Upload
pratap-kumar
View
213
Download
0
Embed Size (px)
Citation preview
8/3/2019 july22-elec-venkatraman
1/24
ABCD
22 July 2003
R Venkatraman, KPMG Consulting
Electricity Act 2003 Opportunities forInvestment & Growth
Transmission Issues
8/3/2019 july22-elec-venkatraman
2/24
ABCD
Background
Indian Electric Transmission grid consists of
nearly 5.7 Million km of high-voltage transmission
lines.
In recent years, the number of transactions and
quantity of power flows on the transmission grid
has increased significantly.
At the same time, transmission investments have
been declining.
8/3/2019 july22-elec-venkatraman
3/24
ABCD
1168MW500MW
166MW
100MW
100MW
1067MW
420MW
100MW
1180MW
1944MW
3187MW
3475MW
100MW 90MW
140MW
1500MW
150MW
1170MW330MW
135MW
450MW
80MW
100MW
Generation capacity addition is expected tocontinue at a brisk pace
State & private sector only.
Central Sector not included
8/3/2019 july22-elec-venkatraman
4/24
ABCD
Generation capacity addition is expected tocontinue at a brisk pace
X Plan Target (2002-2007)
Central State Private Total
Thermal 12,790 6,676 5,951 25,417
Hydro 8,742 4,481 1,170 14,393
Nuclear 1,300 - - 1,300
Total 22,832 11,157 7,121 41,110
The transmission grid will need to transport all this
power to the consumer .
8/3/2019 july22-elec-venkatraman
5/24
ABCD
Consequently, the impact on transmissionwill be significant
Massive new transmission capability needs to be
built to match the increase in generation capacity
Existing transmission infrastructure needs to be
significantly upgraded
Congestion management and system operations
will be key
Information availability will need to raise
dramatically Robust monitoring mechanisms must be
introduced
8/3/2019 july22-elec-venkatraman
6/24
ABCD
And, there are some pre-requisites
Non discriminatory open access and a strong market are
pre-requisites for competition.
Return on Investment and depreciation mechanisms may
need to be reviewed to make it attractive for investors.
A strong and reliable transmission network widens the
market, making it more competitive by allowing more
entities to compete.
Savings to the customers are expected from competition in
generation sector.
- Unless competing generators can reach consumers
efficiently, competition in generation will not produce the
benefits expected.
8/3/2019 july22-elec-venkatraman
7/24ABCD
The Electricity Act seeks to address theseissues through .
Introduction of Open Access.
Creation of National Grid
Creating environment for private investments in
transmission
Technical up gradations
Introduction of market mechanisms
Better coordination and planning by NLDC, RLDC,
SLDC & DLDC(Discom/Area LDCs)
Grid discipline, open access and investment promotion
are critical action areas
8/3/2019 july22-elec-venkatraman
8/24ABCD
1. Grid Discipline2. Non Discriminatory Open Access
3. New Investment in Transmission
8/3/2019 july22-elec-venkatraman
9/24ABCD
The root causes of grid indiscipline
InadequateG enerationC apacity
G R I D I N D I SC I PL IN E
Low focus onEconomi c D ispatch& Unit Commitment
A bsence of Tools& Procedures
PoorPredictability
D e lib era te D e v ia t ion s In ad v e rt en t D ev ia tion s
Power system control priorities System security
Maintaining load / generation balance
Economic dispatch
8/3/2019 july22-elec-venkatraman
10/24ABCD
Grid discipline some issues
Grid discipline issues have resulted from
- Absence of tools and guidelines
- Lack of sufficient generation capacity
In ABT, adherence to drawal schedule may not solve the
frequency problem if grid constituents continue to overload
it.
After ABT, ground situation has not changed much as the
grid constituents in general have preferred to allow the
frequency to decline rather than to proactively shed load. ABT may not address frequency problem where CGS
contribution is low since impact of UI (Unscheduled
Interchange) charges on utility finances is low.
8/3/2019 july22-elec-venkatraman
11/24ABCD
Grid discipline - some suggestions
Frequency regulation needs to be monitored on real time
basis
- Through reliability rules and procedures and not merely by
relying on monetary incentive/ disincentive framework.
The Area Control Error (ACE) principle could be one methodto strengthen frequency control.
- ACE specifies responsibility on each constituent to bring
back the frequency to normative level, even if stated
schedules are being adhered to.
- ACE concepts could be incorporated within ABT to
supplement the price signals in ABT once the system
frequency drops below, say, 49 Hz.
However for this to be effective additional statutory powers
to the regulator and the load dispatcher may be necessary.
8/3/2019 july22-elec-venkatraman
12/24ABCD
Grid discipline - some suggestions
Utilities need to undertake extensive load research to
evaluate the magnitude and characteristics of current load
(both served and unserved), and future load addition.
Load research can not only increase accuracy of load
forecast, but also assist in formulation of demand sidemanagement measures.
A significant systemic tool like Energy Management System
(EMS), has features addressing short term unit commitment,
economic load dispatch and settlements.- Makes it suitable for current needs as well as future
requirements under arrangements like multi-buyer
markets.
8/3/2019 july22-elec-venkatraman
13/24ABCD
EMS - a tool to a tool for efficient dispatch
Cost of procurement
Hydro generation
schedule
XA/21
Dispatch
schedule
Cost of procurement
Grid demand
Thermal & hydro
station availability
Water availability
Machine parameters
MS SQL Server
VB based front-end
Planning
Output
Annual Dispatch Planning
8/3/2019 july22-elec-venkatraman
14/24
ABCD
1. Grid Discipline2. Non Discriminatory Open Access
3. New Investment in Transmission
8/3/2019 july22-elec-venkatraman
15/24
ABCD
Some of the pre-requisites for open accessare
Improved reliability of T & D network.
Reliable information systems.
Technical adequacy of transmission lines.
Knowledge on available capacity (measure
congestion).
Transparent energy accounting systems.
Balancing mechanisms
8/3/2019 july22-elec-venkatraman
16/24
ABCD
Open access some issues
Transmission system development would become more
complex.
CTU & STUs need to strengthen/improve existing networks
to remove congestion & make a realistic plan for expansion.
The concern for stranded cost will increase.
Network operation/planning to take in to consideration of
minimising stranded costs.
Transaction costs have to be minimised so that they do not
off set the benefits of competition.
Regulatory control on transmission access and pricing
would be critical
8/3/2019 july22-elec-venkatraman
17/24
ABCD
Open access some issues
Accuracy of determination of total & available transmission
Capacity is one of the requirements for operating under
open access.
Most utilities' current pricing schemes do not effectively
address the costs of transmission constraints. Nor do they
provide the proper signals concerning whether to remove
constraints through supply side generation, transmission
expansion or demand side measures.
When individual utilities schedule power flow over a singleregional grid, unexpected overloads can arise and become
barriers to competitive power trading.
8/3/2019 july22-elec-venkatraman
18/24
ABCD
1. Grid Discipline2. Non Discriminatory Open Access
3. New Investment in Transmission
8/3/2019 july22-elec-venkatraman
19/24
ABCD
Transco
STU
SLDC
To ensure integrated operation of power system in
the state
Responsible for optimum scheduling and dispatch
Keep account of quantity of electricity transmitted
through state grid Real time operation of grid controls and dispatch
through secure and economic operation
Transmission of electricity through intra-statetransmission system
Planning and co-ordination Ensure development of intra-state transmission
lines. To provide non-discriminatory open access to its
transmission
To build, maintain and operate an efficient andeconomical inter-state or intra-state transmission
system. To comply with the directions of RLDC and SLDC
as the case may be.Lic
ens
ee
Trading
Bulk supply trading of all existing
Contracts
Transmission service
provider
System operator.
Bulk supplier/Trader
EarlierEarlier NowNow
The new structure is complex
8/3/2019 july22-elec-venkatraman
20/24
ABCD
Business separation will be important
Separation of monopoly transmission businesses
from competitive or potentially competitive
activities.
Options range from full ownership separation tomanagement separation.
Europe has a mix of these:
- Ownership unbundling (UK, Finland, Spain, etc)
- Legal unbundling (Austria, Belgium, Denmark, etc)
- Management unbundling (France, Luxembourg)
Source: Ian Pope Associates
8/3/2019 july22-elec-venkatraman
21/24
ABCD
In addition, monitoring regimes are requiredto ensure fairness
Separation and publication of accounts
Appointment of a compliance officer whose job
is to ensure that network access rules are applied
equally and fairly Establishment of a separate corporate identity for
the TSO
Ensuring that the TSO is not physically located in
the same building as an affiliate operating in the
competitive market
Source: Ian Pope Associates
8/3/2019 july22-elec-venkatraman
22/24
ABCD
European experience .
Country Publishe daccounts
Complianceofficer
Separatecorporate ID
Separatelocations
Austria Yes No Yes Yes
Belgium Yes No Yes Yes
Denmark Yes Yes Yes Yes
Finland Yes Yes Yes Yes
France Yes Yes Yes Yes
Germany Yes No Yes Yes
Greece Not yet No Yes Yes
Ireland Yes Yes Yes No
Italy Yes No Yes Yes
Luxembourg Yes No No No
Netherlands Yes Yes Yes Yes
Portugal Yes No Yes Yes
Spain Yes Yes Yes Yes
Sweden Yes Yes Yes Yes
UK Yes Yes Yes YesSource: Ian Pope Associates
8/3/2019 july22-elec-venkatraman
23/24
ABCD
Encouraging investments somesuggestions
Adequate returns (risk adjusted) on the investments andattractive depreciation norms.
Ensure separation of business & introduce monitoring
regime
Realistic transmission planning by CTU/STU based onscientific load research/load forecast & generation plan.
Regulatory certainty over a long period
Cost reflective retail tariffs
Establishment of effective/reliable communication networkand energy data collation system
Settlement systems
Addressing the stranded cost issue
8/3/2019 july22-elec-venkatraman
24/24
ABCD
Thank you
R Venkatraman, KPMG ConsultingEmail: [email protected]