Upload
others
View
41
Download
0
Embed Size (px)
Citation preview
Justification for locating the Project in forest area
Initially the land coming in the alignment was Khatedari land as per
revenue record but during construction forest authorities objected and
claimed that the land belongs to forest.
The matter was brought into the notice of State Government & a joint
inspection was done by forest and revenue officers then it has been
concluded that 1300 Sqm Ownership of land belongs to forest; accordingly
proposal of forest land diversion is being submitted to take the NOC from
forest department.
Detailed note on the project including number of villages and persons
to be benefitted including employment generation:
As per the Railway policy, the works of ROB/RUB’s in lieu of busy level
crossing having Train Vehicle Unit (TVU) more than 1.0 lakh are
undertaken on cost sharing basis; proposal for which are sponsored by
concerned State Government, duly fulfilling certain preliminary pre-
requisite viz. undertaking to bear 50% share of cost, provide land for
approaches and ensure closure of level crossing on completion of ROB/RUB
with action required for road diversion etc. Railway share 50% cost of two
lanes ROB/RUB for the level crossings where TVU is > 1.0 lakh and < 3.0
lakh. Railway share 50% cost of 4 lanes ROB for the level crossing having
TVU more than 3.0 lakhs.
As per the census of April 2010, TVU of LC34 was 136032 at Makrana. So,
Railway Board has approved LC34, Makrana for construction of 2 lanes
ROB in his pink book 2011-12 for his cost sharing. So State and Railway has
shared 50-50% cost in construction of ROB. Both Railway and State has
deputedIRCON as a Construction agency, so that work of ROB may
completed by the single agency.
GAD was approved by CBE/NWR Jaipur and as per the alignment shown in
GAD; 0.13 hectare forest land comes under the construction of ROB.
Without the use of forest land, it is not possible to construct ROB at LC34
Makrana.
Around 25000 Man days have been created as employment generation.
In addition to this, employment has been generated indirectly for suppliers
of steel and aggregates which in turn creates employment opportunities for
staff at Crusher plant, steel plant etc.
Ultimate policy of Railways is to close all the LC’s in a phased manner.
Cost Benefit Analysis Report:
Total contract value Rs 2648.84 lakhs or
Average Daily Traffic =5668
The benefits for above cost are as follows:
1. POL (Fuel & Lubricant) saving:
Considering 0.05 litre of fuel consumption for each traffic per day, so total
fuel consumption per day as average daily traffic=5668 comes as 5668 x
0.05 = 283.4 litres per day.
Considering cost of 1 litre fuel (diesel/petrol) = Rs.65/-, total amount =
283.4 x 65 = 18421 per day
So Amount incurred in 1 year= 18421 x 365 = Rs. 67, 23,665/-
Assuming life of ROB =80 Years & price escalation @ 5% per year, the total
amount incurred in 80 years will come as Rs. 6530217233/- i.e. Say Rs.653
Crores.
Hence, Rs. 653 crores can be saved on account of POL after construction of
ROB.
�