Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Cities Development Initiative for Asia
CDIA
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014
August 2014
TABLE OF CONTENTS
TABLE OF CONTENTS ..................................................................................................................... I
LIST OF ABBREVIATIONS ............................................................................................................... II
PROGRAM SCOPE ....................................................................................................................... III
A EXECUTIVE SUMMARY ........................................................................................................... 1
B CONTRIBUTION TO OVERARCHING DEVELOPMENT OBJECTIVES ............................................. 2
C CITY INTERVENTIONS ............................................................................................................ 7
D PROGRESS DURING THE REPORTING PERIOD ....................................................................... 10
D.1 PROGRESS AGAINST ENVISAGED OUTCOMES & OUTPUTS ............................................................ 10
D.2 CHALLENGES AND MITIGATION ..................................................................................................... 19
E CMT TIME REGISTRATION, CDIA CORE RESOURCES EXPENDITURE AND BUDGET ................... 21
F KEY ACTIVITIES (UNDERTAKEN AND PLANNED) .................................................................... 24
F.1 KEY ACTIVITIES UNDERTAKEN (JANUARY – JUNE 2014) ................................................................. 24
F.2 KEY ACTIVITIES PLANNED (JULY – DECEMBER 2014) ...................................................................... 25
F.3 CDIA PUBLIC RELATIONS (PR) AND COMMUNICATIONS STRATEGY ............................................... 26
ANNEX 1 CDIA RESULTS CHAIN AND INDICATORS FRAMEWORK 2013-2017 ............................... 28
ANNEX 2 IMPLEMENTATION MILESTONES ................................................................................. 30
ANNEX 3 APPROVED CITY INTERVENTIONS STATUS AND EXPECTED IMPACTS (JUN. 2014) .......... 31
ANNEX 4 SUMMARY CDIA INC. ACTIVITIES REPORT (JAN.–JUN. 2014) AND OUTLOOK 2014 ........ 38
ANNEX 5 PRO-POOR AND INCLUSIVE PROGRESS NOTE .............................................................. 40
ANNEX 6 PRC RECOMMENDATIONS & FOLLOW-UP ................................................................... 41
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 ii
LIST OF ABBREVIATIONS
ACCCRN Asian Cities Climate Change Resilience Network
ADB Asian Development Bank
BMZ German Federal Ministry for Economic Cooperation and Development
CIIPP City Infrastructure Investment Programming and Prioritization toolkit
CMT Core Management Team
FS Feasibility Study
GFP Gender Focal Point
GIZ Deutsche Gesellschaft fuer Internationale Zusammenarbeit GmbH
IFI International Financing Institution
IPSIA Initial Poverty and Social Impact Assessment
KfW German Development Bank
LFI Local Financing Institution
M&E Monitoring and evaluation
MFA Ministry of Foreign Affairs, Singapore
MoU Memorandum of Understanding
MoUD Ministry of Urban Development, India
MTR Mid-Term Review
NEA National Environment Agency, Singapore
NPO National Partner Organization
RPO Regional Partner Organization
PFS Pre-Feasibility Study
RETA Regional Technical Assistance
SDS Social Development Specialist
SECO State Secretariat for Economic Affairs, Switzerland
SEI Singapore Environment Institute
Sida Swedish International Development Cooperation Agency
SMG Shanghai Municipal Government
UCCRTF Urban Climate Change Resilience Trust Fund
UN-Habitat United Nations Human Settlements Program
YAPP Young Asian Professional Program
WB World Bank
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 iii
PROGRAM SCOPE
CDIA is a regional initiative established in 2007 by the Asian Development Bank and the Government of Germany, with additional funding support from the governments of Austria, Sweden, Switzerland and the Shanghai Municipal Government. The Initiative provides assistance to medium-sized Asian cities to bridge the gap between their development plans and the implementation of their infrastructure investments. CDIA uses a demand driven approach to support the identification and development of urban investment projects in the framework of existing city development plans that emphasize environmental sustainability, pro-poor development, good governance, and climate change mitigation/adaptation.
To facilitate these initiatives at city level, CDIA provides a range of international and domestic expertise to cities that can include support for the preparation of pre-feasibility studies for high priority infrastructure investment projects as one of several elements.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 1
A EXECUTIVE SUMMARY
This report covers the progress achieved by CDIA from January to June 2014 and includes a brief work plan for July to December 2014.
The following summary reflects the main highlights and challenges of CDIA’s progress during the reporting period:
From January to June 2014, 3 CIIPP exercises were conducted, 10 city applications for PFS support approved, and 4 PFS projects in 3 cities completed. CDIA thus counts a total of 65 PFS partner cities as of June 2014 including 110 PFS projects out of which 67 have been completed, with 39 of these being at least partially linked to financing. Adding the 26 cities with CIIPPs but no PFS application to date, CDIA accounts for city interventions in 91 cities;
Additional MoUs and workplans have been agreed upon with 3 national and 1 regional partner organizations aiming to implement the newly established accreditation system. All of the 3 CIIPPs undertaken during the reporting period were led by NPOs;
2 NPO staff members from UDRC (Mongolia) and Sevanatha (Sri Lanka) supported PFSs in their respective countries under the Young Asian Professional Program (YAPP) and will join the CDIA office in Manila in August 2014;
the PRC decided at its 12th meeting in March 2014 to continue the previous institutional and financial set up and arrangements of CDIA and CDIA Inc. as the preferred option recommended by a respective study.
During the reporting period, the CDIA team was further strengthened by a new Regional Networking Specialist, a Communications specialist and a project assistant joining to support and expand its activities. These included the organization of several training courses with participants from partner cities and organizations, the approval of PFS applications for two additional Asian countries (Georgia and Sri Lanka), and increased regional and international interest in and recognition of CDIA.
In addition, efforts have been increased to improve the CDIA Monitoring and Evaluation (M&E) system with its various instruments. Among others, an evaluation of IPSIAs of all completed PFSs was undertaken and is provided as a separate Annex 5 to this progress report. A larger share of resources was dedicated to receiving advice and to resuming client satisfaction surveys and tracer studies as well as gathering additional and analyzing this along with existing data. Initial results of ongoing activities are reflected in Section B and D of this report.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 2
B CONTRIBUTION TO OVERARCHING DEVELOPMENT OBJECTIVES
Regarding CDIA’s contribution to over-
arching development objectives like pro-
poor development, environmental sustain-
ability, mitigation of and adaptation to
climate change as well as enhanced
governance, Figure 1 shows the number of
PFS projects that consider each of these.
By June 2014, CDIA counted 67 completed
and 12 ongoing PFS projects, while 16
approved PFS projects are expected to start
within 2014.1
Figure 1 Number of PFS projects contributing to each
overarching development objective (June 2014).
As a result of increased efforts regarding the monitoring and evaluation (M&E) of CDIA activities,
client satisfaction surveys were distributed to all four cities that completed a PFS in 2013. Three of
these replied in time for including their responses in this progress report. Immediate post-training
evaluations reflected high rates of satisfaction
(cmp. e.g. p. 6-7). In addition, tracer studies
were initiated on the status and impact of
CDIA projects considered as “linked to
financing” (cmp. Table 3, p. 10) and in the
form of follow-up surveys also with
participants of CDIA training courses in 2014.
Samples of the responses received so far also
entered this report (cmp. Figure 2). These
efforts will be pursued on a continuous basis.
Figure 2 Response rate of follow-up surveys per training
Interviews conducted with stakeholders in 11 of its partner cities in 2013 were also evaluated and
served to identify good practices and potential CDIA Centers of Learning. Preparations started for a
workshop in fall under the 2014 Annual Thematic Focus where selected cities will be trained on
various ways of documenting and sharing good practices and lessons learnt.
Pro-poor and gender-related aspects: Under the responsibility of a long-term Social Development
Specialist (SDS), CDIA focused on the M&E of its activities in relation to pro-poor and inclusive
infrastructure development to respond to the achievement of results stated in the CDIA Strategy and
Business Plan 2013-2017. Appendix 5 shows a detailed analysis of IPSIAs implemented from January
2013 up to June 2014. In addition, resources have been facilitated to ensure that all Pre-Feasibility
Studies (PFSs) of CDIA since the S&BP 2007-12 have been appraised through the “Initial Poverty and
Social Impact Assessment” (IPSIA). 57 IPSIAs were completed until 2012, and additional 10 IPSIAs can
be counted since release of CDIA’s new S&BP in 2013.
CDIA activities for the Pro-poor and Gender dimension have been and will continue to be
mainstreamed by the Pro-Poor Checklist, ToRs for consultants, the Municipality Guide, as well as the
1 2 PFS projects were deferred and 13 projects cancelled, thus amounting to a total of 110 PFS inter-
ventions in 65 cities across Asia.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 3
IPSIA checklist. After an intensive review of these internal CDIA tools at the beginning of 2014, the
ToRs for consultants are updated to better respond to the need of poverty reduction orientation. As
CDIA Pre-Feasibility Studies combine different disciplines, they should be better connected and
consultants need to strongly cooperate with each other. For instance, pro-poor design features like
waste banks can be enhanced by integrating poverty and gender concerns as well in the ToR tasks
for the Solid Waste Management and Financial Specialist. In addition, it was experienced that the
IPSIA often does not cover sufficiently the level of participation. “Participation” is now integrated
into the IPSIA template in order to assess the multi-stakeholder involvement on all levels leading to
pro-poor governance.
As the below example of Hai Phong City in Vietnam demonstrates, the preparation of IPSIAs
contributes greatly to ensuring that social aspects are considered in most city interventions. By June
2014, there were 6 out of 67 completed PFS (9%) with poverty reduction as their explicit target2,
while as many as 46 (69%) aim for enhanced inclusiveness3.
Gender aspects remain mainstreamed in all CDIA guidelines, going hand in hand with the pro-poor
tools as mentioned above. CDIA constantly incorporates gender considerations or gender-sensitive
design features, thus significantly influencing the work with partner institutions and cities. This
involves for example the request for and collection of gender-disaggregated data and the raising of
gender-related questions and development aspects while working with them.
The CDIA Gender Focal Point (GFP) actively participated in the Gender Working Group meetings of
GIZ Philippines and the Pacific in the first half of 2014. Main concerns have been to discuss disaster-
related issues, like the governmental report of the Philippine National Economic and Development
Authority, to discourse the Operational Plan for 2014, and to follow up on the "Online survey
Corporate Culture & Gender Competence” to address gender discrimination and harassment within
the organization and programs.
The GFP/SDS is aiming to raise awareness of gender issues in all direct and indirect city
interventions. Since a common understanding is essential to promote the social part of a PFS, the
SDS organized a Pro-poor and Gender Orientation for all CMT members including the Philippine,
China and India office. The first hour provided an introduction/refresher on Social Development at
CDIA, while the second hour served as a discussion round on practical issues. CMT members got the
possibility to provide recommendations to the content needed for facilitating their daily work.
For more details on pro-poor and gender-related aspects, please see Annex 5.
Hai Phong in Vietnam improves its drainage and sewerage system in a pro-poor way (PFS duration: August 2012 – January 2013; total cost of city interventions USD 345,000; still to be linked to financing) Through enhancing the wastewater system and its treatment facilities the project will lead to better living conditions by reducing environmental and health risks from water related diseases. The PFS focused on two severly affected districts of Don Son and Duong Kinh, where the average poverty rate varies between 2% and 8%, and being much higher in unsewered areas. The majority of the urban poor have migrated from surrounding rural areas, in search of employment opportunities. As many are unable to find suitably paid jobs or accommodation, they settle in the peri-urban areas of the city.
2 Targeted Poverty Reduction Approach: The urban poor, poorly serviced, vulnerable areas and people are the main
beneficiaries of the infrastructure projects. More than half of the beneficiaries are considered poor or disadvantaged people with low resources. 3 Enhanced Inclusiveness Approach: All people in the city benefit from equal access to infrastructure services networks. In
order to make the overall system more inclusive, the percentage of poor beneficiaries is higher than the percentage of people living below the poverty rate. Benefits for the poor are perceived also through complimentary interventions.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 4
From an economic perspective, the project’s benefits include stimulating the tourism industry and thereby increasing employment opportunities. Agriculture as well as fishery will benefit from an improved overall water quality. A reduction in water related diseases can lead to increased productivity and thus contributes to poverty alleviation. Women in the project area will specially benefit from improved health, living, and overall economic conditions. As tourism and agriculture provide job opportunities for women in particular they can contribute to household income, therefore reducing the poverty rate. In the scope of both infrastructure projects organizational strengthening and capacity building are central project components. Apart from ensuring that the urban poor will have access to the infrastructure network, the tariff system will be shaped in an affordable way. As the urban poor are scattered throughout the city those residing in new settlements within the peri-urban project area will benefit from the intervention. In addition, the PFS recommends further studies on user charges or fees for the system. It is therefore recommended to conduct a detailed tariff study as part of a feasibility study taking into account anticipated cost-recovery levels and recommend pro-poor policy measures in order to ensure that the whole population will benefit from the improved sanitation services. Once implemented, the wastewater and sanitation project is expected to improve the living conditions of approx. 100,000 residents in Hai Phong. Based on the household surveys and poverty rate for the target areas about 51,000 urban poor would benefit directly from the infrastructure components.
Environment: As visualized by Figure 1, environmental aspects are considered in the vast majority
of PFSs, mostly ensured through respective expertise of at least one of the PFS consultants. In an
effort to create synergies in promoting environmental planning in cities, CDIA played an active role
in the launch of ADB’s GrEEEn Cities Initiative in May 2014. The regional conference “Enabling
GrEEEN Cities” brought together various organizations and networks concerned with integrated
urban development as well as several representatives from Asian cities. At the 4th Global
Infrastructure Basel Summit, the Distributed Energy System & District Cooling and Heating Project in
Xiaolan Zhongshan, China was featured as a best practice case (PFS completed in Feb. 2014, cmp.
description in previous progress report).
Water supply and wastewater management in Darkhan, Mongolia (PFS duration: February – June 2014; PFS input: USD 315,000; ADB loan of USD 13 mio. expected) The PFS team worked together with the city officials and the NPO UDRC towards an improved environment in peripheral ger areas by targeting essentially poor income households. It proposed decentralized sanitation solutions and water supply and proper water treatment through better wastewater management of the Khara River. The entire process was supported by an employee from UDRC under the CDIA Young Asian Professional Program (YAPP) who will join the CDIA office after completion of the PFS in Darkhan. An ADB pre-loan agreement is already in place for financing of the wastewater treatment plant.
Climate Change: The project ‘Linking Climate Change Resilient Planning to Urban Investments in Asian Cities,’ supported by the Rockefeller Foundation started in October 2013. The collaboration aims at identifying and developing bankable infrastructure projects rooted in cities’ Climate Resilience Strategies (CRS), and the focus cities have been Hat Yai, Quy Nhon, Semarang and Surat.
While there are many organizations that are supporting cities with climate change planning, including the Rockefeller Foundation, ICLEI, GIZ, UN-Habitat and others, there are very few support mechanisms in place to support cities translate these broad plans into concrete projects that can be picked by financiers. In order to facilitate this transition from strategy to financing, CDIA has developed a Climate Resilience City Infrastructure Investment Programming and Prioritization (CIIPP) Toolkit. The modified CIIPP Toolkit integrates elements of resilience, such as redundancy, safe-failure, and robustness into an already proven prioritization methodology.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 5
Due to CDIA’s relatively unique experience working towards building this bridge between climate planning and project development, the Rockefeller Foundation invited CDIA to present some of the lessons learned in early June at the Foundation’s meeting on “Investing in Urban Climate Change Resilience: Sharing Lessons and Accelerating Action.”
Selected Lessons Learned in Linking Climate Strategies to Finance
Momentum generated by the development of the CRS needs to be leveraged in order to effectively translate planning into projects.
The current approach to CRS orientation means it is less focused on infrastructure invest-ment and the identification of priorities requires review of additional city strategies & plans.
Linking infrastructure investments to financing requires targeted outputs to financiers’ spatial and sectoral requirements.
Some climate change adaptation priorities are strategic and will require investment beyond the city boundary.
Climate change projections are uncertain and their localization difficult, and this uncertainty needs to be built into project design.
Infrastructure investments are, by their nature, longer-term, and design horizons need to build in climate projections.
Infrastructure investments will require quantitative cost-benefit analysis in line with the investment life cycle.
Addressing urban resilience issues, in common with urban development more generally, will prove opportunistic, i.e. investments tend to be driven also by supply of finance rather than exclusively by the needs of the city.
The procurement of specialists with requisite urban development and climate change adaptation skills and experience may prove challenging.
One of the significant outcomes of the project was that CDIA has been asked by the Rockefeller Foundation to continue the partnership with work on a new project called “Aligning Downstream Finance with Upstream Urban Climate Change Resilience Planning.” The objective of the new project will be to find modalities to ensure that Urban Climate Change Resilience (UCCR) planning efforts, project development and downstream financing are integrated through a more connected and leveraged ecosystem of actors, so that an expanded and more streamlined pipeline of projects that contribute to UCCR is built.
Capacity Development in Cities and Climate Change A training on Cities and Climate Change with a focus on flood management was conducted by CDIA with the support of the Singapore Ministry of Foreign Affairs (MFA) and the Singapore Environment Institute (SEI) / National Environment Agency (NEA) from 26-28 March, 2014. 19 participants came from ten cities in Bangladesh, Bhutan, Indonesia, Nepal, Philippines, Sri Lanka, and Vietnam. An important indicator of the relevance and requirement for such a training was reflected by the fact that there was high ranking representation, including two mayors from the Philippines and one Vice Chairman of a Vietnamese Province along with 8 heads of department. In addition to covering issues related to governance, co-benefits, financing for CC project, there was also a ‘Mayors’ Roundtable’, and a session on ‘peer-to-peer advice’, which intensively explored two real cases: Blitar City (IND): How to achieve support at House of Representatives, and how to increase community awareness for implementing the CC Action Plan. General Santos (PH): Localized flood risks are being addressed through combined infrastructure development (drainage) and land banking/resettlement. How to cope with opposition by the concerned community groups?
According to feedback from the participants, the strong focus on the ‘special theme’ Flood Risk
Management made the training more concrete and more relevant to key challenges in many Asian
cities. The evaluation of the training provided high scores especially for the issue ‘relevance to your
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 6
work’, which had a tendency to be assessed lower during previous trainings. This high relevance
seems to be related to the fact that the training addressed one of the key themes for Asian cities in a
quite concrete and specific way. A powerful way of transferring training messages to the day-to-day
work of the participants was the exercise ‘The Way Forward’ during day 3. Rather than focusing on
fictitious case situations, the trainees identified key challenges in their home countries/cities in
categories addressed by the training and developed approaches to overcome them (‘To-do-list’).
The demand prior to the course and the response following the course so positive, the CDIA and
MFA, along with the ABD’s Urban Climate Change Resilience Trust Fund (UCCRTF) will conduct a
training of trainers to up-scale and roll out a similar training, albeit with a greater focus on urban
climate resilience, in the countries of Bangladesh, India, Indonesia, Pakistan, Philippines, and
Vietnam, which are not only the countries eligible for UCCRTF funds, but are also among the most
vulnerable countries to the impacts of climate change in Asia.
Good Governance: Among the above mentioned development impacts, good governance
represents the largest increase due to a respective focus of most CDIA interventions approved
during the reporting period. This can partly be explained through an increased awareness of CMT
members about the importance of ensuring the participation of various stakeholders early on in the
infrastructure investment process. Based on input from the CDIA Social Development Specialist, they
are now better equipped to give respective advice to cities in the PFS application process.
The training follow-up surveys indicated that the CDIA approach to stakeholder involvement has
been taken into account for projects by the Pakistani NPO Infrastructure Project Development
Facility (IPDF), including for the following projects: Karachi-Lahore Motorway, Karachi-Hyderabad
Motorway, Lahore-Islamabad Motorway & Coal Transportation.
Public transport system in Peshawar, Pakistan (PFS duration: November 2013 – March 2014; PFS input: USD 372,000; ADB financing of USD 533 mio. expected) In order to cope with its increasing demand of commuters for transport, the city of Peshawar requested CDIA to conduct a PFS for potential public transport modalities. For the first time in its history of planning urban infrastructure, the city officials followed a participatory and consultative process based on the CDIA support. The PFS consultants led focus group discussions with the urban poor residing in the envisioned transport corridor, who also sent representatives to later presentations and discussions. Other involved stakeholders included business owners in the corridor, city planners and the transport department. The process hence led to a change in dynamics of the city government with non-governmental actors. Peshawar expects to access ADB financing for a Bus Rapid Transport system.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 7
C CITY INTERVENTIONS
Progress is reported with reference to the three main focus areas of CDIA, namely a) Prioritization; b) Pre-Feasibility Studies; and c) Linking projects to financing.
Prioritization
As of June 2014, there were 15 active Memoranda of Understanding (MoUs) between CDIA and its regional and national partner organizations (RPOs/NPOs) and initial partnership discussions with 2 others. For various reasons, NPO engagement was not renewed for 2 NPOs each in China, India, and Vietnam, and 1 each for Nepal, Pakistan and Sri Lanka.
Together with its partners, CDIA has so far supported cities in prioritizing infrastructure investment projects by using its CIIPP toolkit in as many as 45 reported cases since 2012, with 3 undertaken in the reporting period by previously capacitated NPOs in Surat (India), Ha Giang and Vinh Yen (Vietnam). Out of all CIIPPs, most took place in the Philippines, India and Vietnam (see Figure 3). Tracer studies with training course participants aim to identify any potentially unreported CIIPPs.
Figure 3
CIIPP interventions by country
Pre-Feasibility Studies
From January until June 2014, final PFS reports have been submitted for the cities of Xiaolan and Yongzhou (China) and Peshawar (Pakistan). CDIA further approved PFS applications from 10 additional cities. The PFSs in Darkhan and Colombo (Sri Lanka) were strongly supported by YAPs from the NPOs UDRC and Sevanatha, respectively.
As of June 2014, CDIA has approved PFS applications in 65 different cities in 16 Asian countries for a total of 110 PFS projects (completed: 67 in 40 cities, ongoing: 12 in 8 cities).4 In addition to its prior sectors, the CDIA project portfolio has been extended to include social infrastructure as well (see Figure 4).
4 Out of these, 13 PFS applications were cancelled, and 2 were deferred due to limitations in budget,
changing local political situations and priorities (see Table 1).
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 8
Table 1 City Interventions (City applications/PFS)
City Applications Cities PFS projects
Completed 40 67
Approved 10 16
Ongoing 8 12
Deferred 2 2
Cancelled 7 13
TOTAL 65* 110
* Guiyang and Da Nang each submitted 2 successful applications which are thus subtracted from the total number of cities.
Figure 4 CDIA engagement by sector (June 2014)
Linking to Finance
Out of the 67 PFSs completed in 40 cities (13 countries) by June 2014, at least one component of 39 PFS projects was linked to finance (either through entering into FS phase for an International Financing Institution (IFI) or a Bilateral Agency, or through a signed letter of intent for PPP or other, mostly local, financing institutions). For 17 of these projects, actual construction of project components has started or is completed. Once implemented, at least 6.85 mio. people are expected to benefit.
Table 2 shows the distribution of projects linked and pipelined for financing per institution/ arrangement. The few KfW linkages result from the CDIA city demands not always being within BMZ/KfW focus sectors, a more complex CDIA application process, and KfW officers’ easier access to alternate study funds. Negotiations for the projects previously considered for WB financing were cancelled for reasons out of reach for CDIA, so that the respective linkages did not materialize. Other financing modalities included a detailed engineering design financed by Australian Aid and the Government of Indonesia for Balikpapan and Tangerang, and commercial borrowing in Palembang (Indonesia). Figure 5 shows the share of linked CDIA projects by financing institution.
Table 2 Summary of envisaged financing of completed CDIA supported projects
Primary Financing Institution
PFS linked to finance PFS linking in pipeline
no. of PFS
USD mio. no. of
PFS USD mio.
ADB 15 691.8 8 269.6
KfW 2 93.8 8 866.0
LFI 12 2566.7 8 17.7
PPP 6 948.2 8 407.7
WB 1 23.14 0 0.0
Other 3 112.5 0 0.0
Sub-total 39 4,436.1 32 1,561.0
TOTAL USD 5,997.1 LFI – Local Financing Institutions
Figure 5 CDIA projects Linked to Finance by Financing Institution
Definition Linked to Finance: At least one PFS component entering into FS phase for IFI or bilateral agency
(e.g. KfW); signed letter of intent (PPP, other financial institutions). Pipeline: Long term planning for IFI or bilateral agency (e.g. KfW); documented
correspondence of interest (PPP, other financial institutions).
The detailed status of CDIA PFS projects linked to finance (as of Dec. 2013) is indicated in Table 3 and Figure 6. For more information on each project, please refer to Annex 3.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 9
Linked to finance
Main Financing
Institution
Feasibility
EIV
Construction
EIR**1 Khulna, Bangladesh Solid Waste Management 6.5 ADB 6.51 Financing agreement signed 700,000
2 Khulna, Bangladesh Drainage 11.1 ADB 11.06 Financing agreement signed not specified
3 Khulna, Bangladesh Urban transport 13.8 KfW 13.76 Follow-up financing informally confirmed 1,300,000
4 Battambang, Cambodia Sewage/drainage system improvement 9.2 ADB 9.18 Financing agreement signed 130,000
5 Battambang, Cambodia Solid Waste 4.8 ADB 4.83 Financing agreement signed not specified
6 Geiju, China Land Development 900.0 PPP 900.00 Financing agreement signed 120,000
7 Guiyang 1, China Water resources rehabilitation 101.0 ADB 150.00 Follow-up financing informally confirmed not specified
8 Guiyang 1, China Urban transport (LRT project) 2300.0 LFI 2300.00 Follow-up financing informally confirmed 1,000,000
9 Guiyang 2, ChinaUrban transport (passenger hub and freight
logistics)200.0 LFI 59.00 Follow-up financing informally confirmed 530,000
10 Pu’er, China Rehabilitation Simao River 225.5 KfW 80.00 Construction ongoing 175,000
11 Yangzhou, China Water supply 60.0 LFI 60.00 Construction fully completed 500,000
12 Greater Suva Area, Fiji Drainage and flood management 24.4 LFI 10.00 Follow-up financing informally confirmed 256,000
13 Greater Suva Area, Fiji Urban transport 13.2 LFI 5.00 Follow-up financing informally confirmed [256000]
14 Pimpri, India Water Supply 66.4 LFI 11.70 Follow-up financing informally confirmed 150,000
15 Rajkot, India Urban transport 15.7 LFI tbc Some components completed not specified
16 Balikpapan, Indonesia Solid Waste Management 53.6 Other 38.00 Follow-up financing informally confirmed 350,000
17 Banda Aceh, IndonesiaRiver-based urban infrastructure development,
CBD rehabilitation22.6 PPP 15.00 Follow-up financing informally confirmed not specified
18 Palembang, IndonesiaUrban transport (Bridge project + selected bus
routes)175.0 Other 19.50 Some components completed not specified
19 Surakarta, Indonesia Urban transport 49.0 LFI 36.70 Some components completed not specified
20 Tangerang, Indonesia Solid Waste Management 91.1 Other 55.00 Some components completed not specified
21 Yogyakarta, Indonesia Urban transport 62.8 LFI tbc Follow-up financing informally confirmed not specified
22 Pakse, Lao PDR Sewerage/drainage system 25.4 ADB 25.40 Financing agreement signed 25,000
23 Pakse, Lao PDR Solid waste management 1.9 ADB 1.86 Financing agreement signed 135,000
24 Pakse, Lao PDR Green Infrastructure 6.9 ADB 6.90 Financing agreement signed not specified
25 Kathmandu, Nepal Urban Infrastructure improvement 23.7 ADB 23.70 Follow-up financing informally confirmed not specified
26 Kathmandu, Nepal Solid waste management 1.0 ADB 1.00 Follow-up financing informally confirmed not specified
27 Kathmandu, Nepal Urban transport (Bishnumati link road) 8.8 ADB 8.80 Follow-up financing informally confirmed not specified
28 Faisalabad, Pakistan Urban transport 583.2 PPP tbc Follow-up financing informally confirmed not specified
29 Faisalabad, Pakistan Industrial waste water management 141.9 PPP tbc Follow-up financing informally confirmed not specified
30 Islamabad, Pakistan Urban Transport 400.0 LFI 79.00 Follow-up financing informally confirmed 1,151,900
31 Cebu, PhilippinesReview of existing SRP Plan Service utilities
(Urban public transport)23.1 WB 23.14 Follow-up financing informally confirmed not specified
32Metro Iloilo-Guimaras,
PhilippinesFerry Terminal System (GIFTS) 9.2 PPP 3.40 Construction ongoing not specified
33Metro Iloilo-Guimaras,
PhilippinesCBD revitalization 29.8 PPP 29.79 Construction ongoing not specified
34 Naga, Philippines River walk 4.9 LFI 4.85 Some components completed not specified
35 Naga, Philippines River transport 0.4 LFI 0.40 Construction fully completed not specified
36 Da Nang 2, Vietnam Sewage/drainage system improvement 35.7 ADB 35.70 Follow-up financing informally confirmed 150,000
37 Da Nang 2, Vietnam Waste water treatment 368.0 ADB 368.00 Follow-up financing informally confirmed 90,000
38 Thanh Hoa, Vietnam Water supply 19.5 ADB 19.45 Financing agreement signed 40,000
39 Thanh Hoa, Vietnam Waste water treatment 19.5 ADB 19.45 Financing agreement signed 48,000
1,657.4 2,778.7 6,850,900
* Expected Investment Value (in mio. US$) 6,108.3
** Estimated Investments Realized (in mio. US$)
T O T A L S (in mio. US$)
Status: As of June 2014, 69 PFS projects have been completed in 41 cities (13 countries). Of these, 39 PFS projects in 24 cities were linked to finance (either through entering into FS phase for an IFI
or Bilateral Agency or through a signed letter of intent for PPP or other financing institutions). For 17 of these projects actual construction has started or is completed.
Target
PopulationStatus of Linked Projects
4,436.1
City, Country Project Sector/PFSEIV*
as per PFS
Implementation Phase
STATUS DETAILS
Construction completed: The construction of the infrastructure project is completed. Individual components completed: Individual components of the infrastructure project are already constructed while other components remain to be completed. Construction ongoing: All components of the infrastructure project are under construction. Financing agreement signed: A financing agreement for the infrastructure project has been signed and the construction phase is to commence. Follow-up financing informally confirmed: An informal statement (e.g. by a Project Officer at an International Financing Institution, a CDIA Country Manager) confirmed that follow-up financing has been secured (e.g. in the scope of a Detailed Technical Design (DTD), Project Preparatory Technical Assistance (PPTA), Feasibility Study (FS)). In some cases, initial parts of the project have already been implemented with city resources and are thus counted as being under construction.
Figure 6 Status of CDIA projects Linked to Finance
Table 3 Status of CDIA PFS Projects Linked to Finance (June 2014)
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 10
D PROGRESS DURING THE REPORTING PERIOD
The following tables present the progress made towards achievements of the overall development objective, outcomes and outputs on the basis of the program Impact Chain and Indicators Framework 2013 – 2017 (Annex 1). In addition to progress made towards achieved outcomes and outputs in the current reporting period and overall achievements of the CDIA Strategy and Business Plan 2013-2017, this report will also inform on main activities. Based on suggestions from an M&E consultant, a more refined “traffic light” coding has been introduced to determine the level of achievement of each indicator using the following criteria:
green: on track,
yellow: requires some action,
orange: requires substantial action,
red: facing severe challenges.
Indicators with orange and red traffic lights will be further discussed in the “Challenges” part of this chapter, where also strategies are proposed how to address them.
D.1 PROGRESS AGAINST ENVISAGED OUTCOMES & OUTPUTS
Indicators Results achieved to date/Traffic Light Remarks
OUTCOME (Overall Contribution of the CDIA Program 2007-2017): Cities and partner organizations (national/regional) prepare priority sustainable urban infrastructure investment projects, and link these projects to finance (with focus on environment, climate change, pro-poor, good governance)
1. By December 2017, the services of 10
CDIA-accredited partner organizations
(national/regional) are routinely utilized
by cities for their infrastructure
investment, planning and programming,
pre-feasibility studies and linking these to
finance, utilizing CDIA process tools
(sources: partner organization
certification, partner organizations
contract data, client surveys).
CDIA has a total of 8 accredited partner
organizations as of June 2014. During the
reporting period, MoUs were renewed with 3
NPOs that included work plans (as the basis for
accreditation) for providing city-level support.
Re-accreditation is envisioned in Q4 2015.
While some MoUs expired and others were
not renewed for different reasons, active
MoUs are in place with 11 NPOs in 7 countries
as well as with 4 RPOs. Discussions are ongoing
with other potential partner organizations.
Progress to date
Justification for progress assessment: Progress is on track. Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 11
Indicators Results achieved to date/Traffic Light Remarks
2. By December 2017, in a total of 50
Asian cities, CDIA-supported urban
infrastructure investment projects that
have a focus on at least two development
impacts (out of four: environment,
climate change, pro-poor, and good
governance) have been accepted for
funding and are implemented (sources:
tracer studies, baseline end-2012: 20
projects in 10 cities).
To date, components of 39 PFS projects in 24
cities have been linked to financing. For 17
projects in 10 cities implementation of at least
some components has started, with only 2
projects in 2 cities being fully completed and
operational.
All CDIA supported PFSs address at least two
development impacts (see column “Develop-
ment Impacts” in Annex 3).
Progress to date
Justification for progress assessment: Indicator is unlikely to be met. Justification of change in progress assessment vis-à-vis previous reporting period:
Substantial external delays have been identified in project implementation.
3. By December 2017, supported by
enhanced selected national frameworks
and the CDIA Institute, at least 10 cities
demonstrate that they have put into
use/applied CDIA good practice
innovations in their routine local
infrastructure planning and/or financing
processes (sources: good practice
documentation, client survey).
The evaluation of existing CDIA good practice
documentation and new client satisfaction
surveys indicate that at least two CDIA partner
cities already apply CDIA good practices in
their routine processes.
At the national level, CDIA is in dialogue with
ministries in Cambodia, China, Indonesia and
the Philippines to institutionalize change
processes.
Progress to date
Justification for progress assessment: Evidence shows impact of CDIA inter-ventions at local level. The CDIA flagship event aims at documenting good practices. Action needed to demonstrate influence on national frameworks. Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 12
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
“Bridging the capacity gap”, Output 1: Partner organizations (national/regional) have been strengthened to support cities in preparing infrastructure investment projects
1.1. By end 2017, as part of their regular
core activities, at least 10 accredited
partner organizations provide capacity
development support for the preparation
of infrastructure investment projects
(sources: tracer studies, training programs
offered by partner organizations).
Currently 8 regional and national partner
organizations are accredited to provide
support to cities using CDIA tools and
approaches. All of the 3 CIIPP exercises during
the reporting period were conducted by
accredited NPOs.
Follow-up surveys with NPO participants in
CDIA training courses indicate that also non-
accredited partner organizations already do
so.
Justification for progress assessment: Progress is on track. Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
1.2. By end 2017, all CDIA NPO
implemented city interventions reflect
inclusive processes and/or outcomes in
accordance with PFS guidelines, Pro-Poor
Urban Infrastructure Investment Guide
and Gender Strategy and Action Plan
(sources: PFS terms of reference, IPSIA,
PFS reports, progress reports).
No additional PFS was
implemented by a CDIA NPO
during the reporting period. 3 out of 4 city
interventions that were previously implement-
ted by NPOs reflect inclusive processes.
The indicator can never be met completely
due to one NPO implemented city intervention
that did not comply with CDIA standards.
Justification for progress assessment: 3 out of 4 (75%) NPO implemented PFSs were implemented in compliance with CDIA PFS requirements. 1 (25%) was implemented below standard. Thus the indicator will never be met 100%. Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 13
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
1.3. By end 2017, all CDIA NPO
implemented city interventions explore
options for private sector involvement in
project implementation and/or financing
(sources: PFS reports, progress reports).
At least 4 of the CDIA NPOs
have an explicit mandate to
facilitate private sector involvement in project
implementation and/or financing. In order to
capacitate other NPOs with knowledge about
opportunities and challenges of private sector
financing and public private partnerships, CDIA
incorporates these topics in its training
courses.
However, ensuring that all NPOs indeed will be
able to consider, justify and advice cities on
private sector financing still requires
substantial work.
Justification for progress assessment: By June 2014, CDIA NPOs have been involved in 4 completed PFS assignments. 2 out of these (50%) seriously considered private sector involvement while 2 (50%) did not. Thus the indicator will never be met 100%. Justification of change in progress assessment vis-à-vis previous reporting period:
This indicator was marked as yellow during the previous reporting period. Given the indicator will never be met 100%, there is a need to review whether it should be adjusted.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 14
“Bridging the planning-financing gap”, Output 2: Cities have enhanced capacities to access finance for prioritized sustainable urban infrastructure investment projects
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
2.1. By end 2017, in 40 cities, follow-up
financing has been secured for projects
that demonstrate sustainable develop-
ment (sources: signed agreements).
To date, components of 39 PFS projects in 24
cities have been linked to follow-up financing.
2 PFS projects are fully operational, and 14
others in various stages of implementation,
including full-fledged feasibility studies,
detailed technical designs, tendering for
public-private partnerships, or under
construction.
Follow-up financing is in the pipeline for
components of PFS projects in an additional 17
cities.
Justification for progress assessment: Progress is on track.
Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
2.2. By end 2017, follow-up financing has
been secured for five additional pro-poor
urban infrastructure investment projects
(sources: defined and approved projects
by cities and/or national agencies).
Since the start of the second S&BP in 2013, 2
targeted poverty reduction projects have been
linked to financing.
By June 2014, 4 additional targeted poverty
reduction projects were in the pipeline to be
linked to financing.
Justification for progress assessment: Progress is on track.
Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 15
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
2.3. By end 2017, follow-up private sector
participation has been secured for five
additional urban infrastructure
investment projects (sources: defined
project documents approved by cities
and/or national agencies).
During the reporting period, 2 PFS projects
have been linked to private sector
partnerships, bringing the total number to 3
since the start of the second S&BP.
8 additional projects are expected to be
financed with private sector participation.
Justification for progress assessment: Progress is on track. Justification of change in progress assessment vis-à-vis previous reporting period:
No change in progress assessment compared to previous reporting period.
2.4. By end 2014, collaboration with 2
national pro-poor financing institutions
and 2 PPP centers or branches of national
government undertaking infrastructure
investment projects in cities has been
assured (sources: signed MoUs, joint work
programs).
Since 2013, collaboration
exists with 2 PPP centers in
Indonesia and the Philippines, but no formal
collaboration has been established yet with
national institutions which have an explicit
pro-poor financing focus. Continuous scanning
of possible institutions is taking place though
without success so far.
Justification for progress assessment: Collaboration with 2 PPP centers but no national pro-poor financing institution has been secured to date. Justification of change in progress assessment vis-à-vis previous reporting period:
Challenges consist in lack of pro-poor financing institutions which invest in infrastructure. Substantial action will have to be taken in order to reach this indicator within the set timeline.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 16
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
2.5. By end 2013, appropriate framework
is in place to enable monitoring projects’
actual contribution to development
impacts (sources: tracer studies, client
satisfaction surveys).
This target has not been
met. During the reporting
period, additional resources have however
been invested and advisory services were used
so that client satisfaction surveys and tracer
studies for cities and participants to training
courses could be resumed. These efforts will
further be taken over by an M&E specialist
who will ensure an integrated framework.
Justification for progress assessment: While the deadline of Dec. 2013 was not
met, building blocks for a Monitoring and Evaluation (M&E) system are in
place. A GIZ consultant has reviewed and endorsed CDIA’s M&E framework
and an intern joined in June 2014 to support respective activities. The
recruitment of a national M&E specialist was delayed due to few suitable
applications but has been secured for Sep. 2014.
Justification of change in progress assessment vis-à-vis previous reporting period:
In the previous reporting period, this indicator was marked as red. As M&E
activities have been resumed, it was now changes to yellow.
“Bridging the institutional gap”, Output 3: Sustainable knowledge and innovation support for urban infrastructure investment is available and accessible to stakeholders
3.1. By end 2015, in 20 cities urban
infrastructure planning processes reflect
lessons from CDIA centers of learning
(sources: assessment surveys of
institutional, organizational, and human
capacities).
So far, record exists only for
one city (Hai Phong,
Vietnam) that learned lessons of a CDIA
partner city. This indicator is thus not
expected to be reached by end 2015.
However, the 2014 Thematic Focus of CDIA
serves to clarify the concept further by means
of an expert group discussion in the sidelines
of the World Cities Summit. It is furthermore
planned to officially establish some initial
Centers of Learning by training selected
partner cities in documenting and ways of
sharing good practices and lessons learnt.
Client satisfaction surveys were updated to
include a question on city-to-city learning.
Justification for progress assessment: Based on documented good practices & lessons learnt, action is required for monitoring their sharing across cities. Justification of change in progress assessment vis-à-vis previous reporting period:
In the previous reporting period, this indicator was marked as yellow. Substantial action is required to reach it before end 2015.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 17
Indicators Results achieved to date/Traffic Light Progress to date/Remarks
3.2. By end 2017, in 6 countries, in
collaboration with development partners,
CDIA processes are aligned with and have
enhanced nationally mandated urban
development processes (sources: minutes
of meetings, conference documents,
national policies, laws, regulations).
So far, the criteria of this
indicator are met in 1
country, i.e. Indonesia, where CDIA has
strategic entry points for contributing to and
enhancing the development of National Urban
Development Policy. Further options to
synchronize CDIA’s operations with nationally
mandated procedures are being explored in
China, Indonesia, the Philippines, and recently
also in Cambodia.
Limitations in resource availability may impede
the possibilities to meet this target. In
addition, monitoring of CDIA influence on
national development processes will be
difficult in order to demonstrate respective
results.
Justification for progress assessment: While in Indonesia and Philippines progress is on track, additional work is required to make sure that also in other countries CDIA tools and approaches are closely aligned with and have enhanced nationally mandated urban development processes. Justification of change in progress assessment vis-à-vis previous reporting period:
In the previous reporting period, this indicator was marked as yellow. As changes at the national level prove to be challenging, it was now changed to orange.
3.3. By end 2017, financing of CDIA core
functions has been secured with at least 4
regional partners contributing at least
60% (sources: agreements of
organizations).
Financing from 3 regional
partners has been secured
within the second business phase of CDIA,
contributing about 35% of CDIA resources. The
funds from Shanghai Municipal Government
(SMG) and Singapore were however restricted
to specific purposes instead of CDIA core
functions.
The assessment mission looking at the long
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 18
term organizational and financial sustainability
of CDIA made recommendations for increasing
regional contributions which were the basis
for follow up action from PRC members.
During his visit to the Philippines in March
2014, the PRC Chairman met with ADB DGs
and planning started for a high-level side
event at the ADB Annual Meeting 2015.
Justification for progress assessment: ADB is still the only regional contributor of completely untied CDIA core resources. PRC members support the efforts of CMT at a higher political level, e.g. with a side event at the ADB Annual Meeting 2015 in Baku. In order to reach 60% of core resources by end 2017, more action is however required. Justification of change in progress assessment vis-à-vis previous reporting period:
In the previous reporting period, this indicator was marked as yellow. Due to challenges in securing regional contributions to CDIA core resources, it was now changed to orange.
3.4. By end 2017, 30% of CDIA city
interventions will have (partial) cost-
recovery mechanisms in place (sources: TA
agreements).
12% out of all CDIA city
inter-ventions (or 83% since
2013) have (partial) cost-recovery mechanisms
in place. All Technical Assistance (TA)
agreements for new partner cities in which PFS
support will be provided are designed to
consider principles for partial cost-recovery.
While the mechanism is in place, actual cost
recovery is not yet happening to a significant
degree. Based on the recommendations from
the long-term sustainability study, internal
discussions took place during the reporting
period and an existing concept note has been
revised that explores various ideas for cost
recovery along with their potential
implementation.
Justification for progress assessment: Progress is on track. Justification of change in progress assessment vis-à-vis previous reporting period:
During the previous reporting period, this indicator was marked as red. Among others with the help of the assessment mission on CDIA long term organizational and financial sustainability, additional ideas were generated on how CDIA can approach cost-recovery from cities in a pragmatic manner and advance its implementation. This indicator was thus changed to yellow.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 19
D.2 CHALLENGES AND MITIGATION For the indicators where progress during the reporting period was highlighted as orange (requires substantial action) and red (facing severe challenges) in the above section, further clarification is provided below and strategies are proposed on how to address them.
Indicators Further clarification on challenges Proposed actions to mitigate
1.3. By end 2017, all CDIA NPO
implemented city interventions explore
options for private sector involvement
in project implementation and/or
financing (sources: PFS reports,
progress reports).
By June 2014, CDIA NPOs have been involved in 4 completed
PFS assignments. 2 out of these (50%) seriously considered
private sector involvement while 2 (50%) did not. Thus the
indicator will never be met 100%.
MTR to consider rephrasing of the indicator in order
to acknowledge the limited influence of CDIA on NPO-
implemented PFSs.
2. By December 2017, in a total of 50
Asian cities, CDIA-supported urban
infrastructure investment projects that
have a focus on at least two develop-
ment impacts (out of four: environ-
ment, climate change, pro-poor, and
good governance) have been accepted
for funding and are implemented
(sources: tracer studies, baseline end-
2012: 20 projects in 10 cities).
CDIA only has limited influence on the negotiation process
between a city and financiers following a PFS.
Significant delays between the finalization of a PFS, the
granting of funds and the completion of an infrastructure
project up to its operation and maintenance present
considerable challenges for reaching this indicator.
MTR to consider rephrasing of the indicator through
reducing the target cities in light of the CDIA mandate
and influence, or through limiting the target to the
level of funding and thus excluding implementation.
2.4. By end 2014, collaboration with 2
national pro-poor financing institutions
and 2 PPP centers or branches of
national government undertaking
infrastructure investment projects in
cities has been assured (sources: signed
MoUs, joint work programs).
The main challenge consists in the limited number of explicit
pro-poor financing institutions which invest in infrastructure.
CDIA thus aims to mainstream pro-poor investments in
traditional financing institutions.
Due to the rather low share of targeted poverty reduction
projects among all CDIA projects, a low demand can be
assumed for establishing such cooperations.
A Senior Infrastructure Financing Expert is expected to
join CMT in fall 2014. This person will support the
identification of suitable pro-poor financing
institutions.
MTR to review this indicator and consider changing
the number of pro-poor financing institutions to 1.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 20
3.1. By end 2015, in 20 cities urban
infrastructure planning processes
reflect lessons from CDIA centers of
learning (sources: assessment surveys
of institutional, organizational, and
human capacities).
So far, only one CDIA partner city indicated to have learned
from a previous experience of another.
Challenges consist in adequately documenting and sharing
good practices and lessons learnt and making them accessible
for / distributing them to other cities.
In addition, the monitoring of lessons learnt beyond CDIA
partner cities is challenging.
As agreed by the PRC in March 2014, the MTR should
make recommendations on how this indicator can be
achieved within the given timeframe, and consider
reducing it to a target of 10 cities by end 2015 or
extend the timeframe.
3.2. By end 2017, in 6 countries, in
collaboration with development
partners, CDIA processes are aligned
with and have enhanced nationally
mandated urban development
processes (sources: minutes of
meetings, conference documents,
national policies, laws, regulations).
Given the limited staff resources and influence of CDIA,
changes at the national level prove to be challenging.
Interventions mostly focus at the city level within a timeframe
of several months only.
So far, this is only achieved to some extent in Indonesia, with
additional potential and efforts undertaken in China, the
Philippines and Cambodia.
Instead of working in an increasing amount of
countries, the focus on specific countries may help to
achieve a greater impact.
Based on recommendations by the MTR, the PRC
should take a respective decision at its next meeting.
3.3. By end 2017, financing of CDIA core
functions has been secured with at
least 4 regional partners contributing at
least 60% (sources: agreements of
organizations).
Challenges persist in securing regional contributions to CDIA
core resources.
MTR to review and consider rephrasing of the
indicator to refer to “CDIA functions” instead of “CDIA
core functions” to also reflect tied regional
contributions.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 21
E CMT TIME REGISTRATION, CDIA CORE RESOURCES EXPENDITURE AND BUDGET
Introduction: CDIA core resources used in the first half of 2014 were in cash and in-kind from ADB (including resources channeled through RETA from Austria, Sweden, and Switzerland as well as through the UCCRTF/Urban Financing Partnership Facility also from DFID, Rockefeller Foundation and USAID) and from BMZ (through GIZ). Additional resources originated from the Shanghai Municipal Government for CDIA China, and others were generated through CDIA Inc. The different financial management procedures (commitment- vs. disbursement-based expenditure tracking) employed for various streams of funds continue to pose challenges in coherent financial reporting. Financial data in the standard expenditure type classification of ADB and GIZ budgets is reconciled with the more detailed CDIA activities classification. Therefore, CDIA CMT time registration by main CDIA activities classification assigns CDIA CMT resources to certain components to obtain integral costs of activities and to monitor their development over time.
lesser focus on pipeline activities, investment programming and prioritization, and linking to finance work due to an existing pipeline of cities. The release of funds for the new S&BP at the end of 2013 enabled the approval of 10 Pre-Feasibility Studies and thus an increase of time spent on PFS work within the reporting period. Under the heading Capacity Development, time spent on regional capacity development, networking and knowledge development has increased due to several training courses taking place during the reporting period and vast number of attended events (cmp. Chapter F.1 Key Activities Undertaken). The release of funds in 2013 is also reflected in a decrease in time allocation on ADB administration and management. Table 5 shows a more detailed overview of expenses per component.
Time registration: January-June 2014 CDIA time registration outcomes for CMT professional staff are presented in Table 4. This includes ADB, GIZ and CDIA Inc. staff and consultants, for a total of 13.69 Full-time Equivalent (FTE) staff time at end June 2014 – compared to 11.42 FTE at end December 2013. The table indicates that in the first half of 2014, CMT staff spent 33% of their total time on preparing and backstopping city-level activities, 32% on capacity development (including NPO collaboration, networking activities and knowledge development), and 12% on institutionalization activities (including Nodal Offices development, program resource mobilization and PRC support activities). Time spent on various non-project/overhead activi-ties amounted to 24% of time spent.
Compared to 2013, the proportions for the above broad categories varied by showing slight decrease on time allocated to city-level project and non-project/overhead activities, and in-crease in capacity development.
Within these categories themselves, under the heading City-level project preparation activi-ties, there were some changes including a
Table 4 CDIA Time Registration Jan.-Jun. 2014
Summary outcome CMT time registration 2013 Jan - June 2014
City Level Project Preparation Activities
General Specific Pipeline Activities 14% 11%
Investment Programming & Prioritization 1% 0.4%
Pre-Feasibility Studies 14% 20%
Linkage to Financing 8% 2%
Sub-total 36% 33%
Capacity Development
Capacity Development in City 0% 1%
Regional Capacity Development 3% 7%
NPO Collaboration / YAPP 4% 5%
Networking / SHF / Conferences / PR 10% 12%
Knowledge Development 4% 6%
Sub-total 21% 32%
Institutionalization
Institutionalization 12% 12%
Sub-total 12% 12%
Non-project activities
CMT Meetings 3% 4%
CMT Administration 1% 1%
Sick Leave 2% 0.4%
Annual Leave (including national holidays) 13% 11%
Staff Training 4% 0.5%
GIZ Administration/management 3% 3%
ADB Administration/management 5% 2%
CDIA Inc. Administration 1% 2%
Sub-total 32% 24%
Total 100% 100%
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 22
Component ADB GIZCDIA Inc.
(other source of
funds)
SMG Total Expenses
in '000% of TE
City Intervention Preparatory Activities 27 59 11 96
Investment Prioritization 0 4 4 8
Pre-Feasibility Studies 625 105 220 950
Linkage to Finance 58 43 101
Total Expenditure CLPA 710 212 15 220 1,156 41%
Capacity Development - in City 13 33 74 119
Regional Capacity Development 21 111 45 177
NPO Collaboration /YAPP 7 12 19
Networking / SHF / Conference / PR 75 53 21 149
Total Expenditure CD 116 208 45 95 464 16%
Nodal Offices 0 4 4
Strategy Development 0 0
CDIA Institutionalization 18 8 26
Resource Mobilization 0 0
Monitoring & Evaluation 0 0
Project Review Committee (PRC) 13 13
Total Expenditure Institutionalisation 18 20 4 43 2%
CMT Costs 29 173 201
ADB in Kind 225 225
Management/Administration Cost 75 73 33 86 267
GIZ Overheads (HO & Regional Offices) 466 466
Total Expenditure NPA 329 712 33 86 1,160 41%
TOTAL EXPENDITURE 1,172 1,152 92 405 2,822 100%
Non-project Activities
City Level Project Activities January - June 2014
Capacity Development (CD)
Institutionalization
Table 5 Consolidated CDIA Core Funds Expenditure per Component from Jan.-Jun. 2014 in USD thousand
Available budget and expenditure 2013: The available budget and expenditure for the first six months of 2014 (Table 6) shows a total aggregate expenditure of US$2.8 million from ADB, GIZ, the Shanghai Municipal Government, and CDIA Inc. resources. This is about 13% total utilization of the overall funds available in 2014. ADB through Regional Technical Assistance (RETA), and GIZ through Financing Agreement continue their support to CDIA Inc. for networking and capacity development activities and operational expenditure. Both institutions allocated a total budget of US$185,605 in 2014 and out of this amount, US$76,718 were released as of June 2014.
The disbursements and percentage of funds utilization per source shows that for 2014, about US$1.1 million (58%) of the GIZ resources for CDIA and CDIA Inc. for capacity development activities were spent. About US$1.2 million (7%) of the funds from ADB RETA sources and in-kind contributions were used. About US$0.4 million (68%) from the available resources of the Shanghai Municipal Government (SMG) were utilized to support the CDIA China Nodal Office, and about US$0.01 million (15%) from the CDIA Inc. resources out of the grant from Rockefeller Foundation, were utilized to support activities related to climate change.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 23
Table 6 Available Budget and Expenditure in 2014 in USD
Available Funds
in 2014
Breakdown of 2014
Expenditure of ADB
Supports to CDIA
Jan. - June 2014
Expenditure
% of Utilization
per Source
Supports to CDIA Inc. for 2014 $ 53,200.00
Asian Development Bank (ADB) ($ 17,313,000.00) 1,172,361.00$ 7%
Supports to CDIA Inc. for 2014 $ 132,405.00
Switzerland (SECO), 2015-2017 $ 4,000,000.00
Total $ 6,400,000.00
- RETA 7450: Project Preparation
Support for Livable Cities in Asia
(TA completion 31 Dec. 2014)
$ 379,000.00 47,843.00$ 13%
Austria, 2013-2015 $ 2,000,000.00
Sweden (Sida), 2013-2017 $ 7,084,000.00
Urban Financing Partnership
Facility (UFPF), 2013-2018 $ 5,000,000.00
Total 14,084,000.00$ 14,084,000.00$ -$ 0%
- ABD in-kind allocation $ 450,000.00 225,000.00$ 50%
Shanghai Mun. Govt (SMG) financial
support to CDIA1,260,000.00$ 405,234.64$ 68%
Cities Development Institute for Asia
(CDIA), Inc.68,883.00$ 10,615.00$ 15%
21,341,883.00$ 2,717,359.33$ 13%
CDIA Source of Funds
Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ)
GmbH
Cities Development Initiative for Asia Program
financial support for 20142,700,000.00$ 58%
Total per Regional Technical Assistance (RETA)
and in-kind allocation for 2014
Remaining funds for CDIA implementation up to
2017 $ 2,400,000.00 $ 899,518.00 63%
1,129,148.69$
- RETA 6293: Managing the
Cities in Asia
(TA completion 31 Dec. 2017)
- RETA 8556: Supporting the
Cities Development Initiative
for Asia
(TA completion 31 Dec. 2017)
Remaining funds to support CDIA under the ADB
special funding until 31 Dec. 2014
Professional & Admin Support for 2014
Supports to CDIA China for 2014
Grant from Rockefeller Foundation (RF) , Asian
Cities Climate Change Resilience Network
(ACCCRN) (Oct. 2013 - 30 Nov. 2014)
Total Available Funds and Expenditure in 2014
In order to allow for a better comparison with the budget scenarios introduced in the S&BP 2013-2017 (cmp. Table 4, p. 30), the Table 7 below reflects the Jan.-Jun. 2014 expenditure components rearranged according to the expenditure areas and activities outlined therein:
Expenditure Area ADB GIZ
CDIA Inc.
(other source
of funds)SMG
Total Expenses
in '000 % of TE
City Intervention Preparatory Activities 27 59 11 97
Investment Prioritization 0 4 4 8
Pre-Feasibility Studies 625 105 220 950
Capacity Development - in City 13 33 74 119
Total Expenditure Project prep. city level 664 201 15 294 1,174 41.6%
NPO supportNPO Collaboration /YAPP 7 12 19
Total Expenditure NPO support 7 12 19 0.7%
Linking to finance supportLinkage to Finance 58 43 101
Total Expenditure Linking to finance support 58 43 101 3.6%
Networking activitiesRegional Capacity Development 21 111 45 177
Networking / SHF / Conference / PR 75 53 21 149
Total Expenditure Networking activities 96 164 45 21 326 11.6%
Activities 1,620 57.4%
CMT Costs 29 173 201
Strategy Development 0 0
CDIA Institutionalization 18 8 26
Resource Mobilization 0 0
Monitoring & Evaluation 0 0
Total Expenditure CMT staff support and development workers 47 181 227 8.0%
CMT structure costs (incl. nodal office and PRC)Nodal Offices 0 4 4
Project Review Committee (PRC) 13 13
Total Expenditure CMT/nodal office costs 13 4 17 0.6%
ADB in Kind 225 225
Management/Administration Cost 75 73 33 86 267
GIZ Overheads (HO & Regional Offices) 466 466
Total Expenditure ADB/GIZ in-kind general costs and institutional
overheads
300 539 33 86 958 33.9%
1,202 42.6%
TOTAL 2,822 100%
Project preparatory city level interventions (cities)
Direct and indirect support costs
CMT staff support and development workers (incl. travel costs)
ADB/GIZ in-kind general costs and institutional overheads
Table 7 Expenditure per area from Jan.-Jun. 2014 according to S&BP 2013-2017
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 24
F KEY ACTIVITIES (UNDERTAKEN AND PLANNED)
This section highlights key activities undertaken and planned in relation to ensuring institutional and financial sustainability of CDIA and providing an overview of key events in which CDIA participated.
F.1 KEY ACTIVITIES UNDERTAKEN (JANUARY – JUNE 2014) Institutional and financial sustainability of CDIA: The recommendations from the study on long term institutional and financial sustainability of CDIA were discussed at the 12th PRC meeting in March 2014. It was unanimously decided to continue the institutional set-up of CDIA as it is along with CDIA, Inc. to allow for further channeling of funds and expenditures that cannot be accommodated through the ADB and GIZ systems. The CDIA Mid-term Review will be tasked with suggesting ways of mainstreaming the governance structures of CDIA and CDIA, Inc. It was also decided to organize a side event at the 2015 ADB Annual Meeting as incentive to regional funders. Monitoring and Evaluation (M&E): Following the 12th PRC meeting, CDIA has increased its efforts to improve its M&E system which had suffered from a sudden staff leave in spring 2013 and subsequent lack of handover to new staff joining in late 2013. An advisory session with a GIZ M&E consultant in June 2014 served to revive client satisfaction surveys and tracer studies. The recruitment of an M&E specialist through the ADB is expected to be finalized in August 2014. In preparation of the 2014 Mid-Term Review, CDIA furthermore undertook a self-assessment. Major events/workshops: Thanks to its strengthened team, CDIA was able to be a key organizer or participant in the following events and workshops during the reporting period:
Event Title Venue Date
1 PPP Workshop: The Role PPP can Play in Urbanization of China
China, Shanghai 10 January
2 Introduction Training for Implementing the CDIA CIIPP & PFS Toolkits
Thailand, Bangkok 14-17 January
3 PPP Module I Training China, Beijing 23-25 February
4 5th High-Level Seminar on Environmentally Sustainable Cities
Indonesia, Surabaya
28 February – 1 March
5 Effective Urban Infrastructure Programming Course
Singapore 5-14 March
6 Metropolis Peer Review Process Workshop Korea, Seoul 12-14 March
7 Regional ToT on Pro-Poor Urban Climate Resilience in Asia-Pacific (UN HABITAT/UN ESCAP/Rockefeller Foundation)
Philippines, Manila 17-22 March
8 12th PRC Meeting Germany, Berlin 18-20 March
9 Executive Seminar on Cities and Climate Change: Financing Module - Thematic Focus on Flood Risk Management
Singapore 26-28 March
10
World Urban Forum 7 – CDIA hosted events: Networking event: Linking Cities To Financing:
Realizing Low-carbon And Climate Resilient
Infrastructure Investments; German booth event:
Connecting mobility plans with financing and
Colombia, Medellin 5-11 April
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 25
knowledge; Training event: How to Strengthen
Urban Spatial Planning to reduce Social Vulnerability
and Exclusions in South Cities; Side-event: Linking
Cities to Financing: Bridging the gap between plan-
ning and implementation of urban infrastructure
investments
11 Community Resilience and Human Security Workshop
Singapore 10-11 April
12 2nd City Creditworthiness Academy Korea, Seoul 21-26 April
13 ADB GrEEEn Cities Forum Philippines, Manila 13-14 May
14 4th Global Infrastructure Basel Summit Switzerland, Basel 21-22 May
15 Intl. Training Program on Urban Planning Infra-structure and Service Delivery for Indian Officials
Malaysia, Kuala Lumpur
22-24 May
16 Myanmar Urban Development Conference Myanmar, Yangon 25-28 May
17 5th Global Forum on Urban Resilience Germany, Bonn 29-31 May
18 CDIA Expert Group Meeting during the World Cities Summit
Singapore 1 June
19 World Cities Summit: Young Leaders & Mayors Forum
Singapore 2-5 June
20 Presentation at Eco-City Event (EU-Asia Dialogue) Singapore 5 June
21 Investing in Urban Climate Change Resilience: Sharing Lessons and Accelerating Action (Rockefeller Foundation)
Italy, Bellagio 2-6 June
22 Eschborner Fachtage: Word in motion: mobility, migration, digital change
Germany, Eschborn 17-18 June
23 Connective Cities Platform Launch Event (GIZ) Germany, Leipzig 24 June
24 Urban Nexus: Third Regional Workshop on Inte-grated Resource Management in Asian Cities (UN ESCAP/GIZ)
Vietnam, Da Nang 25-27 June
F.2 KEY ACTIVITIES PLANNED (JULY – DECEMBER 2014) Institutional and financial sustainability of CDIA: The 13th PRC meeting will be held in December 2014. A South-South City Leaders Forum organized by the ADB in early December 2014 and its 2015 Annual Meeting in Baku are furthermore used as opportunities to increase regional ownership of CDIA through more Asian funders. Major events/workshops: Key activities planned for July – December 2014 include:
Event Title Venue Date
1 ICLEI – ACCCRN Process Review Philippines, Makati 3-4 July
2 IPCC 5th Assessment Report Outreach Philippines, Manila 8 July
3 Urban Infrastructure Financing Options in the Asia Pacific Region: Short-course for City and Municipal Officers
Korea, Seoul 14-17 July
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 26
4 Urban Infrastructure Financing Options in the Asia Pacific Region: Training of Trainers
Korea, Seoul 14-19 July
5 Inter-American Development Bank Sustainable Urban Development Summer Course in Santander
Spain, Santander 28 July – 1 August
6 Partner Meeting - City Climate Finance Leadership Alliance
USA, Washington DC
4-5 August
7 OECD Bangkok Knowledge Sharing Workshop on Urban Green Growth in Dynamic Asia
Thailand, Bangkok 6-7 August
8 ADB Waterlinks Forum Philippines, Manila 11-13 August
9 APEC Urban Infrastructure Financing Forum Australia, Melbourne
1-2 September
10 UCLG ASPAC Congress 2014 Taiwan, Taipei 3 September
11 ADB conference: Innovation and Learning in a Changing Asia
Philippines, Manila 9-10 September
12 GIZ Sector Network Governance Asia Steering Group meeting
Philippines, Manila 10-12 September
13 ADB Transport Forum Philippines, Manila 15-18 September
14 Metropolis Congress GIZ-FMDV Session India, Hyderabad 7-10 October
15 1st Connective Cities Dialogue Event in Asia: Greening Cities and Promoting Urban Green Growth
Thailand 20-25 October
16 CDIA-MFA Singapore: Cities and Climate Change Singapore 10-14 November
17 7th Annual City Development Conference Singapore 21 November
18 CIIPP training for facilitators Cambodia 19-21 November
19 Clean Air Asia Better Air Quality Conference Sri Lanka, Colombo 19-21 November
20 CDIA Flagship Event: Investing in Asia’s Urban Future: Strengthening City-to-City Learning
Philippines, Manila 24-26 November
21 CityNet Congress Vietnam, Hue 28-30 November
22 ADB South-South City Leaders Forum Philippines, Manila 2-3 December
23 13th PRC Meeting Indonesia, Tangerang (tbc)
15-16 December
F.3 CDIA PUBLIC RELATIONS (PR) AND COMMUNICATIONS STRATEGY In light of the increased attention CDIA is receiving at the international level and to attract regional partners and applications, CDIA has boosted its PR and Communications to further institutionalize the corporate identity of CDIA and to support program goals with adequate PR instruments that will enhance CDIA’s image and create more awareness of what CDIA does. The PR and Marketing Activities as carried out by the new Communications specialist who joined CDIA in January 2014 are set out below:
Publications: Existing CDIA publications and knowledge material are being updated based on the latest achievements and assimilated through the use of a corporate design. During the reporting period, CDIA was approached by G20 to serve as an example for a comparison of project development facilities. The draft document suggests that CDIA compares fairly well.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 27
Exhibitions/public presentations: Exhibition booth and staffing in selected strategic regionally focused events such as the World Cities Summit, Singapore (June 2014, cmp. image to the left) and the ADB conference Enabling GrEEEn Cities (May 2014). CDIA China co-organized a GIZ booth at the EU-China Exhibition on Urban Development (Nov. 2013) to strengthen the relationship with GIZ Beijing and promote CDIA with the aim of increasing regional ownership of the initiative.
Targeted presentations: Creating standardized set of communication materials that each expert can carry on mission for presentation at local and national levels; as well as with potential strategic partners in each country.
Web- and Electronic Media: (1) Building an attractive and useful website that will encourage ‘return’ visitors and elevate ‘ranking’ of CDIA in search engines; (2) distributing a quarterly E-newsletter to a mailing list; (3) maintaining a CDIA Facebook page with visible interactivity and popularity based on LIKES (increase of about 44 new “LIKES” per month since Jan 2014); (4) producing a 60-second CDIA corporate video showing a simple, explaining-type video what CDIA does to be shown during presentations in training courses, conferences and activities.
The Key Messages We Are Communicating: Who We Are: CDIA is an international partnership initiative established in 2007 by the Asian Development Bank and the Government of Germany, with additional funding support from the governments of Austria, Sweden, Switzerland, and the Shanghai Municipal Government
What We Do: CDIA assists medium-sized Asian cities in identifying and developing urban investment projects and links them with potential financiers.
What We Have Done: By Aug. 2014, CDIA had interventions in 91 medium-sized Asian cities (65 PFS cities plus 26 others with CIIPP only); and 67 completed infra project studies in 9 different sectors (cmp. Figure 4 on page 9).
Where We Are Going: To carry out our mandate more effectively, CDIA will strengthen its activities in the following areas: (1) Service delivery processes to cities in pursuance of bridging the capacity gap, (2) Linking to finance in pursuance of bridging the planning-financing gap, and (3) CDIA as a catalyst for innovation in pursuance of bridging the institutional gap.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 28
ANNEX 1 CDIA RESULTS CHAIN AND INDICATORS FRAMEWORK 2013-2017
Impact (Long-term Development Effect):
Living conditions and the environment in Asian cities, particularly for the urban poor, have improved
Outcome (Overall Contribution of the CDIA Program 2007–2017):
Cities and partner organizations (national/ regional) prepare priority sustainable urban infrastructure investment projects, and link these
projects to finance (with focus on environment, climate change, pro-poor, good governance)
1. The services of 10 CDIA-accredited partner
organizations (national/ regional) are routinely
utilized by cities for their infrastructure
investment planning and programming, pre-
feasibility studies and linking these to finance,
utilizing CDIA process tools (sources: partner
organization certification, partner organizations
contract data, client surveys) [Dec. 2017]
2. In a total of 50 Asian cities, CDIA-supported
urban infrastructure investment projects that
have a focus on at least two development
impacts (out of four: environment, climate
change, pro-poor, and good governance) have
been accepted for funding and are implemented,
(sources: tracer studies, baseline end-2012: 20
projects in 10 cities) [Dec. 2017]
3. Supported by enhanced selected national
frameworks and the CDIA Institute, at least 10 cities
demonstrate that they have put into use/applied
CDIA good practice innovations in their routine local
infrastructure planning and/or financing processes.
(sources: good practice documentation, client
survey) [Dec. 2017]
Output (Results of CDIA 2013-2017)
“Bridging the capacity gap”
OUTPUT 1: Partner organizations (national/
regional) have been strengthened to
support cities in preparing infrastructure
investment projects
“Bridging the planning-financing gap”
OUTPUT 2: Cities have enhanced capacities
to access finance for prioritized sustainable
urban infrastructure investment projects
“Bridging the institutional gap”
OUTPUT 3: Sustainable knowledge and
innovation support for urban infrastructure
investment is available and accessible to
stakeholders
1. As part of their regular core activities, at least
10 accredited partner organizations provide
capacity development support for the
preparation of infrastructure investment
projects (sources: tracer studies, training
programs offered by partner organizations)
[Dec. 2017]
2. All CDIA NPO implemented city interventions
reflect inclusive processes and/or outcomes in
accordance with PFS guidelines, pro-poor
urban infrastructure investment guide and
gender strategy and action plan (sources: PFS
terms of reference, IPSIA, PFS reports,
progress reports). [Dec. 2014]
3. All CDIA NPO implemented city interventions
explore options for private sector involvement
in project implementation and/or financing
(sources: PFS reports, progress reports) [Dec.
2014]
1. In 40 cities, follow-up financing has been
secured for projects that demonstrate
sustainable development (sources: signed
agreements) [Dec. 2017]
2. Follow-up financing has been secured for five
additional pro-poor urban Infrastructure invest-
ment projects (sources: defined and approved
projects by cities and/or national agencies) [Dec.
2017]
3. Follow-up private sector participation has been
secured for five additional urban Infrastructure
investment projects (sources: defined project
documents approved by cities and/or national
agencies) [Dec. 2017]
4. Collaboration with 2 national pro-poor financing
institutions and 2 PPP centers or branches of
national government undertaking infrastructure
investment projects in cities has been assured
(sources: signed MoUs, joint work programs)
[Dec. 2014]
5. Appropriate framework is in place to enable
monitoring projects’ actual contribution to
development impacts. (sources: tracer studies,
client satisfaction surveys [Dec. 2013]
1. In 20 cities infrastructure planning processes
reflect lessons from CDIA centers of learning
(sources: assessment surveys of institutional,
organizational, and human capacities) [Dec. 2015]
2. In 6 countries, in collaboration with development
partners, CDIA processes are aligned with and
have enhanced nationally mandated urban
development processes (sources: minutes of
meetings, conference documents, national policies,
laws, regulations) [Dec. 2017]
3. Financing of CDIA core functions has been secured
with at least 4 regional partners contributing at least
60% (sources: agreements of organizations) [Dec.
2017]
4. 30% of CDIA city interventions will have (partial)
cost-recovery mechanisms in place (sources: TA
agreements) [Dec. 2017]
Main Activities (2013 - 2017)
1. 6 CDIA process tools (prioritization, PFS, PPP,
pro-poor, and two others) that mainstream
environment, climate change, pro-poor, gender,
and good governance will be developed,
updated, and/or localized (sources: CDIA
manuals/guidelines and software) [Dec. 2017]
2. 20 partner organizations will be trained and
supported in localizing and using CDIA process
tools (sources: training courses held, client
satisfaction surveys) [Dec. 2017]
3. 40 cities will receive capacity development
support through partner organizations in using
CDIA process tools (sources: NPO agreements
1. 50 cities will be supported in managing the
preparation of sustainable urban infrastructure
investment projects (source: CDIA city long list)
[Dec. 2017]
2. 10 urban infrastructure investment projects with
a demonstrable pro-poor focus will be prepared
(sources: CDIA city long list, project reports,
IPSIA evaluation) [Dec. 2016]
3. 10 urban infrastructure investment projects will
be prepared for private sector participation and
funding (sources: CDIA city long list, project
reports) [Dec. 2016]
4. A financier map of possible downstream in-
1. Innovative good practices based on CDIA
interventions will be documented and disseminated
to support the establishment of 10 cities as CDIA
centers of learning, demonstrating enhanced
organizational and human capacities for sustainable
urban infrastructure investments. (sources: on-line
database, NPO reports, client satisfaction surveys)
[Dec. 2017]
2. In 6 countries national CDIA strategies will be
developed and regularly updated to ensure linkages
to national development processes and financing
(source: country/regional strategies). [Dec. 2017]
3. CDIA Stakeholders Forum will be enhanced to
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 29
and training reports) [Dec. 2017]
4. A support accreditation system for partner
organizations (and consultants) will be
developed and made operational (sources:
CDIA quality assurance protocol, accreditation
system) [Dec. 2017]
vestors will be developed at the regional level
and for 6 selected countries (sources: financier
map, country strategies) [Dec. 2014]
5. All CDIA CMT implemented PFSs will apply tools
to secure inclusive processes and/or outcomes
in accordance with PFS guidelines, pro-poor
strategy, pro-poor urban infrastructure
investment guide and gender strategy and
action plan (sources: PFS terms of reference,
IPSIA, PFS reports, progress report) [July. 2013]
6. All CDIA CMT PFSs will apply tools to secure
reflection of possibilities of private sector
involvement in project implementation and/or
financing (sources: PFS reports, progress
reports [Dec. 2013]
ensure that CDIA operations reflect client demands
and regional partner interests (sources:
Stakeholders Forum effectiveness assessment)
[July 2013]
4. The CDIA monitoring and evaluation system will be
adapted to respond to the requirements of the
results chain, made operational and accessible
(source: on-line monitoring and evaluation)
[December 2013]
5. A sustainable institutional form has been
established for CDIA and made operational in at
least 3 locations (sources: legal documents,
operational manual, budget) [Dec. 2016]
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 30
ANNEX 2 IMPLEMENTATION MILESTONES
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1.1 6 CDIA process tools (Prioritization, PFS, PPP, Pro-poor and two others) which mainstream environment, climate change, pro-poor, gender, good governance, will be developed, updated and/or localized (source: CDIA manuals/guidelines and software) (Dec. 2017)
1.2 20 partner organizations will be trained and supported in localizing and using CDIA process tools (source: training courses held, client satisfaction surveys) (Dec. 2017)
1.3 40 cities will receive capacity development support through partner organizations in using CDIA process tools (source: NPO agreements and training reports) (Dec. 2017)
1.4 A support accreditation system for partner organizations (and consultants) will be developed and made operational (source: CDIA quality assurance protocol, accreditation system) (Dec. 2017)
2.1 50 additional cities will be supported in managing the preparation of sustainable urban infrastructure investment projects (source: CDIA city long list) (Dec. 2017)
2.2 10 urban infrastructure investment projects with a demonstrable pro-poor focus will be prepared(source: CDIA city long list, project reports, IPSIA evaluation) (Dec. 2016)
2.3 10 urban infrastructure investment projects will be prepared for private sector participation and funding (source: CDIA city long list, project reports) (Dec. 2016)
2.4 A financier map of possible downstream investors will be developed at regional level and for 6 selected countries (source: financier map, country strategies) (Dec. 2014)
2.5 All CDIA CMT implemented PFS will apply tools to secure increased inclusiveness (source: PFS ToR, IPSIA, PFS reports, Progress Report). (Dec. 2013)
2.6 All CDIA CMT PFS will apply tools to secure reflection of possibilities of private sector involvement in project implementation and/or financing (source: PFS reports, Progress Report (Dec. 2013)
3.1 Innovative good practices based on CDIA interventions will be documented and disseminated to support the establishment of 10 cities as CDIA centers of learning demonstrating enhanced organizational and human capacities for sustainable urban infrastructure investments. (Source: online data base, NPO reports, client satisfaction surveys). (Dec. 2017)
3.2 In 6 countries national CDIA strategies will be developed and regularly updated to ensure linkages to national development processes and financing (source: country/regional strategies). (Dec. 2017)
3.3 The CDIA governance structures will be enhanced to ensure CDIA operations reflect client demands and regional partner interests (source: minutes of advisory panel-; expert groups-; and stakeholders- meetings) (Dec. 2013)
3.4 The CDIA monitoring and evaluation system will be adapted to respond to the requirements of the results chain, made operational and accessible (source: online monitoring and evaluation) (December 2013)
3.5 The Cities Development Institute for Asia will be legally recognized and made operational in at least 3 locations (source: legal documents, operational manual, budget) (Dec. 2017)
Six-monthly work plans
Annual CMT Reviews
* to be firmed up in detailed activity planning on a six-monthly basis 2nd Mid-term review
Key Monitoring and Evaluation Milestones
Six-monthly progress reports
1st Self-assessment review (Q4/2014)
1st Mid-term review
2nd Self-assessment review (Q4/2016)
OUTPUT 3: Sustainable knowledge and innovation support for urban infrastructure
investment is available and accessible to stakeholders
Strengthen CDIA as a catalyst for innovation
2017
OUTPUT 1: Partner organizations (national/ regional) have been strengthened to support
cities in preparing infrastructure investment projects
OUTPUT 2: Cities have enhanced capacities to access finance for prioritized sustainable
urban infrastructure investment projects
CDIA S&B Plan 2013-2017 Activities and Broad Milestones
2013 2014 2015 2016 Indicative Progress 2013-2017*
Strengthen service delivery processes
Strengthen linking cities to finance
1ST MID
- TERM REVIEW
2ND MID
- TERM REVIEW
1ST MID
- TERM REVIEW
2ND MID
- TERM REVIEW
20% 40% 80% 60% 100
25% 40% 60% 85% 100
15% 35% 50% 75% 100
30% 75% 100
20% 40% 60% 80% 100
25% 50% 75% 100
25% 50% 75% 100
50% 100
100
20% 40% 60% 80% 100
20% 40% 80% 90% 100
40% 50% 80% 90% 100
100
20% 40% 80% 90% 100
100
Key CDIA=Cities Development Initiative for Asia; CMT=Core Management Team; NPO=national partner organization; IPSIA=Initial Poverty and Social Assessment; MoU=memorandum of understanding; PFS=prefeasibility study; PPP=public-private partnership; Q=Quarter; TA=technical assistance; TOR=terms of reference
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 31
ANNEX 3 APPROVED CITY INTERVENTIONS STATUS AND EXPECTED IMPACTS (JUN. 2014)
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 32
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 33
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 34
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 35
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 36
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 37
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 38
ANNEX 4 SUMMARY CDIA INC. ACTIVITIES REPORT (JAN.–JUN. 2014) AND OUTLOOK 2014
CDIA Inc. Strategic Context
In 2009, the Cities Development Initiative for Asia Incorporated (CDIA Inc.) was established to support the implementation of the program of activities of CDIA. CDIA Inc. is legally incorporated as a non-stock, non-profit corporation in the Philippines. In general terms, this arrangement provides for legal recognition of CDIA in the Philippines and facilitates ease of CDIA Core Management day-to-day operations.
The Articles of Incorporation and By-Laws reflect the subservience of CDIA Inc. to the overall governance structure of CDIA, in particular to the policy guidance of the CDIA Program Review Committee (PRC). To further safeguard this, two members of the Board of Trustees of CDIA Inc. (including the Chairman) serve with bilateral mandates of the PRC members ADB and BMZ respectively. In 2011, the Articles of Incorporation were changed and refer to CDIA Inc. as Cities Development Institute for Asia Inc. (changing from “initiative” to “institute”).
CDIA Inc. work plans are an integral part of the CDIA CMT work plans. As such, CDIA Inc. activities have been included in the main part of this progress report. However, this annex separately reports on CDIA Inc. operational activities as per PRC members’ request. Operational activities January – June 2014
Activities in the reporting period have been carried out in the areas of Regional Networking and Capacity Development. Table 8 below specifies the expenditures of CDIA Inc. for the first half of 2014:
Table 8 Financial Overview of CDIA Inc. for 2014
For 2014, the budget of CDIA Inc. totaled about USD254,488. CDIA Inc. is supported by ADB for operational activities through RETA 6293 (provision of office facilities & utility bills and admin-istrative staff). GIZ provided support through Financing Agreement for the activities on (i) capacity strengthening of NPOs, (ii) indirect city interventions through NPOs; (iii) Young Asian Professional Program (YAPP); (iv) cross-cutting topic on Climate Change Mitigation and adaptation; (v)
Stakeholders’ Forum Expert Group; and (vi) Publications. Rockefeller Foundation funded CDIA Inc. to complete the study “From Climate Change Resilient Planning to Urban Investments in Asian Cities”.
Jan - June
in USD
Professional Expert - Local 4,089.45
Local Experts on IT 434.45
Locally Contracted Personnel 20,569.50
Maintenance & Other Operating Expenses 11,716.40
Sub-total 36,809.80$
17,659.57
13,762.58
8,771.43
4,866.00
Sub-total 45,059.58$
Consultancy Services (support to project activities)
10,615.00
Sub-total 10,615.00$
Over-all Expenditures 1st half of 2014 92,484.38$
Budget Available for 2014 254,488.00$
Percentage of Utilisation 36%
Pre-Feasibility Studies (PFS) and Public Private Partnership Tools
Linking Climate Change Resilient Planning to Urban Investments in
Asian Cities
2014 Financial Overview CDIA Inc
Expenses
Operational Expenses
Project/Activities
CDIA Cities Infrastructure Investment Priority Programming (CIIPP)
Training Course on Cities and Climate Change
Training Course on Effective Infrastructure Programming
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 39
Following are the activities supported by CDIA Inc. in the first half of 2014:
i) Regional Networking and Capacity Development
During the reporting period, CDIA Inc. resources were among others used for, and in the form of participation fees also partially generated from, the following:
Introduction Training for Implementing the City Infrastructure Investments Prioritization and Programming (CIIPP) and Pre-Feasibility Studies Toolkits, 14-17 January 2014, Bangkok, Thailand
Effective Urban Infrastructure Programming Course, 5-14 March 2014, Singapore
Training on Cities and Climate Change, 26-28 March 2014, Singapore
Pre-feasibility Studies (PFS) and Public Private Partnership Tools
ii) Climate Change related topics
During the last quarter of 2013, CDIA Inc. started work through a grant from Rockefeller Foundation on a study called “From Climate Change Resilient Planning to Urban Investments in Asian Cities”. The study will undertake a scan of climate resilience action plans as prepared in 10 cities and identify down-stream financing options for infrastructure investments as prepared through climate resilience action plans. A consultant was recruited by CDIA Inc. to undertake the work. This assignment is expected to conclude in the last quarter of 2014.
iii) 13th Board of Trustees (BoT) meeting and 5th Annual General Meeting (AGM) of members
On May 28, 2014 the CDIA Inc. Board of Trustees and members gathered to discuss the audited financial report of 2013, the outcomes of the 12th PRC meeting concerning CDIA’s sustainability and the vacancy of CDIA Inc.’s Executive Director. Also, the trustees with expiring terms were re-elected. It was reiterated that CDIA Inc., in its present form, still provided value added to the CDIA Program by (i) obtaining funds that the CDIA Program is not able to receive, and (ii) receiving funds through cost recovery which the CDIA Program also cannot do.
Operational activities envisioned for 2014
It is envisioned that the following activities are pursued through CDIA Inc. subject to budget availability:
Complete the work for Rockefeller Foundation to undertake a scan of climate resilience action plans as prepared in 10 cities. For this CDIA Inc. has recruited one consultant which is funded with Rockefeller funds while another consultant has been recruited using GIZ funds;
Workshops within the framework of the 2014 cross-cutting theme which is focusing on how cities learn;
Capacity strengthening of National Partner Organizations (NPOs) including direct work in cities as well training activities for NPOs;
Young Asian Professional Program (2 YAPPs from Mongolia and Sri Lanka);
Stakeholders’ Forum Expert Group meeting activities;
Continue to run smaller assignments through CDIA Inc. for which third parties such as World Bank and Rockefeller pay CDIA Inc. a fee;
Continue to work toward CDIA Inc. tax-free status and following up on the CDIA Inc. bill in the Senate.
As CDIA is working towards financial long-term sustainability, CDIA aims that in at least 30% of CDIA city interventions, partial cost-recovery mechanisms are in place (CDIA Impact Chain in Strategy and Business Plan 2013-2017). Since both CDIA implementing parties, GIZ and ADB, are unable to receive funds generated through cities or financing agencies through such cost-recovery mechanisms, CDIA Inc. is essential for accommodating such funds. This requires endorsement by the CDIA Program Review Committee at its next meeting.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 40
ANNEX 5 PRO-POOR AND INCLUSIVE PROGRESS NOTE
In response to PRC requests for increased M&E efforts, a comprehensive evaluation of the previous “Initial Poverty and Social Impact Assessments” (IPSIAs) for PFSs was undertaken. The results are attached to this report as a separate document. This section thus only refers to some highlights.
During the reporting period, the following progress was achieved with regard to poverty reduction and inclusiveness:
By the first half of 2014, CDIA staff and partners were able to successfully disseminate and initiate discussions on the needs of disadvantaged groups in the urban context among its training course participants.
To respond to the need of providing innovative examples and well-thought-through ideas for a pro-poor and socially inclusive project design, CDIA developed a brief overview of sector-specific good practices and started to disseminate the information to PFS consultants and municipal officials.
CDIA strengthened its collaboration on pro-poor activities with UN ESCAP and UN-Habitat by supporting their regional Training of Trainers (ToT) on Pro-poor Urban Climate Resilience in Asia-Pacific, held at UP Diliman in Quezon City, Philippines, in March 2014.
In April, CDIA hosted three events as part of the official program of the World Urban Forum 7. Among them an event on “How to Strengthen Urban Spatial Planning to Reduce Social Vulnerability and Exclusions in South Cities?” – a training session highlighting urban vulnerability and social segregation and developing innovative solutions on how spatial planning and infrastructure investments can address these challenges. The event was jointly organized with CDIA’s partner organization CEPT and locally supported by SKL International.
IPSIAs were completed for all of CDIA’s completed 67 PFS projects. While 57 IPSIAs were completed under S&BP 2007-12, 10 IPSIAs can be counted since release of CDIA’s new S&BP in 2013. In total 6 completed PFSs explicitly target poverty reduction, while as many as 47 aim at enhanced inclusiveness. From all the PFSs carried out during 2007 to 2012, 79% are considered as ‘pro-poor’-targeted and enhancing inclusiveness by improving the living conditions of the urban poor and disadvantaged people like women, the elderly and children.
80% of the 10 PFSs completed since 2013 reflect a ‘pro-poor’ approach, with 1 explicitly targeting poverty reduction – meaning the majority of beneficiaries are vulnerable with low resources – and 7 approaching enhanced inclusiveness.
Under the new S&BP, the estimated number of poor and disadvantaged residents to benefit from infrastructure investments of completed PFSs in 7 different cities is about 514,000, with about 17,000 urban poor and members of other vulnerable groups, like the elderly, women and children benefiting from direct positive impacts.
In contrast to the PFSs applied before 2012, all PFSs from 2013 onwards assigned a Social Development Specialist (SDS) to the respective consultant team working with the city.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 41
ANNEX 6 PRC RECOMMENDATIONS & FOLLOW-UP
Recommendations were made by the CDIA Program Review Committee (PRC) during its 12th meeting in Berlin in March 2014; none were received via email.
RECOMMENDATIONS OF THE PRC FOLLOW UP BY CDIA
AGENDA ITEM 4 – ADOPTION OF THE MINUTES OF THE 10TH
AND 11TH
PRC MEETINGS
1. According to the PRC Protocol, the Minutes are to be finally approved by the Chair after circulation to the PRC members and upon receipt of their comments.
Done.
AGENDA ITEM 5 – CDIA JULY-DECEMBER 2013 PROGRESS REPORT
1. The formulation of the indicators is not consistent in relevant management documents and the progress report. This needs to be revised based on the formulation in the S&BP.
Done.
2. M&E efforts should be increased based on the CDIA Results Chain and Indicators Framework 2013-2017.
In progress. Revised M&E draft concept note expected to be shared with PRC for comments in October 2014.
3. M&E efforts need to track how many of the investment projects that are linked to financing and implemented tackle development impacts addressed by CDIA. The focus should be on monitoring whether as part of CDIA project preparatory work, the various development impacts are sufficiently addressed and flagged for further downstream financing.
Tracer studies were initiated during the reporting period and results will be presented in future progress reports.
4. Concrete Baseline and Target values will be added to each indicator. Also, possible changing of indicator 3.1 should be assessed by Mid-term Review.
Initial advisory services regarding the M&E system were received at the end of the reporting period. Recruitment of an M&E specialist is expected to be finalized in September 2014.
5. The Pro-Poor Progress Note in Annex 5 was welcomed. From now on, the progress report should focus on the overall performance of CDIA on poverty reduction and gender-related activities for the respective reporting period, and elaborate on specific activities and the use of relevant tools, in particular the IPSIA.
Done. In addition, a comprehensive IPSIA assessment has been undertaken and published as separate report.
AGENDA ITEM 6 – PLANNING FOR CDIA MID-TERM REVIEW Q3-Q4
1. Based on the previous discussion on the M&E system (Agenda Item 5), it was decided to focus on Objective 1 and 2 mentioned in the current draft Terms of Reference (ToR) rather than overburdening the mission with objective 3. Objective 2 is to be split so that a new Objective 3 refers to reviewing the M&E system and give recommendations how it can be further improved to assess development impacts within the CDIA mandate.
Done.
2. The CMT was asked to submit a revised ToR by 10 April in track changes.
Done.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 42
AGENDA ITEM 7 – CDIA PARTNERSHIP ACCREDITATION
1. The Mid-Term Review is expected to give recommendations concerning the role of RPOs and NPOs.
Noted.
2. It was furthermore suggested to circulate the concept note for comments to the Stakeholders’ Forum Expert Group.
Done. However, in spite of various reminders, no comments have been received to date.
AGENDA ITEM 9 – CDIA LONG TERM SUSTAINABILITY
1. It was agreed that the following PRC Priorities need to be reflected in the future institutional set-up of CDIA:
• Regional Ownership/Membership of regional partners • Maintain policy guiding body • Demand driven-approach • Options for cost-recovery • Capacity development activities • Funding options for KFW and ADB
Noted.
2. It was agreed to further pursue Option 1 while at the same time remain open for trust-fund option in the future and explore potential when window of opportunity opens up.
Noted.
3. ADB is to make a proposal on how it could increase its role within and support to CDIA, including stronger coordination between ADB and CDIA, HR support, strategic support, and lobbying for regional membership.
In progress.
4. Mid-Term Review is to submit a proposal at the next PRC meeting how CDIA Inc. can be streamlined with CDIA.
Included in ToR and briefing for MTR consultants.
5. Core funding It may be considered to allow for a variety of membership/sponsorship from regional donors in addition to the present flexibility regarding tied and untied contributions.
A working group consisting of SECO (Alain Geiger), BMZ (Josef Füllenbach) and the CMT will submit a proposal of financial mechanisms and criteria for new CDIA contri-butors to the next PRC meeting, including various kinds of memberships, membership fees, and the potential impact of the suggested changes on the current PRC Protocol, and a footnote on the development priorities of potentially new donors.
No feedback on progress during the reporting period.
6. Engaging new members through initiatives on the political level It is intended to convene current and prospective PRC members in the sidelines of the annual ADB meeting in May 2015.
ADB (Gil-Hong Kim) will inquire within ADB on this possibility.
BMZ will include a paragraph in briefing note of Mr. Fuchtel (State Secretary) for bilateral talks with the ADB during the ADB Annual Meeting which takes place in the first week of May 2014. Other PRC members are encouraged to do likewise.
Such talks should also remark that ADB is encouraged to assume a stronger role within CDIA.
ADB (Srinivas Sampath) will draft a concept note (0.5 pages) on the objective of this side event to be used by PRC members to raise the issue with the respective delegations to the ADB annual meeting in 2014.
Forum on urban development secured for next ADB Annual Meeting in Baku. Done. Done. Done. Done.
Six-monthly Progress Report January – June 2014 and Workplan July – December 2014 43
7. Cost recovery The Strategic Options Study has highlighted a range of options for cost recovery mechanisms.
CMT will submit a proposal for concrete steps for the next PRC meeting including ways of cost sharing and parallel financing as an alternative and how more regional consultants can be engaged to lower the cost per PFS.
In progress for next PRC meeting.
8. Stronger coordination of CDIA with ADB and KfW
Respective suggestions and decisions are to be
communicated at next PRC meeting. These should include the use of the KfW study fund.
The internal CDIA country strategies should take into account potential synergies.
The latest progress report should reflect the reasons for
the few successful linkages.
In progress for next PRC meeting. During the reporting period, coordination took place with regard to cities of common interest in India and Indonesia, and an application was approved by CMT for a collaboration in Batumi, Georgia. Done, cmp. p. 9.
9. Programmatic approaches to project development It was decided to “maintain the demand driven approach by CDIA and to further pursue programmatic ap-proaches where deemed necessary”.
CMT to report on activities undertaken with regard to its annual themes and to facilitate a discussion on their implications at the next PRC meeting.
The Mid-Term Review is to make further recommendations in case it perceives a programmatic approach as necessary for CDIA to reach its indicators.
In progress for next PRC meeting. In progress.
10. Focus on core countries If CDIA is to focus on certain countries, its relationships with NPOs are highly important therein.
CMT is to suggest criteria for the selection of core countries in light of increasing demand for its support to cities.
For next PRC, CMT will share for information up to 4 country strategies.
Noted and in progress. Discussions are among other countries ongoing in Indonesia. In progress for next PRC meeting. In progress for next PRC meeting.
AGENDA ITEM 12 – ANY OTHER BUSINESS
1. The chair noted that much better use could be made of CDIA’s advisory panel.
CMT to provide list with advisory panel members for the PRC to decide whether or not to reactivate the panel and debate composition at next meeting.
Done.
Cities Development Initiative for Asia
Suite 202-203 Hanston Building, Emerald Ave., Ortigas Center, Pasig City 1605,
Metro Manila, Philippines Phone: +63-2 631-2342 • Fax: +63-2 631-6158
Website: www.cdia.asia
CDIA is supported by: