June 2013 © CRMCA.com1

Hidden Landmines in Concrete Specifications

Eric T. Misenheimer, PEChair, CRMCA Technical

Committee

June 22, 2013

Page 2: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com2

What is a Specification?

A specification (often abbreviated as spec) is an explicit set of requirements to be satisfied by a material, design, product, or service. – ASTM

Page 3: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com3

Why should we be concerned?

Specification Requirements:– Aggregates

Alkali Silica Reactivity – ASR

– Concrete Properties Shrinkage Permeability Air Void Analysis Freeze-Thaw Durability Scaling Resistance

Page 4: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com4

Why should we be concerned?

Time– From 16 days to 68 weeks

– Most tests around 30 days, but some take SIGNIFICANTLY longer

– Communicate the time frame(s) to potential bidders so that they are aware of schedule impacts.

– Avoid last minute job award/submittal requests

Page 5: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com5

Why should we be concerned?

Cost– From $400 per test to $2500 per test

– Make sure that ALL anticipated testing costs are captured and expensed

Page 6: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com6

C 1260/C 1567 Example – Standard**Note age of data allowed**

Page 7: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com7

C 1260/C 1567 Example – 30 days

Page 8: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com8

Why should we be concerned?

Variance from ASTM Standard– Communicate with lab performing test to make

sure variance is noted and incorporated and test is run to completion

– Check on additional cost of variance

Page 9: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com9

C 157 - Example

Page 10: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com10

C 457 Example

Page 11: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com11

C 457/C 666 Example

Page 12: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com12

Why should we be concerned?

Design vs. Construction Testing

– Construction stage testing can be very difficult

Most tests are intended for lab conditions

– Many construction stage tests are affected by conditions beyond our control

Placement, consolidation, finishing and curing

– Make sure design and construction testing responsibilities/liabilities are covered in your contractual/PO agreements

Page 13: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com13

C 1202 Example

Page 14: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com14

Test – Standard – Time – Cost

Test Purpose ASTM Time Cost CommentsStandard Required

Petrographic Exam - Aggregates

C 295 ** $2000 to $2500 ** No specific time for test, but highly specialized and very few labs perform this test. Can take 30 days to get results.

Alkali Reactivity - Aggregates

C 1260 16 to 30 days

$1000 to $1600 Standard calls for 16 days but some specs extend to 30 days

Alkali Reactivity – w/ Cementitious

C 1567 16 to 30 days

$1000 to $1600 Standard calls for 16 days but some specs extend to 30 days

Shrinkage C 157 ** $500 to $1200 ** Standard calls for 28 days initial curing followed by up to 64 weeks. Typically modified to 7 days initial curing followed by 28 days.

Microscopic Air Void Analysis

C 457 ** $400 to $600 ** No specific time for test, but highly specialized and very few labs perform this test. Can take 30 days to get results.

Page 15: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com15

Test – Standard – Time – Cost

Test Purpose ASTM Time Cost CommentsStandard Required

Freeze-Thaw Resistance C 666 40 to 60 days**

$1200 to $1500 **Procedure after 14 days(typical) curing

Permeability (?) C 1202 ** $500 to $700 **Curing method controls length. Typically 28 days.

Scaling Resistance C 672 50 days** $800 to $1000 **Procedure after 28 days(typical) curing

Page 16: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com16

Why should we be concerned?

Time

– Time noted in tables is for the test only Does noted include gathering/delivering materials to the

lab or mix/sample preparation

Costs– Costs noted in table are for standard test

procedures and any variance from the standard can have SIGNIFICANT effect on test costs.

Page 17: June 2013 © CRMCA.com 1 Hidden Landmines in Concrete Specifications Eric T. Misenheimer, PE Chair, CRMCA Technical Committee June 22, 2013

June 2013 © CRMCA.com17

QUESTIONS ??