervision charges from any of

the suppliers bills.

Modified Vol 1- Commercial

requirements and Vol II has been

uploaded.

Clause no 7.3 of GC & PC and

Volume II section -4

As per GC and PC recommended spares for a period

of 3 years is to be considered by the contractor.

But as per Volume II section-4 clause 16, recommended

spares for a period of 5 years needs to be supplied.

With regard to the above, request you to kindly clarify

the period for which the recommended spares needs

to be supplied.

Recommended spares for a

period of 3 years is to be

considered by the contractor.

Modified Vol 1- Commercial

requirements has been

uploaded.

GC clause no.10 We understand that the 220kV line work is under

present scope of works. With regard to the same,

As the premises of Station

Location is within the solar park,

Page 30: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

30

request you to clarify the following:

ROW and land clearances required pertaining to

above works is in KSPDCL's scope. Please confirm.

the question of ROW does not

arise.

Appendix 1 payment terms We understand that the 10% advance payment

towards supply,design and installation services shall be

interest free advance.

Ten percent (10%) of the amount

as an advance payment shall be

made by the employer against

receipt of invoice, and an

irrevocable advance payment

security for the equivalent

amount made out in favor of the

Employer.

The advance payment shall be

interest free.

Appendix 1 payment terms In case of payment towards installation & design

services, we presume that 100% tax applicable for

installation and design services shall be paid along

with the stage payment of 70% (for installation

services)and 80% (design services).Kindly confirm.

100% taxes if any applicable on

design and installation services

portion of the contract shall be

payable on completion of the

work and on production of

documentary proof.

Modified Vol 1- Commercial

requirements and Vol II has been

uploaded.

Appendix 1 payment terms Interest for delayed payment- Incase the payment is

delayed and not paid within 45 days period from

contractor's invoice then the interest for the delayed

payment will be calculated from the 46th day till the

payment is done for the due payments.

Kindly confirm whether our understanding is in line with

tender conditions.

Modified Vol 1- Commercial

requirements and Vol II has been

uploaded.

GC & PC 11 With reference to the clause, the contract price should

be FIRM/FIXED. As the scope comprises of Transformers,

& major Civil items whose raw material prices varies

drastically over time, we request you to kindly provide

"PRICE VARIATION" for the above items as per IEEMA /

Contract Price Adjustment:

The Prices, only for the following

items, quoted by the Bidder shall

be VARIABLE in accordance with

Page 31: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

31

LME. the relevant IEEMA/CACMAI

Price Variation Formula and

Indices without ceiling during the

contractual delivery period. Price

Variation is not admissible for

other Items. The base date

applicable for Price Variation is

the date of Tendering i.e., date

of Techno-Commercial Bid

Submission date as notified

(either original or extended) as

per IEEMA/ CACMAI Circulars:

I Equipments / Materials :

1) Power Transformers

2) Circuit Breakers /

Switchgears.

3) Conductors & Ground

Wires.

4) Lightning Arresters.

5) Transformer Oil.

6) Tower Parts, equipment

mounting/Station

Structures.

7) Control Cables.

8) HT UG Cables

9) Conductor Hardware.

10) Battery & Battery Chargers.

11) Instrument Transformers.

12) Insulators

II. In respect of above Electrical

Page 32: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

32

goods covered under works

contract / procurement shall be

in accordance with the relevant

IEEMA / CACMAI Price Variation

formulae and indices.

III. In respect of Turnkey Projects

involving Civil Works and Erection

Portion shall be as per relevant

Formulae as evolved by IEEMA.

However, as far as admissibility of

price variation towards erection

and civil works is concerned, the

same would be restricted to

below appended activities only.

a) Concreting (With or without

steel reinforcement)

b) Steel reinforcement and

structural steel.

c) Any other civil works where

rates are individually/

independently indicated for

concreting (with or without

reinforcement) and Steel

reinforcement and structural

steel.

The quoted Prices for all the

remaining items shall remain fixed

during the Performance of the

Page 33: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

33

Contract and shall not be subject

to variation on any account save

for change in Quantity.

Modified Vol 1- Commercial

requirements has been

uploaded.

GC clause no.14 Taxes & duties We understand that taxes and duties are not taken for

evaluation purpose. Kindly confirm

Taxes & Duties are considered for

evaluation purpose.

Modified Vol 1- Commercial

requirements has been

uploaded.

General Kindly confirm that hindrance free land will be handed

over to the contractor on the date of award of

contract.

Any delay occurring due to delay in handing over of

land or ROW issues should be excluded from the

completion period.

As the premises is within the solar

park, the question of ROW does

not arise.

Tentative schedule of handing

over of site: April 2016.

Bid Price Schedule, A.8.-6(Busbar

protection)

We presume the scope of bus bar protection (central

unit / bay units) is restricted to the number of present

feeders. No hardware / software for future scope is

considered under this contract. However, the central

unit will be selected in such a manner that it shall be

possible to expand in the future. Please confirm

whether our understanding is correct

No expansion is anticipated.

Bid Price Schedule, A.8.- 7

(Substation Automation System)

Stations at Nagalamadike Hobli in Pavagada taluk are

being new stations, complete SAS will be based on IEC

61850 protocol. We are not considering any works in

the remote stations / SLDC end. Scope envisaged is

restricted upto gateway in these substation. Please

confirm

Provision for OPGW will be

provided for communication

purpose.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Page 34: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

34

Bid Price Schedule, A.8.- 7

(Substation Automation System)

As per Note-3, Electronic Trivector Meter is required only

on HV & LV side of transformer bay. However, as per

technical specification of CRP & SAS (Annexures)

Trivector meters are required in all line feeders, in

addition to transformer feeders. Please check & inform

the requirement.

Electronic Trivector Meters shall

have to be provided for both

sides of transformers & for line

feeders.

Bid Price Schedule, A.11. (Busbar

formation)

ACSR Drake conductors are covered under Sl. no.

A11.1 and insulators / hardware are covered under

Sl.no. A12.2. Hence, kindly inform what are the supply

items to be covered under Sl.no. A.11

A11 consists of ACSR Drake

conductors and rigid bus bar

formation.

A12 Consists of formation of cross

bus with drake and twin drake.

Line items Please include separate line items for the following, as

we could not find those in the available price schedule:

a)Indoor lighting works.

b) Outdoor lighting works

c) Bay marshalling kiosks / Junction boxes.

Provision is made under Sl. No.

A14, 3, 5 & 6 and yard lighting.

Outdoor lighting In line with technical specification Cl. 2.8, outdoor light

fixtures and street light fixtures shall be of HPSV / MH

fittings. LED based street light fittings as per Annexure - I

is not envisaged. Please confirm.

As in the BOQ, HPSV need to be

provided.

Indoor lighting As per Annexure-1, both fluorescent type fittings & LED

based fittings are given for indoor application. For

control building application, whether combination of

these fittings to be used (or) only LED fittings are

acceptable ?

Both fluorescent type fittings &

LED based fittings can be

provided for control building.

Quantities shall be finalized at the

time of execution.

Mounting of light fixtures We presume that light fixtures shall be mounted on

both tower gantries & Lighting mast based on the

suitability. Please confirm our assumption.

Light fixtures shall be mounted on

lighting mast and on lighting

poles as per approved design.

Technical specification, Section

Switchyard Erection, Cl. 8.4 (Earthing)

Please include a separate line for earthing material in

price schedule. Also please specify the type of earthing

conductor to be used for each application (main mat,

Specification are provided in the

BOQ. Deviations if any will be

intimated at the time of

Page 35: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

35

above ground, below ground, cable trench etc.) execution.

Technical specification, Section - 12,

Earthmat (Technical specification for

design and laying of earthmat)

As per the clause-2.1 of specified section, earthmat

layout is available. However, we are not in receipt of

the same. Kindly furnish the same.

Tentative earthmat design is

uploaded in modified Vol II .

Technical specification, Section

Switchyard Erection, Cl. 16.0

(Installation of cables)

We presume that for both indoor and outdoor

applications, cables shall be laid in cables trenches

with angle support only. Nowhere cable trays are

required. Please confirm.

Specification are provided in the

BOQ of Vol III.

Price schedule - A24, 48V Battery &

charger

As per the price schedule, 48V battery and charger are

required for PLCC system, whereas there is no line item

for 48V DCDB. Please include the same.

The provision for PLCC system has

been replaced with OPGW

system.

General We presume the following are not included in bidders

scope of work.

1. Visual monitoring system.

2. HVAC system.

3. Please confirm. If it is required, please include a line

item in BPS and also furnish the specification.

They are not required.

Lightning mast Please indicate the height of lightning mast Height of lightning mast should be

around 25mtrs.

LT Power supply We presume incoming supply (HT) to DP structure is in

scope of contractor only. Please confirm.

Incoming supply to DP structure

for auxiliary is not in the scope of

Bidder.

Tender Specification,Volume III,Price

Schedule, Schedule 3B(II)

Clause no.B1,B8(3)

In order to ascertain the adequacy of the cutting and

filling quantities given in price schedule.

Please furnish the following details :- (for 8 locations)

1. Plot plan indicating boundary of substation.

2. FGL of the proposed substation.

3. Contour Layout & Spot levels

4. Soil report for Proposed SS

Provisional design of switchyard

layout is provided. Work is to be

executed after availing

approved drawings on site basis.

Preliminary Geo Technical study

in respect of location of each of

the station is uploaded. However,

the successful bidder needs to

conduct geo-technical

investigation before taking up of

design of various structures.

Page 36: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

36

Tender document We wish to inform that, "Specification for Civil Works" is

not attached in the Tender document.Please provide

the same.

Modified uploaded documents

contains Specification for Civil

Works in Vol II.

Tender Specification,Volume II A,Sec.

7.0 Structures

Cl.no : 1.3 & 1.3.2

As per referred clause, it is mentioned that, "The towers

beams and lightning/Lighting masts shall be fabricated

as per the single line diagrams furnished. In the part 1 of

Technical specifications, only the single line diagrams

enclosed". However in Tender document the Single

Line diagram for towers and equipment is not

enclosed. Request you to kindly provide the same.

Provisional design of switchyard

layout is provided. Work is to be

executed after availing

approved drawings.

Tender Specification, Volume II

A,Sec. 7.0 Structures

We trust that grade of structural steel ,used for

Switchyard structure are Mild steel of grade E250A as

per IS:2062.

Please confirm.

Yes

Tender Specification,VolumeIII,Price

Schedule, Schedule 3B(II)

clause no.B2

We presume that, if the soil is expansive type in nature.

Soil improvement by Murram/CNS material /Boulder

filling may be required. Please furnish the details of soil

improvement items & include items for the same in the

price schedule.

Soil improvement will be as per

the prevailing standards followed

as per IS codes.

Provisional quantities are

provided in the price sheets. Work

is to be executed as per

approved design drawings.

Tender Specification,VolumeIII,Price

Schedule, Schedule 3B(II)

We presume that, if the soil is expansive type, the same

soil cannot be used for backfilling and Bought out earth

may be required. We trust that the same shall be paid

under Price Schedule, Schedule 3B(II) SL. No. B1b).

Please confirm.

Provisional quantities are

provided in the price sheets. Work

is to be executed as per

approved design drawings.

Tender Specification,VolumeIII,Price

Schedule, Schedule 3B(II)

As per price schedule, the below items are not

specified in scope and price schedule. Hence, We trust

that the following works are not in bidders scope.

The scope of work in the price

schedule 3B(II) is within the scope

of the bidder. However, the

Page 37: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

37

1. Boundary wall along with gate.

2. Security hut/cabin.

3. DG house building.

4. Store building (open or Closed Building).

5. Fire fighting Pump house and Water tank. Foam

house building.

6. Rain water harvesting.

7. Switchyard Panel Room

8. Fence & Gate

Please confirm.

quantities for the left out items

are provided in the corrigendum

uploaded on 21-01-2016.

Modified price sheets and techno

commercial sheets uploaded

vide Vol III.

Tender Specification,Volume III,Price

Schedule, Schedule 3B(II)

We understand that, Bidder scope of work is limited

with-in the Switchyard fence area. Beyond that, we

have not considered any work in our scope.(except for

Approach road).

Please confirm.

Yes. The scope of work of the

bidder is within the switchyard

fence area.

Tender Specification,Volume III,

Price Schedule, Schedule 3B(II)

We have considered the outlet point of switchyard of

50m (max) beyond switchyard fence to connect the

nearest main drain. Please confirm.

Yes. As per the approved

drawings.

Tender Specification,VolumeIII,Price

Schedule, Schedule 3B(II)

Please provide the following drawing along

specification. In order to assess the quantum of Civil

works

1. 220kV Control Room Building

2. RCC Cable trench & Trench crossings

3. Drain & Drain crossings.

4. Switchyard Road & Approach road

5. Towers & Equipment Structure drawings (220kV &

66kV)

6. Station Transformer

7. Retaining wall

8. Towers,LM & Equipment foundation drawings (220kV

& 66kV)

9. Transformer Foundation & Fire wall

10. Inspection Chamber

11. Lighting & Lighting Mast drawing

Details of drawing along with

specification have been

provided in the corrigendum

uploaded on 21-01-2016.

Towers & Equipment Structure

drawings (220kV & 66kV) will be

uploaded.

Modified Technical Specifications

and drawings uploaded vide Vol

II.

Page 38: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

38

GA layout : KREDL/TECH/SS-220/Sp-4

&

Tender Specification,Volume III,Price

Schedule, Schedule 3B(II)

calsue no.B3

As per referred layout, Cable trench "A" type is shown.

However in Price schedule there is no item for the

same.

Please include the same in Price schedule.

Drawings provided are only

indicative.

Cable trench "A" type is not

required. Hence, it is not provided

in price sheets.

Tender Specification,Volume III,Price

Schedule, Schedule 3B(II)'cl no B8

We wish to inform that, item for Drain crossing is not

there in referred price schedule. But it is required for the

road crossing.

Kindly include the item for the same in BPS.

Provision is made for RCC cable

duct- Road crossing for A,B,C,D

type cable ducts. However

execution of works shall be taken

up as per approved drawings.

Tender Specification,Volume III,Price

Schedule

We trust that, the connection of all structures to their

foundations shall be by base plates embedded

foundation bolts. However in BPS, there is no item for

the same.

Please add items for foundation bolts of Towers

&equipments.

Quantities are already provided

in the price sheets. The actual

shall be as per approved design.

Modified Vol II & Vol III uploaded.

Tender Specification,Volume IIA,Part

1 of 3Cl No 2.1

We have received detailed layout plan of substation at

solar park, Pavagada.As per the scope the substation is

proposed at Eight different locations.Please provide the

detailed layout plan at below locations as mentioned

in the referred clause

Lot1

(a) TirumaniSy no. 154/2,3,4&5

(b) TirumaniSy no. 131/1 & 2

(c) RayacharluSy no. 225/1,2 & 3

(d)RayacharluSy no. 175

Lot2

a) KyataganacharluSy no. 44

b)VallurSy no. 242

c) VallureSy no. 166

d) BallasamudraSy no.35/2

Typical detailed layout plan for

one substation is provided. The

same need to be adopted for all

the balance 7 stations.

However, during execution the

drawings for individual stations

have to be designed and got

approved.

Page 39: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

39

VOLUME-IIA (PART 1 OF 3)

TECHNICAL SPECIFICATION/2.0

Scope/b/vi

Cable Trench: The routes of cable trench of A, B, C & D

type is indicated in the layout drawing provided. The

detailed drawings for above type side type of cable

trench has not been provided

We request you to provide cable ducts

details/drawings.

Also kindly confirm us that ladder type cable tray is only

applicable for both outdoor &In door cable trench.

Provisional drawings will be

uploaded for different type of

cable trenches.

Modified Vol II uploaded.

VOLUME-IIA (PART 1 OF 3)TECHNICAL

SPECIFICATION2.7

2.7 Reference Drawings: We request you to provide us

the reference drawings

Modified Vol II uploaded.

Volume - IIA

Section 5.2

(415/240 Volts LTAC Panels) - 25.1, 26

Refer drawing for 415V LTAC panel (Typical) for 220 KV

station: We request you to provide us the SLD for the

LTAC panel.

Modified Vol II uploaded.

Volume - IIA

Section 5.3 (A.C.Outdoor Distribution

Box)

Drawing No.KF-B/TECIVSub-Station/220/168/9.9.92 -

detailed arrangement of distribution box "Type - A" -

Single front type.

2. Drawing No. KEB/TECIVSub-Station/220/168/9-9.92 -

detailed arrangement of distribution box "Type - B" -

Double front type.

We request you to provide us the drawings for the AC

outdoor distribution box.

Modified Vol II uploaded.

VOLUME-IIA SECTION 5.4: LIGHTING

SYSTEM

Distribution panel: We understand distribution panels for

Lighting system is applicable, we request you to

provide us the details of the Lighting system.

Modified Vol II uploaded.

VOLUME - IIA SECTION 6.0 -

SWITCHYARD ERECTION

8.5.3 Tap connections from the earthing grid to the

equipment /structure to be earthed shall be terminated

on the earthing terminals of the equipment / structure

as per "Earthing Details-

We request you to confirm the drawings for the

earthing shall be considered during detailed

engineering. Kindly confirm

Modified Vol II uploaded.

Page 40: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

40

VOLUME-IIA

TECHNICAL SPECIFICATION

SECTION 12.0- Earth mat &

SECTION 6.0 SWITCHYARD ERECTION

MS Flat of the designed cross section shall be laid at the

designed depth of (around 0.9 Mtr.) and spacing duly

straightening and removing any bends.

As per section 12.0: the depth is 900mm.

As per section 6.0: the depth is 600mm.

Kindly clarify the depth of Earth Conductor in ground.

MS Flat of the designed cross

section shall be laid at the

designed depth of 0.9 Mtr only.

General DC Distribution boards

We request you for the detail of DC Distribution

board.(SLD)

Modified Vol II uploaded.

However, the drawings shall be

got approved before taking up

for execution.

General Earthing and indoor illumination is not available in bid

price schedule.

Understand that Earthing and Indoor Illumination is

under present scope. Please confirm and kindly revise

the price schedule accordingly.

Modified Vol II uploaded.

However, the drawings shall be

got approved before taking up

for execution.

General Price schedule

It has been observed that some rows in price schedule

are hidden. We understand that hidden rows are

excluded from the present scope.

Modified Vol III uploaded.

General Price schedule

We have observed that few additional items like 66kV

Cable Termination kit, Supporting Structure, Cable Tray

support etc has not been explicitly mentioned in the

price schedule but those are required to full fill the

present scope. Kindly include in the revise price

schedule.

Provision is made for 66kV LA

mounting structure in the 220kV

stations and they shall be of

composite type to

accommodate both LA and

cable.

Modified Vol II uploaded.

However, the drawings shall be

got approved before taking up

for execution.

Page 41: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

41

Layout Sectional details

We have observed that 220KV wave trap is under hung

type from the conductor as shown in section drawing,

We request you to confirm the 220kV wave trap is

under hung type connected to beam.

Consequent to adoption of

OPGW system , the concept of

wave trap does not arise.

Technical Specification Civil works

Kindly provide the Detailed Technical Specification for

Civil works.

Modified Vol II uploaded.

Layout Kindly clarify the requirement of Station Transformer. Layout diagram clearly indicates

that bidder has to provide 2 nos.

of 150MVA, 220/66kV power

transformers and 2 of 250 kVA,

11kV/433V,3 phase distribution

transformers with copper winding

for each of the stations.

Layout & Price schedule We understand that 66/11KV transformer and

associated equipments which are not mentioned in the

Price Sheet - BOQ Station is not in the present scope.

Please confirm.

Yes.

Technical Specification - Tender

Drawings

Switchyard Layout drawings : KREDL/TECH/SS-220/SP-4

We understand the layout drawing provided shall be

adopted for all the substation vide Lot I & Lot II. Kindly

confirm

Yes. They are indicative drawings

only. However, the drawings shall

have to be got approved before

taking up execution of work.

Site Location Site Location

We request you to confirm encumbrance free site shall

be provided from the date of issue of LOI/Purchase

order.

Yes. It is proposed to hand over

land free of encumbrance from

the date of issue of LOI.

Site - Approach Road Approach Road

During our site visit we have observed the locations for

the substation has no access road. We request you to

confirm site approach road shall be provided by

KSPDCL.

Suitable approach roads will be

provided by KSPDCL.

Page 42: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

42

Technical Specification Soil Investigation

We request you to provide us soil investigation report for

to evaluate and propose the required foundations.

Preliminary Geo Technical study

in respect of location of each of

the station is uploaded. However,

the successful bidder needs to

conduct geo-technical

investigation before taking up of

design of various structures.

Technical Specification Contour map

We request you to provide us the contour map along

with the reference FGL to enable us to assess the

cutting and filling for all the substations. Also we request

you to provide us the layout with co-ordinates for the

respective substations.

Modified Vol II uploaded.

Technical Specification Strom water drainage

We request you to provide us the details of the exit

point of storm water drainage. We request you to

confirm that our scope shall be limited to storm water

drainage within the substation boundary.

Yes

Tender Drawings Civil Drawings

We request to provide us the applicable civil drawings

for

Control Room Building, Tower foundations, Equipment

foundations, cable trench, road, culvert, drainage,

security fence etc.

The same shall help us for our estimation.

Modified Vol II uploaded.

Price Schedule Civil Price Schedule

We request to provide the detailed civil BOQ (defined

quantities instead of numbers) for the scope.

Modified Vol III uploaded.

Price Schedule Civil Price Schedule

Request M/s. KSPDCL to provide the quantity for site

leveling for all the proposed switchyard

Modified Vol III uploaded.

Page 43: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

43

Price schedule - Foundation Additional Item - Hard rock excavation

During our site visit we have observed that the

presence of hard is more in the proposed substation

land. Hence we request you to provide a separate line

item for excavation in hard rocks, weathered rock,

normal soil which shall be operated as per site

conditions.

Modified Vol III uploaded.

Price schedule - Foundation Backfilling of earth around the foundations

In the view of presence for the rock the required

backfilling soil has to be bought from the nearest point.

We have observed the nearest vicinity for availability of

the bought soil is 50KM away from the proposed

substation locations. Hence we request you to provide

us a separate line item for the bought out soil.

Backfilling of earth vests with

Bidder. The Bidder has to quote

accordingly and include it in the

cost of foundations. Quantity of

excess earth available out of

excavation of cable ducts etc.,

may be used for backfilling which

is suffice.

Modified Vol III uploaded.

Technical Specification Disposal yard

We request you to provide the details of the disposal

yard with the lead distance from the proposed site

locations.

Disposal of surplus earth vests with

Bidder. The Bidder has to quote

accordingly and include it in the

cost of foundations. The disposal

points is available within the

vicinity of about 5 Kms.

Technical Specification Quantity variation

We request KSPDCL mention the maximum allowable

quantity variation in percentage.

Modified Vol I uploaded.

Technical Specification Quality Test

We understand the minimum quantity of R/F steel and

cement bags per lot supplied to the site shall be sent

for testing. Kindly confirm and request you to indicate

the applicable Quantity.

As per respective IS codes.

Modified Vol I uploaded.

Page 44: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

44

Technical Specification M-Sand

We request your confirmation for usage of M-sand in

place of river sand for RCC works

For plastering works, river sand

only shall be used and M-sand

can be used for concrete works.

Technical Specification Transformer foundation

We request to clarify if the transformer foundation shall

be designed to accommodate the oil within the dyke

wall in order to avoid constructing the separate oil pit?

Separate provision for oil

drainage sump is made. Hence,

accommodating the oil within

the dyke wall does not arise.

Modified Vol II uploaded.

Technical Specification RMC - Acceptance

We request your acceptance for usage of design mix

concrete for the RCC works?

As per IS code, RMC is allowed for

construction.

Technical Specification Anti weed treatment

Kindly clarify weather antiweed treatment is only

applicable for the depth below the 100mm of

switchyard gravel spreading

As per standards in practice.

Price Schedule Switchyard RCC road

We request you to confirm that the scope for

construction of RCC road is only applicable within the

substation boundary.

Yes. RCC road is within the

substation boundary.

Technical Specification Parking shed

We request you to confirm parking shed is not

applicable for the specific contract.

Parking areas shall be provided

for site personnel and visitors at

convenient locations.

Technical Specification Fire wall

Kindly confirm weather plastering is applicable for the

fire protection

Provision for baffle wall is deleted

in the modified BOQ uploaded

on 21-01-2016.

Modified Vol III uploaded.

Page 45: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

45

Technical Specification Security compound wall

We understand that construction of security compound

wall with chain link fence is not applicable for the

specific contract.

The provisions provided in the

Technical specifications shall

stand replaced with the

provisions provided in B15 of BOQ

civil uploaded on 21-01-2016.

Modified Vol II & Vol III uploaded.

Technical Specification Control Room Building

We request your acceptance for change of control

design during detailed engineering based on the

feasibility.

The designs provided in the Bid

document are only provisional.

However, the detailed

engineering drawings are to be

got approved prior to execution

of the work for approval before

taking of work.

Technical Specification False Ceiling

Kindly provide the details for the location of false

ceiling in the proposed substation building

No False Ceiling is proposed for

substation control room building

Technical Specification Construction Power & Water

We request you to provide us the source for

construction water and power at a single point. Kindly

confirm

Arranging power and water for

construction shall be the

responsibility of the Contractor.

KSPDCL shall not be responsible

for arranging construction power

and water.

Technical Specification Testing laboratory

We request you to provide the details for the approved

construction material testing laboratory.

Testing has to be done by NABL

accredited Laboratory.

Site office, Labour camps, stores etc Site office, Labour camp

We request you to permit us for having site office /

stores / skilled labour camps within KSPDCL proposed

site for smooth coordination works.

The successful Bidder has to

establish site office for smooth

coordination works within KSPDCL

proposed site.

Page 46: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

46

Hindrances in the proposed site Site Hindrances

Trees / bushes / scrap materials / collapsed boundary

wall / cable drums / stores etc – These are the items

which will cause hindrance during execution, Kindly

confirm that the site will be handed over encumbrance

free by clearing all the items as specified.

As per Technical specification Vol

II (3 of 3) captioned “Site

Leveling” provides for

Clearing the site area free of

bushes, trees including removal of

roots, any unsuitable materials,

demolition of any temporary

building/structure and removal of

debris/unserviceable materials,

stacking within the premises or

any disposal point away from the

station area as per the decisions

of the Engineer in charge of the

work and stacking of

useful/serviceable materials

outside the yard within the station

premises in the manner directed.

Modified Vol II uploaded.

General - Construction items Approved Vendors

Request KSPDCL to provide the details of makes of

major construction materials like cement, R/F steel ,

structural steel, tiles, pipes, paints etc…

Materials for construction should

confirm with the respective

standards as per IS codes.

General - Field quality plan Field Quality Plan.

Request M/s.KSPDCL to provide the field quality plan for

civil works

The successful bidder shall

provide the quality assurance

plan for approval before taking

up of work.

NIT Clause No. 3 : Commissioning 12 months for Lot I and 18 Months for Lot II from the

date of Letter of Award/ Letter of Intent (as applicable)

including Monsoon period.

We request your consideration for completion of 18

The commissioning period for

both the Lots is 12 months from

the date of Letter of Award/

Letter of Intent (as applicable)

Page 47: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

47

months for both the Lots. including Monsoon period.

Modified Vol I uploaded.

NIT : Clause No.5 : EMD Bids shall be accompanied by Bid security (EMD) for Rs.

210.00 Lakhs for Lot I and Rs.190.00 Lakhs for Lot II as

follows: We understand the submission of bids for either

1 Lot is acceptable. Kindly confirm.

The bidder has the option to

participate in either of the Lots or

both the Lots. However, if

intending to participate in both

the lots, the Bidder has to meet

the qualifying requirements

cumulatively.

Modified Vol I uploaded.

NIT : Clause No.6 : Qualifying

Requirement

The Bidder or his JV partner should possess valid Super

Grade Electrical Contractor‟s License issued by the

Government of Karnataka as on the date of opening

of techno-commercial bid We request your

consideration for submission of "Super Grade License"

along with LOI/Purchase Order Acceptance

Bidder or his JV partner should

possess valid Super Grade

Electrical Contractor‟s License

issued by the Government of

Karnataka as on the date of

opening of techno-commercial

bid.

The following listed criteria for

qualification at section 3

evaluation and qualification

criteria-without pre qualification

appearing in pages 1-42 to 1-55

of Volume I which was uploaded

on 29-12-2015 shall stand deleted.

2.1 Eligibility

2.2 Historical Contract non

performance

2.3 Financial situations

2.4 Experience

Page 48: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

48

2.5 Personnel

2.7. Sub contractors

Modified Vol I uploaded.

NIT : Clause No.6 : Qualifying

Requirement

TRANSMISSION LINE: For one lot

Should have constructed 220/66kV Transmission Line or

above category on Total Turnkey basis or Partial

Turnkey basis to an extent equivalent to the length of

the line proposed in the tender or to an extent of 25

kmswhich ever is less in the last Seven years preceding

the date of Bid submission, out of which 50% of the

above quantity or 15 Km whichever is less shall be in

satisfactory service for a period of One year prior to the

date of submission of the Bid.

We understand the clause is applicable for the tender

irrespective of the specific Lot.

“220/66kV” shall be read as

“220kV” only in the Qualifying

Requirement of TRANSMISSION

LINE as 66kV Transmission Line are

not envisaged in this package.

In the same clause at note 2, it is

specified that “In case the bidder

is quoting for Lot 1 & Lot 2, then

the bidder shall meet the

qualifying requirements

cumulatively”.

Modified Vol I uploaded.

Price Sheet : BOQ Station : Column 3a: Quantity / Station

We understand the indicative quantity for 1 substation

is provided in the price sheet We request your clarity for

Column 5 & 6 : Total Qty - Lot 1 & Lot II shall be multiples

of the substation per lot i.e.

"Colum 5 = Column 3a x 4 & Colum 6 = Column 3a x 4"

Kindly confirm.

In the BOQ wherein the quantity /

station is indicated, the bidder

shall have to multiply by 4 times

and to be indicated in Lot 1 and

similarly for Lot 2. If participating in

both the lots, the total quantity is

the sum of Lot1 & lot 2. However,

in the BOQ for transmission lines

for Lot1 at Annexure 13 & 14 and

for Lot 2 at Annexure 15&16, the

quantities indicated are on Lot

wise basis for 4 stations in each

lot.

Modified Vol III uploaded.

Page 49: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

49

Price Sheet : BOQ Tr. Line Transmission Line BOQ. We request you for the

Transmission Line BOQ.

Details are provided in the

corrigendum uploaded on 21-01-

2016.

Modified Vol III uploaded.

Price Sheet : Civil BOQ Line Item No. B1a, B1b, B2.iv, B2.xii, B2.xiii, B2.xiv, B2e,

B3vi, B3vii, B8 (3), We understand the said line items with

"0" quantity shall not be considered for evaluation.

Modified BOQ have been

provided in the corrigendum

uploaded on 21-01-2016.

Modified Vol III uploaded.

We understand that in Price Excel Sheet the Column

No. 3A of BOQ Substation Sheet is showing the Quantity

of one substation and Bidder to multiply this quantity

with 4 if quoting One lot and multiply by 8 if quoting

both lots. Please confirm if our understanding is correct.

In the BOQ wherein the quantity /

station is indicated, the bidder

shall have to multiply by 4 times

and to be indicated in Lot 1 and

similarly for Lot 2. If participating in

both the lots, the total quantity is

the sum of Lot 1 & lot 2. However,

in the BOQ for transmission lines

for Lot1 at Annexure 13 & 14 and

for Lot 2 at Annexure 15&16, the

quantities indicated are on Lot

wise basis for 4 stations in each

lot.

Modified Vol III uploaded.

GA drawing of Substation Plot Area is not available.

Please provide.

GA drawing of Substation Plot

Area has been provided in the

corrigendum uploaded on 21-01-

2016.

Modified Vol II uploaded.

Please confirm if Land for Substation work is already

identified and acquired by KSPDCL.

Land for substation has been

identified and acquisition of land

on lease basis is under process.

Page 50: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

50

Please provide the list of approved vendor OR criteria

of vendor acceptance.

Vendors list approved by KPTCL is

accepted. However in respect of

150MVA Power transformers,

approved vendor list for 100MVA

power transformer will also be

considered.

Please mention the Quantity variation clause.

The designs provided in the Bid

document are only provisional.

However, the detailed

engineering drawings are to be

got approved prior to execution

of the work.

Modified Vol I uploaded.

Please confirm if quoting both Lots, Bidder can submit

single Bank Guarantee of Rs. 3.90 Cr.

Since the bid document provides

for separate evaluation for both

the lots, separate bank

guarantees for each of the lots

need to be provided.

Modified Vol I uploaded.

We understand that any additional item which is not

reflecting in BoQ Station and BoQ Civil will be paid

extra. If yes, how the rate of that item will be arrived.

Please confirm

All the required items have been

reflected in the BOQ station and

BOQ Civil. Hence, the question of

paying extra amount for

additional item does not arise.

In Schedule -3A & 3B, BoQ is not furnished for

Transmission Line. Please confirm if complete Design

and Engineering for Transmission line will be in Bidders

Scope.

Modified BOQ for transmission line

have been provided in the

corrigendum uploaded on 21-01-

2016.

Modified Vol III uploaded.

Please furnish the tentative route of Transmission Line

proposed by KSPDCL.

KSPDCL has provided the

tentative BOQ for transmission

line. However, conducting the

detailed survey vests with the

Page 51: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

51

Successful Bidder subject to

approval by KSPDCL.

Modified Vol III uploaded.

Please provide Soil Report is available for the Land.

Preliminary Geo Technical study

in respect of location of each of

the station is uploaded. However,

the successful bidder needs to

conduct geo-technical

investigation before taking up of

design of various structures.

We request KSPDCL that as per tender terms let us

know when we can go for Site Visit along with KSPDCL

official in order to understand the Project Site details.

As decided in the pre bid

meeting, site visit was proposed

on 25-01-2016.

PQ clause as mentioned in 2.4.2 (b) in Section-III is not

reflecting in the PQ clause no. 6. Please confirm which

one need to followed.

PQ clause as mentioned in 2.4.2

(b) in Section-III is deleted.

However, the PQ as mentioned in

Clause 6 shall prevail over.

Modified Vol I uploaded.

Price schedule is given in Excel Sheet. Hence we

understand that Schedule No. 1 to 6 as given in

Section-IV page no. 63 to 68 are not applicable.

Format of these price schedules are different than the

price schedule given in Excel sheet. Please confirm.

Schedule No. 1 to 6 as given in

Section-IV page no. 63 to 68 are

not applicable.

Bidder has to upload in the price

sheets provided in the Excel

sheets.

Modified Vol III uploaded.

Refer the Declaration form at page no. 71 in Section-IV.

As per point no. 3, we are to mention Make of

equipment and Value to get the Certificate. Also as

per point no. 4, we cannot modify this list once tender

will be opened. But it is very difficult to freeze the single

vendor name during bidding stage. Secondly, Value

Modified Vol I uploaded.

Page 52: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

52

cannot be mentioned in Technical Bid format. Please

clarify.

Refer Form FUNC at page no. 80 of Section-IV. We

understand that here bidder to mention the Losses

(NLL, LL and Auxiliary Loss) proposed for offered Power

Transformer. Please confirm.

Modified Vol I & Vol II uploaded.

Refer the clause no. 37 of Section-VII. It is not clear that

if the project affected by the event of Force Majeure,

the payment of all executed work at site will be paid by

Customer or not. Please clarify.

Notwithstanding GC Sub-Clause

37.5, Force Majeure shall not

apply to any obligation of the

Employer to make payments to

the Contractor herein.

Modified Vol I uploaded.

Refer the Appendix-4. No. of days as mentioned in

Table and as mentioned in Para 6 is not matching with

each other. Please check

The time schedule for

commissioning of the proposed

stations in either of the LOTS shall

stand revised to 12 months from

the Letter of award/Letter of

intent (as applicable) including

monsoon period.

Modified Vol I uploaded.

Refer the clause no. 4.4 of Section-IX (Appendix-8) and

PC clause no. PC30. Please clarify whether limit of

liability is 100% of Project value or 110% of Project Value

Modified Vol I and Vol II

uploaded.

The file “Volume –II (2 of 3)” available on Website is

having some problem while opening. Please check

Modified “Volume –II has been

uploaded

Refer the Declaration form at page no. 71 in Section-IV.

Modified Vol I uploaded.

Page 53: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

53

As per point no. 3, we are to mention Make of

equipment and Value to get the Certificate. Also as

per point no. 4, we cannot modify this list once tender

will be opened. But it is very difficult to freeze the single

vendor name during bidding stage. Secondly, Value

cannot be mentioned in Technical Bid format. Please

clarify.

Tender Notification- Qualifying

Requirement Cl. 3.2 of Sl. No. 6 TRANSMISSION LINE :For one lot

Should have constructed 220/66kV Transmission Line or

above category on Total Turnkey basis or Partial

Turnkey basis to an extent equivalent to the length of

the line proposed in the tender or to an extent of 25

kms whichever is less in the last Seven years preceding

the date of Bid submission, out of which 50% of the

above quantity or 15 Km whichever is less shall be in

satisfactory service for a period of One year prior to the

date of submission of the Bid

“220/66kV” shall be read as

“220kV” only in the Qualifying

Requirement of TRANSMISSION

LINE as 66kV Transmission Line are

not envisaged in this package.

Modified Vol I uploaded.

Tender Notification- Qualifying

Requirement Cl. 3.2 of Sl. No. 6

Tender calls for 220/66kV Transmission Lines as

Prequalification requirement from Bidders. Please clarify

bidders having PQR for Tr. Lines from 66kV upto 132kV

are also eligible to participate.

Also, please clarify Contractors meeting PQR of

Transmission line with 66kV upto 132kV can be

considered as a Sub contractor (without Consortium)

by the main bidder for meeting the prequalification

Clause 3.2 of NIT specifies that:

Bidder Should have constructed

220kV Transmission Line or above

category on Total Turnkey basis or

Partial Turnkey basis……….. As

such, the bidders request for

having PQR for Tr. Lines from 66kV

upto 132kV can not be

considered for participating in

the tender.

Since the work is awarded to the

main contractor the experience

of the sub contractor /labour

contractor cannot be considered

as a qualifying requirement for

Page 54: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

54

requirement. awarding the work to main

contractor.

Modified Vol I uploaded.

General We understand, in price schedule sheet “BOQ Station”,

quantity of varies equipment indicated for per

substations only.

In the BOQ wherein the quantity /

station is indicated, the bidder

shall have to multiply by 4 times

and to be indicated in Lot 1 and

similarly for Lot 2. If participating in

both the lots, the total quantity is

the sum of Lot 1 & lot 2. However,

in the BOQ for transmission lines

for Lot1 at Annexure 13 & 14 and

for Lot 2 at Annexure 15&16, the

quantities indicated are on Lot

wise basis for 4 stations in each

lot.

The quantities provided in the Bid

document are only provisional.

However, the detailed

engineering drawings are to be

got approved prior to execution

of the work for assessing the

actual quantity.

Modified Vol III uploaded.

General We understand, bidder to quote unit rate for all 4

substation in lot-1 & lot-2. Bidder shall be paid as per

actual quantity measured during execution.

General We understand layout and SLD shall be common for all

4 substation in lot-1 and lot-2.

Yes

General We understand all statutory approval shall not be in

bidder‟s scope.

All clearance and approvals

required by Bidder‟s except

the following shall be

obtained by KSPDCL:

1. Drawing & safety Approval

by Chief Electrical Inspector,

GoK.

Page 55: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

55

2. RT and RD Pre

Commissioning approval –

RT Department, KPTCL.

3. Station Commissioning and

pre commissioning by –

KPTCL and ESCOM.

4. Material inspection by

TA&QC wing, KPTCL

General Please provide the line length for all the substations. Modified Vol III uploaded.

However, conducting the

detailed survey vests with the

Successful Bidder subject to

approval by KSPDCL.

General We understand, supply of PLCC for remote end is not in

bidder‟s scope

The provision for PLCC system has

been deleted in the BOQ station.

Modified Vol III uploaded.

Volume IIA , 1of 3 Appendix-3, Part 1

of 2

Technical Parameters of Current Transformers (Type &

Rating)

It is mentioned as “Please refer uploaded scanned

copy of APPENDIX-3 Technical particulars for Current

Transformers”. Appendix 3 is missing in the uploaded

documents. Request to furnish the same.

Modified Vol II uploaded.

Tech. Spec. Vol II 1of 3 page 12 of 14,

Volume-IIA Annexure-II Section-I S.No

5 Altitude - up to 1500 Mtr.

As per mentioned clause altitude is upto 1500 Mts but

as per Tech. Spec. 2.Vol ii a (2 of 3) page 66, Cl3.0 (f)

Maximum altitude above mean sea level [Mtrs] is 1000

Mets. Please clarify the requirement.

For all the proposed 8 stations,

the details provided in Vol IIA 1 of

3, page 12 of 14 i.e altitude - up

to 1500 Mtr shall be considered.

Tech. Spec. 2.Vol ii a (2 of 3) page 64,

Cl1.01 Scope.

Parallel operating equipments

We will provide RTCC panel which will suitable for

parallel operation. Apart from this all equipment

accessories required for parallel operation shall not be

our scope.

Parallel operation of power

transformers is in the bidder‟s

scope.

Tech. Spec. 2.Vol ii a (2 of 3) page 66, The transformers shall be designed to suit the same “rail Requirement is not applicable for

Page 56: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

56

Cl 4.02 (b) track” provided for the already existing 100MVA

transformers at 220 KV Hoody and Hebbal Stations.

We understand that mentioned requirement is not

applicable for present package. Please confirm.

present package.

Tech. Spec. 2.Vol ii a (2 of 3) page 67,

Cl 7.03

MV & TV Fault level

Please specify the short circuit level for MV (66 kV) & TV

(11 kV) Winding.

The accessories of the transformer

like bushings CTs etc., shall be

designed to withstand short time

current rating of 40KA.

Modified Vol II uploaded.

Tech. Spec. 2.Vol ii a (2 of 3) page 75,

Cl 9.03.01 j(1)

At the option of the purchaser, a large valve may be

furnished with an eccentric reducer.

Requirement is not clear. Please clarify the same.

One drain valve - 100 mm (4")

flanged at the bottom of the tank

to completely drain the tank. At

the option of the purchaser, a

large valve may be furnished with

an eccentric reducer. This valve

shall be equipped with a small

sampling cock. Also another

sampling cock shall be provided

at the top of the tank.

Modified Vol II uploaded.

Tech. Spec. 2.Vol ii a (2 of 3) page 80,

Cl 9.03.09 'E

There will be minimum eight probes inside the

transformer, out of which one probe should be

installed in top of the transformer for the detection

of top oil temperature.

We understand that we have to supply 1 Probe in each

phase of MV (66kV) & HV (220 kV) winding (6 No's Total)

& 1 No for top oil & last 1 quantity as spare for top oil.

Please confirm our understanding.

Yes.

Modified Vol II uploaded.

Tech. Spec. 2.Vol ii a (2 of 3) page 82,

Cl 9.05.01 'a)

The oil shall be got tested by R&D section, KPTCL before

filling and after filling into the transformer (before

R&D section, KPTCL will conduct

oil test duly collecting nominal

Page 57: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

57

energizing) as per relevant standards.

We understand that mentioned test by KPTCL R&D

Section are free of cost. Please confirm.

charges.

Tech. Spec. 2.Vol ii a (2 of 3) page 82,

Cl 9.05.01 'c)

For 100MVA & 150MVA transformer, the supplier shall

dispatch the transformer filled with an atmosphere of

Nitrogen.

Transformer shall be dispatch filled with dry air.

For 100MVA & 150MVA

transformer, the supplier shall

dispatch the transformer filled

with an atmosphere of Nitrogen.

Tech. Spec. 2.Vol ii a (2 of 3) page 84,

Cl 9.07.00 'e)-2

When bushings have an under -oil end of re-entrant

form, the pull – through lead shall be fitted with thea

gas bubble deflector.

Yes.

Tech. Spec. 2.Vol ii a (2 of 3) page 89,

Cl 9.10.02 'd)

The OLTC oil chamber shall have oil filling and drain

plug, oil sampling valve, relief vent and level glass, It

shall also be fitted with a Buchholtz relay the outlet of

which shall be connected to a separate conservator

tank.

We understand that mentioned Buchholz relay is oil

surge relay. Please confirm.

Yes. Buchholz relay may be read

as oil surge relay.

Tech. Spec. 2.Vol ii a (2 of 3) page 89,

Cl 9.10.02 'd)

A dial type indicating thermometer of rolrest pattern

shall be provided for OLTC and mounted in the side of

transformer at convenient height to read the

temperature in the hottest part of the oil fitted with

alarm and trip contacts

We will provide PT sensor at top of OLTC chamber to

measured OLTC oil temperature & meter at marshalling

box to display its reading.

Yes.

Tech. Spec. 2.Vol ii a (2 of 3) page 94,

Cl 9.11.02 'h)(ii)

Motor and oil pump shall be enclosed in an oil tight

container with motor leads brought through a

hermetically sealed bushing.

We will supply Inline Axial Flow pump in which pump

motor will be enclosed in air filled container. Please

confirm.

Inline Axial Flow pump shall

perform the same action as a

motor and oil pump.

Tech. Spec. 2.Vol ii a (2 of 3) page 97,

Cl 9.11.03e)

Glazed door of suitable size shall be provided for

convenience of reading.

The temperature indicators shall

be so mounted that the deals are

Page 58: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

58

Cooler control Box / Marshalling box will have glazed

window (Not fully Glazed door) to read temperature

indicator reading.

not more than 1600 mm from

ground level. Glazed door of

suitable size shall be provided for

convenience of reading.

Tech. Spec. 2.Vol ii a (2 of 3) page

108, Cl 9.16.00 ii)

ii) Temperature indicator compatible with SCADA

We will provide 4-20 mA output of temperature

indicator for SCADA Communication as per Note b

Page 108.

Yes.

Tech. Spec. 2.Vol ii a (2 of 3) page

117, Cl 12.2.2.1

The temperature rise test shall be conducted at a tap

for the worst combination of loading on the three

windings of the transformer.

As per Technical specification 11 kV winding is for

stabilizing purpose (Unloaded), hence worst

combination of loading on the three windings of the

transformer will not be applicable.

The temperature rise test shall be

conducted at a tap for the worst

combination of loading on the

three windings of the transformer.

The Contractor before carrying

out such test shall submit detailed

calculations showing alternatives

possible, on various taps and for

the three types of ratings of the

transformer and shall recommend

the combination that results in

highest temperature rise for the

test.

Tech. Spec. 2.Vol ii a (2 of 3) page

118, Cl 12.2.3.7

Dynamic short circuit withstand test shall be carried out

as per IEC 60076-5/ IS 2026-5.

We do not envisage any performance of Short circuit

test on transformer, however we will carried out design

review as per cl 7.00 B (Page 69) & submit short circuit

calculation to proof transformer short circuit withstand

capability.

Conducting dynamic short circuit

withstand test can be considered

for waiver subject to condition

that the design provided by the

bidder shall be got approved by

competent agency.

Annexure-A Page 133 Note for both

Sl. Nos 17 & 18 6(a)

In case the Bidder indicates the losses as Maximum in

the Bid, it will be considered that the Bidder has

included 10% tolerance as per IS and the Guaranteed

a) In case the Bidder indicates the

losses as Maximum in the Bid, it

will be considered that the

Page 59: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

59

loss will be arrived by deloading 10%.

We understand that if we indicate the losses as

maximum, then during factory test these losses should

be within the guaranteed value & no penalty will

impose because of same. Please confirmed our

understanding.

Bidder has included 10%

tolerance as per IS and the

Guaranteed loss will be arrived

by deloading 10%.

b) In case the Bidder indicates the

tolerances, penalty will be

levied as per para no. 8.05 and

8.09 to an extent of the limit of

the tolerance quoted.

Annexure-A Page 133 S.No 19B Note

3)

The tolerance for the above impedance values shall be

as per IS 2026-Part 1(2011) or latest version.

As per specification, required impedance value

between HV-LV & IV-LV are min. at rated MVA, hence

IS tolerance (Positive or negative) limit is not applicable

for same. Please confirm.

HV – LV: 25%, (Minimum) at line

MVA

IV – LV: 30% (Minimum) at line

MVA

Tech. Spec. 2.Vol ii a (2 of 3) page 24,

Cl 25.2

The, support structures should be hot dip galvanized

with minimum 610 gram / m2 net of zinc.

Support structure used for transformer & transformer

structure shall be paint as per procedure mentioned

under Tech. Spec. 2.Vol ii a (2 of 3) page 105 Cl 9.13.04

only.

The, support structures for

transformer & transformer

structure should be hot dip

galvanized with minimum 610

gram / m2 net of zinc.

Section - VII, GCC14 Taxes and Duties

Any additional tax impact on manufactured items /

bought out goods that will arise because of GST

implementation, shall be entirely passed on to the

customer. Please confirm the same.

In case of any statutory variation

in taxes/duties/levies or if any

tax/duty/levy is newly introduced

by the Government applicable

for this Contract with effect from

the next day of the date of

submission of the bid these

variations/additional

taxes/duties/levies will be to the

account of the owner. In case

Page 60: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

60

the Bidders indicate lesser rates of

taxes and duties with reference

to the prevailing rates of taxes

and duties at the time of bidding

any variations in the taxes and

duties would be paid/recovered

keeping the rates of taxes and

duties applicable as on the date

of bid opening as the base and

not the quoted rates of taxes and

duties for payment/recovery of

difference in the taxes and

duties. If the Contractor is

required to pay additional tax or

duty, then the owner shall

reimburse the Contractor the

additional tax or duty so paid by

the contractor against submission

of documentary evidence to the

satisfaction of the owner by the

contractor. This provision will not

be applicable to transaction

between the contractor and his

sub-suppliers, sub-contractors for

raw materials, for „bought out‟

items etc., and will be applicable

only for the „own/direct

transactions‟ between the

contractor and the owner for the

materials supplied from his own

manufacturing units and erection

and civil works.

Modified Vol I uploaded.

Section - VII, GCC 14 Taxes and Duties In case of any statutory variation

Page 61: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

61

We presume, If any rates of Tax are increased or

decreased, a new Tax is introduced, an existing Tax is

abolished, or any change in interpretation or

application of any Tax occurs during the pendancy of

the Contract, the same shall be passed on to the

Employer. And this Statutory Variation is applicable for

both Own manufactured items and Bought out items.

Please confirm.

in taxes/duties/levies or if any

tax/duty/levy is newly introduced

by the Government applicable

for this Contract with effect from

the next day of the date of

submission of the bid these

variations/additional

taxes/duties/levies will be to the

account of the owner. In case

the Bidders indicate lesser rates of

taxes and duties with reference

to the prevailing rates of taxes

and duties at the time of bidding

any variations in the taxes and

duties would be paid/recovered

keeping the rates of taxes and

duties applicable as on the date

of bid opening as the base and

not the quoted rates of taxes and

duties for payment/recovery of

difference in the taxes and

duties. If the Contractor is

required to pay additional tax or

duty, then the owner shall

reimburse the Contractor the

additional tax or duty so paid by

the contractor against submission

of documentary evidence to the

satisfaction of the owner by the

contractor. This provision will not

Page 62: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

62

be applicable to transaction

between the contractor and his

sub-suppliers, sub-contractors for

raw materials, for „bought out‟

items etc., and will be applicable

only for the „own/direct

transactions‟ between the

contractor and the owner for the

materials supplied from his own

manufacturing units and erection

and civil works.

Modified Vol I uploaded.

General Please add the clause for No nuclear use.

No nuclear use:It is understood that the Material/

equipment/services sold by the Supplier/ contractor

are not intended for use in connection with any

nuclear facility or activity, and the Owner warrants that

it shall not use or permit any third party to use the

material/ equipment/ services for such purpose,

without prior written consent of Supplier/ Contractor.

If in breach of this, any such use occurs, the Contractor

(and its parent, affiliate, suppliers and subcontracts)

disclaims all liability for any nuclear or other damage,

injury or contamination, in addition to any other rights it

may have under the Contract or law. Owner shall

indemnify the Contractor against all such liability.

Consent of Contractor under this section to any nuclear

use, if any, will be conditioned upon additional terms

and conditions that it may determine as acceptable

for protection against nuclear liability.

Not applicable.

Page 63: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

63

The Owner shall indemnify the Contractor for any and

all claims arising out of or related to contaminated or

hazardous materials:

• Pre-existing at the site/Works

• Improperly handled by customer

• Brought, generated, produced or released on site by

others executing the Related Works by other

Contractors at Site

Tender Notification Cl. 5.0 Bid Security (EMD) We request KSPDCL to accept Bank

Guarantee for the complete EMD value i.eINR 210

lakhs for Lot I and INR.190 lakhs for Lot II

Rs. 10.00 Lakhs shall be paid

through e-procurement, balance

of shall be paid through separate

BG‟s for each of the Lots.

Modified Vol I uploaded.

General Construction of the contract - Divisible contract

We understand that KSPDCL will issue three separate

contracts i.e Supply contract, ETC contract and Civil

contract, please confirm

Contract will be awarded on

total turnkey basis including

supply of all Materials, Erection

(including Civil Works), Testing

and Commissioning.

Modified Vol I uploaded.

Section IX- Contract Forms Appendix

- 1 - Price Adjustment

Supply

10% of the total EXW amount as an advance against

receipt of invoice, and an irrevocable advance

payment security for the equivalent amount.

80% of the EXW amount along with the 100% Taxes &

duties against despatch Documents on pro rata basis

against Sight Letter of Credit.

10% of the total EXW amount against Commissioning

within 30 days.

Should there be a delay in commissioning due to

reasons not attributable to the bidders, the 10%

payment shall be released within 30days from the date

of submission of invoice.

Modified Vol I uploaded.

Installation Services 10% of the total EXW amount as an advance against

receipt of invoice, and an irrevocable advance

Modified Vol I uploaded.

Page 64: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

64

payment security for the equivalent amount

80% against completion of works on pro rata basis

against Sight Letter of Credit.

10% of the total EXW amount against Commissioning

within 30 days. Should there be a delay in

commissioning due to reasons not attributable to the

bidders, the 10% payment shall be released within

30days from the date of submission of invoice.

We request to accept Price Variation Clause as per

IEEEMA for the equipment offered.

Contract Price Adjustment:

The Prices, only for the following

items, quoted by the Bidder shall

be VARIABLE in accordance with

the relevant IEEMA/CACMAI

Price Variation Formula and

Indices without ceiling during the

contractual delivery period. Price

Variation is not admissible for

other Items. The base date

applicable for Price Variation is

the date of Tendering i.e., date

of Techno-Commercial Bid

Submission date as notified

(either original or extended) as

per IEEMA/ CACMAI Circulars:

I Equipments / Materials :

13) Power Transformers

14) Circuit Breakers /

Switchgears.

15) Conductors & Ground

Page 65: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

65

Wires.

16) Lightning Arresters.

17) Transformer Oil.

18) Tower Parts, equipment

mounting/Station

Structures.

19) Control Cables.

20) HT UG Cables

21) Conductor Hardware.

22) Battery & Battery Chargers.

23) Instrument Transformers.

24) Insulators

II. In respect of above Electrical

goods covered under works

contract / procurement shall be

in accordance with the relevant

IEEMA / CACMAI Price Variation

formulae and indices.

III. In respect of Turnkey Projects

involving Civil Works and Erection

Portion shall be as per relevant

Formulae as evolved by IEEMA.

However, as far as admissibility of

price variation towards erection

and civil works is concerned, the

same would be restricted to

below appended activities only.

d) Concreting (With or without

steel reinforcement)

Page 66: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION …kspdcl.in/SP_DOCS/Queries on 220 kV tender.pdffor 66kV Isolators. Also kindly provide us the mounting height of under hung isolator

66

e) Steel reinforcement and

structural steel.

f) Any other civil works where

rates are individually/

independently indicated for

concreting (with or without

reinforcement) and Steel

reinforcement and structural

steel.

The quoted Prices for all the

remaining items shall remain fixed

during the Performance of the

Contract and shall not be subject

to variation on any account save

for change in Quantity.

Modified Vol I uploaded.

Sd/-

Chairman

KSPDCL