july22-elec-venkatraman

Embed Size (px)

Citation preview

  • 8/3/2019 july22-elec-venkatraman

    1/24

    ABCD

    22 July 2003

    R Venkatraman, KPMG Consulting

    Electricity Act 2003 Opportunities forInvestment & Growth

    Transmission Issues

  • 8/3/2019 july22-elec-venkatraman

    2/24

    ABCD

    Background

    Indian Electric Transmission grid consists of

    nearly 5.7 Million km of high-voltage transmission

    lines.

    In recent years, the number of transactions and

    quantity of power flows on the transmission grid

    has increased significantly.

    At the same time, transmission investments have

    been declining.

  • 8/3/2019 july22-elec-venkatraman

    3/24

    ABCD

    1168MW500MW

    166MW

    100MW

    100MW

    1067MW

    420MW

    100MW

    1180MW

    1944MW

    3187MW

    3475MW

    100MW 90MW

    140MW

    1500MW

    150MW

    1170MW330MW

    135MW

    450MW

    80MW

    100MW

    Generation capacity addition is expected tocontinue at a brisk pace

    State & private sector only.

    Central Sector not included

  • 8/3/2019 july22-elec-venkatraman

    4/24

    ABCD

    Generation capacity addition is expected tocontinue at a brisk pace

    X Plan Target (2002-2007)

    Central State Private Total

    Thermal 12,790 6,676 5,951 25,417

    Hydro 8,742 4,481 1,170 14,393

    Nuclear 1,300 - - 1,300

    Total 22,832 11,157 7,121 41,110

    The transmission grid will need to transport all this

    power to the consumer .

  • 8/3/2019 july22-elec-venkatraman

    5/24

    ABCD

    Consequently, the impact on transmissionwill be significant

    Massive new transmission capability needs to be

    built to match the increase in generation capacity

    Existing transmission infrastructure needs to be

    significantly upgraded

    Congestion management and system operations

    will be key

    Information availability will need to raise

    dramatically Robust monitoring mechanisms must be

    introduced

  • 8/3/2019 july22-elec-venkatraman

    6/24

    ABCD

    And, there are some pre-requisites

    Non discriminatory open access and a strong market are

    pre-requisites for competition.

    Return on Investment and depreciation mechanisms may

    need to be reviewed to make it attractive for investors.

    A strong and reliable transmission network widens the

    market, making it more competitive by allowing more

    entities to compete.

    Savings to the customers are expected from competition in

    generation sector.

    - Unless competing generators can reach consumers

    efficiently, competition in generation will not produce the

    benefits expected.

  • 8/3/2019 july22-elec-venkatraman

    7/24ABCD

    The Electricity Act seeks to address theseissues through .

    Introduction of Open Access.

    Creation of National Grid

    Creating environment for private investments in

    transmission

    Technical up gradations

    Introduction of market mechanisms

    Better coordination and planning by NLDC, RLDC,

    SLDC & DLDC(Discom/Area LDCs)

    Grid discipline, open access and investment promotion

    are critical action areas

  • 8/3/2019 july22-elec-venkatraman

    8/24ABCD

    1. Grid Discipline2. Non Discriminatory Open Access

    3. New Investment in Transmission

  • 8/3/2019 july22-elec-venkatraman

    9/24ABCD

    The root causes of grid indiscipline

    InadequateG enerationC apacity

    G R I D I N D I SC I PL IN E

    Low focus onEconomi c D ispatch& Unit Commitment

    A bsence of Tools& Procedures

    PoorPredictability

    D e lib era te D e v ia t ion s In ad v e rt en t D ev ia tion s

    Power system control priorities System security

    Maintaining load / generation balance

    Economic dispatch

  • 8/3/2019 july22-elec-venkatraman

    10/24ABCD

    Grid discipline some issues

    Grid discipline issues have resulted from

    - Absence of tools and guidelines

    - Lack of sufficient generation capacity

    In ABT, adherence to drawal schedule may not solve the

    frequency problem if grid constituents continue to overload

    it.

    After ABT, ground situation has not changed much as the

    grid constituents in general have preferred to allow the

    frequency to decline rather than to proactively shed load. ABT may not address frequency problem where CGS

    contribution is low since impact of UI (Unscheduled

    Interchange) charges on utility finances is low.

  • 8/3/2019 july22-elec-venkatraman

    11/24ABCD

    Grid discipline - some suggestions

    Frequency regulation needs to be monitored on real time

    basis

    - Through reliability rules and procedures and not merely by

    relying on monetary incentive/ disincentive framework.

    The Area Control Error (ACE) principle could be one methodto strengthen frequency control.

    - ACE specifies responsibility on each constituent to bring

    back the frequency to normative level, even if stated

    schedules are being adhered to.

    - ACE concepts could be incorporated within ABT to

    supplement the price signals in ABT once the system

    frequency drops below, say, 49 Hz.

    However for this to be effective additional statutory powers

    to the regulator and the load dispatcher may be necessary.

  • 8/3/2019 july22-elec-venkatraman

    12/24ABCD

    Grid discipline - some suggestions

    Utilities need to undertake extensive load research to

    evaluate the magnitude and characteristics of current load

    (both served and unserved), and future load addition.

    Load research can not only increase accuracy of load

    forecast, but also assist in formulation of demand sidemanagement measures.

    A significant systemic tool like Energy Management System

    (EMS), has features addressing short term unit commitment,

    economic load dispatch and settlements.- Makes it suitable for current needs as well as future

    requirements under arrangements like multi-buyer

    markets.

  • 8/3/2019 july22-elec-venkatraman

    13/24ABCD

    EMS - a tool to a tool for efficient dispatch

    Cost of procurement

    Hydro generation

    schedule

    XA/21

    Dispatch

    schedule

    Cost of procurement

    Grid demand

    Thermal & hydro

    station availability

    Water availability

    Machine parameters

    MS SQL Server

    VB based front-end

    Planning

    Output

    Annual Dispatch Planning

  • 8/3/2019 july22-elec-venkatraman

    14/24

    ABCD

    1. Grid Discipline2. Non Discriminatory Open Access

    3. New Investment in Transmission

  • 8/3/2019 july22-elec-venkatraman

    15/24

    ABCD

    Some of the pre-requisites for open accessare

    Improved reliability of T & D network.

    Reliable information systems.

    Technical adequacy of transmission lines.

    Knowledge on available capacity (measure

    congestion).

    Transparent energy accounting systems.

    Balancing mechanisms

  • 8/3/2019 july22-elec-venkatraman

    16/24

    ABCD

    Open access some issues

    Transmission system development would become more

    complex.

    CTU & STUs need to strengthen/improve existing networks

    to remove congestion & make a realistic plan for expansion.

    The concern for stranded cost will increase.

    Network operation/planning to take in to consideration of

    minimising stranded costs.

    Transaction costs have to be minimised so that they do not

    off set the benefits of competition.

    Regulatory control on transmission access and pricing

    would be critical

  • 8/3/2019 july22-elec-venkatraman

    17/24

    ABCD

    Open access some issues

    Accuracy of determination of total & available transmission

    Capacity is one of the requirements for operating under

    open access.

    Most utilities' current pricing schemes do not effectively

    address the costs of transmission constraints. Nor do they

    provide the proper signals concerning whether to remove

    constraints through supply side generation, transmission

    expansion or demand side measures.

    When individual utilities schedule power flow over a singleregional grid, unexpected overloads can arise and become

    barriers to competitive power trading.

  • 8/3/2019 july22-elec-venkatraman

    18/24

    ABCD

    1. Grid Discipline2. Non Discriminatory Open Access

    3. New Investment in Transmission

  • 8/3/2019 july22-elec-venkatraman

    19/24

    ABCD

    Transco

    STU

    SLDC

    To ensure integrated operation of power system in

    the state

    Responsible for optimum scheduling and dispatch

    Keep account of quantity of electricity transmitted

    through state grid Real time operation of grid controls and dispatch

    through secure and economic operation

    Transmission of electricity through intra-statetransmission system

    Planning and co-ordination Ensure development of intra-state transmission

    lines. To provide non-discriminatory open access to its

    transmission

    To build, maintain and operate an efficient andeconomical inter-state or intra-state transmission

    system. To comply with the directions of RLDC and SLDC

    as the case may be.Lic

    ens

    ee

    Trading

    Bulk supply trading of all existing

    Contracts

    Transmission service

    provider

    System operator.

    Bulk supplier/Trader

    EarlierEarlier NowNow

    The new structure is complex

  • 8/3/2019 july22-elec-venkatraman

    20/24

    ABCD

    Business separation will be important

    Separation of monopoly transmission businesses

    from competitive or potentially competitive

    activities.

    Options range from full ownership separation tomanagement separation.

    Europe has a mix of these:

    - Ownership unbundling (UK, Finland, Spain, etc)

    - Legal unbundling (Austria, Belgium, Denmark, etc)

    - Management unbundling (France, Luxembourg)

    Source: Ian Pope Associates

  • 8/3/2019 july22-elec-venkatraman

    21/24

    ABCD

    In addition, monitoring regimes are requiredto ensure fairness

    Separation and publication of accounts

    Appointment of a compliance officer whose job

    is to ensure that network access rules are applied

    equally and fairly Establishment of a separate corporate identity for

    the TSO

    Ensuring that the TSO is not physically located in

    the same building as an affiliate operating in the

    competitive market

    Source: Ian Pope Associates

  • 8/3/2019 july22-elec-venkatraman

    22/24

    ABCD

    European experience .

    Country Publishe daccounts

    Complianceofficer

    Separatecorporate ID

    Separatelocations

    Austria Yes No Yes Yes

    Belgium Yes No Yes Yes

    Denmark Yes Yes Yes Yes

    Finland Yes Yes Yes Yes

    France Yes Yes Yes Yes

    Germany Yes No Yes Yes

    Greece Not yet No Yes Yes

    Ireland Yes Yes Yes No

    Italy Yes No Yes Yes

    Luxembourg Yes No No No

    Netherlands Yes Yes Yes Yes

    Portugal Yes No Yes Yes

    Spain Yes Yes Yes Yes

    Sweden Yes Yes Yes Yes

    UK Yes Yes Yes YesSource: Ian Pope Associates

  • 8/3/2019 july22-elec-venkatraman

    23/24

    ABCD

    Encouraging investments somesuggestions

    Adequate returns (risk adjusted) on the investments andattractive depreciation norms.

    Ensure separation of business & introduce monitoring

    regime

    Realistic transmission planning by CTU/STU based onscientific load research/load forecast & generation plan.

    Regulatory certainty over a long period

    Cost reflective retail tariffs

    Establishment of effective/reliable communication networkand energy data collation system

    Settlement systems

    Addressing the stranded cost issue

  • 8/3/2019 july22-elec-venkatraman

    24/24

    ABCD

    Thank you

    R Venkatraman, KPMG ConsultingEmail: [email protected]