K115 Part III General Terms Construction

  • Upload
    artu01

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

  • 8/11/2019 K115 Part III General Terms Construction

    1/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 1 of 48

    INDEX OF SECTIONSPAGE

    1.0 GUARANTEES .............................................................................................................................. 4

    2.0 INSPECTION, TESTING AND QUALITY CONTROL ................................................................... 5

    3.0 CONDITIONS AND RISKS OF WORK ......................................................................................... 6

    4.0 ISSUED FOR CONSTRUCTION DRAWINGS AND SPECIFICATIONS ...................................... 7

    5.0 INTENT OF SPECIFICATIONS AND DRAWINGS ....................................................................... 7

    6.0 SAFETY AND CLEAN-UP ............................................................................................................. 8

    7.0 SUBCONTRACTS AND PURCHASE ORDERS .......................................................................... 9

    8.0 TERMINATION FOR DEFAULT .................................................................................................. 10

    9.0 STOP WORK ORDERS ............................................................................................................... 12

    10.0 SCHEDULING, REPORTING AND COORDINATION ................................................................ 12

    11.0 OVERTIME ................................................................................................................................... 13

    12.0 DELAYS ....................................................................................................................................... 14

    13.0 POSSESSION PRIOR TO COMPLETION .................................................................................. 15

    14.0 NOTICE OF COMPLETION AND FINAL ACCEPTANCE .......................................................... 15

    15.0 CHANGES ................................................................................................................................... 16

    16.0 SUSPENSION OF WORK ........................................................................................................... 17

    17.0 TERMINATION AT COMPANYS OPTION ................................................................................. 18

    18.0 CLAIMS ........................................................................................................................................ 19

    19.0 PROTECTION OF MATERIALS, EQUIPMENT AND WORK ..................................................... 21

    20.0 CONTRACTOR'S CONSTRUCTION EQUIPMENT .................................................................... 21

    21.0 CONTRACTOR'S SHIPMENTS .................................................................................................. 22

  • 8/11/2019 K115 Part III General Terms Construction

    2/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 2 of 48

    22.0 CONTROL OF COMPANY FURNISHED MATERIALS .............................................................. 22

    23.0 CARE, CUSTODY, CONTROL AND TITLE TO MATERIALS AND EQUIPMENT .................... 23

    24.0 CONTRACTOR'S PERSONNEL ................................................................................................. 24

    25.0 LABOR HARMONY ..................................................................................................................... 26

    26.0 EMPLOYMENT CERTIFICATIONS AND PRACTICES .............................................................. 27

    27.0 WORK RULES ............................................................................................................................. 28

    28.0 INDEMNITY .................................................................................................................................. 28

    29.0 INSURANCE ................................................................................................................................ 30

    30.0 SURETY INSTRUMENTS ............................................................................................................ 33

    31.0 CONTRACTUAL RELATIONSHIP .............................................................................................. 33

    32.0 PERMITS AND LICENSES ......................................................................................................... 35

    33.0 INDEPENDENT CONTRACTOR ................................................................................................. 35

    34.0 CONFIDENTIAL INFORMATION ................................................................................................ 35

    35.0 PUBLICITY .................................................................................................................................. 35

    36.0 OWNERSHIP AND USE OF DRAWINGS ................................................................................... 35

    37.0 ASSIGNMENTS ........................................................................................................................... 36

    38.0 LAWS AND REGULATIONS ....................................................................................................... 36

    39.0 EMERGENCY MEDICAL SERVICES ......................................................................................... 37

    40.0 DOCUMENTATION AND RIGHT OF AUDIT .............................................................................. 38

    41.0 LIENS ........................................................................................................................................... 39

    42.0 RIGHT TO OFFSET ..................................................................................................................... 39

    43.0 FINAL PAYMENT CERTIFICATION AND RELEASE ................................................................ 40

  • 8/11/2019 K115 Part III General Terms Construction

    3/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 3 of 48

    44.0 ARBITRATION OPTION .............................................................................................................. 40

    45.0 VALIDITY OF PROVISIONS ....................................................................................................... 40

    46.0 WAIVER ....................................................................................................................................... 41

    47.0 BUSINESS CONDUCT AND ETHICS EXPECTATIONS ............................................................ 41

    48.0 INTERPRETATION ...................................................................................................................... 42

    49.0 SURVIVAL ................................................................................................................................... 42

    50.0 WAIVER OF TRIAL, DISPUTE RESOLUTION ........................................................................... 42

    51.0 EXPORT AUTHORIZATIONS ..................................................................................................... 43

    52.0 LOSS PREVENTION; SAFETY AND SECURITY; ENVIRONMENTAL POLICY ...................... 44

    53.0 PERSONNEL ............................................................................................................................... 46

    54.0 EMPLOYEE RELATIONS ........................................................................................................... 47

    55.0 COMPLIANCE WITH OCCUPATIONAL HEALTH AND SAFETY LAWS ................................. 47

  • 8/11/2019 K115 Part III General Terms Construction

    4/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 4 of 48

    WORK QUALITY STANDARDS

    1.0 GUARANTEES

    1.1 Contractor guarantees Company and Engineer that the Work shall complystrictly with the provisions of this Contract and all specifications, drawings andstandards referred to in this Contract or thereafter furnished by Company, andthat the Work shall be first-class in every particular and free from defects inmaterials and workmanship and in any design or engineering furnished byContractor. Contractor further guarantees Company and Engineer that allmaterials, equipment and supplies furnished by Contractor for the Work shallbe new, merchantable, of the most suitable grade and fit for their intended

    purposes. Without limitation of any other rights or remedies of Company orEngineer, if any defect in the Work in violation of the foregoing guaranteesarises within the period set forth below, Contractor shall, upon receipt of writtennotice of such defect, promptly furnish, at no cost to Company or Engineer,design and engineering, labor, equipment and materials necessary to correctsuch defect and cause the Work to comply fully with the foregoing guarantees.

    1.2 Contractor's guarantees set forth in Section 1.1 shall extend for twenty-four(24) months after the date of final written acceptance of the Work by Companyor eighteen (18) months after the start of regular operation or use of the Workby Company, whichever occurs first. Any period wherein the Work is notavailable for use due to defects in materials, workmanship or engineering

    furnished by Contractor shall extend the guarantee period by an equal periodof time.

    1.3 Design and engineering, labor, equipment and materials furnished byContractor pursuant to Section 1.1 in order to correct defects shall beguaranteed by Contractor in accordance with the guarantees set forth inSection 1.1 for a period of eighteen (18) months from the date of completion ofthe correction, or for the remainder of the guarantee period set forth inSection 1.2 above, whichever is longer.

    1.4 In the event Contractor has been notified of any defects in the Work in violationof Contractor's foregoing guarantees and fails to promptly and adequately

    correct such defects, Company and Engineer shall have the right to correct orto have such defects corrected for the account of Contractor, and Contractorshall promptly pay Company the costs incurred in correcting such defects.

  • 8/11/2019 K115 Part III General Terms Construction

    5/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 5 of 48

    1.5 Contractor shall include, at a minimum, the foregoing guarantee requirementsin any subcontract that it places.

    1.6 To the extent that Contractor performs procurement services for the Work,Contractor will demand from its contractors, manufacturers and supplierswritten warranties, equipment manuals, parts lists, operating instructions,maintenance instructions and repair instructions on all services, materials andequipment relating to the Work, deliver copies to Company in a form andmedia required by Company and enforce them on behalf of Company.

    2.0 INSPECTION, TESTING AND QUALITY CONTROL

    2.1 Contractor shall inspect all materials, supplies and equipment which are to beincorporated in the Work. In addition, Contractor shall conduct a continuousprogram of construction quality control for all Work. Contractor's quality controlprogram and inspection procedures for the foregoing shall be submitted inwriting to Company for review and approval, in sufficient detail to delineatethose items to be inspected and the manner in which they are to be inspected,and shall adequately describe all construction quality control activitiescontemplated, including provision for adequate documentation of Contractor'sperformance of such quality control and inspection. No such review andapproval by Company or Engineer will relieve Contractor from its quality controland inspection obligations under this Contract, nor constitute Companysassumption of responsibility for quality control and inspection, nor constitute

    any change in the obligations that Contractor has regarding guarantees or anyother right described in this Contract.

    2.2 Contractor shall, during the course of performance of the Work hereunder,without additional compensation, make or cause to be made all tests requiredby this Contract. Company or Engineer may require additional inspections andtests. Contractor shall furnish Engineer with satisfactory documentation of theresults of all inspections and tests. Company and Engineer shall be given notless than five (5) working days notice of any tests to be made by Contractor orContractor's subcontractors in order that Company or Engineer may witnessany such tests.

    2.3 Company and Engineer and their representatives, and others as may berequired by applicable laws, ordinances and regulations, shall have the right atall reasonable times to inspect the Work and all material, supplies andequipment for the Work at the jobsite and at Contractor's and its

  • 8/11/2019 K115 Part III General Terms Construction

    6/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 6 of 48

    subcontractors' shops for conformance with the Contract. Contractor shallprovide, or cause to be provided access and sufficient, safe and properfacilities for such inspections. Neither the failure to make such inspection nor todiscover defective workmanship, materials or equipment, nor approval of orpayment to Contractor for such Work, materials or equipment shall prejudicethe rights of Company or Engineer.

    2.4 If Contractor covers any portion of the Work prior to any inspection or testprovided for in the specifications, inspection schedule, or as previouslyrequested by Company or Engineer, the cost of uncovering and covering theWork to allow for such inspection or test shall be borne by the Contractor.Reexamination of any Work may be ordered by Company or Engineer. In the

    event of such reexamination, if any material, equipment or any part of the Workis determined by Company or Engineer to be defective, Contractor shall not bereimbursed for uncovering, repair or corrective and restoration costs. If suchWork is found to be in accordance with the Contract requirements upon suchreexamination, Company shall pay Contractor the cost of uncovering andrestoration.

    2.5 Rejection by Company or Engineer of any or all parts of defective Work forfailure to conform to this Contract shall be final and binding. Such rejectedWork shall be promptly corrected or replaced by Contractor at Contractor'sexpense. If Contractor fails to commence and diligently continue correction orreplacement of such rejected Work immediately after receipt of written notice

    from Engineer to correct or replace the rejected Work, Company may at itsoption remove and replace the rejected Work, and Contractor shall promptlyreimburse Company for the costs of such removal and replacement ofdefective Work.

    3.0 CONDITIONS AND RISKS OF WORK

    Contractor represents that it has carefully examined the documentation, drawings andspecifications for the Work and has fully acquainted itself with all other conditionsrelevant to the Work, and its surroundings, and Contractor assumes the risk of suchconditions and will, regardless of such conditions, the expense, difficulty of performingthe Work, or negligence, if any, of Company or Engineer, fully complete the Work for

    the stated Contract Price without further recourse to Company or Engineer.Information on the site of the Work and local conditions at such site furnished byCompany or Engineer in specifications, drawings or otherwise is not guaranteed byCompany or Engineer and is furnished only for the convenience of Contractor.

  • 8/11/2019 K115 Part III General Terms Construction

    7/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 7 of 48

    4.0 ISSUED FOR CONSTRUCTION DRAWINGS AND SPECIFICATIONS

    4.1 The Work shall be performed using only drawings and specifications marked"Issued for Construction" or equivalent by Engineer. Such indication shall notrelieve Contractor of any obligations under this Contract, nor constituteCompany's or Engineers assumption of responsibility for the accuracy oradequacy of any of Contractor's information or Work incorporated in suchdocuments.

    4.2 Contractor shall perform all Work outside of the areas marked "HOLD" on"Issued for Construction" specifications and drawings to maintain the scheduleof Work, but shall not perform any Work in the areas or sections marked

    "HOLD" on "Issued for Construction" specifications and drawings until revised"Issued for Construction" specifications and drawings are received with the"HOLD" markings deleted.

    4.3 If Contractor's schedule will be delayed by "HOLD" markings on specificationsand drawings, Contractor shall report such delay to Engineer immediately inwriting but in any event not less than five (5) working days prior to the start ofthe delay.

    4.4 Contractor shall maintain at the work site a complete and current set of "Issuedfor Construction" drawings and specifications.

    5.0 INTENT OF SPECIFICATIONS AND DRAWINGS

    5.1 The specifications and drawings may not be complete in every detail.Contractor shall comply with their manifest intent and general purpose, takenas a whole, and shall not make use of any errors or omissions therein to thedetriment of the Work. Should any conflict, error, omission or discrepancyappear in the drawings, specifications, instructions, in work done by others, orin site conditions, Contractor shall notify Engineer in writing at once andEngineer will issue written instructions to be followed. If Contractor proceedswith any of the Work in question prior to receiving such instructions, thenrequired corrections shall be at Contractor's expense.

    5.2 Contractor shall not deviate from the specifications and drawings without priorwritten approval from Company.

  • 8/11/2019 K115 Part III General Terms Construction

    8/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 8 of 48

    5.3 Materials shall not be substituted for those specified, nor shall "or equal" itemsbe furnished pursuant to the specifications without Company prior writtenapproval.

    6.0 SAFETY AND CLEAN-UP

    6.1 Contractor shall take necessary safety and other precautions to protectproperty and persons from damage, injury or illness arising out of theperformance of the Work. Contractor shall comply strictly with local, municipal,provincial, state and national laws, orders, and regulations pertaining to healthor safety which are applicable to Contractor or to the Work, includingapplicable Peruvian laws, and including without limitation the Occupational

    Safety and Health Act of 1970 (84 U.S. Statutes 1590), as amended, and anystate plans approved thereunder and regulations thereunder, to the extentapplicable, and Contractor warrants the materials, equipment and facilities,whether temporary or permanent, furnished by Contractor in connection withthe performance of the Work shall comply therewith. In the event that servicesare performed outside the United States of America, safety and health acts,laws and regulations of the country where the services are to be performedshall apply. At all times while any of Contractor's employees, agents orsubcontractors are on Company's premises, Contractor shall be solelyresponsible for providing them with a safe place of employment, andContractor shall inspect the places where its employees, agents orsubcontractors are or may be present on Company's premises and shall

    promptly take action to correct conditions which are or may become an unsafeplace of employment for them.

    6.2 Accidents, injuries and illnesses requiring medical attention other than first aid,damage to property of Company or Contractor, and fires shall be orallyreported immediately to Company at the time of the incident. Written reports,satisfactory in form and content to Company shall be submitted by Contractorwithin forty-eight (48) hours after each incident. Contractor shall be familiarwith Peruvian laws regarding reports to authorities in order to allow Companyto comply with the law on time.

    6.3 Contractor shall maintain, in form and content approved by Company, jobsite

    accident, injury and illness statistics which shall be available for inspection by,and submitted to, Company upon its written request.

  • 8/11/2019 K115 Part III General Terms Construction

    9/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 9 of 48

    6.4 Contractor shall keep Companys and Engineers premises and the vicinitythereof clean and free of any debris and rubbish caused by the Work and oncompletion of the Work, shall leave such premises clean and ready for use.

    Areas used for the purposes of material/equipment lay-down, temporaryfacilities, storage and the like shall be restored to the condition existing prior toContractors occupation.

    7.0 SUBCONTRACTS AND PURCHASE ORDERS

    7.1 Contractor shall not subcontract performance of all or any portion of the Workunder this Contract without first notifying Engineer of the intendedsubcontracting and obtaining Companys acceptance in writing of the

    subcontracting and the subcontractor. If requested by Company, Contractorshall furnish Company or Engineer a copy of the proposed subcontract (withprice deleted if the subcontracted work is part of fixed price Work of Contractorunder this Contract) for Company review of the terms and conditions thereofand shall not execute such subcontract until Company has accepted suchterms. Failure of Contractor to comply with this Section may be deemed byCompany to be a material breach of this Contract. By doing this Company isnot assuming any responsibility regarding obligations by Contractor of itssubcontractors.

    7.2 Contractor guarantees that its subcontractors will comply fully with the terms ofthis Contract applicable to the portion of the Work performed by them. If any

    portion of the Work which has been subcontracted by Contractor is notprosecuted in accordance with this Contract, on request of Company, thesubcontractor shall be replaced at no additional cost to Company, includingcosts which may arise from additional work or resources to be employed tomaintain schedule and performance parameters, and such subcontractorsshall not be employed again on the Work.

    7.3 Contractor shall include a provision in every subcontract that it placesauthorizing assignment of such subcontract to Company or Engineer withoutrequiring further consent from such subcontractor or supplier.

    7.4 Company or Engineer shall have the right from time to time to contact

    Contractor's subcontractors to discuss their progress.

    7.5 As used in this Contract, the term "subcontract" shall also include purchaseorders and rental agreements for materials or equipment, and the term

  • 8/11/2019 K115 Part III General Terms Construction

    10/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 10 of 48

    "subcontractor" shall also include vendors or suppliers of such material orequipment.

    7.6 Contractor shall not be relieved of its responsibility for the Work by virtue ofany subcontracts it may place regardless of Company's acceptance of suchsubcontract.

    7.7 The United Nations Convention on Contracts for the International Sale ofGoods does not apply to this Contract and shall be disclaimed and excludedfrom any subcontracts placed by Contractor.

    8.0 TERMINATION FOR DEFAULT

    8.1 In the event that Contractor shall default in the performance of any obligationto be performed by Contractor under this Contract and shall fail to correct suchdefault within five (5) working days following written notice thereof fromCompany or Engineer, Company may, without prejudice to any other rights orremedies Company may have, hold in abeyance further payments toContractor and/or terminate Contractor's right to continue performance of thisContract by written notice to Contractor specifying the date of termination. Inthe event of such termination by Company, Company may take possession ofthe Work at the jobsite and any or all materials and plant equipment (whetherdelivered to the jobsite or on order therefore by Contractor), tools andconstruction equipment at jobsite and finish the Work by whatever method

    Company may deem expedient.

    8.2 In the event of termination by Company under Section 8.1, Contractor shall,upon request by Company, promptly advise it of all outstanding subcontracts,rental agreements and purchase orders which Contractor has with otherspertaining to performance of the Work and furnish Company or Engineer withcomplete copies thereof. Upon request by Company, Contractor shall assign toCompany, in form and content satisfactory to Company, Contractor's title tomaterials and plant equipment for the Work and those subcontracts designatedby Company.

    8.3 In the event of termination by Company under Section 8.1, Contractor shall not

    be entitled to receive any further payment until the Work is completed. Uponcompletion and final acceptance of the Work, Company will determine the totalcost incurred in completing the Work including, without limitation, additionaloverhead, legal and other costs incurred by Company to effect such

  • 8/11/2019 K115 Part III General Terms Construction

    11/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 11 of 48

    termination and to complete the Work, plus a markup for profit in the amount often percent (10%) on the total cost of the Work performed by Company. If thetotal costs noted above exceed the balance of the Contract Price unpaid at thetime of the termination, Contractor shall, promptly after receipt of an invoice,pay to Company the amount of such excess. Company shall have the right andis authorized to set-off against and deduct from any excess payable toContractor any other damages suffered by Company or Engineer due to saiddefault or event giving rise to the termination or due to other defaults ofContractor in complying with the terms of this Contract. Contractor shallcontinue to be fully liable for all such other damages to Company andEngineer. A waiver by Company of one default by Contractor shall not beconsidered to be a waiver of any subsequent default by Contractor, nor be

    deemed to amend or modify the terms of this Contract. Contractor expresslywaives any formal notice by Company of Contractor's failure to perform, orpassive breach of, Contractor's express obligations under this Contract.

    8.4 Contractor agrees that upon commencement of a case, receivership, civilaction or other proceeding by or against Contractor under state, federal orother applicable insolvency law, or upon any general assignment by Contractorfor the benefit of its creditors, Company may, in its sole discretion, treatContractor as in default under Section 8.1 and may exercise any of theremedies of this Section. In the event Company's remedies under this Section8.4 are limited by the commencement by or against the Contractor of a caseunder any chapter of the United States Bankruptcy Code, Contractor

    stipulates, acknowledges and agrees that time is of the essence indetermination of whether this Contract should be "assumed" or "rejected,"within the meaning of 11 U.S.C. 365; and Contractor therefore furtherstipulates and agrees that subject only to calendaring constraints of theBankruptcy Court having jurisdiction, it will take all necessary action to causethe assumption or rejection of this Contract on or before the thirtieth day filingthe Petition commencing any such case. In such event, if Contractor seeks to"assume" this Contract, Contractor expressly stipulates, acknowledges andagrees that "adequate assurance of future performance" within the meaning of11 U.S.C. 365 (b)(1)(C) means a determination that there is no foreseeablelikelihood that there will be any further interruption of Contractor's performanceunder this Contract following its assumption.

    8.5 Contractor shall be considered in default from complying with the obligations ofthis Contract whenever, by reason of strikes, picketing or disputes of anynature between Contractor and any individual, group or organization,

  • 8/11/2019 K115 Part III General Terms Construction

    12/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 12 of 48

    Contractor persistently, repeatedly, or for any period of five (5) consecutiveworking days, should be unable to supply enough properly skilled workers orproper materials or equipment to execute the Work.

    8.6 If any termination for default is determined to have been made in error, theprovisions of Section 17.0, Termination at Companys Option, shall apply.

    8.7 In the event Contractor abandons the Work or otherwise repudiates thisContract, the notice requirements of Section 8.1 shall not apply.

    9.0 STOP WORK ORDERS

    Upon failure of Contractor or its subcontractors to comply with any of the requirementsof this Contract, Engineer shall have the authority given by Company as its Engineerto stop any operations of Contractor or its subcontractors affected by such failure untilsuch failure is remedied or to terminate this Contract in accordance with Section 8.0.No part of the time lost due to any such stop work orders shall be made the subject ofa claim for extension of time or for increased costs or damages by Contractor.

    TIMING OF WORK

    10.0 SCHEDULING, REPORTING AND COORDINATION

    10.1 Contractor shall schedule and coordinate the details of the Work beingperformed to meet the schedule requirements set forth in Part I of this

    Contract. Within thirty (30) calendar days after award of this Contract andbefore submittal of the first progress payment payment application, Contractorshall submit to Engineer for approval, a detailed schedule showing thesequence in which Contractor proposes to perform the Work, the start andcompletion dates of all separable portions of the Work, manpower forecasts,materials procurement and delivery plans and any other information specifiedby Company. Contractor agrees to adhere to the schedule approved byEngineer and attend and participate in scheduled progress and coordinationmeetings called by Company or Engineer.

    10.2 During the performance of Work, Contractor shall submit to Engineer periodicprogress reports on the actual progress and updated schedules as may be

    required by this Contract or requested by Company. In the event Contractor'sperformance of the Work is not in compliance with the schedule established forsuch performance, Engineer may, in writing, require the Contractor to submitits plan for schedule recovery, or specify in writing the steps to be taken to

  • 8/11/2019 K115 Part III General Terms Construction

    13/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 13 of 48

    achieve compliance with such schedule, and/or exercise any other remediesunder this Contract. Contractor shall thereupon take such steps as may bedirected by Engineer or otherwise necessary to improve its progress withoutadditional cost to Company.

    10.3 Contractor recognizes that Company, Engineer, other contractors andsubcontractors may be working concurrently at the jobsite. Contractor agreesto cooperate with Company, Engineer and other contractors so that the projectas a whole will progress with a minimum of delays. Engineer reserves the rightto direct Contractor to schedule the order of performance of its Work in suchmanner as not to interfere with the performance of others.

    10.4 If any part of Contractor's Work is dependent upon the quality and/orcompleteness of work performed under another contract, Contractor shallinspect such other work and promptly report to Engineer any defects thereinwhich render such work unsuitable for the proper execution of the Work underthis Contract. Failure to make such inspections or to report any such defects toEngineer shall constitute Contractor's acceptance of such other work assuitable to receive Contractor's Work provided however, that Contractor shallnot be responsible for defects which could not have reasonably been detected.

    11.0 OVERTIME

    Unless expressly stated elsewhere in this Contract, Work at the jobsite shall be

    compatible with Company's starting and quitting times or other times approved byCompany. Scheduled overtime work by Contractor must be approved in advance andin writing by Company. Contractor shall notify Engineer in advance of any incidentalspot overtime which Contractor elects to work due to such operations as concreteplacement, non-disruptable work activities and emergencies to protect life and/orproperty. Overtime work, whether scheduled or incidental, shall be to Contractor'saccount unless the compensation therefore is specifically authorized in writing byCompany. In the event Company approves compensation of Contractor's overtime inadvance, such compensation as separately authorized shall be limited to the actualcost to Contractor of the premium portion only of all applicable wages, craft fringebenefits, and payroll burdens imposed by any governmental authority and measuredby the compensation payable to employees. To establish the amount of payment,

    Contractor shall submit supporting documents satisfactory in form and content toEngineer for its verification and approval by Company.

  • 8/11/2019 K115 Part III General Terms Construction

    14/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 14 of 48

    12.0 DELAYS

    12.1 In the event Contractor, Engineer or Company is delayed in performing any oftheir respective obligations in this Contract and such delay is caused by acts ofGod, war, riots, civil insurrection, acts of the public enemy, accidents, acts ofcivil or military authority, fires, floods, or earthquakes, beyond the reasonablecontrol of the party delayed, such delay will be excused and the period of suchdelay will be added to the time for performance of the obligation delayed,unless the date, schedule or time period for performance of the obligation isexpressly stated in this Contract to be guaranteed. In the event any delay dueto the foregoing causes or events occurs or is anticipated, the party delayed oranticipating delay shall promptly notify the other party in writing of such delay

    or expected delay and the cause and estimated duration of such delay. In theevent of a delay due to the foregoing causes or events, the party delayed shall,at no cost to the other party, exercise due diligence to shorten and avoid thedelay and shall keep the other party advised as to the continuance of the delayand steps taken to shorten or terminate the delay.

    12.2 Contractor shall, within five (5) working days of the commencement of anydelay, give to Engineer written notice thereof and of the anticipated effectsthereof. Within two (2) working days of the termination of any delay, Contractorshall file a written notice with Engineer specifying the actual duration of thedelay. If Engineer determines that a delay was beyond the control and withoutthe fault or negligence of Contractor or its subcontractors and not foreseeable

    by Contractor at the effective date of this Contract, Engineer shall determinethe duration of the delay and shall extend the time of performance of thisContract thereby as approved by Company.

    12.3 Contractor shall not be entitled to, and hereby expressly waives recovery of,any damages suffered by reason of delays of any nature, including thenegligence of Company and Engineer, and extension of time shall constitutethe sole liability of Company and Contractor's sole remedy for delays.

    12.4 The Delay events identified at Section 12.1 above shall expressly not includethe following conditions, except and to the extent that the following conditionsresult directly from a Delay event:

    a) Late delivery of a Work product submission required in the ContractMilestone Schedule;

  • 8/11/2019 K115 Part III General Terms Construction

    15/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 15 of 48

    b) A delay in the performance of Contract, any of Contractorssubcontractors, agent, or any assignee of Contractor, or failure of anysuch entity to comply with, and complete, the obligations specified inthis Contract in a timely manner; and

    c) Normal wear and tear, random flaws or breakdowns in software,materials or equipment.

    13.0 POSSESSION PRIOR TO COMPLETION

    Company shall have the right to move into Contractor's working and storage areasand the right to take possession of or use any completed or partially completed part of

    Contractor's Work as Company deems necessary for its operations. In the eventCompany desires to exercise the foregoing right, Company through its Engineer willso notify Contractor in writing. Such possession or use shall not constitute acceptanceof Contractor's Work.

    14.0 NOTICE OF COMPLETION AND FINAL ACCEPTANCE

    14.1 When Contractor deems the Work fully completed, including satisfactorycompletion of such inspections, tests and documentation as are specified inthis Contract, Contractor shall, within ten (10) working days thereafter, give awritten Notice of Completion of the Work to Company, specifying the Workcompleted and the date it was completed. Within thirty (30) calendar days after

    receipt of said Notice of Completion, Company may inspect the Work and shalleither reject the Notice of Completion and specify defective or uncompletedportions of the Work, or shall give the Contractor a written Notice of

    Acceptance of the Work either for the purpose of final payment only, or for thepurposes of final payment and final acceptance.

    14.2 In the event Company rejects the Notice of Completion and specifies defectiveor uncompleted portions of the Work, Contractor shall within five (5) workingdays provide for Company review and approval, a schedule detailing when alldefects will be corrected and/or the Work will be completed and shall proceedto remedy such defective and uncompleted portions of the Work. Thereafter,Contractor shall again give Company a written Notice of Completion of the

    Work, specifying a new date for the completion of the Work based upon thedate such defective or uncompleted portions of the Work were corrected. Theforegoing procedure shall apply again and successively thereafter until

  • 8/11/2019 K115 Part III General Terms Construction

    16/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 16 of 48

    Company has given Contractor written Notice of Acceptance for purposes offinal payment and final acceptance.

    14.3 Any failure by Company to inspect or to reject the Work or to rejectContractor's Notice of Completion as set forth above, shall not be deemed tobe acceptance of the Work for any purpose by Company, nor implyacceptance of, or agreement with, said Notice of Completion.

    WORK CHANGES

    15.0 CHANGES

    15.1 The Scope of Work shall be subject to change by additions, deletions orrevisions thereto by Company. Contractor will be notified of such changes byreceipt of additional and/or revised drawings, specifications, exhibits or otherwritten notification.

    15.2 If, upon receipt of any notification, Contractor considers that a change isinvolved that could affect its costs of performing the Work or upon the schedulefor performance of the Work, Contractor is obligated to inform Company andEngineer within five (5) working days of Contractor receiving the notification.Unless Contractor notifies Company and Engineer in accordance with thisSection, Contractor is obliged to perform the Work in accordance with thechange and will have no entitlement to any additional compensation or to anychange to the schedule.

    15.3 Contractor shall submit to Company and Engineer within ten (10) working daysafter submission of the notification from Contractor required under Section15.2, above, a detailed takeoff with supporting calculations and pricing for thechange, together with any requested adjustments in the schedule. The pricingshall be itemized as required by Company and shall be in sufficient detail topermit an analysis of all labor, material and equipment and shall cover all workinvolved in the change, whether such work was deleted, added or modified.

    Amounts related to subcontracts shall be supported in similar detail. Anyadjustments to the schedule must be accompanied by a revised version of thedetailed schedule, agreed in accordance with Section 10.1 demonstrating thatany proposed changes to the schedule have been caused by the change and

    have affected a critical path on such previously agreed detailed schedule.

    15.4 If Contractor does not provide the detailed take-off to Company and Engineer,within the time allowed by Section 15.3, Contractor will have waived any right

  • 8/11/2019 K115 Part III General Terms Construction

    17/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 17 of 48

    to additional compensation or to a change to the schedule, in respect of thechange and will proceed with the work in accordance with the changenotification issued pursuant to Section 15.1, above.

    15.5 Contractor shall not perform changes in the Work in accordance with Section15.1 until Company has approved in writing the pricing for the change and anyadjustment in the schedule for performance of the Work, except as set forth inSections 15.4 and 15.6. Upon receiving such written approval from Company,Contractor shall diligently perform the change in strict accordance with thisContract.

    15.6 Notwithstanding Section 15.5 Company may expressly authorize Contractor in

    writing to perform the change prior to such approval by Company. Contractorshall not suspend performance of this Contract during the review andnegotiation of any change, except as may be directed by Company orEngineer pursuant to Section 16.0, Suspension of Work. In the event Companyand Contractor are unable to reach timely agreement regarding any change,Contractor shall then comply with Section 18.0, Claims.

    15.7 Contractor shall not comply with oral changes in the Work. If Contractorbelieves that any oral notice or instruction received from Company or itsEngineer will involve a change in the cost, time to perform or integrity of theWork, it shall require that the notice or instruction be given in writing and shallcomply with the provisions of Sections 15.2, 15.3, 15.5 and 15.6. Any costs

    incurred by Contractor to perform oral changes shall be for Contractor'saccount, and Contractor waives any and all rights to claim from Company orEngineer for such costs or additional time to perform the Work as a result ofcompliance by Contractor with such oral changes.

    16.0 SUSPENSION OF WORK

    16.1 Company through its Engineer may, at any time and from time to time, bywritten notice to Contractor, suspend further performance of all or any portionof the Work by Contractor. Said notice of suspension shall specify the date ofsuspension and the estimated duration of the suspension. Such suspensionsshall not exceed one hundred eighty (180) consecutive calendar days each nor

    aggregate more than two hundred seventy (270) calendar days. Uponreceiving any such notice of suspension, Contractor shall promptly suspendfurther performance of the Work to the extent specified, and during the periodof such suspension shall properly care for and protect all Work in progress and

  • 8/11/2019 K115 Part III General Terms Construction

    18/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 18 of 48

    materials, supplies, and equipment Contractor has on hand for performance ofthe Work. Upon the request of Company or Engineer, Contractor shall promptlydeliver to Company or Engineer copies of outstanding subcontracts ofContractor and shall take such action relative to such subcontracts as may bedirected by Company. Contractor shall use its best efforts to utilize its material,labor and equipment in such a manner as to mitigate costs associated withsuspension. Company may at any time, withdraw the suspension ofperformance of the Work as to all or part of the suspended Work by writtennotice to Contractor specifying the effective date and scope of withdrawal, andContractor shall resume diligent performance of the Work for which thesuspension is withdrawn on the specified effective date of withdrawal.

    16.2 If Contractor believes that any such suspension or withdrawal of suspensionjustifies modification of the Contract Price, Contractor shall comply with theprovisions of the procedure set forth in Section 15.0, Changes. Contractorsfinal claim for modification of the Contract Price shall substantiate Contractorsincreased costs for such suspension or withdrawal of suspension, withdocuments satisfactory to Company. Upon Companys verification andapproval of such additional costs, Contractor and Company shall agree uponan adjustment in the Contract Price, based upon such verified and approvedadditional costs as full settlement to Contractor for the suspension orwithdrawal of suspension. Contractor shall not be entitled to any prospectiveprofits or any damages because of such suspensions or withdrawals ofsuspension.

    17.0 TERMINATION AT COMPANYS OPTION

    17.1 Company may, with or without cause, terminate further performance of all orpart of the Work by written notice to Contractor specifying the date oftermination. On the date of such termination stated in said notice, Contractorshall discontinue performance of the Work and shall preserve and protecttools, construction equipment and facilities on jobsite, materials and plantequipment purchased for or committed to the Work (whether delivered to the

    jobsite or on order), Work in progress and completed Work (whether at jobsiteor other locations) pending Company's or Engineers instructions and, ifrequested by it, shall turn over the same to Company, including title to said

    materials and plant equipment, or dispose of same in accordance withCompany's instructions.

  • 8/11/2019 K115 Part III General Terms Construction

    19/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 19 of 48

    17.2 Upon receipt of said notice, Contractor shall advise Company and Engineer ofits outstanding subcontracts pertaining to performance of the terminated workand, upon request, furnish Company and Engineer with complete copies.Contractor shall place no further subcontracts except as may be necessary forcompletion of such portion of the Work as is not terminated. Contractor shallpromptly make every reasonable effort to procure cancellation, upon termssatisfactory to Company, of all subcontracts to the extent they relate to theperformance of Work terminated or, as directed by Company, shall assign toCompany, in form satisfactory to Company, such of its subcontracts as aredesignated by Company or shall take such other action relative to suchsubcontracts as may be directed by Company.

    17.3 If Contractor has fully and completely performed all obligations under thisContract up to the date of termination, Contractor shall recover from Companyas complete and full settlement for such termination for Work to be performedunder this Contract, the actual costs of all such Work satisfactorily executed tothe date of termination, plus an allowance for reasonable overhead and profiton such costs incurred prior to termination (but not to exceed a pro rata portionof such Contract Price for such Work based on the percentage of Workproperly completed to the date of termination), together with reasonable costsoccasioned by such termination and not previously paid for, less such sums asContractor has already received on account of the Work performed. In noevent shall total payment to Contractor exceed the Contract Price.

    17.4 All requests for compensation under any of the foregoing provisions ofSection 17.3 shall be submitted to Company in accordance with the provisionsof Section 15.0, Changes. In no event shall Contractor be entitled to anyprospective profits or any damages.

    18.0 CLAIMS

    18.1 If, for any reason, Contractor considers that an event has occurred pursuant towhich it has a right to claim compensation from Company or an extension tothe schedule, Contractor shall notify Company and Engineer in writing of theexistence of such claim within five (5) working days of the Parties failure toreach a timely agreement pursuant to Section 15.6 for changes or from the

    occurrence of the event in question for other claims. Within ten (10) days ofgiving such a notification, Contractor shall submit to Company and Engineerthe proposed cost and schedule effect of the change. In this respect,Contractor shall comply with the provisions of Section 15.3. Contractor shall

  • 8/11/2019 K115 Part III General Terms Construction

    20/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 20 of 48

    substantiate its claim with payroll documents, paid invoices, receipts, recordsof performance and other documents satisfactory to Company and subject toits verification. Neither Company nor Engineer shall be liable for, andContractor hereby waives, any claim or potential claim of Contractor which wasnot reported by Contractor in accordance with the provisions of this Section,regardless of the cause including the negligence of Company and Engineer.

    18.2 Company will determine the extent, if any, to which the Contract Price is to bechanged by reason of the claim and the extent to which the schedule is to bechanged by reason of the claim. Company thorough Engineer will adviseContractor of the result of this determination and will issue a Contractmodification accordingly. If Contractor disputes Company's determination and

    notifies Company or Engineer within five (5) working days of receiving it,Contractor may seek to resolve the dispute in accordance with Section 50.0. IfContractor elects to proceed pursuant to Section 50.0, Contractor agrees tolimit its claim to the amount claimed by it in accordance with Section 18.1. Inno event shall any work be halted, whether or not the claim can be resolved toContractor's satisfaction, and Contractor shall be bound by the terms andconditions of this Contract to prosecute the Work without delay to its successfulcompletion.

    18.3 The following shall not constitute changes and Contractor has no right to makeany claim in relation thereto:

    18.3.1 Instructions, interpretations, decisions or acts by Company or Engineerwhich are:

    A. to achieve compliance with the Contract by Contractor; or

    B. to correct errors, omissions, poor engineering, defectiveworkmanship or other failure of the Contractor to comply with theContract;

    18.3.2 Delay in the performance of Contractors work or any additional workcaused by Contractor.

    18.3.3 Any work performed by Contractor required by Companys orEngineers comments to Contractors submittals, to the extent that suchcomments are consistent with the Contract.

  • 8/11/2019 K115 Part III General Terms Construction

    21/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 21 of 48

    18.4 If Contractor fails to follow the requirements of Section 18.1, it shall havewaived any right to make any claim in respect of the events referred to inSection 18.1, regardless of the cause including the negligence of Engineer andCompany. Contractor's sole remedy in respect of any claim will be as providedin Section 18.2. No claim by Contractor in relation to events referred to inSection 18.1 shall be allowed after final payment is made pursuant to theprovisions set forth in Section 43.0.

    18.5 Company will not be bound to any adjustments in the Contract Price orscheduled time unless expressly agreed to by Company in writing.

    MATERIALS AND EQUIPMENT

    19.0 PROTECTION OF MATERIALS, EQUIPMENT AND WORK

    19.1 Contractor shall at all times, in accordance with the best practices and at noadditional cost to Company, preserve and protect material and equipment usedby Contractor in the execution of the Work from damage or loss due toweather, fire, theft, unexplained disappearance or other similar casualty.

    19.2 Contractor shall at all times, in accordance with the best practices and at noadditional cost to Company, protect from damage due to Contractor'soperations, equipment and materials (whether stored or installed), paving,structures and any and all other items on the jobsite belonging to Company,Engineer or others.

    19.3 Neither Company nor Engineer shall be responsible for any loss suffered byContractor, or damage to the Work, or to materials, tools and equipment ofContractor or of any other contractor, regardless of the cause including thenegligence of Company and Engineer, and Contractor assumes responsibilityfor any such loss or damage and for any cost of repairing, making good, orreplacing any such loss or damage that may be directed by Company orEngineer for the Company.

    20.0 CONTRACTOR'S CONSTRUCTION EQUIPMENT

    Construction equipment obtained or furnished by Contractor which is to be used by

    Contractor on the jobsite shall be in first-class operating condition, safe, fit for the usesfor which intended, and suitable for the safe, legal and efficient performance of theWork. Such equipment shall be subject to inspection from time to time by Company.

  • 8/11/2019 K115 Part III General Terms Construction

    22/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 22 of 48

    Any such equipment of Contractor which is rejected by Company as not conformingwith the foregoing shall be promptly removed by Contractor and replaced withequipment acceptable to Company, without additional cost to Company and withoutdelaying the schedule for performance of the Work by Contractor.

    21.0 CONTRACTOR'S SHIPMENTS

    21.1 Contractor shall be responsible for arranging all shipments of Contractorsupplied materials and equipment to the site of the Work and shall consignsuch shipments to itself as Consignee at the project shipping address, freightfully prepaid. Contractor shall be responsible for making demurrageagreements and settlement with carriers for its shipments.

    21.2 Contractor shall advise Company and Engineer, in writing, in advance of majorshipments of Contractor's materials and equipment and shall coordinate withCompany or Engineer the arrival, unloading and release of carriers' equipment.Contractor shall promptly unload its shipments and promptly release carrier'sequipment.

    21.3 In the event Contractor may be unable to promptly unload its shipment,Contractor shall notify Company and Engineer of such inability not less thanten (10) working days in advance of arrival. Company, at its option, may unloador make arrangements for others to unload such shipments for the accountand risk of Contractor. Contractor will promptly pay Company for such costs of

    unloading.

    22.0 CONTROL OF COMPANY FURNISHED MATERIALS

    22.1 Materials and equipment furnished by Company shall be received byContractor in the presence of Company authorized representative andquantities thereof shall be checked jointly by Contractor and Company. Thedelivery and acceptance of all such materials and equipment shall be recordedin writing, and Contractor shall evidence receipt and acceptance of suchmaterials and equipment by signing forms satisfactory to Company.

    22.2 Contractor shall carefully note any visible damage to Company furnished

    materials and equipment prior to Contractor's acceptance of delivery. AfterContractor has accepted delivery of such materials and equipment, Contractorshall assume full responsibility for any loss of or damage to such materials andequipment. Contractor shall notify Company and Engineer of any materials andequipment supplied to Contractor by Company which are surplus and, without

  • 8/11/2019 K115 Part III General Terms Construction

    23/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 23 of 48

    additional compensation, shall cooperate with Company and Engineer in thedisposition of such surplus as directed by Company.

    22.3 Contractor shall notify Company and Engineer of any lack of, or requirementfor, materials and equipment required under this Contract to be supplied byCompany in sufficient time for Company to furnish said materials or equipmentin advance of Contractor's need. In the event of misfit of Company furnishedmaterials or equipment, Contractor shall promptly notify Company andEngineer of such misfit. Contractor shall take all reasonable steps to avoidstandby time due to such misfit or lack of Company furnished materials orequipment and to continue progress of other portions of Work pendingcorrection of such misfit and/or the furnishing of materials or equipment.

    23.0 CARE, CUSTODY, CONTROL AND TITLE TO MATERIALS AND EQUIPMENT

    23.1 Good and clear title to all materials and equipment furnished by Contractorunder this Contract for the Work shall, except as expressly providedotherwise, pass proportionally to Company to the extent of, and at the timethat, Company makes progress payments to Contractor under this Contract.Notwithstanding the foregoing, in the event that one or more progresspayments are scheduled after the delivery and incorporation of Work into theProject or if there is any retention of payments by Company, full andunrestricted title to the Work shall pass to Company no later than the time ofincorporation of the Work into the Project. Contractor shall ensure that

    subcontractors from whom Contractor obtains materials are subject to thesame title passage and do not retain, encumber or reserve title to suchitems, and Contractor shall defend, indemnify and hold Company andEngineer harmless from any such claims by its subcontractors.

    23.2 Notwithstanding the provisions of Section 23.1, the care, custody and controlof Contractor's Work incorporated into the permanent plant shall remain withContractor until such Work has been accepted in writing by Company and shallthereupon pass to Company unless Company or Engineer notify Contractor inwriting that such care, custody, and control is assumed by Company at anearlier date. The taking of possession of such Work pursuant to Section 13.0,Possession Prior to Completion, shall not constitute the assumption of care,

    custody and control of such Work until such time as such Work has either beenaccepted in writing by Company or Contractor has been notified as set forthherein.

  • 8/11/2019 K115 Part III General Terms Construction

    24/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 24 of 48

    23.3 Contract revenues representing payments to subcontractors shall not beconsidered to be earned by Contractor unless and until Contractor has paid thecurrent invoices of such subcontractor. In the event Company determines, in itssole discretion, that Contractor has become insolvent or is in danger ofbecoming insolvent, then Company is authorized, but not required, to makedirect payment to Contractor's subcontractors with respect to any current orpast-due invoices then outstanding. Alternatively, Company may, in its solediscretion, require that contracts between Contractor and any suchsubcontractor be assigned to Company, and Contractor hereby authorizes andconsents to any such assignment. Company shall be entitled to full creditagainst any obligations to Contractor for any payments made to anysubcontractor under this Section 23.3, whether made pursuant to assigned

    subcontracts or otherwise. Title to any materials or equipment for which suchdirect payment is made shall pass directly from such subcontractor toCompany.

    LABOR AND WORK RULES

    24.0 CONTRACTOR'S PERSONNEL

    24.1 At all times during the course of the Work, Contractor shall provide at thejobsite a qualified, competent and responsible supervisor who shall besatisfactory to Company and Engineer. The supervisor shall have authority torepresent Contractor and directions given to him shall be binding onContractor. Upon Companys written request, Contractor shall give thesupervisor, in writing, complete authority to act on behalf of, and to bindContractor in all matters pertaining to the Work and this Contract. Contractorshall furnish Company and Engineer a copy of the authorization. Contractorshall not transfer or remove any of its supervisory or key personnel fromperformance of Work without the prior written approval of Company.

    24.2 Any employee of Contractor deemed by Company or Engineer, in their solejudgment, to be objectionable shall be removed from the jobsite immediatelyupon Company or Engineer request and shall be promptly replaced byContractor at no extra expense to Company. Contractor shall neverthelessretain all authority and control over its employees, including responsibility for allcosts arising from providing reasonable accommodations for its employees.

    24.3 If requested by Company or Engineer, Contractor shall furnish it with thenames and addresses of Contractor's subcontractors, field employees of

  • 8/11/2019 K115 Part III General Terms Construction

    25/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 25 of 48

    Contractor and its subcontractors, and others who have performed or areperforming the Work hereunder.

    24.4 Compliance with safety obligations and occupational health

    24.4.1 Contractor acknowledges that its personnel, agents and subcontractorswill observe the applicable legal regulations for safety and occupationalhealth and other regulations established by a pertinent authority in thefield of safety and occupational health. Contractor acknowledges andcommits to identify and implement obligations arising out of the safetyand occupational health legal regulations, which may include but arenot limited to: medical monitoring, monitoring of exposure, specific

    training for the identification of dangers and evaluation of risks,development and implementation of safety plans and program, records,and other commitments and obligations resulting from the current legalregulations. Contractor or its subcontractors, at any time during theeffective period of this Contract, shall provide, if so deemed necessaryin order to be compliant with the applicable laws, the required training oits personnel, agents or subcontractors. Company reserves the right tospecify the scope of such training or to require that Contractor performadditional training activities, and thereafter submit proof of documents,registrations or to certifications to attest written compliance with andcompletion of such training.

    24.4.2 Contractor agrees to assume completely the correspondingresponsibility for any violation of or incompliance with the current legalregulations related to safety and occupational health, incurred by itspersonnel, agents and/or subcontractors. In that sense, Contractor willpay any penalty established by the administrative or legal authority, aswell as any indemnity, sanction, penalties, charge, or fines that wouldbe established by such authorities as a consequence of such non-compliance. Should Company or Engineer be summoned toadministrative proceedings or legal processes arising out of the non-compliance with safety or occupational heath obligations of Contractor,and should Company or Engineer be required to take part in the lawsuitin connection therewith, Contractor shall indemnify Company and

    Engineer for all expenses incurred by Company and Engineer duringsuch complaints or lawsuits, including indemnifications, sanctions,penalties, fines, costs and other administrative and/or legal costs andattorneys fees. In case that the administrative or judicial complaint will

  • 8/11/2019 K115 Part III General Terms Construction

    26/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 26 of 48

    have been filed only against Company, due to non-compliance withsafety or occupational obligations caused by the personnel ofContractor or its subcontractors, Contractor shall defend Company,answer the complaint or action and perform the legal proceedingsneeded to release Company from any responsibility. The obligations ofContractor described in this clause are additional to any other clauseapplicable according to this Contract.

    24.4.3 In connection with the foregoing, Contractor will provide to Companywritten reports, no later than the 10th day of each calendar monthduring the term of the Contractor, or otherwise as directed by theCompany from time to time, specifying (i) the number of man-hours

    worked by Contractors employees in connection with the Work duringthe stipulated period of time, and (ii) the number of reportable incidentsof Contractors employees during the said time. Each report will be in aform provided or otherwise approved by Company.

    25.0 LABOR HARMONY

    25.1 Contractor agrees that all labor employed by it, its agents, and/or itssubcontractors for Work on the Work Site shall be in harmony with and becompatible with all other labor used by Company, Engineer or othercontractors. Whenever Contractor has knowledge that any actual or potentiallabor dispute is delaying, or threatens to delay, the timely performance of the

    Work, Contractor shall immediately give notice thereof, including all relevantinformation to Company and Engineer.

    25.2 Contractor shall comply with and shall cooperate with Company and Engineerin enforcing Work Site conditions including, but not limited to starting andquitting time, hours of work, overtime, shift differentials, holidays, travel andsubsistence payments, smoking regulations, daily clean-up and/or otherconditions that affect the overall performance of the Work.

    25.3 Company may determine that all field construction labor be performed inaccordance with a standard nationally recognized labor agreement (including,but not limited to the National Maintenance Agreement or the National

    Construction Agreement if available and applicable). Such determination, whenapplicable, shall be noted in Part I to the Contract and the terms of suchagreement shall be set forth in an attachment to the Contract. In the event ofsuch determination, Contractor shall make available upon request of Company

  • 8/11/2019 K115 Part III General Terms Construction

    27/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 27 of 48

    including, but not limited to all records and documents for the purpose ofverifying Contractor's compliance with working in accordance with the saidnational agreement. Compliance by Contractor or any of its subcontractors inany tier with the provisions of the specified national agreement is a specificContract obligation and any failure or default in compliance will be grounds fortermination under Section 8.0, Termination for Default.

    25.4 UNION LABELS

    In the event that Company makes the determination set forth in Section 25.3above, Contractor and its suppliers and subcontractors in any tier shall beresponsible to adhere to all fabrication and work preservation requirements as

    outlined in the national agreement. In the event that the applicable nationalagreement has no reference to the fabrication and work preservationrequirements of the local, regional or area collective bargaining agreement,then at a minimum, all fabricated piping that is shipped loose, all special builtelectrical cabinets that are not standard catalog items and all HVAC duct workthat is fabricated offsite for later installation at the Work Site, shall carry a"Union Label" from an approved shop of the International Union that has thehistoric jurisdictional claim to the work.

    26.0 EMPLOYMENT CERTIFICATIONS AND PRACTICES

    26.1 Contractor certifies that it has an affirmative action policy ensuring equal

    employment opportunity without regard to race, color, national origin, sex, age,religion or handicap, that it maintains no employee facilities segregated on thebasis of race, color, religion or national origin and that it is not debarred orsuspended from being awarded federal or federally assisted contracts.

    26.2 If applicable to this Contract, and not in conflict with the applicable Peruvianlaw, the following laws, orders and regulations, as amended, are herebyincorporated by reference: Executive Order 11246; Vietnam Era VeteransReadjustment Act; Rehabilitation Act of 1973; Veterans Compensation,Education and Employment Act; 41 CFR 60-1.4 (Equal EmploymentOpportunity); 41 CFR 60-250.4 (Veterans Affirmative Action); 41 CFR 60-741.4(Handicap Affirmative Action); 41 CFR 601.40 (Affirmative Action Plans);

    41 CFR 601.7 (EE01 Reports); 41 CFR 61650 (Veterans EmploymentReports).

  • 8/11/2019 K115 Part III General Terms Construction

    28/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 28 of 48

    26.3 Upon request of Company, Contractor will furnish it with a certificatesatisfactory in form to Company that goods furnished by Contractor inperformance of this Contract were produced in full compliance with therequirements of Sections 6, 7, and 12 of the Fair Labor Standards Act of 1938,as amended, and the regulations and orders of the U.S. Department of Laborissued under Section 14 thereof.

    27.0 WORK RULES

    Contractor shall comply strictly with Company's and Engineers rules governing theconduct of Contractor and Contractor's employees, agents and subcontractors at andabout the jobsite. Contractor agrees that it shall ensure that its supervisory personnel,

    employees, agents and subcontractors at the jobsite comply strictly with such rules.Company or Engineer reserves the right to, from time to time, revise any such rules,and Contractor shall comply fully with such rules as revised in accordance with theforegoing provisions. Such right shall not deem by any means that Company assumesany responsibilities regarding Contractors employees and/or subcontractors.

    INDEMNIFICATION AND INSURANCE

    28.0 INDEMNITY

    28.1 Contractor agrees to defend, indemnify and hold harmless Company andEngineer, the affiliated companies of each, and all of their directors, officers,employees, agents and representatives, from and against any claim, demand,cause of action, liability, loss or expense arising:

    28.1.1 By reason of Contractor's actual or asserted failure to comply with anylaw, ordinance, regulation, rule or order, or with this Contract. ThisSubsection 28.1.1 includes, but is not limited to, fines or penalties bygovernment authorities and claims arising from Contractor's actual orasserted failure to pay taxes.

    28.1.2 From actual or asserted violation or infringement of rights in any patent,copyright, proprietary information, trade secret or other property rightcaused or alleged to be caused by the use or sale of goods, materials,equipment, methods, processes, designs or information, including

    construction methods, construction equipment and temporaryconstruction facilities, furnished by Contractor or its subcontractors inperformance of the Work. Should any goods or services provided byContractor become, or appear likely to become, the subject of a claim

  • 8/11/2019 K115 Part III General Terms Construction

    29/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 29 of 48

    of infringement of a patent, copyright or other property right, Contractorshall, at Company's option, either procure for Company the right tocontinue using such goods or services, replace same with equivalent,non-infringing goods or services, or modify the goods or services sothat the use thereof becomes non-infringing, provided that any suchmodification or replacement is of equal quality and provides equalperformance to the infringing goods or services.

    28.1.3 From injury to or death of persons (including employees of Company,Engineer, Contractor and Contractor's subcontractors) or from damageto or loss of property (including the property of Company or Engineer)arising directly or indirectly out of this Contract or out of any acts or

    omissions of Contractor or its subcontractors. Contractor's defense andindemnity obligations hereunder include claims and damages arisingfrom non-delegable duties of Company or Engineer or arising from useby Contractor of construction equipment, tools, scaffolding or facilitiesfurnished to Contractor by Company or Engineer.

    28.1.4 From actual or alleged contamination, pollution, or public or privatenuisance, arising directly or indirectly out of this Contract or out of anyacts or omissions of Contractor, its subcontractors or suppliers.

    28.2 Contractor's indemnity obligations shall apply regardless of whether the partyto be indemnified was concurrently negligent, whether actively or passively,

    excepting only where the injury, loss or damage was caused solely by thenegligence or willful misconduct of, or by defects in design furnished by, theparty to be indemnified. Contractor's defense and indemnity obligations shallinclude the duty to reimburse any attorneys' fees and expenses incurred byCompany or Engineer for legal action to enforce Contractor's indemnityobligations.

    28.3 In the event that the indemnity provisions in this Contract are contrary to thelaw governing this Contract, then the indemnity obligations applicablehereunder shall be construed to be to the fullest extent allowed by applicablelaw.

    28.4 With respect to claims by employees of Contractor or its subcontractors, theindemnity obligations created under this Section 28.0 shall not be limited bythe fact of, amount, or type of benefits or compensation payable by or forContractor, its subcontractors or suppliers under any workers' compensation,

  • 8/11/2019 K115 Part III General Terms Construction

    30/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 30 of 48

    disability benefits, or other employee benefits acts or regulations, andContractor waives any limitation of liability or immunity arising from workers'compensation or such other acts or regulations.

    28.5 Company shall be entitled to retain from payments otherwise due Contractorsuch amounts as shall reasonably be considered necessary to satisfy anyclaims, suits or liens for damages that fall within Contractor's indemnityobligations under this Section 28.0, until such claims suits or liens have beensettled and satisfactory evidence to that effect has been furnished to Companyand Engineer.

    29.0 INSURANCE

    29.1 Contractor shall, at its sole cost, obtain and maintain in force, for the durationof the Contract (including the guarantee period set forth in Section 1.0),insurance of the following types, with limits not less than those set forth below:

    29.1.1 Workers' Compensation Insurance, including occupational illness ordisease coverage, labor accidents, in accordance with the laws of thenation, state, territory or province having jurisdiction over Contractor'semployees and Employer's Liability Insurance with a minimum limit of$1,000,000 per accident and, for bodily injury by disease, $1,000,000per employee. Contractor shall not utilize occupational accident orhealth insurance policies, or the equivalent, in lieu of mandatory

    Workers' Compensation Insurance or otherwise attempt to opt out ofthe statutory Workers' Compensation system.

    29.1.2 Commercial General Liability Insurance ("Occurrence Form") with aminimum combined single limit of liability of $1,000,000 eachoccurrence for bodily injury and property damage; with a minimum limitof liability of $1,000,000 each person for personal and advertising injuryliability. Such policy shall have an aggregate products/completedoperations liability limit of not less than $2,000,000 and a generalaggregate limit of not less than $2,000,000, which general aggregatelimit will be provided on a per project basis by means of ISOEndorsement CG 25 03 03 97. The products/completed operations

    liability coverage shall be maintained in full force and effect for not lessthan three (3) years following completion of Contractor's services. Thepolicy shall be endorsed to name Company and Engineer, includingtheir respective affiliates, the financing parties and the respective

  • 8/11/2019 K115 Part III General Terms Construction

    31/48

    CONTRACT PART III GENERAL TERMS STANDARD(CONSTRUCTION)

    SOCIEDAD MINERA CERRO VERDEProject: Cerro Verde Production Unit ExpansionArequipa, PeruProject No. A6CV

    RFP No: A6CV-90-K115S,C,M,P,E&I Install at TSF

    CVPUE PART III GENERAL TERMS STANDARD (CONSTRUCTION)[FORM 000.430.F0103 (Revision Date: 19Apr2010)]Copyright 2007, Fluor Corporation. All Rights Reserved.

    Contract ManagementPage 31 of 48

    officers, directors and employees of each, as additional insureds. Suchendorsement shall be made upon ISO Endorsements CG 20 10 07 04and CG 20 37 07 04, "Additional Insured Owners, Lessees orContractors Scheduled Person or Organization/CompletedOperations." Current endorsements providing coverage identical to thatprovided under ISO Endorsements CG 20 10 07 04 and CG 20 37 0704, and coverage limits identical to those provided under ISOEndorsement CG 25 03 03 97 may be employed by ContractorsCommercial General Liability Insurer to meet the above requirements.

    29.1.3 Automobile Liability Insurance covering use of all owned, non-ownedand hired automobiles with a minimum combined single limit of liability

    for bodily injury and property damage of $1,000,000 per occurrence.This policy shall be endorsed to name Company and Engineer,including their respective affiliates, directors and employees, asadditional insureds.

    29.1.4 If Contractor will utilize tools or equipment in the performance of itsservices under the Contract, Equipment Floater Insurance (Tools andEquipment Insurance) covering physical damage to or loss of all majortools and equipment, construction office trailers and their contents, andvehicles for which Contractor is responsible, throughout the course ofthe Work.

    29.1.5 Umbrella Liability Insurance providing coverage limits in excess of thatrequired in Subsections 29.1.1 Employers Liability, 29.1.2 GeneralLiability and 29.1.3 Automobile Liability, with a